ksa concrete earth
TRANSCRIPT
-
8/15/2019 Ksa Concrete Earth
1/48
able
of Contents
KINGDOM
O
SAUDI R BI
MINISTRY OF COMMUNICATIONS
GENERAL SPECIFICATIONS
FOR
ROAD AND BRIDGE CONSTRUCTION
November 998
PART THREE
AGGREGATE SUBBASE AND BASE COURSES
-
8/15/2019 Ksa Concrete Earth
2/48
ableof Contents
PART THREE
AGGREGATE
SUBB SE
AND BASE COURSES
T BLE OF CONTENTS
PART THREE: AGGREGATE SUBBASE AND BASE COURSESSECTION 3 01 -
PRODUCTION HANDLING AND STOCKPILING AGGREGATES 1
3.01.1 DESCRIPTION .......................................................................................... 1
3.01.2 MATERIALS .................................................................................. .......... 1
3.01.2.1 Sources ........................................................................................... 1
3.01.2.2 Definitions ...........................................................
......................... 1
3.01.3 PRODUCTION REQUIREMENTS ........
............................................... 2
3.01.3.1 Preparation of Site .................................... ... .................................... 2
3.01.3.2 Production
of
Aggregates .................... .......................................... 2
3.01.3.3 Rejected Aggregates .......................... ........................................... 3
3.01.3.4 Surplus Screenings ................................. . ............................... 3
3.01.3.5 Site Cleanup ...................................................... .... .... ...................... 3
3.01.4 QUALITY ASSURANCE PROCEDURES .....................................
.... ....... 3
3.01.4.1 Methods and Procedures ................................................................ 3
3.01.4.2 Preliminary Testing ....................................... .... ............................. 4
3.01.4.3 Production Testing .................................... ... .................................... 4
3.01.4.4 Acceptance Testing ................................ .......................................... 4
3.01.5 STOCKPILING AGGREGATES .............. ..... ....................................... 4
3.01.5.1 Sites ................................................................................... .............. 4
3.01.5.2 Preparation of Stockpile Site ........................................................... 4
3.01.5.3 Construction of Stockpiles ............................................................... 4
3.01.5.4 Removing Aggregate From Stockpiles ...........................
........... 5
3.01.5.5 Site Cleanup ...................................................... .... .... ...................... 5
3.01.6 METHOD OF MEASUREMENT ....................
.......................................... 5
3.01.7 PAYMENT ............................................................................. .................. 5
SECTION 3.02 - AGGREGATE SUBBASES ................................................................ 6
3.02.1 DESCRIPTION .......................................................................................... 6
3.02.2 MATERIALS .............................................................................................. 6
3.02.3 PROPORTIONING AGGREGATE SUBBASE MIXTURES ....................... 7
3.02.3.1 Job Mix Design Proposal ................................................................. 7
3.02.3.2 Acceptance
of
Job Mix Formula ............................................. ....... 8
3.02.3.3 Job Mix Formula Revisions .............. .......................................... 9
3.02.4 EQUIPMENT ................................................................................ ............. 9
3.02.5 CONSTRUCTION ......................................................... ...... ..................... 9
3.02.5.1 Contractor Quality Control Procedures ....................... ..................... 9
3.02.5.2 Surface Preparation ....................................
............................. 10
3.02.5.3 Placing and Spreading ....................... ....... .................................... 10
3.02.5.4 Compacting ....................................................... ............................ 10
3.02.5.5 Finishing ........................................................................................ 12
3.02.5.6 Maintenance and Protection .......................................................... 12
3.02.5.7 Compaction Test Trials ......................... ......................................... 12
3.02.6 QUALITY ASSURANCE PROCEDURES ..................................... ....... 12
-
8/15/2019 Ksa Concrete Earth
3/48
Table of ontents
3.02.6.1 Compaction ................................................................................... 13
3.02.6.2 Thickness ...................................................................................... 14
3.02.6.3 Aggregate Gradation Sand Equivalent and Plasticity Index ......... 14
3.02.6.4 California Bearing Ratio and Abrasion ........................................... 15
3.02.6.5 Surface Tolerances ....................................................................... 15
3.02.6.6 Acceptance .................................................................................... 15
3.02.7 METHOD OF MEASUREMENT ...... ....... ....
........................................... 16
3.02.8 PAYMENT ........................................................................ .......
.............. 16
SECTION 3.03 - AGGREGATE BASES .......................... ....
..................................... 17
3.03.1 DESCRIPTION ........................................................................................ 17
3.03.2 MATERIALS ....................................................................... ................. 17
3.03.3 PROPORTIONING AGGREGATE BASE MIXES ............................. 19
3.03.3.1 Job Mix Design Proposal ............................................................... 19
3.03.3.2 Acceptance of Job Mix Formula .............................................. ...... 20
3.03.3.3 Job Mix Formula Revisions ............................................................ 20
3.03.4 EQUIPMENT ...........................................................................................
21
3.03.5 CONSTRUCTION ..................................................
.... ....
......................
21
3.03.5.1 Contractor Quality Control Procedures ...................... ... .............. 21
3.03.5.2 Preparation and Maintenance ............................................. ...... 22
3.03.5.3 Mixing ............................................................... ............................. 22
3.03.5.4 Transporting .................................................... ....
........................ 22
3.03.5.5 Placing and Spreading .............. .................................................. 22
3.03.5.6 Compacting .............................................. ..................................... 23
3.03.5.7 Finishing ....................................................................
.................. 24
3.03.5.8 Maintenance and Protection .......................................................... 24
3.03.5.9 Compaction Test Trials .................................................................. 25
3.03.6 QUALITY ASSURANCE PROCEDURES ............................ .................... 25
3.03.6.1 Compaction ................................................................................... 26
3.03.6.2 Thickness ...................................................................................... 26
3.03.6.3 Aggregate Gradation Sand Equivalent and Plasticity Index ......... 27
3.03.6.4 California Bearing Ratio and Abrasion ........................................... 27
3.03.6.5 Surface Tolerances ....................................................................... 28
3.03.6.6 Acceptance ......................................................... ......................... 28
3.03.7 METHOD OF MEASUREMENT ...... ........................................................ 29
3.03.8 PAYMENT ...................................................................... ......................... 29
SECTION 3.04 - CEMENT TREATED BASES ....... .................................................. 30
3.04.1 DESCRIPTION ........................................................................................ 30
3.04.2 MATERIALS ...................................................................
....................... 30
3.04.2.1 Portland Cement ....................................
...................................... 30
3.04.2.2 Aggregate .....................................................
......
....................... 30
3.04.2.3 Water ................................................................. ............................
31
3.04.2.4 Flyash and Chemical Admixtures........................................ ...... 31
3.04.2.5 Bituminous Curing Seal ................................................................. 31
3.04.3 MIX DESiGN .................................. ........................................... .... ..... 31
3.04.4 WEATHER LIMITATIONS ........................ ............................................. 32
3.04.5 EQUIPMENT .................................................................
....
................ 32
3.04.6 CONSTRUCTION REQUIREMENTS ...................................................... 32
-
8/15/2019 Ksa Concrete Earth
4/48
ableof Contents
3.04.6.1 Surface Preparation ........................
....... ...................................... 32
3.04.6.2 Proportioning and Plant Mixing ........................................ ............ 33
3.04.6.3 Transporting and Spreading .......................................................... 34
3.04.6.4 Compacting and Finishing ........... ................................................ 35
3.04.6.5 Operation Time Requirement ........................................................ 35
3.04.6.6 Construction Joints ........................................................................ 36
3.04.7 CURING ................................................................................................... 36
3.04.8 CONTRACTOR QUALITY CONTROL PROCEDURES .......................... 36
3.04.9 QUALITY ASSURANCE PROCEDURES ............................
................ 36
3.04.9.1 Compaction ................................................................................... 37
3.04.9.2 Thickness ...................................................................................... 37
3.04.9.3 Aggregate Gradation Sand Equivalent and Plasticity Index ......... 38
3.04.9.4 California Bearing Ratio or Compressive Strength ........................ 39
3.04.9.5 Surface Tolerances ....................................................................... 39
3.04.9.6 Acceptance .................................................. .... .............................. 39
3.04.10 METHOD
OF
MEASUREMENT ............................................................. 40
3.04.11 PAYMENT .............................................................................................. 40
SECTION 3.05 - SHOULDERS AND LAYBYS ...... ................................................. 41
3.05.1 DESCRIPTION ..........................................................
............................ 41
3.05.2 EQUIPMENT ................................................................
......................... 41
3.05.3 CONSTRUCTION REQUIREMENTS ............................................
........ 41
3.05.3.1 General ................................................
....
........................... 41
3.05.3.2 Earth Shoulders and Laybys ..............................................
....... 42
3.05.3.3 Aggregate Shoulders and Laybys .......................................
...... 42
3.05.3.4 Bituminous Base Shoulders and Laybys ................
...
................ 42
3.05.3.5 Bituminous Wearing for Shoulders and Laybys ............................. 42
3.05.4 SHOULDERING AND DELINEATION ...................................... ........... 42
3.05.5 COMPACTION REQUiREMENTS ........................................................... 42
3.05.6 METHOD OF MEASUREMENT .......... ...
............................................... 43
3.05.7 PAYMENT .......................................................................
...................... 43
-
8/15/2019 Ksa Concrete Earth
5/48
oeGeneral Specifications November 1998
Table of ontents
PART
THREE:
AGGREGATE
SUBBASE
AND
BASE
COURSES
SECTION 3.01 - PRODUCTION, HANDLING
AND
STOCKPILING
AGGREGATES
3.01.1 DESCRIPTION. This work consists
of
producing, handling and stockpiling
crushed and screened aggregates including pit run aggregates
of
the kind, quality and
grading specified for all types
of
materials to be used
in
road and bridge and related
construction.
Requirements set forth herein shall apply whether the source be ledge rock, talus ,
gravel , sand, or a combination thereof.
3.01.2 MATERIALS.
3.01.2.1 Sources. Materials sources may be shown
on
the plans, described
in
the
special specifications, or established by the Contractor after approval by the Engineer.
The Contractor shall furnish the Engineer, not less than thirty 30) days prior to the
scheduled date for beginning crushing operations, information
on
the source of
aggregates, the method of production to be employed, types and capacity of equipment
to be used and a schedule showing rates of production for the several types of
aggregate to be produced.
Whether or not the materials sources are shown
on
the plans, specified
in
the
special specifications, or established by the Contractor after approval by the Engineer,
the Contractor shall determine for himself the types and numbers
of
equipment and
extent of work needed to remove overburden and produce the volumes of aggregates
required for the work within the contract time, and produce aggregates having the
fracture, gradation and quality conforming to the specifications.
The Engineer may require procurement
of
aggregate from any portion
of
a source
and may reject portions
of
the source as being unacceptable.
3.01.2.2 Definitions.
1. Coarse aggregate consists of particles retained on the 4.75 mm No.4) sieve.
2.
Fine aggregate consists
of
particles passing the 4.75 mm No.4) sieve.
3.
Crushed stone consists
of
rock and stone fragments
or
gravel having one 1)
or more mechanically fractured faces. Every fractured face shall have a minimum
dimension from edge to edge across the fractured face which is not less than one-third
1
/3) the minimum dimension of the aggregate particle.
4. Gravel consists of uncrushed aggregate particles passing a seventy-five 75)
millimeter 3-inch) sieve and retained on a 4.75 mm No.4) sieve.
-
8/15/2019 Ksa Concrete Earth
6/48
oeGeneral Specifications November 1998
Table of ontents
5
Sand consists of aggregate particles passing a 4.75 millimeter No.4) sieve and
retained
on
a 0.075 millimeter (No. 200) sieve and may be naturally occurring,
manufactured or combinations thereof.
6 Material passing a 0.075 mm (No. 200) sieve may be referred to as silt or clay
or
dust depending on other characteristics.
3.01.3 PRODUCTION REQUIREMENTS.
3.01.3.1 Preparation
of
Site. The portion of the quarry or pit site to be used shall
be cleared and grubbed as specified
in
Section 2.01, Clearing and Grubbing
in
these
General Specifications.
When clearing and grubbing is completed, all surface materials which are
unsatisfactory for the kind of aggregate to be produced shall be stripped and removed.
Materials from clearing, grubbing and stripping which are removed as unsatisfactory
for producing specified aggregates shall be disposed of at locations not visible from the
roadway,
in
a manner that precludes erosion by wind
or
water and the form and
contours
of
the finished disposal area blends with adjacent terrain.
The costs involved
in
preparing the site, clearing , grubbing, stripping and removing
overburden and other operations shall be incidental to the production of aggregate and
shall be included by the Contractor in the contract unit price for the specific aggregate
produced.
3.01.3.2
Production of
Aggregates. The Contractor shall , as a minimum, utilize
all stone, rock fragments or boulders occurring
in
the source, up to and including those
measuring four hundred and fifty (450) millimeters in greatest dimension,
in
the
manufacture of crushed aggregates. The Contractor, at his option, may use stone and
boulders larger than four hundred and fifty (450) millimeters
in
greatest dimension.
When the percent fracture and other requirements cannot be obtained by using the
natural material, portions of the material may be rejected to the extent necessary to
produce aggregates conforming to the requirements of the specifications.
Failure to include an aggregate scalping and rejection requirement in the
specifications for any type of aggregate shall not relieve the Contractor of the
responsibility for scalping and rejection of portions of the materials
if
such become
necessary to produce aggregates conforming to the requirements of the specifications.
When scalping over a screen of specified size is required
in
the special
specifications, the scalping screen shall be of such size and capacity that enough of the
fine material will be removed to produce aggregates conforming to the requirements
of
the specifications.
Rejected materials may be used
in
other portions of the work and locations when it
conforms to the specified requirements for said other portions and locations.
-
8/15/2019 Ksa Concrete Earth
7/48
oeGeneral Specifications November 1998
Table of ontents
Surplus screenings accumulated during crushing and screening
of
specified
aggregates shall be kept separate from materials rejected during scalping operations.
Washing of coarse and fine aggregates shall be performed as specified in the
special specifications or as may be necessary to produce aggregates free from clay,
loam, alkali , vegetable and other deleterious material.
Washing and reclaiming
of
rejected material and subsequent addition to any finished
aggregate shall not be allowed unless authorized
in
writing by the Engineer.
When producing screened gravel or sand materials, the Contractor shall remove all
oversize material by screening at the source. Operations at the source shall be such
that the grading of aggregates in each hauling unit is reasonably uniform within
tolerances that are specified for individual materials. The Contractor shall use the most
suitable materials available at the source. He shall move his loading equipment as
many times as may be necessary to fulfill these requirements.
3.01.3.3 Rejected Aggregates All rejected materials unsatisfactory for use
in
other portions
of
the work and locations, shall
e
disposed
of
as specified
in
Paragraph
3.01.3.1 , Preparation of Site in these General Specifications.
3.01.3.4 Surplus
Screenings
Surplus screenings accumulated during the
production
of
the specified aggregates at material sources established by the
Contractor shall remain the property of the Contractor.
Surplus screenings accumulated during the production
of
the specified aggregates
at materials sources shown on the plans or described in the special specifications and
furnished by the Ministry shall be stockpiled at the source and become the property
of
the Ministry.
The stockpile area shall be prepared and constructed as specified
in
Subsection
3.01.5, Stockpiling Aggregates
in
these General Specifications. All costs incurred
in
producing, hauling and stockpiling the surplus screenings shall be incidental to the
production
of
the specified aggregates and shall be included by the Contractor
in
the
contract unit prices for said aggregates.
3.01.3.5 Site Cleanup Upon completion of the Contractor's operations at any
source, the quarry or pit shall be cleared of rubbish, equipment, temporary structures
and other items brought to the site by the Contractor. The site shall be left
in
a neat
and presentable condition. When the special specifications require that aggregate
sources e reclaimed
in
accordance with an approved reclamation plan, the Contractor
shall comply with such approved reclamation plan.
3.01.4
QUALITY
ASSURANCE PROCEDURES
3.01.4.1 Methods and Procedures All aggregate testing shall be performed in
accordance with methods and procedures described in the specifications and Materials
Manual publications issued by the Ministry of Communications, Materials and Research
Department.
-
8/15/2019 Ksa Concrete Earth
8/48
oeGeneral Specifications November 1998
Table of ontents
3.01.4.2 Preliminary
Testing
The Contractor shall submit to the Engineer all
results
of
testing as may be necessary to confirm that the source
of
materials ,
equipment and production methods to be employed by the Contractor will produce
aggregates conforming to the requirements of the specifications. No installation of
equipment or production shall start at any materials source until the Engineer has
approved the source, and the dimensions
of
the area to be excavated. The equipment
and methods proposed by the Contractor shall also be approved by the Engineer.
The approval
of
the Engineer shall not be construed as final acceptance
of
the
aggregate to be produced.
Representative samples of materials may be obtained by the Contractor and , when
requested, duplicate samples shall be furnished to the Engineer for testing and future
reference.
Testing may be accomplished
in
the Contractor's laboratory or a commercial
laboratory. The testing shall be the responsibility
of
the Contractor and performed at
his expense.
3.01.4.3 Production Testing The Contractor shall arrange all testing necessary
to control specified aggregate fracture , gradation and quality during production as
specified
in
Paragraphs 3.02.5.1, 3.03.5.1 and 3.04.8 all entitled Contractor Quality
Control Procedures in these General Specifications. The results of such testing shall
be promptly delivered to the Engineer. Such test results are intended to be used to
guide the Contractor operations and shall not be used to infer that the aggregates being
produced are acceptable and
in
conformance to the specifications.
3.01.4.4 Acceptance Testing The Engineer shall sample or supervise the
sampling testing and evaluation of aggregates furnished to the work as specified in
Subsections 3.02.6, 3.03.6 and 3.04.9 all entitled Quality Assurance Procedures
in
these General Specifications.
3.01.5 STOCKPILING
AGGREGATES
3.01.5.1 Sites. The site for constructing stockpiles shall be approved by the
Engineer and located in a manner that the stockpiled materials will not e contaminated
with other aggregates or altered by dust, dune sand or other natural or processed
material. Stockpiling
on
private property shall be permitted with the written consent
of
the owner or lessee. The Engineer shall be afforded access to the stockpiled materials
at all times.
3.01.5.2
Preparation of Stockpile
Site. Before placing aggregates on the
stockpile site, the site shall be cleared
of
vegetation, rocks and debris and the ground
leveled to a smooth, firm uniform surface.
3.01.5.3 Construction of Stockpiles The stockpiles shall be constructed
on
the
prepared site, shall be neat and regular
in
shape and not more than eight (8) meters
in
height.
-
8/15/2019 Ksa Concrete Earth
9/48
oeGeneral Specifications November 1998
Table of ontents
Stockpiles
n
excess of two hundred 200) cubic meters shall be built up n layers not
more than one and one-half 1.5) meters
n
depth using methods and equipment
approved by the Engineer. Pushing aggregate into a stockpile using dozers will not be
permitted. Each layer shall be completed over the entire area of the pile before
depositing aggregate n the succeeding layer. Any method of placing aggregate n a
stockpile which,
n
the opinion
of
the Engineer, results
n
segregation, breaks, degrades
or otherwise damages the aggregate will not be permitted.
Stockpiles
of
different kinds or sizes
of
aggregate shall be separated by space or
suitable walls or partitions to prevent mixing. Aggregate shall not be stockpiled where
vehicles will run over or through the piles and cause foreign material to become mixed
with the stockpiled aggregate.
3.01.5.4 Removing Aggregate From Stockpiles Aggregate shall be removed
from the stockpiles using equipment and methods approved by the Engineer and n a
manner that precludes segregation
of
particle sizes or adulteration with underlying or
adjacent soil or foreign material.
When removing aggregate from stockpiles, the removal equipment shall be operated
n such a manner as to face-load from the floor to the top of the stockpile to obtain
maximum uniformity of aggregate.
The Contractor shall remove only such aggregate quantities as are necessary to
complete work under the contract.
3.01.5.5
Site Cleanup
If a surplus remains
n
the stockpile , the Contractor shall
leave said surplus
n
neat, regular shaped piles, free
of
foreign matter and equipment.
3.01.6 METHOD OF MEASUREMENT. No measurement will be made for any work
or
aggregate produced under this section.
3.01.7 PAYMENT. Full compensation for performing all
of
the work specified
n
this
section shall be considered as subsidiary to other items
of
work appearing
n
the Bill
of
Quantities unless otherwise provided for
n
the Special Specifications and listed
n
the
Bill of Quantities.
-
8/15/2019 Ksa Concrete Earth
10/48
oe
General Specifications November
1998
able of Contents
SECTION 3.02 -
AGGREGATE
SUBBASES
3.02.1 DESCRIPTION. This work shall consist of furnishing, spreading and
compacting aggregate subbases to the lines and elevations shown on the plans as
specified in these General Specifications and the Special Specifications.
Aggregate subbases will be designated as Aggregate Subbase Course
or
Aggregate
Subbase Course, Grading
_
The grading s)
of
aggregate subbase to be furnished
shall be according to the item s) shown
in
the Plans or Special Specifications and listed
in
the Bill
of
Quantities. If the grading
of
aggregate subbase is not specified, aggregate
subbase course shall be furnished meeting one
of
the gradations listed
in
Table 3.02-1
as designated by the Engineer. The designation of the appropriate Grading shall be
such that the maximum size of aggregate will not exceed two thirds 2/3) of the
thickness of the subbase course layer to be constructed.
ITEMS IN BILL OF QUANTITIES:
Aggregate Subbase Course
Aggregate Subbase Course,
rad ing_
3.02.2 MATERIALS. Aggregate used for aggregate subbase shall be free from
vegetation matter and other deleterious substances and, when compacted under
watering and rolling, form a firm, stable subbase. Coarse aggregate shall be crushed
stone, crushed slag,
or
crushed gravel. Fine aggregate, material passing the 4.75 mm
No. 14) sieve, shall consist of natural
or
crushed sand and fine material particles.
The Contractor shall furnish , produce, stockpile, blend and mix all necessary
materials using such equipment and procedures as will produce specified aggregate
subbase. Aggregate shall conform to one of the following grading and quality
requirements on the road bed after all blending and mixing and spreading and before
compacting:
TABLE 3.02-1
AGGREGATE SUBBASES GRADATION REQUIREMENTS - MTDTM 204
Sieve Sizes Grading I Grading II
62.5 mm
2
inch) 100
50 mm 2
in
ch) 90-100 100
37.5 mm 1 inch)
-
90-100
25 mm 1 inch)
-
55-85
19 mm 3/4 inch)
-
50-80
9.5 mm inch)
-
40-70
4.75 mm
No.4)
35-70 30-60
2.54 mm No.1 0)
-
20-50
0.425 mm No. 40)
-
10-30
0.075 mm No. 200) 0-15 0-15
-
8/15/2019 Ksa Concrete Earth
11/48
oeGeneral Specifications November 1998
Table of ontents
QUALITY
REQUIREMENTS
Sand Equivalent (MRDTM 313) 25 Min.
Plasticity Index (MRDTM 208) 6 Max.
Abrasion Loss (MRDTM
309) 50 Max.
California Bearing Ratio (CBR) 50 Min.
(MRDTM 213)
Aggregate for Grading
III
aggregate subbase shall conform to the requirements
specified
in
the Special Specifications.
3.02.3 PROPORTIONING AGGREGATE
SUBBASE
MIXTURES.
3.02.3.1 Job Mix Design Proposal. A proposed Job Mix Formula (JMF) shall be
formulated by the Contractor and submitted to the Engineer for approval. The JMF
shall be prepared by the Contractor in precise compliance with procedures and
requirements set forth
in
the Materials and Research Department Manual of Materials
and Tests and all current letters issued by the Ministry
of
Communications.
The Contractor shall select his sources of aggregate and , after sufficient quantities
have been stockpiled or are available for use obtain representative samples of the
materials and test to determine if they conform to the requirements of these
specifications. At least thirty (30) days before producing aggregate subbase mixtures,
the Contractor shall submit
in
writing to the Engineer detailed information for each mix
which he proposes to furnish. The information shall include, but not be limited to the
following:
1 The source and gradation of the aggregate for each mix to be furnished. If the
aggregate (coarse, fine, supplemental fine)
is
separated into two (2) or more sizes , the
information provided shall consist of gradations for all individual sizes, the proportions
of each individual size to be used, and the mathematically combined gradation for each
mix to be furnished. Such combined gradation shall meet the applicable grading
requirements shown
in
Subsection 3.03.2, Materials
in
these General Specifications
and show the percentage passing each
of
the specified sieve sizes.
2 Pertinent test data and a written certification that the aggregates to be furnished
conform to all quality requirements shown
in
Subsection 3.03.2, Materials
in
these
General Specifications.
3
The type
of
plant to be used for mixing each mix to be furnished.
4. The beginning date for producing aggregate subbase mixtures.
-
8/15/2019 Ksa Concrete Earth
12/48
oeGeneral Specifications November 1998
Table of ontents
The Engineer shall be provided access to the materials sampling and testing
operations at all times. The combined aggregate, including mineral additives, shall
conform to the approved JMF grading within the following tolerances:
9.75 mm (3/8 ) and larger sieves,
4.75 mm
No.4)
sieve,
2.36 mm
No.8)
sieve,
0.300 mm (No. 50) sieve,
0.075 mm (No. 200) sieve ,
percentage points
10 percentage points
9 percentage points
8 percentage points
8 percentage points
At the same time the above information is provided, the Contractor shall supply to
the Engineer fifty (50) kilogram samples of each individual aggregate size, when used,
ten (10) kilogram samples
of
mineral filler and chemical admixture, all representing the
materials which the Contractor proposes to furnish.
3.02.3.2
Acceptance
of
Job
Mix Formula. The Engineer shall review the JMF to
determine that it contains all required information. If it does not contain all required
information, it shall be returned within seven (7) days to the Contractor for further action
and resubmission by the Contractor.
If the proposed JMF contains all required information but fails to meet all the
requirements specified, it shall not be accepted by the Engineer and will be returned to
the Contractor within fourteen (14) days. The Contractor shall prepare and submit to
the Engineer a new JMF conforming to the requirements specified and propose a new
date for beginning production.
When the Engineer is satisfied that the JMF proposed by the Contractor conforms
to all the requirements of the specifications, he shall order the Contractor to construct
a minimum two hundred (200) meter long field control strip. The Engineer shall
evaluate the control strip as to its constructability and compactability and conformance
to the laboratory tested JMF. Split samples of the aggregate subbase mix for and
components raw material along with the field laboratory test results are to be sent to the
Materials and Research Departments Central Laboratory for a one (1) point check and
documentation. If the Engineer is not satisfied with the results of the control strip, he
shall state his objections
in
writing and request a revised JMF and a new control strip.
When the Engineer is satisfied that the JMF proposed by the Contractor conforms
to all requirements
of
the specifications and the control strip results are acceptable, he
will issue written acceptance to the Contractor to begin producing the mixes proposed.
Production
of
aggregate subbase mixes shall not begin until the Engineer has given
written acceptance of the Job Mix Formula.
Acceptance of the JMF by the Engineer does not relieve the Contractor of his
obligation to produce aggregate subbase mixes conforming to all specified
requirements.
-
8/15/2019 Ksa Concrete Earth
13/48
oeGeneral Specifications November 1998
Table of ontents
3.02.3.3 Job Mix
Formula
Revisions The Contractor shall not alter his methods
of
crushing, screening, blending , or stockpiling from that used to produce materials for
the approved JMF. Changes to the JMF will not be permitted without retesting and
resubmission of a proposed (revised) JMF in accordance with all the steps in Paragraph
3.02.3.1, Job Mix Design Proposal in these General Specifications. Significant
changes may include, but not be limited to, changes
in
the amount or type
of
materials
rejected or wasted, changes
in
the amount
of
materials crushed, reductions
in
the
amount
of
crushed fines, changes
in
the amount and type
of
mineral filler.
Should the Contractor change his source
of
aggregate, he shall furnish a new job
mix design proposal and samples
of
materials, as described
in
Paragraph 3.02.3.1 , Job
Mix Design Proposal in these General Specifications, as determined by the Engineer
to be necessary, at least twenty-one (21) days before their intended use.
At any time after the JMF is approved the Contractor may submit a new JMF for
approval by the Engineer. If the revised JMF is approved it shall become the approved
JMF.
3.02.4 EQUIPMENT. The Contractor shall furnish all necessary equipment for
production, stockpiling and hauling aggregate, preparing the subgrade and placing,
compacting, finishing and maintaining the aggregate subbase according to the minimum
type and number outlined in the contractor's detailed Program
of
Work as approved by
the Engineer.
Blending and mixing aggregates and adjusting the moisture content as required for
compaction shall be performed
in
a central mixing plant or on the grade by means that
insure uniformity.
The blended and mixed aggregates shall be placed and spread to the width and
thickness specified.
3.02.5 CONSTRUCTION.
3.02.5.1
Contractor
Quality
Control Procedures
Testing to control the quality
of aggregate furnished for subbase shall be the responsibility of the Contractor. Copies
of all test results shall be forwarded to the Engineer at the end of each working day.
The Engineer shall have access to the Contractor's testing laboratory at all times and
reserves the right to obtain samples
of
the materials at any point during construction.
When requested by the Engineer, the Contractor shall obtain aggregate subbase
materials and prepare duplicate samples by quartering . One (1) sample shall be
delivered to the Engineer and the duplicate sample shall be tested by the Contractor.
The Contractor shall perform the following minimum types and number
of
tests:
1
Gradation, sand equivalent and plasticity index - One (1) test each per two
thousand (2000) cubic meters of aggregates produced but no less than one (1) test per
production day.
-
8/15/2019 Ksa Concrete Earth
14/48
oeGeneral Specifications November 1998
Table of ontents
2
Abrasion Loss - One (1) test for the first, second and third five hundred (500)
cubic meters
of
aggregate produced and one (1) test for each twenty-five hundred
(2500) cubic meters thereafter.
3 CBR Value - One (1) test for each five thousand (5,000) cubic meters placed.
When test data indicate that the aggregate subbase does not conform to specified
requirements, the Contractor shall take effective action to correct his production
methods to assure that subbase aggregate will conform to all specified requirements.
Such action shall include halting production, changing the source
of
aggregate supply,
altering amount
of
aggregated scalped and rejected , increasing degree
of
crushing, and
revising blending and handling methods. Such material if already placed, shall be
removed and modified or replaced to produce material conforming to the specified
requirements.
3.02.5.2
Surface Preparation
The surface to receive aggregate subbase,
immediately prior to spreading aggregate subbase, shall conform to specified
compaction and elevation tolerances and shall be free
of
loose or extraneous material.
The Contractor shall correct, at his own expense, any deviation from specified
elevation and compaction in the surface to receive aggregate subbase.
When surfaces to receive aggregate subbase are lower than specified , the low areas
may be filled with aggregate subbase. The volume
of
aggregate subbase so placed
shall not be measured for payment under any item listed
in
the Bill
of
Quantities.
3.02.5.3
Placing
and
Spreading
Aggregate for subbase, immediately prior to
spreading, shall be uniform mixtures free from pockets and streaks of coarse or fine
material and shall be deposited on the subgrade in uniform layers or windrows using
approved equipment.
The layers or windrows
of
aggregate subbase shall be shaped to such thickness
that, after watering and compacting, the completed subbase layer shall conform to the
required width, grade and thickness within the tolerances specified
in
Paragraph
3.02.4.5, Finishing in these General Specifications.
The material shall be handled so as to avoid segregation . Segregated materials
shall be remixed until uniform. The water can either be added
in
the borrow pit or on
a mixing platform or
on
the grade.
Where the subbase thickness is twenty (20) centimeters or less, the aggregate
subbase may be spread and compacted
in
one (1) layer. Where the required thickness
is more than twenty (20) cm, the aggregate subbase shall be spread
in
two (2) or more
layers of approximately equal thickness.
3.02.5.4 Compacting Each layer of subbase material, after being shaped to the
required lines and cross section, shall be compacted to a uniform density with no
individual test being less than ninety-five percent (95%)
of
the maximum dry unit weight
determined from MRDTM 212. Each
of
lot
of
subbase material as described
in
1
-
8/15/2019 Ksa Concrete Earth
15/48
oeGeneral Specifications November 1998
Table of ontents
Subsection 3.02.6 Quality Assurance Procedures
n
these General Specifications shall
have a percent relative compaction
o
no less than ninety-nine percent (99%)
o
the
maximum dry unit weight determined from MRDTM 212. The subbase shall be watered
or
dried as may be necessary to obtain a moisture content suitable for compaction.
Material which has dried prior to final compaction or which has dried and decompacted
subsequent to final compaction shall be watered and recompacted using equipment
and procedures approved by the Engineer. Should the Contractor be unable to return
the material to its original or specified condition with respect to compaction, thickness,
and surface tolerances , the Contractor shall remove the material and reconstruct the
course on a reapproved subgrade.
When there are delays n constructing the remaining pavement structure over a
granular course, the compaction
o
the granular course shall be reverified and deficient
areas corrected or replaced to the satisfaction
o
the Engineer. Such corrections or
replacement shall be at the Contractor's expense.
The Contractor shall plan the work and handle the various operations so that the
least amount
o
water will be lost by evaporation from uncompleted surfaces. If the
Contractor delays placing
or
succeeding layers o material to the extent that additional
water must be applied to prevent raveling or excessive drying , the application
o
such
water shall be at the Contractor's expense and will not be considered as the basis for
a claim for additional compensation.
The material shall be compacted by means
o
approved compaction equipment,
progressing gradually from the outside towards the center, with each succeeding pass
uniformly overlapping the previous pass. Rolling shall continue until the entire thickness
o
each layer is thoroughly and uniformly compacted to the specified density. The final
rolling o the completed course shall be done with a self-propelled roller as approved
by the Engineer. Rolling shall be accompanied by sufficient blading, n a manner
approved by the Engineer, to insure a smooth surface, free from ruts
or
ridges and
having the proper section and crown. When additional water is required, it shall be
added
n
the amount and manner approved by the Engineer. Initial layers
o
material
must be constructed to a uniform grade and cross section and compacted by the
Contractor and approved by the Engineer prior to the delivery
o
materials for a
succeeding layer.
Prior to placing a succeeding layer
o
granular material, the surface
o
the
underlayer shall be made sufficiently moist , to insure bond between the layers. The
edges and edge slopes
o
the base course shall be bladed or otherwise dressed to
conform to the lines and dimensions shown on the plans, and present straight, neat and
workmanlike lines and slopes as free
o
loose material as practicable.
Any areas inaccessible to normal compaction equipment shall be compacted by
means of portable mechanical tampers until satisfactory compaction s obtained. When
the final layer is to be trimmed to final grade by an automatic grading machine , this
layer shall be constructed approximately one (1) to three (3) centimeters above grade ,
so that the grading machine cuts continually. After the final pass
o
the grading
machine , the subbase shall be wetted and rolled.
-
8/15/2019 Ksa Concrete Earth
16/48
oeGeneral Specifications November 1998
Table of ontents
3.02.5.5 Finishing All subbase material shall be placed, trimmed and finished
n
a neat and workmanlike manner
n
compliance with the lines, grades and typical cross
sections shown
on
the plans
or
staked by the Engineer within the tolerances listed n
Paragraph 3.02.6.5, Surface Tolerances n these General Specifications.
3.02.5.6
Maintenance
and
Protection
Following construction
of
the subbase
course, the compacted course shall be maintained by the Contractor at his expense.
The Contractor shall blade, broom, and otherwise maintain the course, keeping it free
from raveling and other defects that result
n
lost density until such time as the next
element
of
the pavement structure
s
placed. Water shall be applied at such times and
n
such quantities as directed by the Engineer, and the Engineer shall have full authority
to require the suspension of all other work on the project to insure the proper
maintenance of previously compacted material.
The Engineer shall determine when the surface
of
the subbase is
n
the proper
condition to permit the placement of aggregate subbase course or the bituminous prime
and/or surfacing to be applied. The Contractor must continue to maintain the surface
of
the base course, including the application
of
necessary water, at his expense until
such time as the bituminous prime or the subsequent layer is applied. Any additional
expense incurred by the Contractor because of delay n placing subsequent layers or
applying the bituminous prime when so permitted by the Engineer will not be considered
as the basis for a claim for additional compensation.
3.02.5.7
Compaction
Test Trials If directed by the Engineer, or requested by the
Contractor, prior to the commencement
of
his subbase compaction operations, the
Contractor shall construct compaction trial lengths, not to exceed one (1) kilometer.
The materials used
n
the trials shall be that approved for use as aggregate subbase
and the equipment used shall be that according to the Contractor's approved detailed
Program of Work.
The object
of
these trials is to determine the adequacy
of
the Contractor's
equipment, the loose depth measurements necessary to result
n
the specified
compacted layer depths, the field moisture content, and the relationship between the
number
of
compaction passes and the resulting density
of
the material.
The Contractor may proceed with aggregate subbase work only after the methods
and procedures established n the compaction trial has been approved by the Engineer.
3.02.6 QUALITY ASSURANCE PROCEDURES. Aggregate subbase shall be
accepted by lot. Unless otherwise stated
n
the Special Specifications, the lot size shall
be ten thousand (10,000) square meters for each layer constructed. The aggregate
subbase shall be sampled, tested and evaluated
n
accordance with Section 1.08
Acceptance
of
Work
n
these General Specifications. The Engineer may, during the
beginning of placement of subbase, at times when test results indicate erratic
characteristics and at any other time, reduce the lot size to sections of subbase with
similar quality characteristics. This should facilitate the isolation and modification or
replacement of low-quality materials with materials of acceptable quality to maintain the
overall strength
of
the pavement structure.
2
-
8/15/2019 Ksa Concrete Earth
17/48
oeGeneral Specifications November 1998
Table of ontents
The Engineer shall perform or supervise the performance
of
all quality assurance
sampling and testing. The location
of
all samples and tests shall be recorded by
roadway, lane and centerline station (kilometer). Quality assurance sampling and
testing for each lot shall include:
1
Compaction
2
Thickness
3
Aggregate Gradation, Sand Equivalent and Plastic Limit
4 California Beating Ratio and Abrasion
5 Surface Tolerances
3.02.6.1
Compaction
The compacted density for each layer
of
aggregate subbase
shall be determined by the sand cone method, MRDTM 215, or by nuclear method,
MRDTM 218 using full depth penetration, at the option
of
the Engineer.
When the sand cone method is used, unless otherwise stated in the Special
Specifications , the tests shall be made at a minimum of five (5) randomly selected
locations
in
each lot.
When the nuclear method is used, unless otherwise stated
in
the Special
Specifications , the tests shall be made at a minimum
of
eight (8) randomly selected
locations
in
each lot. Three nuclear gauge readings shall
be
made at each test location
within a radius
of
two (2) meters. The three (3) readings shall be averaged and the
average considered to be the density for that test location.
Percent relative compaction shall be computed by comparing the average actual in-
place compacted density from the nuclear gauge or sand cone test results with the
maximum density determined by MRDTM 212. MRDTM 212 maximum density shall be
determined from samples
of
aggregate subbase obtained from the roadbed at a
sampling frequency
of
one (1) test per three (3) lots. The maximum density used for
determining percent relative compaction shall be the running average for three (3)
consecutive tests.
Any lot
of
aggregate subbase that has a percent relative compaction below the
minimum percent compaction specified in Paragraph 3.02.5.4, Compacting, in these
General Specifications resulting
in
a reduced pay factor
of
0.75 or higher determined
in
accordance with Subsection 1.08.5, Statistical Evaluation
of
Work for Acceptance
and Determination
of
Pay Factor (Value
of
Work)
in
these General Specifications may
be accepted on the basis
of
a reduced payment
if
requested
in
writing by the
Contractor. Otherwise the lot shall be removed and replaced by the Contractor at his
expense. Lots that have percent relative compaction resulting in a reduced pay factor
less than 0.75 shall be removed and replaced by the contractor at his expense.
3
-
8/15/2019 Ksa Concrete Earth
18/48
oeGeneral Specifications November 1998
Table of ontents
3.02.6.2
Thickness
The thickness
of
each course
of
aggregate subbase complete
as placed and compacted, shall be measured from test holes obtained at a minimum
of five (5) random locations within the lot. The thickness of each hole shall be
determined after determination that the compacted density is acceptable. The average
of the test hole thicknesses shall be reported as the thickness of the lot.
A lot shall be accepted when the average total thickness is not less than the planned
thickness.
Any lot
of
aggregate subbase course with an average thickness less than shown
in
the plans but resulting
in
a reduced pay factor
of
0.75 or higher determined
in
accordance with Subsection 1.08.5, Statistical Evaluation of Work for Acceptance and
Determination of Pay Factor (Value of Work), in these General Specifications may be
accepted
on
the basis of reduced payment if requested in writing by the Contractor,
otherwise additional material shall be provided as specified
in
the preceding paragraph.
When the average thickness
of
a lot
of
aggregate subbase course is less than the
planned thickness by an amount resulting
in
a reduced pay factor below 0.75 the
Contractor, at his own expense, shall place and remix additional aggregate subbase
material with the original aggregate subbase material and recompact before new test
holes are dug.
3.02.6.3 Aggregate Gradation , Sand
Equivalent
and Plasticity Index.
Aggregate subbase gradation , sand equivalent and plasticity index will be sampled ,
tested and evaluated based
on
the average
of
a minimum
of
five (5) test results per lot
in
accordance with the Job Mix Formula Tolerances listed
in
Paragraph 3.02.3.1 Job
Mix Design Proposal , and Subsection 1.08.5, Statistical Evaluation
of
Work for
Acceptance and Determination of Pay Factor (Value of Work) , in these General
Specifications.
Every sample of aggregate subbase shall be taken on a random time basis from
each uncompacted lot during each one-half ( ) day
of
work, or portion thereof. The
initial sample shall be randomly selected from within one and one-half 1 ) meters
either side
of
the centerline
of
and weigh at least twenty-five (25) kilograms. The initial
sample shall be thoroughly mixed and quartered to obtain a test sample weighing at
least six (6) kilograms. The test sample shall be forwarded to the project laboratory and
the aggregate gradation, and sand equivalent and plastic light determined.
When the aggregate gradation, sand equivalent or plasticity index test results for any
lot produce a reduced pay factor of 0.75 or higher determined
in
accordance with above
referenced Subsection 1.08.5, Statistical Evaluation
of
Work for Acceptance and
Determination
of
Pay Factor (Value or Work) in these General Specifications , the lot
may be accepted on the basis
of
a reduced pay factor if requested
in
writing by the
Contractor. Otherwise said lot shall be removed and replaced by Contractor at his
expense.
When the gradation , sand equivalent or plasticity index pay factor determined
in
accordance with above referenced Subsection 1.08.5, Statistical Evaluation
of
Work
for Acceptance and Determination
of
Pay Factor (Value or Work)
in
these General
4
-
8/15/2019 Ksa Concrete Earth
19/48
oeGeneral Specifications November 1998
Table of ontents
Specifications , for any lot whose pay factor is less than 0.75 the aggregate subbase
shall be removed and replaced by the Contractor at his expense.
3.02.6.4 California Bearing Ratio and
Abrasion
Random samples shall be taken
and tested for California Bearing Ratio and Abrasion from the first three (3) lots and
every fifth lot thereafter unless test results indicate failure to conform to the values
specified
in
Subsection 3.02.2, Materials
in
these General Specifications.
n
such a
case, increased sampling and testing shall be performed .
3.02.6.5
Surface Tolerances
The surface layer
of
the aggregate subbase shall
be evaluated for compliance with the following surface tolerances:
The cross section of the finished subbase surface shall be checked by the
Contractor in the presence of the Engineer at maximum intervals of twenty-five (25)
meters and at intermediate points as directed by the Engineer. The deviation
of
the
elevation
of
the surface above the design elevation shall be not more than twenty (20)
millimeters. Deviations above the design elevation shall not result
in
the diminished
thickness
of
any subsequent pavement course. The deviation
of
the elevation below
the design elevation shall not be more than twenty (20) millimeters. Isolated deviations
below the design elevation shall be compensated by additional thickness of the
subsequent pavement layer. Additional cost and materials resulting from deviations
from the design elevation shall be borne by the Contractor. Contractor shall furnish all
devices necessary to check the surface, such as stringlines , straightedges, etc., and
the labor necessary to handle the task.
3.02.6.6 Acceptance. Aggregate subbase construction including Califomia Bearing
Ratio, abrasion and surface tolerances shall be accepted under Subsection 1.08.4,
Measured
or
Tested Conformance in these General Specifications.
Compaction, thickness, aggregate gradation, sand equivalent and plasticity index
will be accepted under Subsection 1.08.5, Statistical Evaluation
of
Work for
Acceptance and Determination
of
Pay Factor (Value
or
Work) in these General
Specifications
in
two (2) stages as follows: The first stage shall be the selection
of
the
lowest
of
the four
of
pay factors for the quality
of
the aggregate subbase relating to
aggregate gradation, compaction, sand equivalent and plasticity index. The second
stage involves the selection and application of a quantity pay factor based on the
thickness of the aggregate subbase. The reduced thickness pay factor for the lower
course lots
of
multiple layer courses will be applied provisionally based on the results
of the depths of the holes dug in the lower layers. Additional holes will be dug in the
total depth
of
all aggregate subbase layers within the lot represented by lower layer
reduced thickness pay factors. If the total thickness depths show that the increased
upper level layer thickness has resulted
in
total thickness acceptability, the lower level
layer reduced thickness pay factor will be adjusted accordingly. The second stage
thickness quantity pay factor will be applied to all the individual course lots in addition
to the first stage lowest quality pay factor as determined in accordance with Subsection
1.08.5, Statistical Evaluation of Work for Acceptance and Determination of Pay Factor
(Value or Work)
in
these General Specifications.
5
-
8/15/2019 Ksa Concrete Earth
20/48
oeGeneral Specifications November 1998
able of Contents
3.02.7 METHOD OF MEASUREMENT. Aggregate subbase shall be measured by the
cubic meter after placement and compaction to the required density, using horizontal
dimensions shown on the plans or as directed by the Engineer and thickness
measurements determined as specified in this specification. No allowance for
overdepth shall be permitted except as approved in writing by the Engineer prior to
spreading the aggregate subbase.
3.02.8 PAYMENT. Aggregate subbase shall be paid for at the contract unit price or
adjusted contract unit price per cubic meter for the aggregate subbase item(s) shown
on the plans and listed
in
the Bill
of
Quantities. Such price and payment shall be full
compensation for furnishing all rnaterials, equiprnent, labor, tools and incidentals and
all other items necessary to complete the work as specified in Subsection 1.07.2,
Scope
of
Payment in these General Specifications.
When a lot
of
aggregate subbase course is accepted with a deficiency, the adjusted
contract unit price for said lot shall be the product
of
the contract unit price
of
aggregate
subbase, and the lowest quality and quantity pay factors specified
in
Subsection 3.02.6,
Quality Assurance Procedures,
in
these General Specifications.
PAYMENT WILL BE MADE UNDER ONE OR MORE OF THE FOLLOWING:
ITEM NO.
P Y
ITEM
P Y
UNIT
30201 Aggregate Subbase Cubic Meter
Course
3020101 Aggregate Subbase Cubic Meter
Course, Grading I
3020102 Aggregate Subbase Cubic Meter
Course, Grading
3020103 Aggregate Subbase Cubic Meter
Course, Grading
6
-
8/15/2019 Ksa Concrete Earth
21/48
oeGeneral Specifications November 1998
able of Contents
SECTION 3.03 -
GGREG TEB SES
3.03.1 DESCRIPTION. This work shall consist of furnishing, spreading and
compacting aggregate bases to the lines, elevations and thicknesses shown on the
plans and as specified
in
these General Specifications and the Special Specifications.
Aggregate bases will be designated as Aggregate Base Course
or
Aggregate Base
Course, Grading
_
The grading(s)
of
aggregate base to be furnished shall be
according to the item(s) shown
in
the Plans
or
Special Specifications and listed
in
the
Bill
of
Quantities. If the aggregate base course grading is not specified aggregate base
course shall be furnished meeting one of the gradations listed in Table 3.03-1 as
designated by the Engineer. The designation of the appropriate Grading shall be such
that the maximum size of aggregate will not exceed two thirds (2/3) of the thickness of
the aggregate base course layer to be constructed.
ITEMS
N BILL
OF QUANTITIES:
Aggregate Base Course
Aggregate Base Course, rad ing_
3.03.2 MATERIALS. Aggregates used for aggregate base shall be hard durable
particles or fragments free from vegetation matter and other deleterious substances
and, when compacted under watering and rolling, form a firm , stable base. Aggregate
shall consist of crushed stone, crushed slag, or crushed gravel.
Crushed stone aggregate shall contain not more than eight (8) percent , by weight,
flat, elongated, soft, or disintegrated pieces. Aggregate retained
on
the 2.36 mm (No.
8) sieve shall consist of stone particles of which at least ninety percent (90 ), by
weight, shall have at least two (2) mechanically fractured faces.
The specified gradation shall be obtained by crushing , screening and blending
processes, as necessary. The Contractor shall furnish, produce stockpile, blend and
mix all necessary materials using such equipment and procedures as will produce the
specified aggregate base.
If additional fine material, in excess of that already present in the base course
material, is necessary for correcting the gradation properties, for satisfactory bonding
of
the base material, or for adjusting the material characteristics
of
the fraction passing
the 0.425 mm (No. 40) sieve, it shall be uniformly blended and mixed with the crushed
aggregates. Such mixing shall take place at the crusher, at an approved stationary
proportioning and mixing plant
or on
a traveling plant. Reworking
of
the base course
material
in
place to obtain the specified requirements shall not be permitted. The
additional fine material, if any, shall be obtained from crushing stones, gravel, or slag,
and shall be of a gradation as required to accomplish the specified gradation of the final
mixture.
Aggregate shall conform to one
of
the following grading and quality requirements on
the road bed after all blending and mixing and spreading and before compacting:
7
-
8/15/2019 Ksa Concrete Earth
22/48
oeGeneral Specifications November 1998
Table of Contents
TABLE 3.03-1
AGGREGATE
BASES
GRADING
REQUIREMENTS
MRDTM 204
PERCENTAGE
PASSING
SIEVE SIZES Grading I Grading II Grading III
50 mm (2 inch) 100
37.5
mm
1 inch) 100
25 mm
1
inch) 55-85 70-95 100
19 mm ( inch) 50-80 55-85 70-100
4.75
mm
No.4) 30-60 30-60 35-65
0.425
mm
(No.
40)
10-25 10-25 15-25
0.075 mm (No. 200) 3-10 3-10 3-10
The
fraction
passing the
No. 200
sieve shall not
exceed
the
fraction passing
the
0.425 mm (No. 40) sieve.
QUALITY REQUIREMENTS
Sodium Sulphate Soundness MRDTM
311)
, Loss 12 Max.
Abrasion Loss
MRDTM
309)
45
Max.
Sand Equivalent MRDTM 313)
45
Min.
Liquid Limit
MRDTM 209)
25 Max.
Plasticity Index MRDTM 208) 6 Max.
California Bearing Ratio MRDTM 213) Grading I 100 Min.
California Bearing Ratio
MRDTM 213)
Grading
II
80 Min.
California Bearing Ratio (CBR) MRDTM 213) Grading III
65 Min.
18
-
8/15/2019 Ksa Concrete Earth
23/48
oeGeneral Specifications November 1998
Table of ontents
3.03.3 PROPORTIONING
AGGREGATE BASE
MIXES.
3.03.3.1 Job Mix Design Proposal. A proposed Job Mix Formula (JMF) shall be
formulated by the Contractor and submitted to the Engineer for approval. The JMF
shall be prepared by the Contractor
in
precise compliance with procedures and
requirements set forth
in
the Materials and Research Department Manual
of
Materials
and Tests and all current letters issued by the Ministry
of
Communications.
The Contractor shall select his sources
of
aggregate and, after sufficient quantities
have been stockpiled or are available for
use,
obtain representative samples
of
the
materials and test to determine if they conform to the requirements of these
specifications. At least thirty (30) days before producing aggregate base mixtures, the
Contractor shall submit in writing to the Engineer detailed information for each mix
which he proposes to furnish. The information shall include, but not be limited to the
following:
1
The source and gradation
of
the aggregate for each mix to be furnished. If the
aggregate (coarse, fine, supplemental fine) is separated into two (2) or more sizes, the
information provided shall consist of gradations for all individual sizes, the proportions
of each individual size to be used, and the mathematically combined gradation for each
mix to be furnished. Such combined gradation shall meet the applicable grading
requirements shown
in
Subsection 3.03.2 Materials
in
these General Specifications
and show the percentage passing each of the specified sieve sizes.
2
Pertinent test data and a written certification that the aggregates to be furnished
conform to all quality requirements shown
in
Subsection 3.03.2, Materials
in
these
General Specifications.
3
The type
of
plant to be used for mixing each mix to be furnished.
4
The beginning date for producing aggregate base mixtures.
The Engineer
shall be provided access to the materials sampling and testing
operations at all times. The combined aggregate, including mineral additives, shall
conform to the approved JMF grading within the following tolerances:
9.75 mm (3/8 ) and larger sieves,
4.75 mm No.4) sieve,
2.36 mm No.8) sieve,
0.300 mm (No. 50 sieve,
0.075 mm (No. 200) sieve ,
9 percentage points
8 percentage points
7 percentage points
6 percentage points
4 percentage points
At the same time the above information is provided, the Contractor shall supply to
the Engineer fifty (50) kilogram samples of each individual aggregate size, when used,
ten (10) kilogram samples of mineral filler and chemical admixture, all representing the
materials which the Contractor proposes to furnish.
9
-
8/15/2019 Ksa Concrete Earth
24/48
oeGeneral Specifications November 1998
Table of ontents
3.03.3.2
Acceptance of Job
Mix Formula. The Engineer shall review the
JMF
to
determine that it contains all required information. If it does not contain all required
information, it shall be returned within seven (7) days to the Contractor for further action
and resubmission by the Contractor.
If the proposed
JMF
contains all required information but fails to meet all the
requirements specified, it shall not be accepted by the Engineer and will be returned to
the Contractor within fourteen (14) days. The Contractor shall prepare and submit to
the Engineer a new
JMF
conforming to the requirements specified and propose a new
date for beginning production.
When the Engineer is satisfied that the
JMF
proposed by the Contractor conforms
to all the requirements of the specifications, he shall order the Contractor to construct
a minimum two hundred (200) meter long field control strip. The Engineer shall
evaluate the control strip as to its constructability and compactability and conformance
to the laboratory tested JMF. Split samples of the aggregate base mix for and
components raw material along with the field laboratory test results are to be sent to
the Materials and Research Departments Central Laboratory for a one (1) point check
and documentation. If the Engineer is not satisfied with the results of the control strip,
he shall state his objections n writing and request a revised
JMF
and a new control
strip.
When the Engineer is satisfied that the
JMF
proposed by the Contractor conforms
to all requirements of the specifications and the control strip results are acceptable , he
will issue written acceptance to the Contractor to begin producing the mixes proposed.
Production
of
aggregate base mixes shall not begin until the Engineer has given
written acceptance of the Job Mix Formula.
Acceptance of the
JMF
by the Engineer does not relieve the Contractor of his
obligation to produce aggregate base mixes conforming to all specified requirements.
3.03.3.3 Job
Mix Formula
Revisions
The Contractor shall not alter his methods
of
crushing, screening, blending , or stockpiling from that used to produce materials for
the approved JMF. Changes to the
JMF
will not be permitted without retesting and
resubmission of a proposed (revised)
JMF
n accordance with all the steps n
Paragraph 3.03.3.1 , Job Mix Design Proposal
n
these General Specifications.
Significant changes may include, but not be limited to, changes
n
the amount or type
of materials rejected or wasted, changes
n
the amount of materials crushed, reductions
n
the amount of crushed fines, changes
n
the amount and type of mineral filler.
Should the Contractor change his source of aggregate, he shall furnish a new job
mix design proposal and samples
of
materials, as described n Paragraph 3.03.3.1 , Job
Mix Design Proposal n these General Specifications as determined by the Engineer
to be necessary, at least twenty-one (21) days before their intended use.
2
-
8/15/2019 Ksa Concrete Earth
25/48
oeGeneral Specifications November 1998
Table of ontents
At any time after the JMF is approved the Contractor may submit a new JMF for
approval by the Engineer. If the revised JMF is approved it shall become the approved
JMF.
3.03.4 EQUIPMENT. The Contractor shall furnish all necessary equipment for
producing, stockpiling, moisture conditioning, and hauling aggregate, preparing the
surface
on
which the aggregate base will be placed, and placing, spreading,
compacting, finishing and maintaining the aggregate base
in
accordance with the
minimum type and number outlined
in
the Contractor s Program
of
Work as approved
by the Engineer. Blending and mixing aggregates and adjusting the moisture content
as required for compaction shall be performed
in
a central mixing plant.
The blended and mixed aggregates shall be placed and spread to the width and
thickness specified using approved mechanical spreading equipment. Motor graders
shall not be used for spreading.
3.03.5 CONSTRUCTION.
3.03.5.1 Contractor Quality Control Procedures Testing to control the quality
of aggregate base furnished shall be the responsibility of the Contractor. Copies of all
test results shall be forwarded to the Engineer at the end of each working day. The
Engineer shall have access to the Contractor s testing laboratory at all times and
reserves the right to obtain samples of the materials at any point during construction.
When requested by the Engineer, the Contractor shall sample aggregate base
materials and prepare duplicate samples, by quartering. One (1) sample shall be
delivered to the Engineer and the duplicate sample shall be tested by the Contractor.
The Contractor shall perform the following minimum types and number of tests:
1
Gradation, sand equivalent and plasticity index - One (1) test each per one
thousand (1000) cubic meters
of
aggregates produced but not less than one (1) per
production day.
2
Abrasion Loss - One (1) test for first, second and third five hundred (500) cubic
meters of aggregate produced and one (1) test for each twenty-five hundred (2500)
cubic meters thereafter.
3
Percent Crushed Faces - One (1) test for each five hundred (500) meters
of
aggregate produced.
4
CBR Value - One (1) test for each five thousand (5000) cubic meters.
When test data indicate that the aggregate base does not conform to specified
requirements, the Contractor shall take effective action to correct his production
methods to assure that the materials produced will conform to all specified
requirements. Such action shall include halting production, changing the source of
aggregate supply, altering amount of aggregate scalped and rejected , increasing
degree
of
crushing, and revising blending and handling methods.
2
-
8/15/2019 Ksa Concrete Earth
26/48
oeGeneral Specifications November 1998
Table of ontents
3.03.5.2
Preparation
and
Maintenance
After the subgrade or subbase surface
has been prepared , the Contractor shall maintain it true to cross section , grade and
density. The surface of the subgrade or subbase, immediately prior to receiving the
aggregate base shall conform to the specified cross section , grade and density and
shall be free of any loose or extraneous material. All subgrade or subbase protection,
maintenance or repair work is considered subsidiary to items
in
the Bill
of
Quantities.
3.03.5.3
Mixing
The aggregate and the water shall be thoroughly mixed
in
a twin
shaft pugmill type mixer, unless another type of mixer is approved. The amount of
water added to the aggregate shall be an amount which will provide the mixture with a
satisfactory moisture content for compaction to the specified in-place density. The rate
of fiow of the water to the pugmill shall be controlled by valves or other devices which
can be easily reset when a change in the rate of fiow is desirable. The water supply
system shall be equipped with a positive cut-off control which will stop the fiow of water
simultaneously with any stoppage
in
the fiow of aggregate into the pugmill.
3.03.5.4 Transporting The plant-mixed material shall be transported
in
such
manner as to deliver the mix to the project without loss or segregation. Each truck load
shall be covered with a heavy canvas sheet to reduce the loss of moisture in transit
whenever the time between loading the work and spreading the moisture exceeds thirty
(30) minutes.
3.03.5.5 Placing and Spreading The mixture shall be placed on the existing
roadway, approved subgrade or approved subbase, as the case may be,
in
a uniform
layer or layers not exceeding fifteen (15) centimeters
in
compacted depth. Where the
required thickness is greater than fifteen (15) centimeters, the material shall be placed
in
layers
of
equal thickness. However, if heavy duty vibratory compaction equipment
approved by the Engineer is used, the maximum compacted layer thickness may be
increased to twenty (20) centimeters provided test trial compaction tests indicate
compliance with these General Specifications including the following:
1
Compaction samples are taken from the entire layer including the lower part
of
the increased thickness.
2 The coarse aggregates on the top of the Aggregate Base layers are not
damaged or crushed.
The increased thickness approval will be rescinded by the Engineer if more than
fifteen percent (15 ) of the subsequent field density tests taken
on
the thicker layer
initially fail, necessitating retesting after additional compaction.
The mixture course shall be placed on the roadbed to the required width and
uncompacted thickness as follows:
1
Through an approved self-propelled spreading machine.
2 In a sized windrow from which a paving machine or travel plant will pickup and
spread the aggregate base.
-
8/15/2019 Ksa Concrete Earth
27/48
oeGeneral Specifications November 1998
Table of ontents
3
To protect the underlayer and to allow proper drainage, the spreading
of
the
base course material shall begin along the centerline on stretches with a crowned
section
or
on the high side of stretches with a one-way slope.
The approved spreader shall deliver the mixture in such a condition that the material
will be ready for compaction without further shaping. Unless otherwise permitted by the
Engineer, the aggregate shall be spread not more than two thousand (.2000) square
meters ahead
of
the rollers. Any necessary sprinkling shall be kept within this limit.
The material shall be handled so as to avoid segregation. If the approved spreader
causes segregation
in
the material , or leaves ridges or other objectionable marks
on
the
surface which cannot be eliminated easily or prevented by adjustment to the spreading
operation , the use of such approved spreader shall be discontinued , and it shall be
replaced. All segregated material shall be removed and replaced with well-graded
material. No skin patching shall be permitted. Only minor surface manipulation and
watering to achieve the required surface tolerances shall be permitted during the
compaction process.
No hauling or placement of material will be permitted when, in the judgement of the
Engineer, the weather or road conditions are such that hauling operations will cause
rutting of the road surface or cause contamination of the subbase or base course
material. Before placing the mixture, the subgrade or previous layer shall be wetted to
insure bond between the layers. The mixture shall be placed and shaped by power
equipment to the lines, elevations, cross sections, depths and density specified
in
the
following subsections.
3.03.5.6 Compacting Each layer
of
aggregate base material, after being shaped
to the required lines and cross section, shall be compacted to a uniform density with no
individual test being less than ninety-five percent (95%) of the maximum dry unit weight
determined from MRDTM 212. Each lot
of
base material as described
in
Subsection
3.03.6, Quality Assurance Procedures
in
these General Specifications shall have a
percent relative compaction
of
no less than one hundred percent (100%)
of
the
maximum dry unit weight determined from MRDTM 212. The aggregate base shall be
watered or dried as may be necessary to obtain a moisture content suitable for
compaction. Material which has dried prior to final compaction or which has dried and
decompacted subsequent to final compaction shall be watered and recompacted using
equipment and procedures approved by the Engineer. Should the Contractor be
unable to return the material to its original or specified condition with respect to
compaction, thickness, and surface tolerances, the Contractor shall remove the material
and reconstruct the course
on
a reapproved subgrade.
When there are delays
in
constructing the remaining pavement structure over a
granular course, the compaction
of
the granular course shall be reverified and deficient
areas corrected
or
replaced to the satisfaction of the Engineer. Such corrections or
replacement shall be at the Contractor's expense.
The Contractor shall plan the work and handle the various operations so that the
least amount
of
water will be lost by evaporation from uncompleted surfaces. If the
Contractor delays placing or succeeding layers
of
material to the extent that additional
3
-
8/15/2019 Ksa Concrete Earth
28/48
oeGeneral Specifications November 1998
Table of ontents
water must be applied to prevent raveling or excessive drying , the application of such
water shall be at the Contractor s expense and will not be considered as the basis for
a claim for additional compensation.
The material shall be compacted by means of approved compaction equipment,
progressing gradually from the outside towards the center, with each succeeding pass
uniformly overlapping the previous pass. Rolling shall continue until the entire thickness
of each layer is thoroughly and uniformly compacted to the specified density. The base
course shall not be rolled when the underlayer is soft or yielding or when rolling causes
undulation of the base course. The final rolling of the completed course shall be done
with a self-propelled roller as approved by the Engineer. Rolling shall be accompanied
by sufficient blading , n a manner approved by the Engineer, to insure a smooth
surface, free from ruts or ridges and having the proper section and crown. When
additional water is required, it shall be added n the amount and manner approved by
the Engineer. Initial layers of material must be constructed to a uniform grade and
cross section and compacted by the Contractor and approved by the Engineer prior to
the delivery of materials for a succeeding layer.
Prior to placing a succeeding layer
of
granular material , the surface
of
the underlayer
shall be made sufficiently moist, to insure bond between the layers. The edges and
edge slopes of the base course shall be bladed or otherwise dressed to conform to the
lines and dimensions shown on the plans, and present straight, neat and workmanlike
lines and slopes as free of loose material as practicable.
Any areas inaccessible to normal compaction equipment shall be compacted by