in the high court of punjab and haryana at chandigarhnhai.org.in/spw/courtcase/fao 8377-14 nhai...
TRANSCRIPT
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
F.A.O. No.____________of 2014
National Highways Authority of India .…..Appellant
Versus
Sukhwinder Singh and others …..Respondents
I N D E X
Sr.No Particulars Date Page No. Court Fee1. Application for Exemption. 30.08.2014 1-2 3.00
2. Affidavit. 30.08.2014 3-4 ----
3. Application for Stay. 30.08.2014 5-6 3.00
4. Affidavit. 30.08.2014 7-8 ----
5. Grounds of Appeal 30.08.2014 9-17 ----
6. Affidavit 30.08.2014 18 ----
7. Memo of Parties 30.08.2014 19 500.00
8. Award passed by ADJ,(FTC)
Rupnagar 28.05.2014 20-30 9.00
9. Award passed by Arbitrator 03.03.2012 31-45 15.00
10. Award passed by Competent
Authority
04.05.2010 46-50 5.00
11 Power of Attorney alongwith
authority letter 30.08.2014 51-52 5.00
Total Rs. 540/-
Note : No Caveat has been received.
Chandigarh (Puneet Kaur Sekhon) Dated: 30.08.2014 Advocate Counsel for the Appellant
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
Civil Misc. Application No.______________ of 2014 IN
F.A.O. No.____________of 2014
National Highways Authority of India .…..Appellant/Applicant
Versus
Sukhwinder Singh and others …..Respondents.
Application U/s 151 of the C.P.C. seeking exemption
from filing certified copy & typed copy of the Awards
dated 04.05.2010 & 03.03.2012 passed by the
Competent Authority under the National Highways
Act, 1988 & the Arbitrator respectively; and typed
copy of the impugned Award dated 28.05.2014.
Respectfully Submitted;
1. That the applicant is filing the accompanying appeal against the Award
dated 28.05.2014 passed by the Learned Additional District Judge, (Fast Track
Court) Rupnagar dismissing the petition filed by the applicant under Section 34 of
the Arbitration and Conciliation act, 1996, by upholding the Award of the
Arbitrator dated 03.03.2012 enhancing the compensation awarded for the land
acquired.
2. That the applicant is filing the appeal alongwith certified copy of the
impugned Award. As at present the applicant is not having certified copy of the
awards dated 04.05.2010 & 03.03.2012 and to avoid delay in filing the appeal
true Photostat copy of the Original/Certified copy of the same is appended.
3. That the applicant undertakes to place on record the certified copies/typed
copies of the Awards on the record in case this Hon’ble Court so directs.
It is, therefore, most respectfully prayed that in the interest of justice
the present application may kindly be allowed and exemption may be granted
from filing certified copy & typed copy of the Awards dated 04.05.2010 &
03.03.2012 passed by the Competent Authority under the National Highways
Act, 1988 & the Arbitrator respectively; and typed copy of the impugned Award
dated 28.05.2014.
Chandigarh Dr. Puneet Kaur Sekhon Dated: 30.08.2014 Advocate Counsel for the Appellant/Applicant
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
Civil Misc. Application No.______________ of 2014 IN
F.A.O. No.____________of 2014
National Highways Authority of India .…..Appellant/Applicant
Versus
Sukhwinder Singh and others …..Respondents
Affidavit of O.C. Mathur, Project Director, National Highways
Authority of India, Project Implementation Unit-Chandigarh-
Bays No. 35-38, Sector-4, Panchkula.
I, the above named deponent do hereby solemnly state and affirm as under;
1. That the applicant is filing the accompanying appeal against the Award
dated 28.05.2014 passed by the Learned Additional District Judge, (Fast Track
Court) Rupnagar dismissing the petition filed by the applicant under Section 34 of
the Arbitration and Conciliation act, 1996, by upholding the Award of the
Arbitrator dated 03.03.2012 enhancing the compensation awarded for the land
acquired.
2. That the applicant is filing the appeal alongwith certified copy of the
impugned Award. As at present the applicant is not having certified copy of the
awards dated 04.05.2010 & 03.03.2012 and to avoid delay in filing the appeal
true Photostat copy of the Original/Certified copy of the same is appended.
3. That the applicant undertakes to place on record the certified copies/typed
copies of the Awards on the record in case this Hon’ble Court so directs.
Chandigarh Deponent Dated: 30.08.2014
Verification: Verified that the contents of para 1 to 3 of the affidavit are true and
correct to my knowledge. No part of it is false and nothing relevant has been
concealed therein.
Chandigarh Deponent Dated: 30.08.2014
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
Civil Misc. Application No.______________ of 2014 IN
F.A.O. No.____________of 2014
National Highways Authority of India .…..Appellant/Applicant
Versus
Sukhwinder Singh and others …..Respondents
Application under Order 41 Rule 5 read with Section 151
CPC seeking stay of operation of the impugned Award dated
03.03.2012 of the Arbitrator and the Award dated 28.05.2014
passed by the Learned Additional District Judge, (Fast Track
Court) Rupnagar.
Respectfully Submitted;
1. That the applicant is filing the accompanying appeal against the Award
dated 28.05.2014 passed by the Learned Additional District Judge, (Fast Track
Court) Rupnagar dismissing the petition filed by the applicant under Section 34 of
the Arbitration and Conciliation act, 1996, by upholding the Award of the
Arbitrator dated 03.03.2012 exorbitantly enhancing the compensation awarded
for the land acquired.
2. That as detailed in the grounds of appeal, both the Awards are totally
arbitrary being against the facts and law. That the applicant has a good prima
facie case in its favour and the applicant is sanguine about the success of
appeal. Balance of convenience is also in favour of the applicant as in case the
amount awarded by the Arbitrator is paid to the contesting
respondents/landowners, it would not be possible to recover the same in the
eventuality of success of the present appeal.
It is therefore, respectfully prayed that keeping in view the
facts and circumstances of the case the application may kindly be allowed
and operation of the impugned Award dated 03.03.2012 of the Arbitrator and
the Award dated 28.05.2014 passed by the Learned Additional District Judge,
(Fast Track Court) Rupnagar may kindly be stayed during the pendency of
appeal.
Chandigarh Dr. Puneet Kaur Sekhon Dated: 30.08.2014 Advocate Counsel for the Appellant/Applicant
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
Civil Misc. Application No.______________ of 2014
IN
F.A.O. No.____________of 2014
National Highways Authority of India .…..Appellant/Applicant
Versus
Sukhwinder Singh and others …..Respondents
Affidavit of O.C. Mathur, Project Director, National Highways
Authority of India, Project Implementation Unit-Chandigarh-
Bays No. 35-38, Sector-4, Panchkula.
I, the above-named deponent do hereby solemnly state and affirm as under;
1. That the applicant is filing the accompanying appeal against the Award
dated 28.05.2014 passed by the Learned Additional District Judge, (Fast Track
Court) Rupnagar dismissing the petition filed by the applicant under Section 34 of
the Arbitration and Conciliation act, 1996, by upholding the Award of the
Arbitrator dated 03.03.2012 exorbitantly enhancing the compensation awarded
for the land acquired.
2. That as detailed in the grounds of appeal, both the Awards are totally
arbitrary being against the facts and law. That the applicant has a good prima
facie case in its favour and the applicant is sanguine about the success of
appeal. Balance of convenience is also in favour of the applicant as in case the
amount awarded by the Arbitrator is paid to the contesting
respondents/landowners, it would not be possible to recover the same in the
eventuality of success of the present appeal.
Chandigarh Deponent Dated:30.08.2014
Verification: Verified that the contents of para 1 to 3 of the affidavit are true and
correct to my knowledge. No part of it is false and nothing relevant has been
concealed therein.
Chandigarh Deponent Dated: 30.08.2014
GROUNDS OF APPEAL
1. That the appellant, National Highways Authority of India, a body
corporate constituted under Section 3 of the National Highways Authority of
India Act, 1988, (for short NHAI Act) is filing the present appeal through Sh.
O.C. Mathur, Project Director, Project Implementation Unit, Chandigarh, who
is well conversant with the facts of the case and is duly authorised to file the
present appeal against the Award dated 28.05.2014 passed by the Learned
Additional District Judge, (Fast Track Court) Rupnagar in Arbitration Petition
No. 449 of 2012 dismissing the petition filed by the appellant under Section 34
of the Arbitration and Conciliation Act, 1996, by upholding the Award of the
Arbitrator dated 03.03.2012 enhancing the compensation awarded for the land
acquired under the provisions of NHAI Act.
BRIEF FACTS 2. That the Government of India vide its Notification dated 24.11.2009
issued under Section 3 (A) of the NH Act, declared its intention to acquire the
land for building (widening four laning etc.), maintenance, management and
operation of NH-21 on the stretch of land from K.M.32.250 to K.M.66.250
(Kurali-Kiratpur Section of NH-21), in the Revenue Estate of Bharatgarh,
Barapind, Bari Jhakian, Chhoti Jhakian, Haner and Bhouwal, District
Rupnager. Thereafter, vide Notification dated 09.03.2010 issued under
Section 3-D of the NH Act declaration was made that the land specified in
the schedule shall vest absolutely in the Central Government.
3. That during the proceedings for assessment of compensation under
Section 3-G of the NH Act before the ‘competent authority’, the measurement
and classification of the land described in the aforesaid Notifications was not
disputed by the land owners. As per the aforesaid classification land of the
private respondents/land owner is as follows:-
Village Bharatgarh, H.B. No.327
Khasra No. Area Kanal-Marla
Type of land Nature of land
1049/1 0-4 Private Gair Mumkin Abadi
1104 0-3 Private Gair Mumkin Abadi
1105 0-6 Private Gair Mumkin Abadi
1052 0-4 Shamlat Gair Mumkin School
4. That the competent authority vide its award dated 04.05.2010 awarded
compensation at the following rates:-
Sr. No
Name of the village & H.B.No.
Nature of land
D.C Rates of that particular type of land
Rate of compensation
Remarks
1 Bharatgarh-
327
Residential-
cum-
Commercial
40,00,000/-
(Residential)
96,00,000/-
(Commercial)
68,00,000/- As the land is
being used
for residential
and
Commercial
purpose, the
average of
commercial
and rates has
been
awarded
2 Bara Pind-
326
Residential 32,00,000/- 32,00,000/- -----
3 Bari Jhakian
-324
Residential 32,00,000/- 32,00,000/- ---
4 Chotti
Jhakian -5
Residential 32,00,000/- 32,00,000/-
---
5 Halerh-323 Residential 32,00,000/- 32,00,000/- ---
6 Bhouwal-325 Residential 32,00,000/- 32,00,000/- ---
5. That against the award of the competent authority, the private
respondents/land owners availed the statutory remedy of the arbitration and
demanded compensation for land @ 4.0 crore per acre.
6. That the arbitrator vide its award dated 03.03.2012 assessed the
market price of the aforesaid land @ Rs.0.975 lacs per Marla.
Disadvantageous factor of statutory restrictions on the use of land have not
been taken in to consideration while assessing the market value of the land.
Not only this, despite the fact that Arbitrator was a full time Government
servant and was discharging the duties as an Arbitrator on the instructions of
the Central Government, he has illegally claimed arbitration cost of
Rs.14,000/-, to be shared by both the parties to the arbitration.
7. That faced with this, the appellant filed petition under Section 34 of the
Arbitration and Conciliation Act, 1996 for setting aside the aforesaid illegal,
arbitrary and perverse award. However, learned Addl. District Judge (Fast
Track Court), Rupnagar, failed to exercise its jurisdiction under the
misconception of fact and law that the case is not covered by the grounds
provided under Section 34 of the said Act. Resultantly, the aforesaid petition
filed by the appellant against the totally illegal and perverse award of arbitrator
was dismissed in perfunctory manner vide award dated 28.05.2014.
8. That in the aforesaid factual background the appellant is impugning the
award dated 03.03.2012 passed by the Arbitrator and the award dated
28.05.2014 passed by the learned Additional District Judge (Fast Track Court)
Rupnagar, upholding the award of the arbitrator by dismissing the petition filed
by the appellant under Section 34 of the Arbitration and Conciliation Act, 1996
on the grounds detailed hereunder.
GROUNDS OF CHALLENGE
9. That learned Additional District Judge (Fast Track Court) Rupnagar,
failed to exercise the jurisdiction vested in it on the erroneous assumption that
the case is not covered under Section 34 (2) of the Arbitration and Conciliation
Act, 1996. In view of the following position of law reiterated by Hon’ble
Supreme Court in its Judgememt in the matter of DELHI DEVELOPMENT
AUTHORITY V/S R S SHARMA AND COMPANY reported in 2008 (13) SCC
80, it was incumbent upon the learned Additional District Judge (Fast Track
Court) Rupnagar to set aside the Award of the arbitrator;
“[12] From the above decisions, the following principles emerge:
(a) An Award, which is
(i) contrary to substantive provisions of law ; or
(ii) the provisions of the Arbitration and Conciliation Act, 1996 ; or
(iii) against the terms of the respective contract ; or
(iv) patently illegal, or
(iv) prejudicial to the rights of the parties, is open to
interference by the Court under Section 34(2) of the Act.
(b) Award could be set aside if it is contrary to :
(a) fundamental policy of Indian Law; or
(b) the interest of India; or
(c) justice or morality;
(c) The Award could also be set aside if it is so unfair and
unreasonable that it shocks the conscience of the Court.
(d) It is open to the Court to consider whether the Award is
against the specific terms of contract and if so, interfere with it on
the ground that it is patently illegal and opposed to the public
policy of India.”
Hence, if the Arbitral Tribunal does not dispense justice, it cannot
truly be reflective of an alternate dispute resolution mechanism. Hence, if the
award has resulted in an injustice, a Court would be well within its right in
upholding the challenge to the award on the ground that it is in conflict with the
public policy of India.
10. That under Section 28 of the Arbitration and Conciliation Act, 1996,
the arbitrator is bound to pass the award according to the substantive law of
India and Section 31 (3) of the said Act mandates to give reasons. In the
present case the award of the arbitrator has been passed in utter disregard of
these provisions. The principle applied to arrive at the market rate of the land
is not discernable from the award of the arbitrator, the award does not satisfy
the requirement of a reasoned award. Therefore, the same is contrary to the
provisions of the Act and is contrary to the public policy of India.
11. That in the present case the arbitrator failed to take into consideration
the relevant facts and based his decision on irrelevant factors, thus has
committed a legal misconduct. Therefore, in view of the following observations
of Hon’ble Supreme Court in the matter of UNION OF INDIA V/S V
PUNDARIKAKSHUDU AND SONS reported in 2003 (8) SCC 168, the award
of the arbitrator deserved to be set aside;
“ ……………………… and furthermore if in determining the
disputes between the parties the arbitrator failed to take into
consideration the relevant facts or based his decision on
irrelevant factors not germane therefor; the arbitrator must be
held to have committed a legal misconduct.”
12. That the arbitrator acted illegally in referring to sale instances without
there being any evidence that the same pertain to the land having
disadvantageous factor of statutory restrictions on the use of land and the
same are the relevant comparable instances.
13. That a perusal of the impugned award of the arbitrator would reveal that
the arbitrator, while granting compensation has over looked the provisions of
sub-section 7 of section 3-G of the NH Act, hence the judgment upholding the
award of Ld. Arbitrator is liable to be set aside on this ground alone.
14. That the Ld. Arbitrator while determining the market value of the land
failed to take into consideration the effect of statutory provisions and the
material on record, especially the Notification dated 05.10.2005 banning
construction upto 50 meters along the National Highway on the market value
of the land under acquisition. The Ld. Addl. District Judge, Ropar has failed to
appreciate this glaring illegality.
15. That neither there was any structure meant for being used as
commercial building on the land in question nor the private
respondents/landowners in the present case claimed the existence of any
such structure. Therefore, there is no basis to treat the land as commercial.
However, without going into the issue with regard to the nature of land, Ld.
Arbitrator own its own declared the land as commercial land.
16. That Ld. Arbitrator as well as the Ld. Addl. District Judge, Ropar failed
to consider the fact that only small strips of the land were acquired for
widening of NH. The value of such land cannot be same as that of the plots in
the developed commercial area.
17. That the award passed by the Competent Authority and Ld. Arbitrator
are on the basis of contradictory record. Perusal of both the awards reveal
that during the proceedings of both the awards, the revenue officials produced
the different average rates of the land. Thus Ld. Arbitrator granted the
compensation by making reference to the record which is contradictory in
itself.
18. That for determination of the market value of the land to be acquired,
the collector rates are the safest guiding factor. The market rate to be taken
into the consideration is, the rate prevailing at the time of issuance of
notification under 3 A of the National Highways Act, 1956. Perusal of the
award passed by the Ld. Arbitrator reveal that both the compensation has
been awarded at much higher than the market rates and the same has been
upheld by the Ld. Addl. District Judge, Ropar. Hence the impugned awards
are liable to be set aside.
19. That Ld. Arbitrator as well as the Ld. Addl. District Judge, Ropar has
completely overlooked the provision of the National Highways (Land and
Traffic) Act, 2002; Punjab Regional & Town Planning & Country Development
Act, 1995; Punjab Scheduled Roads And Controlled Areas Restriction Of
Unregulated Development Act, 1963 where under several restrictions have
been imposed regarding construction and approach to the Highways, making it
almost impossible to use the land abutting the National Highways for
commercial purpose. Thus the Ld. Arbitrator as well as the Ld. Addl. District
Judge, Ropar proceeded on totally misconceived assumption that the land in
question is adjoining to National Highway No. 21 and its market value would
be on the higher side. Hence the impugned Awards are liable to bet set aside.
20. That that Arbitrator is a member of All India Service and was appointed
arbitrator under the provisions of Section 3 G (5) of the NH Act. Being full time
Government servant he was discharging the duties as an Arbitrator on the
instructions of the Central Government, but he has illegally claimed arbitration
cost of Rs.14,000/-, to be shared by both the parties to the arbitration. This
illegality has totally been overlooked by the Ld. Addl. District Judge, Ropar.
21. That the Division Bench judgment of this Hon’ble High Court in CWP
No. 11461 of 2005 in the matter of “M/s. Golden Iron & Steel Forging Vs.
Union of India and others” relied upon to award solatium and interest in terms
of the land Acquisition Act, 1894, is under challenge before the Hon’ble
Supreme Court in Appeal No. 10695 of 2011 which is still pending.
22. That without prejudice to the aforesaid, grant of interest @ 18 % p.a on
the amount awarded is not in terms of the Land Acquisition Act, 1894.
Provisions of an Act are to be applied in its entirety. Therefore, award of
interest over and above the rate of interest provided under the Land
Acquisition Act, 1894 is illegal and arbitrary.
23. That the appellant has not filed any such or similar appeal either before
this Hon’ble Court or before Hon’ble Supreme Court of India nor such appeal
is pending.
24. That the present appeal is within limitation.
It is, therefore, respectfully prayed that the present appeal may
kindly be allowed and the Award dated 28.05.2014 passed in Arbitration
Petition No. 449 of 2012 by the Ld. Addl. District Judge, (Fast Track Court)
Ropar, and the Award dated 03.03.2012 passed by the Arbitrator may kindly
be set aside in the interest of justice.
DATED:30.08.2014 (Dr. Puneet Kaur Sekhon) CHANDIGARH E. No. P-3004/07 Advocate Counsel for the Appellant
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
F.A.O. No.____________of 2014
National Highways Authority of India .…..Appellant
Versus
Sukhwinder Singh and others …..Respondents
Affidavit of O.C. Mathur, Project Director, National Highways
Authority of India, Bays No. 35-38, Sector-4, Panchkula.
I, the above named deponent do hereby solemnly state and affirm as under;
1. That the deponent is Project Director, National Highways Authority of India
(for short NHAI) and is duly authorized to file the accompanying appeal on behalf
of NHAI, which has been drafted on the instructions of the deponent.
2. That the facts stated in para 1 to 24 of the grounds of appeal are true and
correct to the knowledge of the deponent.
3. That the appellant has not filed any such or similar appeal before this
Hon’ble Court against the award which is impugned in the accompanying appeal.
Chandigarh Deponent Dated: 30.08.2014
Verification: Verified that the contents of para 1 to 3 of the affidavit are true and
correct to my knowledge. No part of it is false and nothing relevant has been
concealed therein.
Chandigarh Deponent Dated 30.08.2014
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
F.A.O. No.__________________of 2014 In
Arbitration Case No.: 449/2012
MEMO OF PARTIES
National Highways Authority of India, Project Implementation Unit, Chandigarh -
Bays No. 35-38, Sector-4, Panchkula through O.C. Mathur, Project Director.
..…..Petitioner.
Versus 1. Sukhwinder Singh S/o Ujjagar Singh R/o Village Bharatgarh Tehsil and
District Ropar.
2. Sovinder Kaur d/o Sohinder Kaur R/o Village Bharatgarh Tehsil and
District Ropar.
3. Harwinder Singh S/o Sohinder Kaur R/o Village Bharatgarh Tehsil and
District Ropar.
4. Divisional Commissioner, Patiala Division, Patiala, Sole Arbitrator O/O
Divisional Commissioner, Mini Secretariat, Nabha Road, Patiala.
5. Sub Divisional Magistrate, Ropar, Competent Authority under the National
Highways Act, 1956.
…..Respondents.
6. State of Punjab through its Secretary Punjab Secretariat, Chandigarh.
…..Proforma Respondent.
Chandigarh (Puneet Kaur Sekhon) Dated: 30.08.2014 Advocate Counsel for the Petitioner