john mcleod - sydney trains - the benefits of correct installation
TRANSCRIPT
1
The Benefits of Correct Turnout
Installation
2
The benefits of Correct Installation
• Reduced Maintenance Costs
– Component life and maintenance
• Improved Reliability
– Reduction in failures
• Reduced Operational delays
– Speed restrictions and switch failures
3
The Inputs into Correct Installation
• Design Issues
• Component Issues
• Construction Issues
4
Design Issues
• Surveying
– Control survey for correct alignments
– Ensure that design alignments for approaches are
used
• Design Considerations
– Size of turnouts and operational speeds
• Clearances
– Review clearances against standards to ensure
operational and safe working is maintained
– Waivers and concessions may be sought to vary
standards and design requirements
5
Standard designs in use on Sydney Trains Network
6
6
Pros and Cons for Tangential geometry
7
7
Typical Upgrading Plans of Cross Over
8
8
Design Issues
9
Component Issues
• Switches
– Undercut conventional switches
– Undercut tangential switches
• Bearers
– Concrete
– Timber
– Fibre reinforced foamed Urethane (FFU)
– In bearer switch bearers
Component Issues
10
Conventional Switch Tip
11
Undercut tangential Assymetric switch
12
Rollers for switch Blade
13
FFU Bearers
14
In Bearer Rodding ready to be installed
15
In Bearer Rodding in track
16
16
Traditional Rodding
17
Construction Issues
• Earthworks and compaction
– Compaction and capping layers
– Geotextile between layers
– 250-350mm of ballast below bearers
• Placing of turnout units
– Crane
– Drag
– Desec
– Rollers
Construction Issues
18
• Welding
– Alumino thermic
– Mobile flashbutt
• CWR adjustments
– Neutral temperature for surrounding rail
– Anti Creep Devices
Construction Issues Cont
19
19
Excavation and Capping Layer
20
20
Pre Assembly of switch
21
21
Pre assembly of switch
22
22
Delivery of preassembled switch
23
23
Desec Installation system
24
24
Placing Turnout panel with Desec
25
25
Rolling preassembled switch
26
26
Rolling Continued
27
27
Rolled into Position
28
28
Alumino Thermic Weld
29
29
Alumnothermic Weld
30
30
Creep Brackets
31
31
Creeping Switch
32
Construction Issues Cont.
• Tamping
– Correct alignment
– Design Crossfall on bearers
– Ensure lifting points can support full bearers
– Tamp around vee and switch blades to ensure
compaction
• Rail Brace Bolts
– Correct tension
33
33
Tamping Issues on Concrete Bearers
34
Construction Issues Cont.
• Adjustment of switching systems
– Ensuring rodding is parallel
– Ballast is clear of switches and rodding
– Motors are secure
– Wiring systems correctly located
– Lubrication
– Rollers
– Facing Points locks
35
Construction Issues Cont.
• Grinding of components
– Establish profile on machined parts
– Remove flow of soft metal as parts harden under load
– Regular grinding of all areas
– Establish rail profiles on plain rail
– Use modified tangent profiles and high leg profiles
– Remove the decarbonised zone to stop flow
– Grind at the tangent tonnages
36
36
Running on Gauge Corner uncantedd rail
37
37
Unground rail and running band
38
38
Turnout Grinder
39
39
Continued
40
40
Spark Gards up!!
41
Reduced Operational Delays
• Speed Restrictions
• Book out of turnouts
• Switches failing to shut properly
42
42
Tangential Switch well fitted
43
43
Tangential Switch
44
Speed Restrictions
• Component damage
– Worn switch blades
– Worn vees
– Averaging 15 crossings per annum requring major
repairs
– Averaging 15 Rail Brace Bolts causing major
incidents on the network
• Geometry Issues
– Rough ride
– Misalignments
45
45
Geometry Issues
46
46
Ballast fouling from Load Out
47
47
Poor Geometry during set up
48
48
Transfer of wheel load across crossing
49
49
Grinding of components
50
50
Rail not on plates
51
51
Overdriven Clips
52
52
Damage to plates
53
53
Insulated Joints separating
54