iter codac co ntrol, d ata a ccess and c ommunication system for iter anders wallander

28
EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010 Page 1 ITER CODAC ITER CODAC CO CO ntrol, ntrol, D D ata ata A A ccess and ccess and C C ommunication System for ITER ommunication System for ITER Anders Wallander ITER Organization (IO) 13067 St. Paul lez Durance, France

Upload: badru

Post on 01-Feb-2016

61 views

Category:

Documents


0 download

DESCRIPTION

ITER CODAC CO ntrol, D ata A ccess and C ommunication System for ITER Anders Wallander ITER Organization (IO) 13067 St. Paul lez Durance, France. Plasma is an ionized hot gas The fourth state of matter Lawson criterion (“triple product”) Temperature * Density * Time > Big Number. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 1

ITER CODACITER CODAC

COCOntrol, ntrol, DData ata AAccess and ccess and CCommunication System for ITERommunication System for ITER

Anders Wallander

ITER Organization (IO) 13067 St. Paul lez Durance, France

Page 2: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 2

Basics

Plasma is an ionized hot gasThe fourth state of matter

Lawson criterion (“triple product”)Temperature * Density * Time > Big Number

Page 3: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 3

ITER

Goal: Demonstrate feasibility of fusion as an energy sourceMetric: Q=10 sustained for 300-500 seconds(Q=10 means output power equal 10 times input power)

Schedule: 10 years construction phase just startedFirst plasma 2019, first D-T plasma 2027

Collaboration: CN, EU, IN, JA, KO, RF, US

Method: Magnetic confinement (Tokamak)

Page 4: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 4

This is ITER

Page 5: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 5

This is the ITER Agreement

140 slices

Page 6: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 6

A bit of interface problems

Page 7: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 7

Island mentality

Page 8: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 8

Missing Items

Page 9: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 9

The control system can help to fix this

Page 10: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 10

The control system is horizontal

Page 11: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 11

it connects to everything

Page 12: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 12

it identifies and may eliminate missing items

Page 13: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 13

it integrates

Page 14: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 14

and is the primary tool for operation

Page 15: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 15

But this will only work if…

…all these links work

StandardsArchitecture

Page 16: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 16

EPICS

In February 2009 ITER Organization decided to use EPICS for the control system

This decision was based on three independent studies

In February 2010 ITER Organization released the first version of CODAC Core System, which basically is a package of selected EPICS products

Page 17: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 17

Finite set of “Lego blocks”, which can be selected and connected as required

Page 18: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 18

Plant System I&C

Is a deliverable by ITER member state.Set of standard components selected from catalogue.One and only one plant system host.

Page 19: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 19

ITER Subsystem

is a set of related plant system I&C

Page 20: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 20

CODAC Servers and Terminals

are servers running Red Hat Enterprise Linux (RHEL) and EPICS/CSS/???. These servers implements supervision, monitoring, coordination, configuration, automation, data handling, archiving, visualization, HMI…

Page 21: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 21

Plant Operation Network

is the work horse general purpose flat network utilizing industrial managed switches and mainstream IT technology

Page 22: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 22

Plant System Host

is an IO furnished hardware and software component installed in a Plant System I&C cubicle. There is one and only one PSH in a Plant System I&C. PSH runs RHEL (Red Hat Enterprise Linux) and EPICS (Experimental Physics and Industrial Control System) soft IOC (Input Output Controller). It provides standard functions like maintaining (monitoring and controlling) the Common Operation State (COS) of the Plant System. PSH is fully data driven, i.e. it is customized for a particular Plant System I&C by configuration. There is no plant specific code in a PSH. PSH has no I/O.

Page 23: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 23

Slow Controller

is a Siemens Simatic S7 industrial automation Programmable Logic Controller (PLC). There may be zero, one or many Slow Controllers in a Plant System I&C. A Slow Controller runs software and plant specific logic programmed on STEP 7 and interfaces to either PSH or a Fast Controller using IO furnished interface (EPICS driver and self description). A Slow Controller has normally I/O and IO supports a set of standard I/O modules. A Slow Controller has no interface to HPN. A Slow Controller synchronizes its time using NTP over PON. A Slow Controller can act as supervisor for other Slow Controllers.

Page 24: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 24

Fast Controller

is a dedicated industrial controller implemented in PCI family form factor and PCIe and Ethernet communication fabric. There may be zero, one or many Fast Controllers in a Plant System I&C. A Fast Controller runs RHEL and EPICS IOC. It acts as a channel access server and exposes process variables (PV) to PON. A Fast Controller has normally I/O and IO supports a set of standard I/O modules with associated EPICS drivers. A Fast Controller may have interface to High Performance Networks (HPN), i.e. SDN for plasma control and TCN for absolute time and programmed triggers and clocks. Fast Controllers involved in critical real-time runs a RT enabled (TBD) version of Linux on a separate core or CPU. A Fast Controller can have plant specific logic. A Fast Controller can act as supervisor for other Fast Controllers and/or Slow Controllers. The supervisor maintains Plant System Operating State.

Page 25: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 25

High Performance Computer

are dedicated computers (multi core, GPU) running plasma control algorithms.

Page 26: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 26

High Performance Networks

are physically dedicated networks to implement functions not achievable by the conventional Plant Operation Network. These functions are distributed real-time feedback control, high accuracy time synchronization and bulk video distribution.

Page 27: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 27

ITER subsystem # of PS I&C # of PSH+controllers # of servers+terminals

Tokamak 6 55 6

Cryo and cooling water 5 40 3

Magnets and coil power supply 8 30 3

Building and power 37 66 3

Fuelling and vacuum 6 45 3

Heating 8 55 4

Remote handling 2 15 2

Hot cell and environment 3 20 2

Test blanket 6 24 7

Diagnostics 89 400 20

Central 0 0 170

TOTAL 167 750 220

Estimate of system size

~1000 computers connected to PON

Page 28: ITER CODAC CO ntrol,  D ata  A ccess and  C ommunication System for ITER Anders Wallander

EPICS Collaboration Meeting Spring 2010, Aix France, Jun 2, 2010Page 28

Conclusions

• The non-technical peculiarities of the ITER project has been addressed• Components making up ITER control system have been defined and a baseline architecture outlined• Flexibility in combining these standard components have been emphasized• Having a set of standard components and a sound architecture will ease integration

We would like to thank the EPICS community allowing us to get started very quickly on the ITER control system

We promise to pay back to the community in the future with the development of ITER control system and an enlargement of the community

https://www.iter.org/org/team/chd/cid/codac/Pages/