Extreme weather is becoming more common in our region. Flood events can impact human health and safety, and result in substantial costs to property and infrastructure. Geared toward municipal decision makers and concerned citizens, this forum provides on-the-ground examples of flood resilience strategies that can help Hudson Valley communities minimize risks while conserving financial resources. Presentation by Gregg Swanzey, Director of the Office of Economic Development and Strategic Partnerships, City of Kingston and Libby Murphy, Climate Outreach Specialist, Hudson River Estuary Program, NYSDEC for a flood management forum hosted by the Cary Institute of Ecosystem Studies in Millbrook, NY on May 4, 2013.

TRANSCRIPT

Page 1: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Kingston Waterfront Flooding Task Force:

Libby Murphy Gregg Swanzey

Hudson River Estuary Program/Cornell WRI Economic Development, City of Kingston

A case study for community-driven flooding adaptation.

Page 2: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Outline• The Hudson River Estuary Program

• Case Study: Kingston Waterfront Flooding Task Force

•What can you do?

•Municipal perspective from Gregg Swanzey

•Wrap up

• Questions

Page 3: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Hudson River Estuary Program

Core Mission

• Ensure clean water

• Protect and restore fish, wildlife, and

their habitats

• Provide water recreation and river access

• Adapt to climate change

• Conserve world-famous scenery

Page 4: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Climate Change & The Hudson River Estuary Program• Climate Smart Communities• Flooding Task Forces•Watershed Resiliency• Watershed planning• Green infrastructure• Assessing culverts for correct sizing• Assessing dams for removal or repair• Trees for Tribs (stream buffer restoration)

• Biodiversity Resiliency

Page 5: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Kingston Flooding Task ForceCase Study

Page 6: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Current situation

Page 7: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Community-driven process

Page 8: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Flooding Adaptation Strategies

•Fortify

•Accommodate

•Strategically Relocate

Page 9: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Fortify

Levee, New Orleans, LA Seawall, Beacon, NY

Page 10: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Elevated structures with flood gates, Hamburg, Germany

Accommodate

Floodable park concept, NYC

Page 11: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Steelhouse restaurant, Kingston, NY

Local example of accommodation

Page 12: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Strategic Relocation

Natural shoreline with gazebo, Cold Spring

Wetland with walkway concept, Toronto, Canada

Page 13: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Simulations

Page 14: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Kingston waterfront low tide

E Strand in Kingston

Page 15: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Kingston waterfrontSimulation: elevated sea level (4’) at low tide

4’ of Sea Level Rise

Page 16: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Kingston waterfront Simulation: elevated sea level (low tide), armored protection

Example of Fortify

Page 17: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Kingston waterfront Simulation: elevated sea level (low tide), vegetated revetment, floodproofed buildings

Example of Accommodate

Page 18: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Kingston waterfront Simulation: elevated sea level (low tide), strategic retreat

Example of Strategic Relocation

Page 19: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

TF uses a variety of tools to reach consensus:•Participatory mapping• Surveys•Dot voting•Vulnerability and risk assessments•Cost Benefit Analysis•CSC planning assessment

Page 20: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Flood risk maps

Page 21: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Participatory Mapping

Page 22: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Scenario: damage from a 100-yr (1%) storm in 2013 with no sea level rise.

Cost benefit tool

Scenario: damage from a 100-yr (1%) storm in 2100 with high sea level rise.

Page 23: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Worse case scenarioYear 2100, With High Sea Level Rise and a 100-year Storm1% Probability of Occurrence in Any Given Year

Total Damage for this Event: $39.9 MillionDamage to Wastewater Treatment Plant: $27.6 Million

• Lost Value Due to Sea Level Rise• Lost Value Due to Sea Level Rise + Storm Surge

Cumulative Expected Damages by 2100With High Sea Level Rise = $126 Million

Page 24: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

What can you do?

Page 25: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation
Page 26: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

NYS 2100 Commission Report (2012)

NYS Sea Level Rise Task Force Report (2010)

Responding to Climate Change in NYS / ClimAID (2011)

Page 27: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation
Page 28: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

What else can you do?

• Stay in touch with the Hudson River Estuary Program

• CanVIS free visualization tool by NOAA

• Sea level rise webviewer, Hudson River, by Scenic Hudson (coming soon)

• Check out the new Climate Adaptation page on the DEC website (coming soon)

Page 29: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Sandy and Irene: two different storms

• Irene: extreme rain event

• Sandy: extreme storm surge at height of spring tide

• The Perfect Storm? Irene plus Sandy

Page 30: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Flooding Impacts on the Kingston Waterfront

• Sewage Treatment Plant

• Marinas and other water dependent uses

• Adjacent Businesses

• Residential Areas

• Parks and other amenities

• Structures in the Waterways

Page 31: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation
Page 32: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

What can municipalities do?

•Assess and manage stormwater

•Build community awareness and consensus

•Plan for the future

• Evaluate Zoning and Code

•Work closely with developers and residents

Page 33: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Planning for the future in Kingston

• Kingston Comprehensive Master Plan• Local Waterfront Revitalization Program• Waterfront Development Implementation Plan• Stormwater Management Plan• Tidal Rondout Watershed Management Plan• Brownfield Opportunity Area and 70 acre GEIS• Kingston Waterfront Flooding Task Force• Hazard Mitigation strategies

Page 34: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Funding Mechanisms• Consolidated Funding Application Process• Department of Environmental Conservation• Department of State• Office of Parks Recreation & Historic Preservation• US DOC Economic Development Administration• US DHS FEMA & Hazard Mitigation Funding• USDA• HUD Community Development Block Grants & Low interest loans• Greenway Conservancy• Local Development Corporations & Private Financing

Page 35: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Other important activities

• Kingston Conservation Advisory Council• Climate Smart Community• Climate Action Plan• Natural Resources Inventory• Open Space Plan• Work with Planning Board

Page 36: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Wrap Up

• Hudson River Estuary Program

• Kingston Waterfront Flooding

Task Force

• Municipal perspective

• What you can do

Page 37: Kingston Waterfront Flooding Task Force: A Case Study for Community-driven Flooding Adaptation

Questions?

Thank you.

Libby Murphy Gregg SwanzeyHudson River Estuary Program Kingston Economic Development(845) 256-3016 (845)[email protected] [email protected]