initial environmental examination · 2014. 9. 29. · head khanki or the khanki headwork is the...
TRANSCRIPT
Initial Environmental Examination August 2011
Pakistan: MFF-Punjab Irrigated Agriculture Sector Development T2 (New Khanki Barrage Project) Prepared by Punjab Management Office (PMO) for Punjab Barrages for the Asian Development Bank
GOVERNMENT OF THE PUNJAB IRRIGATION DEPARTMENT
PUNJAB MANAGEMENT OFFICE(PMO) FOR PUNJAB BARRAGES
New Khanki Barrage Project (NKBP)
INITIAL ENVIRONMENTAL EXAMINATION REPORT
IEE Report
August 2011
GOVERNMENT OF THE PUNJAB IRRIGATION DEPARTMENT
PUNJAB MANAGEMENT OFFICE (PMO) FOR PUNJAB BARRAGES
New Khanki Barrage Project (NKBP) IEE Report
i
TABLE OF CONTENTS
EXECUTIVE SUMMARY
Page No.
1. INTRODUCTION 1-1
1.1 GENERAL 1-1
1.2 PROJECT DETAILS 1-1
1.3 BACKGROUND 1-3
1.4 PROJECT LOCATION 1-4
1.5 PROJECT CATEGORIZATION 1-5
1.6 OBJECTIVES OF THE REPORT 1-5
1.7 STRUCTURE OF THE REPORT 1-6
1.8 METHODOLOGIES OF PERFORMING THE STUDY 1-6
1.9 ENVIRONMENTAL AND RESETTLEMENT ISSUES 1-7
2. LEGAL AND ADMINISTRATIVE FRAMEWORK POLICY 2-1
2.1 REGULATORY REQUIREMENTS IN PAKISTAN 2-1
2.2 NATIONAL CONSERVATION STRATEGY 2-1
2.3 NATIONAL ENVIRONMENT POLICY 2-1
2.4 GUIDELINES FOR ENVIRONMENTAL ASSESSMENT 2-2
2.4.1 Guidelines for the Preparation and Review of Environmental
Reports, Pakistan Environmental Protection Agency, 1997 2-2
2.4.2 Guidelines of Public Consultation, Pakistan Environmental
Protection Agency, May, 1997 2-2
2.5 ENVIRONMENTAL INSTITUTIONS AND THEIR RESPONSIBILITIES 2-3
2.5.1 Provincial EPA 2-3
2.5.2 Provincial Departments of Forestry and Wildlife 2-3
2.5.3 Local Government and Municipalities 2-3
2.5.4 Social & Environmental Management Unit (SEMU) 2-3
2.5.5 Environment-Related Statutes 2-4
2.6 ASIAN DEVELOPMENT BANK GUIDELINES 2-5
2.7 NATIONAL ENVIRONMENTAL QUALITY STANDARDS (NEQS) 2000 2-6
2.8 INTERNATIONAL CONVENTIONS 2-12
New Khanki Barrage Project (NKBP) IEE Report
ii
3. THE PROJECT 3-1
3.1 GENERAL 3-1
3.2 THE NEW KHANKI BARRAGE PROJECT 3-1
3.3 OBJECTIVES OF THE PROJECT 3-1
3.4 DESCRIPTION OF THE PROJECT 3-2
3.4.1 Environmental Assessment 3-3
3.4.2 Old Barrage (Area A) 3-3
3.4.3 New Barrage site (Area B) 3-3
3.4.4 Public Park (Area C) 3-3
3.4.5 Consultants Residence and New Staff Colony (Area D) 3-6
3.4.6 Offices (Area E) 3-6
3.4.7 Old Workers Colony (Area F) 3-6
3.4.8 New L.C.C (Area G) 3-6
3.4.9 Private Land (Area H) 3-6
3.4.10 Government land; Tree Plantation (Area I) 3-6
3.4.11 Lake (Area J) 3-6
3.4.12 Old Workshop (Area K) 3-7
3.4.13 Contractors Facilities (Area L) 3-7
3.4.14 Palku Nallah 3-7
3.4.15 Borrow Area 3-7
3.4.16 High Level Channel 3-7
3.4.17 Development and Improvement of Access Road 3-7
3.4.18 Rehabilitation of School 3-7
3.4.19 Construction of Basic Health Unit (B.H.U) 3-8
3.5 WORKS & MATERIALS 3-8
3.5.1 Estimated quantities of works 3-8
4. ENVIRONMENTAL AND SOCIAL BASELINE 4-1
4.1 GENERAL 4-1
4.2 AREA OF INFLUENCE (AOI) 4-1
4.3 PHYSICAL ENVIRONMENT 4-2
4.3.1 Alluvial Deposits 4-2
4.3.2 Physiography 4-3
4.3.3 Soil Type 4-3
4.3.4 Land Use 4-3
4.3.5 The River and Hydrologic Regime at Old Khanki Headworks 4-4
4.3.6 Effect of Dismantling of Old Khanki Barrage on Peak
Discharge of Chenab River 4-5
New Khanki Barrage Project (NKBP) IEE Report
iii
4.3.7 Water Resource for the Vicinity Area 4-5
4.3.8 Climate 4-8
4.3.9 Ambient Quality of Environment 4-9
4.4 BIOLOGICAL ENVIRONMENT 4-14
4.4.1 Flora 4-14
4.4.2 Fauna 4-16
4.4.3 Endangered Species 4-21
4.4.4 Livestock 4-21
4.4.5 Agriculture 4-22
4.4.6 Horticulture 4-22
4.4.7 Socio-Economic and Cultural Aspects 4-22
4.4.8 Population and Community Structure 4-23
4.4.9 Poverty Status 4-23
4.4.10 Land Tenure System 4-24
4.4.11 Land Value 4-24
4.4.12 Social Equity 4-25
4.4.13 Social Cohesion 4-25
4.4.14 Gender Issues and Status of Women 4-25
4.4.15 Services and Facilities in the area 4-26
4.4.16 Credit Facilities 4-30
4.4.17 Resettlement 4-31
4.4.18 Conclusions 4-31
5. ANALYSIS OF ALTERNATIVES 5-1
5.1 No Project Option/Worst Scenario Option 5-2
5.2 Option of Remodeling and Repairing the Old Headworks and Not
Building New Barrage 5-3
5.3 Option of Constructing the New Barrage on the Site of Old Barrage 5-4
5.4 Option of Constructing the New Barrage Upstream the Old Barrage 5-5
5.5 Option of New Barrage 900 Feet Downstream of the Old Headworks 5-6
5.6 Option of Dismantling the Old Khanki Barrage 5-7
5.7 Option of Not Locating Logistics and Irrigation Department Land 5-8
5.8 Option of Employing Outside Labour Instead Of Local Labour 5-9
5.9 Summary of Alternatives 5-10
6. PUBLIC CONSULTATION AND DISCLOSURE 6-1
6.1 CONSULTATION PROCESS 6-1
6.2 STAKEHOLDER IDENTIFICATION 6-2
New Khanki Barrage Project (NKBP) IEE Report
iv
6.3 CONSULTATION FINDINGS 6-3
6.4 GENDER COMPONENT 6-4
6.5 SOCIAL FRAMEWORK AGREEMENT (SFA) 6-5
6.3.1 Parties 6-5
6.3.2 Agreement Contents 6-5
7. ENVIRONMENTAL IMPACT ASSESSMENT AND MITIGATION
MEASURES 7-1
7.1 METHODOLOGY 7-1
7.2 IMPACT ASSESSMENT – OVERVIEW 7-1
7.3 EXPLANATION OF THE IMPACT ASSESSMENT 7-4
7.3.1 Construction Phase 7-4
7.3.1.1 Land Resources 7-4
7.3.1.2 Hydrology and Water Resources 7-9
7.3.1.3 Air Quality and Noise Pollution 7-11
7.3.1.4 Biological Resources 7-13
7.3.1.5 Socioeconomic, Cultural and Archaeological Issues 7-15
7.3.2 Operational and Management Phase 7-16
7.3.3 Socio-economic Impacts on the overall Project Area 7-16
8. ENVIRONMENTAL MANAGEMENT PLAN (EMP) 8-1
8.1 INTRODUCTION 8-1
8.1.1 Objective of Environmental Management Plan 8-1
8.1.2 Regulatory Requirements and Applicable Standards 8-2
8.1.2.1 National Regulatory Requirements 8-2
8.1.2.2 ADB Procedures 8-3
8.1.2.3 Status of Regulatory Clearances 8-4
8.1.3 Components of the EMP 8-4
8.2. ORGANIZATIONAL STRUCTURE AND RESPONSIBILITIES 8-5
8.2.1 Management Approach 8-5
8.2.2 Project Management Office (PMO) 8-5
8.2.3 Contractor 8-6
8.2.4 Construction Supervision Consultants 8-6
8.2.5 Organizational Structure 8-6
8.3. IMPACT ASSESSMENT AND MITIGATION PLAN 8-10
8.3.1 Corridor of Impact 8-10
8.3.2 Mitigation Plan 8-10
8.3.3 Social Development Assistance 8-11
New Khanki Barrage Project (NKBP) IEE Report
v
8.4. ENVIRONMENTAL MONITORING PLAN 8-28
8.4.1 Objectives 8-28
8.4.2 Monitoring 8-28
8.4.2.1 Effects Monitoring 8-29
8.4.2.2 Compliance Monitoring 8-29
8.4.2.3 Post-Project Monitoring 8-30
8.4.2.4 Third Party Monitoring / Environmental Audit Annually 8-31
8.4.3 Grievance Redress System 8-33
8.4.4 Reporting Structure and Outcomes 8-34
8.4.4.1 Data Recording and Maintenance 8-34
8.4.4.2 Storage of information 8-34
8.4.4.3 Meetings 8-34
8.4.4.4 Photographic record 8-35
8.4.4.5 Social complaints register 8-35
8.4.4.6 Change record register 8-35
8.4.4.7 Reporting 8-35
8.4.5 Communication Strategy 8-36
8.5. PUBLIC CONSULTATION AND DISCLOSURE 8-38
8.5.1 Meeting with local and regional officials 8-38
8.5.2 Meeting with Local Communities 8-39
8.6. ENVIRONMENTAL TECHNICAL ASSISTANCE AND
TRAINING PLAN 8-44
8.7. CHANGE MANAGEMENT 8-46
8.8. ESTIMATED COST OF ENVIRONMENTAL MANAGEMENT 8-46
9. GRIEVANCE REDRESS MECHANISM 9-1
9.1 GENERAL 9-1
9.2 INSTITUTIONAL ARRANGEMENT 9-1
9.2.1 Management Responsibilities 9-1
9.3 SOCIAL COMPLAINTS REGISTER 9-5
New Khanki Barrage Project (NKBP) IEE Report
vi
LIST OF TABLES
Page No.
Table - 2.1: Pak EPA NEQS (2000) for Effluent Discharge 2-6
Table - 2.2: Pak EPA NEQS (2000) for Gaseous Emission 2-7
Table - 2.3: Pak EPA NEQS (2009) for Vehicular emissions 2-8
Table - 2.4: Pak EPA NEQS (2010) for Noise Level 2-9
Table - 2.5: Pak EPA NEQS (2010) for Drinking Water 2-9
Table - 2.6: Pak EPA NEQS (2010) for Ambient Air Quality 2-11
Table - 3.1: Provide year-wise estimation of physical activities 3-9
Table - 3.2: Availability of Raw Materials 3-9
Table - 4.1: Taking the peak annual discharge of the river Chenab at Khanki
Headworks, as an indicator of the hydrological behavior of the river,
following is the discharge data of past 86 years. 4-4
Table - 4.2: Summary Parameters of Surface Water Quality Analysis 4-6
Table - 4.3: Summary parameters of ground water quality 4-7
Table - 4.4: Percentage Surface Salinity Statistics 4-8
Table - 4.5: Summary of Ambient Air Quality & Noise Level 4-10
Table - 4.6: Traffic Count crossing over L.C.C. Headworks, on old
Khanki headworks (passing both ways) 4-10
Table - 4.7: Some Sources and Effects of Noise 4-12
Table - 4.8: Mammals 4-17
Table - 4.9: Birds 4-17
Table - 4.10: Reptiles 4-19
Table - 4.11: (a): Turtles – Hard Shells 4-20
Table - 4.11: (b): Turtles – True Soft Shells 4-20
Table - 4.12: Amphibians 4-20
Table - 4.13: Fish reported in river Chenab upstream and downstream
Khanki Barrage. 4-21
Table - 4.14: Area, Production and Cropping Intensities of Main Agri
Crops in Rancha Doab 4-22
Table - 4.15: Land Capability Class 4-24
Table - 6.1: Summary of Consultation Meeting 6-3
Table - 6.2: Social Condition of Women in the project Area 6-4
Table - 7.1: Check list of potential impacts for Construction and
Operational Phases 7-2
Table - 8.1: Applicable Regulatory Requirements (Environmental) 8-2
Table - 8.2 Environmental Impact Mitigation Plan 8-12
New Khanki Barrage Project (NKBP) IEE Report
vii
Table - 8.3: Social Impact Mitigation Plan 8-23
Table - 8.4: Effects Monitoring Plan 8-31
Table - 8.5: Periodic Reports 8-35
Table - 8.6: List of Officials Contacted 8-38
Table - 8.7: Member of Public in Khanki Barrage Area Interviewed 8-40
Table - 8.8: Employment Opportunities in the Construction of New Khanki Barrage
Project 8-42
Table - 8.9: Training Program 8-45
Table - 8.10: Cost Estimates for Environmental Management 8-47
Table - 9.1 Grievance Resolution Process 9-5
New Khanki Barrage Project (NKBP) IEE Report
viii
LIST OF FIGURES
Page No.
Figure - 1.1: Location map of Khanki Barrage 1-5
Figure - 3.1: (a) Proposed Project Area map of the New Khanki Barrage 3-4
Figure - 3.1: (b) Proposed Project Area map of the New Khanki Barrage 3-5
Figure - 4.1: Water distribution systems to communities in Rachna Doab,
through a contemporary Project 4-2
Figure - 4.2: Land use pattern in Project Area 4-3
Figure - 4.3: Seismic Hazard Zones of Pakistan 4-13
Figure - 8.1: Organization structure of PMO 8-8
Figure - 8.2: Organization Chart for Environment Management / monitoring
implementation 8-9
New Khanki Barrage Project (NKBP) IEE Report
ix
LIST OF ABBREVIATION
ADB Asian Development Bank
AOI Area of Influence
BOD Biological Oxygen Demand
CMS Conservation of Migratory Species
COD Chemical Oxygen Demand
COSHH Control of Substances Hazardous to Health
EC Electrical Conductivity
EIA Environmental Impact Assessment
EMMP Environmental Management & Monitoring Plan
EMP Environmental Management Plan
EPA Environmental Protection Agency
EPA’s Environmental Protection Agencies
ESIA Environmental & Social Impact Assessment
FAO Food and Agriculture Organization G
CA Gross Cultivated Area
GRC Grievance Redress Committee
ID Irrigation Department
IEE Initial Environmental Examination
IWT Indus Water Treaty
LARAP Land Acquisition & Resettlement Action Plan
M&E Monitoring and Evaluation
NCS National Conservation Strategy
NEQS National Environmental Quality Standards
NOC No-Objection Certificate
O&M Operation and Maintenance
NKBP New Khanki Barrage Project
PEPA Pakistan Environmental Protection Act
PEPC Pakistan Environmental Protections Council
PHS Public Health and Safety
PID Punjab Irrigation Department
PMO Project Management Office
PMU Project Management Unit
PPE Personal Protective Equipment
RSC Residual Sodium Carbonate
RE Resident Engineer SAR Sodium Adsorption Ratio
New Khanki Barrage Project (NKBP) IEE Report
x
SCARP Salinity Control and Reclamation Project
SEMU Social & Environmental Management Unit
SFA Social Frame Work Agreement
SMO SCARPS Monitoring Organization
SOP Survey of Pakistan
SOP Soil Survey of Pakistan
TDS Total Dissolved Solids
US-EPA United States Environmental Protection Agency
WAPDA Water and Power Development Authority
WHO World Health Organization WWF Worldwide Fund for Nature
New Khanki Barrage Project (NKBP) IEE Report
i
EXECUTIVE SUMMARY
THE PROJECT
Head Khanki or the Khanki Headwork is the oldest head work of Pakistan
(32o24’09.65” N 73o58’14.30”E). It is present at river Chenab in Gujranwala District. It
is shutter type structure used to control water flow and flood flow in river Chenab.
The current operations are mainly manual in nature and are cumbersome. Khanki
Headwork provides water to Lower Chenab Canal (L.C.C). It was built in 1889-1892
and remodeled in 1935, is now too old and outdated to continue providing required
services. The Discharge Capacity of NKBP will be 1,100,000 cusecs and the flow
and capacity of L.C.C will remain same.
It is therefore proposed to build a new Barrage about 900 ft. downstream of existing
Headworks as a replacement of the old barrage due to technical, economic and
safety reasons.
The Project activity will consist of the following:
1. Construction of the new barrage at 900 ft downstream of the old head work
2. Dismantling of old Khanki Head work
3. Construction of new bridge over the new barrage
4. Construction of public park
5. Demolition of old Govt Servant colony and their relocation to the new colony
6. Rehabilitation of Boys& Girls schools
7. Construction of new Basic Health Unit (BHU)
8. Construction of the Consultant’s Residence
9. Rehabilitation of the old Workshop
10. Acquisition of Private land
11. Construction of Coffer Dams
12. Construction of LCC Head Regulator and small road bridge
13. Alteration in route of High level Channel along the new LCC
14. Tree cutting
15. Establishment and operations of Contractor’s Camp/facilities
16. Development and improvement of the access road (about 35 km)
17. Excavation from Borrow Areas and Restoration.
For the purpose of the above an Environmental Impact Assessment (EIA) Report has
been prepared to ensure the following objectives:
Apply ADB’s Environment safeguards
New Khanki Barrage Project (NKBP) IEE Report
ii
The applicable environmental administrative and legal frame work on the
project
Environmental & social base line data of the project area of influence (AOI)
Assessment of potential environmental impacts and determining mitigation
measures of expected adverse impacts
Develop a basic Environmental Management Plan (EMP) Framework (inclusive of all
major environmental aspects and risk bases assessment plan) and envisaged EMP
implementation cost.
The base line data was developed and analyzed to identify potential environmental
impacts of the project. An Environmental Assessment Checklist methodology was
adopted to identify the high risk activities and suggest their mitigation measures.
Where possible, eliminating the risk by altering the scope or method of execution of
work was preferred rather than minimizing the risk with control measures.
The “no project” option is considered inappropriate. In view of the long term and wide
spread benefits of safe and a long term New Khanki Barrage Project (NKBP).
Legal and Administration Framework Policy
Pakistan Environmental Protection Act 1997 is the primary legislation which
applies in Environmental Assessment studies in Pakistan. Under section 12 of the
Act a project falling under any category specified in Schedule II (SRO 339(1)/2000)
require the proponent to file an Environmental Impact Assessment (EIA) with the
concerned Environmental Protection Agency (EPA), which in case of New Khanki
Barrage Project (NKBP) is EPA Punjab.
The nature and scope of work and the environmental setting of the AOI (established
through REA Checklist) indicates that there will neither be any significant adverse
impact to the environment nor there would be any irreversible ecological damage due
to the project activities. All the adverse impacts either would be temporary or would
be easily mitigable. The projects benefits on the other hand would easily outweigh
any small and temporary adverse impacts. The project will have significant positive
environmental and social benefits by uplifting the aesthetics of the area (Public Park,
new colonies and better infrastructure) and also through providing better efficiency in
regulating water bodies.
Therefore, the project should be categorized as B, as per the Asian
Development Guidelines (ADB)
New Khanki Barrage Project (NKBP) IEE Report
iii
However such a project requires an EIA as per section 12 of PEPA 1997 an EIA is
prepared to obtain No Objection Certificate (N.O.C). All project activities should be
compliant with NEQS and should establish monitoring and evaluation systems.
Description of the Environment
The New Khanki Barrage (Latitude 32o24’09.11” North and Longitude 73o58’01.25”
East) will be located on Chenab River approximately 900 ft downstream of the
existing Khanki Head works in Wazirabad Tehsil of Gujranwala District in Punjab
Province. It is 72 miles from Lahore, 15 miles from Wazirabad Town, 40 miles below
Marala Barrage and 15 miles upstream of Qadirabad Barrage.
The settlements nearest to the Khanki Head work are as follows (All distances
approximate to project near vicinity):
Khanki Village (500 meters)
Kot Imam Baksh (800 meters)
Kot-Natho (800 meters)
Kacha kay quarters (800 meters)
Ranekay (1 km)
Chak Ali Sher (1.5 Km)
Goraali (2 km)
In general the area has access to electricity and communication networks. Health
facilities are scarce and inadequate. Literacy rate is low and about 80% population is
based on agriculture. The main surface water sources of the area include River
Chenab, Lower Chenab Canal (L.C.C), Palkhu Nallah.
LCC Command area is 3.0 million acres. The population in the area is nearly 5.0 million
persons. Density of population per sq. km is 570 as compared to 350 for overall Punjab.
The socio-economic structure of project area is primarily agrarian. About 74 percent of
the total population lives in rural area and depends upon agriculture. The remaining
population lives in cities and towns with ample facilities for work as the cities are
generally well industrialized especially in metal works, electrical goods, ceramics and
agro-based industries. Some of the rural population travels and even migrates to cities
for employment.
The socio-economic structure of project area is primarily agrarian. About 74 percent of
the total population lives in rural area and depends upon agriculture. The remaining
population lives in cities and towns with ample facilities for work as the cities are
generally well industrialized especially in metal works, electrical goods, ceramics and
New Khanki Barrage Project (NKBP) IEE Report
iv
agro-based industries. Some of the rural population travels and even migrates to cities
for employment.
Social consultations were carried out with officials and local communities. The aim
was to solicit views on the proposed project and incorporate their concerns, demands
and needs into Environmental Management Plan (EMP) and Social Framework
Agreement (SFA). Indirect women consultations were carried out to incorporate
gender issues in the social assessment. The idea of construction of new Khanki
barrage was hailed by almost all the interviewees.
The flora of the project area can be divided into two parts i.e. riverian Flora and inland
Flora
The immediate and surrounding area of the project has been under human inference for
a long time and, therefore no endangered species is present or spotted in the area.
Environmental Impacts and Mitigation Measures
Most of the adverse environmental and social impacts of the Project will be
associated with the construction phase. Except for resettlement issues which would
need to be addressed carefully, the remaining impacts associated with the
construction phase will be temporary, reversible, phased over a period of time,
localized and manageable.
The air quality was analysed and found reasonably clean and no any obvious source
of air pollution was located in the vicinity of the project area of influence. However
there are kacha paths and may cause dust pollution during traffic movement. Air
quality shall be controlled by regular spraying of water on kacha paths. All vehicles,
machinery, equipment and generators used during construction activities will be kept
in good working conditions to minimize the exhaust emissions. Cutting & burning
trees and shrubs as a fuel shall be prohibited and clean source of energy should be
provided at the contractor’s camp e.g. gas cylinders etc. Noise, air quality and water
sources shall be monitored periodically, as specified in EIA report. All the work
activities should be restricted within the allowed working hours.
There is not any designated environmentally protected or archaeological site falling
within the direct project area of influence. The Project will not have any significant
impacts on fish, fishermen communities, wildlife and wildlife habitat. However,
monitoring measures have been recommended to ensure that any unforeseen
impacts can be identified, compared with baseline and mitigated during the
implementation stage. All forest, wildlife and fisheries laws should be fully respected
and abided by the contractor and his work force. No fire arms should be carried out
by the contractor’s work force. Tree cutting (1000) would be required for the
construction of new L.C.C (diverted path; it would meet the existing L.C.C. at 3500
New Khanki Barrage Project (NKBP) IEE Report
v
ft.). 10000 trees will be planted as compensation of the same. Public Park will be
developed near Khanki village. This will raise the aesthetic values of the area and
provide a picnic spot to the local community and tourist.
During construction, the Contactor’s work force is expected to be largely available
from the local population, which will enhance the economic opportunities for the
locals of working age group. Socioeconomic conditions of the project area will
generally have positive impacts due to the project implementation i.e. availability of
jobs during construction phase.
The Project will also improve some of the social infrastructure as part of the repair
and rehabilitation (access road, rehabilitation of school, construction of Basic Health
Unit). The livelihoods of farming communities will also improve through increased
and equitable canal water availability and improved agricultural productivity through
improved agricultural practices and road network. The representation of women and
other vulnerable groups will be ensured in the Project benefits.
The noticeable adverse impact of the Project will be resettlement and relocation of
affected communities. Detailed resettlement action plans to mitigate these impacts
will be prepared and implemented before commencing the work on site. A
Resettlement Framework and representative Resettlement Action Plans have been
prepared as part of the feasibility study.
It is very important to protect the water sources during the construction phase from
accidental spills of diesel or any chemical, as any spill could percolate to the
groundwater through the sandy stratum at site. All the solid waste and wastewater
generated from the project activities and contractor camp shall be disposed-off
according to the waste disposal plan, which would be a component of the EMP. If the
groundwater is to be used for the water supply in the Contractor Camp then it would
be required to abstract water from sufficient depth and confirm that it meets the WHO
standards by the contractor.
The proposed project will bring about a net-positive benefit in terms of improved
water resource management and agricultural productivity in the area. Continuous
environmental monitoring will be carried out for the entire construction phase, to
ensure due diligence of environmental performance. The EMP will also ensure
reporting of all non-conformances and their rectification within a specified period of
time along with safety, health and environment (SHE) audits
New Khanki Barrage Project (NKBP) IEE Report
vi
CONCLUSION
It is anticipated that all environmental and social issues involved during the
construction and operational phase of the project are manageable, therefore it
is concluded that the project is environmentally friendly, financially viable,
economically sustainable, generally neutral and pro-poverty elevation.
New Khanki Barrage Project (NKBP) IEE Report
1-1
1. INTRODUCTION
1.1 GENERAL
The province of Punjab is only one fourth of the total area of Pakistan, yet its fertile
land yields are more than 50% of the total national agricultural produce. One of the
reasons for such high agricultural production is the efficient use of water resources
through Punjab’s irrigation network. The Punjab irrigation network comprises 24
canals fed by 14 barrages / headworks and 9 major inter-river link canals, irrigating
more than 21 million acres of land.
Khanki Headwork is the oldest head work of Pakistan (32o24’09.65”N 73o58’14.30”E).
It is present at river Chenab in Gujranwala District. It is shutter type structure used to
control water flow and flood flow in river Chenab. The current operations are mainly
manual in nature and are cumbersome. Khanki Headworks provides water to Lower
Chenab Canal (L.C.C). It was built in 1889-1892 and remodeled in 1935, is now too
old and outdated to continue providing required services. Lower Chenab Canal
(L.C.C) originates from Head Khanki. It provides water to three million acres (12,000
km²) of agricultural lands by one main distributary (Lower Chenab) and 59 minor
distributaries. In the last 118 years there were 11 occasions when water reached 730
feet higher than the sea level (at times of high floods). It is therefore proposed to
build a new Barrage about 900 ft. downstream of existing Headworks as a
replacement of the old barrage due to technical, economic and safety reasons. The
Discharge capacity of New Khanki Barrage will be 1,100,000 cusecs. The flow and
capacity of the L.C.C remains same.
Asian Development Bank (ADB) is providing assistance to improve the management
of Punjab Water Resources and increase the agricultural productivity of the province
under the Punjab Irrigation Agriculture Investment Program (PIAIP).
1.2 PROJECT DETAILS
Punjab Irrigation Department (PID) is the executing agency of the Punjab Irrigated
Agriculture Investment Program (PIAIP). New Khanki Barrage Project will be carried
out under PIAIP. The consultancy of the project including feasibility and detailed
design work was awarded to a joint venture of NDC / NESPAK / ATKINS.
This report comprises the Initial Environmental Examination (IEE) study of the NKBP
on Chenab River. The IEE study takes into account the natural environment (air,
New Khanki Barrage Project (NKBP) IEE Report
1-2
water, land, flora & fauna), human health and safety. This study evaluates the
project’s potential environmental risks and impacts in its areas of influence and
outlines planning, designing and implementation by preventing, minimizing, mitigating
or compensating for adverse environmental impacts and enhancing positive impacts
throughout project implementation.
The Social Assessment (SA) has been conducted to evaluate the project’s potential
positive and adverse effects on the affected people and to examine project
alternatives where adverse effects may be significant. The breadth, depth and type of
analysis in the social assessment are proportional to the nature of the project and
scale of its potential effects, positive or adverse, on the affected people.
The New Khanki Barrage Project (NKBP with Discharge capacity of 1,100,000
cusecs), (Latitude 32o24’09.11” North and Longitude 73o58’01.25” East) will be
located on Chenab River approximately 900 ft. downstream of the existing Khanki
Head works in Wazirabad Tehsil of Gujranwala District in Punjab Province. It is 72
miles from Lahore, 15 miles from Wazirabad Town, 40 miles below Marala Barrage
and 15 miles upstream of Qadirabad Barrage.
The Project activity will consist of the following:
1. Construction of the new barrage at 900 ft. downstream of the old head work
2. Construction of new bridge over the new barrage
3. Construction of LCC Head Regulator and small bridge
4. Dismantling of old Khanki Head work
5. Construction of public park
6. Demolition of old workers colony and their relocation to the new colony
7. Rehabilitation of school
8. Construction of new Basic Health Unit (BHU)
9. Construction of the Consultant’s Residence
10. Rehabilitation of the old Workshop
11. Acquisition of Private land
12. Construction of Coffer Dams
13. Alteration in route of High level Channel along the new LCC
14. Felling of 1000 trees (Eucalyptus)
15. Establishment and operations of Contractor’s Camp/facilities
16. Development and improvement of the access road (about 35 km)
17. Excavation from borrow areas and Restoration
New Khanki Barrage Project (NKBP) IEE Report
1-3
The base line data was developed and analyzed to identify potential environmental
impacts of the project. An Environmental Assessment Checklist methodology was
adopted to identify the high risk activities and suggest their mitigation measures.
Where possible, eliminating the risk by altering the scope or method of execution of
work was preferred rather than minimizing the risk with control measures.
The old barrage is a shutter type structure, planned to provide perennial irrigation
supplies to the Rachna Doab through L.C.C. The barrage, originally constructed in
1892, was a very flimsy structure. It comprised of a low crest block of brick masonry
with dry stone protection on upstream and downstream glacis of stone in lime mortar
and gated canal head regulator. There were repeated failures and damages while
additions and alterations continued at frequent intervals. It was extensively rehabilitated
and reconstructed in 1933-35. Presently the old headwork is an assortment of different
design principles and various construction styles like the monitoring and managing
high floods up to 1.1 million cusecs a Flood Control Centre was established at Khanki
Headworks, which now needs to be modernized.
Sub-surface flow condition uplift pressures and exit gradient at different critical points
of headworks cannot be accurately measured due to choking of 40% and
malfunctioning of many other pressure pipes.
1.3 BACKGROUND
The history of construction of L.C.C. is older than the Khanki Headworks. LCC was
initially constructed as an inundation canal in 1887 off-taking from a point 4½ miles
downstream of Khanki Headworks. It was later converted into a perennial canal off-
taking from the headworks. Presently LCC is a gigantic contiguous irrigation system
which is irrigating a vast area in Rachna Doab. Some idea of the extent and vastness of
this canal system, as it stands today, can be obtained from the following facts:
Designed discharge at head : 11538 Cusecs.
Area served : 3,647,683 Acres (Located in 6 districts of
(Central Punjab)
Area irrigated 2006-07 : 5,000,350 Acres
Designed intensity of irrigation : 75%
Actual intensity of irrigation : 165%
Length of channels : 2,925 units (4680 km)
Number of outlets : 6,954
Water Flow : perennial
New Khanki Barrage Project (NKBP) IEE Report
1-4
The headworks have a designed discharge capacity of 1,100,000 cusecs whereas
the actual flood exceeded this figure for nine (9) times, the maximum being
1,086,000 cusecs. The flow and capacity of the L.C.C. will remain same. Control on
the river flows and pond level is very loose, regulation through outdated shutters
results in heavy leakages of water during periods of acute shortage. Also, there is no
bridge or regulation platform across the river.
The structural durability of the headworks is unreliable and it may yield to any stress
beyond its present capacity. With this eventuality, irrigation will be a serious problem
in about 3 million acres of very fertile land served by Khanki headworks, which is
about 14 percent of entire canal irrigated area of the Punjab. Consequently, a
condition of famine may occur in the country. Prevention of the above mentioned loss
shall in fact be a gain in the water/agriculture, sector of the national economy.
In view of operational constraints and structural deficiencies, PID launched safety
evaluation study of Khanki headworks in 1998 under the program “Safety evaluation
of major hydraulic structure”. Study concluded that feasibility study should be
undertaken to determine whether the weir should be replaced or remodeled.
Subsequent to the recommendation of evaluation study, a feasibility study was
carried out in year 2003-2005 which recommended the replacement of existing
headworks with new barrage at a distance of 900 ft. on the downstream side.
Evaluation of existing headworks was also studied by the consultants through a desk
study in year 2007, which revealed that remodeling of existing headworks is not
feasible because of extensive dismantling and rebuilding operation and would cost
more than building a new barrage.
1.4 PROJECT LOCATION
The headworks are located across the river Chenab just below the confluence of Palkhu
Nallah with the river Chenab. It is 18 km from Wazirabad town and 16 km below the
Alexandra Railway Bridge, 56 km below Marala barrage and 32 km above Qadirabad
barrage. (See Fig 1.1 Location Map of Khanki Barrage)
It is proposed to build a new barrage about 900 ft. downstream as a replacement for the
old headworks. The new barrage will be a key element of one of the most important
irrigation systems of the province; the LCC system.
New Khanki Barrage Project (NKBP) IEE Report
1-5
Fig. 1.1: Location map of Khanki Barrage
1.5 PROJECT CATEGORIZATION
According to ADB Safeguard Policy Statement, projects are to be categorized into
three environmental categories; A, B, or C. All the anticipated adverse environmental
impacts of the project are mitigable, temporary, nature and localized. Also there is no
environmentally sensitive or archeological site falling within project area of influence;
therefore the project is classified as Category B. This report comprises the Initial
Environmental Examination (IEE) of the proposed project to fulfill the requirements
according to ADB’s guidelines.
1.6 OBJECTIVES OF THE REPORT
The main objectives of the report are as follows:
The application of environmental administrative and legal frame work on the
project
Develop Environmental Baseline Data for the project Area of Influence (AOI);
derive land use and environmental maps.
New Khanki Barrage Project (NKBP) IEE Report
1-6
Assessment of potential environmental Impacts and development of mitigation
measures to cater for adverse impacts.
Preparation of framework of Environmental Management Plan (EMP) and
envisaged EMP implementation cost for this project.
Environmental approval from government agency; Environmental Approval for
the same has already been obtained twice before (2005, 2009). However the
current approval expires in May 2012, therefore a fresh approval is required
before commencement of construction activity.
1.7 STRUCTURE OF THE REPORT
This report is divided into following chapters:
Chapter No.1: Introduction
Chapter No. 2: Policy, Law and Administrative Framework
Chapter No. 3: The Project Description
Chapter No. 4: Environmental Baseline Conditions
Chapter No. 5: Study of Alternatives
Chapter No. 6: Public Consultation
Chapter No. 7: Impact Assessment, Mitigation and Enhancement Measures
Chapter No. 8: Outline of Environmental Management Plan
Chapter No. 9: Grievance Redress Mechanism
Appendices
1.8 METHODOLOGY OF PERFORMING THE STUDY
The environmental and social data were collected and analyzed for the overall
environmental study area. Data was collected during site visits and stake holder
consultation works. The concerned departments and institutions are Wildlife, Forestry
& Fishery Department, Water Management Office, Irrigation, SMO, SEMU and Land
Revenue etc.
The base line data was developed and analyzed to identify potential environmental
impacts of the Project. A risk based methodology was adopted to identify the high
risk activities and suggest their mitigation measures. Where possible, eliminating the
risk by altering the scope or method of execution of work was preferred rather than
minimizing the risk with control measures. Public consultations were also undertaken
including a gender study to take into account the public point of view about the
project.
New Khanki Barrage Project (NKBP) IEE Report
1-7
1.9 ENVIRONMENTAL AND RESETTLEMENT ISSUES
The project activities include construction of a New Khanki Barrage about 900 ft.
downstream of the existing old headworks, a L.C.C from the new barrage and allied
mechanical and civil structure within the project area. This will cause some disturbance
due to construction activities on the main barrage site and the allied sites involving
borrow material, camping grounds, material dump, machinery yard, link road and
necessary facilities for the staff and labour to be engaged for the construction of the
project. The materials and labour shall have to be carried from the Depot/camp to the
work sites on either bank of the river. There is no such irreversible adverse
environmental impact of the project but the construction-related impacts such as air
pollution, noise and use of community resources can be well mitigated through the
proper implementation of the mitigation measures, which have been identified in this
report. During the construction phase of the L.C.C and studs, about 1054 trees
(Eucalypts) will required to be felled, for which compensatory tree plantation of the
appropriate species would be carried out by PID.
The construction of new barrage is within the river bed, so no private land or property
acquisition will be involved anywhere during construction. However construction of new
L.C.C involves acquisition of private land which will be carried out by the Land
Acquisition Act 1894 and through proper implementation of the LARAP.
New Khanki Barrage Project (NKBP) IEE Report
2‐1
2. LEGAL AND ADMINISTRATIVE FRAMEWORK POLICY
This chapter provides an overview of the policy framework and national legislation
that applies to the proposed Project. The Project is expected to comply with all
national legislations and Asian Bank Guidelines relating to environmental and social
issues, and all the required regulatory clearances will be obtained.
The environmental study includes primarily Pakistan Environmental Protection Act
1997 (PEPA 1997), Pakistan IEE and EIA review regulations (2000) and Asian
Development Bank SPS. All other laws and guidelines relevant to the project have
also been reviewed. Synopses of relevant laws and guidelines are provided in this
chapter.
2.1 REGULATORY REQUIREMENTS IN PAKISTAN
Under section 12 (with subsequent amendment) of the 1997 Act, a project falling
under any category specified in Schedule I (SRO 339(1)/2000), requires the
proponent to file an IEE with concerned federal agency (Pak-EPA). Projects falling
under any category specified in schedule II require the proponent to file an EIA with
the federal agency. Within ten working days of the lodging of IEE or EIA, the federal
agency will confirm that the document submitted is complete for the purpose of
review.
2.2 NATIONAL CONSERVATION STRATEGY
The Pakistan National Conservation Strategy (NCS) was approved by federal cabinet
in March 1992 and is the principal policy document on environmental issues in the
country. The NCS outlines the country’s primary approaches towards encouraging
sustainable development, conserving natural resources and managing resources.
The NCS has 68 specific programs in 14 core areas in which policy intervention is
considered crucial for the preservation of Pakistan’s natural and physical
environment. The core areas that are relevant in the context of the proposed Project
are pollution prevention and abatement, conserving biodiversity and preservation of
cultural heritage.
2.3 NATIONAL ENVIRONMENT POLICY
The National Environmental Policy provides an overarching framework for
addressing the environmental issues facing Pakistan, particularly pollution of fresh
New Khanki Barrage Project (NKBP) IEE Report
2‐2
water bodies and coastal waters, air pollution, lack of proper waste management,
deforestation, loss of biodiversity, desertification, natural disasters and climate
change. It also gives directions for addressing the cross sectoral issues elaborating
the underlying causes of environmental degradation and international obligations.
The policy provides broad guidelines to the Federal Government, Provincial
Government, Federally Administrated Territories and Local Government for
addressing environmental concerns and ensuring effective management of their
environmental resources.
2.4 GUIDELINES FOR ENVIRONMENTAL ASSESSMENT
The Pak-EPA has published set of environmental guideline for conducting
environmental assessment and the environmental management of different types of
development projects. The guidelines relevant to the proposed Project are listed
below.
2.4.1 Guidelines for the Preparation and Review of Environmental Reports,
Pakistan Environmental Protection Agency, 1997
The guidelines, targeted at project proponents, specify:
The nature of the information to be included in environmental reports
The minimum qualification of the EIA conductors appointed
The need to incorporate suitable mitigation measures during project
implementation
The need to specify monitoring procedures
The report must contain baseline data relating to the project area, an interpretation of
the data and mitigation measures.
2.4.2 Guidelines of Public Consultation, Pakistan Environmental
Protection Agency, May, 1997
These guidelines deal with possible approaches to public consultation and
techniques for designing an effective program of consultation that reaches out to all
major stakeholders and ensure that their concerns are incorporated in any impact
assessment study.
New Khanki Barrage Project (NKBP) IEE Report
2‐3
2.5 ENVIRONMENTAL INSTITUTIONS AND THEIR RESPONSIBILITIES
2.5.1 Provincial EPA
The Punjab Irrigation & Power Department (PIPD) will be responsible for providing
the complete environmental documentation required by the provincial EPA and
remain committed to the approved project design. No deviation is permitted during
project implementation without the prior and explicit permission of the EPA.
2.5.2 Provincial Departments of Forestry and Wildlife
The rehabilitation works are expected to involve some clearing of vegetation that
exists on government land where labour camp and batching plants are to be
installed. Widening and strengthening of the embankments may also involve some
uprooting of trees. All the trees along the canal belong to Forest department.
Plantation at the irrigation rest houses and at the barrages belongs to irrigation
department. Wildlife department nominates any sensitive wildlife area as game
reserve or highly sensitive area as wildlife sanctuary. A competent person should
manage the work activities in wildlife sensitive areas to minimize any adverse
impacts on wildlife habitat. However no environmentally sensitive area has been
identified within the direct influence of the project activities.
2.5.3 Local Government and Municipalities
The IPD and its contractors must ensure that the project meets the criteria of district
governments as related to the establishment of construction camps and plants, and
the safe disposal of wastewater, solid waste and toxic materials. The IPD will
coordinate and monitor environment-related issues.
2.5.4 Social & Environmental Management Unit (SEMU)
Punjab Irrigation Department (PID), under Punjab Irrigation and Drainage Authority
(PIDA), established the Social and Environmental Management Unit (SEMU) in
December 2006 to enable it to address the environmental and social issues in a
timely and effective manner during operation, maintenance, rehabilitation,
construction of new canals and drains etc. SEMU has developed checklists for canal
rehabilitation works covering construction or remodeling of J-Head Spur / Dike /
Flood Bund / Training Works, new canals, new distributaries, new Barrages or lining
New Khanki Barrage Project (NKBP) IEE Report
2‐4
of any channel. SEMU may also be involved as an independent environmental
monitoring organization during construction phase of this Project.
2.5.5 Environment-Related Statutes
This section outlines statutes apart from the Pakistan Environmental Protection Act,
1997, which are relevant to the project.
The Forest Act, 1927 (and Provincial Acts and Rules)
The Act, inter alia, deals with the matters related with protection and conservation of
natural vegetation/habitats. It empowers the concerned agency to declare protected
and reserved forest areas and their maintaining. In spite of the fact that it recognizes
the right of people for access to the natural resources for their household use, it
prohibits unlawful cutting of trees and other vegetation from forest reserve area. The
permission is required prior to undertake any tree cutting from the Forest Department
of Punjab province. The contractor will inform formally to the Punjab Forest
Department and PIPD at-least 1 month before cutting any tree on site.
Provincial Wildlife (Protection, Preservation, Conservation and
Management) Act, Ordinances and Rules
In addition to empowering provincial wildlife department to establish game reserves,
parks, and wildlife sanctuaries, these acts regulate the hunting and disturbance of
wildlife. This law will help in eliminating any trespassing into protected areas.
Antiquities Act, 1975
The Antiquities Act relates to the protection, preservation and conservation of
archaeological/historical sites and monuments. There are no archeological site(s) or
cultural heritage site inside or in the AOI of the project. Nevertheless if there is
chance find during the construction phase this law would provide due guidance.
Provincial Local Government Ordinances, 2001
These ordinances, issued following the devolution process, establish regulations for
land use, conservation of natural vegetation, air, water, and land pollution, the
disposal of solid waste and wastewater effluents, as well as matters related to public
health and safety. This law will help as and when participatory management of
irrigation system becomes the order of the day.
New Khanki Barrage Project (NKBP) IEE Report
2‐5
Factories Act, 1934
The clauses relevant to the project are those that are related with the health, safety
and welfare of workers, disposal of solid waste and effluent, and damage to private
and public property. The Factories Act also provides regulations for handling and
disposing of toxic and hazardous materials. There are no factories / industries inside
the project area.
Land Acquisition Act 1894
Land Acquisition Act (LAA), 1894 is the primary law governing land acquisition in
Pakistan. For the acquisition of land, the above-mentioned Act, rules and regulations
are followed whether the acquisition is for Government of Punjab or any other
agency.
2.6 ASIAN DEVELOPMENT BANK GUIDELINES
The Asian Development Bank’s Safeguard Policy Statement (SPS) 2009 and
Environmental Policy 2002 require that environmental considerations be incorporated
in to ADB’s funded project to ensure that the project will have minimal environmental
impact and be environmentally sound. Occupational health & safety of the local
population should also be addressed as well as the project workers as stated in SPS.
A Grievance Redress Mechanism to receive application and facilitate resolution of
affected peoples’ concerns, complaints, and grievances about the project’s
environmental performance is also established and provided in chapter 9.
Environment Categorization
All loans and investments are subject to categorization to determine environmental
assessment requirements. Categorization is to be undertaken using Rapid
Environmental Assessment (REA), consisting of questions relating to (i) the
sensitivity and vulnerability of environmental resources in project area, and (ii) the
potential for the project to cause significant adverse environmental impacts. Projects
are classified into one of:
Category A: Projects with potential for significant adverse environmental impacts. An
Initial Environmental Examination (IEE) is required to address significant impacts.
Category B: Projects judged to have some adverse environmental impacts, but of
lesser degree and/or significance than those for category A projects. An initial
environmental examination (IEE) is required to determine whether or not significant
New Khanki Barrage Project (NKBP) IEE Report
2‐6
environmental impacts warranting an EIA are likely. If an EIA is not needed, the IEE
is regarded as the final environmental assessment report.
Category C: Projects unlikely to have adverse environmental impacts. No EIA or IEE
is required, although environmental implications are still reviewed.
Category FI: Projects are classified as category FI if they involve a credit line
through a financial intermediary or an equity investment in a financial intermediary.
The financial intermediary must apply an environmental management system, unless
all subprojects will result in insignificant impacts.
2.7 NATIONAL ENVIRONMENTAL QUALITY STANDARDS (NEQS)
The NEQS specify the following standards:
1. Maximum allowable concentration of the Pollutants, (32 parameters) in
emission and liquid industrial effluents discharged to inland water.
2. Maximum allowable concentration of pollutants (16 parameters) in gaseous
emission.
3. Maximum allowable exhaust emissions and noise emission from vehicles.
4. Maximum allowable noise level from vehicles
5. Maximum allowable limits for Drinking Water
6. Maximum allowable limit for Ambient Air Quality
Table - 2.1: Effluent Discharge Standards (NEQS 2000) Applicable to the Works
Sr. No. Determinant NEQS1 Temperature 40 OC =≤3 deg. 2 pH 6 – 9 3 BOD5 80 mg/l 4 Chemical Oxygen Demand (COD) 150 mg/l 5 Total Suspended Solid (TSS) 200 mg/l 6 Total Dissolved Solids 3500 mg/l 7 Grease and Oil 10 mg/l 8 Phenolic compounds (as phenol) 0.1 mg/l 9 Ammonia 40 mg/l
10 Chlorine 1.0 mg/l 11 Chloride 1000.0 mg/l 12 Sulphate 600 mg/l 13 Manganese 1.5 mg/l 14 Fluoride 10 mg/l 15 Cyanide (as CN’) total 1.0 mg/l 16 An-ionic detergents (as MB As) 20 mg/l
New Khanki Barrage Project (NKBP) IEE Report
2‐7
Sr. No. Determinant NEQS17 Sulphide (S-2) 1.0 mg/l 18 Pesticides 0.15 mg/l 19 Cadmium 0.1 mg/l 20 Chromium trivalent and hexavalent 1.0 mg/l 21 Copper 1.0 mg/l 22 Lead 0.5 mg/l 23 Mercury 0.01 mg/l 24 Selenium 0.5 mg/l 25 Nickel 1.0 mg/l 26 Silver 1.0 mg/l 27 Total Toxic metals 2.0 mg/l 28 Zinc 5.0 mg/l 29 Arsenic 1.0 mg/l 30 Barium 1.5 mg/l 31 Iron 8.0 mg/l 32 Boron 6.0 mg/l
Table – 2.2: National Environmental Quality Standards for Gaseous Emission (mg/Nm3, Unless Otherwise Defined)
Sr. No.
Parameter Source of Emission Existing Standards
Revised Standards
1 2 3 4 5 1. Smoke Smoke Opacity not to exceed 40% or 2
Ringlemann Scale
40% or 2 Ringlemann Scale or equivalent smoke number
2. Particulate Matter (I)
(a) Boilers and Furnaces (i) Oil fired (ii) Coal fired (iii) Cement Kilns (b) Grinding, crushing, clinker coolers and Related processes, Metallurgical Processes, converter, blast furnaces and cupolas.
300 500 200 500
300 500 200 500
3. Hydrogen Chloride
Any 400 400
4. Chlorine Any 150 150 5. Hydrogen
Fluoride Any 150 150
6. Hydrogen Sulphide
Any 10 10
7. Sulphur Oxide (2) (3)
Sulfuric acid/ Sulphonic acid plants Other plants except power plants operating on oil and coal
400
1700
8. Carbon Monoxide
Any 800 800
9. Lead Any 50 50
New Khanki Barrage Project (NKBP) IEE Report
2‐8
10. Mercury Any 10 10 11. Cadmium Any 20 20 12. Arsenic Any 20 20 13. Copper Any 50 50 14. Antimony Any 20 20 15. Zinc Any 200 200 16. Oxides of
Nitrogen (3)
Nitric acid manufacturing unit. Other plants except power plants operating on oil or coal: Gas fired Oil fired Coal fired
400 - -
400 600 1200
Explanations:-
1. Based on the assumption that the size of the particulate is 10 micron or more.
2. Based on 1 percent sulphur content in fuel. Higher content of Sulphur will case
standards to be pro-rated.
3. In respect of emissions of sulphur dioxide Nitrogen oxides, the power plants operating
on oil and coal as fuel shall in addition to National Environmental Quality Standards
(NEQS) specified above, comply with the following standards.
Table - 2.3: NEQS, 2009 for Vehicular Emission
Sr. No.
Parameter Standard (Maximum permissible Limit)
Measuring Method
Applicability
1 Smoke 40% or 2 on the Ringlemann Scale during engine acceleration mode.
To be compared with Ringlemann Chart at a distance of 6 meters or more
Immediate effect
2 Carbon Monoxide (CO) 6% Under idling condition: Non-dispersive infrared detection through gas analyzer.
3 Noise 85 dB(A) Sound Meter at 7.5 meters from the source
New Khanki Barrage Project (NKBP) IEE Report
2‐9
Table - 2.4: National Environmental Quality Standards (NEQS, 2010) for Noise
Sr. No.
Category of Area / Zone
Effective from 1st July, 2010
Effective from 1st July, 2013
Limit in dB (A) Leq*
Daytime Night-time Daytime Night-time
1 Residential Area (A) 65 50 55 45
2 Commercial Area (B) 70 60 65 55
3 Industrial Area (C) 80 75 75 65
4 Silence Zone (D) 55 45 50 45
Note:
1. Daytime hours: 6:00 a.m. to 10:00 p.m.
2. Night-time hours: 10:00 p.m. to 6:00 a.m.
3. Silence Zone: Zones which are declared as such by the competent authority.
An area comprising not less than 100 meters round hospitals, educational
institutions and courts.
4. Mixed categories of areas may be decided as one of the four above
mentioned categories by the competent authority.
*dB (A) Leq: Time weighted average of the level of sound in scale “A” which is
relatable to human hearing.
Table – 2.5: National Environmental Quality Standards (NEQS, 2010) for
Drinking Water
Sr. No.
Properties/Parameters Standard Values for Pakistan
WHO Standards Remarks
BACTERIAL
1 All water is intended for drinking (E.Coli or Thermotolerant Coliform bacteria)
Must not be detectable in any 100ml sample
Must not be detectable in any 100ml sample
Most Asian Countries also follow WHO Standards
2 Treated water entering the distribution system (E.Coli or Thermotolerant Coliform and total Coliform bacteria)
Must not be detectable in any 100ml sample
Must not be detectable in any 100ml sample
Most Asian Countries also follow WHO Standards
New Khanki Barrage Project (NKBP) IEE Report
2‐10
Sr. No.
Properties/Parameters Standard Values for Pakistan
WHO Standards Remarks
3 Treated water entering the distribution system (E.Coli or Thermotolerant Coliform and total Coliform bacteria)
Must not be detectable in any 100ml sample. In case of large supplies, where sufficient samples are examined, must not be present in 95% of the samples taken throughout any 12-month period.
Must not be detectable in any 100ml sample. In case of large supplies, where sufficient samples are examined, must not be present in 95% of the samples taken throughout any 12-month period.
Most Asian Countries also follow WHO Standards
PHYSICAL
4 Colour ≤15 TCU ≤15 TCU
5 Taste Non Objectionable/ Acceptable
Non Objectionable/ Acceptable
6 Odour Non Objectionable/ Acceptable
Non Objectionable/ Acceptable
7 Turbidity <5 NTU <5 NTU
8 Total hardness as CaCO3 <500mg/l ---
9 TDS <1000 <1000
10 pH 6.5-8.5 6.5-8.5
RADIOACTIVE
11 Alpha Emitters bq/L or pCi 0.1 0.1
12 Beta Emitters 01 01
CHEMICAL
Essential Inorganics mg/litre mg/litre
13 Aluminum (Al) mg/l ≤0.2 0.02
14 Antimony (Sb) ≤0.005 0.02
15 Arsenic (As) ≤0.05 0.01 Standard for Pakistan similar to most Asian developing Countries
16 Barium (Ba) 0.7 0.7
17 Boron (B) 0.3 0.3
18 Cadmium (Cd) 0.01 0.003 Standard for Pakistan similar to most Asian developing Countries
19 Chloride (Cl) <250 250
20 Chromium (Cr) ≤0.05 0.05
21 Copper (Cu) 2 2
Toxic Inorganics mg/litre mg/litre
22 Cyanide (CN) ≤0.05 0.07 Standard for Pakistan similar to most Asian developing Countries
23 Fluoride (F) ≤1.5 1.5
New Khanki Barrage Project (NKBP) IEE Report
2‐11
Sr. No.
Properties/Parameters Standard Values for Pakistan
WHO Standards Remarks
24 Lead (Pb) ≤0.05 0.01 Standard for Pakistan similar to most Asian developing Countries
25 Manganese (Mn) ≤0.5 0.5
26 Mercury (Hg) ≤0.001 0.001
27 Nickel (Ni) ≤0.02 0.02
28 Nitrate (NO3) ≤50 50
29 Nitrite (NO2) ≤3 3
30 Selenium (Se) 0.01 0.01
31 Residual Chlorine 0.2-0.5 at consumer end 0.5-1.5 at source
---
32 Zinc (Zn) 5.0 3 Standard for Pakistan similar to most Asian developing Countries
Organics
33 Pesticides mg/L
--- PSQCA No. 4629-2004, Page No.4, Table No. 3, Serial No. 20-58 may be consulted
Annex-II
34 Phenolic Compounds (as Phenols) mg/L
--- ≤0.002
35 Poly nuclear aromatic hydrocarbons (as PAH) g/L
0.01 (By GC/MS method)
***PSQCA: Pakistan Standards Quality Control Authority
Table – 2.6: National Environmental Quality Standards (NEQS, 2010) for Ambient Air
Pollutants Time-weighted average
Concentration in Ambient Air Method of Measurement
Effective from 1st July 2010
Effective from 1st January 2013
Sulphur Dioxide (SO2)
Annual Average*
80µg/m3 80µg/m3 Ultraviolet Fluorescence Method
24 hours** 120µg/m3 120µg/m3
Oxides of Nitrogen as
(NO)
Annual Average*
40µg/m3 40µg/m3 Gas Phase Chemiluminescence
24 hours** 40µg/m3 40µg/m3
Oxides of Nitrogen as
(NO2)
Annual Average*
40µg/m3 40µg/m3 Gas Phase Chemiluminescence
24 hours** 80µg/m3 80µg/m3
Ozone (O3) 1 hour 180µg/m3 130µg/m3 Non disperse UV absorption method
Suspended Particulate
Annual Average*
400µg/m3 360µg/m3 High Volume Sampling, (Average
New Khanki Barrage Project (NKBP) IEE Report
2‐12
Matter (SPM) 24 hours** 550µg/m3 500µg/m3 flow rate not less than 1.1m3/minute)
Respire able Particulate
Matter (PM10)
Annual Average*
200µg/m3 120µg/m3 ß-Ray Absorption Method
24 hours** 250µg/m3 150µg/m3
Respire able Particulate
Matter (PM25)
Annual Average*
25µg/m3 15µg/m3 ß-Ray Absorption Method
24 hours** 40µg/m3 35µg/m3 1 hour 25µg/m3 15µg/m3
Lead (Pb) Annual Average*
1.5µg/m3 1µg/m3 AAS Method after sampling using EPM 2000 or equivalent Filter paper
24 hours** 2µg/m3 1.5µg/m3
Carbon Monoxide
(CO)
8 hours** 5µg/m3 5µg/m3 Non Dispersive Infrared (NDIR) method 1 hour 10µg/m3 10µg/m3
*Annual arithmetic mean of minimum 104 measurements in a year taken twice a week 24 hourly at uniform intervals.
**24 hourly/8 hourly values should be met 98% in a year. 2% of the time, it may exceed but not on two consecutive days.
2.8 INTERNATIONAL CONVENTIONS
Pakistan is signatory to a number of International Conventions, Protocols and
Understandings relating to the environment. Those relevant to the project are
described in the following paragraphs.
Convention on Biological Diversity
The Convention of Biological Diversity was the outcome of the “Earth Summit” held in
Riode-Janeiro in 1992. The Convention binds the signatories to respect, protect and
conserve the earth environment and bio-diversity through sustainable use of natural
resources. In all development projects in Pakistan the protocols of this convention
are respected in letter and spirit.
Ramsar Convention
The Convention on Wetland of International Importance, especially on Waterfowl
Habitats held in Iran in 1972 at village Ramsar in Iran, places an obligation on the
signatories to protect habitats of migratory waterfowl. There is no notified Ramsar
site within the canal command area and AOI of the project.
Bonn Convention
The Convention on the conservation of migratory species of wild animals was held in
Bonn in 1979. The Convention broadens the scope of Ramsar to include migratory
New Khanki Barrage Project (NKBP) IEE Report
2‐13
species other than water fowl. Not being a Ramsar site, this protocol is not obligatory
for new Khanki Barrage. But it will be respected during construction phase to the
extent that no damage is caused to habitat of any species.
New Khanki Barrage Project (NKBP) IEE Report
3‐1
3. THE PROJECT
3.1 GENERAL
Head Khanki or the Khanki Headwork is the oldest head work of Pakistan
(32o24’09.65”N, 73o58’14.30”E). It is present at river Chenab in Gujranwala District. It
is shutter type structure used to control water flow and flood flow in river Chenab.
Another use is to provide water to Lower Chenab Canal. It was built in 1889-1892.
Lower Chenab Canal (L.C.C) originates from Head Khanki. It provides water to three
million acres (12,000 km²) of agricultural lands by one main distributary (Lower
Chenab) and 59 minor distributaries. The existing Khanki Barrage is an inappropriate
structure, which requires major rehabilitation or re-construction. The operations are
mainly manual in nature and are cumbersome.
In general the area has access to electricity and communication networks. Health
facilities are scarce and inadequate. Literacy rate is low and about 80% population is
based on agriculture.
3.2 THE NEW KHANKI BARRAGE PROJECT (NKBP)
The New Khanki Barrage (Latitude 32o24’09.11” North and Longitude 73o58’01.25”
East) will be located on Chenab River approximately 900 ft. downstream of the
existing Khanki Head works in Wazirabad Tehsil of Gujranwala District in Punjab
Province. It is 72 miles from Lahore, 15 miles from Wazirabad Town, 40 miles below
Marala Barrage and 15 miles upstream of Qadirabad Barrage. NKBP discharge
capacity will be 1,100,000 cusecs, the flow and capacity of the L.C.C will remain
same.
The project area of influence (AOI) is the area likely to be effected by the project,
including all its ancillary aspects such as power transmission corridors, pipelines,
canals and access roads, borrow & waste disposal sites, batching plant and labor
camp as well as unplanned development induced by the project.
3.3 OBJECTIVES OF THE PROJECT
Main objectives of the New Khanki Barrage Project are as follows:
To replace the old barrage with a new structure about 900 ft. downstream of the old
barrage and to avoid possible catastrophe, should the old barrage collapse or get
washed away due to old age.
New Khanki Barrage Project (NKBP) IEE Report
3‐2
By replacing the barrage, save the canal network of 2925 channels (4680 kms)
irrigating above 3 million acres in 6 districts of central Punjab.
By saving agriculture and Fisheries in Central Punjab, save the socio-economic
structure of agricultural communities consisting of above 5 million people.
Mitigate any adverse impacts (physical, biological or social).
3.4 DESCRIPTION OF THE PROJECT
The New Khanki Barrage (Latitude 32o24’09.11” North and Longitude 73o58’01.25”
East) will be located on Chenab River approximately 900 ft. downstream of the
existing Khanki Head works in Wazirabad Tehsil of Gujranwala District in Punjab
Province. It is 72 miles from Lahore, 15 miles from Wazirabad Town, 40 miles below
Marala Barrage and15 miles upstream of Qadirabad Barrage.
The Project activity will consist of the following:
1. Construction of the new barrage at 900 ft. downstream of the old head work
2. Dismantling of old Khanki Head work
3. Construction of new bridge over the new barrage
4. Construction of public park
5. Demolition of old workers colony/ Govt. Servants and their relocation to the
new Irrigation colony
6. Rehabilitation of schools (Boys & Girls)
7. Construction of new Basic Health Unit (BHU)
8. Construction of the Consultant’s Residence
9. Rehabilitation of the old Workshop
10. Acquisition of Private land
11. Construction of Coffer Dams
12. Construction of LCC Head Regulator and small road bridge
13. Alteration in route of High level Channel along the new LCC
14. Felling of 1054 trees
15. Establishment and operations of Contractor’s Camp/facilities
16. Development and improvement of the access road (about 35 km)
17. Borrow Area
18. Construction of studs.
New Khanki Barrage Project (NKBP) IEE Report
3‐3
3.4.1 Environmental Assessment
The project area of influence (AOI) is the area likely to be effected by the project,
including all its ancillary aspects such as power transmission corridors, pipelines,
canals and access roads, borrow & waste disposal sites, batching plant and labor
camp as well as unplanned development induced by the project.
There are no forest, sanctuary, and wildlife reserve in the close vicinity of the project
which would likely to be affected. The project area map has been marked into
different areas (A-J). (See figure - 3.1).
3.4.2 Old Barrage (Area A)
Area A comprises of the old barrage which would be subsequently dismantled after
the completion of new barrage. There may be some disturbance due to dismantling
activity, which can be mitigated
3.4.3 New Barrage site (Area B)
New barrage will be constructed 900 ft. downstream of the old head work. The new
barrage will provide improved mechanisms of operations and also would have cross
over bridge allowing traffic to commute conveniently to the left bank of the barrage.
Currently there is no way traffic can go to the right bank other than going through a
very long way (from near G.T Road)
3.4.4 Public Park (Area C)
13 acres of government land would be converted into Public Park. Currently, it is
uncultivated land having few shrubs and trees on it. This would improve the
aesthetics of the project area and also would provide a recreational place to the
visitors and local people
New Khanki Barrage Project (NKBP) IEE Report
3‐4
Fig.3.1- (a): Proposed Project Area Map of the New Khanki Barrage
New Khanki Barrage Project (NKBP) IEE Report
3‐5
Fig.3.1 - (b): Proposed Project Area Map of the New Khanki Barrage
New Khanki Barrage Project (NKBP) IEE Report
3‐6
3.4.5 Consultants Residence and New Staff Colony (Area D)
Consultant’s residence and new staff colony will be constructed on the government
land. This is nearer to the Khanki village and therefore would require serious
mitigations and monitoring while construction phase. The area currently consists of
old building structures (government owned) and opens land.
3.4.6 Offices (Area E)
Currently there are old offices, which will be rehabilitated. It is government owned
land
3.4.7 Old Workers/Govt. Servants Colony (Area F)
Old workers colony will be demolished once workers are shifted into the new colony
being constructed in Area D (above). The current colony is old and have dilapidated
structure.
3.4.8 New L.C.C (Area G)
The new L.C.C will be constructed at 900 ft. downstream of the old head work. It will
mainly pass through government land (except some portion through private land) and
would meet the old L.C.C (existing) at 3500 ft. A small road bridge will also be
constructed at the point where L.C.C passes through the road
3.4.9 Private Land (Area H)
6 Acres private land would be acquired for the new L.C.C. It includes household,
house and cultivated land. The compensation is included in the resettlement
framework. The owner has willingly consented for the same.
3.4.10 Government land; Tree Plantation (Area I)
Eucalyptus trees are planted on the government land. The proposed L.C.C will pass
through this area and felling of approximately 1054 trees is envisaged. The felling of
trees would be duly compensated through plantation of 10000 trees along LCC,
Public Park and at barrage.
3.4.11 Lake (Area J)
Due to breach at the right bank, a lake was formed. The lake has become permanent
feature of the area. There is going to be no significant project activity near the lake on
the right bank therefore no adverse impact is envisaged to the lake.
New Khanki Barrage Project (NKBP) IEE Report
3‐7
3.4.12 Old Workshop (Area K)
An old workshop on the government land would be rehabilitated
3.4.13 Contractors Facilities (Area L)
Around 12 acres of government land would be used for the establishment of
contractor’s facilities. The contractor facilities would include batching plant, messing,
material storage area and labor camp. This area is nearer to the new small
settlements; Kot Imam Baksh and Kot Nathu. The batching plant would be located on
the farthest possible distance to these settlements. Contractor’s camp would be
walled and fenced (where adjacent to these settlements). Social Framework
Agreement should address this issue
3.4.14 Palkhu Nallah
Besides river Chenab and L.C.C, Palkhu Nallah is the only source of surface water.
This source contains waste water from different sources and should be monitored
3.4.15 Borrow Area
The selected borrow site is old LCC spoil banks 4-5 miles from headworks. There is
sufficient quantity available.
3.4.16 High Level Channel
High Level Channel will be constructed alongside the new L.C.C. This channel runs
for only 3 months’ time. The construction of the same will take place during its
closure time; 9 months’ time is ample for the construction of the same.
3.4.17 Development and Improvement of Access Road
The access road to Khanki Head Works will be developed and rehabilitated. This
would benefit the nearby communities and would also improve accessibility to head
work. Mitigation measures would be taken to keep the adverse impacts of
construction insignificant.
3.4.18 Rehabilitation of Schools
Schools at Khanki village would be rehabilitated. Improved schooling facilities would
enhance educational opportunities.
New Khanki Barrage Project (NKBP) IEE Report
3‐8
3.4.19 Construction of Basic Health Unit (B.H.U)
A BHU will be constructed on the government land either on Area D or Area E. This
would provide convenient access to health facilities to the locals. There are few and
distant health facilities available in the area.
3.5 WORKS AND MATERIALS
3.5.1 Estimated Quantities of Works
Basis of determining the capital cost be provided. It includes market survey,
schedule rates, estimation on the basis of previous work done etc.
Cost estimate for civil, electrical & mechanical works are prepared separately. In civil
works, unit rates for main items of work on barrage are derived through analyses
using input rates for materials, labour, equipment as notified by Punjab Finance
Department for 2nd quarter, 2011 and other parameters taking same as observed on
similar mega projects in the Punjab. While preparing analyses of rates, 15%
overhead charges are incorporated as already adopted by Punjab Communication
and Works (C&W) department in case of Lahore ring road project. Provisional sums
for certain items have been provided in the cost estimates in view of the provisions
made on similar other mega projects. For ordinary works, MRS rates notified by the
Finance department for the 2nd quarter, 2011 are used in estimation. For mechanical
and electrical works prevailing market rates have been used in preparation of the
estimate.
Estimated base cost inclusive of project management support cost is segregated into
foreign and local costs year wise in consideration of nature of material and items of
works. Escalation is worked out using price escalation rates (6.5%for local
component and 3 % on foreign component) over segregated costs. Physical
contingencies are worked out as 5% of base cost of works and project management
support cost inclusive of escalation. Prescribed factors of taxes and duties
(12.5%over foreign cost) and interest during construction (9.23 % on local and 2.5%
on foreign) are applied over respective costs to arrive at total project cost. The
estimated quantities of work and availability of raw materials are discussed as follows
in Table - 3.1 and 3.2 respectively.
New Khanki Barrage Project (NKBP) IEE Report
3‐9
Table - 3.1: Provide year-wise estimation of physical activities
Items Unit Year -I Year-II Year- III Year- IV Description Quantity
1. Earth work 133958 1000 Cft 47000 47000 39958
2. Concrete 191343 100 Cft 83781 90000 17562
3. Fabrication of Steel 225696 100 Kg 98025 105300 22371
4. Stone work 97095 100 Cft 32365 37000 27730
5. Roads 35 Km 33 2
6. Sheet Pilling 6294461 Kg 3147230.5 3147230.5
7. Gates & hoists 73 No. 40 33
8. Dismantling of existing head works
i)- Concrete 11379 100 Cft 11379
ii)-Stone masonry 14923 100 Cft 14923
iii)-Mechanical parts. 13245 100 Kg 13245
Table - 3.2: Availability of Raw Materials
Sr. No.
Raw Material Availability Source
1 Borrow Material/Earth Available locally within 5 miles radius
2 General and stone/shingle Available at Taraki at 100’ Km
3 Sand Available locally
4 Clean water for specific uses Available locally
5 Other water for compaction etc. Available locally
6 Rip rap and other purpose stone Available 100 Km away in Sargodha District
7 Reinforcement Bars Available in Regional Market
8 G.I. Pipes Available in Regional Market
9 Cement Available in Regional Market
10 Steel Beam Available in Regional Market
11 Steel sheet Piles Available in Regional Market
12 Jute Bags Available in Regional Market
Borrow material is amply available from nearly areas of the project. (Spoil banks of the
old L.C.C Left side PID land upstream of the barrage right side). The stones shall be
brought from the stone quarries in Districts Sargodha and the quarries there shall be
shaped and rehabilitated by the owners. Cost of stone shall be included in the BOQ.
New Khanki Barrage Project (NKBP) IEE Report
4‐1
4. ENVIRONMENTAL AND SOCIAL BASELINE
4.1 GENERAL
The Purpose of this chapter is to establish the baseline conditions for the physical,
biological and the social aspects of environment of the project area. The data were
collected regarding the physical environment, biological environment and social
aspects of the study area during stake holder consultation and technical visits
conducted by the environment team.
4.2 AREA OF INFLUENCE
This Chapter describes the environmental, social and biological baseline conditions of
the project area. The baseline conditions have been established on the basis of the
data collected from the field, and through unstructured interaction with the local
communities as well as the officials from various departments. In addition, the published
data (secondary data) was also used to provide background information about the
project area.
The extended area of influence of the project is part of Rachna Doab 3 million Acres of
best agricultural land located in six districts of central Punjab with a population of above
five million people. The new barrage located 900 ft. downstream below the old
headworks, will replace the old one and a new Khanki Head Regulator will feed the
L.C.C through a new link. Marala Barrage is 63 km above and Qadirabad Barrage is 24
km below to New Khanki Barrage. The extended area of influence of the barrage may in
fact not experience any marked difference except that stoppage of leakages which will
help the L.C.C. system to give a better water supply at the tails, and the crop production
there will increase. (See the Rachna system as shown by a contemporary project PIDA
on Fig. 4.1).
New Khanki Barrage Project (NKBP) IEE Report
4‐2
Fig 4.1: Water distribution systems to communities in Rachna Doab, through a
contemporary Project.
The project’ area of influence (AoI) is referred to all those areas which may be affected
directly or indirectly by the project activities. This includes the following:-
The Barrage and its surroundings, including the river corridor where the
construction of new Khanki Barrage will be carried out;
The labor and construction camps, site offices, equipment and vehicle yards
and additional depots;
Haul tracks to transport construction material;
Batching plants;
Borrow areas, from where the fill material will be obtained;
Waste disposal sites; and
Uunplanned development induced by the project
4.3 PHYSICAL ENVIRONMENT
4.3.1 Alluvial Deposits
Khanki new barrage site is located in District Gujranwala, which is entirely situated on
the alluvium, Kanker is found all over the district. Sediment deposits are visible in the
low velocity area of the river where initial plant colonizers can be seen at the early seral
stages of succession of vegetation. Along the banks of the river, gradual accumulation
of sediments has resulted in “Bela” formation, which supports tree growth and hence
New Khanki Barrage Project (NKBP) IEE Report
4‐3
named as “Zakeeras”. On the left bank, the alluvial action of the Chenab is joined by
that of Nullah Palkhu. After running almost parallel to the River Chenab for about 30
kms the Palkhu joins the River a little upstream of the old Khanki headworks. The
Palkhu flood has also been depositing alluvium alongwith that of the Chenab with the
result that the alluvial deposits present on the left bank of the river below Alexandra
Bridge down to old Khanki headworks is a joint action of River Chenab and Nullah
Palkhu.
4.3.2 Physiography
Entire Gujranwala district is a flat plain. The district can be divided into two parts i.e., the
low lying area located close to Chenab River and Dek Nullah and uplands between the
two. The plain of Rachna Doab, inclusive of the immediate and extended area of
influence of the project, is a region of generally uniform slope, with a tilt south west
wards. Not broken by any marked elevation or depression, it is a level or nearly level
piece of land.
4.3.3 Soil Type
The types of soil commonly found in entire district Gujranwala are Gora, Rohi, Doshai,
Maira, Tibba, Kallar and Riverine. The immediate project area soil is riverine alluvial silt
tending to fall in Rohi group.
4.3.4 Land Use
On an average, within the direct influence of the river and in the immediate vicinity of the
project area, 90% of the land is under agriculture. About 6% is under Fish culture or
wetlands and the remaining 4% is Pakkar / Banjar as shown Fig. 4.2.
90%
6% 4%
Agricultural
Fish culture
Banjar
Fig. 4.2 Land use pattern in Project Area
About 80% of total population depends upon agriculture. Most of the land under
agriculture is cultivation. Rice is the main Kharif Crop (90%). The other being Maize,
New Khanki Barrage Project (NKBP) IEE Report
4‐4
Bajra, Sugarcane and Oil seeds. Wheat is the main Rabi crop, the other being barley,
pulses, gram, linseed and green fodders. The cropping intensity is over 100% and
multicropping is quite common. Also see Satellite Imagery of land use in Figure 4.3
(Map).
4.3.5 The River and Hydrologic Regime at Old Khanki Headworks
Peak Discharge
Taking the peak annual discharge of the river Chenab at Khanki Headworks, as
an indicator of the hydrological behavior of the river, following is the discharge
data of past 86 years.
Table - 4.1
Year Discharge Year Discharge
Cusecs
Year Discharge
Cusecs
Year Discharge
1922 160000 1945 152600 1968 235400 1991 314600
1923 257000 1946 229600 1969 362000 1992 910500
1924 203000 1947 251200 1970 275100 1993 439400
1925 266800 1948 438500 1971 311500 1994 425200
1926 225000 1949 225000 1972 281700 1995 630500
1927 261000 1950 1011700 1973 856300 1996 851300
1928 750000 1951 217900 1974 197900 1997 847700
1929 747300 1952 315300 1975 666200 1998 220300
1930 249000 1953 315000 1976 615000 1999 177800
1931 352400 1954 806700 1977 472100 2000 309300
1932 256000 1955 340700 1978 433100 2001 162800
1933 278100 1956 261500 1979 246900 2002 244400
1934 208000 1957 1086400 1980 194800 2003 371800
1935 273800 1958 401700 1981 563900 2004 104433
1936 189100 1959 1021000 1982 261900 2005 368078
1937 123400 1960 709500 1983 303900 2006 418740
1938 264500 1961 354000 1984 167400 2007 300197
1939 184800 1962 345300 1985 309100 2008 215412
1940 145600 1963 186700 1986 341000 2009 105358
1941 287400 1964 406200 1987 109400 2010 334437
1942 288400 1965 200700 1988 864200
1943 220600 1966 631600 1989 512200
1944 173200 1967 240700 1990 345700
New Khanki Barrage Project (NKBP) IEE Report
4‐5
4.3.6 Effect of Dismantling of Old Khanki Barrage on Peak Discharge of
Chenab River
After the commissioning of the New Khanki Barrage, 900 ft. downstream of headworks
the existing, old structure shall have to be dismantled to remove the obstruction and
cause a smooth flow of water into the part of the pond below. The discharge of water
shall be measured at new site.
4.3.7 Water Resource for the Vicinity Area
Surface Water
Main source of surface water in the immediate project area is river Chenab itself.
However, the surface water consists of several Nullahs (torrents) and the L.C.C.
system. The most important Nullahs are Palkhu, Bhimber, Aik, Dek and Bhair, which
mark general drainage lines in the watershed. The surface water supply plays an
important role in irrigation and drainage of the extended project area. Major source of
Irrigation water is River Chenab through L.C.C. which presently off takes from Old
Khanki Headworks in Wazirabad Tehsil and enters Hafizabad district at Muradian. Two
Surface water samples were collected on 08.07.2011& analyzed on 13.07.2011. The
surface water quality results are shown in Table – 4.2.
New Khanki Barrage Project (NKBP) IEE Report
4‐6
Table - 4.2: Summary Parameters of Surface Water Quality Analysis
Almost all the parameters analyzed are well within NEQS Limit of Pak-EPA except the
TSS (567.0 mg/l) of Sample -1 (Surface Water Chenab River at Head Khanki) and TSS
S. No. Parameters Units NEQS WHO
Guidelines
Surface Water (Chenab
River At Head Khanki)
Surface Water ( Palkhu
Nallah falls into Old
Khanki Barrage)
1 Temperature oC 40 - 30.0 25.0
2 pH Value .... 6.5-8.5 6.5-8.5 7.4 7.4
3 TDS mg/l 3500 1000 110.0 740
4 TSS mg/l 200 - 567.0 860
5 COD mg/l 150 N.D 40.0 498
6 BOD5 mg/l 80 N.D 18.0 254
7 Chloride mg/l 1000 250 8.4 314
8 Grease & Oil mg/l 10 - 0.0 7
9 Phenolic Compound mg/l 0.1 - BDL 0.086
10 Sulphate mg/l 600 250 18.0 150
11 Cyanide mg/l 1.0 0.07 0.005 0.007
12 An-ionic Detergents mg/I 20.0 - BDL 0.064
13 Sulphide mg/l 1.0 0.05 0.091 0.124
14 Fluoride mg// 10 1-5 0.08 0.68
15 Ammonia mg/l 40 1-5 0.55 3.2
16 Cadmium mg/l 0.1 0.003 BDL BDL
17 Chromium Total mg/l 1.0 0.05 0.01 BDL
18 Copper mg/l 1.0 1-2 0.04 0.08
19 Lead mg/l 0.5 0.01 BDL BDL
20 Nickel mg/l 1.0 0.02 0.02 0.09
21 Silver mg/l 1.0 NS BDL 0.024
22 Selenium mg/I 0.5 0.01 BDL BDL
23 Mercury mg/I 0.001 0.001 BDL BDL
24 Total Toxic Metal mg/I 2.0 - 0.07 0.194
25 Zinc mg/l 5.0 3.0 0.07 0.26
26 Arsenic mg/l 1.0 0.01 0.01 BDL
27 Barium mg/l 1.5 0.7 BDL 1.0
28 Iron Total mg/l 8.0 0.3 0.25 0.67
29 Manganese mg/I 1.5 0.1-0.5 0.154 0.256
30 Boron mg/l 6.0 0.3 0.5 0.0
31 Chlorine Total mg/I 1.0 0.6-1.0 0.0 0.10
New Khanki Barrage Project (NKBP) IEE Report
4‐7
(860 mg/l), COD (498 mg/l) and BOD5 (254 mg/l) of Sample – 2 (Surface Water where
Palkhu Nallah falls into old Khanki Barrage).
Ground Water
The ground water aquifer is recharged by surface water. The sub-soil ground water
table is about 32-65 feet and the water is sweet and of drinkable quality. There are
above 30,000 tube wells in the extended project area which meet about 20% of the
requirement of water for drinking and irrigation. By and large the tube wells are owned
privately by people of the area. The reservoir of ground water becomes significant
during Rabi season when the canal water is not available and rainfall is scanty. Around
23000 (77%) tube wells are being run on diesel while the remaining about 7000 (23%)
are running with the help of electricity lesser dependence upon electricity is due to its
undependable supply in the rural areas. Three Ground water samples were collected
on 08.07.2011& analyzed on 13.07.2011.The ground water quality analysis results are
shown in Table – 4.3. Almost all the parameters are within the WHO standards except
the Sulphate (Kot Imam Buksh Village Hand Pump sample), Sodium (Kot Imam Buksh
Village Hand pump) and TDS (Kot Imam Buksh Village Hand Pump sample).
Table – 4.3: Summary parameters of ground water quality
Sr.
No.
Parameters Units WHO
Guide lines
Hand pump
Near
Workshop
Khanki Head
Hand pump
Kot Imam
Buksh
Village
Tube well
Kot Imam
Buksh
Village
1 Temperature oC .... 28.0 23.0 23.0
2 pH Value .... 6.5-8.5 7.2 7.4 7.2
3 Arsenic mg/l 0.01 0.005 0.005 0.010
4 Chloride mg/l 250 0.8 17.9 10.1
5 Fluoride mg// 1.5 0.10 0.96 0.48
6 Sulphate mg/l 250 8.0 465.0 200.0
7 Sulphide mg/l - -- 0 0 0
8 Sodium mg/l 200 5.8 215.5 131.5
9 Potassium mg/l -- 3.6 7.7 4.8
10 TSS mg/l -- 0.0 1.0 2.0
11 TDS mg/l 1000 182.0 1060.0 684
12 Chromium Total mg/l 0.05 0 0 0
13 Lead Mg/l 0.05 0 0 0
14 Iron mg/l 0.3 2.13 0.05 0.02
15 Nitrate mg/l 50 1.2 1.2 1.0
16 Total Colony count Cfu/ml < 500 318 386 295
New Khanki Barrage Project (NKBP) IEE Report
4‐8
Surface Salinity
SCARPS Monitoring Organization (SMO) undertakes the study to identify the saline
area in New Khanki Barrage command area. Portable digital conductivity meter was
used to measure the EC of 0-15cm soil. Four categories namely, non-saline (S1 (EC
up to 4dS/m)), slightly saline (S2 (EC between 4 to 8dS/m)), moderately saline (S3
(EC between 8-15dS/m)) and strongly saline (S4 (EC above 15dS/m)) were
recognized and mapped. The percentage of saline area found within the Barrage
command area is summarized in Table 4.4.
Table 4.4: Percentage Surface Salinity Statistics
Class Percentage
Non Saline (S1) 88
Slightly Saline(S2) 1
Moderately Saline (S3) 1
Strongly Saline (S4) Negligible
Miscellaneous Land Type 9
Erosion of Protection Embankments
The possibility of the bund (embankment) erosion will be rather limited. Local water
pressures or whirlpools caused due to burrows of rodents, loosening of soil by root
action of trees, dissolution of some localized deposits, faults developed in the
embankment due to heavy rain showers or direct washing away of the embankment
due to sheet erosion during heavy rains, can collectively or severally weaken the bunds
through erosion. These possibilities shall have to be warded off through an effective
maintenance and frequent monitoring of the safety of the protection bunds.
4.3.8 Climate
The project is located in Gujranwala and Gujrat Districts, which have a hot climate
during summer and moderately cold in winter. The summer season starts in April and
continues till September. The winter season begins in November and lasts till March.
Temperature
June is the hottest month of the year while January is the coldest. During June the
mean maximum and minimum temperature ranges between 40°C and 27°C
respectively. During January the mean maximum temperature is 19°C and means
minimum is 5°C.
New Khanki Barrage Project (NKBP) IEE Report
4‐9
Relative Humidity
The relative humidity during rainy season is as high as 60-70%. During dry months it
falls below 50%. The evaporation effect from river surface, however, takes it a little
higher, in the belt close to the river. The average daily relative humidity for July is
around 69%.
Precipitation
Average annual rainfall is about 375 mm (14.8 inches) with most of it descending in the
months of July, August and September. Winter rainfalls are rare and scanty.
Wind Velocity
The average daily wind speed in July has been around 4 km/h, that’s the equivalent to
about 3 mph, or 2 knots. In recent years the maximum sustained wind speed has
reached 61 km/h, that’s the equivalent of around 38 mph, or 33 knots. Prevalent wind
velocity is 10-25 km/h. At times during summers it can got to 30-50 km/h creating dust
storms and making the air hazy and dusty. The low pressure areas suck in cold winds
often accompanied by rain showers. Wind direction keeps changing according to
seasons. During summery mostly it is northerly while during winter it is usually south
easterly.
4.3.9 Ambient Quality of Environment
Ambient Air Quality
Kick of dust suspension of fine particles from the ground will be the major source of
atmospheric pollutant together with smoke particles arising from wood fires used for
cooking and heating. Carbon monoxide and oxides of sulfur and nitrogen will be
derived from powered vehicles and from burning domestic fuels, Asphalt Plants, etc.
(See Table – 4.5 for Ambient Air Quality).
Carbon Monoxide (CO)
Carbon Dioxide (CO2)
Sulfur Dioxide (SO2)
Nitrogen Dioxide (NO2)
Oxygen (O2)
Respirable Particulate Matter (PM10)
Noise Level
New Khanki Barrage Project (NKBP) IEE Report
4‐10
Table – 4.5: Summary of Ambient Air Quality & Noise Level
Sr.
No.
Locations CO SO2 NO2 CO2 O2 PM10 Noise
Level
ppm µg/m3 µg/m3 ppm % µg/m3 dB(A)
1 Head Khanki Near Right
Protection Bund
0 BDL BDL 402.0 20.9 106.9 63.6
2 Had Khanki near Railway
track (Left Protection
Bund)
0 BDL BDL 418.0 20.9 112.4 68.4
3 Kot Imam Buksh Village
near Khanki Head
0 BDL BDL 436.0 20.9 103.5 61.2
All determinants were within the values defined in the Pak-EPA, NEQS air quality
standards.
Table - 4.6: Traffic Count Crossing Over L.C.C. Headworks, on Old Khanki
Headworks (passing both ways)
Day
No.
Date and
Day Harvesters Tractors/Trolleys
Buses
and
Trucks
Dallas
and
Pick-
Ups
Cars
and
Small
vehicles
Rickshaws/
Qinchis
Motor
Bikes Total
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
01. Friday 0 12 20 10 20 15 35 102
02. Saturday 2 11 18 14 15 14 30 104
03. Sunday 2 12 22 13 20 22 45 136
04. Monday 1 10 19 15 14 10 33 102
05. Tuesday 2 13 20 12 20 12 35 114
06. Wednesday 1 11 20 13 22 13 30 110
07. Thursday 0 9 22 14 11 14 30 100
Total for the Week 8 78 141 101 122 100 238 788
Daily Average 1 11 20 14 17 14 34 112
Source: Primary data collected on the spot through Sub-Engineer Khanki, (June
2011).
New Khanki Barrage Project (NKBP) IEE Report
4‐11
Noise Level
The noise level presently never exceeds 68.4 dB (A). Even after the construction of
new bridge along the new barrage, the noise level will not exceed 85. However during
construction due to construction machinery temporarily higher noise levels shall be
experience. Just for comparison safe absolute values of various noise levels are given
in Table - 4.7 and base data analysis results are shown in Table - 4.5.
The New Bridge
At present, there is a road only over the head works of canal. There is no bridge over
the river. The new barrage shall have a bridge running parallel to the Barrage across
the river.
When the new barrage with a bridge across Chenab is built, it will generate new traffic
because of cultural reunion between people from two sides of the river and will promote,
trade and commerce and transport of agricultural produce to the markets. Over a two
lane carriageway of 24 feet width having paved shoulders (to be used as foot paths, 3
feet wide on either side has been provided). The bridge will be designed for IRC Class
AA loading. The length of the new barrage bridge shall be equal to that of barrage
across the river i.e., 4384 ft. Since there has never been a bridge across Chenab at
Khanki, so no estimates are available as to how much traffic shall be generated when a
new bridge is commissioned. If the traffic passing over the bridge over the present
L.C.C. Headworks is taken as a base and the trend of increase in traffic is taken to be
ten times of the current level, the new bridge will be facilitating some 460 vehicles
passing over it daily. For the new bridge, the specifications shall have to be rich enough
to help the new barrage to stay much beyond the ordinary anticipated age of 50 years.
All will depend upon the safety factor kept in design.
New Khanki Barrage Project (NKBP) IEE Report
4‐12
Table - 4.7: Some Sources and Effects of Noise
Sr.
No.
Source Sound pressure
(dynes/cm2
Decibels
(db)
Power at
ear
Effects
1 Shot gun blast
(1m)
4000 300 10-1 Instant damage-complete loss
of hearing
2 Stereo headphone
(full volume)
2000 150 10-1 Hearing damage in 30 seconds
3 50- hp siren (at
100m)
1000 130 10-3 Pain thresh hold
4 Jet take off (200m) 200 120 10-4 Hearing damage in 7.5 minutes
5 Heavy metal rock
band
100 110 10-5 Hearing damage in 30 minutes
6 Bus, truck, 6-10
wheels
20 100 10-5 Hearing damage in 2 hours
7 Railway train 20 100 10-5 Hearing damage in 2 hours
8 Power mover,
motorcycle
20 85 10-5 Hearing damage in 2 hours
9 Heavy city traffic 20 85 10-6 Hearing damage in 2 hours
10 Pick ups 18 80 10-7 Hearing damage in 8 hours
11 Small cars 10 60 10-9 Hearing damage in 8 hours
12 Lord classical
music
2 60 10-9 Hearing damage in 8 hours
13 Vacum cleaner 01 60 10-9 Hearing damage in 8 hours
14 Normal
conversation
0.02 60 10-9 Concentration disrupted
15 Bedroom 0.02 40 10-11 Speech disrupted
16 Library 0.01 30 10-13 Quiet
17 Soft whisper 0.002 20 10-14 Very Quiet
18 Leaves rustling in
the wind
0.001 10 10-15 Barely audible
19 Mosquito wing at
4m
0.0002 0 10-15 Hearing threshold youth 1000-
4000 Hz
Source: Urbanization and Sustainable Cities 100: Environmental Science,
International Science, 5th edition (1991) Cunningham Saigo.
New Khanki Barrage Project (NKBP) IEE Report
4‐13
Natural History Event
The area has no history of any serious damages due to earthquakes. There is no report
on record of any earthquake creating any serious impact on the old Khanki headworks,
its barrage or any part of the river or L.C.C. system.
Figure 4.3: Seismic Hazard Zones of Pakistan
National Seismic Monitoring Centre of Pakistan issued the seismic zone map for
Pakistan, as shown in Figure 4.3. New Khanki Barrage command area falls in low
hazard area and low risk associated with the infrastructure found in this area.
Floods
Being fed by the melting snow falling on the peaks of Western Himalayas, River
Chenab does experience fluctuations in its flow. An exhaustive study of historic flood
data of Chenab River and flood frequency analysis by a number of methods was carried
out and it was concluded that a 100 year design flood can be of the order of 1,100,000
cusecs, which happens to be about 40% in excess of the existing (old) barrage capacity
of 800,000 cusecs. For peak discharge statement at Khanki (See table 4.1)
New Khanki Barrage Project (NKBP) IEE Report
4‐14
Archaeological Sites/Chance Finds
No sites of archeological, historical, cultural, or religious significance are known to
exist in the areas where construction will take place or where different project
facilities will be established / located. In case there is a chance find, it can be handled
as per Law and Procedures
4.4 BIOLOGICAL ENVIRONMENT
Forests and Flora
There are no protected forests in or adjacent to the project area. An area of land
owned by PID has been assigned for use by the Contractor as the works area to be
used for worker accommodation, materials and plant storage and concrete batching
plant. The area is designated as grassland but there are occasional trees at the
boundary and within the area. A survey has been carried out to identify the types,
number and condition of the trees within the area. The results of the survey of the
whole area are describe below.
The flora of the project area can be divided into two zones, that occupying the
riverine levels and that occupying the higher surrounding areas. The predominant
flora of the riverine tracts is listed below, whereas, flora for higher surrounding areas
is also given as under.
4.4.1 Flora
The flora of the project area can be divided into two parts:-
i. Riverian Flora
ii. Inland Flora
Flora of Riverian Tract
On fresh silt alluvium, mostly located in the pond area of the old headworks, depending
upon the maturity of soil and its drainage status a variety of river vegetation can be
seen. In clearly visible succession of vegetation, first colonizers are grasses, sedges,
Typha, Saccharum, Erianthus munja, Sacharum spontanem, Tamarix and Shisham.
From small vegetation to trees the stages appear as the alluvium level rises and
becomes capable of anchoring an erect tree. In its present status the flora of the
Chenab riverian tract can be listed as follows:-
New Khanki Barrage Project (NKBP) IEE Report
4‐15
Other Plants
Lai/Pilchi (Tarmarix dioca)
Khabbal (Cynodon dactylon)
Kanwal, Kamian (Nelumbium speciosum)
Munj (Saccharum munja)
Kunder (Typha elephantina)
Kai (Saccharum spontaneum)
Flora of Inland Tract
The Inland areas are either the alluvial deposits along the river banks or the right and
left banks themselves. The main inland species of the flora of the immediate and
extended projects area are listed below:-
Trees
Kikar, Babool (Acacia nilotica)
Shisham, Tahli (Dalbergia sissoo)
Pipal (Ficus religiosa)
Bohar (Ficus bengalensis)
Mulberry (Morus alba)
Lasoora (Cordia obliqua)
Siris (Albizzia lebbela)
Amaltas (Cassia fistula)
Beri (Zizyphus jujuba)
Bakain, Dharek (Melia azedarach)
Sufaida (Eucalyptus camelduleusis)
Simal (Bombax ceiba)
Other Plants
Harmal (Peganum harmala)
Pohli (Argemone maxicana)
Khardar (Alhaji camelorum)
Khabbal (Cynodon dactylon)
Datura (Datura alba)
Phog (Calligonum polygnoides)
Malla (Zizyphus numularia)
Laily (convolvulus arvensis)
Shahtara ( Fumaria parviflora)
Saunchal (Malva parviflora)
Dhodhak (Euphorbia sp.)
New Khanki Barrage Project (NKBP) IEE Report
4‐16
It sit (Boerhauid diffusa)
AK (Calotropis procera)
Aksin (Ipomea crassicaulis)
Dib Koonder (Typha elephantina)
Deela (Cyperus rotundus)
Bhang (Cannabis sativa)
Bathu (Chenopodium album)
Datura (Datura inrokia)
Jantar (Sesbania sesbans)
And agricultural crops like wheat, maize, sugarcane and tobacco in Rabi season and
rice and pulses in Kharif season.
The existing flora including the year round agricultural crops in the extended area of the
project is because of adequate irrigation. If irrigation were not there, the original Tropical
Thorn Forest Flora would have continued to grow and which was as follows:-
Jand (Prosopis spicigera)
Karir (Capparis aphylla)
Var (Salvadora oleoides)
Peeloo (Salvadora persica) and the associated shruks, herb and grosses
The irrigation has changed the ecological conditions so much that the dry land flora has
been wiped out.
The riverian as well as the inland flora plays a significant role in the local economy by
way of Timber and Fuel wood production, protection from wind and water erosion,
habitat of birds and animals environmental balance, cultural identification and
rehabilitation of soils affected by water logging and salinity.
4.4.2 Fauna
The immediate and surrounding area of the project has been under human inference for
a long time and, therefore, a large number of wildlife species are already extinct or have
shifted to other sites where they could find protection. The species left behind are those
which have either adjusted with the present state of habitat or have adapted such like
habit that they keep migrating between alternate habitats to strike their best balance
with physical, biological or human factors of environment.
New Khanki Barrage Project (NKBP) IEE Report
4‐17
Following list shows an approximate state of fauna in immediate and extended project
area:-
Table - 4.8: Mammals
Species Scientific Name Status
Jungle cat Felis chaus Common
Porcupine Hystrise indica Common
Hedge Hog Hemiechinus spp Common
Jackal Canis aureus Common
Wild Boar Sus scrofa Common
Hare Lepus nigricollis Common
Squirrel Funbulus penanti Common
Mole Rat Bandicota bengalensis Common
House Rat Mus musculus Common
Black Rat Ratus Ratus Common
Chamgadar/Bat Pipistralius terwis Common
Gheese, House Shrew Suncus marirus Common
Table - 4.9: Birds
(a) Resident Birds of Prey
Species Zoological Name Status
Brahminy Kite Haliaster Indus Common
Black Kite Milvus rigrans Common
White breasted King
Fisher
Heleyon sinyrnensis Common
(b) Seed Eating Birds
Species Zoological Name Status
Dove (ring necked) Streptopelia dacaocto Common
Dove Streptopelia tranquebarica Common
Dove Streptopelia senegalensis Common
Finches Estrilda amandava Common
Larks Mirafa erythroptera Common
Weaver birds Ploceus philippinus Common
New Khanki Barrage Project (NKBP) IEE Report
4‐18
Species Zoological Name Status
Indian Sand Martins Riparia paludicola Common
Indian river tern Sterna auranlia Common
Black Partridge Francolinus francolinus Common
Common Babbler Turdoides candatus Common
Woody – Wood Pecker
(Chakki Ra)
Chakki ra Common
Stark/Bagla Bagla Common
(c) Common Terrestrial Birds
Species Zoological Name Status
Grey partridge Pyeronotus xynthopygos Common
Jungle Pigeon Teron walia Common
Sun Bird Necterine spp Common
House sparrow Passer spp Common
Russian sparrow Hirundo rustica Common
Crow Corcias abyssinicus Common
Owl Bubo Africans Common
Parakeets/Tota Psittaciformes Common
Shrikes Passeriformes Common
Tree-pies Passeriformes Common
Fly Catchers Passeriformes Common
Rollers Passeriformes Common
Neel Kanth Gracius garrulous Common
Common Babler Turdiodes cardatus Common
House Sparrow Passer Sp. Common
Mynas Passeriformes Common
Bee-eaters Passeriformes Common
Minivits Passeriformes Common
Munias Passeriformes Common
Koel Koel Common
Parrot Psittacula krameri Common
Quail (Batera) Pycnonotus cafer Common
Black Rock Pigeon Columbia livia Common
New Khanki Barrage Project (NKBP) IEE Report
4‐19
Migratory Birds
The project site is not situated along regular flyway of the water fowls. However, some
migratory birds are seen in the pond area during various times of the year and the pond
behind the old headworks has been a habitat for a large number of local as well as
migratory birds. Some of the reported birds are as follows:-
(d) Migratory Birds
Species Zoological Name Status
Cattle egret Bubalbus ibis Common
Common Coot Fulica atra Common
Common Pochard Athya ferinal Common
Common Sand Piper Actitis hypalencus Common
Common Teal Anaz crecia Common
Grey heron Ardea cinerea Common
Pond heron Ardeola grayti Common
River tern Sterna aurantia Common
Lesser Whistiling teal Denrocygna bicolor Common
Little egret Egretta garzetta Common
Little grebe Tackybaptus ruficollis Common
Purple heron Ardea purpurea Common
Red Shank Tringa tetanus Common
Common Starling Sturnus vulgaris Common
Table - 4.10: Reptiles
Species Scientific Name Status
Chequered Keel back
Snake
Natrix piscator Common
Dark-bellied marsh Snake Xenochrophis cerasogaster Common
Indian Monitor Lizard Veranus bengalensis Common
Common Field Lizard Uromastrix hardwickir Common
Common House Lizard Geko geko -
And a variety of Turtles as follows:-
New Khanki Barrage Project (NKBP) IEE Report
4‐20
Table - 4.11(a): Turtles – Hard Shells
Brown River Turtle Kachuga smithin Common
Saw Back Turtle Kachuga tecta Common
Brahminy River Turtle Hardella thurgi Common
Table - 4.11(b): Turtles – True Soft Shells
Common Tortoise --- Common
Table - 4.12: Amphibians
Frogs Rara Tigrina Common
Toods Common
Fish
A series of barrages i.e., Marala, Khanki and Qadirabad have over the years, seriously
hampered the survival and propagation of a large number of river fish species, the
number of which had been recorded as high as forty seven in 1960. All subsurface
swimmer fishes, being unable to use fish ladder, suffer the most. Their upstream
migration becomes impossible and their habitat gets broken. Chances for natural
selection and survival of the fittest are denied to the species and over the time, it gets
extinct. That is how most of the fishes now flourish only below Qadirabad barrage and
some above Marala barrage. Khanki Barrage as a fish habitat is blocked on upstream
as well as downstream side. That is why the fisheries as an economic activity has
exhibited a consistent decline in the project area. The Fishermen communities are
traditionally called “Machies” (singular Machi), have become merely “boatmen” or have
taken alternate professions and have shifted elsewhere. However, the biological
presence of the following fish species has been reported by the Fisheries Department
Punjab. Two fish ladders were provided in the Old khanki Barrage. Two fish ladders
have also been provided in the new barrage design which will facilitate the fish
migration especially of the species which are surface swimmers and have managed to
survive over the time. With the provision of fish ladders, the Fisheries Department will
adapt ways and means to increase the fish population in the pond area behind the new
barrage. The Fisheries Department has reported a biological presence of the following
fish in Chenab waters above and below the old barrage.
New Khanki Barrage Project (NKBP) IEE Report
4‐21
Table 4.13 Fish reported in river Chenab upstream and downstream Khanki
Barrage.
Local Name Zoological Name Status
Dumbra Labeo rohita Present
Morakha/Mori Cirrhinus mrigala Present
Rohu/Tapra Labeo rohita Present
Seenghala Mystus (Osteobagrus) seenghala Present
Singhari Mystus (Osteobagrus) aor Present
Takla Xenentodon cancila Present
Tangra Mystus (Mystus) vittatus Present
Thaila Catla catla Present
Tilapia Oreochromis niloticus Present
Tirkanda Rita rita Present
(Source: Fisheries Department, Punjab).
However, the Wildlife Department as well as the Fisheries Department is of the view
that as long as there is no drastic change in the general river habitat there can hardly be
any change in the status of the wildlife, or fishes. Due to getting blocked on either side,
the river habitat has already detracted to an almost minimum level. And the biological
inter balance in the ecosystem of the old headworks with a new one may not cause any
further deterioration in biota.
4.4.3 Endangered Species
There are no endangered, extinct or rare species reported/ pertains to AOI.
4.4.4 Livestock
The Project area lies in Rachna Doab, which is famous for buffaloes known as one of
highest milk producing animals. The people of the Doab have been cattle breeders
traditionally and have been carrying their cast name as “Gujars”. In fact, the main city of
the area took its name after Gujars “and is called” Gujranwala. The livestock includes
cattle, buffalos, sheep, goats, camels, horses, asses and mules nearly 25% of the
farmers income is from livestock. At least 10% of the population is landless cattle
raisers and their living comes from cattle milk marketing. An average family possesses
5-6 cattle and 7-10 sheep and goats.
New Khanki Barrage Project (NKBP) IEE Report
4‐22
4.4.5 Agriculture
About 80% of the population of extended project area depends upon agriculture. Most
of the area is well cultivated. Rice is the main kharif crop. Gujranwala district is known
for its high quality Basmati with very pleasant flavor, which is very popular in the world
especially in the Middle East. The other Kharif crops are Maize, Bajra, Sugarcane and
oilseeds. Similarly wheat, barley, pulses, grams, linseed and green fodders area main
Rabi crops Rice is grown on about 30% of cultivated area during Kharif and wheat is
cultivated on 80% of area during Rabi season. The cropping intensity is 100% and even
more than 100% on some areas. The area and production under different Rabi and
Kharif crops is given as follows:-
Table - 4.14: Area, Production and Cropping Intensities of Main Agri Crops in
Rancha Doab
4.4.6 Horticulture
The main fruits grown in District Gujranwala are Jaman, falsa, malta, kino, fruiter, sweet
lemon, plum, mulberry, guava and pomegranate. The principal vegetables grown in the
district are onions, potatoes, ginger, egg plant, arum, lady finger, spinach, mint, tomato,
turnip, carrot, cauliflower, bitter gourd, garlic, pea, reddish and cucumber etc.
The soil as well as climate is quite suitable for growing citrus fruits like malta, kino,
lemon etc, and guava. Horticulture is being practiced on about 8,000 acres which
produces about 3000 tons of fruits and vegetables.
4.4.7 Socio-Economic and Cultural Aspects
This section provides an overview of the socioeconomic conditions and cultural
mores in the project area. Socio economic conditions of the area depend upon the
population, employment level, trade and businesses, customs, religion, social
activities, occasions, and their social cohesion.
Sr.
No.
Crops Area
(Hectares)
Cropping
Intensity
1 Wheat 117,000 100%
2 Rice 40,000 100% and more
3 Sugarcane 4,000 100%
Source: Agriculture Extension service of Punjab Agriculture Department
New Khanki Barrage Project (NKBP) IEE Report
4‐23
Social impacts can be defined as the consequences to people of any proposed
action that changes the way they live, work, relate to one another, organize
themselves and function as individuals and members of society. This definition
includes social-psychological changes, for example to people’s values, attitudes and
perceptions of themselves and their community and environment. (Narayan 2005)
4.4.8 Population and Community Structure
LCC Command area is 3.0 million acres. The population in the area is nearly 5.0 million
persons. Density of population per sq. km is 570 as compared to 350 for overall Punjab.
The socio-economic structure of project area is primarily agrarian. About 74 percent of
the total population lives in rural area and depends upon agriculture. The remaining
population lives in cities and towns with ample facilities for work as the cities are
generally well industrialized especially in metal works, electrical goods, ceramics and
agro-based industries. Some of the rural population travels and even migrates to cities
for employment.
The Community economy depends upon an agriculturally oriented cost system. Most of
the agricultural land ownership belongs to Jats, Arains, Gujars and Rajpoots. Jats are
mostly Cheemas, Chathas, Kahlon Waraich and Sahis. Other casts in the rural area
playing a supportive role to agriculture consist of the artisans like carpenters,
blacksmiths, goldsmiths, In cities population has Kashmiries, Mughals, Shiekhs and
Khokars etc. Ninety seven percent populations are Muslims. Remaining 3% are
Christians and other denominations. The ratio of female population is lower than male
i.e. male 60%: female 40%. Average family size is about 7 members with a range
between 4 – 27 members per household. Mostly the families are used to live in a joint
family system. The age of around 50% of the farmers engaged in farming fell between
40 – 60 years. General trend in the younger age groups is to diversify away from
agriculture.
4.4.9 Poverty Status
About 40% of the population in the immediate as well as the extended project area is
under poverty line for their food and basic necessities and their income is less than Rs.
2,000/- per month per family of 6-8 persons. The population below poverty line falls in
various categories like small landowners, tenants, artisans and servicemen etc.
New Khanki Barrage Project (NKBP) IEE Report
4‐24
4.4.10 Land Tenure System
Land is inherited patrilineally. The land ownership is between ½ acre to 125 acres. Eight
percent farmers are subsistence farmers owning 5 – 12.5 acres of land. Farmers
owning 50 acres and above are less than 5% while 0.5 acres to 5.0 acres is owned by
15%. Those falling in the last category either take land on share or lease to make it an
economic tillage or quit agriculture altogether and go to big town and cities for taking up
small jobs or work as labour.
Women are not encouraged to inherit land. According to Sunni Mohammadan Law the
females inherit ½ share while males receive a full share. And according to Shia Law the
male and female inherit equal share. But in both the sects the sisters, out of their love
for their material linkage, do not claim their share. Land ownership, acquisition and
management is governed by land laws. Land Acquisition Act 1894 is the basic land law.
Land Revenue is a Rent and not a Tax.
4.4.11 Land Value
Agricultural land is treated differently from a piece of land in a town city or a village.
Urban land has higher value. According productivity the total land mass of a
country/province is divided into 8 broad classes as shown in the following sketch:
Table - 4.15: Land Capability Class
I II III IV V VI VII VIII
Agriculture Land Forests Rang
Lands
Story Gills Show Clad
Peeks
The value of land is kept at its productivity. Usually the value is assessed at 20 years
produce or latest sale price of a similar peace of property, whichever is higher.
Agriculture land is divided into 4 classes, the best being class I and least productive
being class IV. At the time of land consolidation these classes are interchanged
mutually and proportionately. Prevalently in Bela area per acre price of agricultural land
varies between Rs. 5 lacs to 6 lacs, while outside bunds the land value simply gets
doubled.
New Khanki Barrage Project (NKBP) IEE Report
4‐25
4.4.12 Social Equity
Social equity does not exist in the area now-a-days. Old systems of equity and social
security such as Punchayat, Bradri, village community, have collapsed and the new
system such as NGO’s, Union councils and professional organizations have not yet fully
taken roots.
4.4.13 Social Cohesion
The human society in project area is Muslim by 97 percent and Christians by 3 percent.
The Muslims are Sunnis (70%) and Shias (30%). The village population is mostly Jats
(Cheemas, Chathas, Kahloon, Waraich, Nats and Sindhu, tribes), Arains, Moghals and
Rajpoots.
4.4.14 Gender Issues and Status of Women
The number of women in the households is more than male members (women 40%
and men 60%). Sixty five percent populations, male and female together are under 30
years of age. In rest of 35% the age groups taper off as they go towards high age. Due
to ethnic and social reasons most of the times only male population appears in streets
and bazars.
There is a tendency to marry early (men 21 – 25 years, women 18 – 21 years). There
are no teen age marriages. Because of family bonds social values and caste pressures
the rate of divorce is rather low. Most males are contented with one wife through a small
minority of Jut brotherhood have 2 – 3 wives.
The roll of women is crucial for any sustainable development process. The women
situation survey shows that 42% respondent is literate while 58% respondent is illiterate.
The most impressing need of the women of the area is the basic health facilities and the
educational facilities for the girls of the project area. The construction of New Khanki
Barrage will definitely promote the above mentioned needs and also other social
development works.
Average age for men is 60 years, within a range of 35 – 89 years. Average are of
women is 65 years within a range of 25 – 100 years. Infant mortality is 35% because of
lack of gynecological and antenatal facilities in BHU’s People cooperate with Polio
drops campaign every year. Courses of vaccines against small pox, cholera, typhoid
and hepatitis are offered but are ignored by many village households.
New Khanki Barrage Project (NKBP) IEE Report
4‐26
4.4.15 Services and Facilities in the area
Educational level
Above 70% of the population, including females, possess basic primary pass (5
Classes) certificate. About 50% of he males as well as females is middle school pass,
while 30% males and females are matriculates. Almost 82% of the matriculates go for
technician level jobs, traders, shop keepers and factory workers. For those who join
FA/FSc, there are adequate numbers of education institutions. At Gujranwala there is
an independent Board of Secondary Education. After FA / FSc, the inlets are
colleges/universities, Engineering colleges/universities, Armed forces as officers and
other Govt, Department in the middle level careers. About 3% of the FA/FSc pass
candidates join regular BA/BSc classes, and less than 1% reach Master level studies.
Only 1-2 persons per year go to Lahore or Islamabad for their Ph.D. studies. In overall
pursuits the qualitative as well as quantitative performance of female students is
superior to that of male students. Demand for Gujranwala for a university is gaining
momentum.
Industry
The project area is located in Districts of Gujranwala and Gujrat. Gujranwala District
has made a considerable progress in light as well as heavy industries. There are
large industrial units e.g. chemicals, food products, textiles and engineering.
Similarly Gujrat District is centre of production of high quality fans, wood furniture, top
quality table ware, china ware, cottage and other pottery goods. The furniture is
exported to Europe also.
Telephone and Internet
Over past few years the urban as well as the rural parts of the extended project area
have experienced a dramatic change in personal communication. There is a Public Call
Office (PCO) almost in every village and on every corner of the towns and cities.
The availability of telephone connection has also facilitated the computer technology
and internet to reach Khanki village.
Transportation and Accessibility
Almost all villages in the immediate and extended area of influence of the Khanki
headworks system are well connected to cities, town, railway stations and other
villages. There is net work of District Council farm to market roads. Buses, Pick-Ups,
Tongas and Chand Garies (Qinchis) ply on almost every road. Even in relatively remote
New Khanki Barrage Project (NKBP) IEE Report
4‐27
areas like Khanki Headworks, on an average, 5 buses and trucks, 3 pick-ups, 5 cars, 7
Qinchis, 30 motorbikes daily make 40, 14, 11, 42 and 68 trips respectively. Lahore-
Peshawar main railway line passes through Rachna Doab and crosses Chenab River
over Alexandra Bridge 16 Km upstream Khanki Barrage. The G.T. Road connects
Gujrat, Wazirabad and Gujranwala with Lahore and Rawalpindi. The embankments
along river, canals and the tracks along distributaries and Rajbahs provide additional
communications routes to the rural communities. Boats are used only to cross the river
wherever a bridge is not available. Almost every part of Rachna Doab is conveniently
accessible, including the proposed work bases on either side of the river for
construction of the new Khanki Barrage, 900 ft. downstream below the existing barrage.
Electricity, Sui-Gas Supply and energy use
One hundred percent houses in all the rural and urban areas have access to electricity.
However, the households falling below the poverty line restrict themselves to use of few
bulbs and fans.
Hydel – Electricity Power Station at Shadiwal
There is a Hydro-Electric Power Hosue at Shadiwal on Upper Jhelum Canal. If the
level of new barrage is kept at 741 amsl, there will be a reduction of 18.75% (2.53
MW) in power production. It is noteworthy that a level upto 736.50 will have no effect.
In urban areas Sui-gas connections have been provided to almost all houses. In rural
areas 85% still use fuel wood, agricultural wastes or dried dung of cattle. Ten percent of
village inhabitants use Fon-gas cylinders while 5% use Kerosene oil stoves.
Petrol and diesel supplies for transport and agricultural machinery are from Petrol
Pumps along major roads and towns.
Health Facilities
Government Hospitals are located only in big towns and cities like Gujranwala and
Wazirabad while the Basic Health Units (BHUs) have been established at every Union
Council Headquarters. However, the standard of services in the Government run
institutions is not satisfactory. Private Doctors are, therefore, filling up the gap but their
service is dependent upon patients’ affordability. Availability of antenatal services
through Lady Health Visitors has brought the death rate of child bearing mothers and
new-born babies fairly down. It is possible to arrange almost all the child deliveries in
labour rooms in Government or Private Hospitals. Effective preventive programmes on
Smallpox, Cholera and Polio have brought the incidence of these epidemics to almost
zero level. The media campaign against Hepatitis is making people aware of the
New Khanki Barrage Project (NKBP) IEE Report
4‐28
preventive measures against this disease. Recently a very effective awareness
campaign has been initiated by the Health Departments regarding HIV/AIDS (see next
paragraph for details).
Alongwith allopathic cover usually used by comparatively more aware people, a large
part of the rural population is still relying upon, “Hakeems” and Homeopathic treatment.
HIV/AIDS Risk Awareness
This is relevant at two stages.
1. For the population of the project area at all times.
2. For the labour and field staff employed during construction phase.
For general population, an effective awareness campaign is informing on the mass
media and through Lady Health Visitors that one can become HIV positive through
use of infected syringe, transfusion of HIV carrier blood, and sexual intercourse with
HIV carrying male or female. Its transmitting probability is higher in male
homosexuals. HIV positive ultimately gets the AIDS for which there is presently no
known cure. Social barriers and religious values are also helping the communities to
save themselves from getting infected by HIV/AIDS. Well drafted messages on the
subject have been included in the Ethics/Islamiyat syllabi of Schools, Madrissas and
Colleges to prepare the new generation for their protection against HIV/AIDS. Postal
stamps issued on AIDS day also carry a very pointed message for the target
groups. However, no case of HIV/AIDS has been reported in any of the Government
Hospitals/BHUs in the project area so far.
During construction phase, in the labour camps and their interaction with truck
drivers and alike personnel are potential epicenters for spread of HIV/AIDS, if the
incidence exists in any component of this complex. Also the presence of a large
alien male population camping for many years near the villages around the
immediate project area may cause such intercourse which may lead to transmission
of HIV/AIDS if it is present anywhere. Although the prevalent religious and cultural
value system, to a large extent excludes the outbreak or rapid communication of
HIV/AIDS, yet its occurrence in such a situation cannot be precluded. It is necessary
that alongwith other communicable diseases like cholera, typhoid and tuberculosis,
awareness and preventive campaigns are run, from time to time in the labour
camps and among contractor’s other employers in the fields, regarding HIV/AIDS.
And arranging such awareness should be made a contractual obligation of the
contractor by providing it in the Tender as well as the Contract Documents.
New Khanki Barrage Project (NKBP) IEE Report
4‐29
Employment
Increasing education and multiplying population create more and more hands to be
employed. The agriculture alongwith industry has the capacity to absorb at least 50% of
the fresh educated male and female youth. The rest of the 50% has to find their way out
by going to middle east countries, seeking employment in Armed Forces or Police or
other Government offices, hunt jobs in other regions of Punjab or simply sit at home as
unpaid-unemployed youth. Making about 20-30% of the total youth force, the employed
ones make a sizeable unutilized human resource. Of these at least half are males.
Income
Prevalent daily wage in Wazirabad is Rs. 250/- for the labour employed in
construction work. For softer jobs and carriage labour a reduction of Rs. 25 – 50 is
common. The artisan, electricians, blacksmiths, carpenters, cobblers, barbers, tailees
(oilmen) and potters etc. charge according to the services they render. In towns and
cities the services are paid for individual assignments. In rural areas there is service
contract (sape) for a year in lieu of which the payment is done in kind i.e. a
contracted quantity of Rice and Wheat at the time of harvest. Farm labour is also
contracted for season or month and can be paid in cash or kind, the value of which is
nearly equal to the minimum wage in the town.
The big landlords make almost Rs. 6,000/- per acre as their net earning. Most of
them live in big cities and they visit their lands only to get a self reassurance that they
are the landlords. They mostly run their management through their employed.
Managers called “Munshis” or “Muneems”
Vulnerable Groups
Less than two percent of the population truly fell in vulnerable groups. These groups
mainly consisted of widows, handicapped, landless shelterless and religious minority.
The vulnerable groups had an even distribution all over the project area.
Indigenous Peoples Safeguards
During the field survey it was especially focused to screen out Indigenous Peoples.
People living in project areas belong to various caste patterns and have homogeneous
culture. People have different caste systems but their culture pattern and living habits
are same as those of people of Punjab province. There is no community that meets the
criteria of ADB definition of Indigenous People. As such the ADB policy on Indigenous
peoples will not be triggered by the project.
New Khanki Barrage Project (NKBP) IEE Report
4‐30
Tourism and Recreational Facilities
More than 5000 local tourists visit Khanki Headwork’s annually. A ride over SWR trolley
across the historic Chenab over Khanki Barrage, especially at sunrise or sunset is an
unforgettable experience. Picnic on either of the protection bunds or boating in the river
upstream the headworks takes one to small alluvial islands in the pond area bearing
riverian flora and fauna. A boat with a “Mallah” cum “Lifeguard” can be hired locally for
Rs. 200 per trip across the river. For fishing behind upstream spurs, license has to be
obtained from Fisheries Department. For killing wildboars in the Bela area a free permit
is issued by the Forest Department. For an overnight stay beside the river, a permit is
available from local office of the Irrigation and Power Department against a prefixed
charge per room in the Irrigation & Power Department Rest House built in 1889. With
construction of new barrage the tourism facilities and number of tourists will increase
manifolds.
4.4.16 Credit Facilities
Agricultural Development Bank, extends credit facilities to farmers but needs
collaterals which farmers cannot arrange. Commercial banks usually have no special
facility for farmers or other professionals. Punjab Provincial Cooperative Bank
extends loans on ornaments security but their system has not earned much
acceptance amongst farmers. Informal money lenders are swarming with their ready
money, no collateral but almost prohibitive rate of compound interest (25 – 50%).
Because of sharp ethnic divisions, efforts to form “Cooperatives” of farmers have not
succeeded. However the farmers have started opening their accounts in village
branches of commercial banks.
4.4.17 Resettlement
Because the new barrage involves the construction of new Khanki Barrage, it has
been estimated that about 36 acres of private land and some houses will come under
the right of way of new L.C.C. and studs construction. Comprehensive Land
Acquisition Resettlement Action Plan (LARAP) is under preparation separately. The
LARAP will be prepared and implemented well before time of construction of the new
Khanki barrage project (NKBP).
New Khanki Barrage Project (NKBP) IEE Report
4‐31
4.4.18 Conclusions
Biological environment will boost local economy in terms of improved
agriculture through ensured and irrigation water by way of conveying
water to tails, in LCC system command area.
Tree plantations around project site in lieu of cut trees at canal excavated
area will enhance the scenic value of the site.
Communication will also be improved through repair and widening of
some 32 km of adjoining roads at both sides of the barrage.
Some low lying areas will be rehabilitated by backfilling with dismantled
materials of old weir structure and cofferdams.
With the construction of new barrage, distribution efficiency, flood control,
fishing and social mobility will improve. The bridge across Chenab at new
barrage site will link up the communities and markets on the two banks. This
will generate a healthy social economic and cultural interaction between the
populations of either bank.
The new barrage shall ensure greater safety for the people living near or
downstream the barrage and possibility of collapse of the old barrage would
be eliminated. Sudden collapse of the headworks could cause serious
damage to Qadirabad barrage and its link canal.
Operation of new barrage will be easier and more efficient to work because
of motorized.
Improvement in esthetic value.
Socio-economic and cultural aspects would improve in following ways:
Improvement in infrastructure pertaining to the roads, bridge,
communication and other social amenities like natural gas;
Significant changes in sustainable development;
Permanent health care services;
Cross-river social and cultural linkages;
Improvement in educational facilities;
Assurance of better drinking water supply;
Enhancement in agricultural/livestock/fisheries produce.
Development of Public Park.
Establishment of BHU.
New Khanki Barrage Project (NKBP) IEE Report
5‐1
5. ANALYSIS OF ALTERNATIVES
The key function of the analysis of options is to compare feasible alternatives to the
proposed project components including the ‘No project’ situation. The potential
environmental impacts of each alternatives and feasibility of mitigation of these
impacts along with their suitability under local conditions are also compared. The
following options/alternatives were analyzed for the assessment of strengths and
weaknesses of the proposed project:
No project option/worst scenario option
Option of remodeling and repairing the old headworks and not building new
barrage
Option of constructing the new barrage on the site of old barrage
Option of constructing the new barrage upstream the old barrage
Option of new barrage 900 feet downstream of the old headworks
Option of dismantling the old Khanki barrage
Option of not locating logistics and Irrigation Department land
Option of employing outside labour instead of local labour
A. BARRAGE LOCATION
1) No project option/worst scenario option.
2) The present barrage is remodeled and repaired and no new barrage is built, with no
additional storage and no electric power.
3) A new barrage is constructed on the site of the old headworks i.e. the old barrage is
completely replaced with a new barrage.
4) A new barrage is built upstream the old (existing) headworks.
5) A new Khanki barrage is built 900 ft. downstream of the old (existing) headworks,
with no storage and electric power generation, with the existing storage capacity.
B. LOGISTICS SITES
6) Instead of locating all link roads, paths; camping sites, dumping grounds and
machinery yards, on state land alternate sites area chosen on nearby private lands.
New Khanki Barrage Project (NKBP) IEE Report
5‐2
C. LABOUR
7) Instead of employing maximum local labour, contractor is allowed to bring his labour
from outside the project area because labour from a particular area may have better
capacity.
Each alternative was subjected to SWOT analysis i.e. it was examined as per its
strengths, weaknesses, opportunities and threats.
A. BARRAGE LOCATION
5.1 NO PROJECT OPTION/WORST SCENARIO OPTION
(a) Analysis
Strength and opportunities
If the Project is not taken up at all, then all the efforts and investments shall be saved
and these will become available for diversion on an other project. Should the old
structures, built in 1892 and modified in 1935, collapse because of its age, the fish from
upstream Qadirabad shall be able to move freely upto downstream Marala and a
broken up water habitat shall be reunited. This will assist in better breeding and spewing
of all under water swimming species of fish.
Furthermore, the recurring cost of the new barrage and its operational expenses would
be avoided. Ecologists believe that taking down a barrage will return a river to an
ecologically healthy state. The remarkably limited scientific evidence available regarding
Chenab River however does not entirely support that.
Weaknesses and Threats
Not taking up the Project will, sooner or later, result in a catastrophic collapse of the old
headworks and the destruction that will follow shall most probably be out of proportion
and without warning. It will mean destruction of entire Khanki Headwork’s Complex.
Unprecedented floods shall be followed by canal closure and destruction of agriculture
by cutting off the crucial Irrigation water to most fertile agricultural lands of Punjab. The
pond will be destroyed and along with that the flora and fauna that has been harboring
the habitat since 1892. The huge flood released by collapsed Khanki barrage will wash
away Qadirabad barrage and the combined water of the two barrages shall on its way
to Indus river cause unprecedented damage. The link canals shall either be closed or
New Khanki Barrage Project (NKBP) IEE Report
5‐3
destroyed. A large number of villages along the left and right bank of the river will be
washed away resulting in heavy death toll of humans and cattle. The women and
children would be the worst affected. A large part of nearby population shall be turned
homeless. All services including electricity, telephone, education and communication
shall be disrupted and destroyed. The Trolley over the river shall no more be there and
the right and the left bank shall be disconnected. And many such sites specific factors,
which cannot be anticipated at this stage, will influence the ecological changes that
accrue when the headworks actually gets removed at once. A doomsday in the area
shall be unleashed.
(b) Conclusion
For this proposal, the weaknesses and threats outweigh the strengths and
opportunities. Therefore, No Project option, possessing the potentials of worst scenario
is not recommended.
5.2 OPTION OF REMODELLING AND REPAIRING THE OLD HEADWORKS
AND NOT BUILDING NEW BARRAGE
Analysis
Strength and opportunities
Beyond doubt the existing structure has stood the test of time since 1892 and the
foundations and piers, their mortar or bricks and the masonry work have shown no sign
of deterioration even apparently, Although the design capacity of barrage is 800,000
cusecs, it has passed floods much larger than that without getting damaged. It is
successfully keeping the pond at such a level that L.C.C is running at its design
discharge as per schedule fixed by Irrigation Department. The existing structure can be
gradually modified, starting from one side and then gradually proceeding to the other
and the whole structure can be modernized on its existing foundations. It will require
less expense, shorter time and will cause least disturbances to upstream or
downstream environment. In this option there shall be no need of shifting the L.C.C
Headwork’s too. These will be modernized in situ and no link canal shall be required to
connect the new pond to the L.C.C system. Part of the money saved could be spent on
rebuilding the labor and staff colony and strengthening the existing river training works
and guide bunds. There shall be no negative impact on flora or fauna or any other
component of the ecosystem.
New Khanki Barrage Project (NKBP) IEE Report
5‐4
Weaknesses and Threats
The old barrage is too old physically and too antiques a model to stand for tenure of 50
years. The brick work and the superstructure can neither be repaired nor modernized. It
has an archaic system of regulation through shutters, which is not only very
cumbersome but also does not permit precise control over pond level. The transport of
equipment and man power across the barrage is through an aerial ropeway system
which is not only very time consuming but also dangerous. The SWR having been used
for the purpose dates back to 1907. The capacity of the barrage (800,000 cusecs) is not
compatible with the capacities of Marala Barrage (1,100,000 Cusecs) and Qadirabad
Barrage (900,000 cusecs). An exhaustive study of historic flood data of Chenab River
and flood frequency analysis by a number of methods was carried out and it was
concluded that a 100 year design flood can be of the order of 11,00,000 cusecs which
happens to be 40% in excess of the existing design capacity. In addition to the
limitations of age and capacity, the very model requires change. Its outmoded shutters
and ropeway system, hydraulic changes like growing accretion and increasing non-
modularity call for serious contemplation about possible remedial measures. Any
attempt to repair or modify the old barrage would mean continuation of the same
inherent limitations and defects.
The design of the old headworks has no road bridge but in the design of the new
barrage a 30 ft wide bridge has been provided.
Conclusion.
The weaknesses and threats of this option are overwhelmingly more than its strengths
and opportunities. The option of remodelling and repairing the old headworks, and not
building a new barrage, is not recommendable.
5.3 OPTION OF CONSTRUCTING THE NEW BARRAGE ON THE SITE OF
OLD BARRAGE
(a) Analysis
Strength and Opportunities
An already tested site shall be used to construct the new barrage. The new foundation
can be laid on a firm foundation of the old headworks. The design capacity of 800,000
Cusecs will be raised to 1,100, 000 Cusecs or even more by making suitable changes
in the design of the structure. No change shall be required in the canal headworks of
L.C.C. No link canals shall have to be dug and no additional land shall be required for
New Khanki Barrage Project (NKBP) IEE Report
5‐5
any purpose. All activities including the work bases shall be housed within the lands
owned by IRRIGATION Department. Since the old barrage shall be replaced by a new
barrage on the same site, no major ecological change will take place and no negative
physical, biological or social impact shall be experienced by flora, fauna, or the human
population residing around.
Weaknesses and Threats
To construct a new barrage exactly on the same foundation, the old structure shall have
to be demolished, in part or whole and it will upset the existing L.C.C. system. The
effects so created may not be easily manageable. There will be a possibility of a mishap
causing high floods downstream submerging villages and causing human and cattle life
losses. The idea of an AR bridge over the barrage may have to be abandoned
altogether. Also huge quantities of debris produced out of the destruction of the old
barrage shall have to be disposed off. Replacing the shutters with proper operational
gates will not be possible, as new foundations will be required which cannot be
constructed without breaking the barrage crest floors.
(b) Conclusion
Although apparently appealing, construction of new barrage exactly on the site of the
old headworks has more weaknesses and threats than the strengths and opportunities.
This option, therefore, is not recommendable.
5.4 OPTION OF CONSTRUCTING THE NEW BARRAGE UPSTREAM THE
OLD BARRAGE
(a) Analysis
Strength and Opportunities
A cumbersome process of simultaneous demolishing and reconstructing the old
barrage shall be avoided.
Weaknesses and Threats
The river span upstream the old barrage is wider than the site where the old barrage
was sited. The length of the barrage shall increase if located 1500’-2000 ft upstream
and the lands and several villages of Nathu Kot others shall be inundated, destroying
1200 houses displacing more than 100,000 persons, and creating an A Class
resettlement problem. The L.C.C. Head Regulator shall also have to be shifted
upstream and a link Canal shall be required to link up the new barrage to L.C.C. The
New Khanki Barrage Project (NKBP) IEE Report
5‐6
link canal will pass through the Irrigation Department Colony and office which shall have
to be shifted elsewhere increasing additional cost of land and buildings. By submerging
more agricultural as well as alluvial lands, significant change will take place in the
upstream habitat of flora and fauna. A change in the pond structure will necessitate
modifications in the existing or construction of altogether new river training works,
accruing exorbitant additional costs.
(b) Conclusion
The weaknesses and threats of this option are much heavier than the strengths and
opportunities. The option therefore is not recommended.
5.5 OPTION OF NEW BARRAGE 900 FEET DOWNSTREAM OF THE OLD
HEADWORKS
(a) Analysis
Strength and Opportunities
The site of the new barrage is about 900 ft downstream of the old barrage near the
ends of the right bell bund and the left bell bund Upto this point the span of the river is
as narrow as that of the old barrage. It will be possible to have a barrage of almost
same length but with a better design and most modern mechanism. The barrage gates
can be controlled through moternization. The height can be so manipulated that the
pond level does not change in its overall shape. Also, there will be no change in the
shore line of pond. The land: water ratio will remain the same and no impact shall be
transferred to flora, fauna or the overall habitat of fish and wildlife. The actual purpose of
the project is to replace the old structure with a new and modern one so as to keep
L.C.C. system running at optimal level. Change in scope can make the project counter
productive environmentally. Some private land, three to four pace rooms and tree
cutting will be involved during the excavation of the New L.C.C. The matter will be
solved by the process of land acquisition and compensation; governed by the Land
Acquisition Act 1894 between the government and the private land owner.
Weaknesses and Threats
Shifting the barrage downstream will obviously mean shifting of canal headworks
downwards. A link canal shall have to flow from the new canal head regulator upto
the L.C.C. and this flow shall necessitate adjustments of gradient. If the link canal
has to be along minimum distance and within I D land, it shall have to be specially
New Khanki Barrage Project (NKBP) IEE Report
5‐7
designed and carefully routed which, may involve curves. To avoid serious bank
erosion on the banks the link canal shall have to be lined and always monitored for
any damages during its perennial flow periods.
The old labour and lower staff colony adjacent to “P” spur shall get demolished
because of the route of the link canal and a new colony shall have to be built on the
adjacent Irrigation Department land. Trees cutting will be involved to pass the link
canal and the link roads from the bridge to the existing roads.
(b) Conclusion
The proposal is favored because all the weaknesses and threats are removable
through preparation and implementation of LARAP and EMP implementation as
well. It is, therefore, an acceptable option under prevailing circumstances.
Various components of the each alternative have been evaluated from technical
and environment point of view and alternate (6) is finally selected for execution
being most feasible and environment friendly.
5.6 OPTION OF DISMANTLING THE OLD KHANKI BARRAGE
a) Analysis
Strength and Opportunities
When the New Khanki Barrage is commissioned, the presence of old
structure at Khanki will only cause obstruction on the way of smooth flow of
water. Its dismantling and removal of waste construction material will clear
off the obstructions. The storage capacity of the New Khanki Headworks will
enhance. Some material will be available which can be used for land fills at
suitable places. By removing obstruction, a 10 km long and 4 km wide lake
of water will become available for tourists, boats, launches and anglers.
Local communities, especially the affectees could get alternate employment
linked with tourist facilities. And if Fisheries Development Institute alongwith
Fish Hatchery is brought to the abandoned Khanki Campus, an open
unobstructed large body of water would be available for mass scale
aquaculture. Aesthetic value of the area will increase. And a carbon
sequestration and carbon credit programme would become possible.
New Khanki Barrage Project (NKBP) IEE Report
5‐8
Weaknesses and Threats
A historical structure, which could be used as a visit spot by engineering
students, will vanish forever. Possibility of SWR Trolley being developed as
tourist attraction will be finished. A lot of waste construction material will
cause disposal problem. If the material is thrown into the river it will cause
loss of water storage capacity of the pond. The old headworks are holding a
number of Belas in position. Its removal can cause catastrophic erosion in
“Belas” and wash them down to the vicinity of the New Khanki Barrage. On
dismantling of the old barrage and transporting and dumping the waste
construction material an extra cost shall be incurred.
b) Conclusion
The strengths and opportunities of the option outweigh the weaknesses and threats. It
is therefore recommended that Old Khanki Headworks and its interlinked structures
should be dismantled soon after the New Khanki Barrage is commissioned.
B. LOGISTICS SITES
5.7 OPTION OF NOT LOCATING LOGISTICS AND IRRIGATION
DEPARTMENT LAND
(a) Analysis
Strength and opportunities
A higher degree of freedom shall be enjoyed by Design Engineers as well as the
construction contractor; most suitable land shall be used, be it private or state. The link
canal will not be constructed on a difficult gradient as envisaged in the proposed design
and there shall be convenience of placing the logistics on private land.
Weaknesses and Threats
Large-scale resettlement and compensation shall be involved. The Project will get cost
heavy. Agricultural land shall be destroyed. The existing Irrigation Department land shall
not be fully utilized.
New Khanki Barrage Project (NKBP) IEE Report
5‐9
(b) Conclusion
In the presence of adequate Irrigation Department land, taking the project to private
lands is not advisable. The weaknesses and threats outweigh the strengths and
opportunities. The option for this alternative is therefore dropped.
C. LABOUR
5.8 OPTION OF EMPLOYING OUTSIDE LABOUR INSTEAD OF LOCAL
LABOUR
(a) Analysis
Strength and opportunities
More efficient, more dependable and well trained man power will be available. The local
communities, thus, will not be able to exert undue pressures on the Contractor or the
project. The outside labour will set model for the untrained local labour which may
improve. Spending in the local market by the outside labour will bring additional benefits
to local economy.
Weaknesses and Threats
Bringing outside labour will take away the economic benefit from the local communities
and the local communities will not develop a sense of “ownership” for the project. The
project objectives of poverty alleviation, social uplift and capacity building shall be
defeated. A massive social problem shall be created.
(b) Conclusion
In case the labour is brought in from outside, the social losses will be much higher than
the economic gains. However ergonomic limitations may necessitate bringing in small
percentage of outside manpower especially at the skilled level. But, as far as possible,
the local human resource shall have to be preferred.
New Khanki Barrage Project (NKBP) IEE Report
5‐10
5.9 SUMMARY OF ALTERNATIVES
1. No project option/worst scenario option is not recommended
2. Option of remodeling and repairing the old barrage and not building new barrage is
not recommendable.
3. Construction of a new barrage upstream the old barrage is also not recommended.
4. The option of constructing the new barrage about 900 ft. downstream of the old
barrage is recommended; being most feasible and environment friendly.
5. Option of placing all logistics on the available Irrigation Department land is the best
choice, for the project within its presently stated scope.
6. Maximum local manpower should be employed on the project.
New Khanki Barrage Project (NKBP) IEE Report
6‐1
6. PUBLIC CONSULTATION AND DISCLOSURE
This section describes the outcome of the public consultation sessions held with
different stakeholders/groups that may be impacted by the project. The consultation
process was carried out in accordance with the) Asian Development Bank’s Safe
Guard Policy Statement (ADB’SPS). The process of the public consultation
proceeded as follows: -
Meetings with regional and local officers of PID Government of Punjab.
Semi-structured interaction held with communities on old and new barrage sites
and around.
Public Hearing through EPA Punjab to get the maximum participating role for the
members of public. (To be done at the convenience of EPA Punjab after
submission of the drafts ESIA report).
6.1 CONSULTATION PROCESS
Information disclosure and public consultation and discussion with the people of the
area have been continuing since the project’s feasibility studies in 2005. This process
was intensified during the EIA studies, and separate rounds of public consultations were
held as part of the preparation of Land Acquisition Resettlement Action Plan (LARP).
Before and during the project execution, this process will be continued, particularly
during the implementation of the EMP and LARP and compensation initiative proposed
in LARP and a comprehensive communication strategy has been devised for this
purpose.
Surveys were carried out in order to investigate physical, biological and socio-economic
resources falling within the immediate area of influence of the project. Primary data
collection included:
Land demarcation, measurement and land record collection.
Pretesting of socioeconomic survey tools in the field.
Physical measurement of structures falling in the ROW.
The semi structured meeting with community representatives held on 2005, 2009 and
2011 in and around the project have the following objectives:-
:
Share information with stakeholders on New Khanki Barrage project and expected
impacts on aspects of affectees of the Project.
New Khanki Barrage Project (NKBP) IEE Report
6‐2
Understand stakeholders’ concerns regarding various aspects of the Project,
including the existing condition of the upgrading requirements, and the likely
impact of construction related activities and operation activities;
Provide an opportunity to the public to influence Project design in a positive
manner;
Obtain local and traditional knowledge, before decision making;
Increase public confidence about the proponent, reviewers and decision makers;
Reduce conflict through the early identification of controversial issues, and work
through them to find acceptable solutions;
Create a sense of ownership of the proposal in the mind of the stakeholders; and
Develop the proposals that are truly sustainable.
6.2 IDENTIFICATION OF STAKEHOLDERS
During the field survey, significant efforts were made to identify the possible categories
of stakeholders and their stakes. During the field survey different stakeholders identified
were the villagers, local residents, government officials, shop owners, public
representative, NGO’s and general public. All those stakeholders had different types of
stakes according to their professions.
Public consultations were carried out in two steps. The first step employed for the
consultations carried out during the Environmental and Social Assessment studies was
the identification and categorization of the stakeholders. Two types of the stakeholders
were identified: the primary stakeholders, who would be directly affected by the project;
and the secondary stakeholders, who would be indirectly affected by the project (or who
could indirectly affect the project).
Subsequent to the stakeholder identification, guidelines and questionnaires were
prepared for conducting the focus group discussions/meetings, which were arranged
through contacting the key persons from the community, such as, village heads, and
patwaris.
After completing the preparatory steps described above, the consultations were carried
out in the communities. During the ESIA study, stakeholder meetings and focus group
discussions were held in 10 villages nearby the Khanki barrage and around that of the
Newly construction L.C.C area, whereas for developing LARP, such meetings were
held in all of the 4 villages . To meaningfully include the women of the area in the
consultation process, separate focus group discussions were arranged both during the
ESIA and LARP studies.
New Khanki Barrage Project (NKBP) IEE Report
6‐3
The consultations with the secondary stakeholders were carried out in parallel to the
community meetings. These consultations were held with officials and representatives
of public and private departments/institutions, including IPD (PMO Barrages),
The consultation process during the EA studies and preparation of LARP comprised a
total of 771 participants. Table – 6.1 summarizes these meetings; the details are
provided in Annex A.
Table – 6.1: Summary of consultation meetings
Round Year Description Participants
First 2005 Meeting with local communities,
women of nearby villages and project
stakeholders.
70
Second Feb 2009 Meeting with APs, local population
and project stakeholders.
338
Third June 2011 Meeting with residents, APs,
women of the adjoining villages
and meeting with secondary
stake holders.
111
1.Public Hearing
2.Public Hearing
May 7, 2005
March 31,
2009
Public hearing meeting with residents
and Govt. officials of the different
departments
205
47
Total
771
6.3 CONSULTATION FINDINGS
Stakeholder Concerns
The major fears of the people of the project area included closure of L.C.C during the
construction of the barrage for about four years, and the associated crop losses;
reduction in number of fish at Khanki pond and downstream due to high level of
construction activity and noise level generated by new barrage; Loss of the freedom of
local women-folk in the area; possibility of spreading of HIV/AIDS due to labour
interaction with locals; chance to increase the accidents; Rise in the prices of
commodities in construction site and adjoining markets due to arrival of the additional
2000 labors and fear to have impact in the command area due to decrease in canal
capacity; short length of the studs may create problems and there are chances of
New Khanki Barrage Project (NKBP) IEE Report
6‐4
getting less price of land that would be acquired for the construction of the new L.C.C
and studs.
All of the above concerns and expectations have been adequately incorporated in the
project design in the form of the mitigation measures included in the Environmental
Management Plan and LARP and the communities were so informed during the
consultation meetings.
6.4 GENDER COMPONENT
A total of 40 women from the project area were interviewed by the female staff, as per
level of awareness on the project, most women were aware of the construction of
Barrage and Studs project. Table 6.2 indicates the social condition of women surveyed.
45% had access to school, 35% had to college level education and only 20% ladies had
access to university level education. This reveals that they were free in getting education
if they were willing and educational facilities were available in their surrounding areas.
On the other hand, 30% women had access to lady health visitor, 32% consult
government doctor, 25% consult private doctor and 20% consult quacks in case of
sickness/ailments.
Table - 6.2: Social Condition of Women in the project Area
Age
Group
Access to Education Access to Health Facility
School College University Nurse/
LHV
Govt.
Doctors
Private
Doctors uacks
16-25 9 2 3 2 3 3 2
26-35 4 5 2 3 5 3 1
36-45 3 3 1 4 2 2 1
46-55 2 3 2 2 1 1 2
55/above - 1 - 1 2 1 2
Total 18 14 8 12 13 10 8
% age 45 35 20 30 32 25 20
All the above points would be reflected in Social Framework Agreement (SFA)
between the local community and the PID and when the project is commissioned for
construction.
New Khanki Barrage Project (NKBP) IEE Report
6‐5
6.5 SOCIAL FRAMEWORK AGREEMENT
It is the commitment by the project proponent and the local community to work together
for the successful completion of the project. It establishes bindings for both parties to
minimize possible conflicts.
SFA shall be considered as a “follow up” of the public consultation and public hearing
and indicates that ID and the communities are mutually facilitating the construction
process of new Khanki Barrage.
Parties to Agreement
SFA will be signed through mutual open consent between the local village leaders and
the project proponent. At least two leaders/elders will be chosen from each of the
villages situated adjacent to the area where construction activity will be based. These
leaders/elders will constitute a villagers committee, which will choose a Chairman
among themselves.
SFA shall be signed by ID Resident Engineer (RE) representing the project proponent
and by the Chairman of villagers’ committee representing the local community before
two month start of the construction work.
Agreement Contents
SFA shall be prepared in the form of a legal agreement in Urdu language on a stamp
paper to be provided by RE at the project cost. Three copies of the agreement shall be
signed by both parties. All the mitigation measures described in EMP which are relevant
to SFA shall be included in the agreement. The obligations of the irrigation Department
and those of the community shall be listed clearly. Signed copies of SFA shall be kept
by both parties and the Executive Engineer in charge of the Barrage.
The suggested format of SFA is provided in Annex - B & Annex - C.
New Khanki Barrage Project (NKBP) IEE Report
7‐ 1
7. ENVIRONMENTAL IMPACT ASSESSMENT AND MITIGATION
MEASURES
This chapter categorizes the potential impacts of the construction of New Khanki
Barrage on the physical, biological and social environment of the project area.
7.1 METHODOLOGY
In order to assess the type and intensity of impacts of the project, a check list of
potential impacts was developed on basis of the literature review, field surveys,
investigations, and stakeholders consultations. The matrix charts the relations
between the project components, and the various aspects of the physical, biological
and social environment, and on the basis of this identifies the potential impacts
associated with each project activity. The check list also characterizes the impacts
with respect to their severity, in addition to determining whether the potential impact
can be avoided through better project design and planning, or mitigated with the help
of appropriate measures to be taken during the project execution.
The check list of potential impacts is presented in Table 7.1. The potential impacts
thus identified are discussed in the following sections.
7.2 IMPACT ASSESSMENT - OVERVIEW
The Initial Environmental Examination (IEE) study has disclosed that the project is
not likely to have any severe negative impacts on the environment and people of the
area. All the potential impacts which have been identified during the present
assessment are associated with the construction stage of the project, and mild to
moderate in severity; and can easily be avoided (through good design and
construction planning) or mitigated (through proper implementation of the EMP and
LARAP), as shown in Table 7.1.
On the other hand, the project will be beneficial; job opportunities particularly for the
local population during construction stage and extremely beneficial for agricultural
production once the construction of the new Khanki Barrage is complete. In addition,
the social assistance activities at the barrage will greatly enhance the project benefits
for the local communities. Significant social indicators of the project benefits are
mentioned below:
Improvement in infrastructure pertaining to the roads, bridge, communication
and other social amenities like natural gas;
New Khanki Barrage Project (NKBP) IEE Report
7‐ 2
Significant changes in sustainable development;
Permanent health care services;
Cross-river social and cultural linkages;
Improvement in educational facilities;
Assurance of better drinking water supply;
Enhancement in agricultural/livestock/fisheries produce.
Table - 7.1: Check list of potential impacts for Construction and Operational
Phases
Environmental Aspects
(Construction Phase)
Impact Categorization
Mild Moderate Severe
* ** *** * ** *** * ** ***
1. Land Resources
1.1 Borrow area for extraction of materials
from borrowing site.
1.2 Site for disposal of waste generation and
disposal of waste material
1.3 Location of labor camps, material camps,
equipment yards and approach roads
1.4 Access tracks
1.6
Land contamination due to spill of
lubricates, fuel, chemicals and other waste
materials.
1.7 Contamination from diesel and other spills
from construction machinery
1.8 Drainages paths roads crossed. Damages
by moving machinery
1.9 Installation of batching plants
1.10 Waste disposal Management
1.11 Agriculture land and crop Damage
1.12 Any discharge or diversion of water to a
graveyard or archaeological site
1.13 Electrical and mechanical works
1.14 Construction of L.C.C., regulator, bridge
and studs.
New Khanki Barrage Project (NKBP) IEE Report
7‐ 3
Environmental Aspects
(Construction Phase)
Impact Categorization
Mild Moderate Severe
* ** *** * ** *** * ** ***
2. Hydrology and Water Resources
2.1 Impact on source of construction water
2.2
Contamination of surface water due to
diesel and other fluids spilling over to river
water from machinery.
2.3 Protection of construction work from floods
2.4 Obstruction of flow of water down stream
2.5 Impact of dismantling of Old Khanki
Barrage.
3. Air Quality and Noise Pollution
3.1 Dust and smoke and other pollutants from
plants and equipments.
3.2 Dust or other pollutant from stored
materials and spoil heaps
3.3 Smoke from burning of waste materials or
burning fire wood
3.4 Noise control from use of old or outdated
machinery
4. Biological Resource
4.1 Damage to biological resource flora, fauna,
biota
4.2 Impact of construction and dismantling of
coffer dam on aquatic life
5. Socioeconomic and Cultural Issues
5.1 Existing services; education health,
electricity, and water supply
5.2 Tribal tensions and local rivalries on canals
and aquatic life
5.3 Land ownership and land acquisition
5.4 Access to other construction materials
5.5 Effects on sites of archeological, historical,
cultural or religious significance
New Khanki Barrage Project (NKBP) IEE Report
7‐ 4
Environmental Aspects
(Construction Phase)
Impact Categorization
Mild Moderate Severe
* ** *** * ** *** * ** ***
5.6 Public safety at construction sites
5.7 Health and safety of labor and employees
on construction site
5.8 Employment
5.9 HIV/AIDS and other communicable
diseases.
5.10 Aesthetic / scenic value
Key:
* Avoidable through design (Preventive)
** Mitigation through contractor’s obligation or through SFA
*** Non-reversible permanent change.
7.3 EXPLANATION OF THE IMPACT ASSESSMENT
Table 7.1 above provides a schematic presentation of the degree, significance and
mitigability of various environmental and social factors at construction and operational
phases. This section provides a brief explanation of each factor, also suggesting a line
of action towards mitigation measures for the adverse impacts.
7.3.1 Construction Phase
7.3.1.1 Land Resources
I. Site for disposal for waste construction material
There is hardly any cutting involved. Most of the work would require filling. There
would, therefore, shall not be much waste material for disposal or burial. If any
such material e.g. left over of the coffer dam, does need disposal, enough land
for that is available on either bank of the river. Most suitable spot is the
depression on other side of protection Bunds, where water is stagnating and is
becoming breeding place for injurious insects like malarious mosquitoes.
Dumping waste material in these ponds will achieve two purposes; dispose the
waste material as well as fill the pond and make the sites more health friendly.
This is a moderately significant but mitigable factor.
New Khanki Barrage Project (NKBP) IEE Report
7‐ 5
Mitigation
To be made contractor’s responsibility through contract document to dispose off
the construction waste material in the water filled depression on outer sides of
the protection bunds.
II. Location of Labour Camps, Material Depots, Equipment yards and
approach roads
Because of availability of ample area belonging to ID, location of labour camps,
material depots, equipment yards and approach roads will not cause any
serious problem. So this is a matter of slight significance and is easily mitigable
and manageable.
Mitigation
The contractor will, in consultation with RE, resolve the exact location of all
these facilities within the land of ID.
III. Contamination from Diesel and other oil spills from Construction
machinery
At places it may be inevitable and may exceed the maximum permissible limit.
In case it is allowed to be as rule rather than an exception, the dumping site will
be permanently damaged alongwith allied physical biological and social losses.
This is mitigable through effective application of the maximum spill regulations.
“Guide Lines for Oil Spill Waste Minimization and Management issued by
International Petroleum Industry Environmental Conservation Associate are as
follows:-
Soil contaminated by minor spills/leakages (defined as leaks from
vehicles, machinery, equipment or storage containers such that the area
and depth of soil contaminated is less than 10 sq ft and 3 inches
respectively) is to scraped and burnt in a burn pit.
Moderate spills defined as spills of volume less than or equal to 200
liters is to be contained and controlled using shovels, sands and native
soil. These equipments and materials are to be made available at camp
sites during the operation. The contaminated soil is to be excavated and
stored in a burn area lined with an impermeable base. Depending on the
volume, the contaminated soil is either disposed-off through by
New Khanki Barrage Project (NKBP) IEE Report
7‐ 6
specialized treatment such as bioremediation or through approved
contractor.
Major spills (defined as spills of volume much greater than 200 liters)
require initiation of Emergency Response Procedures and Oil Spill
Contingency Plan. These spills are to be handled and controlled
according to the Plan and require special treatment such as
bioremediation and through approved contractors.
Mitigation
Contractor’s contractual obligation to impose strict rules on his workers and
labour and ensures that no spill are caused. If it the spills, do take place, it must
be followed by he treatment prescribed above as per the degree of spill.
IV. Damage to, roads, cross drainages by machinery
Such a situation can arise through carelessness of the heavy machinery
drivers/operators. Such carelessness can cause considerable damage to paths,
roads and drainages if the drivers/operators are not made aware, trained and
bound to be careful. An effective sinology can reinforce the instructions to
drivers. It is a concern of moderate significance but is mitigable through care
and regulation.
Mitigation
Contractor’s contractual obligations to impose strict control over operators and
drivers of all types of vehicles. Should the damage take place, the contractor
must be bound to carry out repair immediately.
V. Earthen Embankments or Concrete work, Edge Scouring
Must be dealt at design stage. Wherever such a situation is anticipated, aprons
should be provided to secure edges and specifications must be kept of high
standards. Moderately significant but is a mitigable aspect.
Mitigation
Design stage and strict application of Operational Manual.
VI. Discharge from unstable slope or leakage on construction
Such an impact can destroy the structure leading to unprecedented damage.
Though significant, it can be set aside through a careful planning of the work. If
New Khanki Barrage Project (NKBP) IEE Report
7‐ 7
such a situation does appear, it becomes highly significant though a mitigable
impact.
Mitigation
Contractor’s contractual obligation to not to let such leakage develop. Should
such leakage develop, the contractor must remain fully prepared to immediately
control the discharge.
VII. Any discharge spill or dumping onto any building or houses on river bank
No such situation has been noticed during surveys. Should a situation present
itself during project implementation it will be a moderately significant but a
mitigable problem. Should a situation to such an effect present itself during
project implementation, the owner may be compensated by the contractor.
Mitigation
Contractor’s contractual obligation to compensate such losses.
VIII. Any discharge spill or dumping out to any graveyard or burial
No such situation has been noticed during surveys. Should a situation present
itself during project construction, it will be moderately significant but a mitigable
problem. Should a situation to such an effect, present itself it will be a
moderately significant but mitigable problem. The contractor shall be duty bound
to restore the protection wall of graveyard through appropriate rip-rap work or
pay damages to the community.
Mitigation
Contractor’s contractual obligation to compensate the community either by
getting the graveyard protection wall repaired and covered with rip rap work or
paying the community an amount as compensation with which the community
can get the repair done.
IX. Impact due to the Construction of Coffer Dam
Part of the river flow shall have to be closed behind a coffer dam, within which
the construction of barrage will proceed, while the river shall flow normally in the
remaining part of the river, as before till the completion of the new barrage.
New Khanki Barrage Project (NKBP) IEE Report
7‐ 8
Mitigation
A careful planning of the Coffer Dam an efficient manipulation of gates of old
barrage along with due adjustment of the LCC Headworks.
X. Material left behind after the Coffer Dam is not required
A huge quantity of material shall be used for construction of Coffer Dam during
construction. After the construction, if left behind, this material will disturb biota
as well as the normal flow of river. This will be a significant but a mitigable
impact.
Mitigation
Contractor’s contractual obligation to remove all waste material from the coffer
dam site and dump it safely as construction waste material.
XI. Impact of taking borrow material from earth borrow site
A large quantity of earth fill material will be obtained from the heaps of spoil
banks of the old L.C.C inundation canal and 500 acre land currently set aside for
afforestation situated on the right bank of the river . It is about 5 miles
downstream of the Barrage. Excavation and cutting activities could place
adverse environmental impacts including sliding, soil erosion and drainage on
the surrounding areas.
Mitigation
No private land is acquired for the borrow areas
The Contractor will ensure that selected borrow areas are clearly
demarcated including the allowed depth of the excavation before starting
excavation.
The borrow areas will be leveled. The Contractor will not leave the borrow
pits in such a condition that they are unsuitably filled with rain water and
cause the problem for the community.
If the borrow area is near to the settlements then it should be fenced
completely.
The borrow land on spoil bank of the old L.C.C will be propounded use as
borrowing area. If agriculture land needs to be used as borrowing area
then the Contractor will adopt the following methods during the digging
process.
New Khanki Barrage Project (NKBP) IEE Report
7‐ 9
o Fix the location of excavation.
o Remove thirty centimeters of the top soil and keep it on reserved site
for re-spreading in the field.
o Excavate up to one meter depth.
o Maintain the slope as far as possible.
o Place the top soil back during the restoration process.
o Pay compensation for any crop losses.
XII. Impact on roads used for transport of construction materials
Main roads on either side of the river to convey men and material to the
construction sites. This will cause additional wear and tear and raise
considerable dust. It will be a moderately significant but mitigable impact.
Mitigation
Contractor’s contractual obligation to use the roads and paths carefully and in
case of any damage, repair the damaged paths. On Kacha roads water shall be
sprinkled daily.
XIII. Impact of stone quarrying
Stones shall be procured from quarries in Sargodha district. This will not cause
any impact on the immediate project area except that the vehicles carrying the
stone shall exert additional traffic load on the roads leading to the project area.
By keeping the roads dust free and repaired, only a slight influence is expected
on the immediate project area.
Mitigation
Contractor’s contractual obligation to use the road network carefully and repair
any damages immediately.
7.3.1.2 Hydrology and Water Resources
I. Source of construction water
Ordinarily the river water is suitable for the construction work. If obtained from
elsewhere, it must be compensated.
Mitigation
Contractor’s contractual obligation to pay for water obtained from source other
than the river.
New Khanki Barrage Project (NKBP) IEE Report
7‐ 10
II. Source of surface water
Contractor’s labour will use river water, like other people living or working near
the river banks, for washing, bathing and at time for sewage. The contractor
may however, arrange to pump water from the river and supply running tap
water to his workers. Using some water from river by the contractor’s labour
shall cause only a slight but irreversible effect on the river. But if the contractor
can ensure a system of pit latrines or a set of temporary flush system latrines
with sink tanks in the land around the camp, the river water can stay free of
sewage of about 2000 persons. All sewerages to be treated through septic
tanks.
Mitigation
Contractor’s contractual obligation to supply running tap water, pit latrines/ flush
latrines with sink tanks in the land near the camp. It should be ensured that solid
and liquid waste of about 2000 persons does not fall into the river.
III. Source of drinking water
Communities along Chenab river banks are sufficiently advanced to install tube
wells and hand pumps for obtaining good quality drinking water. Similar
arrangements can be made by the contractor for his labour camps. Drawing
water for drinking from aquifer shall neither cause any significant change in the
under water reservoir, nor the river which recharges it. This impact can be
considered as slight. Surface water not being drinkable, the subsoil water should
be tapped.
Mitigation
The contractor should tap the underground reservoir and install hand pumps or
tube well with overhead tank to supply drinking water to the labour and workers.
The quality of drinking water should be monitored periodically.
IV. Diesel and other fluids spilling over the River from construction
machinery
Contamination from Diesel and other fluids spilling from construction machinery
over river waters, river bed or river banks, as per description of oil spills given
under land.
New Khanki Barrage Project (NKBP) IEE Report
7‐ 11
Mitigation
Contractor’s contractual obligation to not to let it happen. Should it cross the
permissible limits, ways and mean should be adapted to effectively control it
according to the standard specifications for limits on spills.
V. Protection of construction work from floods
A suitable flood warning system from Irrigation Department and full
arrangements to save the New Khanki Barrage from floods shall be in position.
Flood impact is of high significance and is mitigable.
Mitigation
Contractor’s contractual obligation to make fool proof arrangements in advance
to protect the on going construction works from floods, as per information
received from the I D.
VI. Obstruction of the flow of water downstream
Same as Cofferdam effect discussed under Land Resource. This impact is of
high significance and is mitigable.
Mitigation
A careful planning of the Coffer Dam and efficient manipulation of gates of old
barrage along with due adjustment of L.C.C. Headworks. River flow downstream
shall be facilitated by suitable arrangements agreed between the contractor and
the Resident Engineer.
VII. Effect of surface flow conditions
Must be addressed mainly at Design Stage. The impact is significant and
mitigable.
Mitigation
Design Engineer to accommodate this factor in the design so as to avoid
negative impacts. Contractor to follow the Design Specifications meticulously.
7.3.1.3 Air Quality and Noise Pollution
I. Dust and smoke and other pollutants from construction machinery
This impact is inevitable, moderately significant but mitigable.
New Khanki Barrage Project (NKBP) IEE Report
7‐ 12
Mitigation
Contractor’s contractual obligation to keep the dust and smoke low by using
machinery which is well maintenance and is almost noiseless. And all Kacha
roads and paths are sprinkled with water many times a day.
II. Dust or other pollutions from stored material
This is also inevitable, moderately significant and mitigable.
Mitigation
Contractor’s contractual obligation to keep the dust and smoke by carefully
storing and distributing the construction material so as to cause minimum dust
which again will be within the acceptable limits.
III. Smoke from burning of waste material or burning firewood
A large number of big and small fires in the labour camp can produce smoke
and smog which can cut off visibility, reduce trafficability and cause suffocation
alongwith causing diseases of the respiratory tract.
Mitigation
Contractor’s contractual obligation to use clean and smoke free fuel in the
labour camp. Cutting and burning trees/shrubs for fuel shall be prohibited.
Instead Gas Cylinders should be used in the labour camp for cooking purposes.
IV. Noise from use of old or outdated machinery
Old and poorly maintained machinery generates higher decibels of noise. If the
machinery is new and well maintained, its noise is far too less and is within
tolerable limits. Also noise controlling gadgets (ear plugs) can be used to cuts off
the noise for those who work in the close vicinity of heavy machinery.
Mitigation
Contractor’s contractual obligation to use new, well maintained and low noise
machinery preferably during day time. The drivers, operators and workers
working on or near the heavy machinery must be provided ear plugs.
V. Noise or sonar waves generated by pile driving or sheet piling
In case pile driving or sheet piling is done inside water, its sonar effect is far
stronger than that in the air. In this project no such impact is expected because
the construction will be done on dry area inside the Coffer dam. Other
construction noise will be slight and mitigable.
New Khanki Barrage Project (NKBP) IEE Report
7‐ 13
Mitigation
Contractor’s contractual obligation to restrict all the construction work strictly
within the bounds of coffer dam and not to allow any under water noise
producing activity.
VI. Noise due to blasting
Blasting may be used in demolishing of Old Khanki Barrage. But should it
become necessary to blow up some big rock or an embankment, it will generate
all time high shock waves and loud level of spot noise. It can adversely affect
the aquatic, terrestrial and aerial life by a sudden release of high level sound
and echo.
Mitigation
Contractor’s contractual obligation not to cause blasts as envisaged in project
design. But should it become necessary, it should be done with the permission
of Resident Engineer (RE) and all measure should be adapted so as to
minimize the impact of one time blast. All explosions must be performed under
specialist supervision.
VII. Soil Compaction due to labour camps, and machinery yards
The human and mechanical activity normally compacts the soil and turns it
nonproductive.
Mitigation
Contractor’s contractual obligation to mitigate the impact of compaction and
leave the site almost in the same state in which it is occupied. Pictures of the
area should be taken before handing it over to contactor which will help the RE
to ensure an acceptable state of soil while getting the area back from the
contractor.
7.3.1.4 Biological Resources
I. Damage to biological resources Flora, Fauna (Biota)
Since the level of pond will not rise or fall significantly and reservoir shore line
will not change, so no major change is expected in the habitat of the natural
flora or fauna. However in certain cases about 1000 Eucalyptus trees (Govt.
trees), and 54 woody & fruit trees (privately owned trees) may have to be cut to
excavate the new L.C.C and studs. Small readjustment of place may have to be
made by some birds and rodents.
New Khanki Barrage Project (NKBP) IEE Report
7‐ 14
Mitigation
Contractor’s obligation not to cause any additional destruction to Flora and
Fauna of the area by respecting the limits of construction site and not to enter
other territories. About 10,000 trees of different species will be replanted
according to the Tree Plantation plan. No unauthorized tree or bush cutting
should be allowed. Should it be necessary, it should not be done without an
express permission of the RE. If the number of trees is above a limit fixed by
RE, professional advice should be obtained from local Forest officer.
II. Damage to Fisheries
Like the old barrage, the new barrage will also be an obstruction for fish
migration which is necessary for flood, habitat and reproductive adjustments.
The Fish already under adverse pressure because of Marala Barrage upstream
and Qadirabad downstream. Presence of New Khanki Barrage will therefore be
yet another blockade, for fish migration.
Mitigation
while designing the new Khanki Barrage, fish ladders will be provided. And the
Contractor shall, as a contractual obligation, use the best available technology
to construct the fish ladder.
III. Impact on adjustment Bela lands
On both sides of Chenab River at the site of the new barrage there are alluvial
lands still under the influence of river water. These lands support a succession
of vegetation culminating in a climax species shisham (Dulbergia sissoo) tree.
Since the level of water in the pond area behind the barrage is not likely to
change, the alluvial lands popularly called the “Belas” or “Zakheeras”) shall only
experience a slight influence in that water spill to these area may improve.
Mitigation
No negative impact is anticipated. To ward off against any adverse effect it shall
be joint responsibility of the contractor and the RE to ensure that at no stage of
construction the level of the pond area rises above the present level.
IV. Impact on migratory birds
Chenab River at the point of the project does not fall on the recognized route of
globally recognized migratory water fowl or ducks. However a number of
New Khanki Barrage Project (NKBP) IEE Report
7‐ 15
migratory birds do pass this way and stay for wintering in the barrage area.
Since the water: land ratio is not going to change, there shall be no or slight
influence of the new barrage on the temporary habitat of the migratory water
birds.
Mitigation
Contractor’s contractual responsibility to facilities a regular inspection by the
Wildlife Department to ensure that the process of construction does not cause
any hindrance to the migratory birds.
7.3.1.5 Socioeconomic, Cultural and Archaeological Issues
The socioeconomic cultural and archaeological impacts can be:-
I. Disturbance to existing services: education, health, electricity, water supply or
signboards.
II. Aggravation of any disputes on land ownership.
III. Aggravation of any tribal tensions and local rivalries on disputes on canal
water on aquatic life.
IV. Any need for land acquisition.
V. Access to other construction materials.
VI. Adverse effects on known archaeological sites.
VII. Chance finds
VIII. Dealing with chance finds.
IX. Dealing with graveyards or burials.
X. Problems to Health and Safety of labour and employees on construction work
and provision of safety equipment to workers on site.
XI. Employment of locals on the project.
XII. Possibility of spread of HIV/AIDS amongst the project labour and adjoining
population.
XIII. Rise in prices of essential commodities.
XIV. Social reunion over the new bridge.
XV. Gender Issues.
XVI. Recreational facilities for public.
XVII. Any spots of religious significance e.g. Mosques, Tombs and Shrines etc.
Mitigation
1. For matters pertaining to social obligation and benefits of the communities, a
social Framework Agreement shall be signed by the RE with communities to
New Khanki Barrage Project (NKBP) IEE Report
7‐ 16
ensure their participation and full satisfaction in matters pertaining to them. SFA
shall be singed when RE is in position and the construction work is about to
start.
2. All matters where contractor is involved, these should be made as his
contractual obligations.
7.3.2 Operational and Management Phase
At operational phase the Project Manager shall develop a comprehensive operational
and Management Manual and an effective monitoring plan. Mistakes at operational
level or handling of operations by untrained staff can prove very risky and costly.
Important points to be attended at operational stage are as follows: -
Comprehensive O&M Rules as per ISO standards
Strict application of prescribed M&E plan
Continuous evaluation of design efficiencies
Understanding and training of Operational and Maintenance Manual
Annual Environmental Audit.
Regular maintenance of engineering works (mechanical as well as civil).
Staff Welfare
Continued Public consultation and feed back on that
Continued attention towards Gender issues and women consultation
LCC system to run upto its design capacity and not beyond
Refresher Training Courses for operational staff
7.3.3 Socio-economic Impacts on the overall Project Area
In ultimate analysis the impacts of project on social and economic activities in the
Project area will be mostly positive. Salient economic benefits of the project are: -
Boost to agriculture through ensured and enhanced irrigation water by way of
conveying water to tails, in LCC system command area.
Increased economic activity with improved transport will ensure easy
marketing of agriculture produce.
New Khanki Barrage Project (NKBP) IEE Report
7‐ 17
With improved economy, there shall be further improvement in service area
and opportunities for employment, education, healthcare, especially for
women and children, shall improve.
Possible stimulus to other diversified economic development such as Tourism
development programmes, shall be generated
Employment during construction phase shall employ and train a large number
of unemployed youth. They will receive a life time benefit through skill
training, capacity building and poverty alleviation. A large number of semi and
unskilled workers in the project area will be hired.
Greater awareness about Health care including HIV/AIDS amongst the labour
and the close by community shall be created.
At micro-level the hustle and bustle of economic activities may bring the cost
of living down by making essential commodities available at cheaper rates.
This combined with higher incidence of employment will bring the poverty line
and crime rate much lower.
However salient adverse impacts shall be: -
The only adverse impact of the project is the acquisition of private land and tree
cutting which will be handled by implementation of the LARAP and EMP properly and
well in time.
New Khanki Barrage Project (NKBP) IEE Report
8‐1
8. ENVIRONMENTAL MANAGEMENT PLAN (EMP)
8.1 INTRODUCTION
This document provides an overall approach for managing and monitoring
environment and social related issues and describes the institutional framework and
resource allocations proposed by the Punjab Irrigation Department to implement the
Environmental Management Plan (EMP) for the New Khanki Barrage project (NKBP).
During the EIA process mitigation measures have been identified to minimize the
adverse environmental impacts of the project and keep it within acceptable limits.
The Environmental Management Plan (EMP) has been developed to effectively
implement the monitoring and mitigation measures identified in the EIA. ADB places
strong emphasis on the preparation of EMPs during project processing and on
setting out conditions and targets to be met during project implementation. The EMP
has been prepared in conformity with Asian Development Bank’s Safe Guard Policy
Statement (2009).
8.1.1 Objective of Environmental Management Plan
An Environmental Management Plan provides a mechanism to address the adverse
environmental impact of a project during its construction, to accelerate project
benefits, and to introduce standards of good practice to be adopted for all project
works.
The objectives of the EMP are to:
Define the responsibilities of the project proponents, contractors, construction,
supervision consultants and environmental monitors;
Facilitate the implementation of the mitigation measures identified in the EIA;
Define a monitoring mechanism and identify monitoring parameters;
Provide a procedure for timely action in the face of unanticipated
environmental situation; and
Identify training, requirements at various levels.
New Khanki Barrage Project (NKBP) IEE Report
8‐2
8.1.2 Regulatory Requirements and Applicable Standards
8.1.2.1 National Regulatory Requirements
General
This section provides an overview of the policy framework and national legislation
that applies to the proposed Project. The Project is expected to comply with all
national legislations besides Asian Development Bank’s Safe Guard Policy
Statement (2009).
The EIA has been conducted in pursuance to all relevant Policies, laws and
guidelines. These include primarily Pakistan Environmental Protection Act 1997.
Pakistan IEE and EIA review regulations (2000), Safe Guard Policy Statement 2009.
Synopses of relevant laws and guidelines are provided in this section.
The key regulatory requirements, in the context of environmental protection,
applicable to the project under Pakistan legislation are listed in Table-8.1
Table-8.1: Applicable Regulatory Requirements (Environmental)
Instrument Requirement Action
Environmental
Protection Act of
Pakistan, 1997
Makes it mandatory for the
project proponents to carry
out an environmental
impact assessment and
incorporate environmental
and social mitigation actions
as part of the project
planning.
An EIA meets the regulatory
requirements was prepared by the
consultants and submitted to the
Pakistan Environmental Protection
Agency (PEPA) on 2009 & 2011.
Makes it illegal to discharge
any effluent or emission in
violation of the National
Environmental Quality
Standards (NEQS).
The design specifications of the
project ensure that the relevant
components will meet this
requirement.
Land Acquisition Act,
1984
Makes it mandatory that
any land acquisition by the
government should follow
the process laid out in the
act for fairness and
The process of land acquisition and
compensation will be governed by the
Land Acquisition Act 1894 between
the government and the private land
owner.
New Khanki Barrage Project (NKBP) IEE Report
8‐3
transparency. The resettlement Action Plan will be
prepared and implemented well
before the start of the construction
work. The preparation of the RAP is
under process.
Sindh Wildlife
Protection,
Ordinances Sindh,
1972
Makes it illegal to undertake
any project activity inside a
protected area (national
part, wildlife sanctuary, or
game reserve).
There is no protected area near the
New Khanki Barrage Project (NKBP).
Antiquities Act, 1975 Makes it illegal to undertake
any construction work within
200 ft. (60 m) of a building,
site or monument protected
under the Act.
No project activity has been planned
within 60 m of a protected site.
Construction of the structures will be
limited within the river bed. During
construction, the Contractors will
ensure that the prescribed distance is
maintained from the sites in the
proximity of the construction site. Not
disturbed.
Requires that the
Department of Archaeology
and Museum, Government
of Pakistan should be
informed if any
archaeological artifact is
found during excavation.
The Contractor will be required to stop
work if any archaeological artifact is
found during construction. The
Department of Archaeology and
Museum, Government of Pakistan will
be contacted for further action.
8.1.2.2 ADB Procedures
Requirements on Sector Loan Project
In compliance with the ADB Environmental Assessment Guidelines (Manila, 2003),
the environmental assessment of sector impacts is required to ensure the cumulative
impacts of all the known or unknown subprojects are assessed prior to loan approval.
A sector EIA report has been prepared for the Project, which undertake an
assessment of total impact of all subprojects to be financed.
New Khanki Barrage Project (NKBP) IEE Report
8‐4
The second challenge for the environmental assessment and review of sector loans
is to provide an efficient mechanism for environmental assessment of each
subproject. If an environmental assessment is undertaken at the sector level, it
should be possible to streamline the environmental assessment of individual
subprojects. ADB's requirements for IEE/EIA of sample subprojects are also
important. The specific results of the sample IEE/EIAs are very useful in determining
the appropriate level of environmental assessment requires for all subprojects to be
financed under the loan.
Environmental Assessment Requirements
The Environmental Assessment is carried & prepared as per the recommended ADB
format. ADB requires the EIA for Category A and IEE for Category B Sensitive
projects, once prepared, reviewed, accepted and cleared by the ADB staff, and
relevant regulatory agencies, be fully disclosed to the public worldwide as well as to
the local communities 120 days prior to the Board of Director meeting for review and
approval of the projects. All public concerns, queries, comments and objections
received within this period should be appropriately and satisfactorily addressed,
responded or resolved prior to the Board meeting for final loan approval.
8.1.2.3 Status of Regulatory Clearances
An EIA was submitted by the PMO to the Pak-EPA on November, 2004.The Pak-
EPA reviewed the environmental and social documentation to determine the scope
and locations of the hearing(s).
According to the regulatory requirements, The EPA has to hold mandatory public
hearings for the project and publish a mandatory 30-day Notice for Public Hearing in
the national/local papers prior to providing the environmental clearance.
As per requirement for NOC of EIA given in the EIA of Khanki Barrage Construction
Project, Public Hearing was conducted under section 12 of Environmental Protection
Act, at canal rest house Kalabagh Headwork’s on February 26, 2005. After the
successful public hearing, the EPA issued the NOC on dated July 5, 2005. After
revalidation the EPA again issued the NOC on dated 2009. EIA has been submitted
to EPA to enhance the validity of NOC till 2014.
8.1.3 Components of the EMP
The EMP has the following components.
Organizational structure; roles and responsibilities
New Khanki Barrage Project (NKBP) IEE Report
8‐5
Mitigation Plan
Environmental monitoring plan
Emergency response and contingency plan
Communication and documentation
Change management
Environmental training
Capacity development
Waste Water Management
Waste disposal plan
Restoration and Rehabilitation
The above mentioned components will be followed in the construction of new Khanki
Barrage. These components, as per requirements will be incorporated into various
contract documents and agreements needed for the implementation of the project.
The components include brief description of the environmental aspects of the project
activities, listing of mitigation measures, reporting on types of non-compliance with
respect to EIA or Environmental Management Plan (EMP) and EPA conditions of
approval expected during implementation of the project, checklists for identification of
non-compliances and format for environmental issues tracking report.
8.2. ORGANIZATIONAL STRUCTURE AND RESPONSIBILITIES
This section provides institutional arrangements for environmental management
during the proposed activity and defines the roles and responsibility of the various
Organizations/departments.
8.2.1 Management Approach
The responsibilities of different organizations/departments are summarized below:
8.2.2 Project Management Office (PMO)
The overall responsibility for the implementation of Environmental Management Plan
rests with the Head PMO of the Project Management Office (PMO) along with the
assistance of Environmental Sociology Unit (ESU) of PMO. The ESU consists of
Director Environment/Social, Deputy Director Environment, Deputy Director
Sociology, Deputy Director Resettlement/Development Assistance and Deputy
Director Communication. The Director Environment & Social and Deputy Director
New Khanki Barrage Project (NKBP) IEE Report
8‐6
Communication are not yet appointed but in near future they will be selected through
proper recruitment procedure.
PMO will ensure that contractor and supervision consultants appoint a
dedicated environmental officer and allied staff. PMO will also ensure that all
environmental personnel are authorized to implement the environmental &
social policies and requirements of the EMP.
ESU will also coordinate with relevant government departments and
stakeholders on concerned environmental & social issues.
ESU will inspect and monitor residual impacts of the project and record
documentation of the impacts during the project.
ESU will also inspect the significance of impact in case of unanticipated change
in the project.
Any major change in the project shall be reported to ADB before its execution.
8.2.3 Contractor
The contractor responsible for execution of construction activities will be responsible
for environmental protection through his/her environmental field staff. The contractor
is subject to environmental protection liabilities under environmental laws of the
country, project EIA/EMP provisions and under their contract with Irrigation
Department (ID). The contractor shall also be responsible for communicating
environmental & social information and training of staff in all aspects of the EMP.
8.2.4 Construction Supervision Consultants
Construction supervision consultants will hire an environmental monitoring and
evaluation specialist to monitor the environmental performance of the contractor and
the environmental impacts of the project activities.
PMO will ensure that consultant’s team has an unhindered access to all
relevant documents, persons and places to enable it to perform function
smoothly.
This environmental monitoring and evaluation specialist will prepare daily,
monthly, quarterly, annually and final reports for submission to PMO.
8.2.5 Organizational Structure
The organizational structure of the Project Management Office for the construction of
New Khanki Barrage Project (NKBP) is shown below in Fig- 8.1.
New Khanki Barrage Project (NKBP) IEE Report
8‐7
The organization chart for Environment Management/ Monitoring implementation is
shown below in Fig-8.2
New Khanki Barrage Project (NKBP) IEE Report
8‐8
Fig - 8.1: Organization structure of PMO
PROJECT ORGANIZATION
Head PMO / Project Director
DirectorFinance
Procurement Unit
EngineeringUnit
Dy. Director
Proc.(Jinnah)
Finance Unit
Director Procurement & Contract Admin.
Dy. Director
M & E
DirectorMechanical
Design Engr.
(Jinnah)
Dy. DirectorElectrical
SystemAnalyst
Director Social &Environment
Dy. Director Sociology(Jinnah)
Dy. Director
Dev. Asst. /Restt
Dy. Director Comm
Social &Environmental
Unit
Dy. DirectorClaims
ProgrammeCoordinator
Barrages Review CellP & D Department
Dy. Programme Coordinator
Barrages Review CellP & D Department
Barrages Review Cell (Working under Member Infrastructure Development in P&D Deptt.)
Dy. Director Contracts
AcctsOfficer
(Jinnah)
ManagerAdmin
Dy. Director Finance(Jinnah)
QAC Engr.
(Jinnah)
DirectorTechnical / Dy.Project Director
(Jinnah)
Dy. Director
Technical(Jinnah)
Asst. Director Electrical(Jinnah)
Dy. Director
Env
SeniorMechanical
Engr.(Khanki)
Asst. Director Mech.
(Jinnah)
Asst. Director
M & E
Design Engr.
(Khanki)
MaterialEngr.
(Khanki)
DirectorTechnical / Dy.Project Director
(Khanki)
Dy. Director
Technical(Khanki)
ElectricalEngr.
(Khanki)
Dy. DirectorMech.
(Jinnah)
Dy. Director Contract(Khanki)
Posts for Khanki Barrage Unit.
Mechanical Engr.
(Khanki)
Resettlement Specialist(Khanki)
AcctsOfficer
(Khanki)
New Khanki Barrage Project (NKBP) IEE Report
8‐9
Fig – 8.2: Organization Chart for Environment Management / monitoring implementation
Secretary to Government of Punjab Irrigation and Power Department
Head Project Management Office
Contractor Construction Supervision Consultants
Environment Unit
Environment Officer / Team Environment
Specialist
Deputy Director Sociology
Deputy Director Environment
Director Environment/Social
Deputy Director Communication
Deputy Director Resettle. /Develop. Assistance
New Khanki Barrage Project (NKBP) IEE Report
8‐10
8.3. IMPACT ASSESSMENT AND MITIGATION PLAN
This section outlines the potential impact of construction works on the physical,
biological, and socioeconomic environment of New Khanki Barrage. It also provides a
corresponding mitigation plan that focuses on countering the project’s adverse
environmental effects, and assigns responsibility for implementing these measures.
8.3.1 Corridor of Impact
All construction activities will remain confined within the river. However, Situations in
which construction works will extend beyond the existing include:
Establishing construction campsites and batching plant
Borrowing soil material from temporarily acquired land
Construction and dismantling of Coffer Dam
Quarrying aggregate material
Constructing haul tracks in order to transport construction material, etc.
Construction of new L.C.C and Head regulator.
Construction of new Khanki Barrage located 900 feet downstream of the
existing barrage;
Dismantling of Old Weir
Tree Cutting
8.3.2 Mitigation Plan
The mitigation plan is a key component of EMP. This section outlines the potential
impact of construction works on the physical, biological, and socioeconomic
environment and their associated mitigation measures as already identified in EIA
report of the construction of new Khanki Barrage. It also assigns responsibility for
implementing these measures. Now the guidelines for the implementation of
mitigation plan indicated in EIA of Khanki Barrage will cover:
Lists of only those mitigation measures which will be directly covered by the
environmentalist and not those mitigation measures which are covered under
civil or mechanical work.
The person(s) responsible for ensuring the implementation of the measures
The parameters to be monitored for the effective implementation of measures
A time scale for the implementation of measures to ensure that the objectives of
mitigation plan are fully met
The Environmental Impact Mitigation Plan for the activities likely to have a direct
impact on the environment is presented in Table – 8.2.
New Khanki Barrage Project (NKBP) IEE Report
8‐11
8.3.3 Social Development Assistance
Assistance in Infrastructure Development
In addition to construction of new Khanki Barrage, the following development works
will also be carried out in the project area, to further enhance the project benefits for
the local communities:
1. Rehabilitation/construction of mosque at the Barrage.
2. Development of a public park at the Barrage (left-bank, upstream).
3. Establishment of a Basic Health Unit at the Barrage Colony.
4. Rehabilitation and up gradation of Government Girls Primary School at the
Canal Colony.
5. Rehabilitation and up-gradation of Government Boys Primary School at the
Canal Colony.
6. Provision of Natural Gas to the Irrigation Colony
7. Provision of a telephone exchange (200 lines)
8. Rehabilitation/Reconstruction of approach road to the Irrigation Colony
The above works, implemented by PMO, are not likely to cause any significant
environmental or social impacts, nor any cumulative impacts, in view of their nature
and small scale.
New Khanki Barrage Project (NKBP) IEE Report
8‐12
TABLE – 8.2 ENVIRONMENTAL IMPACT MITIGATION PLAN
Sr. # Component Description Impacts Mitigation Measures / Actions
1.
Borrow area for extraction of earthen material. Construction and dismantling of coffer dams
Borrow Material: Soil excavation from the designated area of the site will be required for the construction of coffer dams. The borrowing areas identified are PID’s land, mostly waste land and are spoil banks of old L.C.C.. Construction of coffer dam will be limited within the river bed. The area belongs to irrigation Department.
Soil erosion; Loss of fertile soil; Decrease land productivity; obstruction in natural drainage; dust pollution; Damage to aquatic life
1.1 Ensure that photograph are taken of borrow area before start of the excavation.
1.2 The contractor has to extract the material from the specified and demarcated borrow areas only.
1.3 Ensure that contractor obligation define in contract document and SFA are followed
1.4 No agricultural land will be used as a borrow area. 1.5 If agricultural land is used as borrowing area then the land will be removed
/restored by the contractor and follow the following steps i. Excavation of borrow areas is as per instructions of the Supervision
Consultant’s environmentalist. ii. Remove first 15cm top soil and keep it on site to re-spread after
completion of the excavation. iii. Excavation of the earth fill be limited to an approximate depth of 90cm as
compared to adjacent leveled fields. iv. Stabilized the slope during the excavation. v. Top soil has been spread back during restoration process.
1.6 Contractor to get the approval from ESS before start of the construction and
dismantling of the coffer dams. 1.7 Ensure that the surface drainage is provided to control the surface run off
during rainy season. 1.8 Ensure that the movement of excavating machinery and vehicles is limited to
the work area. 1.9 Ensure that regular water sprinkling carry out during executing of excavation
to mitigate the dust pollution. 1.10 Ensure that erosion protection measures are taken, such as retaining wall and
avoidance of steep cuts. 1.11 Detailed checklist for Management and Monitoring of Borrow area will be
established 1.12 Ensure that the Borrow areas are levelled and top soil restored. 1.13 Ensure the dismantling of coffer dam may be done in a way to minimize the
water turbidity.
New Khanki Barrage Project (NKBP) IEE Report
8‐13
Sr. # Component Description Impacts Mitigation Measures / Actions
2.
Waste generation and disposal
It has generally been observed that at completion of construction the waste material is dumped at the site without proper planning. The material from the coffer dams will be in significant quantity and will require proper disposal site.
Soil and water contamination; obstruction in natural drainage; obstruction of community paths; aesthetic problem
2.1 Ensure that the site selected for waste disposal is demarked before starting the work (waste could be disposed on: (1) left bank downstream of the barrage adjacent to the Govt. employ colony near the road).
2.2 Ensure the colony must be shifted to new place before start of the construction of the new Khanki Barrage.
2.3 Ensure that all the waste generated from different locations must be disposed off according to the Waste Disposal Plan.
2.4 Ensure that photographs of selected area are taken prior to and after the waste disposal.
2.5 Ensure that all trucks used for the transportation of waste construction material will be airtight and watertight.
2.6 Ensure that Contractor obligations defined in contract document and Social Framework Agreement (SFA) are followed.
2.7 Ensure that the movement of waste lifting machinery and vehicles is limited to the work area.
2.8 Ensure that waste material is properly disposed off in a manner that does not affect the natural drainage.
2.9 Ensure that the dumping area has been levelled properly after disposal of waste material.
2.10 Ensure that: material suitable for recycling stored separately in three bin system and sold; the combustible waste burnt at burn pit only; non-combustible, non-recyclable garbage sent to the designated landfill site in an area; medical waste if any transported to any hospital incineration plant; solid residue from the septic tanks transported to municipal sewage facilities at Wazirabad and District Gujranwala; and the contaminated soil sent to burn pit or landfill. Minimize smoke emissions from the burn pit by managing the quantity of waste to be burnt at one time.
2.11 Ensure that construction of burn pit must be quite away from the labour camp and work area. The Medical & other hazardous will not be disposed off in the burn pit.
New Khanki Barrage Project (NKBP) IEE Report
8‐14
Sr. # Component Description Impacts Mitigation Measures / Actions
3 4
Relocation of camps, material and special approaches routes and roads Dust, smoke and other potential pollutants from construction machinery
If, happen contractor obligations are defined as per SFA agreement and contract documents A lot of machinery consisting of bulldozers, dumpers generators and vehicles will be used during the construction phase. This construction machinery will generate lot of dust, smoke and other potential pollutants in the air. Using strict standards for maintenance of construction’s machinery and sprinkling of water can be minimized
contamination of soil and water; soil erosion; resource consumption ; Change in land use and land form; Ambient air quality ; Health hazards; Ecstatic values
3.1 Ensured that the contractor change the location of all things mentioned under heading “component’ according to the obligations defined in the EIA and SFA.
3.2 Ensured that new locations for camps, material and assess roads are environmentally friendly and socially acceptable.
3.3 Ensured that no private land is acquired for new location for amenities. 4.1 Ensure that all equipment, generator and vehicles used during the project are
properly tuned and maintained in good working condition, in order to minimize the exhaust emissions
4.2 Ensure that dust emissions due to vehicular traffic are minimized by reduced speed, vehicular traffic minimized through good journey management and water sprinkling when required.
4.3 Ensure that dust emissions at the construction sites are minimized by implementing good housekeeping and sound management practices.
4.4 Ensure that strict standard for maintenance of construction machinery should be observed by the contractor.
New Khanki Barrage Project (NKBP) IEE Report
8‐15
Sr. # Component Description Impacts Mitigation Measures / Actions
5
Establishment and operation of labor camps, material and equipment yards and approach roads.
There is ample PID land available around the project area for the contractor’s camp and work shop. So no private land will be acquired for the construction of these facilities.
Change in land use and land form; contamination of soil and water; soil erosion; resource consumption; Additional load on local facilities/utilities such as schools, hospitals, electricity and water supply.
5.1 Ensure that the sites for camps and other site facilities are approved by the supervision consultants/PMO, and no private land is used for this purpose.
5.2 No involuntary land acquisition will be carried out (otherwise, a Resettlement Action Plan (RAP) will be prepared).
5.3 Photographic record to be maintained to record the baseline condition before establishing the caps/other facilities.
5.4 Ensure that camp size is as per standard specifications. 5.5 Ensue that washing areas are demarcated and water from washing areas and
kitchen is released in sumps. 5.6 Ensure septic tanks of appropriate design have been used for sewage
treatment and outlets are released into soak pit after being monitored through a certified laboratory..
5.7 Ensure that the outlets released into sumps must not make a pond of stagnant water.
5.8 Ensure that septic tanks and soak pits are the engineered design. 5.9 Ensure that sumps are in absorbent soil, down slope and away from the
camp, downstream from the camp water source and above the high watermark of any nearby water body.
5.10 Ensure that effective drainage is in place at the site. 5.11 Contractor to make assessment of existing sewerage and drainage system in
the barrage colony and carry out renovation / expansion works in consultation with PID.
5.12 In case of emergency spills, standard operating procedures should be developed and followed.
5.13 Fuel wood will not be used in the camp or in the field. 5.14 Fuel and water consumptions will be recorded. 5.15 Contractor to ensure that the local facilities/utilities are used in a manner not
to negatively affect the local communities/existing consumers. 5.16 Ensure that temporary wall or fencing is constructed/ fixed along the road
near the settlement in the vicinity of labour camp and batching plant.
New Khanki Barrage Project (NKBP) IEE Report
8‐16
Sr. # Component Description Impacts Mitigation Measures / Actions
6. Construction of new Access Roads and rehabilitation of Existing Roads
New roads may require providing the access to the contractor’s facilities i.e. batching plant, material yard, labour camp etc. There is ample PID land available on site for these facilities therefore no private land acquisition requires for these facilities. For the rehabilitation/widening of existing roads; no land acquisition is required. The general mobility of both local and residents and their livestock as well as the operators of residence business and their clientele in and around the construction area is likely to be hindered. Unchecked speeding may cause human and livestock injuries and fatalities as a result of highway accidents.
Soil erosion; Blockage of natural drainage; dust emission; Hindrance in movement; loss of natural vegetation; Loss of trees safety hazard for communities; Damage to public infrastructure; cumulative impacts of Project.
6.1 The moving machinery should remain within the project boundary. 6.2 All sections of the access tracks that are prone to dust emission and where
sensitive receptor are located within 500 m should be identified and marked on the map of the project area.
6.3 Ensure that the access tracks which are prone to dust emissions and marked on the map should be maintained by water spraying daily.
6.4 After completion of construction work all the damaged roads / tracks will be restored by the Contractor, as it is included in Contractor’s obligations defined in contract document.
6.5 Ensure that gravel is dumped only on locations allowed by ESS and dumping of gravel does not result in blocking of traffic or damaging vegetation.
6.6 Ensure that construction corridors along the access roads are marked on map.
6.7 Ensure that the access roads do not block the natural drainage and culverts are constructed where necessary.
6.8 Ensure that surface run-off controls are installed and maintained so as to minimize erosion.
6.9 Ensure adherence to the speed limit of 40 km/hr at the access roads. 6.10 Ensure that the access roads does not block the natural drainage and culverts
are constructed where necessary 6.11 Ensure that vegetation clearing is minimized and no trees are felled without
prior permission of ESS. Compensatory tree plantation will be carried out if any trees are felled. If the cutting of more than 100 trees at one place is involved, then the Contractor will consult Forest/Wildlife Departments prior to cutting of these trees.
6.12 Ensure that the alternative route is designed on the basis of the traffic survey conducted by the contractor.
6.13 Ensured that contractor does the tree plantation along both sides of the road according to the tree plantation plan.
New Khanki Barrage Project (NKBP) IEE Report
8‐17
Sr. # Component Description Impacts Mitigation Measures / Actions
7 Dismantling of Old existing Headworks.
The old Khanki weir will be dismantled soon after the commissioning of New Khanki Barrage and that for doing this the contractor will adopt a technology acceptable to the Project Management. A special Dismantling Plan formulated by the contractor under the guidance and supervision of ESU & Environments/Social Experts of the SC will, in fact, ensure the solution of related problems, viz. noise pollution during dismantling of the huge steel and stone structure, debris transportation
Blockage of road traffic; disruption of works at the other project sites; safety hazards Dust Pollution; Noise emission Damage to aquatic life. cumulative impacts of the two projects
7.1 All the structure above same elevation (714.00) will be removed in the fourth year of construction after completing the construction of new barrage.
7.2 The Contractor will be responsible for preparation and seeking approval of the Traffic Management Plan at least one month prior to start of dismantling work.
7.3 Ensure that contractor prepared the dismantling and disposal plan and got approval from the ESS of Consultant before start of the work.
7.4 Ensure that no blasting material will be used for the dismantling of the old Headworks.
7.5 Ensure that dismantled material i.e. debris of concrete and stone masonry will be disposed of in depression located on the left side down stream of the barrage.
7.6 Ensure that dust emissions due to vehicular traffic are minimized by reduced speed, vehicular traffic minimized through good traffic management and water sprinkling when required.
7.7 Contractor obligation is to use appropriate and fit machinery keeping noise levels & emissions are within NEQS.
7.8 Ensure periodic monitoring to verify the above (7.7). 7.9 The dismantling of barrage may be done in a way to minimize the water
turbidity.
New Khanki Barrage Project (NKBP) IEE Report
8‐18
Sr. # Component Description Impacts Mitigation Measures / Actions
8 Construction of new L.C.C., Head Regulator, High level channel and bridge.
The new L.C.C Head regulator will be constructed just above the new Khanki barrage in the new pond area to pass the flow in the canal. The bridge over the new LCC head regulator will be built to pass the traffic.
Blockage of road Traffic; Blockage of natural drainage; Dust Pollution; Hindrance in movement; loss of natural vegetation and trees; Loss of land and crops; Noise emission
8.1 The Contractor shall be responsible for preparation and seeking approval of the Traffic Management Plan at least one month prior to start of construction work
8.2 Ensure that gravel is dumped only on locations allowed by ESS and dumping of gravel does not result in blocking of natural drainage or damaging vegetation.
8.3 Ensure that dust emissions due to vehicular traffic are minimized by reduced speed, vehicular traffic minimized through good traffic management and water sprinkling when required.
8.4 Ensure that the alternative route is designed on the basis of the traffic survey conducted by the contractor
8.5 Ensure that the owner of the private land is fully compensated through proper implementation of the RAP and the RAP implementation must be done before the execution of the project.
8.6 Contractor obligation is to use appropriate and fit machinery keeping noise levels within NEQS.
8.7 Ensure that vegetation clearing is minimized and no trees are felled without prior permission of ESS. Compensatory tree plantation will be carried out if any trees are felled. If the cutting of more than 100 trees at one place is involved, then the Contractor will consult Forest/Wildlife Departments prior to cutting of these trees.
8.8 Ensure that implementation of the tree plantation plan must be done during the construction period of the project.
8.9 Ensure that the contractor will keep monitoring and maintenance of the planted tree during his period of contract.
8.10 Ensure documentation/record of planted trees.
New Khanki Barrage Project (NKBP) IEE Report
8‐19
Sr. # Component Description Impacts Mitigation Measures / Actions
9 Construction activities; handling of fuels, lubricants and chemicals
The construction machinery includes cranes, trucks, loaders/ dumber and batching plants will be used during the construction period. There are chances of contaminating of the land due to release of contaminated effluents, accidental spill, leaks, run of from the material storage yard etc.
Soil and water contamination; safety hazard; damage to crops; air contamination; noise emissions; damage to natural vegetation, habitat and wildlife
9.1 Ensure that the maintenance of vehicle and other equipment takes place only in designated areas underlined with concrete slabs and a system to collect runoff in to safe containers.
9.2 Ensure that no contaminated effluent is released in to the environment. 9.3 Ensure machinery wash and other potentially contaminated effluents are
released in safe containers. 9.4 To avoid the chemical and oil spills in storm water runoff such materials
should be properly stored. 9.5 Ensure that fuels, oils, and other hazardous substances are handled and
stored according to standard safety practices such as secondary containment. Fuel tanks should be labelled and stored in impervious lining and dykes etc.
9.6 Ensure spills are avoided during fuel and oil transfer operations. Appropriate arrangements, such as concrete base or drip pans, should be used to avoid spills.
9.7 Ensure fuels, oil and chemical storage are daily checked for leakage. 9.8 Ensure that shovels, plastic bags, sand bags and absorbent materials, are
kept available near fuel and oil storage areas. 9.9 Ensure that vehicle refuelling is planned on need basis to minimize travel and
chance spills. 9.10 Ensure that operating vehicles are checked regularly for any fuel, oil, or
battery fluid leakage. 9.11 Ensure all effluents be treated and disposed off through approved
methodology.
New Khanki Barrage Project (NKBP) IEE Report
8‐20
Sr. # Component Description Impacts Mitigation Measures / Actions
9.11 Ensure that leak /spill record is maintained for each vehicle and such vehicles are operated after proper repair.
9.12 Soil contaminated by minor spill (covering an area up to 1 m² and 7.5 mm deep) will be collected and disposed-off.
9.13 Ensure that soil contaminated by moderate spills or leaks (up to 200 liters) is controlled using shovels, sand and mud. The contaminated soil will be removed from the site and disposed-off through approved contractors. Major spills (exceeding 200 litres) will be handled and controlled by specialized contractor as suggested in waste disposal plan of EIA report of Khanki barrage.
9.14 In case if the agriculture land/crops are damaged by the construction activities, proper compensation will be paid to the owner by the Contractor.
9.15 If during the construction activities, any archeological or religious sites (such as graves) are found, these will be protected, in consultation with PMO, the relevant communities and the concerned Departments.
9.16 Ensure that dust emissions due to vehicular traffic are minimized by reduced speed, vehicular traffic minimized through good traffic management and water sprinkling when required.
9.17 Ensure that dust emissions at the construction sites are minimized by implementing good housekeeping and sound management practices.
9.18 Using strict standards for maintenance of construction machinery and sprinkling of water, dust and smoke can be minimized.
9.19 Ensure that all equipment, generators and vehicles used during the construction are properly tuned and maintained in good working condition in order to minimize the emissions. Vehicular emissions will be monitored, reported & documented.
9.20 Contractor obligation is to use appropriate and fit machinery keeping noise levels within NEQS.
9.21 Ensure prohibition of use of vehicle horns anywhere inside the fenced areas or on the access roads.
9.22 Ensure that drivers are discouraged from keeping vehicles running in parking lots.
9.23 Ensure the use of Personal Protective Equipment (PPE) wherever required (Safety gloves, safety boats, goggles, ear plugs/muffs, etc.)
New Khanki Barrage Project (NKBP) IEE Report
8‐21
Sr. # Component Description Impacts Mitigation Measures / Actions
9.24 Fuel consumption will be recorded. 9.25 Ensure that during aligning the access roads, and other construction activities,
minimum vegetation is lost. If any tree is uprooted, ensure that the Contractor has planted at least three fold of trees lost.
9.26 After completion of construction phase the vegetation of the area should be restored through plantation of the indigenous species.
9.27 Adequate water supply to riverine floral habitat should be maintained during construction phase of the project.
9.28 Ensure camp waste/food waste is disposed in such a way that animals are not attracted.
9.29 Natural habitats should be maintained to the maximum extent and undue interference should be avoided during construction phase of the project.
9.30 Sighting of any endangered species should be documented and activities should be carried out to reduce negative impacts on such species.
9.31 Contractor’s staff should be strictly prohibited from buying any wild animals/birds.
9.32 Ensure that discharging firearms is not allowed. 9.33 Ensure that safe driving practices are observed so that the accidental killing of
reptiles or small animals crossing the roads could be avoided. 9.34 Ensure that damage to the natural topography and landscape is minimized. 9.35 Ensure that the no-hunting, no-trapping, no-harassing and no-fishing policy is
strictly observed. 9.36 Ensure that the general awareness of the crew is enhanced regarding the
wildlife and natural vegetation, through environmental training, and notices boards.
9.37 The construction and dismantling of coffer dam may be done in a way to minimize the water turbidity.
9.38 Planning, designing and execution of the project should be carried out through adopting proper mitigation measures to conserve aquatic life. Ensure that no oil/lubricant or other toxic materials are released into the river.
New Khanki Barrage Project (NKBP) IEE Report
8‐22
Sr. # Component Description Impacts Mitigation Measures / Actions
10 Installation and operation of batching plant
Land Requirement: Ample PID land is available near barrage to establish batching plant. So no private land is required for the installation of Batching Plant. Raw material for the construction work mainly include cement, sand, aggregate, steel, water lubricants, fuel and additives. The material will be stock pilled at the area provided by PID near the batching plant. Wind direction While installing the batching plant the direction of the wind should be consider.
Soil, air and water contamination; safety hazard for communities;
10.1 Ensure that no private land is used for installation of the batching plant. 10.2 Ensure that location of batching plant must be at least 500 meters away from
the settlement. 10.3 Ensure that batching material is stocked on specified area in compliance with
specifications of installation of batching plant. 10.4 Ensure that the batching plant is installed with emission-control mechanism. 10.5 Ensure that batching plant does not contaminate the soil and water, or block
natural drainage. 10.6 Ensure that the location of the batching plant is such that the wind direction
may be away from the settlement. 10.7 Ensure that land contamination from the batching plant, during transportation
and dumping of the waste fresh concrete is controlled through careful working of the Contractor’s crews to avoid spillage of concrete and dumping of waste concrete on private land. Carry fresh concrete in suitable lorries.
11 Electric & Mechanical Works
No impact on the water resources
No impact on the water resources
11.1 If anything goes wrong due to this activity then it is the contractor responsibilities to mitigate the impact by using good engineering.
New Khanki Barrage Project (NKBP) IEE Report
8‐23
TABLE – 8.3: SOCIAL IMPACT MITIGATION PLAN
Component Description Impacts Mitigation Measures / Actions
1
Land
acquisition
The land used for
deliverables and
other project
activities has two
parts. The biggest
portion of land used
for the construction
of New Khanki
Barrage is state-
owned and the other
are 36 acres land
belonging to private
farmers which will
be acquired officially
in order to construct
new L.C.C for
supplying water to
the command areas.
Involuntary
resettlement;
loss of assets
and income
opportunities;
damage to
crops;
damage to
trees
1.1 All sites except construction of new L.C.C., required for construction activities,
camps, offices and workshops are owned by PID, and no private land
acquisition is envisaged.
1.2 In case private land acquisition has to be undertaken, a RAP will be prepared,
in accordance with the ABD guidelines and RPF agreed under the project.
1.3 Ensure RAP must be implemented before start of the construction activities at
Barrage.
New Khanki Barrage Project (NKBP) IEE Report
8‐24
Component Description Impacts Mitigation Measures / Actions
2
Water
consumption
The contractor will
require water for
sprinkling the earth
material for
compaction. For this
purpose river water
will be used.
Preparation of
concrete at the
batching plant would
need water free
from sediments and
high salt
concentrations,
particularly
sulphates. Ground
water will meet this
requirement.
Therefore contractor
will install tube well
at the site to meet
this.
Water
shortage for
the local
communities;
Social conflict
2.1 Avoiding wastage of water through conservation techniques and selection of
adequate water supply sources, ensuring no impact on local consumptions.
2.2 Record will be maintained for water consumption.
2.3 Ensure that community is compensated for the water extracted from the
community area aquifers.
2.4 Ensure water consumption for domestic use is monitored at camp site and
aquifer/well.
2.5 Ensure that Contractor obligations defined in contract document and Social
Framework Agreement (SFA) are followed.
3
Interruption
of canal
water supply
During the
construction of new
Khanki Barrage and
No impact
No mitigation measure is required.
New Khanki Barrage Project (NKBP) IEE Report
8‐25
Component Description Impacts Mitigation Measures / Actions
new L.C.C the
supply of water in
the old L.C.C will not
be interrupted.
4
Social issues
The construction
site is for away from
the human
settlements. Local
population will not
disrupted from the
contractor activities
Local
conflicts;
privacy of
women
4.1 Ensure that conflicts with village leaders and local communities are avoided.
4.2 Ensure that women are informed through traditional means of communication
of the presence of foreigners (if any) in their area.
4.3 Ensure that individuals holding titles to private property used in the project (if
any) are compensated in accordance with the market rates and all payments
are recorded.
4.4 Ensure that focus group meetings are conducted with both men and women
to identify any water related and other issues related to project
implementation.
4.5 Ensure that PMO representatives visit the site twice a month and gather
complaints from Social / Environment Complaints Management Register and
provide feedback to the concerned on the compliance status.
4.6 Ensure that project staff interaction with local community is minimized.
4.7 Ensure that guidelines are prepared and implemented to sensitize labourers
to local norms and customs in order to minimize cultural tensions.
5 Public health
and safety
issues
Settlement being
located far of from
the site, there will be
no safety and health
hazards for the local
population.
Safety hazard
for local
population;
health hazard
for local
population
5.1 The contractor will develop and implement a Health, Safety, Environment and
Social (HSES) plan.
5.2 Due precautions shall be taken by the Contractor, to ensure the safety of his
staff and labour and, in collaboration with and to the requirement of the local
authorities.
5.3 Ensure that medical staff headed by qualified medical doctor, first aid
New Khanki Barrage Project (NKBP) IEE Report
8‐26
Component Description Impacts Mitigation Measures / Actions
However there will
be significant safety
and health hazards
for the work force,
particularly for the
people working on
the repair/
renovation of gates
and hoists and
installing electric
equipment under a
condition of full
impoundment of the
barrage pond. The
safety hazards are
also involved at the
blasting site for the
rock excavation
and project
staff
equipment and stores, sick bay and suitable ambulance service are available
at the camps, housing, and on the site at all times throughout the period of the
contract and that suitable arrangements are made for the prevention of
epidemics and for all necessary welfare and hygiene requirements.
5.4 Ensure no machinery is left unattended in the project area.
5.5 Ensure that a proper ambulance (preferably a four-wheel-drive vehicle should
be available at site on 24- hour basis).
5.6 Ensuring that all materials, gears and equipment (including personal
protective equipment) needed to carry out the job safely has been provided to
the workers.
5.7 Ensure that employees have access to running potable water at their place of
work and also shadow area is provided for rest.
5.8 Ensure that use of horns is prohibited, except when necessary.
5.9 Ensure all entry points into construction sites are staffed 24 hours a day.
5.10 Ensure that safe driving practices are adopted, particularly while passing
close to settlements. This includes a speed limit of 40 km per hour if passing
within 100 m of settlements anywhere in the project area.
5.11 A proper screening of labour should be done at the time of recruitment.
Ensure that periodic awareness campaigns for HIV/AIDS are undertaken for
the project staff.
5.12 Ensure that a risk assessment of the spread of HIV/AIDS is undertaken in the
project area on the basis of data from the Punjab HIV/AIDS program.
6 Employment
opportunities
The project will open
new job
opportunities which
Local dissent
associated
with influx of
6.1 Ensure that maximum employment may be given to the local people.
6.2 Ensure that inter-tribal balance is maintained when giving employment to the
local population. Preference to be given to the people directly affected by the
New Khanki Barrage Project (NKBP) IEE Report
8‐27
Component Description Impacts Mitigation Measures / Actions
the local population
could avail.
Contractor will hire
skilled and unskilled
labour force from
the local
communities. ID
may request the
contractor to hire
labor from the local
communities.
workers from
other parts of
the country
project.
6.3 Ensure project staff interaction with local community is minimized.
7 Aesthetic/
scenic
quality.
The
construction
activities
could affect
the aesthetic /
scenic value
of the area
7.1 Carry out complete restoration of the construction sites. Remove all waste,
debris, unused construction material, and spoil from the worksites.
7.2 Develop a public park at the Barrage to increase its value for the
communities.
The old Khanki weir will be dismantled soon after the commissioning of New Khanki Barrage Project and construction of new L.C.C that for
doing this the contractor will adopt a technology acceptable to the Project Management. A special Dismantling Plan formulated by the
contractor under the guidance and supervision of ESU & Environments/Social Experts of the SC will, in fact, ensure the solution of related
problems, viz. noise pollution during dismantling of the huge steel and stone structure, debris transportation, debris dumping etc.
New Khanki Barrage Project (NKBP) IEE Report
8‐28
8.4. ENVIRONMENTAL MONITORING PLAN
This section provides a Monitoring plan that identifies the roles and responsibilities of
Project staff involved in environmental and social monitoring, and lists the
parameters that will be used in the monitoring process.
8.4.1 Objectives
The main objectives of the pre-construction and construction phase monitoring plans
will be to:
Monitor the actual project impact on physical, biological and socio-economic
receptors.
This will indicate the adequacy of the EIA.
Recommend mitigation measures for any unexpected impact or where the
impact level exceeds that anticipated in the EIA.
Ensure compliance with legal and community obligations including safety on
construction sites.
Monitor the rehabilitation of borrow areas and the restoration of construction
campsites as described in the EMP.
Ensure the safe disposal of excess construction materials.
The main objectives of monitoring during the operation phase will be to:
Appraise the adequacy of the EIA with respect to the project’s predicted long
term impact on the corridor’s physical, biological and socio-economic
environment.
Evaluate the effectiveness of the mitigation measures proposed in the EMP,
and recommend improvements in the EMP, if necessary.
Compile periodic accident data to support analyses that will help minimize
future risks.
Monitor the survival rate of canal side, road & barrage plantations.
8.4.2 Monitoring
The monitoring will be carried out at two levels: At the first level, the contractor (for
the mitigation measures given in Tables - 8.4 and PMO (for the infrastructure
development works) will carry out internal monitoring to ensure that all the
environmental and social requirements are adequately implemented. At the second
level, ESS of the Supervision Consultants and ESU will monitor the implementation
of the environmental and social mitigation measures. Appropriate checklists and
forms will be developed for this purpose.
New Khanki Barrage Project (NKBP) IEE Report
8‐29
8.4.2.1 Effects Monitoring
The actual impacts on physical, biological and socio-economic receptor of the project
area due to project activities will be monitored. The Effect Monitoring is done to
identify any effects either not anticipated in EIA or exceeding the level anticipated in
the mitigation plan so that appropriate mitigation measures can be adopted in time.
The common theme of Effect Monitoring is the proper management of environmental
risks and uncertainties. The Effect monitoring has four Objectives:
To verify that the impact of the proposed project is within acceptable limits, thus
establishing credibility.
To facilitate research and development by documenting the effects of the
proposed project that can be used to validate impact- predication techniques
and provided a basis for more accurate prediction of future impact.
In case of adverse impacts or sudden changes in the anticipated impacts
immediately inform the PMO and other regulatory agencies so that the
corrective can be taken such as modification of mitigation measures and
inclusion of additional measures
To minimize the effects control the timing, location and level of certain project
activities
The effect-monitoring plan is given in Table-8.4. Improvement of the detailed
methodologies for effect monitoring will be included in Consultants scope of work.
The effect monitoring includes the monitoring of land, water, air noise wildlife and
socio-economic and cultural aspects.
8.4.2.2 Compliance Monitoring:
Compliance with the requirement of EMP will be checked by monitoring the activities
of the contractor on daily basis by the environmental specialist of the consultants.
The objectives of EIA compliance monitoring will be:
Systematically observe the activities undertaken by the contractor in the civil
and mechanical works.
Verify that the activities undertaken are in compliance with the EIA and other
conditions identify by PMO and PID.
Documents and communicate the observations to the concerned persons in
PMO so the corrective action, if required, can be taken timely.
Maintain a record of all incidents of the environmental significance and related
action and corrective measures.
Prepare periodic reports of the environmental performance of PMO and its
consultant and contractor.
New Khanki Barrage Project (NKBP) IEE Report
8‐30
Develop an environmental issue tracking system for an effective monitoring and
ensuring that all environmental concerns are identified and addressed in a
timely manner.
The Mitigation Measures Implementation plan will be used as a management and
monitoring tool for compliance monitoring. Inspection will be done using checklists,
samples of which are attached at the end of this section as (Annexure 1, Table - 2).
The remaining checklist will be developed by the environmental specialist of the
Construction. Supervision Consultants on the basis of mitigation plan. The
responsibility of compliance monitoring is laid on all organizations such as PMO,
consultants and the contractor.
PMO ‘s ESU will be environmental implementer / coordinator
Environmental team of Construction Supervision Consultants will be field
monitors
8.4.2.3 Post-Project Monitoring:
The objective of this monitoring will be to determine the level of residual impact of the
project on physical, biological and socio-economic receptors of the project area. This
monitoring may be carried out within one month of the end of project activities. Post –
project monitoring is included in effects monitoring, discussed above.
After the construction work a detail inspection by consultant and ESU, PMO of the
area will be conducted to verify that proper restoration work if done and photographic
evidence of the restoration work will be taken.
It is also anticipated that additional inspection will be required in response to any
complaints by local communities. So another two visits per quarter may be budgeted
for M&E Units. All officers concerned with M&E shall prepare their own M&E
Implementation Plans for information of all concerned. All M&E units shall be given
optimal mobility and flexibility to implement their M&E implementation plans.
List of indicators: will be used to monitor the environmental performance of the
project. The indicators may include the specific measures that must be taken.
These are, for example:
Revision of the EMP annually
Compilation of all operating documents twice a year
Closure on SFA before the start of contractor mobilization.
Timely appointment of all environmental staff by contractor and supervision
consultants before the implementation of contract. PMO environmental staff is
already appointed
Mid-term review of the environmental performance of the project
New Khanki Barrage Project (NKBP) IEE Report
8‐31
8.4.2.4 Third Party Monitoring / Environmental Audit Annually.
The PMO will engage a third party monitor to do the environmental audit annually
during the construction period. Three periodic audits will be carried out; one at
preconstruction stage, the second will be carried out during the construction and third
at post construction stage. The firm’s terms of reference will define a clear work plan,
including monitoring indicators, and reporting structures and timelines. The PMO will
provide the necessary logistical support to facilitate the selected firm in
Environmental audit.
The Parameters, frequency, responsibility and mitigation measures for monitoring
have been described in Environment Monitoring Plan (EMP) in Table 8.2.
Table 8.4: Effects Monitoring Plan
Sr. # Description Monitoring Location
Monitoring Parameters Frequency of Measurement
CONSTRUCTION PHASE 1. Ambient air quality Barrage, batching
plant site, labor camp site and borrow areas.
NOx, SOx, CO and Particulate matter (PM10).
Quarterly
2. Quantity and quality of ground water used for domestic purposes.
Camp site and 1 km away from the camp site.
Water table depth, discharge, physical-chemical parameters, biological contamination, heavy metals and toxic organic compounds.
Quarterly
3. Quality of surface water used for construction activities
At source of surface water used.
pH, EC, SAR and RSC
Quarterly
4. Emission of dust, smoke and potential air pollutants from the construction machinery.
Construction sites, campsite, access roads, borrow areas.
Dust, smoke, gases Throughout construction phase
5. Visual check for exhaust emissions from the vehicles.
Construction sites, campsite, access roads, borrow areas.
Visible emissions. During routine monitoring.
6. Visual check for vegetation loss
Construction site, campsite, access roads, borrow area.
Type and number of tree species uprooted.
At the beginning of construction activities.
7. Noise Construction site, camp site, access roads, communities within 500 m of
Noise measurement
Once a week throughout the construction phase.
New Khanki Barrage Project (NKBP) IEE Report
8‐32
Sr. # Description Monitoring Location
Monitoring Parameters Frequency of Measurement
construction site.
8. Soil erosion
Construction site, campsite, access roads, borrow area.
Visual observations for street or rill/gully erosion.
During routine monitoring of entire project activities especially after rains.
9. Resources utilization
Project site. Quantity of material used including water and fuel
Daily during construction phase
10 Solid Waste Generation
On camp site and Construction site.
Any sign of soil or water contamination;
Daily during whole construction phase
11. Wastewater generation
Camp site, offices, colony and construction site.
Waste water generation rate, integrity and maintenance of the septic tanks and soaking pits, any sign of soil or water contamination
To be determined through water management techniques.
12. Oil Waste Spills Oil storage area, vehicle washing lines; any other spill area.
Facilities to control the accidental oil spill as per oil spill contingency plan; any sign of soil or water contamination
Daily during construction phase
13
Socioeconomic Issues
At Project Locations; Settlements
Local people recruited for all manual labour and other jobs for which local skill are available; grievances of and conflicts with communities;
During construction phase
CONSTRUCTION PHASE 14. Monitoring of Fish
Immediately upstream and downstream of Khanki Barrage.
fish survey; effectiveness of the fish ladders.
Throughout the construction phase
15. Monitoring of water flows in the river and LCC
Khanki Barrage and various location in the L.C.C.
Water flows. Also vigilance on any water thefts in particular during low flow periods
Throughout the construction period
16 Monitoring of cumulative impacts
All project sites, All environmental and social parameters such as soil erosion, soil/water contamination, noise, air
Throughout the construction period
New Khanki Barrage Project (NKBP) IEE Report
8‐33
Sr. # Description Monitoring Location
Monitoring Parameters Frequency of Measurement
contamination, vehicular traffic, local resource utilization, and other impacts on communities.
OPERATION PHASE
1. Restoration
At all project locations (construction sites, camp sites, offices, tracks and others)
Restoration and rehabilitation as per Restoration Plan
At the end of the construction phase
2
Surface Water quantity and Quality
Upstream and downstream of the Barrage, at the same locations where design- and construction-phase monitoring was done
Flows, pH, conductivity, TSS, TDS, BOD and COD
3 Ground water Quality
Water sources used for construction purposes and dug wells within 1 km from wastewater mud ponds (if any). At the same location where construction-phase monitoring was done
Physical- chemical parameters, heavy metals and toxic organic compounds.
Once in pre and post monsoon season for 2 years.
4. Soil Erosion At project sites and along the aligned borrow areas; at locations prone to soil erosion.
Visual observations.
After site restoration.
5. Habitat Disturbance Within the project boundaries.
Visual Observation. At the end of the construction phase
6. Compensatory tree plantation
According to the tree plantation plan.
Survival rate of tree saplings
Twice in a year for three years.
8.4.3 Grievance Redress System
A Grievance Redress System (GRS) will be established by the PMO to handle the
community complains received from the complaints. Under this mechanism, a
Grievance Redress Cell (GRC) will be established. GRC will be headed by the
HPMO; others members will include the Deputy Director (Environment), Deputy
New Khanki Barrage Project (NKBP) IEE Report
8‐34
Director (Sociology), the Deputy Director (Social Assistance), the SS of the
Supervision Consultants, Executive Engineer Irrigation at site, one Sub Divisional
Officer, a representative of local administration, the supervising engineer, and a
representative from the local communities. The sub-divisional officer will be the key
grievance redress officer. The project will establish a Project Information Centre at
the Barrage site and a community complaints-management register (CCMR) will be
placed there for logging complaints and grievances. All written and oral grievances
will be recorded in the Register. The information recorded in the register will include
the date of the complaint and particulars of the complainant; a description of the
grievance; the follow-up action required; the person responsible for implementing the
action; and a target date for its completion.
Affected communities and their representatives will be identified during the project
preparation stage. The ESU will work towards resolving the grievances recorded in
the CCMR in conjunction with the Supervision Consultant within seven calendar
days. After this deadline, any unresolved issues will be forwarded to Irrigation
Department.
8.4.4 Reporting Structure and Outcomes
8.4.4.1 Data Recording and Maintenance. All forms to be used for recording
information during the environmental monitoring will follow a standard format which
will correspond to the data base in to which all the gathered information will be
placed. Check boxes will be used as much as possible to facilitate data entry. A
tracking system will be developed for each form. A comprehensive system will be
established to store the environmental and social data of the project.
8.4.4.2 Storage of information
The database may include Training programs; Staff deployment; Non-compliance;
Corrective actions; List of environmental data and List of environmental data to be
maintained: Soil and land pollution; disposal of excavated silt and earth disposal of
waste water resource ;quality quantity fuel oil and chemical spills; vegetation record
and record of wildlife :Noise pollution ;Air and dust pollution and Socio-economic
data .
8.4.4.3 Meetings.
These will include the kick-off meeting, and daily/weekly meetings. The main focus
of these meetings will be EMP and RAP compliance, non-compliances, and the
measures to be taken to address them.
New Khanki Barrage Project (NKBP) IEE Report
8‐35
8.4.4.4 Photographic record.
A comprehensive photographic record will be maintained of the key locations and key
events of the project.
8.4.4.5 Social complaints register
The consultants ‘ environmental team will maintain a social complaint register at
camp site office to document all complaints received from the local communities, the
register will also record the measures taken to mitigate these concerns. The final
report will be communicated to ESU of PMO
8.4.4.6 Change record register:
This will be maintained at a site to document any change in the project design. These
changes will be handled through the change management mechanism if any. The
final report will be communicated to ESU of PMO
8.4.4.7 Reporting
Overall, progress reporting will be the responsibility of each contractor who will
provide inputs to the Supervision Consultant to be collated and submitted to the ESU
of PMO. The Supervision Consultant will be responsible for submitting a monthly,
quarterly, annually and final environmental/social report. The Supervision
consultant’s monthly progress report will include the following environmental
information:
Contract-wise breakdown of environmental non-compliances and rectification
by the contractor.
The results of monitoring environmental and social parameters carried out by
the contractors.
In addition the environmental specialist of the SC will prepare a quarterly report
encompassing environmental concerns and submits to the ESU of the PMO.
The list of distribution reports is given in Table-8.5
.
Table - 8.5: Periodic Reports
Report Timing Prepared by Reviewed by
Distribution
Daily
--
Environmental team of the Construction Supervision Consultants
Reviewed by PMO ESU.
Resident Engineer PMO
Monthly
Environmental team of the Construction
Reviewed by PMO
Resident Engineer
New Khanki Barrage Project (NKBP) IEE Report
8‐36
-- Supervision Consultants
ESU. PMO ID Department ADB
Quarterly
--
Environmental team of the Construction Supervision Consultants
Reviewed by PMO ESU.
Resident Engineer PMO ID Department EPD ADB
Annually
--
Environmental team of the Construction Supervision Consultants
Reviewed by PMO ESU&. EPD
Resident Engineer PMO ID Department EPD ADB
Change Management
--
Environmental team of the Construction Supervision Consultants
Reviewed by PMO ESU. & EPD
Resident Engineer PMO ID Department EPD ADB
Final --
Environmental team of the Construction Supervision Consultants
Reviewed by PMO ESU.
Resident Engineer PMO ID Department EPD P&D ADB
8.4.5 Communication Strategy
Effective communication between the project agency and its stakeholders helps build
trust and collaboration which in turn contributes to better project design and speedy
implementation. To this end, stakeholder consultations were conducted during the
project design and planning stage and while conducting the EA studies, as discussed
in Section 5 of this document.
The need to continue these consultations and communication with the stakeholders
particularly the local communities during the project construction phase cannot be
understated, and the success of the project can only be guaranteed by involving all
the stakeholders - especially the farming communities in the saline zones, as the
inhabitants of these areas are totally dependent on the continuous water supply for
New Khanki Barrage Project (NKBP) IEE Report
8‐37
irrigation and household purposes - in this consultation and communication process.
During the construction phase, it is very important to consult and involve
stakeholders, on an on-going basis, to ensure liaison and a high degree of
transparency among all the policy makers, PID/PMO, contractor, consultants, the
farming community and the media. Each of them will be encouraged to provide
feedback on the design and implementation processes.
To meet the above needs, a Communication Strategy has been developed for the
proposed project. The lessons learnt from the Taunsa experience have proved
invaluable in developing this Strategy. The key objectives and functions of the
strategy are: to provide mechanism for two-way communication and consultations
between the project personnel and the stakeholders, particularly the farmers in the
command area; and to provide necessary information to the farmers and other
stakeholders on the key project activities such as canal closure, to receive their
feedback in this respect, and to adjust the construction activities/schedule
accordingly, where possible/necessary.
ESU will be responsible to implement the Strategy, and the Deputy Director
(Communications) will be appointed in the Unit for this purpose (See Figure 2).
Communications Methods
The following communication methods will be used as part of the Strategy:
a) Involvement of policy makers. PMO will initiate a series of direct communication
measures to inform and involve the policy makers including the concerned
Ministers, Members of the National Assembly (MNAs) and Members of the
Provincial Assembly (MPAs). This can be achieved by making presentations to
them and holding briefing sessions with them on a regular basis. They will be
invited to participate in the consultation process to ensure transparency and to
gain public support for the project. This will be carried out simultaneously with
the mass media campaign.
b) Communication through Numberdars of village and Imam Masjid (Muslim prayer
leader). Since Numberdars and Imams are also closely associated with the
villagers, the project information can also be disseminated to the communities
through them.
c) Communication through PRSP. Being the project NGO, PRSP will also
disseminate the project information, including schedule of the annual canal
closure, to the communities, and obtain feedback from them, through its own
communication mechanism.
d) Communication through media: The print and electronic media are very effective
means of mass communication, and have a vast reach among all potential project
New Khanki Barrage Project (NKBP) IEE Report
8‐38
partners. The project will carry out a media analysis, as part of the
Communication Strategy, to assess the reach and effectiveness of different
publications, television and radio stations among the various target audiences,
and to develop the most efficient and effective media campaign for the project.
f) Involvement of IPD: IPD provides services to the farming community through
its functionaries (Zaildars and Canal Patwaries). The issues regarding irrigation
water of farming community are initially resolved through these functionaries.
They will also be involved in the dissemination of information to the farmers and
obtaining their feedback regarding the matters
8.5. PUBLIC CONSULTATION AND DISCLOSURE
This section describes the outcome of the public consultation sessions held with
different stakeholders/groups that may be impacted by the project. The consultation
process was carried out in accordance with the) Asian Development Bank’s Safe
Guard Policy Statement (ADB’SPS). The process of the public consultation
proceeded as follows: -
Meetings with regional and local officers of PID Government of Punjab.
Semi-structured interaction held with communities on old and new barrage sites
and around.
Public Hearing through EPA Punjab to get the maximum participating role for the
members of public. (To be done at the convenience of EPA Punjab after
submission of the drafts EIA report).
8.5.1 Meeting with local and regional officials.
Phase –1: A series of meetings were held with local and regional officials (See the list
of officials contacted in Table 8.6. below)
Table – 8.6: List of Officials Contacted
Sr. No. Officials Contacted Title
1 Mr. Shahid SaIEEm
Chaudhry
EX-En. Khanki Headworks
2 Mr. Shafiq Ahmed SDO Headworks Khanki
3 Mr. Khadim Hussain Sub Engr Headworks Khanki
4 Mr. Abdul Ghaffar Sub Engr. Khanki
5 Mr. Arshad Ahmed Jamadar Khanki Headworks
6 Mr. Ijaz Ahmed Sounding Mistry, Khanki Headworks
7 Mr. Nasar Ahmed Head Boatman Khanki Headworks
New Khanki Barrage Project (NKBP) IEE Report
8‐39
8 Mr. Nasrullah Regulation, Khanki
9 Mr. Muhammad Riaz Boatman Khanki
10 Mr. Muhammad Riaz Naib Jamadar, Khanki
11 Mr. Ghulam Rasool Artificiar, Khanki
12 Mr. Muhammad Anwar Beldar, Khanki
13 Mr. Liaqat Ali Regulation Beldar, Khanki
14 Mr. Muhammad Aslam Guage reader, Khanki
15 Mr. Muhammad Asif
Bharoke
Fish watcher, Khanki
16 Mr. Nazar Muhammad
Ratta
Wildlife Inspector, Khanki
17 Mr. Raza Ahmed Khan Ex-En RE Shadiwal Power House
18 Mr. Naseem Ahmed Khan SDO Shadiwal Power House
19 Engr. Bashir Zahid JE, PRO Electrical, Shadiwal Power
House
20 Engr. Muhammad Anwar Lengah, JE, PRO water, Shadiwal Power
House
Meetings with officials provided multiple and diverse objectives such as:
Provided a forum for the initial definition of critical environmental and social issues.
Established their interpretation, as official stake-holders, the key sector development
issues and linkages to the environmental and social development.
Confirmation of the suitability of initial list of communities selected for consultation.
Facilitation of Field Work.
8.5.2 Meeting with Local Communities
Phase –2: Involved the undertaking of a programme of semi-structured discussion with
communities in the project area of influence. This programme included both community
discussion and discussion with women (through women organizers). Some of selected
members of the public in New Khanki Barrage area, who were interviewed, are listed
below: (See Table 8.7).
New Khanki Barrage Project (NKBP) IEE Report
8‐40
Table – 8.7: Member of Public in Khanki Barrage Area Interviewed
Sr. No. Name Village
1 Arshad s/o Nazar Muhammad Wadhan Nathu Kote
2 Nasir s/o Nazar Muhammad Wadhan Nathu Kote
3 Muhammad Riaz s/o Muhammad Bashir Wadhan Nathu Kote
4 Muhammad Afzal s/o Ch. Bahawal Bukhsh Jut Nathu Kote
5 Gul Hussain s/o Nawab Nathu Kote
6 Muhammad Anwar s/o Bashir Ahmed Basiana Numberdar Nathu Kote
7 Muhammad Bashir s/o Khushi Muhammad Machchi Nathu Kote
8 Shaukat Ali s/o Muhammad Ali Jutt Kahloon Kot Kahluan
9 Alta Muhammad s/o Khushi Kot Kahluan
10 Muhammad Yousaf s/o Muahammad Islam Din Rajpoot Kot Kahluan
11 Mehdi Hussain s/o Amir Ali Rajpoot Kot Kahluan
12 Nasrullah s/o Abaidullah Hanjra Kot Kahluan
13 Mian Javed s/o Faiquir Ahmed Hanjra Kot Kahluan
14 Muhammad Afzal s/o Mian Khan Kot Kahluan
15 Muhammad Malik s/o Bahawal Bukhsh Kot Kahluan
16 Muhammad Aslam s/o Muhammad Hanif Kot Kahluan
17 Manzoor Huassian s/o Rehmat Khan Cheema Kot Kahluan
18 Nazir Ahmed s/o Rehmat Khan Cheema Kot Kahluan
19 Liaquat Ali s/o Muhammad Nazir Cheema Numberdar Kot Kahluan
20 Muhammad Ramzan Cheema Kot Kahluan
21 Shabbir Hussain s/o Muhammad Shafi Cheema Rattowali
22 Atta Muhammad Numberdar s/o Rehamt Ali Waraich Rattowali
23 Ghulam Nabi s/o Sardar Muhammad Jutt Rattowali
24 Muhammad Akram s/o Nawab Cheema Rattowali
25 Muhammad Ejaz s/o Atta Muhammad Rattowali
26 Muhammad Ashraf s/o Nazar sahi Rattowali
27 Syed Maqbool Hussian Shah s/o Usool Hussian Shah Rattowali
28 Hassan Mehmood s/o Sardar Cheema Rattowali
29 Muhammad Ashraf s/o Ghulam Haider Rattowali
30 Muhammad Anwer s/o Muhammad Khan Cheema Rattowali
31 Ramzan S/O Mian Khan Rattowali
32 Muhammad Ashraf s/o Ali Muhammad Machi Rattowali
33 Muhammad Irshad s/o Hayat Muhammad Rattowali
New Khanki Barrage Project (NKBP) IEE Report
8‐41
Sr. No. Name Village
34 Muhammad Sadiq s/o Mian Khan Rattowali
35 Muhammad Riaz Cheema Churri Mar Gorali
36 Muhammad Javed Wadhan Gorali
37 Muhammad Anwer Jhammer Gorali
38 Irsah Shah Syed Gorali
39 Syed Masoom Shah Gorali
40 Muhammad Tufail Waraich s/o Ghulam Haider Waraich Gorali
41 Nazir Ahmed s/o Rehmat Khan Cheema Khanki
42 Abdul Majeed s/o Nawab Khan Cheema Khanki
43 Atta Muhammad Cheema Khanki
44 Muhammad SaIEEm s/o Ghulam Qadir Waraich Khanki
45 Muhammad Aslam s/o Muhammad Hussian Cheema Khanki
46 Muhammad Hanif s/o Ibrahim Araeen Khanki
47 Haji Zahoor Hussain Shah Thathi Baluch
48 Chaudhry Rasool Ahmed Arain Kot Imam Bakhsh
49 Chaudhry Tariq Duraji Shadiwal
50 Chaudhry Muhammd Sharif Sandu Kot Manj Din
The semi structured meeting with community representatives, in and around the project
area achieved the following objectives:-
Elimination of the scare that the canals will remain closed during the construction
of the barrage for about four years. It was clarified that due measures will be taken
that canals would run as per usual programme and canal closure will take place
only under the notified canal closure programme as follows:
Name of Canals : Lower Chenab Canal (LCC)
Status of Canals : Perennial
Period when Canals would run : Throughout the year except for
notified maintenance closure
Period of Canal Closure
for repairs and maintenance
: January 13 to January 31
(adjustable)
No change would be made in the existing capacity of canals, so no effect shall be
impacted on the canal command area. It could be explained that project aimed at
replacing the old and out dated model of weir with a new and modernized barrage one
and not to change the capacity of the barrage or increase or decrease the capacity of
New Khanki Barrage Project (NKBP) IEE Report
8‐42
the L.C.C. system or cause any change in the pond level or change the stated scope of
the project.
Elimination of the fear that for contractor’s labour camp Material Depot, Machinery
Yard, access roads and work site, any private agricultural lands shall be acquired
or occupied. It was noted that state did not possess a healthy record regarding
payment of compensation. It was reported that lands were occupied immediately
but compensation was delayed for generations. It was clarified that no private land
would be required at all for the new barrage, labour camp, material depot,
machinery yard, access roads or work basis. With the help of a map it was shown
to the community that adequate Irrigation Department land and link roads existed
to accommodate all the requirement. No private agricultural land shall be acquired
or occupied for the contractor facilities but for construction of new L,C,C about 17
Acres of land would be acquired. For this the resettlement Action Plan will be
prepared and implemented well before the start of the construction work. The
preparation of the RAP is under process..
Settled down the concern that the workers and Iabour will be brought by the
Contractor from outside the project area and an opportunity of employment,
generated by Khanki Barrage shall be availed by people from other areas. The
community gathering was informed that it had been put as a condition in the
Tender Document as well as the Contract Document that maximum employment
shall be offered to the local labour/workers. On their question as to how much
would be the local employment, they were given the following illustrative numbers.
Table – 8.8: Employment Opportunities in the Construction of New Khanki
Barrage Project
Sr. No. Category Approximate Total
Number
Minimum Parentage
of Local Labour
1. Skilled Labour 200 Open. As much as
available locally
2. Semi-Skilled
Labour
300 50% locally
3. Un-skilled Labour 1,500 100% locally
Total 2000 80% local
The community expressed their satisfaction on the proposed arrangement.
Fisherman community expressed their concern that after construction of Marala
and Qadirabad barrages the fish in Khanki pond and downstream had markedly
New Khanki Barrage Project (NKBP) IEE Report
8‐43
decreased. They feared that high level of construction activity and noise level
generated by new barrage will further disturb the Fish. They were informed that
the construction activity will be restricted close to the Barrage about 900 m below
the existing headworks. The fish is mostly in calm water behind the spurs. Their
fishing activity shall continue as per rules of he Fisheries Department. Further to
that two fish ladders would be built to facilitate the fish migration.
Question was posed by the community that presence of some 2000 male
members of labour from general locality of project will not only restrict the chances
of women employment, but also cause moral and social problems for a free
movement of local women-folk in the area. It was clarified that strict discipline
would be exercised on the labour force by providing stringent clauses in the
contract document and also in SFA.. To cull out the possibility of any moral issues
or HIV/AIDS spread, a well-organized campaign shall be run. And if some women
were interested in working on the project, they would be most welcome, on equal
opportunity basis without any gender discrimination.
With heavy project traffic on the main and link roads, there is higher likelihood of
road accidents. It was clarified that due and necessary training of drivers and
security guards would be adapted to exclude possibility of road accidents. Efforts
would be made that the work is generally restricted to day light hours when
possibility of road accident is lesser. Road safety shall further be beefed up with
good traffic control guards, a bold set of sinology an efficient wireless
communication between field commanders and the drivers.
A fear was expressed that with the arrival of about 2000 additional persons, the
prices of commodities in construction site and adjoining markets would go up, and
price index would go unfriendly for the local villages. It was clarified by some trade
oriented people within the community that instead of rise in price those would fall
because larger market activity reduces the profit margin, and thus the prices.
General discussion on this point ended up in favour of the trade oriented group.
The following points came up in open acceptance of the project:
Greater employment opportunity was most welcome.
Greater economic activity will alleviate poverty.
Old Khanki Weir would be replaced. The new barrage will give a new boost
to dependent agriculture in Rachna Doab.
Present level of services i.e. electricity, communication, schooling, water
supply etc., is likely to improve with the construction of a bridge across
Chenab.
Roads in general will improve.
New Khanki Barrage Project (NKBP) IEE Report
8‐44
Diversification of the opportunity of employment will help the fishermen to
get employed on this project which will compensate them for loss of fishing
activity.
The new bridge will bring in greater cultural reunion and reinforce the
marketing activity.
All the above points would be reflected in Social Framework Agreement (SFA) between
the local community and the PID as and when the project is commissioned for
construction.
The detail about the disclosure and public hearing is given in the main EIA report of
Khanki Barrage.
8.6. ENVIRONMENTAL TECHNICAL ASSISTANCE AND TRAINING PLAN
An environmental and social trainings and technical assistance (TA) program will
help to ensure that the requirements of the ESIA, EMP and RAP are clearly
understood and followed by all project personnel. The primary responsibility of
providing these trainings to all project personnel will be that of the contractor and
Supervision Consultants. The trainings will be provided to different professional
groups separately such as managers, skilled personnel, unskilled labors, and camp
staff. An indicative training program is given in Table 6.
The PMO will engage an international technical assistance (TA) consultant to
manage the environmental training program. The objective of the TA will be to help
establish appropriate systems, and to train senior PMO staff responsible for
managing environment, operations, and planning, who can then impart training at a
broader level within and outside the PMO (i.e., the training of trainers). The TA
consultant will organize foreign and in-country training courses for PMO staff; train
PMO staff in specialized areas such as air and noise pollution modeling; develop
environment operation manuals in consultation with the PMO D/DD. In addition to the
training arranged and imparted by the TA consultant, the supervision consultant will
train the staff working under the project’s contractors and the PMO’s Deputy Project
Coordinator, in environmental compliance and the daily monitoring of construction
projects. The cost of this training will be included in the budget of services provided
by the supervision
New Khanki Barrage Project (NKBP) IEE Report
8‐45
Table – 8.9: Training Program
Staff Trainer Contents Schedule
Selected field staff of PMO
ESU Specialists; ESS of the Construction Supervision Consultants
Environmental and social aspects, particularly sensitivities of the project; Key finding of the ESIA, EMP and RAP; Social and cultural values of the area; Leadership dynamics.
Before construction activities
All site personnel Contractor: Managerial staff, engineers, Environment, social, health and safety staff. Consultants: Managerial staff and engineers
ESS of the Construction Supervision Consultants
Environmental and social aspects, particularly the sensitivities of the project; Wildlife and vegetation related sensitivities of the project; Key finding of the ESIA, EMP and RAP; Mitigation measures; Contingency plan; Community issues; Social and cultural values of the area
Before and during construction stage
Construction crew ESS of the Construction Supervision consultants; Environmental and Social Officers of the contractor
EMP; RAP; Waste disposal; HSES plan
Before and during construction stage
Drivers Environmental and Social Officers of the contractor
HSES plan; Road safety; Road restrictions; Vehicle restrictions; Defensive driving; Waste disposal; Social and cultural values of the area.
Before and during the construction
Mechanics Environmental and Social Officers of the contractor
Waste disposal; HSES plan; Vehicle restriction
Before and during the construction
Camp staff Environmental and Social Officers of the contractor
HSES plan; Camp operation Waste disposal Natural resource conservation Housekeeping
Before and during the construction
Restoration team ESS of the Construction Supervision consultants; Environmental and Social Officers of the contractor
Waste disposal; Site restoration; Leveling and dewatering of borrow area
Before the start of the restoration activity
New Khanki Barrage Project (NKBP) IEE Report
8‐46
8.7. CHANGE MANAGEMENT
An environmental assessment of the proposed project has been made during the
preparation of EIA. However it is possible that change in project design or during
/execution may be required when the project is implemented. This section describes
the mechanism to handle Changes that might affect the project environmental
impact. The changes in the project design may be:
First Order Change is one that leads to a significant departure from the project
described in the EIA such change in location, design of the project. The project will
be submitted to EPA for approval of change.
Second Order Change is one that is not significantly different from those described
in the EIA such as;
Increase in project personnel by 25%
Changes in the documentation and communication, stakeholders consultation
program
Third Order Change is one that is of little consequence to the EIA findings, such as;
Re-aligning a particular section of road to avoid cutting tree
Changes in the EMP
The possible categories of changes have been discussed above. The changes in the
project design or result of the environmental monitoring may necessitate changes in
the EMP. In this regard the following actions will be taken:
Bidding between PMO, contractor and consultants representatives.
Based on the discussion during the meeting a change report will be produced
collectively which will include the additional EMP clauses.
A copy of the report will be sent to the head offices of PMO, the Contractor and
the Consultants.
All relevant project personnel will be informed of the additions. These additions
will be reported in the Consultants monthly environmental reports.
Midterm review of the EMP to review any changes that might affect the project
environmental impact.
8.8. ESTIMATED COST OF ENVIRONMENTAL MANAGEMENT
The total cost of the environmental and social management of the proposed project is
about 11.100 million Rupees. This includes the cost of environmental and social cost
, environmental and social trainings ,tree plantation, waste disposal plan , emergency
response plan, traffic management plan, third –party monitoring. Cost estimates of
New Khanki Barrage Project (NKBP) IEE Report
8‐47
mitigation and other environmental management measures are summarized in Table
– 8.10. All these costs have been incorporated into the project budget.
Table 8.10: Cost Estimates for Environmental Management
Sr. # Item Rs. In million
1 Water sampling & testing 0.200
2 Air sampling & testing 0.200
3 Purchase of Noise meter 0.050
4 Purchase of DO meter 0.100
5 Purchase of EC meter 0.020
6 Maintenance of equipment 0.030
7 Traffic Management 0.100
8 Tree plantation 1.000
9 Waste Disposal 0.500
10 Waste water Treatment 0.500
11 Environment Audit 1.200
12 EHS Training 2.000
13 Timber plant (Eucalyptus) compensation 5.000
14 Plants of ornamental & historic value 0.200
Total 11. 1
Note: The land, crop losses, structures and some private tree costs are covered
under the LARP which is under preparation.
New Khanki Barrage Project (NKBP) IEE Report
8‐48
ANNEXURE -1
Checklists
TABLE - 1 CHECKLIST FOR CAMP SITE
Description Status Notes
Is the camp layout according to the design
documents?
Yes
No
Has the campsite been selected in consultation with
the consultants’ environmental team
Yes
No
Have the photographs been taken to record the pre
camping conditions?
Yes
No
Are there any settlements within 500 meters of the
campsite
Yes
No
Has the camp been established in the existing
clearings / designated area?
Yes
No
Was the hunting, fishing, or capturing wildlife, or
discharging fireman avoided
Yes
No
Was the harassment or pushing of wildlife avoided Yes
No
Has any vegetation been cleared?
If yes, is the vegetation loss significant?
If yes, have mitigation measures been discussed and
agreed?
Yes
No
Yes
No
Yes
No
Has any trees felled? Yes
No
Has the topsoil been removed and stored separately? Yes
No
Have the trees or bushes been burnt? Yes
No
Have bushes been disposed of in a water body or dry
streambed?
Yes
No
Has the natural drainage been disturbed or blocked? Yes
No
Has the septic tank been built for sewerage?
Yes
No
New Khanki Barrage Project (NKBP) IEE Report
8‐49
Has the sump been built for wastewater disposal? Yes
No
Has the sump been built in absorbent soil? Yes
No
Has the sump been built down-slope from the camp? Yes
No
Is the sump covered, in order to reduce access of
insects and animals?
Yes
No
Do the fuel storage facilities have adequate
secondary containments arrangements in case of
leakage or spilling?
Yes
No
Is the concrete pad has been constructed for fuel, oils
and other chemical liquid transfer
Yes
No
Is the firefighting equipment available near fuel
storage area/
Yes
No
Is the fuel storage downwind and down slope of the
camp?
Yes
No
Is there any other combustible or flammable material
in the fuel storage area?
Yes
No
Are the fuel tanks properly marked with their
contents?
Yes
No
Note:
Signature Date
ESU
Consultants’ Environmentalist
Contractor’s Environmentalist
New Khanki Barrage Project (NKBP) IEE Report
8‐50
Table - 2 Checklists for Construction Work Site
Description Status Notes
Is the construction site layout is according to the
design documents?
Yes
No
Has the construction site selected in consultation with
the consultants’ environmental team
Yes
No
Have the photographs been taken to record the pre-
construction conditions?
Yes
No
Are there any settlements within 500 meters of the
construction
Yes
No
Has the construction site been established in the
existing clearings or designated site
Yes
No
Does the temporary diversion channel built per
specifications
Yes
No
Was the hunting, fishing, or capturing wildlife, or
discharging fireman avoided
Yes
No
Was the harassment or pushing of wildlife avoided Yes
No
Was the disposal of waste material in the protected
area avoided
Yes
No
Has any vegetation been cleared?
If yes, is the vegetation loss significant?
If yes, have mitigation measures been discussed and
agreed?
Yes
No
Yes
No
Yes
No
Has any trees felled? Yes
No
Has the excavated earth / silt disposed of properly? Yes
No
Does the borrowed earth used for filling meet the
specifications
Yes
No
Has the natural drainage been disturbed or blocked? Yes
No
New Khanki Barrage Project (NKBP) IEE Report
8‐51
Has the sump been built for wastewater disposal? Yes
No
Is the sump covered, in order to reduce access of
insects and animals?
Yes
No
Do the fuel storage facilities have adequate
secondary containments arrangements in case of
leakage or spilling?
Yes
No
Is the concrete pad has be constructed for fuel, oils
and other chemical liquid transfer
Yes
No
Is the firefighting equipment available near fuel
storage area/
Yes
No
Is the fuel storage downwind and down slope of the
camp?
Yes
No
Is there any other combustible or flammable material
in the fuel storage area?
Yes
No
Are the fuel tanks properly marked with their
contents?
Yes
No
Note:
Signature Date
ESU
Consultants’ Environmentalist
Contractor’s Environmentalist
New Khanki Barrage Project (NKBP) IEE Report
8‐52
Table - 3 Checklists for Borrow Areas
Description Status Notes
Is the borrow area is marked according to the design
documents?
Yes
No
Has the borrow been selected in consultation with the
consultants’ environmental team
Yes
No
Have the photographs been taken to record the pre
camping conditions?
Yes
No
Are there any settlements within 500 meters of the
borrow area
Yes
No
Has the access roads been established in the existing
clearings / designated area?
Yes
No
Has any vegetation been cleared?
If yes, is the vegetation loss significant?
If yes, have mitigation measures been discussed and
agreed?
Yes
No
Yes
No
Yes
No
Has any trees felled? Yes
No
Have the trees or bushes been burnt? Yes
No
Has the natural drainage been disturbed or blocked? Yes
No
Has the borrow area been fenced to avoid animal
access and human safety
Yes
No
Is there proper mechanism to control dust pollution? Yes
No
Does the borrowed earth used for filling meet the
specifications
Yes
No
Note:
Signature Date
ESU
Consultants’ Environmentalist
Contractor’s Environmentalist
New Khanki Barrage Project (NKBP) IEE Report
8‐53
Table - 4 Checklists for Access Roads
Description Status Notes
Has the Access roads selected in consultation with
the consultants’ environmental team
Yes
No
Have the photographs been taken to record the pre-
construction conditions?
Yes
No
Are there any settlements within 500 meters of the
construction
Yes
No
Has the access roads been established in the existing
clearings or designated site
Yes
No
Was the harassment or pushing of wildlife avoided in
establishment of access roads
Yes
No
Has any vegetation been cleared?
If yes, is the vegetation loss significant?
If yes, have mitigation measures been discussed and
agreed?
Yes
No
Yes
No
Yes
No
Has any trees felled? Yes
No
Has the compacted gravel topping provided access
roads
Yes
No
Has the excavated earth / silt disposed of properly? Yes
No
Do the access roads have sufficient width? Yes
No
Do the diversion signs and required signs boards
placed on the access roads
Note:
Signature Date
ESU
Consultants’ Environmentalist
Contractor’s Environmentalist
New Khanki Barrage Project (NKBP) IEE Report
8‐54
Table 11: Environmental Issues Tracking Report
Tracking
No.
Log
Date
Source Location Issue Action
Required
Responsibility Target
date
Completion
Status
New Khanki Barrage Project (NKBP) IEE Report
9-1
9. GRIEVANCE REDRESS MECHANISM
9.1 GENERAL
The stakeholder or affected people’s concerns, complaints and grievances about the
project environmental performance will be received recorded and replied in a
systematic way using an understandable and transparent process that is gender
responsive, culturally appropriate and readily accessible to all segments of the
affected people at no cost and without retribution.
9.2 INSTITUTIONAL ARRANGEMENT
9.2.1 Management Responsibilities
Overall responsibility for environmental management will rest on PMU of the
Irrigation Department, Government of the Punjab.
i. The Executing Agency: PMU of Punjab Irrigation Department (PID)
ii. Supervising and Monitoring: Environmental Unit of PMU. Agency
iii. General Assistance to all: Head PMU/The Project Director, Irrigation above
agencies in their Department will facilitate communications, respective tasks
logistics and data collection as and when required.
iv. Logistic Support: Head PMU/The Project Director, Irrigation Department shall
provide the logistic support and shall be the focal point for the construction
activity.
(i) Project Management Unit (PMU)
The overall responsibility for the implementation of Environmental
management/Monitoring Plan rests with the Project Management Unit (PMU) along
with the assistance of Environmental Unit (EU) of PMU. The EU consists of Director
Environment & Sociology, Deputy Director Environment and Deputy Director
Sociology.
PMU will assume overall responsibility for ensuring:
That while executing the contract and undertaking the construction all environmental
norms, regulations and requirements promulgated by Pakistan Environmental
Protection Council (PEPC), Pakistan Environmental Protection Act (PEPA),
Environmental Protection Agency (EPA) Punjab and environmental safeguard
policies of Asian Development Bank , with respect to the work site and adjacent
New Khanki Barrage Project (NKBP) IEE Report
9-2
areas are fully respected and implemented. Overall responsibility for implementation
of EMP. Ensure that Contractor and Construction Supervision Consultants appoint a
dedicated environmental officer and allied staff. PMU will also ensure that all
environmental personnel are authorized to implement the socio- environmental
policies and requirements of the EMP. Coordinate with relevant government
departments and stakeholders on concerned socio-environmental issues. Inspect
and monitor residual impacts of the rehabilitation work and observe documentation of
the impacts during the construction phase. Inspect the significance of impact in case
of unanticipated change in the project. Construction Supervision Consultants will
assist and advise PMU in implementation of EMP. Inspect and monitor residual
impacts of the rehabilitation work and observe documentation of the impacts during
the construction phase. Inspect the significance of impact in case of unanticipated
change in the project. Construction Supervision Consultants will assist and advise
PMU in implementation of EMP.
(ii) Environment Unit (EU) of PMU
The Environmental Unit (EU) within PMU will monitor Project performance.
The EU will function in coordination with the Construction Supervision
Consultants and will receive reports from them on behalf of PMU.
EU will prepare and submit biannual Environmental Monitoring Reports to ADB.
(iii) Head PMU/The Project Director
The Project Director shall provide or arrange the logistics including communication,
transport and accommodation to all visiting persons/teams experts from any of the
above monitoring units and shall coordinate with the contractor(s) to facilitate the
visits/inspections.
(iv) Contractor
The contractor will be responsible for implementation of the project EMP. The
contractor will ensure that EMP for the project is implemented fully and must be
integrated into the Project implementation and made integral part of the contract
document. For any default damages so caused will be remediated by the contractor
at his own cost and expenses. In case the contractor fails to rectify the damage the
employer will remediate at the risk and cost of the contractor. The amount will be
determined by the Construction Supervision Consultants which will be adjusted from
New Khanki Barrage Project (NKBP) IEE Report
9-3
amount due to the contractor. The contractor will also be responsible for
communicating with and training of his staff in environmental aspects and
implementation of the EMP. The contractor will develop and get approved Health,
Safety & Environment (HSE) Plan from Construction Supervision Consultants before
the commencement of the Physical works on site.
(v) Construction Supervision Consultants
The construction supervision consultants will be responsible to ensure quality of work
and fulfillment of contractual obligations. Environmental Specialist of the construction
supervision consultants will ensure that all the environmental and social provisions
comply with the applicable standards. He/She will confirm that the day-to-day
construction activities are carried out in environment friendly manner and periodic
environmental training programs and workshops are organized for the consultant’s
and contractor’s staff. It would be responsibility of the Construction Supervision
Consultant to submit monthly environmental monitoring report to PMU
Project Organizational Structure
The organizational structure for the environment management / monitoring
implementation is shown below. The role of the organization is described in exhibit 1.
New Khanki Barrage Project (NKBP) IEE Report
9-4
Organizational Chart for EMP Implementation
New Khanki Barrage Project (NKBP) IEE Report
9-5
9.3 ENVIRONMENT & SOCIAL COMPLAINTS REGISTER
The consultant’s environmental team will maintain an environment & social complaint
register at camp site office to document all complaints received from the local
communities. The register will also record the measures taken to mitigate these
concerns. The final report will be communicated to Environmental section of PMU.
The Project Monitoring team shall carry out the monitoring of the implementation of
social and environmental mitigation measures as per ADB Safeguard Policy
Statement. The details of Grievance Redress Mechanism related with social issues
of the project are provided in the RAP.
Table 9.1 Grievance Resolution Process
Land / Crop Compensation Issues Project / Other Items Compensation Issues
Complaint resolution will be attempted
at office of SDO 2. If still unsettled, a
grievance will be lodged to the Head
PMU/PD. He will redress in 10 days.
Complaint resolution will be attempted at
village level through GRC* in one week. 2. If
still unsettled, a grievance can be referred to
court of law.
d) Coordination Initiatives
The various agencies identified above need to be coordinated carefully so as to
obtain effective, smooth and timely reply to all the non-compliance. Complaints &
Grievances will be addressed through three different processes as described in
Table 9.1 below:
∗ Grievance Redress Committee (GRC) consisting on concern SDO and DD-
Environment.
New Khanki Barrage Project (NKBP) IEE Report
1
ANNEX A: FORMS AND QUESTIONNAIRES
Name of Interviewer: ------------------------ Date: ------------------------
--------------
(a) Settlement: -------------------------------- (b) Union Council: ---------
---------
(c) Tehsil: -------------------------------------- (d) District: -----------------------------
1. Name of Respondent -----------------------------------------?
2. What is your father’s name -----------------------------------------?
3. What is your age?
Age years 15 – 25 --------------
25 – 35 --------------
35 – 45 ---------------
Above 45 ---------------
4. Marital Status.
1. Married 2. Unmarried
5. What is your caste /ethnic group----------------------------------?
New Khanki Barrage Project (NKBP) IEE Report
2
6. What is your language----------------------------------?
7. What is your educational qualification?
1. Illiterate 2. Primary 3. Middle
4. Metric 5. Intermediate 6. Above
8. What is your profession-------------------------------------?
9. What is your average monthly income?
Income Rs. Less than 5,000 -------------------
5,000 – 10,000 -------------------
10000 – 15000 -------------------
15,000 – 20,000 --------------------
Above 20,000 --------------------
10. What is type of your family system?
1. Joint 2. Nuclear
11. Do you marry outside your tribe?
Formatted: Indent: Left: -0.25", First line:
Formatted: Indent: Left -6.31 ch
New Khanki Barrage Project (NKBP) IEE Report
3
1. Yes (Exogamy) 2. No (Endogamy)
12 What is employment status of your family members
1. Govt. Employee 2. Private Employee
3. Self Employed 4. Unemployed
5. Household
13
1413 What are your major sources of income
1. Agriculture 2. Cattle (meat, hides & wool)
3. Trade /Business 4. Poultry
5. General Labour 6. Milk /Ghee Selling
7. Service 8. Any other
1514 How much is your average monthly expenditure
Expenditure Rs. Less than 5000 -------------
5,000 – 10,000 -------------
10,000 – 15,000 -------------
Above 15,000 -------------
1615 What is type of ownership of your house
1. Self Owned 2. Rented
3. Free on Landlord property 4. Relative House (Free)
Formatted: Indent: Left: -0.25", First line: 0"
Formatted: Indent: Left: 0.5"
New Khanki Barrage Project (NKBP) IEE Report
4
1716 What is nature of construction of your house
1. Kacha 2. Pacca 3. Semi-pacca
1817 Which of the following facilities are available in your house
1. Electricity 2. Water Supply
3. Gas 4. Telephone
5. Sewerage
19
2018 What are the sources of water for your domestic use
1. Public Water Supply 2. Hand Pumps
3. Channel 4. Any other
2119 What are the sources of water for your agriculture use
1. Canals 2. Public Water Supply
3. Channels 4. Rain
5. Any other
2220 What is your Landholding
1. Cultivated Land ------------------------
2. Uncultivated Land ------------------------
3. Cultivable Waste ------------------------
4. Orchards ------------------------
New Khanki Barrage Project (NKBP) IEE Report
5
2321 What is status of ownership of your land
1. Owner 2. Owner-cum-tenant
3. Tenant
2422 What do you grow mostly in your agriculture land
1. Wheat 2. Cotton 3. Sugarcane
4. Fodder 5. Vegetable 6. Maize
7. Fruits Orchards 8. Any other
2523 In your opinion, should this Project be implemented here
1. Yes 2. No
If yes, then reasons If no, then reasons
----------------------------------------- -----------------------------------------
----------------------------------------- -----------------------------------------
----------------------------------------- -----------------------------------------
----------------------------------------- -----------------------------------------
----------------------------------------- -----------------------------------------
2624 In your opinion, what will be possible impacts of this road
During Construction -----------------------------------------------
-----------------------------------------------
-----------------------------------------------
New Khanki Barrage Project (NKBP) IEE Report
6
-----------------------------------------------
-----------------------------------------------
After Construction -----------------------------------------------
-----------------------------------------------
-----------------------------------------------
-----------------------------------------------
-----------------------------------------------
2725 What protective measures do you suggest to safeguard your interests
----------------------------------------------
----------------------------------------------
----------------------------------------------
----------------------------------------------
----------------------------------------------
New Khanki Barrage Project (NKBP) IEE Report
7
ANNEX - B
FIRST ROUND OF PUBLIC CONSULTATION
Sr. No. Officials Contacted Title
1 Mr. Shahid Saleem Chaudhry EX-En. Khanki Headworks
2 Mr. Shafiq Ahmed SDO Headworks Khanki
3 Mr. Khadim Hussain Sub Engr Headworks Khanki
4 Mr. Abdul Ghaffar Sub Engr. Khanki
5 Mr. Arshad Ahmed Jamadar Khanki Headworks
6 Mr. Ijaz Ahmed Sounding Mistry, Khanki Headworks
7 Mr. Nasar Ahmed Head Boatman Khanki Headworks
8 Mr. Nasrullah Regulation, Khanki
9 Mr. Muhammad Riaz Boatman Khanki
10 Mr. Muhammad Riaz Naib Jamadar, Khanki
11 Mr. Ghulam Rasool Artificiar, Khanki
12 Mr. Muhammad Anwar Beldar, Khanki
13 Mr. Liaqat Ali Regulation Beldar, Khanki
New Khanki Barrage Project (NKBP) IEE Report
8
Sr. No. Officials Contacted Title
14 Mr. Muhammad Aslam Guage reader, Khanki
15 Mr. Muhammad Asif Bharoke Fish watcher, Khanki
16 Mr. Nazar Muhammad Ratta Wildlife Inspector, Khanki
17 Mr. Raza Ahmed Khan Ex-En RE Shadiwal Power House
18 Mr. Naseem Ahmed Khan SDO Shadiwal Power House
19 Engr. Bashir Zahid JE, PRO Electrical, Shadiwal Power
House
20 Engr. Muhammad Anwar Lengah, JE, PRO water, Shadiwal
Power House
Member of Public in Khanki Barrage Area interviewed
Sr. No. Name Village
1 Arshad s/o Nazar Muhammad Wadhan Nathu Kote
2 Nasir s/o Nazar Muhammad Wadhan Nathu Kote
3 Muhammad Riaz s/o Muhammad Bashir Wadhan Nathu Kote
4 Muhammad Afzal s/o Ch. Bahawal Bukhsh Jut Nathu Kote
5 Gul Hussain s/o Nawab Nathu Kote
6 Muhammad Anwar s/o Bashir Ahmed Basiana Numberdar Nathu Kote
7 Muhammad Bashir s/o Khushi Muhammad Machchi Nathu Kote
8 Shaukat Ali s/o Muhammad Ali Jutt Kahloon Kot Kahluan
9 Alta Muhammad s/o Khushi Kot Kahluan
10 Muhammad Yousaf s/o Muahammad Islam Din Rajpoot Kot Kahluan
11 Mehdi Hussain s/o Amir Ali Rajpoot Kot Kahluan
New Khanki Barrage Project (NKBP) IEE Report
9
Sr. No. Name Village
12 Nasrullah s/o Abaidullah Hanjra Kot Kahluan
13 Mian Javed s/o Faiquir Ahmed Hanjra Kot Kahluan
14 Muhammad Afzal s/o Mian Khan Kot Kahluan
15 Muhammad Malik s/o Bahawal Bukhsh Kot Kahluan
16 Muhammad Aslam s/o Muhammad Hanif Kot Kahluan
17 Manzoor Huassian s/o Rehmat Khan Cheema Kot Kahluan
18 Nazir Ahmed s/o Rehmat Khan Cheema Kot Kahluan
19 Liaquat Ali s/o Muhammad Nazir Cheema Numberdar Kot Kahluan
20 Muhammad Ramzan Cheema Kot Kahluan
21 Shabbir Hussain s/o Muhammad Shafi Cheema Rattowali
22 Atta Muhammad Numberdar s/o Rehamt Ali Waraich Rattowali
23 Ghulam Nabi s/o Sardar Muhammad Jutt Rattowali
24 Muhammad Akram s/o Nawab Cheema Rattowali
25 Muhammad Ejaz s/o Atta Muhammad Rattowali
26 Muhammad Ashraf s/o Nazar sahi Rattowali
27 Syed Maqbool Hussian Shah s/o Usool Hussian Shah Rattowali
28 Hassan Mehmood s/o Sardar Cheema Rattowali
29 Muhammad Ashraf s/o Ghulam Haider Rattowali
30 Muhammad Anwer s/o Muhammad Khan Cheema Rattowali
31 Ramzan S/O Mian Khan Rattowali
32 Muhammad Ashraf s/o Ali Muhammad Machi Rattowali
33 Muhammad Irshad s/o Hayat Muhammad Rattowali
34 Muhammad Sadiq s/o Mian Khan Rattowali
New Khanki Barrage Project (NKBP) IEE Report
10
Sr. No. Name Village
35 Muhammad Riaz Cheema Churri Mar Gorali
36 Muhammad Javed Wadhan Gorali
37 Muhammad Anwer Jhammer Gorali
38 Irsah Shah Syed Gorali
39 Syed Masoom Shah Gorali
40 Muhammad Tufail Waraich s/o Ghulam Haider Waraich Gorali
41 Nazir Ahmed s/o Rehmat Khan Cheema Khanki
42 Abdul Majeed s/o Nawab Khan Cheema Khanki
43 Atta Muhammad Cheema Khanki
44 Muhammad Saleem s/o Ghulam Qadir Waraich Khanki
45 Muhammad Aslam s/o Muhammad Hussian Cheema Khanki
46 Muhammad Hanif s/o Ibrahim Araeen Khanki
47 Haji Zahoor Hussain Shah Thathi
Baluch
48 Chaudhry Rasool Ahmed Arain Kot Imam
Bakhsh
49 Chaudhry Tariq Duraji Shadiwal
50 Chaudhry Muhammd Sharif Sandu Kot Manj Din
Third Round of Public Consultations / Disclosure
S. No
Village Name/ Venue
Total House hold
Population DateNo of
ParticipantMain
Concerns Expectations
1 Khanki 500 3500 21-7-
201112
Construction of Park
Employment Opportunities
2 Irrigation Colony
25 150 22-7-
18 Construction of Mosque
Construction of new Irrigation
Formatted: Font: Arial
Formatted: Font: 11 pt
Formatted: Font: 11 pt
Formatted: Font: 11 pt
New Khanki Barrage Project (NKBP) IEE Report
11
S. No
Village Name/ Venue
Total House hold
Population DateNo of
ParticipantMain
Concerns Expectations
2011 and School Colony
3 Thatti Baloch
250 1800 22-7-
201122
Earliest Commencing of Studs Construction
Safety from flood
4 Burg Cheema 200 1500
23-7-
201114
Earliest Commencing of Studs Construction
Safety from flood
Total 66
ANNEX - C
FORMAT OF SFA
1. This is a Social Frame Work Agreement between Resident Engineer (RE) Khanki
Barrage Construction Project representing the Irrigation and Power Department
Government of Punjab and the villagers’ committee of Khanki Barrage Area,
whose names have been inscribed below in their presence and full consent.
Sr. No. Village Name Father’s Name
1 Khanki
2 Kot Immam Bakhsh
3 Kot Nathu
4 Thati Balouch
5
6
Formatted: Font: 11 pt
Formatted: Font: 11 pt
Formatted: Font: 11 pt
Formatted: Font: 11 pt
Formatted: Font: 11 pt
New Khanki Barrage Project (NKBP) IEE Report
12
2. We, the committee of village leader/elders of Jinnah Barrage area have agreed
unanimously to nominate ________________________________as our
chairman and authorize him to enter into a Social Framework Agreement with the
Jinnah Barrage Rehabilitation Project on our behalf and on his own behalf. We
understand and pledge that this Social Framework Agreement will be a binding
on us and the RE throughout the currency of the construction work as well as the
operational phase.
3.
Signatures or Village Signature/Left Signature/Left 1 2 3 4 5 6 7 8 9 10
4. By mutual consent it is agreed the Irrigation and Power Department
i. Shall not occupy any agricultural land or acquire any other land during
the construction of this project.
ii. Shall not cause any damage or reduction in the water supply in the
canals during the construction period of the project, except in case of
force majeure e.g. high floods, strong storms or any other act of God.
iii. Shall not cause any disturbance to any public archaeological heritage
or a place of worship.
iv. Shall not interfere in the social political or tribal balance of the area.
v. Shall/wherever possible leave local physical infrastructure in no worse
condition than it was at the start of the project
5. Also, by mutual consent it is agreed that all the villagers residing in the area in the
vicinity of the project named in Clause 1 collectively and severally
i. Shall not interfere in the location of labor camps, material depots,
equipment yards and all the approach roads to be used during project
construction phase, all of which will be located on the land of Irrigation
and Power Department.
ii. Shall not interfere if the Irrigation and Power Department decides to
move the construction of the subsidiary weir elsewhere to a more
suitable site as long as the activity remains on Irrigation and Power
Department’s own land.
New Khanki Barrage Project (NKBP) IEE Report
13
iii. Shall not receive any discharge of water, wastewater, wastewater
sludge or oil spills to any graveyard or archaeological site
iv. Shall not cause any damage to wildlife or trees and no villagers will be
involved in killing, poaching or hunting of any animal or birds.
v. Shall not allow reduction or official interference in existing services
and facilities e.g. education, health, electricity, drinking water supplies,
religious and social congregations.
vi. Shall not allow any interference in our tribal, commercial or social
norms, and we understand that no land acquisition or involuntary
resettlement is involved under the project.
vii. Agree to respect and observe the cautions on the sign boards
displayed by project authorities and shall not remove or cause to be
removed any signboards or installations put up by the Resident
Engineer.
viii. This SFA has been signed this < date > < month > <year >
at_____________________
Signatures Signatures
Resident Engineer Chairman Villagers’ Committee
Full name and address
Name and Address
Counter singed
Executive Engineer( Jinnah Barrage)
Full name and address
New Khanki Barrage Project (NKBP) IEE Report
14
New Khanki Barrage Project (NKBP) IEE Report
15
New Khanki Barrage Project (NKBP) IEE Report
16
Formatted: Font: Arial