ksa concrete earth

Upload: mohammed-irshad

Post on 05-Jul-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/15/2019 Ksa Concrete Earth

    1/48

      able

    of Contents

    KINGDOM

    O

    SAUDI R BI

    MINISTRY OF COMMUNICATIONS

    GENERAL SPECIFICATIONS

    FOR

    ROAD AND BRIDGE CONSTRUCTION

    November 998

    PART THREE

    AGGREGATE SUBBASE AND BASE COURSES

  • 8/15/2019 Ksa Concrete Earth

    2/48

      ableof Contents

    PART THREE

    AGGREGATE

    SUBB SE

    AND BASE COURSES

    T BLE OF CONTENTS

    PART THREE: AGGREGATE SUBBASE AND BASE COURSESSECTION 3 01 -

    PRODUCTION HANDLING AND STOCKPILING AGGREGATES 1

    3.01.1 DESCRIPTION .......................................................................................... 1

    3.01.2 MATERIALS ..................................................................................  .......... 1

    3.01.2.1 Sources ........................................................................................... 1

    3.01.2.2 Definitions ...........................................................

     

    ......................... 1

    3.01.3 PRODUCTION REQUIREMENTS ........

     

    ............................................... 2

    3.01.3.1 Preparation of Site .................................... ... .................................... 2

    3.01.3.2 Production

    of

    Aggregates ....................  .......................................... 2

    3.01.3.3 Rejected Aggregates ..........................   ........................................... 3

    3.01.3.4 Surplus Screenings ................................. .  ............................... 3

    3.01.3.5 Site Cleanup ...................................................... .... .... ...................... 3

    3.01.4 QUALITY ASSURANCE PROCEDURES .....................................

     

    .... ....... 3

    3.01.4.1 Methods and Procedures ................................................................ 3

    3.01.4.2 Preliminary Testing ....................................... ....  ............................. 4

    3.01.4.3 Production Testing .................................... ... .................................... 4

    3.01.4.4 Acceptance Testing ................................ .......................................... 4

    3.01.5 STOCKPILING AGGREGATES .............. .....   ....................................... 4

    3.01.5.1 Sites ................................................................................... .............. 4

    3.01.5.2 Preparation of Stockpile Site ........................................................... 4

    3.01.5.3 Construction of Stockpiles ............................................................... 4

    3.01.5.4 Removing Aggregate From Stockpiles ...........................

     

    ........... 5

    3.01.5.5 Site Cleanup ...................................................... .... .... ...................... 5

    3.01.6 METHOD OF MEASUREMENT ....................

     

    .......................................... 5

    3.01.7 PAYMENT .............................................................................  .................. 5

    SECTION 3.02 - AGGREGATE SUBBASES ................................................................ 6

    3.02.1 DESCRIPTION .......................................................................................... 6

    3.02.2 MATERIALS .............................................................................................. 6

    3.02.3 PROPORTIONING AGGREGATE SUBBASE MIXTURES ....................... 7

    3.02.3.1 Job Mix Design Proposal ................................................................. 7

    3.02.3.2 Acceptance

    of

    Job Mix Formula .............................................   ....... 8

    3.02.3.3 Job Mix Formula Revisions ..............   .......................................... 9

    3.02.4 EQUIPMENT ................................................................................ ............. 9

    3.02.5 CONSTRUCTION ......................................................... ......   ..................... 9

    3.02.5.1 Contractor Quality Control Procedures ....................... ..................... 9

    3.02.5.2 Surface Preparation ....................................

     

    ............................. 10

    3.02.5.3 Placing and Spreading ....................... ....... .................................... 10

    3.02.5.4 Compacting ....................................................... ............................ 10

    3.02.5.5 Finishing ........................................................................................ 12

    3.02.5.6 Maintenance and Protection .......................................................... 12

    3.02.5.7 Compaction Test Trials ......................... ......................................... 12

    3.02.6 QUALITY ASSURANCE PROCEDURES .....................................  ....... 12

  • 8/15/2019 Ksa Concrete Earth

    3/48

    Table of ontents

    3.02.6.1 Compaction ................................................................................... 13

    3.02.6.2 Thickness ...................................................................................... 14

    3.02.6.3 Aggregate Gradation Sand Equivalent and Plasticity Index ......... 14

    3.02.6.4 California Bearing Ratio and Abrasion ........................................... 15

    3.02.6.5 Surface Tolerances ....................................................................... 15

    3.02.6.6 Acceptance .................................................................................... 15

    3.02.7 METHOD OF MEASUREMENT ...... ....... ....

     

    ........................................... 16

    3.02.8 PAYMENT ........................................................................ .......

     

    .............. 16

    SECTION 3.03 - AGGREGATE BASES .......................... ....

     

    ..................................... 17

    3.03.1 DESCRIPTION ........................................................................................ 17

    3.03.2 MATERIALS .......................................................................   ................. 17

    3.03.3 PROPORTIONING AGGREGATE BASE MIXES ............................. 19

    3.03.3.1 Job Mix Design Proposal ............................................................... 19

    3.03.3.2 Acceptance of Job Mix Formula .............................................. ...... 20

    3.03.3.3 Job Mix Formula Revisions ............................................................ 20

    3.03.4 EQUIPMENT ...........................................................................................

    21

    3.03.5 CONSTRUCTION ..................................................

     

    .... ....

     

    ......................

    21

    3.03.5.1 Contractor Quality Control Procedures ...................... ...   .............. 21

    3.03.5.2 Preparation and Maintenance .............................................  ...... 22

    3.03.5.3 Mixing ............................................................... ............................. 22

    3.03.5.4 Transporting .................................................... ....

     

    ........................ 22

    3.03.5.5 Placing and Spreading ..............  .................................................. 22

    3.03.5.6 Compacting .............................................. ..................................... 23

    3.03.5.7 Finishing ....................................................................

     

    .................. 24

    3.03.5.8 Maintenance and Protection .......................................................... 24

    3.03.5.9 Compaction Test Trials .................................................................. 25

    3.03.6 QUALITY ASSURANCE PROCEDURES ............................ .................... 25

    3.03.6.1 Compaction ................................................................................... 26

    3.03.6.2 Thickness ...................................................................................... 26

    3.03.6.3 Aggregate Gradation Sand Equivalent and Plasticity Index ......... 27

    3.03.6.4 California Bearing Ratio and Abrasion ........................................... 27

    3.03.6.5 Surface Tolerances ....................................................................... 28

    3.03.6.6 Acceptance .........................................................  ......................... 28

    3.03.7 METHOD OF MEASUREMENT ...... ........................................................ 29

    3.03.8 PAYMENT ...................................................................... ......................... 29

    SECTION 3.04 - CEMENT TREATED BASES .......   .................................................. 30

    3.04.1 DESCRIPTION ........................................................................................ 30

    3.04.2 MATERIALS ...................................................................

     

    ....................... 30

    3.04.2.1 Portland Cement ....................................

     

    ...................................... 30

    3.04.2.2 Aggregate .....................................................

     

    ......

     

    ....................... 30

    3.04.2.3 Water ................................................................. ............................

    31

    3.04.2.4 Flyash and Chemical Admixtures........................................  ...... 31

    3.04.2.5 Bituminous Curing Seal ................................................................. 31

    3.04.3 MIX DESiGN ..................................   ...........................................   .... ..... 31

    3.04.4 WEATHER LIMITATIONS ........................  ............................................. 32

    3.04.5 EQUIPMENT .................................................................

     

    ....

     

    ................ 32

    3.04.6 CONSTRUCTION REQUIREMENTS ...................................................... 32

  • 8/15/2019 Ksa Concrete Earth

    4/48

      ableof Contents

    3.04.6.1 Surface Preparation ........................

     

    ....... ...................................... 32

    3.04.6.2 Proportioning and Plant Mixing ........................................   ............ 33

    3.04.6.3 Transporting and Spreading .......................................................... 34

    3.04.6.4 Compacting and Finishing ...........  ................................................ 35

    3.04.6.5 Operation Time Requirement ........................................................ 35

    3.04.6.6 Construction Joints ........................................................................ 36

    3.04.7 CURING ................................................................................................... 36

    3.04.8 CONTRACTOR QUALITY CONTROL PROCEDURES .......................... 36

    3.04.9 QUALITY ASSURANCE PROCEDURES ............................

     

    ................ 36

    3.04.9.1 Compaction ................................................................................... 37

    3.04.9.2 Thickness ...................................................................................... 37

    3.04.9.3 Aggregate Gradation  Sand Equivalent and Plasticity Index ......... 38

    3.04.9.4 California Bearing Ratio or Compressive Strength ........................ 39

    3.04.9.5 Surface Tolerances ....................................................................... 39

    3.04.9.6 Acceptance .................................................. .... .............................. 39

    3.04.10 METHOD

    OF

    MEASUREMENT ............................................................. 40

    3.04.11 PAYMENT .............................................................................................. 40

    SECTION 3.05 - SHOULDERS AND LAYBYS ......   ................................................. 41

    3.05.1 DESCRIPTION ..........................................................

     

    ............................ 41

    3.05.2 EQUIPMENT ................................................................

     

    ......................... 41

    3.05.3 CONSTRUCTION REQUIREMENTS ............................................

     

    ........ 41

    3.05.3.1 General ................................................

     

    ....

     

    ........................... 41

    3.05.3.2 Earth Shoulders and Laybys ..............................................

     

    ....... 42

    3.05.3.3 Aggregate Shoulders and Laybys .......................................

     

    ...... 42

    3.05.3.4 Bituminous Base Shoulders and Laybys ................

     

    ...

     

    ................ 42

    3.05.3.5 Bituminous Wearing for Shoulders and Laybys ............................. 42

    3.05.4 SHOULDERING AND DELINEATION ......................................   ........... 42

    3.05.5 COMPACTION REQUiREMENTS ........................................................... 42

    3.05.6 METHOD OF MEASUREMENT .......... ...

     

    ............................................... 43

    3.05.7 PAYMENT .......................................................................

     

    ...................... 43

  • 8/15/2019 Ksa Concrete Earth

    5/48

      oeGeneral Specifications November 1998

    Table of ontents

    PART

    THREE:

    AGGREGATE

    SUBBASE

    AND

    BASE

    COURSES

    SECTION 3.01 - PRODUCTION, HANDLING

    AND

    STOCKPILING

    AGGREGATES

    3.01.1 DESCRIPTION. This work consists

    of

    producing, handling and stockpiling

    crushed and screened aggregates including pit run aggregates

    of

    the kind, quality and

    grading specified for all types

    of

    materials to be used

    in

    road and bridge and related

    construction.

    Requirements set forth herein shall apply whether the source be ledge rock, talus ,

    gravel , sand, or a combination thereof.

    3.01.2 MATERIALS.

    3.01.2.1 Sources. Materials sources may be shown

    on

    the plans, described

    in

    the

    special specifications, or established by the Contractor after approval by the Engineer.

    The Contractor shall furnish the Engineer, not less than thirty 30) days prior to the

    scheduled date for beginning crushing operations, information

    on

    the source of

    aggregates, the method of production to be employed, types and capacity of equipment

    to be used and a schedule showing rates of production for the several types of

    aggregate to be produced.

    Whether or not the materials sources are shown

    on

    the plans, specified

    in

    the

    special specifications, or established by the Contractor after approval by the Engineer,

    the Contractor shall determine for himself the types and numbers

    of

    equipment and

    extent of work needed to remove overburden and produce the volumes of aggregates

    required for the work within the contract time, and produce aggregates having the

    fracture, gradation and quality conforming to the specifications.

    The Engineer may require procurement

    of

    aggregate from any portion

    of

    a source

    and may reject portions

    of

    the source as being unacceptable.

    3.01.2.2 Definitions.

    1. Coarse aggregate consists of particles retained on the 4.75 mm No.4) sieve.

    2.

    Fine aggregate consists

    of

    particles passing the 4.75 mm No.4) sieve.

    3.

    Crushed stone consists

    of

    rock and stone fragments

    or

    gravel having one 1)

    or more mechanically fractured faces. Every fractured face shall have a minimum

    dimension from edge to edge across the fractured face which is not less than one-third

    1

    /3) the minimum dimension of the aggregate particle.

    4. Gravel consists of uncrushed aggregate particles passing a seventy-five 75)

    millimeter 3-inch) sieve and retained on a 4.75 mm No.4) sieve.

  • 8/15/2019 Ksa Concrete Earth

    6/48

      oeGeneral Specifications November 1998

    Table of ontents

    5

    Sand consists of aggregate particles passing a 4.75 millimeter No.4) sieve and

    retained

    on

    a 0.075 millimeter (No. 200) sieve and may be naturally occurring,

    manufactured or combinations thereof.

    6 Material passing a 0.075 mm (No. 200) sieve may be referred to as silt or clay

    or

    dust depending on other characteristics.

    3.01.3 PRODUCTION REQUIREMENTS.

    3.01.3.1 Preparation

    of

    Site. The portion of the quarry or pit site to be used shall

    be cleared and grubbed as specified

    in

    Section 2.01, Clearing and Grubbing

    in

    these

    General Specifications.

    When clearing and grubbing is completed, all surface materials which are

    unsatisfactory for the kind of aggregate to be produced shall be stripped and removed.

    Materials from clearing, grubbing and stripping which are removed as unsatisfactory

    for producing specified aggregates shall be disposed of at locations not visible from the

    roadway,

    in

    a manner that precludes erosion by wind

    or

    water and the form and

    contours

    of

    the finished disposal area blends with adjacent terrain.

    The costs involved

    in

    preparing the site, clearing , grubbing, stripping and removing

    overburden and other operations shall be incidental to the production of aggregate and

    shall be included by the Contractor in the contract unit price for the specific aggregate

    produced.

    3.01.3.2

    Production of

    Aggregates. The Contractor shall , as a minimum, utilize

    all stone, rock fragments or boulders occurring

    in

    the source, up to and including those

    measuring four hundred and fifty (450) millimeters in greatest dimension,

    in

    the

    manufacture of crushed aggregates. The Contractor, at his option, may use stone and

    boulders larger than four hundred and fifty (450) millimeters

    in

    greatest dimension.

    When the percent fracture and other requirements cannot be obtained by using the

    natural material, portions of the material may be rejected to the extent necessary to

    produce aggregates conforming to the requirements of the specifications.

    Failure to include an aggregate scalping and rejection requirement in the

    specifications for any type of aggregate shall not relieve the Contractor of the

    responsibility for scalping and rejection of portions of the materials

    if

    such become

    necessary to produce aggregates conforming to the requirements of the specifications.

    When scalping over a screen of specified size is required

    in

    the special

    specifications, the scalping screen shall be of such size and capacity that enough of the

    fine material will be removed to produce aggregates conforming to the requirements

    of

    the specifications.

    Rejected materials may be used

    in

    other portions of the work and locations when it

    conforms to the specified requirements for said other portions and locations.

  • 8/15/2019 Ksa Concrete Earth

    7/48

      oeGeneral Specifications November 1998

    Table of ontents

    Surplus screenings accumulated during crushing and screening

    of

    specified

    aggregates shall be kept separate from materials rejected during scalping operations.

    Washing of coarse and fine aggregates shall be performed as specified in the

    special specifications or as may be necessary to produce aggregates free from clay,

    loam, alkali , vegetable and other deleterious material.

    Washing and reclaiming

    of

    rejected material and subsequent addition to any finished

    aggregate shall not be allowed unless authorized

    in

    writing by the Engineer.

    When producing screened gravel or sand materials, the Contractor shall remove all

    oversize material by screening at the source. Operations at the source shall be such

    that the grading of aggregates in each hauling unit is reasonably uniform within

    tolerances that are specified for individual materials. The Contractor shall use the most

    suitable materials available at the source. He shall move his loading equipment as

    many times as may be necessary to fulfill these requirements.

    3.01.3.3 Rejected Aggregates All rejected materials unsatisfactory for use

    in

    other portions

    of

    the work and locations, shall

    e

    disposed

    of

    as specified

    in

    Paragraph

    3.01.3.1 , Preparation of Site in these General Specifications.

    3.01.3.4 Surplus

    Screenings

    Surplus screenings accumulated during the

    production

    of

    the specified aggregates at material sources established by the

    Contractor shall remain the property of the Contractor.

    Surplus screenings accumulated during the production

    of

    the specified aggregates

    at materials sources shown on the plans or described in the special specifications and

    furnished by the Ministry shall be stockpiled at the source and become the property

    of

    the Ministry.

    The stockpile area shall be prepared and constructed as specified

    in

    Subsection

    3.01.5, Stockpiling Aggregates

    in

    these General Specifications. All costs incurred

    in

    producing, hauling and stockpiling the surplus screenings shall be incidental to the

    production

    of

    the specified aggregates and shall be included by the Contractor

    in

    the

    contract unit prices for said aggregates.

    3.01.3.5 Site Cleanup Upon completion of the Contractor's operations at any

    source, the quarry or pit shall be cleared of rubbish, equipment, temporary structures

    and other items brought to the site by the Contractor. The site shall be left

    in

    a neat

    and presentable condition. When the special specifications require that aggregate

    sources e reclaimed

    in

    accordance with an approved reclamation plan, the Contractor

    shall comply with such approved reclamation plan.

    3.01.4

    QUALITY

    ASSURANCE PROCEDURES

    3.01.4.1 Methods and Procedures All aggregate testing shall be performed in

    accordance with methods and procedures described in the specifications and Materials

    Manual publications issued by the Ministry of Communications, Materials and Research

    Department.

  • 8/15/2019 Ksa Concrete Earth

    8/48

      oeGeneral Specifications November 1998

    Table of ontents

    3.01.4.2 Preliminary

    Testing

    The Contractor shall submit to the Engineer all

    results

    of

    testing as may be necessary to confirm that the source

    of

    materials ,

    equipment and production methods to be employed by the Contractor will produce

    aggregates conforming to the requirements of the specifications. No installation of

    equipment or production shall start at any materials source until the Engineer has

    approved the source, and the dimensions

    of

    the area to be excavated. The equipment

    and methods proposed by the Contractor shall also be approved by the Engineer.

    The approval

    of

    the Engineer shall not be construed as final acceptance

    of

    the

    aggregate to be produced.

    Representative samples of materials may be obtained by the Contractor and , when

    requested, duplicate samples shall be furnished to the Engineer for testing and future

    reference.

    Testing may be accomplished

    in

    the Contractor's laboratory or a commercial

    laboratory. The testing shall be the responsibility

    of

    the Contractor and performed at

    his expense.

    3.01.4.3 Production Testing The Contractor shall arrange all testing necessary

    to control specified aggregate fracture , gradation and quality during production as

    specified

    in

    Paragraphs 3.02.5.1, 3.03.5.1 and 3.04.8 all entitled Contractor Quality

    Control Procedures in these General Specifications. The results of such testing shall

    be promptly delivered to the Engineer. Such test results are intended to be used to

    guide the Contractor operations and shall not be used to infer that the aggregates being

    produced are acceptable and

    in

    conformance to the specifications.

    3.01.4.4 Acceptance Testing The Engineer shall sample or supervise the

    sampling testing and evaluation of aggregates furnished to the work as specified in

    Subsections 3.02.6, 3.03.6 and 3.04.9 all entitled Quality Assurance Procedures

    in

    these General Specifications.

    3.01.5 STOCKPILING

    AGGREGATES

    3.01.5.1 Sites. The site for constructing stockpiles shall be approved by the

    Engineer and located in a manner that the stockpiled materials will not e contaminated

    with other aggregates or altered by dust, dune sand or other natural or processed

    material. Stockpiling

    on

    private property shall be permitted with the written consent

    of

    the owner or lessee. The Engineer shall be afforded access to the stockpiled materials

    at all times.

    3.01.5.2

    Preparation of Stockpile

    Site. Before placing aggregates on the

    stockpile site, the site shall be cleared

    of

    vegetation, rocks and debris and the ground

    leveled to a smooth, firm uniform surface.

    3.01.5.3 Construction of Stockpiles The stockpiles shall be constructed

    on

    the

    prepared site, shall be neat and regular

    in

    shape and not more than eight (8) meters

    in

    height.

  • 8/15/2019 Ksa Concrete Earth

    9/48

      oeGeneral Specifications November 1998

    Table of ontents

    Stockpiles

    n

    excess of two hundred 200) cubic meters shall be built up n layers not

    more than one and one-half 1.5) meters

    n

    depth using methods and equipment

    approved by the Engineer. Pushing aggregate into a stockpile using dozers will not be

    permitted. Each layer shall be completed over the entire area of the pile before

    depositing aggregate n the succeeding layer. Any method of placing aggregate n a

    stockpile which,

    n

    the opinion

    of

    the Engineer, results

    n

    segregation, breaks, degrades

    or otherwise damages the aggregate will not be permitted.

    Stockpiles

    of

    different kinds or sizes

    of

    aggregate shall be separated by space or

    suitable walls or partitions to prevent mixing. Aggregate shall not be stockpiled where

    vehicles will run over or through the piles and cause foreign material to become mixed

    with the stockpiled aggregate.

    3.01.5.4 Removing Aggregate From Stockpiles Aggregate shall be removed

    from the stockpiles using equipment and methods approved by the Engineer and n a

    manner that precludes segregation

    of

    particle sizes or adulteration with underlying or

    adjacent soil or foreign material.

    When removing aggregate from stockpiles, the removal equipment shall be operated

    n such a manner as to face-load from the floor to the top of the stockpile to obtain

    maximum uniformity of aggregate.

    The Contractor shall remove only such aggregate quantities as are necessary to

    complete work under the contract.

    3.01.5.5

    Site Cleanup

    If a surplus remains

    n

    the stockpile , the Contractor shall

    leave said surplus

    n

    neat, regular shaped piles, free

    of

    foreign matter and equipment.

    3.01.6 METHOD OF MEASUREMENT. No measurement will be made for any work

    or

    aggregate produced under this section.

    3.01.7 PAYMENT. Full compensation for performing all

    of

    the work specified

    n

    this

    section shall be considered as subsidiary to other items

    of

    work appearing

    n

    the Bill

    of

    Quantities unless otherwise provided for

    n

    the Special Specifications and listed

    n

    the

    Bill of Quantities.

  • 8/15/2019 Ksa Concrete Earth

    10/48

      oe

    General Specifications November

    1998

    able of Contents

    SECTION 3.02 -

    AGGREGATE

    SUBBASES

    3.02.1 DESCRIPTION. This work shall consist of furnishing, spreading and

    compacting aggregate subbases to the lines and elevations shown on the plans as

    specified in these General Specifications and the Special Specifications.

    Aggregate subbases will be designated as Aggregate Subbase Course

    or

    Aggregate

    Subbase Course, Grading

    _

    The grading s)

    of

    aggregate subbase to be furnished

    shall be according to the item s) shown

    in

    the Plans or Special Specifications and listed

    in

    the Bill

    of

    Quantities. If the grading

    of

    aggregate subbase is not specified, aggregate

    subbase course shall be furnished meeting one

    of

    the gradations listed

    in

    Table 3.02-1

    as designated by the Engineer. The designation of the appropriate Grading shall be

    such that the maximum size of aggregate will not exceed two thirds 2/3) of the

    thickness of the subbase course layer to be constructed.

    ITEMS IN BILL OF QUANTITIES:

    Aggregate Subbase Course

    Aggregate Subbase Course,

    rad ing_

    3.02.2 MATERIALS. Aggregate used for aggregate subbase shall be free from

    vegetation matter and other deleterious substances and, when compacted under

    watering and rolling, form a firm, stable subbase. Coarse aggregate shall be crushed

    stone, crushed slag,

    or

    crushed gravel. Fine aggregate, material passing the 4.75 mm

    No. 14) sieve, shall consist of natural

    or

    crushed sand and fine material particles.

    The Contractor shall furnish , produce, stockpile, blend and mix all necessary

    materials using such equipment and procedures as will produce specified aggregate

    subbase. Aggregate shall conform to one of the following grading and quality

    requirements on the road bed after all blending and mixing and spreading and before

    compacting:

    TABLE 3.02-1

    AGGREGATE SUBBASES GRADATION REQUIREMENTS - MTDTM 204

    Sieve Sizes Grading I Grading II

    62.5 mm

    2

    inch) 100

    50 mm 2

    in

    ch) 90-100 100

    37.5 mm 1 inch)

    -

    90-100

    25 mm 1 inch)

    -

    55-85

    19 mm 3/4 inch)

    -

    50-80

    9.5 mm inch)

    -

    40-70

    4.75 mm

    No.4)

    35-70 30-60

    2.54 mm No.1 0)

    -

    20-50

    0.425 mm No. 40)

    -

    10-30

    0.075 mm No. 200) 0-15 0-15

  • 8/15/2019 Ksa Concrete Earth

    11/48

      oeGeneral Specifications November 1998

    Table of ontents

    QUALITY

    REQUIREMENTS

    Sand Equivalent (MRDTM 313) 25 Min.

    Plasticity Index (MRDTM 208) 6 Max.

    Abrasion Loss (MRDTM

    309) 50 Max.

    California Bearing Ratio (CBR) 50 Min.

    (MRDTM 213)

    Aggregate for Grading

    III

    aggregate subbase shall conform to the requirements

    specified

    in

    the Special Specifications.

    3.02.3 PROPORTIONING AGGREGATE

    SUBBASE

    MIXTURES.

    3.02.3.1 Job Mix Design Proposal. A proposed Job Mix Formula (JMF) shall be

    formulated by the Contractor and submitted to the Engineer for approval. The JMF

    shall be prepared by the Contractor in precise compliance with procedures and

    requirements set forth

    in

    the Materials and Research Department Manual of Materials

    and Tests and all current letters issued by the Ministry

    of

    Communications.

    The Contractor shall select his sources of aggregate and , after sufficient quantities

    have been stockpiled or are available for use obtain representative samples of the

    materials and test to determine if they conform to the requirements of these

    specifications. At least thirty (30) days before producing aggregate subbase mixtures,

    the Contractor shall submit

    in

    writing to the Engineer detailed information for each mix

    which he proposes to furnish. The information shall include, but not be limited to the

    following:

    1 The source and gradation of the aggregate for each mix to be furnished. If the

    aggregate (coarse, fine, supplemental fine)

    is

    separated into two (2) or more sizes , the

    information provided shall consist of gradations for all individual sizes, the proportions

    of each individual size to be used, and the mathematically combined gradation for each

    mix to be furnished. Such combined gradation shall meet the applicable grading

    requirements shown

    in

    Subsection 3.03.2, Materials

    in

    these General Specifications

    and show the percentage passing each

    of

    the specified sieve sizes.

    2 Pertinent test data and a written certification that the aggregates to be furnished

    conform to all quality requirements shown

    in

    Subsection 3.03.2, Materials

    in

    these

    General Specifications.

    3

    The type

    of

    plant to be used for mixing each mix to be furnished.

    4. The beginning date for producing aggregate subbase mixtures.

  • 8/15/2019 Ksa Concrete Earth

    12/48

      oeGeneral Specifications November 1998

    Table of ontents

    The Engineer shall be provided access to the materials sampling and testing

    operations at all times. The combined aggregate, including mineral additives, shall

    conform to the approved JMF grading within the following tolerances:

    9.75 mm (3/8 ) and larger sieves,

    4.75 mm

    No.4)

    sieve,

    2.36 mm

    No.8)

    sieve,

    0.300 mm (No. 50) sieve,

    0.075 mm (No. 200) sieve ,

    percentage points

    10 percentage points

    9 percentage points

    8 percentage points

    8 percentage points

    At the same time the above information is provided, the Contractor shall supply to

    the Engineer fifty (50) kilogram samples of each individual aggregate size, when used,

    ten (10) kilogram samples

    of

    mineral filler and chemical admixture, all representing the

    materials which the Contractor proposes to furnish.

    3.02.3.2

    Acceptance

    of

    Job

    Mix Formula. The Engineer shall review the JMF to

    determine that it contains all required information. If it does not contain all required

    information, it shall be returned within seven (7) days to the Contractor for further action

    and resubmission by the Contractor.

    If the proposed JMF contains all required information but fails to meet all the

    requirements specified, it shall not be accepted by the Engineer and will be returned to

    the Contractor within fourteen (14) days. The Contractor shall prepare and submit to

    the Engineer a new JMF conforming to the requirements specified and propose a new

    date for beginning production.

    When the Engineer is satisfied that the JMF proposed by the Contractor conforms

    to all the requirements of the specifications, he shall order the Contractor to construct

    a minimum two hundred (200) meter long field control strip. The Engineer shall

    evaluate the control strip as to its constructability and compactability and conformance

    to the laboratory tested JMF. Split samples of the aggregate subbase mix for and

    components raw material along with the field laboratory test results are to be sent to the

    Materials and Research Departments Central Laboratory for a one (1) point check and

    documentation. If the Engineer is not satisfied with the results of the control strip, he

    shall state his objections

    in

    writing and request a revised JMF and a new control strip.

    When the Engineer is satisfied that the JMF proposed by the Contractor conforms

    to all requirements

    of

    the specifications and the control strip results are acceptable, he

    will issue written acceptance to the Contractor to begin producing the mixes proposed.

    Production

    of

    aggregate subbase mixes shall not begin until the Engineer has given

    written acceptance of the Job Mix Formula.

    Acceptance of the JMF by the Engineer does not relieve the Contractor of his

    obligation to produce aggregate subbase mixes conforming to all specified

    requirements.

  • 8/15/2019 Ksa Concrete Earth

    13/48

      oeGeneral Specifications November 1998

    Table of ontents

    3.02.3.3 Job Mix

    Formula

    Revisions The Contractor shall not alter his methods

    of

    crushing, screening, blending , or stockpiling from that used to produce materials for

    the approved JMF. Changes to the JMF will not be permitted without retesting and

    resubmission of a proposed (revised) JMF in accordance with all the steps in Paragraph

    3.02.3.1, Job Mix Design Proposal in these General Specifications. Significant

    changes may include, but not be limited to, changes

    in

    the amount or type

    of

    materials

    rejected or wasted, changes

    in

    the amount

    of

    materials crushed, reductions

    in

    the

    amount

    of

    crushed fines, changes

    in

    the amount and type

    of

    mineral filler.

    Should the Contractor change his source

    of

    aggregate, he shall furnish a new job

    mix design proposal and samples

    of

    materials, as described

    in

    Paragraph 3.02.3.1 , Job

    Mix Design Proposal in these General Specifications, as determined by the Engineer

    to be necessary, at least twenty-one (21) days before their intended use.

    At any time after the JMF is approved the Contractor may submit a new JMF for

    approval by the Engineer. If the revised JMF is approved it shall become the approved

    JMF.

    3.02.4 EQUIPMENT. The Contractor shall furnish all necessary equipment for

    production, stockpiling and hauling aggregate, preparing the subgrade and placing,

    compacting, finishing and maintaining the aggregate subbase according to the minimum

    type and number outlined in the contractor's detailed Program

    of

    Work as approved by

    the Engineer.

    Blending and mixing aggregates and adjusting the moisture content as required for

    compaction shall be performed

    in

    a central mixing plant or on the grade by means that

    insure uniformity.

    The blended and mixed aggregates shall be placed and spread to the width and

    thickness specified.

    3.02.5 CONSTRUCTION.

    3.02.5.1

    Contractor

    Quality

    Control Procedures

    Testing to control the quality

    of aggregate furnished for subbase shall be the responsibility of the Contractor. Copies

    of all test results shall be forwarded to the Engineer at the end of each working day.

    The Engineer shall have access to the Contractor's testing laboratory at all times and

    reserves the right to obtain samples

    of

    the materials at any point during construction.

    When requested by the Engineer, the Contractor shall obtain aggregate subbase

    materials and prepare duplicate samples by quartering . One (1) sample shall be

    delivered to the Engineer and the duplicate sample shall be tested by the Contractor.

    The Contractor shall perform the following minimum types and number

    of

    tests:

    1

    Gradation, sand equivalent and plasticity index - One (1) test each per two

    thousand (2000) cubic meters of aggregates produced but no less than one (1) test per

    production day.

  • 8/15/2019 Ksa Concrete Earth

    14/48

      oeGeneral Specifications November 1998

    Table of ontents

    2

    Abrasion Loss - One (1) test for the first, second and third five hundred (500)

    cubic meters

    of

    aggregate produced and one (1) test for each twenty-five hundred

    (2500) cubic meters thereafter.

    3 CBR Value - One (1) test for each five thousand (5,000) cubic meters placed.

    When test data indicate that the aggregate subbase does not conform to specified

    requirements, the Contractor shall take effective action to correct his production

    methods to assure that subbase aggregate will conform to all specified requirements.

    Such action shall include halting production, changing the source

    of

    aggregate supply,

    altering amount

    of

    aggregated scalped and rejected , increasing degree

    of

    crushing, and

    revising blending and handling methods. Such material if already placed, shall be

    removed and modified or replaced to produce material conforming to the specified

    requirements.

    3.02.5.2

    Surface Preparation

    The surface to receive aggregate subbase,

    immediately prior to spreading aggregate subbase, shall conform to specified

    compaction and elevation tolerances and shall be free

    of

    loose or extraneous material.

    The Contractor shall correct, at his own expense, any deviation from specified

    elevation and compaction in the surface to receive aggregate subbase.

    When surfaces to receive aggregate subbase are lower than specified , the low areas

    may be filled with aggregate subbase. The volume

    of

    aggregate subbase so placed

    shall not be measured for payment under any item listed

    in

    the Bill

    of

    Quantities.

    3.02.5.3

    Placing

    and

    Spreading

    Aggregate for subbase, immediately prior to

    spreading, shall be uniform mixtures free from pockets and streaks of coarse or fine

    material and shall be deposited on the subgrade in uniform layers or windrows using

    approved equipment.

    The layers or windrows

    of

    aggregate subbase shall be shaped to such thickness

    that, after watering and compacting, the completed subbase layer shall conform to the

    required width, grade and thickness within the tolerances specified

    in

    Paragraph

    3.02.4.5, Finishing in these General Specifications.

    The material shall be handled so as to avoid segregation . Segregated materials

    shall be remixed until uniform. The water can either be added

    in

    the borrow pit or on

    a mixing platform or

    on

    the grade.

    Where the subbase thickness is twenty (20) centimeters or less, the aggregate

    subbase may be spread and compacted

    in

    one (1) layer. Where the required thickness

    is more than twenty (20) cm, the aggregate subbase shall be spread

    in

    two (2) or more

    layers of approximately equal thickness.

    3.02.5.4 Compacting Each layer of subbase material, after being shaped to the

    required lines and cross section, shall be compacted to a uniform density with no

    individual test being less than ninety-five percent (95%)

    of

    the maximum dry unit weight

    determined from MRDTM 212. Each

    of

    lot

    of

    subbase material as described

    in

    1

  • 8/15/2019 Ksa Concrete Earth

    15/48

      oeGeneral Specifications November 1998

    Table of ontents

    Subsection 3.02.6 Quality Assurance Procedures

    n

    these General Specifications shall

    have a percent relative compaction

    o

    no less than ninety-nine percent (99%)

    o

    the

    maximum dry unit weight determined from MRDTM 212. The subbase shall be watered

    or

    dried as may be necessary to obtain a moisture content suitable for compaction.

    Material which has dried prior to final compaction or which has dried and decompacted

    subsequent to final compaction shall be watered and recompacted using equipment

    and procedures approved by the Engineer. Should the Contractor be unable to return

    the material to its original or specified condition with respect to compaction, thickness,

    and surface tolerances , the Contractor shall remove the material and reconstruct the

    course on a reapproved subgrade.

    When there are delays n constructing the remaining pavement structure over a

    granular course, the compaction

    o

    the granular course shall be reverified and deficient

    areas corrected or replaced to the satisfaction

    o

    the Engineer. Such corrections or

    replacement shall be at the Contractor's expense.

    The Contractor shall plan the work and handle the various operations so that the

    least amount

    o

    water will be lost by evaporation from uncompleted surfaces. If the

    Contractor delays placing

    or

    succeeding layers o material to the extent that additional

    water must be applied to prevent raveling or excessive drying , the application

    o

    such

    water shall be at the Contractor's expense and will not be considered as the basis for

    a claim for additional compensation.

    The material shall be compacted by means

    o

    approved compaction equipment,

    progressing gradually from the outside towards the center, with each succeeding pass

    uniformly overlapping the previous pass. Rolling shall continue until the entire thickness

    o

    each layer is thoroughly and uniformly compacted to the specified density. The final

    rolling o the completed course shall be done with a self-propelled roller as approved

    by the Engineer. Rolling shall be accompanied by sufficient blading, n a manner

    approved by the Engineer, to insure a smooth surface, free from ruts

    or

    ridges and

    having the proper section and crown. When additional water is required, it shall be

    added

    n

    the amount and manner approved by the Engineer. Initial layers

    o

    material

    must be constructed to a uniform grade and cross section and compacted by the

    Contractor and approved by the Engineer prior to the delivery

    o

    materials for a

    succeeding layer.

    Prior to placing a succeeding layer

    o

    granular material, the surface

    o

    the

    underlayer shall be made sufficiently moist , to insure bond between the layers. The

    edges and edge slopes

    o

    the base course shall be bladed or otherwise dressed to

    conform to the lines and dimensions shown on the plans, and present straight, neat and

    workmanlike lines and slopes as free

    o

    loose material as practicable.

    Any areas inaccessible to normal compaction equipment shall be compacted by

    means of portable mechanical tampers until satisfactory compaction s obtained. When

    the final layer is to be trimmed to final grade by an automatic grading machine , this

    layer shall be constructed approximately one (1) to three (3) centimeters above grade ,

    so that the grading machine cuts continually. After the final pass

    o

    the grading

    machine , the subbase shall be wetted and rolled.

  • 8/15/2019 Ksa Concrete Earth

    16/48

      oeGeneral Specifications November 1998

    Table of ontents

    3.02.5.5 Finishing All subbase material shall be placed, trimmed and finished

    n

    a neat and workmanlike manner

    n

    compliance with the lines, grades and typical cross

    sections shown

    on

    the plans

    or

    staked by the Engineer within the tolerances listed n

    Paragraph 3.02.6.5, Surface Tolerances n these General Specifications.

    3.02.5.6

    Maintenance

    and

    Protection

    Following construction

    of

    the subbase

    course, the compacted course shall be maintained by the Contractor at his expense.

    The Contractor shall blade, broom, and otherwise maintain the course, keeping it free

    from raveling and other defects that result

    n

    lost density until such time as the next

    element

    of

    the pavement structure

    s

    placed. Water shall be applied at such times and

    n

    such quantities as directed by the Engineer, and the Engineer shall have full authority

    to require the suspension of all other work on the project to insure the proper

    maintenance of previously compacted material.

    The Engineer shall determine when the surface

    of

    the subbase is

    n

    the proper

    condition to permit the placement of aggregate subbase course or the bituminous prime

    and/or surfacing to be applied. The Contractor must continue to maintain the surface

    of

    the base course, including the application

    of

    necessary water, at his expense until

    such time as the bituminous prime or the subsequent layer is applied. Any additional

    expense incurred by the Contractor because of delay n placing subsequent layers or

    applying the bituminous prime when so permitted by the Engineer will not be considered

    as the basis for a claim for additional compensation.

    3.02.5.7

    Compaction

    Test Trials If directed by the Engineer, or requested by the

    Contractor, prior to the commencement

    of

    his subbase compaction operations, the

    Contractor shall construct compaction trial lengths, not to exceed one (1) kilometer.

    The materials used

    n

    the trials shall be that approved for use as aggregate subbase

    and the equipment used shall be that according to the Contractor's approved detailed

    Program of Work.

    The object

    of

    these trials is to determine the adequacy

    of

    the Contractor's

    equipment, the loose depth measurements necessary to result

    n

    the specified

    compacted layer depths, the field moisture content, and the relationship between the

    number

    of

    compaction passes and the resulting density

    of

    the material.

    The Contractor may proceed with aggregate subbase work only after the methods

    and procedures established n the compaction trial has been approved by the Engineer.

    3.02.6 QUALITY ASSURANCE PROCEDURES. Aggregate subbase shall be

    accepted by lot. Unless otherwise stated

    n

    the Special Specifications, the lot size shall

    be ten thousand (10,000) square meters for each layer constructed. The aggregate

    subbase shall be sampled, tested and evaluated

    n

    accordance with Section 1.08

    Acceptance

    of

    Work

    n

    these General Specifications. The Engineer may, during the

    beginning of placement of subbase, at times when test results indicate erratic

    characteristics and at any other time, reduce the lot size to sections of subbase with

    similar quality characteristics. This should facilitate the isolation and modification or

    replacement of low-quality materials with materials of acceptable quality to maintain the

    overall strength

    of

    the pavement structure.

    2

  • 8/15/2019 Ksa Concrete Earth

    17/48

      oeGeneral Specifications November 1998

    Table of ontents

    The Engineer shall perform or supervise the performance

    of

    all quality assurance

    sampling and testing. The location

    of

    all samples and tests shall be recorded by

    roadway, lane and centerline station (kilometer). Quality assurance sampling and

    testing for each lot shall include:

    1

    Compaction

    2

    Thickness

    3

    Aggregate Gradation, Sand Equivalent and Plastic Limit

    4 California Beating Ratio and Abrasion

    5 Surface Tolerances

    3.02.6.1

    Compaction

    The compacted density for each layer

    of

    aggregate subbase

    shall be determined by the sand cone method, MRDTM 215, or by nuclear method,

    MRDTM 218 using full depth penetration, at the option

    of

    the Engineer.

    When the sand cone method is used, unless otherwise stated in the Special

    Specifications , the tests shall be made at a minimum of five (5) randomly selected

    locations

    in

    each lot.

    When the nuclear method is used, unless otherwise stated

    in

    the Special

    Specifications , the tests shall be made at a minimum

    of

    eight (8) randomly selected

    locations

    in

    each lot. Three nuclear gauge readings shall

    be

    made at each test location

    within a radius

    of

    two (2) meters. The three (3) readings shall be averaged and the

    average considered to be the density for that test location.

    Percent relative compaction shall be computed by comparing the average actual in-

    place compacted density from the nuclear gauge or sand cone test results with the

    maximum density determined by MRDTM 212. MRDTM 212 maximum density shall be

    determined from samples

    of

    aggregate subbase obtained from the roadbed at a

    sampling frequency

    of

    one (1) test per three (3) lots. The maximum density used for

    determining percent relative compaction shall be the running average for three (3)

    consecutive tests.

    Any lot

    of

    aggregate subbase that has a percent relative compaction below the

    minimum percent compaction specified in Paragraph 3.02.5.4, Compacting,  in these

    General Specifications resulting

    in

    a reduced pay factor

    of

    0.75 or higher determined

    in

    accordance with Subsection 1.08.5, Statistical Evaluation

    of

    Work for Acceptance

    and Determination

    of

    Pay Factor (Value

    of

    Work)

    in

    these General Specifications may

    be accepted on the basis

    of

    a reduced payment

    if

    requested

    in

    writing by the

    Contractor. Otherwise the lot shall be removed and replaced by the Contractor at his

    expense. Lots that have percent relative compaction resulting in a reduced pay factor

    less than 0.75 shall be removed and replaced by the contractor at his expense.

    3

  • 8/15/2019 Ksa Concrete Earth

    18/48

      oeGeneral Specifications November 1998

    Table of ontents

    3.02.6.2

    Thickness

    The thickness

    of

    each course

    of

    aggregate subbase complete

    as placed and compacted, shall be measured from test holes obtained at a minimum

    of five (5) random locations within the lot. The thickness of each hole shall be

    determined after determination that the compacted density is acceptable. The average

    of the test hole thicknesses shall be reported as the thickness of the lot.

    A lot shall be accepted when the average total thickness is not less than the planned

    thickness.

    Any lot

    of

    aggregate subbase course with an average thickness less than shown

    in

    the plans but resulting

    in

    a reduced pay factor

    of

    0.75 or higher determined

    in

    accordance with Subsection 1.08.5, Statistical Evaluation of Work for Acceptance and

    Determination of Pay Factor (Value of Work),  in these General Specifications may be

    accepted

    on

    the basis of reduced payment if requested in writing by the Contractor,

    otherwise additional material shall be provided as specified

    in

    the preceding paragraph.

    When the average thickness

    of

    a lot

    of

    aggregate subbase course is less than the

    planned thickness by an amount resulting

    in

    a reduced pay factor below 0.75 the

    Contractor, at his own expense, shall place and remix additional aggregate subbase

    material with the original aggregate subbase material and recompact before new test

    holes are dug.

    3.02.6.3 Aggregate Gradation , Sand

    Equivalent

    and Plasticity Index.

    Aggregate subbase gradation , sand equivalent and plasticity index will be sampled ,

    tested and evaluated based

    on

    the average

    of

    a minimum

    of

    five (5) test results per lot

    in

    accordance with the Job Mix Formula Tolerances listed

    in

    Paragraph 3.02.3.1 Job

    Mix Design Proposal ,  and Subsection 1.08.5, Statistical Evaluation

    of

    Work for

    Acceptance and Determination of Pay Factor (Value of Work) , in these General

    Specifications.

    Every sample of aggregate subbase shall be taken on a random time basis from

    each uncompacted lot during each one-half ( ) day

    of

    work, or portion thereof. The

    initial sample shall be randomly selected from within one and one-half 1 ) meters

    either side

    of

    the centerline

    of

    and weigh at least twenty-five (25) kilograms. The initial

    sample shall be thoroughly mixed and quartered to obtain a test sample weighing at

    least six (6) kilograms. The test sample shall be forwarded to the project laboratory and

    the aggregate gradation, and sand equivalent and plastic light determined.

    When the aggregate gradation, sand equivalent or plasticity index test results for any

    lot produce a reduced pay factor of 0.75 or higher determined

    in

    accordance with above

    referenced Subsection 1.08.5, Statistical Evaluation

    of

    Work for Acceptance and

    Determination

    of

    Pay Factor (Value or Work) in these General Specifications , the lot

    may be accepted on the basis

    of

    a reduced pay factor if requested

    in

    writing by the

    Contractor. Otherwise said lot shall be removed and replaced by Contractor at his

    expense.

    When the gradation , sand equivalent or plasticity index pay factor determined

    in

    accordance with above referenced Subsection 1.08.5, Statistical Evaluation

    of

    Work

    for Acceptance and Determination

    of

    Pay Factor (Value or Work)

    in

    these General

    4

  • 8/15/2019 Ksa Concrete Earth

    19/48

      oeGeneral Specifications November 1998

    Table of ontents

    Specifications , for any lot whose pay factor is less than 0.75 the aggregate subbase

    shall be removed and replaced by the Contractor at his expense.

    3.02.6.4 California Bearing Ratio and

    Abrasion

    Random samples shall be taken

    and tested for California Bearing Ratio and Abrasion from the first three (3) lots and

    every fifth lot thereafter unless test results indicate failure to conform to the values

    specified

    in

    Subsection 3.02.2, Materials

    in

    these General Specifications.

    n

    such a

    case, increased sampling and testing shall be performed .

    3.02.6.5

    Surface Tolerances

    The surface layer

    of

    the aggregate subbase shall

    be evaluated for compliance with the following surface tolerances:

    The cross section of the finished subbase surface shall be checked by the

    Contractor in the presence of the Engineer at maximum intervals of twenty-five (25)

    meters and at intermediate points as directed by the Engineer. The deviation

    of

    the

    elevation

    of

    the surface above the design elevation shall be not more than twenty (20)

    millimeters. Deviations above the design elevation shall not result

    in

    the diminished

    thickness

    of

    any subsequent pavement course. The deviation

    of

    the elevation below

    the design elevation shall not be more than twenty (20) millimeters. Isolated deviations

    below the design elevation shall be compensated by additional thickness of the

    subsequent pavement layer. Additional cost and materials resulting from deviations

    from the design elevation shall be borne by the Contractor. Contractor shall furnish all

    devices necessary to check the surface, such as stringlines , straightedges, etc., and

    the labor necessary to handle the task.

    3.02.6.6 Acceptance. Aggregate subbase construction including Califomia Bearing

    Ratio, abrasion and surface tolerances shall be accepted under Subsection 1.08.4,

    Measured

    or

    Tested Conformance in these General Specifications.

    Compaction, thickness, aggregate gradation, sand equivalent and plasticity index

    will be accepted under Subsection 1.08.5, Statistical Evaluation

    of

    Work for

    Acceptance and Determination

    of

    Pay Factor (Value

    or

    Work) in these General

    Specifications

    in

    two (2) stages as follows: The first stage shall be the selection

    of

    the

    lowest

    of

    the four

    of

    pay factors for the quality

    of

    the aggregate subbase relating to

    aggregate gradation, compaction, sand equivalent and plasticity index. The second

    stage involves the selection and application of a quantity pay factor based on the

    thickness of the aggregate subbase. The reduced thickness pay factor for the lower

    course lots

    of

    multiple layer courses will be applied provisionally based on the results

    of the depths of the holes dug in the lower layers. Additional holes will be dug in the

    total depth

    of

    all aggregate subbase layers within the lot represented by lower layer

    reduced thickness pay factors. If the total thickness depths show that the increased

    upper level layer thickness has resulted

    in

    total thickness acceptability, the lower level

    layer reduced thickness pay factor will be adjusted accordingly. The second stage

    thickness quantity pay factor will be applied to all the individual course lots in addition

    to the first stage lowest quality pay factor as determined in accordance with Subsection

    1.08.5, Statistical Evaluation of Work for Acceptance and Determination of Pay Factor

    (Value or Work)

    in

    these General Specifications.

    5

  • 8/15/2019 Ksa Concrete Earth

    20/48

      oeGeneral Specifications November 1998

    able of Contents

    3.02.7 METHOD OF MEASUREMENT. Aggregate subbase shall be measured by the

    cubic meter after placement and compaction to the required density, using horizontal

    dimensions shown on the plans or as directed by the Engineer and thickness

    measurements determined as specified in this specification. No allowance for

    overdepth shall be permitted except as approved in writing by the Engineer prior to

    spreading the aggregate subbase.

    3.02.8 PAYMENT. Aggregate subbase shall be paid for at the contract unit price or

    adjusted contract unit price per cubic meter for the aggregate subbase item(s) shown

    on the plans and listed

    in

    the Bill

    of

    Quantities. Such price and payment shall be full

    compensation for furnishing all rnaterials, equiprnent, labor, tools and incidentals and

    all other items necessary to complete the work as specified in Subsection 1.07.2,

    Scope

    of

    Payment in these General Specifications.

    When a lot

    of

    aggregate subbase course is accepted with a deficiency, the adjusted

    contract unit price for said lot shall be the product

    of

    the contract unit price

    of

    aggregate

    subbase, and the lowest quality and quantity pay factors specified

    in

    Subsection 3.02.6,

    Quality Assurance Procedures, 

    in

    these General Specifications.

    PAYMENT WILL BE MADE UNDER ONE OR MORE OF THE FOLLOWING:

    ITEM NO.

    P Y

    ITEM

    P Y

    UNIT

    30201 Aggregate Subbase Cubic Meter

    Course

    3020101 Aggregate Subbase Cubic Meter

    Course, Grading I

    3020102 Aggregate Subbase Cubic Meter

    Course, Grading

    3020103 Aggregate Subbase Cubic Meter

    Course, Grading

    6

  • 8/15/2019 Ksa Concrete Earth

    21/48

      oeGeneral Specifications November 1998

    able of Contents

    SECTION 3.03 -

      GGREG TEB SES

    3.03.1 DESCRIPTION. This work shall consist of furnishing, spreading and

    compacting aggregate bases to the lines, elevations and thicknesses shown on the

    plans and as specified

    in

    these General Specifications and the Special Specifications.

    Aggregate bases will be designated as Aggregate Base Course

    or

    Aggregate Base

    Course, Grading

    _

    The grading(s)

    of

    aggregate base to be furnished shall be

    according to the item(s) shown

    in

    the Plans

    or

    Special Specifications and listed

    in

    the

    Bill

    of

    Quantities. If the aggregate base course grading is not specified aggregate base

    course shall be furnished meeting one of the gradations listed in Table 3.03-1 as

    designated by the Engineer. The designation of the appropriate Grading shall be such

    that the maximum size of aggregate will not exceed two thirds (2/3) of the thickness of

    the aggregate base course layer to be constructed.

    ITEMS

    N BILL

    OF QUANTITIES:

    Aggregate Base Course

    Aggregate Base Course, rad ing_

    3.03.2 MATERIALS. Aggregates used for aggregate base shall be hard durable

    particles or fragments free from vegetation matter and other deleterious substances

    and, when compacted under watering and rolling, form a firm , stable base. Aggregate

    shall consist of crushed stone, crushed slag, or crushed gravel.

    Crushed stone aggregate shall contain not more than eight (8) percent , by weight,

    flat, elongated, soft, or disintegrated pieces. Aggregate retained

    on

    the 2.36 mm (No.

    8) sieve shall consist of stone particles of which at least ninety percent (90 ), by

    weight, shall have at least two (2) mechanically fractured faces.

    The specified gradation shall be obtained by crushing , screening and blending

    processes, as necessary. The Contractor shall furnish, produce stockpile, blend and

    mix all necessary materials using such equipment and procedures as will produce the

    specified aggregate base.

    If additional fine material, in excess of that already present in the base course

    material, is necessary for correcting the gradation properties, for satisfactory bonding

    of

    the base material, or for adjusting the material characteristics

    of

    the fraction passing

    the 0.425 mm (No. 40) sieve, it shall be uniformly blended and mixed with the crushed

    aggregates. Such mixing shall take place at the crusher, at an approved stationary

    proportioning and mixing plant

    or on

    a traveling plant. Reworking

    of

    the base course

    material

    in

    place to obtain the specified requirements shall not be permitted. The

    additional fine material, if any, shall be obtained from crushing stones, gravel, or slag,

    and shall be of a gradation as required to accomplish the specified gradation of the final

    mixture.

    Aggregate shall conform to one

    of

    the following grading and quality requirements on

    the road bed after all blending and mixing and spreading and before compacting:

    7

  • 8/15/2019 Ksa Concrete Earth

    22/48

      oeGeneral Specifications November 1998

    Table of Contents

    TABLE 3.03-1

    AGGREGATE

    BASES

    GRADING

    REQUIREMENTS

    MRDTM 204

    PERCENTAGE

    PASSING

    SIEVE SIZES Grading I Grading II Grading III

    50 mm (2 inch) 100

    37.5

    mm

    1 inch) 100

    25 mm

    1

    inch) 55-85 70-95 100

    19 mm ( inch) 50-80 55-85 70-100

    4.75

    mm

    No.4) 30-60 30-60 35-65

    0.425

    mm

    (No.

    40)

    10-25 10-25 15-25

    0.075 mm (No. 200) 3-10 3-10 3-10

    The

    fraction

    passing the

    No. 200

    sieve shall not

    exceed

    the

    fraction passing

    the

    0.425 mm (No. 40) sieve.

    QUALITY REQUIREMENTS

    Sodium Sulphate Soundness MRDTM

    311)

    , Loss 12 Max.

    Abrasion Loss

    MRDTM

    309)

    45

    Max.

    Sand Equivalent MRDTM 313)

    45

    Min.

    Liquid Limit

    MRDTM 209)

    25 Max.

    Plasticity Index MRDTM 208) 6 Max.

    California Bearing Ratio MRDTM 213) Grading I 100 Min.

    California Bearing Ratio

    MRDTM 213)

    Grading

    II

    80 Min.

    California Bearing Ratio (CBR) MRDTM 213) Grading III

    65 Min.

    18

  • 8/15/2019 Ksa Concrete Earth

    23/48

      oeGeneral Specifications November 1998

    Table of ontents

    3.03.3 PROPORTIONING

    AGGREGATE BASE

    MIXES.

    3.03.3.1 Job Mix Design Proposal. A proposed Job Mix Formula (JMF) shall be

    formulated by the Contractor and submitted to the Engineer for approval. The JMF

    shall be prepared by the Contractor

    in

    precise compliance with procedures and

    requirements set forth

    in

    the Materials and Research Department Manual

    of

    Materials

    and Tests and all current letters issued by the Ministry

    of

    Communications.

    The Contractor shall select his sources

    of

    aggregate and, after sufficient quantities

    have been stockpiled or are available for

    use,

    obtain representative samples

    of

    the

    materials and test to determine if they conform to the requirements of these

    specifications. At least thirty (30) days before producing aggregate base mixtures, the

    Contractor shall submit in writing to the Engineer detailed information for each mix

    which he proposes to furnish. The information shall include, but not be limited to the

    following:

    1

    The source and gradation

    of

    the aggregate for each mix to be furnished. If the

    aggregate (coarse, fine, supplemental fine) is separated into two (2) or more sizes, the

    information provided shall consist of gradations for all individual sizes, the proportions

    of each individual size to be used, and the mathematically combined gradation for each

    mix to be furnished. Such combined gradation shall meet the applicable grading

    requirements shown

    in

    Subsection 3.03.2 Materials

    in

    these General Specifications

    and show the percentage passing each of the specified sieve sizes.

    2

    Pertinent test data and a written certification that the aggregates to be furnished

    conform to all quality requirements shown

    in

    Subsection 3.03.2, Materials

    in

    these

    General Specifications.

    3

    The type

    of

    plant to be used for mixing each mix to be furnished.

    4

    The beginning date for producing aggregate base mixtures.

    The Engineer

    shall be provided access to the materials sampling and testing

    operations at all times. The combined aggregate, including mineral additives, shall

    conform to the approved JMF grading within the following tolerances:

    9.75 mm (3/8 ) and larger sieves,

    4.75 mm No.4) sieve,

    2.36 mm No.8) sieve,

    0.300 mm (No. 50 sieve,

    0.075 mm (No. 200) sieve ,

    9 percentage points

    8 percentage points

    7 percentage points

    6 percentage points

    4 percentage points

    At the same time the above information is provided, the Contractor shall supply to

    the Engineer fifty (50) kilogram samples of each individual aggregate size, when used,

    ten (10) kilogram samples of mineral filler and chemical admixture, all representing the

    materials which the Contractor proposes to furnish.

    9

  • 8/15/2019 Ksa Concrete Earth

    24/48

      oeGeneral Specifications November 1998

    Table of ontents

    3.03.3.2

    Acceptance of Job

    Mix Formula. The Engineer shall review the

    JMF

    to

    determine that it contains all required information. If it does not contain all required

    information, it shall be returned within seven (7) days to the Contractor for further action

    and resubmission by the Contractor.

    If the proposed

    JMF

    contains all required information but fails to meet all the

    requirements specified, it shall not be accepted by the Engineer and will be returned to

    the Contractor within fourteen (14) days. The Contractor shall prepare and submit to

    the Engineer a new

    JMF

    conforming to the requirements specified and propose a new

    date for beginning production.

    When the Engineer is satisfied that the

    JMF

    proposed by the Contractor conforms

    to all the requirements of the specifications, he shall order the Contractor to construct

    a minimum two hundred (200) meter long field control strip. The Engineer shall

    evaluate the control strip as to its constructability and compactability and conformance

    to the laboratory tested JMF. Split samples of the aggregate base mix for and

    components raw material along with the field laboratory test results are to be sent to

    the Materials and Research Departments Central Laboratory for a one (1) point check

    and documentation. If the Engineer is not satisfied with the results of the control strip,

    he shall state his objections n writing and request a revised

    JMF

    and a new control

    strip.

    When the Engineer is satisfied that the

    JMF

    proposed by the Contractor conforms

    to all requirements of the specifications and the control strip results are acceptable , he

    will issue written acceptance to the Contractor to begin producing the mixes proposed.

    Production

    of

    aggregate base mixes shall not begin until the Engineer has given

    written acceptance of the Job Mix Formula.

    Acceptance of the

    JMF

    by the Engineer does not relieve the Contractor of his

    obligation to produce aggregate base mixes conforming to all specified requirements.

    3.03.3.3 Job

    Mix Formula

    Revisions

    The Contractor shall not alter his methods

    of

    crushing, screening, blending , or stockpiling from that used to produce materials for

    the approved JMF. Changes to the

    JMF

    will not be permitted without retesting and

    resubmission of a proposed (revised)

    JMF

    n accordance with all the steps n

    Paragraph 3.03.3.1 , Job Mix Design Proposal

    n

    these General Specifications.

    Significant changes may include, but not be limited to, changes

    n

    the amount or type

    of materials rejected or wasted, changes

    n

    the amount of materials crushed, reductions

    n

    the amount of crushed fines, changes

    n

    the amount and type of mineral filler.

    Should the Contractor change his source of aggregate, he shall furnish a new job

    mix design proposal and samples

    of

    materials, as described n Paragraph 3.03.3.1 , Job

    Mix Design Proposal n these General Specifications as determined by the Engineer

    to be necessary, at least twenty-one (21) days before their intended use.

    2

  • 8/15/2019 Ksa Concrete Earth

    25/48

      oeGeneral Specifications November 1998

    Table of ontents

    At any time after the JMF is approved the Contractor may submit a new JMF for

    approval by the Engineer. If the revised JMF is approved it shall become the approved

    JMF.

    3.03.4 EQUIPMENT. The Contractor shall furnish all necessary equipment for

    producing, stockpiling, moisture conditioning, and hauling aggregate, preparing the

    surface

    on

    which the aggregate base will be placed, and placing, spreading,

    compacting, finishing and maintaining the aggregate base

    in

    accordance with the

    minimum type and number outlined

    in

    the Contractor s Program

    of

    Work as approved

    by the Engineer. Blending and mixing aggregates and adjusting the moisture content

    as required for compaction shall be performed

    in

    a central mixing plant.

    The blended and mixed aggregates shall be placed and spread to the width and

    thickness specified using approved mechanical spreading equipment. Motor graders

    shall not be used for spreading.

    3.03.5 CONSTRUCTION.

    3.03.5.1 Contractor Quality Control Procedures Testing to control the quality

    of aggregate base furnished shall be the responsibility of the Contractor. Copies of all

    test results shall be forwarded to the Engineer at the end of each working day. The

    Engineer shall have access to the Contractor s testing laboratory at all times and

    reserves the right to obtain samples of the materials at any point during construction.

    When requested by the Engineer, the Contractor shall sample aggregate base

    materials and prepare duplicate samples, by quartering. One (1) sample shall be

    delivered to the Engineer and the duplicate sample shall be tested by the Contractor.

    The Contractor shall perform the following minimum types and number of tests:

    1

    Gradation, sand equivalent and plasticity index - One (1) test each per one

    thousand (1000) cubic meters

    of

    aggregates produced but not less than one (1) per

    production day.

    2

    Abrasion Loss - One (1) test for first, second and third five hundred (500) cubic

    meters of aggregate produced and one (1) test for each twenty-five hundred (2500)

    cubic meters thereafter.

    3

    Percent Crushed Faces - One (1) test for each five hundred (500) meters

    of

    aggregate produced.

    4

    CBR Value - One (1) test for each five thousand (5000) cubic meters.

    When test data indicate that the aggregate base does not conform to specified

    requirements, the Contractor shall take effective action to correct his production

    methods to assure that the materials produced will conform to all specified

    requirements. Such action shall include halting production, changing the source of

    aggregate supply, altering amount of aggregate scalped and rejected , increasing

    degree

    of

    crushing, and revising blending and handling methods.

    2

  • 8/15/2019 Ksa Concrete Earth

    26/48

      oeGeneral Specifications November 1998

    Table of ontents

    3.03.5.2

    Preparation

    and

    Maintenance

    After the subgrade or subbase surface

    has been prepared , the Contractor shall maintain it true to cross section , grade and

    density. The surface of the subgrade or subbase, immediately prior to receiving the

    aggregate base shall conform to the specified cross section , grade and density and

    shall be free of any loose or extraneous material. All subgrade or subbase protection,

    maintenance or repair work is considered subsidiary to items

    in

    the Bill

    of

    Quantities.

    3.03.5.3

    Mixing

    The aggregate and the water shall be thoroughly mixed

    in

    a twin

    shaft pugmill type mixer, unless another type of mixer is approved. The amount of

    water added to the aggregate shall be an amount which will provide the mixture with a

    satisfactory moisture content for compaction to the specified in-place density. The rate

    of fiow of the water to the pugmill shall be controlled by valves or other devices which

    can be easily reset when a change in the rate of fiow is desirable. The water supply

    system shall be equipped with a positive cut-off control which will stop the fiow of water

    simultaneously with any stoppage

    in

    the fiow of aggregate into the pugmill.

    3.03.5.4 Transporting The plant-mixed material shall be transported

    in

    such

    manner as to deliver the mix to the project without loss or segregation. Each truck load

    shall be covered with a heavy canvas sheet to reduce the loss of moisture in transit

    whenever the time between loading the work and spreading the moisture exceeds thirty

    (30) minutes.

    3.03.5.5 Placing and Spreading The mixture shall be placed on the existing

    roadway, approved subgrade or approved subbase, as the case may be,

    in

    a uniform

    layer or layers not exceeding fifteen (15) centimeters

    in

    compacted depth. Where the

    required thickness is greater than fifteen (15) centimeters, the material shall be placed

    in

    layers

    of

    equal thickness. However, if heavy duty vibratory compaction equipment

    approved by the Engineer is used, the maximum compacted layer thickness may be

    increased to twenty (20) centimeters provided test trial compaction tests indicate

    compliance with these General Specifications including the following:

    1

    Compaction samples are taken from the entire layer including the lower part

    of

    the increased thickness.

    2 The coarse aggregates on the top of the Aggregate Base layers are not

    damaged or crushed.

    The increased thickness approval will be rescinded by the Engineer if more than

    fifteen percent (15 ) of the subsequent field density tests taken

    on

    the thicker layer

    initially fail, necessitating retesting after additional compaction.

    The mixture course shall be placed on the roadbed to the required width and

    uncompacted thickness as follows:

    1

    Through an approved self-propelled spreading machine.

    2 In a sized windrow from which a paving machine or travel plant will pickup and

    spread the aggregate base.

  • 8/15/2019 Ksa Concrete Earth

    27/48

      oeGeneral Specifications November 1998

    Table of ontents

    3

    To protect the underlayer and to allow proper drainage, the spreading

    of

    the

    base course material shall begin along the centerline on stretches with a crowned

    section

    or

    on the high side of stretches with a one-way slope.

    The approved spreader shall deliver the mixture in such a condition that the material

    will be ready for compaction without further shaping. Unless otherwise permitted by the

    Engineer, the aggregate shall be spread not more than two thousand (.2000) square

    meters ahead

    of

    the rollers. Any necessary sprinkling shall be kept within this limit.

    The material shall be handled so as to avoid segregation. If the approved spreader

    causes segregation

    in

    the material , or leaves ridges or other objectionable marks

    on

    the

    surface which cannot be eliminated easily or prevented by adjustment to the spreading

    operation , the use of such approved spreader shall be discontinued , and it shall be

    replaced. All segregated material shall be removed and replaced with well-graded

    material. No skin patching shall be permitted. Only minor surface manipulation and

    watering to achieve the required surface tolerances shall be permitted during the

    compaction process.

    No hauling or placement of material will be permitted when, in the judgement of the

    Engineer, the weather or road conditions are such that hauling operations will cause

    rutting of the road surface or cause contamination of the subbase or base course

    material. Before placing the mixture, the subgrade or previous layer shall be wetted to

    insure bond between the layers. The mixture shall be placed and shaped by power

    equipment to the lines, elevations, cross sections, depths and density specified

    in

    the

    following subsections.

    3.03.5.6 Compacting Each layer

    of

    aggregate base material, after being shaped

    to the required lines and cross section, shall be compacted to a uniform density with no

    individual test being less than ninety-five percent (95%) of the maximum dry unit weight

    determined from MRDTM 212. Each lot

    of

    base material as described

    in

    Subsection

    3.03.6, Quality Assurance Procedures

    in

    these General Specifications shall have a

    percent relative compaction

    of

    no less than one hundred percent (100%)

    of

    the

    maximum dry unit weight determined from MRDTM 212. The aggregate base shall be

    watered or dried as may be necessary to obtain a moisture content suitable for

    compaction. Material which has dried prior to final compaction or which has dried and

    decompacted subsequent to final compaction shall be watered and recompacted using

    equipment and procedures approved by the Engineer. Should the Contractor be

    unable to return the material to its original or specified condition with respect to

    compaction, thickness, and surface tolerances, the Contractor shall remove the material

    and reconstruct the course

    on

    a reapproved subgrade.

    When there are delays

    in

    constructing the remaining pavement structure over a

    granular course, the compaction

    of

    the granular course shall be reverified and deficient

    areas corrected

    or

    replaced to the satisfaction of the Engineer. Such corrections or

    replacement shall be at the Contractor's expense.

    The Contractor shall plan the work and handle the various operations so that the

    least amount

    of

    water will be lost by evaporation from uncompleted surfaces. If the

    Contractor delays placing or succeeding layers

    of

    material to the extent that additional

    3

  • 8/15/2019 Ksa Concrete Earth

    28/48

      oeGeneral Specifications November 1998

    Table of ontents

    water must be applied to prevent raveling or excessive drying , the application of such

    water shall be at the Contractor s expense and will not be considered as the basis for

    a claim for additional compensation.

    The material shall be compacted by means of approved compaction equipment,

    progressing gradually from the outside towards the center, with each succeeding pass

    uniformly overlapping the previous pass. Rolling shall continue until the entire thickness

    of each layer is thoroughly and uniformly compacted to the specified density. The base

    course shall not be rolled when the underlayer is soft or yielding or when rolling causes

    undulation of the base course. The final rolling of the completed course shall be done

    with a self-propelled roller as approved by the Engineer. Rolling shall be accompanied

    by sufficient blading , n a manner approved by the Engineer, to insure a smooth

    surface, free from ruts or ridges and having the proper section and crown. When

    additional water is required, it shall be added n the amount and manner approved by

    the Engineer. Initial layers of material must be constructed to a uniform grade and

    cross section and compacted by the Contractor and approved by the Engineer prior to

    the delivery of materials for a succeeding layer.

    Prior to placing a succeeding layer

    of

    granular material , the surface

    of

    the underlayer

    shall be made sufficiently moist, to insure bond between the layers. The edges and

    edge slopes of the base course shall be bladed or otherwise dressed to conform to the

    lines and dimensions shown on the plans, and present straight, neat and workmanlike

    lines and slopes as free of loose material as practicable.

    Any areas inaccessible to normal compaction equipment shall be compacted by