im 322 inventory management
TRANSCRIPT
IM 322Inventory Management
Chapter 9: Material Requirement Planning
-1-
Textbook: Donald Waters, Inventory Control and Management, 2nd
ed
Chapter Outline
Master SchedulingThe use of MRP (Material Requirement Planning)Extension of the basic ERP methodIntroduction to ERP
2
Resource Planning for Manufacturing
Resource Planning for Manufacturing
Adapted from: Roberta Russell & Bernard W. Taylor, II, Operations ManagementI3
Determine • when specific products will be made• when specific customer orders will be filled,• and what products / capabilities are still available to meet new demand
Determine • when specific products will be made• when specific customer orders will be filled,• and what products / capabilities are still available to meet new demand
Calculate timing and quantities of material orders needed to support the master schedule
Calculate timing and quantities of material orders needed to support the master schedule
Material Requirement Planning (MRP)
Computerized inventory control & production planning systemSchedules component items when they are needed - no earlier and no later
Key Outputs of MRP
4
When to use MRP
Dependent and discrete itemsComplex productsJob shop productionAssemble-to-order environments
Top clip (1) Bottom clip (1)
Pivot (1) Spring (1)
Rivets (2)Finished clipboard Pressboard (1)
Clipboard
Dependent / Independent Demand?
5
Demand Characteristics
11 22 33 44 55WeekWeek
400 400 –
300 300 –
200 200 –
100 100 –No.
of t
able
sN
o. o
f tab
les
Continuous demandContinuous demand
M T W M T W ThTh F M T W F M T W ThTh FF
400 400 –
300 300 –
200 200 –
100 100 –No.
of t
able
sN
o. o
f tab
les
Discrete demandDiscrete demand
Independent demandIndependent demand
100 tables100 tables
Dependent demandDependent demand
100 x 1 = 100 x 1 = 100 tabletops100 tabletops
100 x 4 = 400 table legs100 x 4 = 400 table legs
Demand Characteristics for Finished Products and Their Components
6
MRP Input & Output
7
Major Inputs to MRP Process:1. Bill of Material
Product structure fileDetermines which component items need to be scheduled
Product Structure RecordProduct Structure Record
ClipboardLevel 0Level 0
Level 1Level 1
Level 2Level 2Spring (1)
Bottom Clip (1)
Top Clip (1)
Pivot (1)
Rivets (2)
Clip Assembly
(1)
Pressboard (1)
Top clip (1) Bottom clip (1)
Pivot (1) Spring (1)
Rivets (2)Finished clipboard Pressboard (1)
Clipboard
8
Major Inputs to MRP Process:2. Master Production Schedule (MPS)
Drives MRP process with a schedule of finished productsQuantities represent production not demandQuantities may consist of a combination of customer orders & demand forecastsQuantities represent what needs to be produced, not what can be producedExample
PERIODMPS ITEM 1 2 3 4 5
Clipboard 85 95 120 100 100Lapdesk 0 50 0 50 0Lapboard 75 120 47 20 17Pencil Case 125 125 125 125 125
9
Major Inputs to MRP Process:2. Master Production Schedule (MPS)
10
MPS example
11
2,000 BackpackMonthWeek 37 38 39 40 41 42 43 44
Forecasted demand 1,500 1,500 1,500 1,400 1,400 1,250 1,250 1,250
Booked demand 1,422 1,505 1,471 1,260 980 853 534 209
Projected ending inventory
Master Production Schedule 4,500 4,000 3,700
Available-to-promise (ATP)
On-hand inventory at end of week 36:
September Octobrt
Major Inputs to MRP Process:3. Inventory Record
Inventory fileContains an extensive amount of information on every item that is produced, ordered, or inventoried in the systemIncludes on-hand quantities, lot sizes, safety stock, lead time, and etc.
DESCRIPTION INVENTORY POLICY
Item Pressboard Lead time 1Item no. 734 Annual demand 5000Item type Purch Holding cost 1Product/sales class Comp Ordering/setup cost 50Value class B Safety stock 0Buyer/planner RSR Reorder point 39Vendor/drawing 07142 EOQ 316Phantom code N Minimum order qty 100Unit price/cost 1.25 Maximum order qty 500Pegging Y Multiple order qtyLLC 1 Policy code 3
12
MRP Processes4 Basic steps
13
Lot Sizing Rules / Batching Order
14
Lot Sizing Rule / Batching Order Comparison
15
MRP Matrix
Gross RequirementDerived from planned order releases of the parentActual / estimated demand, in case of final product
Schedule ReceiptsItems on orderScheduled to arrive in the future time period
Projected on handCurrent inventory, or anticipated inventory at the end of period
Projected on-handInventory at end of period t
Inventory on-hand at end of period t - 1= +
Scheduled / planned receipts in period t -
Gross requirements in period t
16
MRP Matrix
17
Net requirementsActual quantity to produce based on projected on hand and on-order quantity
Planned Order ReceiptsQuantity, when orders need to be received
Consider lot sizing rule: Planned Order Release
When order need to be placed to receive on time
Consider lead time
ITEM: CLIPBOARD LLC: 0 PERIOD
LOT SIZE: L4L LT: 1 1 2 3 4 5Gross Requirements 85 95 120 100 100Scheduled Receipts 175Projected on Hand 25Net RequirementsPlanned Order ReceiptsPlanned Order Releases
18
Example MRP MatrixExample MRP Matrix
MRP Matrices
MRP Example 2
A(2) B(1)
D(5)C(2)
X
C(3)
Item On-Hand Lead Time (Weeks)X 50 2A 75 3B 25 1C 10 2D 20 2
Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10
Requirements include 95 units (80 firm orders and 15 forecast) of X in week 10
20
A(2) B(1)
D(5)C(2)
X
C(3)
Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95
LT=2 Scheduled receipts Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45hand Planned order receipt 4550 Planner order release 45A Gross requirements 90
LT=3 Scheduled receipts Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15 hand Planned order receipt 15 75 Planner order release 15 B Gross requirements 45
LT=1 Scheduled receipts Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20 hand Planned order receipt 20 25 Planner order release 20 C Gross requirements 45 40
LT=2 Scheduled receipts Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40 hand Planned order receipt 35 40 10 Planner order release 35 40 D Gross requirements 100
LT=2 Scheduled receipts Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80 hand Planned order receipt 80 20 Planner order release 80 21
Testing Lot Sizing Rules
Testing Lot Sizing Rules
1 2 3 4 5 6 7 8
Gross Requirements 160 160 160 160 160 100 160 100
Scheduled Receipts 130 160 160
Projected on Hand 60
Net Requirements
Planned Order Receipts
Planned Order Releases
Given that • lead time = 3 periods, • safety stock = 20 units • Inventory carrying cost = $5 / unit-period• Reordering cost = $150 order
Determine the most appropriate lot sizing rule
(a) Lot-for-Lot(b) FOQ = 50 units(c) POQ = 3 periods(d) Use EOQ(e) Use POQ = Q / average d
22
Benefits of MRPMRP can generate many different kinds of report,
including:Timetable of operationsTimetable of ordersChanges in previous ordersPerformance reportsPlanning reportsRecords of inventory transactions
23