ibl cooling tube routing proposal

21
[email protected] IBL cooling tube routing proposal Bart Verlaat 19-01-2011 1 [email protected]

Upload: tale

Post on 15-Feb-2016

43 views

Category:

Documents


0 download

DESCRIPTION

[email protected]. IBL cooling tube routing proposal. Bart Verlaat 19-01-2011. IBL Cooling pipes layout idea :. Concentric tube. Single outlet tube. Single inlet tube. Inlet Manifold. Outlet Manifold. Inlet Capillaries. IBL CO 2 cooling routing proposal. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: IBL  cooling tube routing proposal

[email protected]

IBL cooling tube routing proposal

Bart Verlaat

19-01-2011

1

[email protected]

Page 2: IBL  cooling tube routing proposal

[email protected]

Single outlet tubeSingle inlet tube

Concentric tube

Outlet Manifold

Inlet Manifold Inlet

Capillaries

IBL Cooling pipes layout idea:

Page 3: IBL  cooling tube routing proposal

[email protected] IBL CO2 cooling routing proposal

• A survey of the routing possibilities in Atlas has been carried out to come up with a more detailed proposal than the one on the previous slide.

• Routing in difficult areas was simulated with 50mm PVC piping. A Mock-up is made which can be measured and modeled into CAD.

• The dimensions of the neighboring hardware were measured to find space for additional hardware and accessibility. Measurements will be used to check the available 3D models.

• Preliminary check of measurements is done with existing 2d drawings from CDD.

• A principle design of the full tube routing is made– Where to put manifolds, valves, etc. – What isolation can be applied (Foam / Vacuum).

3

Page 4: IBL  cooling tube routing proposal

[email protected] IBL cooling tube routing CAD measurements

BIL muon

LAR cryo pipesExisting support structuresVertical cables

Cooling pipes

Cooling pipes

Cooling pipes

Cooling pipes

Sector 5

LAR

cry

ogen

ic p

lant

Bart’s CAD office

Page 5: IBL  cooling tube routing proposal

[email protected]

5

Measured cooling tube routing and support environment in the Atlas overall drawing

Page 6: IBL  cooling tube routing proposal

[email protected]

Cooling tube routing mock-up in detector

6

Page 7: IBL  cooling tube routing proposal

[email protected] IBL cooling tube routing at inner detector.

• From the ID-end plate a nice path following the dry-air chimney was found to the top of the tile calorimeter.

• In the empty space between inner muon chamber of sector 5 and the tile calorimeter a path was found to accessible area between sector 5, BIL and BML layers. In this space the transition from IBL feed and return tubing to the concentric transfer tube can be made.

• Delicate equipment can be placed in this area as it is easily accessible.– Valves, filters, sensors.– Manifolds?

• Tubes to ID-end plate can be vacuum insulated and can be installed prefabricated.

• Insulation of transition hardware can only be foam insulated. Placement of a condensation catch channel underneath is possible.

7

Page 8: IBL  cooling tube routing proposal

[email protected] IBL cooling branch

8

IBL Boiling tube:2.0mmID x 1308mm

(Heated length 708mm)

Inlet Capillary(Flexible)

0.8mmID x 5289mm(2609.5+2679.5)

Outlet tube2.0mmID x 2679.5m

Q≈100 Watt / stave

14 staves = 14 parallel branches.

PP1 Connector

IDEP Inlet Manifold

IDEP Outlet Manifold

PP0 Weld Connector

PP0 Weld Connector

Outlet tube3.0mmID x 2609.5m

or2.0mmID x 2609.5m

(TBD)

PP1 Connector

Page 9: IBL  cooling tube routing proposal

[email protected]

50mm pvc dummy tube with 45’ connectors

Longitudinal routing near lower BIL muon chamber corner.

Passage through almost empty channel

Routing and clamping on top of “chimney”

Entering ID-endplate left of “chimney”

IBL CO2 cooling tube routing at calorimeter end flange

Page 10: IBL  cooling tube routing proposal

[email protected] IBL Cooling junction at sector 5

C-side view Top view

ID end plate Vacuum insulated cooling tubesFoam insulated cooling tubes

LAR pipesLAR pipes

Cooling components area

Cable channels

BIL muon chambers

platform

Concentric transfer tube

Concentric transfer tube

Con

nect

ion

to A

-sid

e

Con

nect

ion

to C

-sid

e

Connection to C

-side Con

nect

ion

to A

-sid

e

Page 11: IBL  cooling tube routing proposal

[email protected] End cap region pictures

11PVC mockup @ Aside (Fits also @ Cside)

IDEP interface

Routing on top of chimney Passage of Tile calorimeter cable channel

Entry of Tile calorimeter cable channel

Passage between S5 BIL muon and Tile calorimeter

Clearance above endcap tile calorimeter for installation passage

Page 12: IBL  cooling tube routing proposal

[email protected] Sector 5 junction pipe pictures

12

Junction routing at S5Passage between S5 BIL muon and Tile calorimeter

Passage between S5 BIL muon and Tile calorimeter C-side

Passage of BIL muon layer

Junction routing around muon alignment beams

Passage of BIL muon layer

Free installation space for junction box

Junction tubes on top of cable channel /below LAR pipe

A-side C-side

Page 13: IBL  cooling tube routing proposal

[email protected] IBL transfer tube inside Atlas detector

• A straight path from the sector 5 cooling junction to the outside was found following the cryogenic LAR piping towards the cryogenic LAR plant at level 6.

• The straight path allow us to make the concentric transfer tube in the detector to be vacuum insulated.

• Concentric vacuum assembly can be made using 6m tubes. At the LAR cryogenic plant sufficient space is available for inserting 6m long tubes.

• Construction of 6m long tubes (standard trading length) gives weld joint locations in accessible areas. – BIL/BML sector 5 (Junction box)– BML/BOL sector 7 (Area behind small toroid access door) – LAR cryogenic plant at level 6.

• Routing and inserting was simulated using 50mm PVC piping.

13

Page 14: IBL  cooling tube routing proposal

[email protected] Concentric transfer line in Atlas detector

14

6 m 6 m

BIL/BML sector 5 (Junction box)

BML/BOL sector 7 (Area behind small toroid access door)

LAR cryogenic plant at level 6

Existing mechanical supports

12.9 m

Concentric transfer line

Page 15: IBL  cooling tube routing proposal

[email protected] Vacuum insulated transfer tube pictures (S5 and S7)

15

Transfer line at S5

Transfer line terminal at S5

Transfer line underneath platform in S5

Transfer line following LAR cryo-pipes from S5 to S7

Transfer line next to LAR cryo-pipes in S7

S7 accessible area for welding

Only obstacle in the way: ladder in S7: 1cm shift required.

Page 16: IBL  cooling tube routing proposal

[email protected]

Vacuum insulated transfer tube pictures LAR cryogenic plant

16

Transfer line exits BOL layer at S7/8

Transfer line exits BOL layer at S7/8

Transfer line arrives at LAR Cryogenic plant

Inserted transfer line at LAR Cryogenic plant

Insertion of a 6m tube at LAR cryogenic plant (3)

Insertion of a 6m tube at LAR cryogenic plant (2)

Insertion of a 6m tube at LAR cryogenic plant (1)

Page 17: IBL  cooling tube routing proposal

[email protected] Transfer tube routing to cooling plant

• A nearly horizontal path was found to the cooling plant area in USA15

• Tubes follow LAR vacuum tube towards cavern wall and go along wall to the tube and cable tunnel.

• Tubes can be installed on top of C3F8 cooling channels to USA15

• Vacuum pump can be installed on cavern wall next to LAR vacuum pump

• Insulation will be foam from LAR cryogenic plant towards CO2 cooling plant

17

Page 18: IBL  cooling tube routing proposal

[email protected] Cavern tube routing

18

Start at LAR cryo plant

Follow LAR vacuum pipes

Follow pipes at cavern wall

Follow C3F8 pipes in tunnel

Follow C3F8 pipes in USA15

Terminate at proposed IBL cooling plant platform

Page 19: IBL  cooling tube routing proposal

[email protected] IBL cooling plant location

• A nice free space was found on an empty platform at the upper layer of USA15.

• Tube routing towards this space is easy.• Is this space available for the CO2 plant?

19

Page 20: IBL  cooling tube routing proposal

[email protected] Tube length summary

Length (m)

Upward length (m)

Downward length (m)

Foam transfer feed line 98.4 2.5 3Vacuum transfer feed line 12.9 0 0Inlet junction 2.5 0 0.4Inlet vacuum pipe 6.5 0 2.9Inlet capillary 5.3 0 2.5Total feed line 125.6 2.5 8.8IBL 1.3 0 0Outlet capillary 5.3 2.5 0Outlet vacuum pipe 6.5 2.9 0Outlet junction 3.1 0.4 0Vacuum transfer return line 12.9 0 0Foam transfer return line 98.4 3 2.5Total return line 126.2 8.8 2.5Total length: 251.8 11.3 11.3

20

Page 21: IBL  cooling tube routing proposal

[email protected] Summary and conclusions

• Proposed tube routing from IBL to cooling plant is feasible and looks relatively easy to apply.

• Vacuum insulation in the detector – Except at junction area, but very accessible for a proper insulation.

Condensation catch channels will be installed as guarantee.• Pre-fabricated vacuum channel from junction to ID-end plate.• Vacuum insulated transfer line possible to manufacture in place.• Junction area is easy to access, this will be the location for most of

the sensitive hardware.• It will be investigated to locate the manifolds as well in the junction

area.– Long capillary tubing!!– Accessible manifolds.– Possibility to disconnect an IBL cooling channel.

• Can CO2 plant be placed at the free platform in USA15?21