i-95 and oslo road interchange design and widening project ...oslodesignproject.com/widening...
TRANSCRIPT
Florida Department of Transportation
RICK SCOTT
GOVERNOR 3400 West Commercial Blvd.
Fort Lauderdale, FL 33309
JIM BOXOLD
SECRETARY
PUBLIC HEARING TRANSCRIPT CERTIFICATION I hereby certify that on December 16, 2015 beginning at 5:30 p.m., I presided over a Public Hearing for the following project:
Olso Road Widening Project Development and Environment (PD&E) Study
from East of I-95 to 58th Avenue SW Indian River, Florida
Financial Management No.: 431521-1-22-01 Federal Aid Project No.: 8886-458-A
I further certify that the subject public hearing was conducted relative to the economic and social effects of the location and design concept for the subject project and its impact on the environment, that a transcript was made and the document attached herein is a full, true, and complete transcript of what was said at the hearing, and that the Florida Department of Transportation has considered the social, economic, and environmental effects of the proposed improvement and is of the opinion that it is properly located and should be constructed. ___________________________ ________________________ Ronald Wallace, P.E. Date FDOT Project Manager
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 1
Project Development and Environment Studies Public HearingI-95 & Oslo Road Interchange at Milepost 2.369 & Oslo Road Widening from East of I-95 to 58 AvenueProject Development and Environment (PD& E) Studies Indian River County, FloridaFinancial Management Nos.: 413048-2-22-01 & 431521-1-22-01 Federal Project ID No.: 8886-458-A (Oslo Road Widening Project)
December 16, 2015 5:30 p.m.
Indian River State College Mueller Campus Richardson Center 6155 College Lane Vero Beach, Florida 32966
Present:
Richard Young, District 4 PD&E for FDOT
Ron Wallace, District 4 FDOT Project Manager
John Krane, Consultant Project Manager for Oslo RoadInterchange PD&E Study, Keith and Schnars
Carlos Rodriguez, Consultant Project Manager for Oslo RoadWidening PD&E Study, Metric Engineering
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 2
1 AND THEREUPON:
2 MR. YOUNG: Thank you for coming for a
3 public hearing. Florida Department of
4 Transportation would like to welcome you to the
5 public hearing for the Oslo Road PD&E studies.
6 My name is Richard Young, I'm the District
7 4 Project Development Engineer for the Florida
8 Department of Transportation. The proposed
9 improvements involve an interchange at I-95 and
10 widening of Oslo Road from west of I-95 to 58th
11 Avenue. This hearing is being held to provide
12 you with the opportunity to comment on these
13 projects.
14 Here with me tonight are Mr. Ron Wallace,
15 the FDOT Project Manager with District 4.
16 Mr. John Krane, who's still at the board
17 over there, Consultant Project Manager with
18 Keith and Schnars. He's in charge of the
19 interchange project.
20 And Mr. Carlos Rodriguez, Consultant
21 Project Manager with Metric Engineering.
22 And we have many other representatives and
23 FDOT consulting teams here.
24 At this time, we'd like to recognize any
25 federal, state, county, or city officials who
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 3
1 may be present tonight.
2 Are there any officials that would like to
3 be recognized?
4 Okay, seeing none. We've got the light
5 dimmed already. We'll begin with the
6 PowerPoint presentation. Because we're
7 presenting two projects tonight, the
8 presentation's a little long, it's about 33
9 minutes, but we will have an oral comment
10 period for both projects following the
11 presentation. Thank you.
12 POWERPOINT SLIDE PRESENTATION
13 Good evening. The Florida Department of
14 Transportation would like to welcome you to the public
15 hearing for both the I-95 and Oslo Road Interchange and the
16 Oslo Road Widening Project Development and Environment, or
17 PD&E, Studies from west of SR9/I-95 to 58th Avenue SW within
18 Indian River County. This public hearing is relative to
19 Financial Management Project Numbers 413048-22-01 and
20 431521-1-22-01 and Federal Aid Project Number 8886-458-A.
21 The Oslo Road interchange project entails a new interchange
22 at I-95 and County Road (CR) 606/Oslo Road from west of I-95
23 to east of 82nd Avenue SW. The CR 606 Oslo Road widening
24 project entails the widening from two to four lanes of Oslo
25 Road from east of I-95 to 58th Avenue SW and the
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 4
1 implementation of a complete streets concept.
2 This hearing is being held to provide you with the
3 opportunity to comment on this project.
4 The purpose of this public hearing is to share
5 information with the general public about the proposed
6 improvements, their conceptual design, all alternatives
7 under study, and the potential beneficial and adverse
8 social, economic, and environmental impacts upon the
9 community. The public hearing also serves as an official
10 forum for providing an opportunity to the public to express
11 their opinions and concerns regarding the project. We will
12 utilize the comments gathered here tonight to finalize our
13 study recommendations.
14 There are three primary components to tonight's
15 hearing: First, the open house, which occurred prior to
16 this presentation, where you were invited to view the
17 project displays and to speak directly with the project team
18 and provide your comments in writing or to the court
19 reporter.
20 Second, this presentation, which will explain the
21 project purpose and need, study alternatives, potential
22 impacts, both beneficial and adverse, and proposed methods
23 to mitigate adverse project impacts.
24 And, third, a formal comment period following this
25 presentation, where you will have the opportunity to provide
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 5
1 oral statements at the microphone, or you may continue to
2 provide your comments to the court reporter or in writing.
3 This public hearing was advertised consistent with
4 federal and state requirements. Persons wishing to express
5 their concerns about Title VI may do so by contacting either
6 the Florida Department of Transportation, District 4 office,
7 or the Tallahassee office of the Florida Department of
8 Transportation. This contact information is also provided
9 in the project brochure and on a sign displayed at this
10 hearing. Public participation at this hearing is encouraged
11 and solicited without regard to race, color, national
12 origin, age, sex, religion, disability, or family status.
13 The Project Development and Environment, or PD&E,
14 study phase for planned transportation projects provides the
15 interface between the planning and design phases to evaluate
16 and document solutions to transportation needs that are
17 compatible with the environment. Simply stated, the PD&E
18 study determines if there is an engineering and
19 environmentally feasible alternative to meet the need
20 determined in the planning phase.
21 This process is mandated by the National
22 Environmental Policy Act (or Nee-pah), Federal and State
23 law. It represents a combined effort by technical
24 professionals who analyze information and document the best
25 alternative for a community's transportation needs.
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 6
1 A PD&E study has three main components: an
2 engineering component which entails the identification and
3 analysis of potential design solutions; an environmental
4 component to evaluate potential impacts to the natural,
5 social and physical environments; and a public involvement
6 component to inform and involve all interested parties in
7 the development of the planned transportation project.
8 PROJECT LOCATION
9 The projects are along County Road 606/Oslo Road
10 and extend from west of I-95 to 58th Avenue SW within Indian
11 River County. The I-95 and Oslo Road interchange study
12 extends from west of I-95 to east of 82nd Avenue SW, and the
13 Oslo Road Widening study limits extend from east of I-95 to
14 58th Avenue SW.
15 LOCAL PLANNING ORGANIZATION
16 Both projects are consistent with local and
17 regional plans including the Indian River County
18 Metropolitan Planning Organization (MPO), Transportation
19 Improvement Program, and Long Range Transportation Plan, as
20 well as the FDOT State Transportation Improvement Program.
21 Both projects were identified as priority projects
22 in the MPO 2015 Priority Projects Report. The MPO works
23 with the Florida Department of Transportation and local
24 governments to fund and implement critical projects. The
25 MPO is comprised of local elected officials from Indian
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 7
1 River County, FDOT, and the Town of Orchid.
2 The following slides will discuss the design
3 alternatives that were evaluated for the I-95 at Oslo Road
4 Interchange PD&E Study.
5 PROJECT LOCATION
6 The proposed Oslo Road Interchange is located
7 between the two existing interchanges of Indrio Road in St.
8 Lucie County and SR-60 in Indian River County.
9 PROJECT DESCRIPTION
10 The Oslo Road Interchange study area runs along
11 I-95 from 3200 feet north of and 3200 feet south of Oslo
12 Road, along Oslo Road from 2400 feet west of I-95 to 1320
13 feet east of 82nd Avenue SW, and along 82nd Avenue SW from
14 Oslo Road northward to 5th Street SW.
15 The realignment of 82nd Avenue SW is necessary to
16 provide adequate separation from the proposed east-side ramp
17 locations.
18 This PD&E study was also conducted in coordination
19 with the proposed Oslo Road Widening Project to the east.
20 PURPOSE AND NEED FOR THE INTERCHANGE
21 The purpose of this project is to improve regional
22 connectivity for drivers who begin or end their trips in
23 southern Indian River County, and to improve the emergency
24 and incident response time to incidents along I-95 in
25 southern Indian River County.
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 8
1 This project will provide direct regional access
2 to I-95 eliminating the need to travel either to SR-60 to
3 the north, or Indrio Road to the south in order to make
4 long-distance trips into and out of the area.
5 The project will also improve access for heavy
6 trucks using Oslo Road (a designated truck route).
7 With this project, response time to incidents on
8 I-95 in southern Indian River County will be improved by 43
9 percent.
10 Secondary reasons for this project are: To
11 provide an additional evacuation route for area residents;
12 to accommodate planned economic development in this part of
13 the county; and to facilitate the county's planned vision
14 for this area as a Regional Workplace District.
15 INTERCHANGE JUSTIFICATION REPORT
16 A necessary first step in this process was the
17 development of an Interchange Justification Report, or IJR,
18 to assess the need and operational acceptance of an
19 interchange at the Oslo Road location. In addition to a new
20 interchange, the analysis included alternatives such as
21 minor operational improvements (known as Transportation
22 System Management and Operations, or TSM&O), and
23 improvements to the two existing interchanges.
24 The IJR was accepted by the Federal Highway
25 Administration (FHWA) on September 18, 2014.
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 9
1 Two preliminary interchange concepts were
2 developed and accepted during the IJR process. One was the
3 Wide Diamond or rural diamond.... (north is to the right),
4 and the other was a partial cloverleaf with a loop-ramp in
5 the northwest quadrant.
6 KEY ISSUES
7 There are numerous issues that affect the
8 alternative development and analysis process. The key
9 issues associated with developing an interchange at this
10 location are the need to acquire right of way for the ramps;
11 impacts to 86th and 82nd Avenues SW because of their
12 proximity to the interchange ramps and right of way;
13 potential impacts to the Aerodrome community; wetland
14 impacts in the southeast and southwest quadrants; and an
15 eagle's nest on the east side of Oslo Road, north of 5th
16 Street SW.
17 Building on the information from the IJR, three
18 alternatives were analyzed further as part of this PD&E
19 Study.
20 Alternative 1, a diamond interchange that is
21 similar to the diamond concept from the IJR would have a
22 right-of-way cost of 9.4 million dollars, and a construction
23 cost of 21.9 million dollars.
24 Alternative 2, a partial cloverleaf with a
25 loop-ramp in the northwest quadrant that is similar to the
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 10
1 partial cloverleaf concept from the IJR, would have a
2 right-of-way cost of 9.6 million dollars and a construction
3 cost of 24.0 million dollars.
4 And Alternative 3, a partial cloverleaf
5 interchange with loop-ramps in both the northwest and
6 southeast quadrants would have a right-of-way cost of 9.0
7 million dollars and a construction cost of 24.6 million
8 dollars.
9 RESULTS OF ANALYSIS
10 Key results from the alternatives analysis are
11 that overall right-of-way impact from the interchange ramps
12 will be similar regardless of the alternative, because there
13 are two tracts of land in the southeast quadrant that become
14 landlocked (there would be no access to or from Oslo Road)
15 due to the interchange Limited Access Right-of-Way
16 requirements.
17 Impacts to right of way, wetlands, and the eagle's
18 nest associated with the realignment of 82nd Avenue could be
19 minimized by shortening the length of the realignment.
20 Impacts to access associated with closing 86th
21 Avenue SW can be offset by constructing a shell rock road
22 within the existing right of way of 13th Street SW between
23 86th Avenue SW and 90th Avenue SW.
24 Right of way associated with a diamond ramp in the
25 northeast quadrant (as in Alternatives 1 and 2) would
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 11
1 directly impact the three southwest-most parcels in the
2 Aerodrome and bring potential noise impacts closest to the
3 community.
4 Constructing a loop-ramp in the northwest quadrant
5 (as in Alternatives 2 and 3) will eliminate the need for a
6 signal at the west side ramps.
7 Constructing a loop-ramp in the southeast quadrant
8 (as in Alternative 3) eliminates impacts to the residential
9 parcels and the associated noise is kept further away from
10 the community.
11 The existing noise wall along I-95 is effective in
12 shielding the Aerodrome community from traffic noise.
13 Based on the results of the noise study,
14 lengthening the wall 80 feet southward is recommended.
15 Potential impacts to the Aerodrome access off of
16 82nd Avenue SW can be minimized by revising the design
17 concept to create a new T-intersection from "old" 82nd SW to
18 "realigned" 82nd Avenue SW.
19 During design, the placement of interchange
20 lighting will be coordinated with the Aerodrome community to
21 ensure there are no impacts to airplane take-off and landing
22 patterns; and drainage ponds (all located within the
23 interchange right of way) will be designed as dry retention
24 to avoid attracting birds that could impact airplane
25 takeoffs and landings.
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 12
1 ALTERNATIVES EVALUATION CRITERIA
2 In order to choose a recommended alternative, a
3 series of criteria were developed associated with the key
4 issues identified for the project in terms of the project's
5 social and economic effects, environmental effects,
6 engineering considerations, project costs, and public
7 comments received during the Alternatives Workshop and
8 Aerodrome Community Meeting.
9 Five criteria were developed to assess social and
10 economic effects. These are Planning Consistency, Improved
11 Emergency Evacuation, Improved Emergency Response Time,
12 Improved Regional Connectivity and the potential relocation
13 of residences and businesses.
14 Four criteria were developed to assess
15 environmental effects. These are the Aerodrome community,
16 the Aerodrome airport, acreage of uplands affected, and
17 acreage of wetlands affected.
18 Two criteria were developed to assess engineering
19 considerations. These are improved traffic operations to
20 area roadways and intersections, and the operational design
21 life or anticipated performance over time.
22 Project costs were compared in terms of
23 right-of-away and construction costs, and public input was
24 assessed in terms of how many individuals expressed a
25 preference for a specific alternative.
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 13
1 The three build alternatives and the no-build
2 alternative, which remains a viable alternative until the
3 end of the project, were then ranked 1 to 4, with 1 being
4 the best performing and 4 being the worst performing, for a
5 given criteria.
6 In terms of social and economic effects, each of
7 the build alternatives are equal in their ability to meet
8 the criteria and were given a ranking of 1. The No-Build
9 Alternative received a ranking of 4 for planning
10 consistency, improved emergency evacuation, improved
11 emergency response time and improved regional connectivity
12 because no interchange would be constructed.
13 There are no relocations anticipated as a result
14 of this project; therefore, all build alternatives and the
15 no-build alternative received a ranking of 1 for this
16 criteria.
17 In terms of environmental effects, the No-Build
18 Alternative received a ranking of 1 in each criteria because
19 no interchange would be constructed, and therefore no
20 impacts would be anticipated for these criteria.
21 For community effects to Aerodrome, Alternative 3
22 received the next highest ranking of 2 because the ramp in
23 the northeast quadrant is furthest from the community for
24 this alternative. Alternatives 1 and 2 are closer in the
25 northeast quadrant and therefore were each ranked 3 for this
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 14
1 criteria.
2 For the Aerodrome Airport, none of the
3 alternatives would encroach into the glide slope of
4 aircraft, and therefore all alternatives were given a
5 ranking of 1 for this criteria.
6 For uplands, Alternative 1 ranked second with
7 59.350 acres affected, followed by Alternative 2 with 69.172
8 acres affected and, lastly, Alternative 3 with 76.438 acres
9 affected.
10 For wetlands, each build alternative will affect
11 the same 4.73 acres of wetlands in the southwest and
12 southeast quadrants. Overall, all build alternatives are
13 essentially the same and have been given a ranking of 2.
14 For improved traffic operations, each of the build
15 alternatives has the same positive effect (reduced delay and
16 traffic queues) at the existing SR-60 interchange (a key
17 State Strategic Intermodal System roadway), and has received
18 a ranking of 1. The No-Build Alternative received a ranking
19 of 4 because no interchange would be constructed and
20 therefore no benefit to SR-60 would result for this
21 criteria.
22 For operational design life, Alternative 3
23 received a ranking of 1 since it removes all left-turn
24 movements from Oslo Road using loop-ramps instead of in the
25 northwest and southeast quadrants. Alternative 2 received a
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 15
1 ranking of 2 since eastbound to northbound left turns would
2 still be required from Oslo Road. Alternative 1 received a
3 ranking of 3 since it would require a signal to handle the
4 westbound to southbound left-turn movement. The No-Build
5 Alternative received a ranking of 4 because no interchange
6 would be constructed; and, therefore, no regional connection
7 would be created requiring more circuitous travel for trucks
8 and vehicles along 82nd Avenue SW and SR-60.
9 For project costs, the No-Build Alternative
10 received a ranking of 1 because no interchange would be
11 constructed and therefore no dollars would be expended for
12 this project. Alternative 1 received a ranking of 2 with a
13 cost of 31.3 million dollars in right-of-way and
14 construction costs. Alternatives 2 and 3 each received a
15 ranking of 3 and have a cost of 33.6 million dollars in
16 right-of-way and construction costs.
17 For public input, Alternative 3 received a ranking
18 of 1 because it received the largest number of comments in
19 favor, with 5 specific comments and 6 general comments in
20 favor of any alternative. Alternative 2 received a ranking
21 of 2 because it had one specific comment in favor and six
22 general comments in favor. Alternative 1 received a ranking
23 of 3 because it received six general comments in favor, and
24 the No-Build Alternative received a ranking of 4 because it
25 received three specific comments recommending against
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 16
1 building any interchange.
2 RECOMMENDED ALTERNATIVE
3 The rankings were then summed for each
4 alternative, and the lowest sum total was ranked the
5 highest.
6 Alternative 3 ranked number 1 with a score of 20;
7 Alternatives 1 and 2 tied and were ranked number 2, each
8 with a score of 22; and the No-Build Alternative was ranked
9 number 4 with a score of 34.
10 Based on this assessment, Alternative 3 was
11 selected as the recommended alternative.
12 PROJECT SCHEDULE
13 After the public record closes on December 28th,
14 we will address the public comments received and incorporate
15 them into the final documents. Then we will forward the
16 recommended alternative to FHWA for consideration and
17 concurrence. This is anticipated in the first quarter of
18 2016. If a build alternative is selected, design of the
19 interchange is ready to start upon approval. Funding for
20 right of way and construction have been included in the
21 Approved Second Five-Year Plan of the FDOT Strategic
22 Intermodal System Funding Strategy (Fiscal Year 2020/2021
23 through Fiscal Year 2024/2025). If a build alternative is
24 selected, the interchange could be open to traffic in 2025
25 or 2026.
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 17
1 OSLO ROAD WIDENING PD&E STUDY
2 The following slides will discuss the design
3 alternatives that were evaluated for the Oslo Road Widening
4 PD&E Study.
5 PROJECT LOCATION
6 The Oslo Road Widening study limits extend from
7 east of I-95 to 58th Avenue SW. The project lies within the
8 designated regional workplace district, which encompasses
9 the land uses north and south of Oslo Road from east of I-95
10 to 74th Avenue SW.
11 PROJECT PURPOSES & NEED
12 Some of the key project needs are as follows:
13 Support planned social/economic development by providing
14 improved regional access to the land uses north and south of
15 Oslo Road from east of I-95 to 74th Avenue SW that have been
16 designated as a regional workplace district.
17 Widening of the project corridor would accommodate
18 the planned future travel demand and maintain a level of
19 service C for the segments of Oslo Road as per FDOT level of
20 service standards.
21 Oslo Road is designated as a primary truck route
22 per the Indian River County Metropolitan Planning
23 Organization Truck Traffic Routing Plan. In addition, the
24 MPO Bicycle/Pedestrian Plan Update has identified Oslo Road
25 as having a need for bicycle lanes and sidewalks.
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 18
1 EXISTING CONDITIONS
2 Within the limits of the study, Oslo Road is
3 classified as an undivided rural minor arterial which
4 features one 12-foot lane in each direction with a posted
5 speed of 55 miles per hour. The existing right-of-way width
6 varies from 60 feet to 130 feet, and the approximate project
7 length is 3.24 miles.
8 PROJECT SEGMENTATION
9 The project was divided into three distinct
10 segments having similar characteristics. Each segment has
11 rather unique characteristics as well as potential
12 differences in right of way, operational and geometric
13 features. The breakdown is as follows: Segment 1 is from
14 east of I-95 to 74th Avenue SW; Segment 2 is from 74th
15 Avenue SW to 0.62 miles east of 66th Avenue SW; and, Segment
16 3 is from 0.62 miles east of 66th Avenue SW to 58th Avenue
17 SW.
18 TRAFFIC ANALYSIS
19 A comprehensive traffic analysis was performed for
20 existing conditions as well as for projected vehicular
21 volumes for the years 2020, 2030 and 2040. One of the
22 study's goals is to develop design alternatives that would
23 efficiently accommodate traffic volumes that are projected
24 to occur in 2040, the design year. Traffic efficiency is
25 generally measured in terms of "level of service", which
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 19
1 ranges from "A" (or free flowing conditions), to "F" (or
2 highly congested).
3 The results of the future traffic analysis
4 indicate that in order for Oslo Road to properly accommodate
5 projected 2040 traffic volumes, the existing two-lane
6 facility between the project limits would have to be widened
7 to four lanes.
8 ENGINEERING ANALYSIS
9 Data collection, traffic and safety analysis,
10 analysis of existing roadway and alternative development and
11 evaluation were performed in this PD&E Study. A "No-Build"
12 alternative, several Transportation System Management and
13 Operations, or TSM&O Improvements, and over three distinct
14 build alternatives were developed for Oslo Road. Both the
15 "No-Build" option, which maintains the existing facilities
16 "as is" and the TSM&O alternatives, which entail minor
17 improvements, such as improving signage, and/or providing
18 operational improvements, would not effectively address the
19 safety and capacity needs associated with the corridor.
20 TYPICAL SECTION EVALUATION
21 In order to determine the typical section or
22 sections that will most adequately meet the needs of the
23 project, various options ranging in design from the most
24 ample rural sections to the most restricted urban sections
25 were developed and evaluated. The results indicate that two
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 20
1 suburban typical sections with design speed of 55 miles per
2 hour are the most suitable options. One typical section
3 features four 12-foot lanes, an inside and outside curb and
4 gutter, and has 173 feet of right of way. The second
5 typical section features four 12-foot lanes with an inside
6 curb and a gutter and an outside flush shoulder, and has 190
7 feet of right of way. In order to fully evaluate potential
8 differences, two distinct Alternatives 1 and 2 were
9 generated and are described as follows:
10 Alternative 1 within Segment 1 (from 82nd Avenue
11 SW to 74th Avenue SW), features a four-lane divided typical
12 section with 12-foot travel lanes, 7-foot bicycle lanes,
13 curb and gutters, and 5-foot sidewalks, along with a 30-foot
14 median. The total proposed right of way for this section is
15 173 feet.
16 Along Segment 2 (from 74th Avenue SW to 0.62 miles
17 east of 66th Avenue SW), this alternative also requires 173
18 feet of right of way; however, in order to avoid impacting
19 an existing abutting commercial land use (Jordan Landscape &
20 Irrigation located just east of the 66th Avenue SW
21 intersection), this section was reduced by 25 feet through
22 the provision of guardrail along the south side. This new
23 reduced or "modified" section would extend from just west of
24 the 66th Avenue SW intersection to 1200 feet west of the
25 58th Avenue SW intersection.
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 21
1 The short easternmost project segment (Segment 3)
2 essentially involves a transition between the previous
3 "modified" typical section and the existing urban 45-mile
4 per hour typical section east of the 58th Avenue SW
5 intersection. In order to provide an adequate transition
6 within this segment, a slight alignment shift is necessary.
7 This shift would infringe on a portion of the existing canal
8 and thus would require its piping within the immediate
9 vicinity of the 58th Avenue SW intersection.
10 Alternative 2 within Segment 1 (from 82nd Avenue
11 SW to 74th Avenue SW) features a four-lane divided typical
12 section with 12-foot travel lanes, 7-foot bicycle lanes,
13 flush shoulders, 5-foot sidewalks, along with a 30-foot
14 divided median. The total proposed right of way for this
15 section is 190 feet. The location and characteristics of
16 all proposed median openings along this alternative are
17 similar to Alternative 1. This option was also modified to
18 reduce potential right-of-way impacts to the Jordan
19 Landscaping and Irrigation site located just east of the
20 66th Avenue SW intersection. The new "modified" or reduced
21 typical sections strives to minimize the distance to the
22 sub-lateral B-7 canal by providing guardrail protection.
23 This new "modified" typical section would extend from just
24 west of the 66th Avenue SW intersection to 1200 feet west of
25 the 58th Avenue SW intersection.
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 22
1 As was the case for the previous alternative, the
2 easternmost segment involves the provision of the most
3 effective transition to the recently constructed west
4 approach of the 58th Avenue SW intersection. This
5 transition also involves an alignment shift and the piping
6 of the existing canal within the immediate vicinity of the
7 58th Avenue SW intersection.
8 ALTERNATIVES EVALUATION
9 In order to determine the alternative that will
10 most adequately meet the needs of the project, a
11 comprehensive evaluation utilizing a numerical/descriptive
12 matrix approach was used. Important considerations such as
13 traffic service, right-of-way impacts, cost, as well as
14 impacts to the social, physical, and natural environment,
15 were carefully considered. The results indicate that
16 Alternative 1 offers the best potential to address the
17 project's purpose and need while minimizing right-of-way
18 impacts.
19 ACCESS MANAGEMENT
20 Access Management is the practice of managing the
21 location, number and spacing of driveway connections, median
22 openings and traffic signals. The evaluation and
23 implementation of proper access management techniques can
24 result in improved movement of traffic, fewer vehicle
25 conflicts, and reduced crashes. After a comprehensive
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 23
1 analysis, it was determined that the most effective typical
2 section includes the provision of a 30-foot raised median
3 along Oslo Road. With a raised median, full and directional
4 median openings are recommended at different locations along
5 the corridor. All proposed median openings are displayed on
6 the aerials available here tonight and follow the access
7 management standards for an access class 3 facility.
8 Access class 3 facilities are controlled access
9 facilities where direct access to abutting land will be
10 controlled to maximize the operation of the through traffic
11 movement with directional or full median opening spacing of
12 1320 feet and 2640 feet respectively.
13 PROPOSED POND LOCATIONS
14 A Preliminary Pond Siting Report was prepared.
15 The objective of the report was to determine the type and
16 potential locations for the construction of stormwater
17 facilities to manage the stormwater runoff from the proposed
18 improvements. Oslo Road was divided into three distinct
19 drainage basins. The report identified three potential wet
20 detention pond sites in each basin that will be further
21 analyzed during the design phase.
22 ENVIRONMENTAL ANALYSIS
23 The recommended alternative was evaluated in terms
24 of its impacts to the natural, physical, cultural and social
25 environments. A Categorical Exclusion Type II Report, which
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 24
1 summarizes the environmental impacts associated with the
2 recommended alternative was prepared and is available for
3 review. No significant impacts are anticipated to any
4 environmental categories.
5 No adverse impacts to wildlife are anticipated
6 with the proposed project.
7 Potential for impacts to the undeveloped rural
8 farmlands surrounding the project is minimal. No prime
9 and/or locally important farmlands have been identified
10 within the project limits.
11 There are several potential sources of
12 contamination in the vicinity including petroleum fuel
13 storage tanks, hazardous waste facilities and landfills.
14 Further assessment during the design phase is recommended
15 for these sites.
16 In accordance with the Code of Federal Regulation
17 Part 772, a comprehensive noise analysis on the selected
18 recommended alternative was conducted.
19 One residence along the north side of the project
20 corridor is expected to be impacted by traffic noise due to
21 the planned improvements. No other residences are predicted
22 to be impacted along this project. FDOT policy requires at
23 least two impacted sites in order for a noise barrier to be
24 evaluated. Therefore, noise abatement is not considered
25 feasible.
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 25
1 CONCLUSION & RECOMMENDATIONS
2 In conclusion, Alternative 1 is the recommended
3 build option for the Oslo Road Widening PD&E Study, and
4 consists of widening the existing two-lane roadway to a
5 divided four-lane curb and gutter typical section along all
6 three segments of the project with the canal piped along
7 segment 3, and classified as a controlled access facility
8 (access class 3).
9 PROJECT COST
10 Twenty properties will require partial acquisition
11 in order to implement the recommended improvements. We do
12 not anticipate the relocation of any families or businesses.
13 The right-of-way acquisition cost is estimated to be
14 approximately 5.86 million dollars. Construction cost for
15 Oslo Road is estimated at 16.3 million dollars.
16 REAL ESTATE ACQUISITION PROCESS
17 While one of the unavoidable consequences of many
18 transportation projects is the necessary relocation of
19 families or businesses, we do not anticipate the relocation
20 of any families or businesses for either of these projects.
21 All right-of-way acquisition will be conducted in accordance
22 with the Federal Uniform Relocation Assistance and Real
23 Property Acquisition Policies Act of 1970, commonly known as
24 the Uniform Act.
25 If you are required to make any type of move as a
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 26
1 result of a Department of Transportation project, you can
2 expect to be treated in a fair and helpful manner and in
3 compliance with the Uniform Relocation Assistance Act. If a
4 move is required, you will be contacted by an appraiser who
5 will inspect your property. We encourage you to be present
6 during the inspection and provide the information about the
7 value of your property.
8 You may also be eligible for relocation advisory
9 services and payment benefits. If you are being moved and
10 you are unsatisfied with the department's determination of
11 your eligibility for payment or the amount of that payment,
12 you may appeal that determination. You will be promptly
13 furnished necessary forms and notified of the procedures to
14 be followed in making that appeal.
15 A special word of caution - if you move before you
16 receive notification of the relocation benefits that you
17 might be entitled to, your benefits may be jeopardized.
18 Relocation specialists are available here tonight. They
19 will happy to answer your questions and will also furnish
20 you with copies of relocation assistance brochures.
21 PROJECT SCHEDULE
22 This project is currently in the Project
23 Development and Environment (PD&E) phase. The funds for the
24 final design have been programmed to commence in 2016. The
25 right-of-way acquisition and construction phases of the
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 27
1 project are currently unfunded.
2 PROJECT DOCUMENTS
3 The proposed improvements were documented in the
4 engineering and environmental studies conducted for these
5 projects. These documents and preliminary plans showing the
6 proposed interchange and roadway construction improvements
7 are available here tonight for anyone who wishes to examine
8 them. Project information will also be available for review
9 at the FDOT District 4 office located at 3400 West
10 Commercial Boulevard, Fort Lauderdale, Florida 33309, at the
11 Indian River State College - Mueller Campus Brackett Library
12 located at 6155 College Lane, Vero Beach, Florida 32966, and
13 on the study website, www.oslopde.com.
14 WRITTEN STATEMENTS
15 There have been various opportunities for the
16 public to provide input on this project. Several public
17 meetings have been held dating from October 2014 until
18 tonight. We welcome any oral or written comments you might
19 have that will help us make this important decision. At the
20 conclusion of this presentation, our personnel will
21 distribute speaker cards to those in the audience who have
22 not received one and would like to make a statement. A
23 court reporter will record your statement and a verbatim
24 transcript will be made of all oral proceedings at this
25 hearing. If you do not wish to speak at the microphone, you
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 28
1 may present your comments in writing or directly to the
2 court reporter at the comment table. Each method of
3 submitting a comment carries equal weight. Written comments
4 received or postmarked no later than ten days following the
5 date of this public hearing will become a part of the public
6 record for this public hearing.
7 Thank you, this concludes our presentation.
8 MR. YOUNG: Okay. At this time, anyone
9 desiring to make a statement, represent written
10 views and/or exhibits relative to the location,
11 conceptual design, socioeconomic effects or
12 impacts on the environment as a result of these
13 projects, will have an opportunity to do so.
14 This is an opportunity for you to formally
15 present your comments, opinions and ideas about
16 the project for the permanent record. We ask
17 that you limit your comments to three minutes,
18 and if you have additional comments you may
19 continue after everyone else has had the
20 opportunity to comment. We'll have staff
21 available after the comment period to address
22 any specific questions one-on-one.
23 If you're holding speaker's cards, please
24 pass your card to the aisle and our staff will
25 collect them. And if you have not received a
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 29
1 card and wish to speak, please raise your hand
2 and our staff will provide you with one.
3 Are there any public officials who'd like
4 to make a statement?
5 Okay. We'll now call on those who have
6 turned in cards. When we call your name,
7 please raise your hand and one of our staff
8 will bring you the microphone. Please state
9 your name and address. And if you represent an
10 organization, municipality or other public
11 entity, we'd appreciate that information as
12 well.
13 We have any cards?
14 UNIDENTIFIED SPEAKER 1: I have a
15 question. Is the PowerPoint Presentation
16 available anywhere?
17 MR. YOUNG: Yes, it'll be on the website.
18 UNIDENTIFIED SPEAKER 1: On the county
19 website. Thank you.
20 MR. YOUNG: Does anyone want to make a
21 statement? You can make a statement and we can
22 get a card afterwards.
23 Okay. I guess --
24 UNIDENTIFIED SPEAKER 2: Can we ask a
25 question?
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 30
1 MR. YOUNG: Sure, go ahead.
2 UNIDENTIFIED SPEAKER 2: Did I understand
3 the slide that the construction period is five
4 years?
5 MR. YOUNG: It'll be about five years.
6 UNIDENTIFIED SPEAKER 2: 2025?
7 MR. YOUNG: It'll be about five years
8 until the funding and the design and the
9 right-of-way's complete before construction
10 will begin.
11 UNIDENTIFIED SPEAKER 2: No. But once
12 construction begins, the construction period --
13 MR. YOUNG: Construction's about a year
14 and a half, two years. So if the funding stays
15 as it is, by 2025 or 2026 the interchange will
16 be open. It may be sooner. We try to get
17 these things moved up if we can.
18 So if no one else wants to make a comment,
19 we'll go on. I have to make a few closing
20 statements.
21 Written statements may be sent to the
22 attention of Mr. Ron Wallace at the Florida
23 Department of Transportation, District Four,
24 3400 West Commercial Boulevard, Fort
25 Lauderdale, Florida 33309.
dfe4a655-e909-42df-9548-c8fc30a2bb6c
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 31
1 If written statements are postmarked
2 within ten days after the day of this hearing,
3 they will be included as part of the public
4 record for this hearing. The verbatim
5 transcript of this hearing's oral proceedings,
6 together with all written material received as
7 part of the hearing record and all studies,
8 displays and informational material provided at
9 the hearing, will be made a part of the project
10 decision-making process and will be available
11 at the District Office for public review upon
12 request. It should also be available on the
13 website.
14 And at 6:39, I officially close the public
15 hearing for the Oslo Road PD&E studies.
16 Thank you and good night. Thank you very
17 much for coming.
18 (Proceedings concluded at 6:39 p.m.)
19
20
21
22
23
24
25
060d9e8b-6d7f-4786-9a9c-663e31ccc24d
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 32
1 STATE OF FLORIDA ) : SS
2 COUNTY OF MARTIN )
3
4 CERTIFICATE OF REPORTER
5 I, VANESSA G. ARCHER, Registered Professional
6 Reporter, a Machine Shorthand Reporter and Notary Public of
7 the State of Florida at Large, certify that the foregoing
8 proceedings were stenographically reported by me and is a
9 true and accurate transcription of said proceedings.
10
11 I certify further I am neither attorney nor
12 counsel for, nor related to, nor employed by any of the
13 parties to the action in which the deposition is taken and,
14 further, that I am not a relative or an employee of any
15 attorney or counsel employed in this case, nor am I
16 financially interested in the outcome of this action.
17 DATED this 4th day of January, 2016.
18
19 ________________________ VANESSA G. ARCHER, FPR
20
21
22
23
24
25
(800) 336-0050WWW.ATLANTICREPORTING.COM
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 33
Aabatement
24:24ability 13:7abutting 20:19
23:9acceptance 8:18accepted 8:24
9:2access 8:1,5
10:14,15,2011:15 17:1422:19,20,2323:6,7,8,8,925:7,8
accommodate8:12 17:1718:23 19:4
accurate 32:9acquire 9:10acquisition
25:10,13,16,2125:23 26:25
acreage 12:1612:17
acres 14:7,8,8,11Act 5:22 25:23
25:24 26:3action 32:13,16addition 8:19
17:23additional 8:11
28:18address 16:14
19:18 22:1628:21 29:9
adequate 7:1621:5
adequately19:22 22:10
Administration8:25
adverse 4:7,224:23 24:5
advertised 5:3advisory 26:8aerials 23:6
Aerodrome 9:1311:2,12,15,2012:8,15,1613:21 14:2
affect 9:7 14:10age 5:12ahead 30:1Aid 3:20aircraft 14:4airplane 11:21
11:24airport 12:16
14:2aisle 28:24alignment 21:6
22:5alternative 5:19
5:25 9:8,20,2410:4,12 11:812:2,25 13:2,213:9,15,18,2113:24 14:6,7,814:10,18,22,2515:2,5,9,12,1715:20,20,22,2416:2,4,6,8,1016:11,16,18,2319:10,12 20:1020:17 21:10,1621:17 22:1,922:16 23:2324:2,18 25:2
alternatives 4:64:21 7:3 8:209:18 10:10,2511:5 12:1,713:1,7,14,2414:3,4,12,1515:14 16:717:3 18:2219:14,16 20:822:8
amount 26:11ample 19:24analysis 6:3 8:20
9:8 10:9,1018:18,19 19:3
19:8,9,10 23:123:22 24:17
analyze 5:24analyzed 9:18
23:21and/or 19:17
24:9 28:10answer 26:19anticipate 25:12
25:19anticipated
12:21 13:13,2016:17 24:3,5
appeal 26:12,14appraiser 26:4appreciate
29:11approach 22:4
22:12approval 16:19Approved 16:21approximate
18:6approximately
25:14ARCHER 32:5
32:19area 7:10 8:4,11
8:14 12:20arterial 18:3assess 8:18 12:9
12:14,18assessed 12:24assessment
16:10 24:14assistance 25:22
26:3,20associated 9:9
10:18,20,2411:9 12:319:19 24:1
attention 30:22attorney 32:11
32:15attracting 11:24audience 27:21available 23:6
24:2 26:1827:7,8 28:2129:16 31:10,12
Avenue 1:2 2:113:17,23,256:10,12,147:13,13,1510:18,21,23,2311:16,18 15:817:7,10,1518:14,15,15,1618:16 20:10,1120:16,17,20,2420:25 21:4,921:10,11,20,2421:25 22:4,7
Avenues 9:11avoid 11:24
20:18
BB-7 21:22barrier 24:23Based 11:13
16:10basin 23:20basins 23:19Beach 1:13
27:12begins 30:12beneficial 4:7,22benefit 14:20benefits 26:9,16
26:17best 5:24 13:4
22:16bicycle 17:25
20:12 21:12Bicycle/Pedest...
17:24birds 11:24board 2:16Boulevard 27:10
30:24Brackett 27:11breakdown
18:13bring 11:2 29:8
brochure 5:9brochures 26:20build 13:1,7,14
14:10,12,1416:18,23 19:1425:3
building 9:1716:1
businesses 12:1325:12,19,20
CC 17:19call 29:5,6Campus 1:12
27:11canal 21:7,22
22:6 25:6capacity 19:19card 28:24 29:1
29:22cards 27:21
28:23 29:6,13carefully 22:15Carlos 1:20 2:20carries 28:3case 22:1 32:15Categorical
23:25categories 24:4caution 26:15Center 1:12CERTIFICATE
32:4certify 32:7,11characteristics
18:10,11 21:15charge 2:18choose 12:2circuitous 15:7city 2:25class 23:7,8 25:8classified 18:3
25:7close 31:14closer 13:24closes 16:13closest 11:2
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 34
closing 10:2030:19
cloverleaf 9:4,2410:1,4
Code 24:16collect 28:25collection 19:9College 1:12,13
27:11,12color 5:11combined 5:23coming 2:2
31:17commence
26:24comment 2:12
3:9 4:3,2415:21 28:2,328:20,21 30:18
comments 4:124:18 5:2 12:715:18,19,19,2215:23,25 16:1427:18 28:1,328:15,17,18
commercial20:19 27:1030:24
commonly 25:23community 4:9
9:13 11:3,1011:12,20 12:812:15 13:21,23
community's5:25
compared 12:22compatible 5:17complete 4:1
30:9compliance 26:3component 6:2,4
6:6components
4:14 6:1comprehensive
18:19 22:11,2524:17
comprised 6:25concept 4:1 9:21
10:1 11:17concepts 9:1conceptual 4:6
28:11concerns 4:11
5:5concluded 31:18concludes 28:7conclusion 25:1
25:2 27:20concurrence
16:17conditions 18:1
18:20 19:1conducted 7:18
24:18 25:2127:4
conflicts 22:25congested 19:2connection 15:6connections
22:21connectivity
7:22 12:1213:11
consequences25:17
consideration16:16
considerations12:6,19 22:12
considered22:15 24:24
consistency12:10 13:10
consistent 5:36:16
consists 25:4constructed
13:12,19 14:1915:6,11 22:3
constructing10:21 11:4,7
construction9:22 10:2,7
12:23 15:14,1616:20 23:1625:14 26:2527:6 30:3,9,1230:12
Construction's30:13
Consultant 1:191:20 2:17,20
consulting 2:23contact 5:8contacted 26:4contacting 5:5contamination
24:12continue 5:1
28:19controlled 23:8
23:10 25:7coordinated
11:20coordination
7:18copies 26:20corridor 17:17
19:19 23:524:20
cost 9:22,23 10:210:3,6,7 15:1315:15 22:1325:9,13,14
costs 12:6,22,2315:9,14,16
counsel 32:12,15county 1:3 2:25
3:18,22 6:9,116:17 7:1,8,8,237:25 8:8,1317:22 29:1832:2
county's 8:13court 4:18 5:2
27:23 28:2CR 3:22,23crashes 22:25create 11:17created 15:7
criteria 12:1,3,912:14,18 13:513:8,16,18,2014:1,5,21
critical 6:24cultural 23:24curb 20:3,6,13
25:5currently 26:22
27:1
DData 19:9date 28:5DATED 32:17dating 27:17day 31:2 32:17days 28:4 31:2December 1:8
16:13decision 27:19decision-maki...
31:10delay 14:15demand 17:18Department 2:3
2:8 3:13 5:6,76:23 26:130:23
department's26:10
deposition 32:13described 20:9DESCRIPTION
7:9design 4:6 5:15
6:3 7:2 11:1611:19 12:2014:22 16:1817:2 18:22,2419:23 20:123:21 24:1426:24 28:1130:8
designated 8:617:8,16,21
designed 11:23desiring 28:9
detention 23:20determination
26:10,12determine 19:21
22:9 23:15determined 5:20
23:1determines 5:18develop 18:22developed 9:2
12:3,9,14,1819:14,25
developing 9:9development 1:1
1:2 2:7 3:165:13 6:7 8:128:17 9:8 17:1319:10 26:23
diamond 9:3,39:20,21 10:24
differences18:12 20:8
different 23:4dimmed 3:5direct 8:1 23:9direction 18:4directional 23:3
23:11directly 4:17
11:1 28:1disability 5:12discuss 7:2 17:2displayed 5:9
23:5displays 4:17
31:8distance 21:21distinct 18:9
19:13 20:823:18
distribute 27:21district 1:17,18
2:6,15 5:6 8:1417:8,16 27:930:23 31:11
divided 18:920:11 21:11,14
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 35
23:18 25:5document 5:16
5:24documented
27:3documents
16:15 27:2,5dollars 9:22,23
10:2,3,7,815:11,13,1525:14,15
drainage 11:2223:19
drivers 7:22driveway 22:21dry 11:23due 10:15 24:20
EE 1:2eagle's 9:15
10:17east 1:2 3:23,25
6:12,13 7:137:19 9:15 17:717:9,15 18:1418:15,16 20:1720:20 21:4,19
east-side 7:16eastbound 15:1easternmost
21:1 22:2economic 4:8
8:12 12:5,1013:6
effect 14:15effective 11:11
22:3 23:1effectively 19:18effects 12:5,5,10
12:15 13:6,1713:21 28:11
efficiency 18:24efficiently 18:23effort 5:23either 5:5 8:2
25:20elected 6:25
eligibility 26:11eligible 26:8eliminate 11:5eliminates 11:8eliminating 8:2emergency 7:23
12:11,11 13:1013:11
employed 32:1232:15
employee 32:14encompasses
17:8encourage 26:5encouraged 5:10encroach 14:3Engineer 2:7engineering
1:21 2:21 5:186:2 12:6,1819:8 27:4
ensure 11:21entail 19:16entails 3:21,24
6:2entitled 26:17entity 29:11environment 1:1
1:2 3:16 5:135:17 22:1426:23 28:12
environmental4:8 5:22 6:312:5,15 13:1723:22 24:1,427:4
environmenta...5:19
environments6:5 23:25
equal 13:7 28:3essentially 14:13
21:2ESTATE 25:16estimated 25:13
25:15evacuation 8:11
12:11 13:10evaluate 5:15
6:4 20:7evaluated 7:3
17:3 19:2523:23 24:24
evaluation 12:119:11,20 22:822:11,22
evening 3:13examine 27:7Exclusion 23:25exhibits 28:10existing 7:7 8:23
10:22 11:1114:16 18:1,518:20 19:5,1019:15 20:1921:3,7 22:625:4
expect 26:2expected 24:20expended 15:11explain 4:20express 4:10 5:4expressed 12:24extend 6:10,13
17:6 20:2321:23
extends 6:12
FF 19:1facilitate 8:13facilities 19:15
23:8,9,1724:13
facility 19:6 23:725:7
fair 26:2families 25:12
25:19,20family 5:12farmlands 24:8
24:9favor 15:19,20
15:21,22,23FDOT 1:17,18
2:15,23 6:207:1 16:2117:19 24:2227:9
feasible 5:1924:25
features 18:4,1320:3,5,1121:11
federal 1:4 2:253:20 5:4,228:24 24:1625:22
feet 7:11,11,127:13 11:1418:6,6 20:4,720:15,18,21,2421:15,24 23:1223:12
fewer 22:24FHWA 8:25
16:16final 16:15 26:24finalize 4:12Financial 1:3
3:19financially
32:16first 4:15 8:16
16:17Fiscal 16:22,23five 12:9 30:3,5
30:7Five-Year 16:21Florida 1:3,13
2:3,7 3:13 5:65:7 6:23 27:1027:12 30:22,2532:1,7
flowing 19:1flush 20:6 21:13follow 23:6followed 14:7
26:14following 3:10
4:24 7:2 17:228:4
follows 17:1218:13 20:9
foregoing 32:7formal 4:24formally 28:14forms 26:13Fort 27:10 30:24forum 4:10forward 16:15four 3:24 12:14
19:7 20:3,530:23
four-lane 20:1121:11 25:5
FPR 32:19free 19:1fuel 24:12full 23:3,11fully 20:7fund 6:24funding 16:19
16:22 30:8,14funds 26:23furnish 26:19furnished 26:13further 9:18
11:9 23:2024:14 32:11,14
furthest 13:23future 17:18
19:3
GG 32:5,19gathered 4:12general 4:5
15:19,22,23generally 18:25generated 20:9geometric 18:12given 13:5,8
14:4,13glide 14:3go 30:1,19goals 18:22good 3:13 31:16governments
6:24
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 36
guardrail 20:2221:22
guess 29:23gutter 20:4,6
25:5gutters 20:13
Hhalf 30:14hand 29:1,7handle 15:3happy 26:19hazardous 24:13hearing 1:1 2:3
2:5,11 3:15,184:2,4,9,15 5:35:10,10 27:2528:5,6 31:2,4,731:9,15
hearing's 31:5heavy 8:5held 2:11 4:2
27:17help 27:19helpful 26:2highest 13:22
16:5highly 19:2Highway 8:24holding 28:23hour 18:5 20:2
21:4house 4:15
II-95 1:1,2 2:9,10
3:15,22,22,256:10,11,12,137:3,11,12,248:2,8 11:1117:7,9,1518:14
ID 1:4ideas 28:15identification
6:2identified 6:21
12:4 17:24
23:19 24:9II 23:25IJR 8:17,24 9:2
9:17,21 10:1immediate 21:8
22:6impact 10:11
11:1,24impacted 24:20
24:22,23impacting 20:18impacts 4:8,22
4:23 6:4 9:119:13,14 10:1710:20 11:2,811:15,21 13:2021:18 22:13,1422:18 23:2424:1,3,5,728:12
implement 6:2425:11
implementation4:1 22:23
important 22:1224:9 27:19
improve 7:21,238:5
improved 8:812:10,11,12,1913:10,10,1114:14 17:1422:24
Improvement6:19,20
improvements2:9 4:6 8:21,2319:13,17,1823:18 24:2125:11 27:3,6
improving 19:17incident 7:24incidents 7:24
8:7included 8:20
16:20 31:3includes 23:2
including 6:1724:12
incorporate16:14
Indian 1:3,123:18 6:10,176:25 7:8,23,258:8 17:2227:11
indicate 19:4,2522:15
individuals12:24
Indrio 7:7 8:3inform 6:6information 4:5
5:8,24 9:1726:6 27:829:11
informational31:8
infringe 21:7input 12:23
15:17 27:16inside 20:3,5inspect 26:5inspection 26:6interchange 1:1
1:19 2:9,193:15,21,216:11 7:4,6,107:20 8:15,178:19,20 9:1,99:12,20 10:510:11,15 11:1911:23 13:12,1914:16,19 15:515:10 16:1,1916:24 27:630:15
interchanges 7:78:23
interested 6:632:16
interface 5:15Intermodal
14:17 16:22
intersection20:21,24,2521:5,9,20,2421:25 22:4,7
intersections12:20
invited 4:16involve 2:9 6:6involvement 6:5involves 21:2
22:2,5Irrigation 20:20
21:19issues 9:6,7,9
12:4it'll 29:17 30:5,7
JJanuary 32:17jeopardized
26:17John 1:19 2:16Jordan 20:19
21:18Justification
8:15,17
KKeith 1:19 2:18kept 11:9key 9:6,8 10:10
12:3 14:1617:12
known 8:2125:23
Krane 1:19 2:16
Lland 10:13 17:9
17:14 20:1923:9
landfills 24:13landing 11:21landings 11:25landlocked
10:14Landscape
20:19
Landscaping21:19
lane 1:13 18:427:12
lanes 3:24 17:2519:7 20:3,5,1220:12 21:12,12
Large 32:7largest 15:18lastly 14:8Lauderdale
27:10 30:25law 5:23left 15:1left-turn 14:23
15:4length 10:19
18:7lengthening
11:14level 17:18,19
18:25Library 27:11lies 17:7life 12:21 14:22light 3:4lighting 11:20limit 28:17Limited 10:15limits 6:13 17:6
18:2 19:624:10
little 3:8local 6:15,16,23
6:25locally 24:9located 7:6
11:22 20:2021:19 27:9,12
location 6:8 7:58:19 9:10 17:521:15 22:2128:10
locations 7:1723:4,13,16
long 3:8 6:19long-distance
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 37
8:4loop-ramp 9:4
9:25 11:4,7loop-ramps 10:5
14:24lowest 16:4Lucie 7:8
MMachine 32:6main 6:1maintain 17:18maintains 19:15making 26:14manage 23:17management
1:3 3:19 8:2219:12 22:19,2022:23 23:7
Manager 1:181:19,20 2:152:17,21
managing 22:20mandated 5:21manner 26:2MARTIN 32:2material 31:6,8matrix 22:12maximize 23:10measured 18:25median 20:14
21:14,16 22:2123:2,3,4,5,11
meet 5:19 13:719:22 22:10
Meeting 12:8meetings 27:17method 28:2methods 4:22Metric 1:21 2:21Metropolitan
6:18 17:22microphone 5:1
27:25 29:8Milepost 1:1miles 18:5,7,15
18:16 20:1,16million 9:22,23
10:2,3,7,715:13,15 25:1425:15
minimal 24:8minimize 21:21minimized
10:19 11:16minimizing
22:17minor 8:21 18:3
19:16minutes 3:9
28:17mitigate 4:23modified 20:23
21:3,17,20,23move 25:25 26:4
26:15moved 26:9
30:17movement 15:4
22:24 23:11movements
14:24MPO 6:18,22,22
6:25 17:24Mueller 1:12
27:11municipality
29:10
Nname 2:6 29:6,9national 5:11,21natural 6:4
22:14 23:24necessary 7:15
8:16 21:625:18 26:13
Nee-pah 5:22need 4:21 5:19
7:20 8:2,189:10 11:517:11,25 22:17
needs 5:16,2517:12 19:19,2222:10
neither 32:11
nest 9:15 10:18new 3:21 8:19
11:17 20:2221:20,23
night 31:16no-build 13:1,8
13:15,17 14:1815:4,9,24 16:819:11,15
noise 11:2,9,1111:12,13 24:1724:20,23,24
north 7:11 8:39:3,15 17:9,1424:19
northbound15:1
northeast 10:2513:23,25
northward 7:14northwest 9:5
9:25 10:5 11:414:25
Nos 1:3Notary 32:6notification
26:16notified 26:13number 3:20
15:18 16:6,7,922:21
Numbers 3:19numerical/des...
22:11numerous 9:7
Oobjective 23:15occur 18:24occurred 4:15October 27:17offers 22:16office 5:6,7 27:9
31:11official 4:9officially 31:14officials 2:25 3:2
6:25 29:3
offset 10:21Okay 3:4 28:8
29:5,23old 11:17once 30:11one-on-one
28:22open 4:15 16:24
30:16opening 23:11openings 21:16
22:22 23:4,5operation 23:10operational 8:18
8:21 12:2014:22 18:1219:18
operations 8:2212:19 14:1419:13
opinions 4:1128:15
opportunities27:15
opportunity2:12 4:3,10,2528:13,14,20
option 19:1521:17 25:3
options 19:2320:2
oral 3:9 5:127:18,24 31:5
Orchid 7:1order 8:3 12:2
19:4,21 20:720:18 21:522:9 24:2325:11
organization6:15,18 17:2329:10
origin 5:12Oslo 1:1,1,4,19
1:20 2:5,103:15,16,21,233:24 6:11,13
7:3,6,10,11,127:14,19 8:6,199:15 10:1414:24 15:217:1,3,6,9,1517:19,21,2418:2 19:4,1423:3,18 25:325:15 31:15
outcome 32:16outside 20:3,6overall 10:11
14:12
Pp.m 1:8 31:18parcels 11:1,9part 8:12 9:18
24:17 28:531:3,7,9
partial 9:4,2410:1,4 25:10
participation5:10
parties 6:6 32:13pass 28:24patterns 11:22payment 26:9,11
26:11PD& 1:2PD&E 1:17,19
1:21 2:5 3:175:13,17 6:1 7:47:18 9:18 17:117:4 19:1125:3 26:2331:15
percent 8:9performance
12:21performed
18:19 19:11performing 13:4
13:4period 3:10 4:24
28:21 30:3,12permanent
28:16
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 38
Persons 5:4petroleum 24:12phase 5:14,20
23:21 24:1426:23
phases 5:1526:25
physical 6:522:14 23:24
piped 25:6piping 21:8 22:5placement 11:19Plan 6:19 16:21
17:23,24planned 5:14 6:7
8:12,13 17:1317:18 24:21
planning 5:155:20 6:15,1812:10 13:917:22
plans 6:17 27:5please 28:23
29:1,7,8Policies 25:23policy 5:22
24:22pond 23:13,14
23:20ponds 11:22portion 21:7positive 14:15posted 18:4postmarked
28:4 31:1potential 4:7,21
6:3,4 9:13 11:211:15 12:1218:11 20:721:18 22:1623:16,19 24:724:11
PowerPoint 3:63:12 29:15
practice 22:20predicted 24:21preference
12:25preliminary 9:1
23:14 27:5prepared 23:14
24:2present 1:16 3:1
26:5 28:1,15presentation 3:6
3:11,12 4:164:20,25 27:2028:7 29:15
presentation's3:8
presenting 3:7previous 21:2
22:1primary 4:14
17:21prime 24:8prior 4:15priority 6:21,22procedures
26:13proceedings
27:24 31:5,1832:8,9
process 5:218:16 9:2,825:16 31:10
Professional32:5
professionals5:24
Program 6:196:20
programmed26:24
project 1:1,2,4,41:18,19,20 2:72:15,17,19,213:16,19,20,213:24 4:3,11,174:17,21,23 5:95:13 6:7,8 7:57:9,19,21 8:1,58:7,10 12:4,612:22 13:3,14
15:9,12 16:1217:5,7,11,1217:17 18:6,8,919:6,23 21:122:10 24:6,824:10,19,2225:6,9 26:1,2126:22,22 27:127:2,8,1628:16 31:9
project's 12:422:17
projected 18:2018:23 19:5
projects 2:13 3:73:10 5:14 6:96:16,21,21,226:24 25:18,2027:5 28:13
promptly 26:12proper 22:23properly 19:4properties 25:10property 25:23
26:5,7proposed 2:8 4:5
4:22 7:6,16,1920:14 21:14,1623:5,13,1724:6 27:3,6
protection 21:22provide 2:11 4:2
4:18,25 5:27:16 8:1,1121:5 26:627:16 29:2
provided 5:831:8
provides 5:14providing 4:10
17:13 19:1721:22
provision 20:2222:2 23:2
proximity 9:12public 1:1 2:3,5
3:14,18 4:4,5,9
4:10 5:3,10 6:512:6,23 15:1716:13,14 27:1627:16 28:5,5,629:3,10 31:331:11,14 32:6
purpose 4:4,217:20,21 22:17
PURPOSES17:11
Qquadrant 9:5,25
10:13,25 11:411:7 13:23,25
quadrants 9:1410:6 14:12,25
quarter 16:17question 29:15
29:25questions 26:19
28:22queues 14:16
Rrace 5:11raise 29:1,7raised 23:2,3ramp 7:16 10:24
13:22ramps 9:10,12
10:11 11:6Range 6:19ranges 19:1ranging 19:23ranked 13:3,25
14:6 16:4,6,7,8ranking 13:8,9
13:15,18,2214:5,13,18,1814:23 15:1,3,515:10,12,15,1715:20,22,24
rankings 16:3ready 16:19Real 25:16,22realigned 11:18realignment
7:15 10:18,19reasons 8:10receive 26:16received 12:7
13:9,15,18,2214:17,18,23,2515:2,5,10,1215:14,17,18,2015:22,23,24,2516:14 27:2228:4,25 31:6
recognize 2:24recognized 3:3recommendati...
4:13 25:1recommended
11:14 12:216:2,11,1623:4,23 24:224:14,18 25:225:11
recommending15:25
record 16:1327:23 28:6,1631:4,7
reduce 21:18reduced 14:15
20:21,23 21:2022:25
regard 5:11regarding 4:11regardless 10:12regional 6:17
7:21 8:1,1412:12 13:1115:6 17:8,1417:16
Registered 32:5Regulation
24:16related 32:12relative 3:18
28:10 32:14religion 5:12relocation 12:12
25:12,18,19,22
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 39
26:3,8,16,1826:20
relocations13:13
remains 13:2removes 14:23report 6:22 8:15
8:17 23:14,1523:19,25
reported 32:8reporter 4:19
5:2 27:23 28:232:4,6,6
represent 28:929:9
representatives2:22
represents 5:23request 31:12require 15:3
21:8 25:10required 15:2
25:25 26:4requirements
5:4 10:16requires 20:17
24:22requiring 15:7residence 24:19residences 12:13
24:21residential 11:8residents 8:11respectively
23:12response 7:24
8:7 12:1113:11
restricted 19:24result 13:13
14:20 22:2426:1 28:12
results 10:9,1011:13 19:3,2522:15
retention 11:23review 24:3 27:8
31:11revising 11:16Richard 1:17
2:6Richardson 1:12right 9:3,10,12
10:17,22,2411:23 16:2018:12 20:4,720:14,18 21:14
right-of-away12:23
right-of-way9:22 10:2,6,1110:15 15:13,1618:5 21:1822:13,17 25:1325:21 26:25
right-of-way's30:9
River 1:3,123:18 6:11,177:1,8,23,25 8:817:22 27:11
road 1:1,1,4,191:20 2:5,103:15,16,21,223:22,23,25 6:96:9,11,13 7:3,67:7,10,12,127:14,19 8:3,68:19 9:1510:14,21 14:2415:2 17:1,3,6,917:15,19,21,2418:2 19:4,1423:3,18 25:325:15 31:15
roadway 14:1719:10 25:427:6
roadways 12:20rock 10:21Rodriguez 1:20
2:20Ron 1:18 2:14
30:22
route 8:6,1117:21
Routing 17:23runoff 23:17runs 7:10rural 9:3 18:3
19:24 24:7
Ssafety 19:9,19SCHEDULE
16:12 26:21Schnars 1:19
2:18score 16:6,8,9second 4:20 14:6
16:21 20:4Secondary 8:10section 19:20,21
20:2,5,12,1420:21,23 21:321:4,12,15,2323:2 25:5
sections 19:2219:24,24 20:121:21
seeing 3:4segment 18:10
18:13,14,1520:10,16 21:121:1,6,10 22:225:7
SEGMENTA...18:8
segments 17:1918:10 25:6
selected 16:1116:18,24 24:17
sent 30:21separation 7:16September 8:25series 12:3serves 4:9service 17:19,20
18:25 22:13services 26:9sex 5:12share 4:4
shell 10:21shielding 11:12shift 21:6,7 22:5short 21:1shortening
10:19Shorthand 32:6shoulder 20:6shoulders 21:13showing 27:5side 9:15 11:6
20:22 24:19sidewalks 17:25
20:13 21:13sign 5:9signage 19:17signal 11:6 15:3signals 22:22significant 24:3similar 9:21,25
10:12 18:1021:17
Simply 5:17site 21:19sites 23:20 24:15
24:23Siting 23:14six 15:21,23slide 3:12 30:3slides 7:2 17:2slight 21:6slope 14:3social 4:8 6:5
12:5,9 13:622:14 23:24
social/economic17:13
socioeconomic28:11
solicited 5:11solutions 5:16
6:3sooner 30:16sources 24:11south 7:11 8:3
17:9,14 20:22southbound
15:4southeast 9:14
10:6,13 11:714:12,25
southern 7:237:25 8:8
southward11:14
southwest 9:1414:11
southwest-most11:1
spacing 22:2123:11
speak 4:17 27:2529:1
speaker 27:2129:14,18,2430:2,6,11
speaker's 28:23special 26:15specialists 26:18specific 12:25
15:19,21,2528:22
speed 18:5 20:1SR-60 7:8 8:2
14:16,20 15:8SR9/I-95 3:17SS 32:1St 7:7staff 28:20,24
29:2,7standards 17:20
23:7start 16:19state 1:12 2:25
5:4,22 6:2014:17 27:1129:8 32:1,7
stated 5:17statement 27:22
27:23 28:929:4,21,21
statements 5:127:14 30:20,2131:1
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 40
status 5:12stays 30:14stenographica...
32:8step 8:16storage 24:13stormwater
23:16,17Strategic 14:17
16:21Strategy 16:22Street 7:14 9:16
10:22streets 4:1strives 21:21studies 1:1,2 2:5
3:17 27:4 31:731:15
study 1:19,214:7,13,21 5:145:18 6:1,11,137:4,10,18 9:1911:13 17:1,4,618:2 19:1125:3 27:13
study's 18:22sub-lateral
21:22submitting 28:3suburban 20:1suitable 20:2sum 16:4summarizes
24:1summed 16:3Support 17:13Sure 30:1surrounding
24:8SW 3:17,23,25
6:10,12,147:13,13,14,159:11,16 10:2110:22,23,2311:16,17,1815:8 17:7,1017:15 18:14,15
18:15,16,1720:11,11,16,1720:20,24,2521:4,9,11,1121:20,24,2522:4,7
System 8:2214:17 16:2219:12
TT-intersection
11:17table 28:2take-off 11:21taken 32:13takeoffs 11:25Tallahassee 5:7tanks 24:13team 4:17teams 2:23technical 5:23techniques
22:23ten 28:4 31:2terms 12:4,22,24
13:6,17 18:2523:23
Thank 2:2 3:1128:7 29:1931:16,16
things 30:17third 4:24three 4:14 6:1
9:17 11:1 13:115:25 18:919:13 23:18,1925:6 28:17
tied 16:7time 2:24 7:24
8:7 12:11,2113:11 28:8
Title 5:5tonight 2:14 3:1
3:7 4:12 23:626:18 27:7,18
tonight's 4:14total 16:4 20:14
21:14Town 7:1tracts 10:13traffic 11:12
12:19 14:14,1616:24 17:2318:18,19,23,2419:3,5,9 22:1322:22,24 23:1024:20
transcript 27:2431:5
transcription32:9
transition 21:2,522:3,5
transportation2:4,8 3:14 5:65:8,14,16,256:7,18,19,206:23 8:2119:12 25:1826:1 30:23
travel 8:2 15:717:18 20:1221:12
treated 26:2trips 7:22 8:4truck 8:6 17:21
17:23trucks 8:6 15:7true 32:9try 30:16TSM&O 8:22
19:13,16turned 29:6turns 15:1Twenty 25:10two 3:7,24 7:7
8:23 9:1 10:1312:18 19:2520:8 24:2330:14
two-lane 19:525:4
type 23:15,2525:25
typical 19:20,2120:1,2,5,1121:3,4,11,2121:23 23:125:5
Uunavoidable
25:17understand 30:2undeveloped
24:7undivided 18:3unfunded 27:1UNIDENTIFI...
29:14,18,2430:2,6,11
Uniform 25:2225:24 26:3
unique 18:11unsatisfied
26:10Update 17:24uplands 12:16
14:6urban 19:24
21:3use 20:19uses 17:9,14utilize 4:12utilizing 22:11
Vvalue 26:7VANESSA 32:5
32:19varies 18:6various 19:23
27:15vehicle 22:24vehicles 15:8vehicular 18:20verbatim 27:23
31:4Vero 1:13 27:12VI 5:5viable 13:2vicinity 21:9
22:6 24:12view 4:16views 28:10vision 8:13volumes 18:21
18:23 19:5
Wwall 11:11,14Wallace 1:18
2:14 30:22want 29:20wants 30:18waste 24:13way 9:10,12
10:17,22,2411:23 16:2018:12 20:4,720:14,18 21:14
we'll 3:5 28:2029:5 30:19
we're 3:6We've 3:4website 27:13
29:17,19 31:13weight 28:3welcome 2:4
3:14 27:18west 2:10 3:17
3:22 6:10,127:12 11:620:23,24 21:2421:24 22:327:9 30:24
westbound 15:4wet 23:19wetland 9:13wetlands 10:17
12:17 14:10,11Wide 9:3widened 19:6widening 1:2,4
1:21 2:10 3:163:23,24 6:137:19 17:1,3,617:17 25:3,4
width 18:5wildlife 24:5
(800) 336-0050WWW.ATLANTICREPORTING.COM
Page 41
wish 27:25 29:1wishes 27:7wishing 5:4word 26:15workplace 8:14
17:8,16works 6:22Workshop 12:7worst 13:4writing 4:18 5:2
28:1written 27:14,18
28:3,9 30:2131:1,6
www.oslopde....27:13
X
Yyear 16:22,23
18:24 30:13years 18:21 30:4
30:5,7,14Young 1:17 2:2
2:6 28:8 29:1729:20 30:1,5,730:13
Z
00.62 18:15,16
20:16
11 9:20 10:25
13:3,3,8,15,1813:24 14:5,614:18,23 15:215:10,12,18,2216:6,7 18:1320:8,10,1021:10,17 22:1625:2 29:14,18
12-foot 18:420:3,5,1221:12
1200 20:2421:24
130 18:61320 7:12 23:1213th 10:2216 1:816.3 25:15173 20:4,15,1718 8:25190 20:6 21:151970 25:23
22 9:24 10:25
11:5 13:22,2414:7,13,2515:1,12,14,2015:21 16:7,718:14 20:8,1621:10 29:2430:2,6,11
2.369 1:120 16:62014 8:25 27:172015 1:8 6:222016 16:18
26:24 32:172020 18:212020/2021 16:222024/2025 16:232025 16:24 30:6
30:152026 16:25
30:152030 18:212040 18:21,24
19:521.9 9:2322 16:824.0 10:324.6 10:72400 7:1225 20:212640 23:1228th 16:13
33 10:4 11:5,8
13:21,25 14:814:22 15:3,1415:15,17,2316:6,10 18:1621:1 23:7,825:7,8
3.24 18:730-foot 20:13
21:13 23:231.3 15:133200 7:11,1132966 1:13
27:1233 3:833.6 15:1533309 27:10
30:2534 16:93400 27:9 30:24
44 1:17,18 2:7,15
5:6 13:3,4,914:19 15:5,2416:9 27:9
4.73 14:11413048-2-22-01
1:3413048-22-01
3:1943 8:8431521-1-22-01
1:3 3:2045-mile 21:34th 32:17
55 15:195-foot 20:13
21:135.86 25:145:30 1:855 18:5 20:158 1:258th 2:10 3:17
3:25 6:10,1417:7 18:1620:25 21:4,9
21:25 22:4,759.350 14:75th 7:14 9:15
66 15:196:39 31:14,1860 18:6606 3:23606/Oslo 3:22
6:96155 1:13 27:1266th 18:15,16
20:17,20,2421:20,24
69.172 14:7
77-foot 20:12
21:1274th 17:10,15
18:14,14 20:1120:16 21:11
76.438 14:8772 24:17
880 11:1482nd 3:23 6:12
7:13,13,159:11 10:1811:16,17,1815:8 20:1021:10
86th 9:11 10:2010:23
8886-458-A 1:43:20
99.0 10:69.4 9:229.6 10:290th 10:23