John James Village Project Presentation
Woden Valley Community Council Meeting 3 December 2014Presenter: Mark Blake - Point Project Management
![Page 2: John james village wvcc presentation 3 december 2014](https://reader030.vdocuments.mx/reader030/viewer/2022032618/55b52651bb61eb44188b474e/html5/thumbnails/2.jpg)
Background
• Leukaemia Foundation in ACT/SNSW – current arrangements
• March 2012 - official Lifecycle opening
• June 2012 – MOU between John James Foundation and Leukaemia Foundation
• 2012 – 2014 site identification
• Land allocated April 2014
![Page 3: John james village wvcc presentation 3 december 2014](https://reader030.vdocuments.mx/reader030/viewer/2022032618/55b52651bb61eb44188b474e/html5/thumbnails/3.jpg)
Garran Site Investigation
• Contamination Assessment: Likelihood, if any, low• Flood Control Study: TAMS Requirements of sale of the land• Traffic and Parking: Development to have insignificant impact on road
network• Vegetation: Tree assessment found best opportunity for development in
centre of the block. (current site). Large area of site infested by weeds.• Acoustic Study: Protection against Hindmarsh Dr.• Services: New site services for development• Civil: New footpath on Rusden St.• Walking Trail: Existing trail to remain• Fauna: No Endangered Species found on site.
![Page 5: John james village wvcc presentation 3 december 2014](https://reader030.vdocuments.mx/reader030/viewer/2022032618/55b52651bb61eb44188b474e/html5/thumbnails/5.jpg)
Village Characteristics
• Low scale development intended to be sympathetic to surroundings
• Single level development
• Off-street car parking
• Emphasis on landscaping
![Page 6: John james village wvcc presentation 3 december 2014](https://reader030.vdocuments.mx/reader030/viewer/2022032618/55b52651bb61eb44188b474e/html5/thumbnails/6.jpg)
Project Timeline
• Development Application lodged – December 2014
• Building Approval – April 2015
• Construction Commence – May 2015
• Construction Complete – July 2016