john mcleod - sydney trains - the benefits of correct installation

54
1 The Benefits of Correct Turnout Installation

Upload: informa-australia

Post on 25-Jul-2015

204 views

Category:

Engineering


5 download

TRANSCRIPT

Page 1: John McLeod - Sydney Trains - The benefits of correct installation

1

The Benefits of Correct Turnout

Installation

Page 2: John McLeod - Sydney Trains - The benefits of correct installation

2

The benefits of Correct Installation

• Reduced Maintenance Costs

– Component life and maintenance

• Improved Reliability

– Reduction in failures

• Reduced Operational delays

– Speed restrictions and switch failures

Page 3: John McLeod - Sydney Trains - The benefits of correct installation

3

The Inputs into Correct Installation

• Design Issues

• Component Issues

• Construction Issues

Page 4: John McLeod - Sydney Trains - The benefits of correct installation

4

Design Issues

• Surveying

– Control survey for correct alignments

– Ensure that design alignments for approaches are

used

• Design Considerations

– Size of turnouts and operational speeds

• Clearances

– Review clearances against standards to ensure

operational and safe working is maintained

– Waivers and concessions may be sought to vary

standards and design requirements

Page 5: John McLeod - Sydney Trains - The benefits of correct installation

5

Standard designs in use on Sydney Trains Network

Page 6: John McLeod - Sydney Trains - The benefits of correct installation

6

6

Pros and Cons for Tangential geometry

Page 7: John McLeod - Sydney Trains - The benefits of correct installation

7

7

Typical Upgrading Plans of Cross Over

Page 8: John McLeod - Sydney Trains - The benefits of correct installation

8

8

Design Issues

Page 9: John McLeod - Sydney Trains - The benefits of correct installation

9

Component Issues

• Switches

– Undercut conventional switches

– Undercut tangential switches

• Bearers

– Concrete

– Timber

– Fibre reinforced foamed Urethane (FFU)

– In bearer switch bearers

Component Issues

Page 10: John McLeod - Sydney Trains - The benefits of correct installation

10

Conventional Switch Tip

Page 11: John McLeod - Sydney Trains - The benefits of correct installation

11

Undercut tangential Assymetric switch

Page 12: John McLeod - Sydney Trains - The benefits of correct installation

12

Rollers for switch Blade

Page 13: John McLeod - Sydney Trains - The benefits of correct installation

13

FFU Bearers

Page 14: John McLeod - Sydney Trains - The benefits of correct installation

14

In Bearer Rodding ready to be installed

Page 15: John McLeod - Sydney Trains - The benefits of correct installation

15

In Bearer Rodding in track

Page 16: John McLeod - Sydney Trains - The benefits of correct installation

16

16

Traditional Rodding

Page 17: John McLeod - Sydney Trains - The benefits of correct installation

17

Construction Issues

• Earthworks and compaction

– Compaction and capping layers

– Geotextile between layers

– 250-350mm of ballast below bearers

• Placing of turnout units

– Crane

– Drag

– Desec

– Rollers

Construction Issues

Page 18: John McLeod - Sydney Trains - The benefits of correct installation

18

• Welding

– Alumino thermic

– Mobile flashbutt

• CWR adjustments

– Neutral temperature for surrounding rail

– Anti Creep Devices

Construction Issues Cont

Page 19: John McLeod - Sydney Trains - The benefits of correct installation

19

19

Excavation and Capping Layer

Page 20: John McLeod - Sydney Trains - The benefits of correct installation

20

20

Pre Assembly of switch

Page 21: John McLeod - Sydney Trains - The benefits of correct installation

21

21

Pre assembly of switch

Page 22: John McLeod - Sydney Trains - The benefits of correct installation

22

22

Delivery of preassembled switch

Page 23: John McLeod - Sydney Trains - The benefits of correct installation

23

23

Desec Installation system

Page 24: John McLeod - Sydney Trains - The benefits of correct installation

24

24

Placing Turnout panel with Desec

Page 25: John McLeod - Sydney Trains - The benefits of correct installation

25

25

Rolling preassembled switch

Page 26: John McLeod - Sydney Trains - The benefits of correct installation

26

26

Rolling Continued

Page 27: John McLeod - Sydney Trains - The benefits of correct installation

27

27

Rolled into Position

Page 28: John McLeod - Sydney Trains - The benefits of correct installation

28

28

Alumino Thermic Weld

Page 29: John McLeod - Sydney Trains - The benefits of correct installation

29

29

Alumnothermic Weld

Page 30: John McLeod - Sydney Trains - The benefits of correct installation

30

30

Creep Brackets

Page 31: John McLeod - Sydney Trains - The benefits of correct installation

31

31

Creeping Switch

Page 32: John McLeod - Sydney Trains - The benefits of correct installation

32

Construction Issues Cont.

• Tamping

– Correct alignment

– Design Crossfall on bearers

– Ensure lifting points can support full bearers

– Tamp around vee and switch blades to ensure

compaction

• Rail Brace Bolts

– Correct tension

Page 33: John McLeod - Sydney Trains - The benefits of correct installation

33

33

Tamping Issues on Concrete Bearers

Page 34: John McLeod - Sydney Trains - The benefits of correct installation

34

Construction Issues Cont.

• Adjustment of switching systems

– Ensuring rodding is parallel

– Ballast is clear of switches and rodding

– Motors are secure

– Wiring systems correctly located

– Lubrication

– Rollers

– Facing Points locks

Page 35: John McLeod - Sydney Trains - The benefits of correct installation

35

Construction Issues Cont.

• Grinding of components

– Establish profile on machined parts

– Remove flow of soft metal as parts harden under load

– Regular grinding of all areas

– Establish rail profiles on plain rail

– Use modified tangent profiles and high leg profiles

– Remove the decarbonised zone to stop flow

– Grind at the tangent tonnages

Page 36: John McLeod - Sydney Trains - The benefits of correct installation

36

36

Running on Gauge Corner uncantedd rail

Page 37: John McLeod - Sydney Trains - The benefits of correct installation

37

37

Unground rail and running band

Page 38: John McLeod - Sydney Trains - The benefits of correct installation

38

38

Turnout Grinder

Page 39: John McLeod - Sydney Trains - The benefits of correct installation

39

39

Continued

Page 40: John McLeod - Sydney Trains - The benefits of correct installation

40

40

Spark Gards up!!

Page 41: John McLeod - Sydney Trains - The benefits of correct installation

41

Reduced Operational Delays

• Speed Restrictions

• Book out of turnouts

• Switches failing to shut properly

Page 42: John McLeod - Sydney Trains - The benefits of correct installation

42

42

Tangential Switch well fitted

Page 43: John McLeod - Sydney Trains - The benefits of correct installation

43

43

Tangential Switch

Page 44: John McLeod - Sydney Trains - The benefits of correct installation

44

Speed Restrictions

• Component damage

– Worn switch blades

– Worn vees

– Averaging 15 crossings per annum requring major

repairs

– Averaging 15 Rail Brace Bolts causing major

incidents on the network

• Geometry Issues

– Rough ride

– Misalignments

Page 45: John McLeod - Sydney Trains - The benefits of correct installation

45

45

Geometry Issues

Page 46: John McLeod - Sydney Trains - The benefits of correct installation

46

46

Ballast fouling from Load Out

Page 47: John McLeod - Sydney Trains - The benefits of correct installation

47

47

Poor Geometry during set up

Page 48: John McLeod - Sydney Trains - The benefits of correct installation

48

48

Transfer of wheel load across crossing

Page 49: John McLeod - Sydney Trains - The benefits of correct installation

49

49

Grinding of components

Page 50: John McLeod - Sydney Trains - The benefits of correct installation

50

50

Rail not on plates

Page 51: John McLeod - Sydney Trains - The benefits of correct installation

51

51

Overdriven Clips

Page 52: John McLeod - Sydney Trains - The benefits of correct installation

52

52

Damage to plates

Page 53: John McLeod - Sydney Trains - The benefits of correct installation

53

53

Insulated Joints separating

Page 54: John McLeod - Sydney Trains - The benefits of correct installation

54