independent valuation of luapula processing facility … · 2019. 3. 19. · mets is regarded as a...

112
Winmar Resource Ltd 20 Kings Park Road West Perth WA 6010 P: (08) 6462 1421 www.winmarresources.com.au 19 March 2019 Australian Securities Exchange Limited 20 Bridge Street Sydney NSW 2000 INDEPENDENT VALUATION OF LUAPULA PROCESSING FACILITY COMPLETED Winmar Resources Limited (“Winmar” or the “Company”) (ASX: WFE) is pleased to advise that the independent valuation of the Luapula Processing Facility has now been completed. The independent valuation of the Luapula Processing Facility was determined using a number of valuation methodologies as follows: ASSET VALUE CLASS VALUATION COMMENTS As is” basis US$33,353,000 Based on second hand plant as is and including all infrastructure Historical cost” basis US$46, 317,668 Purchased and installed Going concern” basis US$70,000,000 Assumes US$10m to get the project up and running New plant” basis US$85,000,000 All equipment new and clear site The independent valuation strongly vindicates the decision by the Winmar Board of Directors to pursue the acquisition of a 50% interest in the Luapula Processing Facility. The independent valuation was conducted by Mr Damian Connelly, Principal Consulting Engineer of METS Engineering Group Pty Ltd (METS); and the valuation was conducted in accordance with the written guidelines of the Australasian Institute of Mining and Metallurgy (AusIMM) Valmin Code (2016). Mr Connelly is a licensed valuer and a Fellow of AusIMM and a member of various other industry bodies and associations including the Canadian Institute of Mining and Metallurgy (CIMM) and the South African Institute of Mining and Metallurgy (SAIMM). METS is regarded as a specialist in the areas of mineral processing, engineering design and independent plant valuations having operated for over 30 years and completed over 6,000 individual work assignments. The independent valuation further confirmed that “there are no fatal flaws with the project and the risks for the project can be managed” and furthermore that “there is power, water and good infrastructure to support the project including offices, workshops, stores and accommodation facilities on site.” For personal use only

Upload: others

Post on 19-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

  • Winmar Resource Ltd 20 Kings Park Road West Perth WA 6010

    P: (08) 6462 1421

    www.winmarresources.com.au

    19 March 2019

    Australian Securities Exchange Limited 20 Bridge Street Sydney NSW 2000

    INDEPENDENT VALUATION OF LUAPULA PROCESSING FACILITY COMPLETED

    Winmar Resources Limited (“Winmar” or the “Company”) (ASX: WFE) is pleased to advise that the independent valuation of the Luapula Processing Facility has now been completed.

    The independent valuation of the Luapula Processing Facility was determined using a number of valuation methodologies as follows:

    ASSET VALUE CLASS VALUATION COMMENTS

    “As is” basis US$33,353,000 Based on second hand plant as is and including all infrastructure

    “Historical cost” basis US$46, 317,668 Purchased and installed

    “Going concern” basis US$70,000,000 Assumes US$10m to get the project up and running

    “New plant” basis US$85,000,000 All equipment new and clear site

    The independent valuation strongly vindicates the decision by the Winmar Board of Directors to pursue the acquisition of a 50% interest in the Luapula Processing Facility.

    The independent valuation was conducted by Mr Damian Connelly, Principal Consulting Engineer of METS Engineering Group Pty Ltd (METS); and the valuation was conducted in accordance with the written guidelines of the Australasian Institute of Mining and Metallurgy (AusIMM) Valmin Code (2016).

    Mr Connelly is a licensed valuer and a Fellow of AusIMM and a member of various other industry bodies and associations including the Canadian Institute of Mining and Metallurgy (CIMM) and the South African Institute of Mining and Metallurgy (SAIMM).

    METS is regarded as a specialist in the areas of mineral processing, engineering design and independent plant valuations having operated for over 30 years and completed over 6,000 individual work assignments.

    The independent valuation further confirmed that “there are no fatal flaws with the project and the risks for the project can be managed” and furthermore that “there is power, water and good infrastructure to support the project including offices, workshops, stores and accommodation facilities on site.”

    For

    per

    sona

    l use

    onl

    y

  • 2

    The Company engaged METS (refer ASX Announcement dated 24 January 2019) to complete an independent valuation principally to address concerns raised by ASX following submission by the Company of an Application for In-Principle Advice.

    Specifically, ASX was concerned that “the history of the Luapula Processing Facility, having been constructed over a period of approximately 4 years at an estimated cost of US$80 million, in operation for a period of 2 years, following which it was placed on care and maintenance with its written down value to nil but subsequently re-valued to approximately US$30 million.”

    A copy of the independent valuation report is provided in its entirety as an attachment.

    The Company’s securities currently remain suspended and this will continue to be the case until the Company has satisfied Listing Rules 11.1.2 and 11.1.3, and re-complied with Chapters 1 and 2 of the ASX Listing Rules in order to complete the proposed acquisitions of the 50% interest in the Luapula Processing Facility and the 100% interest in additional exploration licenses (refer ASX announcements of 23 July 2018 and 3 December 2018).

    Based on the above, the Company will continue to seek to complete the proposed acquisitions and by extension the reinstatement of its securities to official quotation.

    The Company notes however that admission to the official list (and by extension, reinstatement of securities to quotation pursuant to listing rule 11.1.3) is in ASX’s absolute discretion and ASX may grant or refuse admission without giving any reasons.

    Please contact the undersigned if you require any further information in relation to this matter.

    Mr Jason Brewer

    Chairman

    Winmar Resources Limited

    Tel: +61 8 6462 1421

    For

    per

    sona

    l use

    onl

    y

  • METS Engineering Group Pty Ltd

    Level 3, Parliament Place West Perth WA 6005 PO Box 1699, West Perth WA 6872

    P: (+61 8) 9421 9000

    ABN 92 625 467 674

    W: www.metsengineering.com E: [email protected]

    TESTWORK MANAGEMENT OPERATIONS PROCESS CONTROL ENGINEERING STUDIES MINERALS PROCESS INNOVATION TRAINING PROCESSING

    WINMAR RESOURCES

    LUAPULA PROCESS PLANT

    VALUATION

    CONFIDENTIAL

    Project No: J5185

    Date: 18/03/2019

    Damian Connelly Principal Consulting Engineer Chartered Professional Engineer Email: [email protected]

    For

    per

    sona

    l use

    onl

    y

  • J5185 - WINMAR RESOURCES LTD.

    REV DESCRIPTION ORIG REVIEW APPROVAL DATE CLIENT APPROVAL

    DATE

    A-F General revisions DC

    D. Connelly

    N/A

    N/A

    G Internal review DC

    D. Connelly

    JB

    11/03/2019

    CONFIDENTIALITY

    This document and its contents, including work scope, methodology and commercial

    terms will be treated in strict confidence by Winmar Resources and the contents will

    be used by Winmar Resources only for their own use.

    Passing of this document to a third party, duplication or re-use of this document, in

    whole or part, electronically or otherwise, is not permitted without the expressed

    written consent of METS Engineering Group Pty Ltd.

    DISCLAIMER

    With respect to all the information contained herein, neither METS Engineering

    Group Pty Ltd, nor any officer, servant, employee, agent or consultant thereof make

    any representations or give any warranties, expressed or implied, as to the accuracy,

    reliability or completeness of the information contained herein, including but not

    limited to opinions, information or advice which may be provided to users of the

    document.

    No responsibility is accepted to users of this document for any consequence of

    relying on the contents hereof.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page i

    TABLE OF CONTENTS

    1. EXECUTIVE SUMMARY ........................................................................... 1

    2. INTRODUCTION ....................................................................................... 4

    2.1 Location and Access ..................................................................................................... 4

    2.2 General DRC Map......................................................................................................... 5

    2.3 Plant Aerial View ........................................................................................................... 6

    2.4 Local Map Area ............................................................................................................. 7

    2.5 Other Aspects ............................................................................................................... 7

    3. SCOPE OF WORK .................................................................................... 9

    3.1 Objectives ..................................................................................................................... 9

    3.2 Site Visit ........................................................................................................................ 9

    3.3 Valuation Report ......................................................................................................... 10

    3.4 Valuation Types .......................................................................................................... 11

    3.4.1 Historical Cost ........................................................................................................ 11

    3.4.2 As Is Value ............................................................................................................. 11

    3.4.3 New Cost Approach ............................................................................................... 11

    3.4.4 Market (Comparable Sales) Approach .................................................................. 11

    3.4.5 Going Concern Approach ...................................................................................... 12

    3.5 Resources Utilised ...................................................................................................... 12

    3.6 Project Management, Meetings and Reporting .......................................................... 12

    4. PROCESS DESCRIPTION ...................................................................... 13

    4.1 Process Description .................................................................................................... 13

    4.2 Flowsheet Changes .................................................................................................... 14

    5. FLOWSHEETS ........................................................................................ 15

    5.1 Overall Flowsheet ....................................................................................................... 15

    5.2 Key Metrics ................................................................................................................. 16

    5.3 Overall Block Flow ...................................................................................................... 16

    5.4 Crushing Plant............................................................................................................. 17

    5.5 Grinding Flowsheet ..................................................................................................... 18

    5.6 Leaching & Impurity Precipitation Flowsheet .............................................................. 19

    5.7 Fume Treatment Removal .......................................................................................... 20

    5.8 Copper Precipitation ................................................................................................... 21

    5.9 Cobalt Precipitation ..................................................................................................... 22

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page ii

    5.10 Copper Cobalt Drying & Packing ................................................................................ 23

    5.11 Reagents ..................................................................................................................... 24

    5.12 Tailings Disposal ......................................................................................................... 25

    5.13 Process Control........................................................................................................... 25

    5.13.1 Distributed Control System (DCS) ......................................................................... 25

    5.13.2 Benefits .................................................................................................................. 26

    5.13.3 Instrumentation ...................................................................................................... 27

    5.13.4 Development .......................................................................................................... 27

    5.13.5 The Benefits of Process Control ............................................................................ 27

    6. INFRASTRUCTURE ................................................................................ 29

    6.1 General Infrastructure ................................................................................................. 29

    6.2 Power .......................................................................................................................... 29

    6.3 Water ........................................................................................................................... 31

    6.4 Climatic Environment .................................................................................................. 31

    6.5 Accommodation .......................................................................................................... 32

    6.6 Offices ......................................................................................................................... 33

    6.7 Weighbridge ................................................................................................................ 33

    6.8 Messing ....................................................................................................................... 34

    6.9 Workshops & Stores Buildings .................................................................................... 35

    6.10 Fuel Tanks .................................................................................................................. 35

    6.11 Other Assets ............................................................................................................... 35

    7. ASSET VALUATION ................................................................................ 36

    7.1 Competent Person ...................................................................................................... 36

    7.2 Valmin Code ................................................................................................................ 36

    7.3 Summary of Asset Values ........................................................................................... 37

    7.4 Historical Cost ............................................................................................................. 37

    7.5 As Is Plant & Infrastructure Value ............................................................................... 38

    7.6 New Plant & Infrastructure .......................................................................................... 39

    7.7 Market (Comparable Sales) Approach ....................................................................... 39

    7.7.1 Tiger Resources ..................................................................................................... 39

    7.7.2 Kalongwe Copper Cobalt ....................................................................................... 40

    7.7.3 MMG Kinserve ....................................................................................................... 42

    7.7.4 Tenke Fungurume.................................................................................................. 42

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page iii

    7.8 Kinsenda Copper ........................................................................................................ 42

    7.9 Market Value ............................................................................................................... 43

    7.10 Fire Sale Value............................................................................................................ 43

    7.11 Income (Earnings) Approach ...................................................................................... 44

    8. REFURBISHMENT .................................................................................. 46

    8.1 Crushing Area ............................................................................................................. 46

    8.2 Engineering and Installation of the Crushing Circuit ................................................... 48

    8.3 Milling and Milled Ore Storage .................................................................................... 50

    8.4 Classification Cyclones ............................................................................................... 51

    8.5 Slurry Holding Tank Internals ...................................................................................... 53

    8.6 Vibratory Feeders........................................................................................................ 53

    8.7 Instruments – Milling (Process) ................................................................................... 54

    8.8 Auxiliary Works – Milling Area .................................................................................... 55

    8.9 Leaching and Impurity Precipitation ............................................................................ 56

    8.10 Fabricate and Install Tank Covers .............................................................................. 57

    8.11 Install Air Blowers and Air Sparging System .............................................................. 58

    8.12 Fume Scrubbing System (SO2 Gas) .......................................................................... 59

    8.13 Instrumentation – Leaching and Impurity Removal (Process) .................................... 61

    8.14 Re-Engineering of the Sulphuric Acid Feed Tank Arrangement ................................. 61

    8.15 Additional Leaching Tanks and Continuous Operation ............................................. 62

    8.16 Install Bunding Around Leaching Tanks ..................................................................... 63

    8.17 Check Integrity of Rubber Lining of Tanks .................................................................. 64

    8.18 Leach Residue Filtration – Conveyor Extension ......................................................... 64

    8.19 Relocation of Cu and Co Liquor Holding Tanks – Cu and Co Precipitation Feed ...... 65

    8.20 Copper & Cobalt Precipitation ..................................................................................... 66

    8.21 Copper and Cobalt Product Drying and Packaging .................................................... 67

    8.22 Reagents Area ............................................................................................................ 67

    8.23 Reagent Preparation Leaching and Precipitation Area (Hydrated Lime and SMBS) . 68

    8.24 Additional Sulphuric Acid Tank to be Located in the Leaching Area .......................... 69

    8.25 Lime Slaking Mill ......................................................................................................... 69

    8.26 Tailings Storage Facility and Water Treatment ........................................................... 70

    8.27 Design and Construction of Water Cleaning (Impurity Removal) Circuit .................... 71

    8.28 Design and Construction of Expanded (off-site) New Tailings Storage Facility (TSF) 72

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page iv

    8.29 Services and Infrastructure ......................................................................................... 72

    8.30 Process Water Storage ............................................................................................... 73

    8.31 Replenishment of Diesel Tank Genset ....................................................................... 73

    8.32 Roofing Over Leaching Section .................................................................................. 74

    9. PLANT CONDITION ................................................................................ 75

    9.1 Battery Limits .............................................................................................................. 75

    9.2 General ....................................................................................................................... 75

    9.3 Civil ............................................................................................................................. 75

    9.4 Mechanical .................................................................................................................. 75

    9.5 Electrical ...................................................................................................................... 76

    9.6 Structural ..................................................................................................................... 76

    9.7 Piping .......................................................................................................................... 76

    9.8 Technical Suitability .................................................................................................... 77

    9.9 Copper Price Chart ..................................................................................................... 77

    9.10 Cobalt Price Chart ....................................................................................................... 78

    9.11 Mobile Plant ................................................................................................................ 78

    9.12 First Fill ........................................................................................................................ 78

    9.13 Crushing & Ore Storage Photos ................................................................................. 79

    9.14 Milling & Ore Storage .................................................................................................. 80

    9.15 Leaching & Impurity Precipitation ............................................................................... 81

    9.16 Copper-Cobalt Precipitation ........................................................................................ 82

    9.17 Product Drying & Packaging ....................................................................................... 83

    9.18 Tailings ........................................................................................................................ 84

    9.19 Reagents ..................................................................................................................... 86

    9.20 Onsite Laboratory........................................................................................................ 86

    9.21 Process Water Storage Dam ...................................................................................... 86

    10. RISKS ...................................................................................................... 87

    10.1 Luapula Risk Assessment Process............................................................................. 87

    10.2 Establish the Context of the Review ........................................................................... 88

    10.3 Identify the Risks ......................................................................................................... 88

    10.4 Analyse the Risks........................................................................................................ 88

    10.5 Prioritise the Risks ...................................................................................................... 88

    10.6 Luapula Plant Risk Table ............................................................................................ 89

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page v

    10.7 Risks Identified ............................................................................................................ 89

    11. FUTURE WORK ...................................................................................... 92

    11.1 Marketing .................................................................................................................... 92

    11.2 Project Execution Plan (PEP) ..................................................................................... 92

    11.3 Project Schedule ......................................................................................................... 93

    11.4 Project Budget............................................................................................................. 93

    11.5 Mechanical Equipment List ......................................................................................... 93

    11.6 Plant Drawings ............................................................................................................ 93

    11.7 Commissioning & Ramp Up ........................................................................................ 93

    11.8 Operating Manuals ...................................................................................................... 94

    11.9 Flowsheet Optimisation ............................................................................................... 94

    12. REFERENCES ........................................................................................ 95

    APPENDIX A – MECHANICAL EQUIPMENT LIST .............................................. 96

    APPENDIX B – HISTORICAL COST .................................................................... 99

    APPENDIX C – AS IS VALUE ............................................................................ 100

    APPENDIX D – NEW REPLACEMENT VALUE ................................................. 101

    LIST OF FIGURES

    Figure 2-1: General map of the DRC .................................................................................... 5

    Figure 2-2: Aerial view of the process plant ......................................................................... 6

    Figure 2-3: Breakdown of plant area by operating sections .................................................. 7

    Figure 5-1: Overall process flowsheet ................................................................................ 15

    Figure 5-2: Overall block flow diagram for the Luapula process plant .............................. 16

    Figure 5-3: Process flow diagram for the Luapula crushing plant ...................................... 17

    Figure 5-4: Process flowsheet for the Luapula grinding circuit .......................................... 18

    Figure 5-5: Process flowsheet for the Luapula leaching circuit .......................................... 19

    Figure 5-6: Process flowsheet for the Luapula impurity removal area ............................... 20

    Figure 5-7: Process flowsheet for the Luapula Cu precipitation circuit ............................. 21

    Figure 5-8: Process flowsheet for the Luapula Co precipitation flowsheet ........................ 22

    Figure 5-9: Process flowsheet for Luapula drying and packaging area .............................. 23

    Figure 5-10: Process flowsheet for the Luapula reagents area ............................................ 24

    Figure 5-11: Process flowsheet for the Luapula tailings area ............................................. 25

    Figure 5-12: Typical simple control room .......................................................................... 26

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page vi

    Figure 6-1: Onsite generators .............................................................................................. 30

    Figure 6-2: Onsite bores ...................................................................................................... 31

    Figure 6-3: Yearly climate for the DRC .............................................................................. 32

    Figure 6-4: Accommodation units ....................................................................................... 32

    Figure 6-5: Office units ....................................................................................................... 33

    Figure 6-6: Conference room .............................................................................................. 34

    Figure 6-7: Mess facilities ................................................................................................... 34

    Figure 6-8: Workshop & stores building............................................................................. 35

    Figure 7-1: Spider chart for sensitivity analysis of the Luapula financial model ............... 45

    Figure 9-1: Electrical switchboards currently installed ....................................................... 76

    Figure 9-2: Historical copper price chart ............................................................................ 77

    Figure 9-3: Historical cobalt price chart ............................................................................. 78

    Figure 9-4: Jaw Crusher ...................................................................................................... 79

    Figure 9-5: Ball mills .......................................................................................................... 80

    Figure 9-6: Ground ore storage ........................................................................................... 80

    Figure 9-7: Leach tanks ....................................................................................................... 81

    Figure 9-8: Stainless steel tanks .......................................................................................... 81

    Figure 9-9: Stainless steel tanks for precipitation ............................................................... 82

    Figure 9-10: Diesel-fired dryer ........................................................................................... 83

    Figure 9-11: Solar drying shed ............................................................................................ 83

    Figure 9-12: Tailings filtration shed.................................................................................... 84

    Figure 9-13: Tailings filters................................................................................................. 85

    Figure 9-14: Tailings dry stacking ...................................................................................... 85

    Figure 9-15: Sulphuric acid storage tanks ........................................................................... 86

    LIST OF TABLES

    Table 1-1: Summary of asset values ..................................................................................... 2

    Table 5-1: Plant metrics ...................................................................................................... 16

    Table 7-1: Summary of asset values ................................................................................... 37

    Table 7-2: Project historical costs ....................................................................................... 37

    Table 7-3: Kalongwe CAPEX cost ..................................................................................... 41

    Table 10-1: Subjective risk ranking matrix ......................................................................... 89

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page vii

    Table 10-2: Luapula process plant risk register .................................................................. 90

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 1

    1. EXECUTIVE SUMMARY

    Mr Jason Brewer, Chairman of Winmar Resources Ltd. requested Mr Damian

    Connelly, Principal Consulting Engineer from METS Engineering Group Pty Ltd

    (METS) to prepare a Valuation Report for the Luapula Process Plant at Likasi in the

    Democratic Republic of Congo (DRC).

    METS conducted a site visit to the Luapula Processing Facility to collect information,

    photos, equipment lists, flowsheets and meet and discuss with key personnel from

    Winmar Resources and the DRC JV Company. The condition of the plant is good but

    will require refurbishment to get back into functional working order. The scope of

    work for the asset valuation report to determine the plant value in detail was based

    on the following groupings:

    Crushing and stockpiling

    Milling and storage

    Leaching and precipitation

    Drying and packing

    Tailings

    Civil structures

    Infrastructure

    Mechanical, piping and electrical installation

    The basic mechanical equipment list was the basis of calculating an asset value

    based on the following asset classes and a physical inspection on site.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 2

    Table 1-1: Summary of asset values

    Asset Value Class Value ($USD) Comment

    1.Historical basis $46,317,668 Purchased and installed

    2.As Is Value $33,353,500 Based on second hand plant as is

    including infrastructure

    3.New Plant Value $85,000,000 All new equipment and clean site

    4.Market Sales No similar data available

    5.Going Concern Value $70,000,000 Assumes $10M spent to get project up

    and running, current estimates of income

    and costs

    There is power, water and good infrastructure to support the project including offices,

    workshops, stores and accommodation facilities on site. The project is based on

    processing 25 tph of copper cobalt ore. The ore can be purchased in the Likasi area

    with typical feed grades of 1-2% cobalt and 2% copper. Purchase terms are 60 days

    based on based on a percentage of London Metal Exchange (LME) prices and with a

    healthy processing margin. Previously, acid was not recycled and this is one of the

    largest cost inputs in the process.

    There are no fatal flaws with the project and the risks for the project can be managed.

    As a part of future project development work Winmar Resources needs to develop a

    Project Execution Plan (PEP) outlining refurbishment, the project schedule, budget

    and commissioning activities. The technical basis of the project is sound and

    installation of a solvent extraction and electrowinning circuit (SX-EW) would add

    significant value to the project.

    A level of automation in the plant would be recommended.

    A budget of US$10M is required to get the project operational which includes

    refurbishment, first fill, working capital and commissioning.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 3

    Competent Person

    The information in this report that relates to the Processing and Metallurgy for the

    Luapula Project in DRC and is based on a site visit and fairly represents, information

    and supporting documentation compiled by Damian Connelly who is a Fellow of The

    Australasian Institute of Mining and Metallurgy and a full time employee of METS

    Engineering Group. Damian Connelly has sufficient experience relevant to the style

    of mineralisation and process plant under consideration and to the activity which he is

    undertaking to qualify as a Competent Person as defined in the 2012 Edition of the

    ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore

    Reserves’. Damian Connelly consents to the inclusion in the report of the matters

    based on his information in the form and context in which it appears.

    Valmin Code

    This Report has been prepared in accordance with the Australasian Institute of

    Mining and Metallurgy (AusIMM) Valmin Code (2016) written guidelines.

    The purpose of the Australasian Code for the Public Reporting of Technical

    Assessments and Valuations of Mineral Assets (VALMIN Code) is to provide a set of

    fundamental principles, minimum requirements and supporting recommendations to

    assist in the preparation of relevant Public Reports on Mineral Assets. The VALMIN

    Code is based on international good practice as currently employed in the Mineral

    industry, but allows for professional judgement in certain instances. The resulting

    Public Reports must be reliable and should be clear, concise, effective and include all

    the Material information required by investors and their advisers when making

    investment decisions. Subject to provisions in paragraph 1.3, AIG and AusIMM

    Members must adhere to the VALMIN Code regardless of where or for whom the

    Public Reports are prepared or the location of the Mineral Assets under

    consideration.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 4

    2. INTRODUCTION

    Mr Jason Brewer, Managing Director of Winmar Resources requested Mr Damian

    Connelly, Principal Consulting Engineer from METS Engineering Group Pty Ltd

    (METS) to prepare a Valuation Report for the Luapula Process Plant at Likasi in the

    Democratic Republic of Congo (DRC).

    2.1 Location and Access

    The Luapula Process plant is located in the heart of the Congolese Copperbelt, near

    the town of Likasi, DRC. Likasi is accessible by sealed road from Lubumbashi (~120

    km) or Kolwezi (~180 km). Both Lubumbashi and Kolwezi have airports that service

    international flights. A regional map showing the location of Likasi relative to other

    population centres is provided in Figure 2-1 below.

    The Luapula process facility is located 400 m from the main Lubumbashi-Likasi road,

    approximately 7 km from the Likasi town centre and 4 km on the Likasi-Lubumbashi

    Copperbelt Road toll gate. Coordinates of the process plant are provided in an aerial

    photograph of the plant facility in Figure 2-2. The facility covers an area of ~12.5 ha

    (~30 acres) and is surrounded by a high brick-and-mortar wall with heavy duty gates

    to restrict access. There are four similar processing plants in the area and a large

    Chinese owned processing facility next door.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 5

    2.2 General DRC Map

    Figure 2-1 illustrates the general map of the DRC. The town of Likasi is located in the

    south-east corner of the map.

    Figure 2-1: General map of the DRC

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 6

    2.3 Plant Aerial View

    Figure 2-2 shows an aerial view of the plot of land occupied by the existing process

    plant. The area bordered in green is the Luapula Process Plant which is currently not

    operating. The adjacent plant is the Chinese plant, which is currently operating.

    Figure 2-2: Aerial view of the process plant

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 7

    2.4 Local Map Area

    Figure 2-3 indicates the relative positions of the processing areas of the plant.

    Figure 2-3: Breakdown of plant area by operating sections

    2.5 Other Aspects

    The following nearby features are noteworthy:

    Winmar Resources will contribute the capital to get the project operational for

    a 50% interest in the Joint Venture (JV).

    The copper cobalt process plant is located 7 km from the centre of Likasi,

    which hosts a skilled workforce

    Winmar Resources will purchase copper cobalt ore from local mines in the

    Likasi area similar to the other processors.

    The Likasi Gecamines workshop in Likasi offers a heavy steel fabrication and

    machinery repair services. Larger workshops are available in Lubumbashi.

    There are a total of 4 similar process plants located within 5 kms

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 8

    A Chinese-owned plant is located adjacent, which processes artisanal-mined

    materials

    The other plants are larger, with conventional tailings storage facilities installed

    The main Copperbelt road, which is sealed, is 400 m from the site gate,

    Larger open pit resources and landholdings located nearby are available for

    acquisition and expansion.

    Winmar Resources have exploration tenements with cobalt resources which

    could be possible feedstock for the plant in the future.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 9

    3. SCOPE OF WORK

    3.1 Objectives

    The objective of this work is to perform a plant valuation based on replacement value

    of existing facilities. The work will provide Winmar Resources with sufficient

    information to progress to the next stage of acquisition.

    The scope of work envisaged for the report is to determine the plant value in detail

    based on the following groupings:

    Crushing and stockpiling

    Milling and storage

    Leaching and precipitation

    Drying and packing

    Tailings

    Civil structures

    Infrastructure

    Mechanical, piping and electrical installation

    3.2 Site Visit

    METS conducted a site visit to the Luapula Processing Facility in late February,

    2019. This was to collect technical information, meet and discuss with key personnel

    from Winmar Resources and the DRC JV company. In addition, photos were taken

    and discussions held with personnel on site.

    References to other projects in DRC were made.

    Process Facility Valuation

    It is assumed that Winmar Resources will provide documents and information

    necessary to assist in valuation of the process facility. This should include, but not be

    limited to the following:

    Process flowsheets

    Equipment list and details

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 10

    Facility building list and details

    General arrangement drawings of the facility

    Photographs of the plant and equipment

    METS complied with the best-in-class cost estimating methodology to perform the

    plant valuation to an accuracy of +/- 25% to 30%. The valuation will evaluate the

    current cost value and replacement cost for all infrastructure and major equipment.

    3.3 Valuation Report

    METS generated a final valuation report for Winmar Resources to provide sufficient

    details and accuracy to be acceptable by a regulatory body, i.e. ASX.

    Several values were estimated for the project. Value refers to the desirability of

    ownership of an asset and more particularly the market value.

    Types of value:

    Market Value

    Replacement value new

    Going concern value

    Referenced value to other projects

    The broad questions of “what is the value of the plant?” or “what is the plant worth?”

    can be answered by investigating the Market Value or price realised in an open

    market where both a willing and able buyer and seller can communicate price and

    conditions of sale to execute the transaction. The value derived will be dependent on

    the level of willingness of each party and by the conditions of the agreement.

    Legal definition of “fair market value” as defined by the judicial courts is the amount of

    cash or in terms reasonably equivalent to cash, for which in all probability the

    property would be sold by a knowledgeable owner willing but not obligated to sell to a

    knowledgeable purchaser who desired but is not obligated to buy.

    The purpose of the report proposed would be to recommend an estimated market

    value at a fixed point in time. Real market value is constantly changing with market

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 11

    conditions and expectations and can only be derived at the moment of contractual

    agreement between buyer and seller.

    There are three generally accepted approaches to market value estimation;

    Historical Cost Approach

    As Is Value

    New Plant Value

    Market (Comparable Sales) Approach

    Going Concern Value

    3.4 Valuation Types

    3.4.1 Historical Cost

    This is based on records of purchase of the original plant and equipment including

    land and buildings.

    3.4.2 As Is Value

    This is based on the mechanical equipment list and a factored installed cost as is. It

    includes civil, structural, piping and transport costs as installed.

    3.4.3 New Cost Approach

    This method calculates the value of the plant in terms of new replacement cost. This

    means the cost of an asset which is identical in size, quality and state of repair. The

    cost approach is rarely applicable in valuing mining properties and is generally the

    least reliable method of valuation due to escalation and contingencies. Few projects

    come in at their predicted cost.

    3.4.4 Market (Comparable Sales) Approach

    This approach is viewed by many as the best approximation of fair market value as it

    incorporates the effects of supply and demand in the current market. This method

    looks at the sales history for similar assets in the market place. The assumption is

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 12

    made that a buyer will not pay more than the cost of acquiring a suitable substitute

    for the property in question.

    However, there are limitations to this approach which include the difficulty in finding

    similar assets due to the nature of most resources being unique in terms of size,

    geographical location, degree of development and that there are only minimal

    numbers of transactions. Even an actual previous sale of the property in question

    may not be a reliable indicator of its value if market conditions such as commodity

    price expectations, production costs and ore reserve information have changed.

    3.4.5 Going Concern Approach

    Future annual net earnings generated from the asset, discounted to the present day

    using an appropriate interest rate. This method assumes that a buyer would not be

    willing to pay more for an asset than the present value of the income it can derive.

    This used a cash flow model developed by Winmar Resources.

    3.5 Resources Utilised

    Process flowsheets

    Process description

    Equipment list

    Close out reports

    Detailed assessment

    Current plant values and changing trends in the market place

    Recent DRC plant sales and throughput rating

    METS database

    3.6 Project Management, Meetings and Reporting

    As part of METS ongoing quality assurance, regular internal project update meetings

    were held to monitor progress and assess the way forward. At the completion of the

    project, METS produced a detailed report encompassing the major findings from the

    comprehensive study. The report also includes recommendations for the way

    forward.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 13

    4. PROCESS DESCRIPTION

    4.1 Process Description

    The process involves crushing the ore and then feeding into ore bins. The material is

    withdrawn from ore bins into one of two ball mills that operate in closed circuit with

    cyclones, with cyclone overflow being held in slurry storage tanks. Slurry is pumped

    from the holding tanks to leaching tanks where sulphuric acid and SMBS are added

    to solubilise metal and adjust the solution ORP to convert Co(III) into acid soluble

    Co(II). The liquor is then neutralised to pH ~4 using hydrated lime and air blown into

    the tanks to allow oxidation of Fe(II) to Fe(III) thereby allowing its precipitation from

    solution.

    The slurry from leaching/neutralisation is filtered in plate-and-frame filters, and

    washed with water, with the liquor and wash water combined and directed to the Cu

    precipitation storage tank. The solids dumped from the filter press are conveyed to

    the tailings storage pad and dry-stacked. Liquor run-off from the dry-stack pad is

    collected and returned to the process water tank.

    Liquor in the Cu precipitation holding tank is pumped to copper precipitation tanks,

    where the pH is adjusted to pH ~7 with slaked lime, thereby effecting the precipitation

    of copper. The precipitated copper is recovered in plate-and-frame filter presses, and

    the liquor is directed to the cobalt precipitation holding tanks. The copper product is

    dried – if necessary – and then packaged and trucked to a nearby copper refinery for

    dissolution and production of cathode copper.

    Liquor from the cobalt precipitation holding tank is pumped to the cobalt precipitation

    tanks, where the pH is adjusted to pH ~8.5 with magnesia. Precipitated cobalt is

    recovered by filtration in a filter press, with liquor directed to the process water tank; a

    portion of this water will likely need to be bled to an impurity removal circuit where

    impurities such as Mn and MgO are removed. The cobalt hydroxide product is dried –

    using a combination of solar drying and fuel drying – after which it is packaged,

    loaded into sea containers and freighted to markets overseas.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 14

    4.2 Flowsheet Changes

    The old flowsheet did not recycle acid which is a major cost. Also the old flowsheet

    did not produce separate copper and cobalt products.

    The crushing plant will need to be installed using existing equipment and new

    conveyors.

    A weightometer on the mill feed belt would be better to control the feedrate

    and for metallurgical accounting.

    Future changes should include a high rate pre-leach thickener to increase the

    leach density and reduce acid consumption. This would allow better control of

    the grind size as well. Currently P80 150 µm is the desired grind size.

    Future changes will also include solvent extraction electrowinning (SX-EW),

    which will allow acid recycling and the production of very clean products. The

    use of LIX 984N for copper and Cyanex 272 for cobalt is well established.

    A process water pond would allow flexibility of operation and minimise water

    consumption.

    Using a sulphur burner would be more cost effective rather than buying

    SMBS.

    An acid fume scrubber is required to minimise environmental acid and

    improve occupational health and safety.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 15

    5. FLOWSHEETS

    5.1 Overall Flowsheet

    A high-level process flowsheet of the Luapula plant is shown in Figure 5-1. Parts of

    the flowsheet – particularly the crushing area – are currently in varying stages of

    completion.

    Figure 5-1: Overall process flowsheet

    The Luapula process plant is suitable for the recovery of copper and cobalt – as

    intermediate products – from oxide mineralisation typical of the African Copperbelt.

    The key metrics of the Luapula process plant are summarised in Table 5-1; these

    have been derived from equipment sizes and process appraisals, and typical

    metallurgical characteristics of CuCo ores in the region.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 16

    5.2 Key Metrics

    Table 5-1: Plant metrics

    Unit Value Source

    Plant Availability % 80 Estimate

    Plant Throughput Tph 25 Design basis

    Annual Throughput Tpa 175,000 Calculation

    Products * Bagged Copper Hydroxide

    Bagged Cobalt Hydroxide

    *Quantity will depend on ore grade and recoveries.

    5.3 Overall Block Flow

    Figure 5-2: Overall block flow diagram for the Luapula process plant

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 17

    5.4 Crushing Plant

    Figure 5-3: Process flow diagram for the Luapula crushing plant

    The jaw crusher, impact crushers and screen are onsite but need to be relocated and

    installed. The ore is soft oxidised ore so the impact crushers will be suitable.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 18

    5.5 Grinding Flowsheet

    Figure 5-4: Process flowsheet for the Luapula grinding circuit

    The grinding flowsheet uses conventional ball mills in closed circuit with cyclones.

    The use of a pre-leach thickener would be justified based on potential acid savings.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 19

    5.6 Leaching & Impurity Precipitation Flowsheet

    Figure 5-5: Process flowsheet for the Luapula leaching circuit

    The leach circuit is a batch process and occurs very quickly on the oxidised ore.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 20

    5.7 Fume Treatment Removal

    Figure 5-6: Process flowsheet for the Luapula impurity removal area

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 21

    5.8 Copper Precipitation

    Figure 5-7: Process flowsheet for the Luapula Cu precipitation circuit

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 22

    5.9 Cobalt Precipitation

    Figure 5-8: Process flowsheet for the Luapula Co precipitation flowsheet

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 23

    5.10 Copper Cobalt Drying & Packing

    Sun drying and a diesel fired dryer are used to dry the concentrates before packing

    and shipping.

    Figure 5-9: Process flowsheet for Luapula drying and packaging area

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 24

    5.11 Reagents

    Figure 5-10: Process flowsheet for the Luapula reagents area

    The biggest reagent is sulphuric acid which is shipped in from Zambia by road. Transport costs are high and VAT tax is 35%.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 25

    5.12 Tailings Disposal

    Figure 5-11: Process flowsheet for the Luapula tailings area

    The tailings are filtered and conveyed to a dry stacking area.

    5.13 Process Control

    The plant has no process control and everything is manual. Whilst labour costs are

    low and this was suitable in the past this is not the case now. A low costs DCS

    system would be justified.

    5.13.1 Distributed Control System (DCS)

    The typical Citec process control system is very good. The hardware costs for such

    systems are very low. For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 26

    Figure 5-12: Typical simple control room

    5.13.2 Benefits

    The Simplicity of distributed control system works well and is normally used by the

    operators. Calibration of field equipment is needed to fully utilise its potential-

    weightometers, density meters, mag flow meters etc.

    The page areas covered with the Distributed Control system would be Crushing,

    Milling, Flotation, Leaching, Precipitation, Filtration, Drying, Reagents, Lime System,

    Utilities, Alarms etc.

    PLC’s are typically used for start-up and shutdown of the crushing circuit, milling

    circuit, filtration circuits and alarms.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 27

    5.13.3 Instrumentation

    The crushing plant should use PLC start-up and shutdown with interlocks and trip

    wires, under speed protection, level switches and blocked chute switches and

    alarms. The impact crushers should be protected with metal detectors.

    The DCS system would be beneficial for the crushing plant.

    There is no ball mill instrumentation or PLC for alarms and lubrication sequencing

    and control. There are no nucleonic density gauges installed on the cyclone feed line

    nor a magnetic flowmeter which would allow mass flow control.

    5.13.4 Development

    The basic distributed control system can be enhanced by some of the following:

    PLC for crushing circuit

    Ball mill circuit optimisation

    o Automatic control of mill discharge density using ore water ratio (hosing down the mill floor drops the cyclone overflow density)

    o Cyclone mass flow measurement and control (mag flow and density)

    Automation of filters

    Continuous leaching and ORP measurement

    Reagent control, i.e. acid stage addition

    5.13.5 The Benefits of Process Control

    For the Luapula process plant to achieve optimum performance the installation of

    automatic control loops needs to be considered and additional auto loops utilised

    around the distributed system.

    One of the problems with process control is that management sees the cost and is

    not convinced of the monetary benefits. The arguments used such as the plant only

    has a short life are true however the payback is usually short. Some of the typical

    benefits in a plant such as this are:

    Increased mill throughput

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 28

    Savings in acid and better control

    Savings in lime with automatic pH control

    Increased copper and cobalt recovery by maximising throughput (milling

    circuit mass flow control)

    Reduction in manpower dependence

    Instrumentation in the crushing plant such as a weightometers for plant

    control

    A metal detector protection in the crushing plant

    Increase in management control

    High return on investment

    Simplification of management reporting

    Consistent product quality

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 29

    6. INFRASTRUCTURE

    6.1 General Infrastructure

    The process plant is on the outskirts of Likasi township. Likasi is a city in Haut-

    Katanga Province, in the south-east of the Democratic Republic of Congo.

    Likasi has a population of 447,000 and remains a centre for industry, especially

    mining, and is a transport hub for the surrounding region. There are mines and

    refineries supplied by nearby deposits of copper and cobalt. There are excellent

    workshops in both Likasi and Lubumbashi including service contractors. There is a

    local workforce and support services in Likasi close by.

    6.2 Power

    The site has its own diesel fired generators which are suitable to run the process

    plant. The site is not currently connected to the grid and would be subject to a

    reconnection fee. The grid power is typically subjected to frequent outages. Diesel

    fuel tanks are installed on site with a fuel truck.

    The Democratic Republic of the Congo has reserves of petroleum, natural gas, coal,

    and a potential hydroelectric power generating capacity of around 100,000 MW. The

    Inga Dam, alone on the Congo River, has the potential capacity to generate 40,000

    to 45,000 MW of electric power, sufficient to supply the electricity needs of the whole

    Southern Africa region. An ongoing uncertainty in the political arena and a resulting

    lack of interest from investors has meant that the Inga dam's potential has been

    limited.

    In 2001, the dam was estimated to have an installed generating capacity of 2,473

    MW. It is estimated that the dam is capable of producing no more than 650–750 MW,

    because two-thirds of the facility's turbines do not work. There were plans to raise the

    Inga power station to 44,000 MW capacity by 2010. The African Development bank

    agreed to supply $8 million towards it. The government also agreed to strengthen the

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 30

    Inga-Kolwezi and Inga-South Africa interconnections and to construct a second

    power line to supply power to Kinshasa.

    In 2007, the DROC had a gross production of public and self-produced electricity of

    8,302 million kWh. The DROC imported 78 million kWh of electricity in 2007. The

    DROC is also an exporter of electric power. In 2003, electric power exports came to

    1.3 TWh, with power transmitted to the Republic of Congo and its capital, Brazzaville,

    as well as to Zambia and South Africa. There were plans to build the Western Power

    Corridor (Westcor) to supply electricity from Inga III hydroelectric power plant to the

    Democratic Republic of the Congo, Angola, Namibia, Botswana and South Africa.

    The national power company is Société nationale d'électricité (SNEL).

    Only 6% of the country has access to electricity. As of 2003, 98.2% of electricity was

    produced by hydroelectric power. The DRC is a member of three electrical power

    pools. These are SAPP (Southern African Power Pool), EAPP (East African Power

    Pool) and CAPP (Central African Power Pool).

    Figure 6-1: Onsite generators

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 31

    6.3 Water

    The site has four water bores which supply water for processing. There is also a

    creek at the bottom of the property. Water supply is not an issue for the scale of the

    project considered. The water is good quality.

    Figure 6-2: Onsite bores

    6.4 Climatic Environment

    The climate is tropical with a typical wet and dry season. See Figure 6-3.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 32

    Figure 6-3: Yearly climate for the DRC

    6.5 Accommodation

    There are a number of rooms on site for key management accommodation. The

    operators would live locally in Likasi and commute to the plant each day.

    Figure 6-4: Accommodation units

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 33

    6.6 Offices

    There are solid brick rendered offices on site which would support the operation. This

    would include administration, accounting, purchasing, management and support

    shared services.

    Figure 6-5: Office units

    6.7 Weighbridge

    There is a weighbridge on site which is used for weighing ore deliveries to the site.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 34

    Figure 6-6: Conference room

    6.8 Messing

    There is a food preparation area and dining facilities for personnel living in the accommodation units.

    Figure 6-7: Mess facilities

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 35

    6.9 Workshops & Stores Buildings

    The site has a number of workshops where repairs and maintenance can be

    undertaken. The workshops include typical equipment and a number of pump spares

    electric motors etc.

    Figure 6-8: Workshop & stores building

    6.10 Fuel Tanks

    There are two diesel fuel tanks on site to supply fuel to the site.

    6.11 Other Assets

    There are a number of earthmoving equipment trucks etc in various states of repair. A CAT excavator in good condition and a fuel truck. There is a stores area with equipment spares, valves, pipes and other items.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 36

    7. ASSET VALUATION

    The asset valuation is based on a site visit and inspection of the facilities. The

    equipment list and infrastructure was used to build up the asset value based on

    knowledge of the equipment and asset values.

    7.1 Competent Person

    The information in this report that relates to the Processing and Metallurgy for the

    Luapula Project in DRC and is based on a site visit and fairly represents, information

    and supporting documentation compiled by Damian Connelly who is a Fellow of The

    Australasian Institute of Mining and Metallurgy and a full time employee of METS

    Engineering Group. Damian Connelly has sufficient experience relevant to the style

    of mineralisation and process plant under consideration and to the activity which he is

    undertaking to qualify as a Competent Person as defined in the 2012 Edition of the

    ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore

    Reserves’. Damian Connelly consents to the inclusion in the report of the matters

    based on his information in the form and context in which it appears.

    7.2 Valmin Code

    This Report has been prepared in accordance with the Australasian Institute of

    Mining and Metallurgy (AusIMM) Valmin Code (2016) written guidelines.

    The purpose of the Australasian Code for the Public Reporting of Technical

    Assessments and Valuations of Mineral Assets (VALMIN Code) is to provide a set of

    fundamental principles, minimum requirements and supporting recommendations to

    assist in the preparation of relevant Public Reports on Mineral Assets. The VALMIN

    Code is based on international good practice as currently employed in the Mineral

    industry, but allows for professional judgement in certain instances. The resulting

    Public Reports must be reliable and should be clear, concise, effective and include all

    the Material information required by investors and their advisers when making

    investment decisions. Subject to provisions in paragraph 1.3, AIG and AusIMM

    Members must adhere to the VALMIN Code regardless of where or for whom the

    Public Reports are prepared or the location of the Mineral Assets under

    consideration.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 37

    7.3 Summary of Asset Values

    Table 7-1: Summary of asset values

    Asset Value Class Value ($USD) Comment

    1.Historical basis $46,317,668 Purchased and installed

    2.As Is Value $33,353,000 Based on second hand plant

    3.New Plant Value $85,000,000 All new equipment

    4.Market Sales No similar data available

    5.Going Concern Value $70,000,000 Assumes $10M spent to get project up

    and running, current estimates of income

    and costs

    Note: Asset values are an estimate based on an inspection, building up spreadsheets

    based on the equipment list and infrastructure. Market conditions can change and

    this will be reflected in the values estimated.

    The worksheets used to develop the values are contained in the Appendices.

    7.4 Historical Cost

    The plant and facilities were established by a Lebanese company under the direction

    of Mr Jalal Zahwe who is a Mechanical Engineer. He supervised the construction of

    the plant and operated the plant for several years.

    The plant equipment was sourced from South Africa and transported to DRC. Apart

    from the transport cost there is a 15% VAT tax on goods imported into country.

    These costs were supplied by Jalal Zahwe.

    Table 7-2: Project historical costs

    No. Description Original Cash Cost ($USD)

    1 Acquisition of Land & Development 2,063,274

    2 Housing 1 284,385

    3 Housing 2 211,535

    4 Restaurant 173,737

    5 Administrative Building 1 265,588

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 38

    6 Warehouse 1 186,647

    7 Warehouse 2 373,294

    8 Staff Building 1 120,517

    9 Staff Building 2 91,131

    10 Under Construction 1 86,302

    11 Under Construction 2 17,745

    12 Gatehouses 82,302

    13 Cement Block Fence Wall 1,428,099

    14 Large Brick Fence Wall 41,958

    15 Weighbridge 76,699

    16 Prefabricated Buildings 13,584

    17 SNEL Substation 19,548

    18 Substation Under Construction 11,971

    19 Basins 23,963

    20 Storage Floor Tiles 34,850

    21 Driveway Doors 16,500

    22 Furniture 82,969

    23 Drains 622,724

    24 Tank – Septic 54,000

    25 Hall 1 381,808

    26 Hall 2 362,588

    27 Hall 3 711,815

    28 Hall 4 646,526

    29 Hall 5 525,846

    30 Hall 6 149,858

    31 Factories Equipment 33,276,957

    32 Electricity facilities 3,878,948

    TOTAL US$46,317,668

    The majority of the cost is in the process plant whereas the infrastructure and

    buildings account for 29%.

    7.5 As Is Plant & Infrastructure Value

    This is based on the mechanical equipment list and a factored installed cost as is. It

    includes civil, structural, piping and transport costs as installed. This means the cost

    of an asset which is identical in size, quality and state of repair.

    This assumes buying second hand equipment sourced from South Africa or

    elsewhere and installed. The asset value of the Luapula plant and infrastructure

    installed and ready to operate would be US$33,353,500. No first fill was included and

    the infrastructure was left at cost which could be argued as conservative. There is

    also mobile equipment on site which has not been included.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 39

    7.6 New Plant & Infrastructure

    This method determines to calculate the value of the plant in terms of new equipment

    cost. This means the cost of an asset which is identical in size, quality and sourced

    new.

    The asset value of the Luapula plant and infrastructure installed and ready to operate

    brand new would be approximately US$85,000,000.

    7.7 Market (Comparable Sales) Approach

    This approach is viewed by many as the best approximation of fair market value as it

    incorporates the effects of supply and demand in the current market.

    This method looks at the sales history for similar assets in the market place. The

    assumption is made that a buyer will not pay more than the cost of acquiring a

    suitable substitute for the property in question.

    However, there are limitations to this approach which include the difficulty in finding

    similar assets due to the nature of most resources being unique in terms of size,

    geographical location, degree of development and that there are only minimal

    numbers of transactions. Even an actual previous sale of the property in question

    may not be a reliable indicator of its value if market conditions such as commodity

    price expectations, production costs and ore reserve information have changed.

    7.7.1 Tiger Resources

    Tiger Resources will not be selling its Democratic Republic of the Congo mining and

    exploration assets to Sinomine HK for $260M.

    Tiger Resources that terms acceptable to the company were not achieved and it

    issued a notice of termination to Sinomine HK.

    The assets comprised of the Kipoi Project, Lupoto Project and La Patience permit.

    Announcing the sale in January, Tiger said it was facing "operational and financial

    headwinds".

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 40

    The Kipoi Copper Project is operated by Société d’Exploitation de Kipoi, a 95%-

    owned subsidiary of Tiger. It is located 75km northwest of Lubumbashi, the capital of

    Katanga Province, and in the central part of the Katanga Copper Belt. The Kipoi

    Mining Licence covers an area of 55sq km and contains a 12km-long extensively

    copper-cobalt mineralised segment. As of December 2014, mineral resources for the

    Kipoi Copper Project were 938,000 tonnes of copper.

    Sinomine is a geotechnical services company based in China with business lines in

    mineral exploration, mining project investments and operations, as well as technical

    and associated supporting services. Sinomine has an international network of

    operations, including existing operations in the DRC and across Africa. The company

    is listed on the Shenzhen Stock Exchange with a market capitalisation of over $530

    million.

    7.7.2 Kalongwe Copper Cobalt

    The Kalongwe Copper Cobalt Project (Kalongwe or the Project) is owned by

    Kalongwe Mining SA (KMSA) under a joint venture agreement between Nzuri Copper

    Limited (Nzuri) (85%), La Generale Industrielle et Commerciale au Congo (GICC)

    (10%) and the Democratic Republic of the Congo Government (5%). GICC is a

    Congolese company which is 90%-owned by Theo Mahuku, a respected Congolese

    businessman.

    In March 2015, KMSA filed an application for the conversion of the Exploration Permit

    to an Exploitation Permit based on a technical study and an approved

    environmental/social assessment (EIE). Ministerial approval was received in October

    2015 with an initial term of 30 years and renewal periods of 15 years.

    The Kalongwe deposit is situated within an Exploitation Permit which covers an area

    of ~8km² and includes the entire area proposed for mining and Project infrastructure.

    This permit allows for mining and processing on site and for the transport and sale of

    copper / cobalt concentrate product.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 41

    Nzuri has successfully completed an updated +15% accuracy Feasibility study (FS)

    in April of 2018 further reinforcing the technical and financial viability of the Project

    from the previous October 2017 FS.

    Updated Project FS highlights include:-

    Updated Ore Reserve of 7.99Mt at 2.94% Cu and 0.34% Co for 234,868t of

    contained Cu and 27,102t of contained Co. All production targets and forecast

    financial outcomes underpinned 100% by Ore Reserves.

    Kalongwe Stage 1 (“K1”) comprises an open pit mine and on-site 1Mtpa Dense

    Media Separation (DMS) processing plant.

    Table 7-3: Kalongwe CAPEX cost

    Main Area US $’000 %

    Construction Distributable/s 3,528 7

    Treatment Plant Costs 10,896 21

    Reagents and Plant Services 2,446 5

    Infrastructure 11,188 21

    Mining 7,155 13

    Management Costs 1,611 3

    KMSA Owner’s Project Costs 6,055 11

    Subtotal 42,879 81

    Contingency 4,968 9

    Taxes and Duties 5,274 10

    Total Project Build Cost US$ 53,121 100

    Project fully-permitted with 12-month timeline to production post-funding and Board

    approval.

    Significant opportunities to improve project economics and mine life through future

    staged project expansions, including leaching solutions for stockpiled cobalt-only ore/

    mineralised rejects from the DMS plant plus improved product pricing terms at offtake

    finalisation.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 42

    7.7.3 MMG Kinserve

    Kinsevere is a world-class copper mine located in the Democratic Republic of the

    Congo (DRC). Kinsevere was acquired by MMG in 2012 and is an important part of

    the company’s portfolio of high quality base metals assets.

    Through a focus on operational excellence, Kinsevere continues to deliver above

    nameplate capacity of 60,000 tonnes of copper cathode per annum.

    In 2017, Kinsevere produced 80,186 tonnes of copper cathode. This was the third

    consecutive year of stable and consistent production above 80,000 tonnes. The

    strong production was supported by significantly improved mining performance with

    total material movement increasing by 140% from 6.2 million tonnes in 2016 to 14.8

    million tonnes in 2017.

    7.7.4 Tenke Fungurume

    Mining giant Freeport McMoRan finalized a deal with China Molybdenum Inc.

    (CMOC) to sell the company’s controlling stake in the Tenke Fungurume copper mine

    in Democratic Republic of Congo (DRC), the company’s largest copper mine in

    Africa. Freeport sold their 56 percent stake in the Congolese project for $2.65 billion.

    At a glance, it would seem that everybody wins in Tenke’s recent sale. Freeport

    offloads the asset in an effort to reduce the company’s global $21 billion debt bill.

    When asked about the government’s position on the transaction, Minister of Mines

    Martin Kabwelulu questioned the opacity of the sale, adding that there must be a tax

    on the sale of the Congolese asset and that they will push the tax authority to claim it.

    But this tax may be more difficult to claim than they think. And while billions of dollars

    transfer between the two companies’ bank accounts, the citizens of DRC may not

    see a penny from the two billion dollar sale.

    7.8 Kinsenda Copper

    A feasibility study was completed by Metorex in 2013 which determined the viability

    of the Kinsenda Project. The ore reserves at the Kinsenda Project are planned to be

    For

    per

    sona

    l use

    onl

    y

    http://www.bloomberg.com/news/articles/2016-05-13/congo-plans-to-investigate-tax-freeport-sale-of-copper-mine

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 43

    extracted in two phases. Phase 1 will involve the high grade extraction of copper

    sulphides/oxides which is estimated to last for a period of ten years. Phase 2 which

    will involve the lower grade extraction of copper sulphides/ oxides, if determined to be

    economically feasible and undertaken, will allow the life of mine of the Kinsenda

    Project to be further extended beyond the ten year period. The Kinsenda Project is

    expected to produce, on average, approximately 24 ktpa of copper. The board of

    Metorex approved the development of the Kinsenda Project in April 2013 and the

    development has commenced since April 2013, and if the development were to

    proceed as planned, the first production is expected to occur during the first quarter

    of 2015. Total project capital expenditure is expected to be approximately US$ 319.4

    million.

    7.9 Market Value

    The market value is based on what a company would pay to acquire the assets. This

    can be based on the equipment discounted for age and condition plus the value of

    the infrastructure.

    Based on the above a likely comparative market value could be as follows.

    The asset value of the equipment and infrastructure is US$40,253,500.

    This would be on the basis of a company purchasing the whole plant. The exchange

    rate, cobalt price and other factors also come into play arriving at a price. The

    general condition of the Luapula equipment is very good which would assist

    achieving the nominated price.

    Selling the whole plant is better for the vendor and very attractive for the purchaser

    who also saves on engineering and has certainty with this project going forward.

    7.10 Fire Sale Value

    This is not appropriate because because this is a highly unlikely situation. The asset is unencumbered. F

    or p

    erso

    nal u

    se o

    nly

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 44

    7.11 Income (Earnings) Approach

    Future annual net earnings generated from the asset, discounted to the present day

    using an appropriate interest rate. This method assumes that a buyer would not be

    willing to pay more for an asset than the present value of the income it can derive.

    This requires a cash flow model which was supplied by Winmar Resources. The plant

    would have a higher value based on a resource and cash flow. A value under this

    scenario has been attempted at a high level and subject to a number of disclaimers

    the financial model NPV value is US$108,000,000. It is expected that a buyer would

    not pay the full NPV value but a discounted rate. On this basis US$70,000,000 might

    be achievable at the metal prices used and operating costs assumed. As a going

    concern the project has the highest value. This is however not the current value.

    Assumptions and Model Construction:

    It is unclear how OPEX and CAPEX figures are estimated.

    Logistics costs and royalties appear to have been estimated reliably, although

    there are no supporting calculations for other inputs to the financial model.

    Likewise to the capital upgrade costs. These will have a notable impact on the

    NPV as they will be required in the early stages of the project and are hence

    not subject to inflation.

    Inclusion of a 5% sustaining capital for an acquisition of an existing plant

    decreases economic risk of the project.

    No allowance for contingencies in financial model. This is possibly accounted

    for in sustaining or ‘other’ cost areas. Inclusion of a contingency would further

    reduce economic risk.

    A number of assumed values are time-independent. Notably feed grade and

    product recoveries. Some basic implementation of geometallurgy could

    improve the accuracy of the financial model.

    Notable Expenses:

    Leaching and reagents costs contribute approximately 63% of the processing

    OPEX.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 45

    Government and other royalties make up 45% of the logistics, exports and

    royalties expenses.

    Processing costs are reasonable

    Sensitivity:

    Figure 7-1: Spider chart for sensitivity analysis of the Luapula financial model

    The project is most sensitive to changes in cobalt feed grade, production and

    pricing.

    The difference in LME copper and cobalt pricing makes variations to the

    copper grade and recovery less significant to cobalt.

    For

    per

    sona

    l use

    onl

    y

  • Luapula Process Plant Valuation

    J5185 – Luapula Process Plant Valuation Page 46

    8. REFURBISHMENT

    Winmar Resources has developed a refurbishment programme in detail which is

    included hereafter.

    8.1 Crushing Area

    Background and Rationale

    There are existing jaw crushers (2 x) and impact crushers (2 x) (aka sand making

    machines) on the site, although they need to be refurbished and tested. There is also

    a cone crusher (1 x) on the site that – in some senses – is preferable over the impact

    crushers although discussions with the current owner of the cone crusher indicate

    that the cone crusher is not available for this project as it belongs as part of another

    plant being stored at the facility.

    Specific Works Required

    Specific items:

    1. Procure and install teeth on impact crushers

    2. Test mechanical functionality and operation of all crushers

    3. Furnish with crusher motors (in storage) and test

    4. Procure spare liners (jaw crushers) and teeth (impact crushers)

    5. Refurbish and test functionality of existing vibrating screen

    6. Furnish with motor

    7. Furnish with wear liners in high abrasion areas

    8. Furnish with screen panels

    9. Service all mechanical equipmen