helmand basin integrated irrigation and power …

116
HELMAND BASIN INTEGRATED IRRIGATION AND POWER DEVELOPMENT Water and Power Authority Republic of Afghanistan

Upload: others

Post on 03-Feb-2022

4 views

Category:

Documents


0 download

TRANSCRIPT

HELMAND BASIN

INTEGRATED IRRIGATION AND POWER DEVELOPMENT

Water and Power Authority

Republic of Afghanistan

HELMAND BASIN

INTEGRATED IRRIGATION AND POWER DEVELOPMENT

Water and Power Authority

Republic of Afghanistan

EstabNshed1989

AFGHANISTAN CENTRE AT KABUL UN VERSITY

NAM °I

November 1975

Kabul

- i -

Table of Contents

Chapter 1 Introduction

Chapter 2 Hclmand River Basin

2.1 General 2 - 1

2.2 Helmand river 2 - 1

2.3 Helmand river basin 2 - 3

Chapter 3 Economic Conditions and Present stageof Development

3.1 General 3 1

3.2 Present stage of Agriculture in theHelmand valley 3 - 1

3.3 Crop pattern and cultural practices 3 - 2

3.4 Crop yields 3 - 3

3.5 Present stage of development 3 - 4

Chapter 4 Hydrology

4.1 Climate 4 - 1

4.2 River Runoff 4 - 2

4.3 Flood flows 4 - 4

4.4 Silt load 4 - 5

Page

1 - 1

Chapter 5 Land Potential, cropping patternand irrigation requirements

5.1 General

5.2 Soils

5.3 Land potential

5.4 Cropping pattern

5.5 Irrigation requirements of crops

5 - 1

5 - 2

5-6

5 -7

5 - 10

Chapter 6 Proposals for development Page

6.1 Irrigation 6 - 1

6.2 Power 6 - 3

Chapter 7 Kamal Khan Flood Diversion Dam andrelated works

7.1 General 7 - 1

7.2 Kamal Khan Dam 7 - 3

7.3 Qala Afzal Dam 7 - 4

7.4 Control Weir 7 - 4

Chapter S Upper Kajakai Dam at Olumbagh

8.1 General 8 - 1

8.2 Location S - i

8.3 Hydrology 8 - i

8,4 Design flood S - 2

8.5 Area -capacity of the proposedreservoir 8 - 2

8.6 Layout S - 3

8.7 Salient features 8 - 5

Chapter 9 Irrigation Works

9.1 Upper Helmand valley 9 - 1

9.2 Lower Helmand valley 9 - 2

9.3 Khanneshin diversion dam 9 - 3

9.4 Taghaz diversion dam 9 - 4

9.5 A low dam between Rodbar andChahar Burjak 9 - 4

9:6 Kamal Khan diversion dam 9 - 4

9.7 Khwabgah diversion dam 9 - 5

9.8 Sikhsar diversion dam 9 - 5

9.9 Lashkary canal 9 - 5

-iii- page

Chapter 10 Command area Development : 10 - 1

Chapter 11 Power Potential 11 - 1

Chapter 12 Estimate of Cost 12 - 1

Chapter 13 Phased Programme of Implementation 13 - 1

Chapter 14 Economic Evaluation 14 - 1

Chapter 15 Conclusions and Recommendations 15 - 1

- iv -

Tables

Chapter 4

Table - 4- 1/Average monthly & annual precipitation in mm

Table - 4 -2 Monthly average relative humidity -Max. &Min.in p rcent

Tabke - 4 -3 Monthly average max. & min. temperature in Deg.0

Table - 4 44 Monthly & annual velocity & max. velocityof wind in km /day

Table - 4 -5 Average monthly evaporation in the'Helmand valley

Chapter 5

Table 5 -

Table 5 -

Table 5 -

Table 5 -

Table 5 -

Table 5 -

Chapter 1

Table 11

Table 11

Chapter 1

Table 12

Chapter 13

Table 31

1 Land Potential of the Helmand basin

2 Irrigation Potential of the Helmand Basin

3 Monthly Crop Consumptive use Requirements

4 Irrigation Water Requirements - Crop Intensity 140%

5 Irrigation water requirements - crop intensity 120%

6 Monthly total water requirements for the rea

proposed for irrigation.

1.

- 1 Upper Kajakai Dam(Olumbagh) - Typical reservoir

Operation Table for the water year 1954 - 1955

- 2 Upper Kajakai Dam (Olumbagh dam) Typical reservoir

operation table for the water year 1961 - 1962

2.

- i Abstract of Cost

- 1 Phasing of Construction and Expenditure.

-v-

Chapter 14

Table 14 - 1 Present Crop Production and Gross Revenue

Table 14 - 2 Present Production Costs

Table 14 - 3 Cropped area after completion of the Project

Table 14 - 4 Future Crop Production and Gross Revenue

Table 14 - 5 Future Production Costs

Table 14 - 6 Upper Helmand valley -Existing irrigated area requiring im-

provements-Present crop production & Gross revenue

Table 14 - 7 Upper Helmand valley - Existing irrigated area re-

quiring improvements - Present production costs

Table 14 - 8 Upper Helmand valley - Existing irrigated area re-

quiring improvements - Future Crop Production and

Gross Revenue

j

able 14 - 9 Upper Helmand valley - Existing Irrigated area

requiring improvements - Future Production Costs

Table 14 - 10 Internal rate of return.

-vi-

Figures

Fig. 5 - 1 Helmand river basin - Irrigable areas

It

it

tr

It

It

t1

tt

"

t'

I!

7 - 1 Kamal Khan flood diversion dam and related works

8 - 1 Water spread area map for the proposed dam sites atOlumbagh

8 - 2 Area capacity curves for proposed reservoir onHelmand at Olumbagh

8 : 3 Topographic map of the proposed dam site atOlumbagh

8 - 4 Longitudinal section and typical cross section of rock -fillDam

8 - 5 Logitudinal section along proposed spillway channel

8 - 6 Longitudinal section along diversion tunnels

9 - i Helmand river basin - Khanneshin Diversion Dam - Right BankCanal

9 - 2 Helmand river basin - Taghaz Diversion Dam - Left BankCanal

9 - 3 Helmand river basin - Kamal Khan Diversion Dam - Right BankCanal

9 - 4 Helmand river basin - Rodbar Diversion Dam - Left Bank CanalKamal Khan Diversion Dam - Left Bank Canal

9 - 5 Helmand river basin - Khwabgah and Sikhsar Diversion Damsand canals

" 11 - i Transmission Lines connecting Kajakai to Kandahar -Kabul-Herat.

1a1

D

CHAPTER 1

INTRODUCTION

The Helmand basin is the largest of the river basins in

Afghanistan. It is said to have been flourishing - particularly

the lower basin - in historic times, with agriculture. Even today

one could see the traces of innumerable irrigation canals in the

region, reminiding of the heritage of the past. In the early fiftees

of the century, the Kajaki dam on the Helmand river and the Arghandab

dam on Arghandab ricer were constructed and large areas of land in

the Arghandab valley and the upper Helmand valley were brought under

irrigated farming. With the result, a beginning has been made for

the planned development of irrigated agriculture in the Helmand

valley.

It has since been 'recognised that the lower Helmand valley should

also be developed sò that its economy could catch up with the rest of

the region. Investigations and studies were therefore made in the

recent past for the purpose. These studies indicated that for the

development of the lower Helmand valley, large areas are to be reclaimed

first by diverting the flood flows into Gaudi- Zirreh, the largest

natural depression in the proximity.

The earlier studies and the available data are made use of

for prepartrigs this report which - outlines the proposals for theirrigation

and power development of the Helmand valley. The salient proposals are:

i. to step up the hydro power generation at Kajakai and

transmit the generated power to potential load

l' -2

centres in the valley and regions around

in a period of about five years from the

commencement of the plan to meet the growing

domestic and industrial needs of the region;

ii. reclaim large areas in the lower Helmand valley by

diverting the flood waters of the Helmand river at

Kamal Khan into Gaudi- Zirreh;

iii. undertake the construction of a number of irrigation diversion

dams and a network of irrigation and drainage systems along the

entire length of the river commencing from Garmab for bringing

under irrigated agriculture about 33,000 hectares of land in the

upper Helmand valley and about 200,000 hectares in the lower

Helmand valley;

iv. improve the irrigation and drainage facilities to about 30,000

hectares out of the 77,000 hectares irrigated area in the upper

Helmand valley;

v. construct a storage reservoir upstream of Kajakal reservoir

on Helmand river, another on the Arghandab river and possibly

a third on the Musa gala river to optimise the various facailities

such as irrigation, power and flood moderation;

vi. generate power at the upper Kajakai dam and transmit the same

to Kajakai system to meet the additional power needs etc.

The entire development as envisaged above, is programmed to be

substantially corm feted in about ten years.

--.,...

2 -1

3

CHAPTER 2

HEIMAND RIVER BASIN

2.1 Afghanistan is a mountainous country situated in the central

part of Asian main land. Mountain ranges run across the country

from North east to South west sloping steeply towards north and then

to south and west. These are a continuation of the Hindu Kush range

of mountains. The Helmand river basin, lies on the northern side of

the dividing mountain mass. Vast tracts of barren land stretch over

15,000 s lams at elevation ranging from 700 to 800 meters in the

south and south west of the country. The Helmand and Bakwa deserts

Hlin the south west and the Registan towards the south form part of

these barren lands. There are large land- locked lakes formed in

the south western parts of the country.

2.2 Helmand river

The Helmand river rises in the Kuh- i.Baba ranges of hills

west of Kabul at an elevation of about 5000 m. It flows west forr-----.some distance and runs south -west in a deep valley. It changes

its direction to the west again skirting Kuh- i- Waris. From Sharan

it runs south -west upto Girishk. The river is a mountain stream

flowing thro deep valleys till upto a few miles upstream of Girishk.

Most of the river yields are from the melting snow in the upper

reaches._, The Kajakai dam constructed across Helmand river in upper

reach issues regulated releases for irrigation lower down. Tributary

Musa Qala joins Helmand river between Kajakai and Girishk.

2-2

On emerging from the hills, the river winds its course thro a

relatively flat terrain where its waters are used for irrigation on

a large scale. The Bogra diversion dam at Girishk diverts water for

irrigation thro a right bank canal to the Marja, Nad -i -Ali and

Shamalan areas. The river after flowing for further distance dcps

to an elevation of about 750 meters at Qala Bist where the Arghandab

river joins the Helmand.

Arghandab river is a major tributary of Helmand river. It is

itself a river of considerable importance with a number of tributaries.

It takes its origin north west of Ghazni and flaws down in a south-

westerly direction passing a few kilometers from Kandahar city. Tarnak,

Atghast an and,Dóri_BusLare its three main tributaries. These tributaries

are seasonal. There is a dam constructed across Arghandab river and

the waters stored there are being utilised for irrigating large areas

of land in the Arghandab valley.

After the confluence of Arghandab river, the Helmand flows thro

the desert area Dasht i - Margo, passing by the places Darweshan, Khawaja

Ali, Chahar Burjak and Kemal Khan. There is a diversion dam at Darweshan

which diverts the regulated releases from Kajakai reservoir for irrigating

the narrow strip along the valley on the left. At Kamal Khan the river

takes a turn to the north and flows for about 50 kilometers before it

reaches the Iran - Afghanistan border. At the border the river branches

off intó a number of channels all of which finally drain into the

Hamuns.

Z-3

At Khwabgah, the Rud-i-Seistan branches away towards the left.

The Nad-i-Ali branch on trie right leads into Shela Charkh which was

originally a drainage channel and then finally into Hamun- i- Puzak.

The Helmand river after flowing for nearly 300 kilometers between

Qala Bist joins the land -locked lakes ( Hamuns).

The area of waterspread and volume of these Hamuns fluctuate

depending -on the flood flows drained into them by the rivers joining

them, the most important of which are the Helmand, the Khash and the

Farah. Hamun -i Puzak, Hamun -i- Sabari and Hamun-i-Kuh-ï Khawaja

are separated from each other by low saddle and hence flood flows will

be surplusing from one to tie other. When the water levels in all

these lakes swell, the excess flows discharge into Gaudi- Zirreh thro

Sari- i-Shellah, a drainage course leading to Gaudi-Zirreh.

2.3 Helmand river basin

The river above Kajakai is hilly and cost of the yields are

contributed from this catchment. There are isolated patches along

the river margins being cultivated in this stretch. Below Kajakai,

the river enters into an alluvial flood plain, bordering the river.

The area on the left between the Helmand river and the Arghandab

river is extensive with alluvial and fertile lands. This is known as

Seraj area. The alluvial strip on the right between Girishk art

Lashkargati along the river is irrigated by the canal taking off from

the Bogra diversion dam. The same canal also irrigates the lower

areas known as Shamalan area and the desert terrace land known as

2-4

Nad-i-Ali and Marja area covering nearly 30,000 hectares. There

e

are large extents of cultivable land in this area without irriga-

tion facilities.

Below the confluence of Arghandab, there is a narrow strip of ,

land extending i to 3 kilometers width on either side of the river

which hold potential arable lands. Most of these lands are under

irrigated agriculture for over a number of years, subject to availa-

bility of water diverted from the river by means of temporary impro-

vised diversion structures which are washed away season after season.

There are a number of open head river channels which do not carry

assured supplies. Irrigated agriculture therefore suffers mostly

for want of water during the critical period of crop growth.

The alluvial strip bordering the river fans out beyond Kamal

Khan forming the expansive plains covering Qala Fateh, Zaranj, Kang,

Kirki, Sherabad and Chakhansur areas. Parts of Chakhansur area

along the river are cultivated at present thro a system of existing

open head canals with no regulating arrangements. This area is

said to have been flourishing with intensive cultivation and habi-

tation in historic times. It is this area that holds out a

promise of extensive development of irrigation and agriculture, if

suitable ameliorative measures are taken.

3 -1

CHAPTER 3

ECONOMIC CONDITIONS AND PRESENTSTAGE OF DEVELOPPENT

3.1 General

Afghanistan is essentially an agricultural country where about

80% of the population have agriculture as their main occupation. Agri-

culture represents nearly 50% of the country's gross national product.

Industrial development of the country is still in its early stages

and employment in the industrial sector is only 1% of the working

population.

A complete census of the country's population has not been

taken so far. Several assessments made indicate that the population

in 70 -71 was around 16 million. Census covering about 15,000 villages

in 1968.69 indicated that the annual rate of population growth is of

the order of 24 while the annual increase of agricultural production

is about 1.3 %. There is therefore need to step up agricultural

production to keep pace with the population growth and for improving

the living standards of the people.

The diet of the people is oriented towards wheat whose per

capita consumption is about 160 kgs per year. In some of the recent

°'... a»i

years nearly 10% of the total wheat requirement had to be imported.

3.2 Present state of agriculture in the Helmand valley

Farming is done in the valley both by traditional and modern

methods. The modern.methods include preparing the land by mechanical

3 -2

means, use of fertilizers, insecticides ,, pesticides , land levelling

etc. Timely irrigation supplies are assured and regulated. The

traditional methods comprise of water supplies from river by tempo-

rary diversions thro open head channels, with no assured supplies

during the cropping period. The use of farm inputs is also very,

much limited.

Where the supplies are thro open head river channels there is

over-irrigation in the head reaches and under irrigation in the lower

reaches. Excessive irrigation in some area has created drainage

and salinity problems. The irrigation channels which are owned and

maintained by the beneficiaries themselves are generally in dis-repair.

As they do not have adequate carrying capacity/ they breach often

interrupting timely supplies.

The valley particularly the lower basin was said to be

flourishing with cultivation. The farmers of the area are therefore

traditionally well experienced in agricultural practices and are

aware of the benefits that accrue from irrigated agriculture, if

properly done. What is therefore necessary is the creation of ade-

quate irrigation facilities and infrastructural facilities for

agricultural development.

Farms are generally of the size of 2 to 7 heçtáres. Lack of

transport facilities in the lower basin stand in the way of growing

some of the cash crops.

3.3 Crop pattern and cultural practices

The agriculture economy is mainly built around the growing

of wheat. Other crops such as cereal grains, melons, vegetables,

tree fruits, grapes etc., constitute a small percentage. The existing

3 -3

cropping pattern is broadly as follows:

v b?

Wheat

Barley

73.0

10.0 %

Cotton 0.3 %

Corn '0.1 %

Sorghum 7.5 to

Melons 7.0 %

Mung Beans 0.1 lo

Other miscellaneous crops 2.0 `o

75-o

If sufficient water is available the more saline lands could

receive adequate water for leaching prior to land preparation and

seeding and drain the salts. In small isolated parts of the area,

lift irrigation is also practised by diesel driven pumps. Most

of the crops are sown broad -cast.

Wheat and barley are the principal crops sown from September

to January and harvested in April or early May. They generally

receive about four waterings subject to the availability of water

but more often they receive less than four irrigations. They are

thrashed in the traditional manner by oxen. Sumner crops are planted

in May and they take about four months to mature.

3.4 Crop yields

Present crop yields in the upper Helmand project areas and

in the non project areas of the lower basin are given below. The figures

given represent average yields for all land classifications :

3-4

Present crop yields kgs /hectare

Crop Upper Helmandproject areas

Non project areasZaranj Kang Chakhansur Chahar -Burjak

Wheat 2520 r'835 518 518 1115

Barley 2040 795 597 716 716

Cotton 960 795 597 597

Sorghum - 995 955 955 1035

Corn 2240 `995

Melons 11500 6360 3180 2390 5170

Mung Beans 800 636 398 398 795

Vegetables 12300 5170

Tree fruits 6750 2980

Grapes 6750 2980

The yields of the crops are very low in the non - project areas.

These low yields are as a result of a combination of various factors

such as inadequate supplies of irrigation water, soil conditions and

poor agricultural practices.

',o,x,3.5. Present stage of development

-Ï 000.4'., 3.5.1 Irrigation : Kajakai dam is constructed across theik çii

river Helmand in a narrow and steep limestone gorge. It is a rock -

fill dam 270 meters long and 97.5 meters high. The gross storage

capacity-of the reservoir is 1710 million cubic meters (1.39 m.ac -ft)

below the level of the existing uncontrolled spillway. The work

on the installation of gates over the spillway is being taken up

3-541

to raise the full reservoir level from elevation 1033.5 to elevation

1015 and thus increase the gross storage capacity to 2720 million

cubic meters. The regulated releases from the dam are being diverted

to Bogra and Darweshan where there are diversion structures across

the river. About 71,000 hectares of land are being irrigated presently

with a network of irrigation canals in the Seraj, Nad -i -Ali, Shamalan

and Darweshan areas. In addition about 6,000 hectares are being

irrigated under inundation canals. In the basin below Darweshan inclu-

ding the Chakhansur area, about 55,000 hectares of land is under

irrigation. Out of these 55,000 hectares of land only about 10,000

hectares get assured supplies for want of permanent diversion works

and intakes at the canal heads with suitable regulating arrangements.

40 The Arghandab dam on river Arghandab was constructed in 1952.CI

00" The earth dam is S40 meters long and 61 meters high with a storage

capacity of 415 million cubic meters. It irrigateslarge area of

land in the Arghandab valley.

3,5.2 Power: The Kajakai dam was constructed with the purpose

of creating irrigation and power potential. A power outlet was in-

corporated in the dam layout and the installation of power plant is

taken up recently after nearly twenty years of completion of the dam.

Two units of 16.51,is each are now being installed in the power

house under construction.

The çnly other hydro power installation in the basin is on

the Bogra canal with two units of 1.2 M.Ws each operating under a

head of about a meters. These units supply power to the nearby

towns of Girishk and Lashkargah.

R,,

3 -6

Power supply to the other areas in the Helmand valley such

as Kandahar, Zaranj etc., at present is mainly by means of diesel

installations.

It is thus seen that the electric power now available is not

adequate to meet even a fraction of domestic needs in the valley and

other places like Kandahar, Herat, Ghazni, Kabul, etc., which have

vast ;aotentialities for rapid domestic and industrial growth, if

only electric power could be supplied in the next four or five

years.

/.

4-1

CHAPTER 4

riiDR37CGY

4.1 Climate

13

The Helmand Arghandab valley lies between elevations varying

from_1,000 meters to 500 meters. The climate of the basin is

generally-hot and arid, particularly at the lower elevations. In the up --

3er valleys yavdrage daily maximum and minimum temperatures over

a period of record are 32 °C and 12 °C respectively. In the lower

basin a maximum of 52 °C is reported to have been recorded. Winters

in the upper valley are characterised with minimum temperatures

fallitg to -12 °C. The winters in the lower valley are however mild,

though occasionally minimum temperatures below freezing point are

reported to have been recorded. The skies are clear with bright.

sunshine throughout the year, cloudy days being an exception.

Another characteristic of the lower basin is the occurance of sand

and dust storms at any time round the year. These are mostly local

and do not last long. But the regional dust storms generally have

their origin in the south western part of the basin. The winds in

the area reach velocities as high as 120 to 160 kus per hour', forming

dense clouds of sand and dust. These storms render the visibility

poor. They last sometimes for days and the dust continues to fill

the atmosphere:,,Sor days even after the storms subside.

The precipitation in the higher elevations of the upper valley

occurs during the months of November to May in the form of snow and

rain and is the main contributing factor for the valley runoff.

4 -2 1 i

In the lower basin most of the rainfall occurs as small daily amounts

of few milli -meters. Rarely heavy rainstorms cause floods in the

lower bain causing damages to the roads and canal structures. About

9D% of the total rainfall occurs during the months of November to

April and 65% precipitation takes place in December, January,_ February

and March. The total annual precipitation in the area around

Lashkargah is only 98.9 mm and in the Chakhansur area X2.7 nm. Hence

most of the water requirements for cultivation are to be met from the

river flaws by means of irrigation works. Average precipitation

recorded at different stations is given in Table 4 - 1.

The relative humidity in the lower valley is low comparatively

to the relative humidity in the upper valley. Data in respect of

a few stations is given in Table 4 - 2.

Meteorological data is being collected at Kandahar, Lashkargah,

etc. The average temperatures and wind velocities recorded at some

of the stations are given in Tables 4 - 3 and 4 - 4. Evaporation

in the central and lower Helmand valley is higher than in the upper

region. The average monthly evaporation in the Helmand valley recorded

at a few stations is given in Table 4 5.

4.2 Rivr runoff

Systematic collection of runoff data in the basin at Dehraout

(upstream of Kajakai reservoir), Kajakai and downstream of Kajakai,

Darweshan, Chahar Burjak and on the tributaries, Musa Qala and Arghandab

commenced from 1946. T. -a uto the conflue

Musa Qala and. river Arhandab is the contributing source for

the total annual runoff of the fiver. The yields of the Helmand

4 -3

15

river at llehraout (upstream of Kajakai) and at Kajakai; and the

yields of the tributaries, river Musa Qala and river Arghandab are

therefore useful for planning the resources development of the

basin.

The average annual runoff of the Helmand river at Kajakai is

6,000 million cubic meters. The 75% dependability flow of the river

for which the irrigation development is generally planned is about

y-/ 4,690 million cubic meters. The 90% dependable flow of the river

9a 'is - ifowever 4,140 m. cubic meters. The planning of the power insta-

llations are done for a 90% dependability.

The 75% dependable yield of the Arghandab river at Oala Bist,

jus upstream of the confluence with the Helmand river is'266 million

cubic meters. Similarly the 75% dependable yield of Musa Qala river

6 {- is 96 million cubic meters. The 75% dependable yield of the Helmand

river at Chahar Burjak after meeting the upstream irrigation require-

ments is 3,580 million cubic meters. The flows are mainly during

the months of March to June. A general comparison of the flows at.00111.011S

Kajakai and Chahar Burjak indicates that the yields from the drainage

area downstream of the point of confluence with Arghandab river are

very erratic and constitute a small portion of the total yields at

Kajakai in years of average and higher dependability. A comparison

of combined total of the flows recorded at Kajakai, Musa Qala and

Qala Bist.with the flows at Chahar Burjak, though does not give a

conclusive-idea of the upstream abstractions for the existing

irrigation for want of data on the actual inflows for the intermediate

4(/

4-4 lcatchment, it is inferred that the irrigation withdrawals upstream

of Chahar Burjak are of the order of about 1,200 million cubic meters.

When the flows of river Helmand are controlled and excessive

flood flows are diverted into Gaudi-Zirreh and larger areas of land

are brought under irrigated agriculture with regulated releases,

the lower Helmand basin particularly the Chakhansur area can be /to a

large extent, relieved of the problems of floods and developed. It

is oñly then the floods of Farah and Khash rivers flowing into the

Seistan basin, that can cause some inundation of the cultivable lands.

However the runoff from these two rivers is a small fraction of the

total runoff of all the rivers now flowing into the Seistan basin

and the submersion problems caused by these two rivers may be said

to be minimal. Even this could be obviated when the waters of these

rivers are also harnessed in the near future.

4.3 Flood flows

The spillway of the Kajakai reservoir is designed for a 1000

year flood of 12.,5ß cubic meters /sec (4,40,000 cfs) which is based

on flood frequency studies. The flood flows at Chahar Burjak are

reported by various authorities and the information relates to periods

dating back to 1885. The Perso-Afghan Commission estimated that the

great flood of 188 had a peak of 18900 cubic meters /sed based on

a number of slope rea calculations using flood marks. It is also

reported that a flood of equal magnitude occured in 1830. But

factual evidence of the severity of such a flood had not been

mentioned. Data on floods collected during the investigations of

Kajakai dam shows-that a flood of about 3520 to 4250 cubic meters

I13tet

'''`._._---..-.-. . a._

31.....-.t3 1-

a,4 -5 .

l

per second occured in the Girishk-Shamalan area in the year 1931

and was considered to be the maximum flood within the memory of any

living man. Another flood with a peak flow estimated at 3970

cubic meter per second has been recorded in 1. The Delta

Commission report estimated the same at Chahar Burjak as 4100 m3 /sec.

Thus the maximum flood experienced at Chahar Burjak is 4100 m3 /sec fi ?

other than the floods of 1830 and 1885 about which a mention is

made earlier. The available recorded flood flaw data for 22 years

excluding that of 1885 whensubjected to frequency analysis indicates

that a 1 in 1000 year flood may be of the order of 11500 /per second.

4.4 Silt load It? v

The U. S. Geological Service conducted a study in 1968 on the

effect of sedimentation in the Kajakai reservoir. It indicates that

the rate of sedimentation average19. 3._m llion- aubi.,am tern per year

in the period from 1953 to 1968, the total accumulation being 145

million cubic meters. It has also been indicated that a further

r,) /. accumulation of 236 million cubic meters could be expected in a period

of 40 to 45 years allowing ,for the compaction of the silt during

this period. The total sediment deposition in the reservoir in a pP ^r1

of 60 years will therefore be 381 million cubic meters. Construction

of storage reservoir upstream of Kajakai would reduce silt deposition

in Kajakai reservoir.

Table

4-1

Average monthly & annual precipitationin mm

Station

Jan.

Feb.

March

April

July

Aug.

Sep.

Oct

Nov.

Dec

Kandahar

45.5

32.5

34.1

16.8

_114zjune

6.3

0.1

2.0

00

0.1

7.0

22.0

Lashkargah

22.7

14.4

23.4

13.7

2.0

01.6

00

0.6

4.8

15.7

f....

....''

Qala Kang/

18.3

3.6

12.7

5.6

0.7

00.8

00

0.5

2.4

8.f

Zaranj

Farah

24.3

29.6

19.3

8.7

2.6

00

00.1

04.0

8.8

Annual

166.4

2242

52.7

Lr`

a) .-I M O.q 0 CCV Lt-- M LO C12 flO r-+O .-+ t

r1 (,1 M O` ...I. I" CO NO L"--t0Z tA r-i igU. r1 C' r- Ctit t0 riú ÑQ e-9 C2

C2 O 0.2 Mr-a u1 r-i r-1 t1 C2 r- I

I-4 ONt['l111^Cs.-1 CM 4-1 i r-t

HI. Q ON CT tr1 ti tO O or' M r-1 -4" Cs2 ul

Ce C` -.t -7 r-C r-+ON r-

lx) :8"f-1N >n `,2g ir C1 LO

,00. 2 v. í-I 02W r'i O 1'4

CrNO LO *4 C - ctii O`

CfN'

-1

Wir1

W" C2 0 Q\CV O r-1

C0 MM Q`O r-t t0

ri Z

a á $.1

tv ,,, ,Ur

ter

Table 4-3

,Monthly average maximwn and minimum temperature in

I3ég.0

Feb.

March

July

-bet._

Station

Jan.

1101

June

Aug

Sep.

Nov.

Dec.

Kandahar

Max:

12.6

15.9

22.1

.10:11

27.8

33.9

35.4

39.6

34.8

34.0

28.6

21.6

15.5

Min:

-0.3

2.3

6.2

11.5

15.3

18.5

21T3

18.8

12.7

6.7

2.1

-0.4

Lashkargah

Max:

14.4

17.9

24.0

29.6

35.6

40.7

41.8

40.0

35.7

30.1

22.3

16.2

Min:

0.6

3.2

8.8

13.3

17.5

21.4

23

20.6

14.7

8.6

3.5

0.9

Qala Kang

Max:

14/1

18.7

23.1

28.9

23.8

38.8

4ó,,

38.4

34.3

28.8

21.1

15.6

Min:

1.8

3.2

.7.8

12.9

17.2

21.2

2.4.

17.1

10.2

4.6

2.2

Zaranj

Max:

13.0

19.8

28.5

32.8

36.4

43.1

42.8

42.1

36.2

31.4

23.8

18.4

Min:

-0.9

3.1

9.2

15.2

20.2

25.5

Zane..

24.3

30.8

11.9

4.9

0.8

Farah

Max:

16.0

19.0

24.9

30.0

35.2

38..8

41.4

40.3

$5.8

31.2

24.9

17.8

Min:

0.3

1.9

7.5

11.9

16.6

20.8

278

21.0

14.6

9.7.

4.1

1.0

ii

H-0

4.4-

j4

Table 4 - 4

Monthly and annual average velocity and maximum velocity

f wind in km /day

Jan.

Feb.

i-.7ch

April

M.

June

Jul'

A.

wed.

Oct.

Nov.

'éc.

Añnúal

Ave.

.189

214

218

211

218

222

182

165

140

142

171

175

187

Max.

521

728

555

739

571

720

417

875

296

571

522

796

608

Avt

174

208

228

235

340

436

463

507

408

286

211

184

307

690

636

951

734

914

850

1179'

$88

845

795

797

662

828

P7g1

- .r

-f e

o1F

tv,r

Average monthly evaporation in the Helmandvalley

4 '

(Pan evaporation in mn

Table 4 -5

¡Rala

Dame-

Chah-

Mar j a

Lashkar - Nad -i -Ali Ka j akai

Kandahar

Arghandab

Jai Surkh

Kang_

shah

i -Anjir

gah

(upper)

Nawar

January

February

124

124

51 86

60 18

89

130

98 120

78 73

61 82

37 51

98

nJc

6446

March

204

153

138

172

185

132

114

95

132

131

April

315

243

242

255

252

256

190

154

155

296

May

451

316

338

414

350

292

270

226

185

`372

June

622

414

474

444

413

355

351

253

222

503

July&

Aug

usta

702

74

6.4

32 386

40 454

4Q6,

360

36.4

..32

0381 3f

259.

251

a6 *¡

.

Sept

..

328

286

356

260

233

235

183

164

518

Oct

326

215

214

230

190

134

214

112

125

113

Nova

205

101

149

166

118

75

130

64

90

122

Dec.

133

52

71

106

90

86

70

38

75

98

Total mit

13306

2821

2994

3145

2772

2298

2391

1752

1789

3549

5 -1

CHAPTER

LAND POTENTIAL, CROPPING PATTERN AND IRRIGATION RE_-

QUIRENENTS

5.1 General

The Helmand basin below Kajakai and the confluence of Musa Qala

and Arghaidab_ rivers cuts across an arid and semi -desert zone. There are

high arid and semi -arid table lands with hills interspersed here and

there, on either side of the Helmand valley downstream of Kajakai upto

Chahar Burjak.

The general elevation of the desert plains at the beginning of the

lower Helmand basin ranges from 600 meters to 735.meters. The cultivable

land in the upper reaches pf the lower Helmand basin is also confined

between the river margins and the steep slopes of the desert land on either

side. Down stream of Chahar Burjak, the valley fans out on both sides.

On the right side are the expansive plains of Khwabgah, Sherabad and Cha-

Khansur. It is understood that these plains were in historic times flouri-

shing with cultivation but most of them are at present left fallow. On

the left side beyond Bander lie the plains bounded by Biyaban channel in

the north and the Khushk channel in the east. In this area the general

ground level is about 520 meters and the terrain falls gradually to elevations

upto 500 meters towardsth-west, south and southeast, Thereafter the

country falls rapidly to the existing natural depression of Gaudi- Zirreh

on the south and the Hamun-i-Kuhirpmaja on the western side. These

plain lands between 520 and 500 contours which are not being cultivated

now could be brought under command of the Helmand waters.

5 -2

5.2 Soils

Soil surveys in the Helmand valley were carried out earlier by various

investigators over a period of 20 years. Their investigations cover the

areas between Kajakai and Chahar Burjak and the Chakhansur area mn the

right bank of the river. The area to the left of the river down stream

of Chahar Burjak is not covered in the earlier investigations, except for a

small strip adjoining Rud -i- Biyaban. The soil surveys to a limited extent

are also= -carried out by the Helmand Arghandab Valley Authority. Extracts

of findings based on the investigations are given in the following para-

graphs.

The soils of most of the cultivable lands in the upper valley origina-

ted from alluvial and aeolian materials. The lower basin at one time was

a large inland sea, which gradually got filled with deep deposits of manly

clays stratified with thin layers of sand. Soil materials around the Hamm

have turned onto lacustrine soils by the action of water and organic matter.

The Dasht -i -Margo lying north of the great loop of the Helmand mostly

consists of reddish desert soils over a bed of gravels intermixed with lime.

Generally gypsum beds occur a few inches below the surface. A few areas

in this vast, relatively barren desert, have accumulated a sufficiently

thick mantle of soil to afford some promise of agricultural use. The deeper

desert soils have in many places a very compact, reddish brown, sandy clay

loam subsoil which is slowly permeable. Compaction and cementation to

different degrees is found in these desert soils. Cementing agents appear

to be calcium -carbonate, silicates and in a few places iron oxides.

These soils are being irrigated with varying degrees of success.

The Marja project 11,000 hectares, Nad -i -Ali or Bogra protect 7,500 hectares

and parts of Seraj project 24,000 hectares have red desert soils on outwash

-j

plain materials and underlain at varying depth by cemented or compacted

layers, hardpans, or conglomerates.

Textures, depth and permeability vary widely. The highest proportion

are thin soils with greyish brown or weak reddish brown silt loam, loam

or fine sand loam surface soils over thin to moderately thick reddish brown

loam to sandy clay loam subsoil containing varying amounts of gravel. Lime

in soft masses is common. Some soils have thick layers of calcium carbonate

of varying degrees of hardness.

Salts are common in the gravelly desert soils, the concentrations

varying from 0.5% to 3% on the surface.. There are mainly chlorides,. sul-

phates and bicarbonates. Very few desert soils appear to be strongly

alkaline. Soluble carbonates are low. Wind erosion is another problem

in the desert plains. At certain times of the year strong winds blow

causing movement of soil particles. Vast dunes have formed due to this

action. The strongest wind effect is in the Chakhansur area.

Soil fertility is low in desert soils. Many of the sandier types and

thin, more gravelly soils are low in available phosphates. Tests repeatedly

show this to be true in the Nad -i -Ali area. Organic matter and nitrogen

are typically low in most of the desert soils and use of legumes and fer-

tilisers is essential for good yield. The more promising lands for irri-

gation development are the deep valley fill and river terrace soils lying

along the Helmand valley.

The valley fill soils represent the gradual accumulation of alluvial

sediment together with wind-laid materials at the lower extremities of the

slopes and above the more recent stream terraces. These soils become thin-

ner toward the upper slopes until they become indistinguishable from the true red.

dish desert ou#washplain- soils. In the upper reaches, the compact reddish

brown subs,,l.ls of the desert plain soils extend underneath these later,

5-4 24'

less weathered deposits. Irrigation with silt -laden waters during high

runoff has through the centuries built thick layers of silts and fine sands

over the original soils. Stratification of the thin soil layers is common

in these older irrigated sections.

In general, the valley fill soils are deep, moderately light brawn to

very pale brown silt loans and fine sandy loans with silt loam to silty

clay loam sub -soils. Soil structure varies depending on the manner ix4..hich the

doilslwore aä down: 1 and developed. Where stratified with thin lenses

of compact, massive silty clays, the permeability is low. The more uniform

profiles are more permeable and better drained. Underlying materials vary

from the red desert soils and outwash gravels to more recent alluvial gra-

vels and sands. These deep valley fill soils occur in small areas along

the west side of the Helmand between Musa Gala and Kajakai.

The more recent series of terraces and benches along the various

rivers constitute important agricultural areas. Dominantly the soils are

deep, light - coloured silt loans, loans and very fine sandy loans. Along

the Helmand considerable areas of uniformly sandy soils, sandy .loans to

loamy fine sand also occur. some of the older terraces have accumulated

several feet of silts, fine sand and clays. Old pottery shards occur

extensively under the Shamalan terrace soils at about one meter depth. Part

of this deposition is probably due to a period of heavy flood deposition,

since the shards do not continue upward through the profile. Some parts

of the terrace benches along the Helmand are heavy silty clay loans and

silty clays several feet in thickness. The stream terraces are moderately

to well drained at present and appear to be well- adopted to irrigation

development.

In the Chakhansur area the sediments are moderately calcarious and

5 -5

oC,

rich in gypsum. The organic content is generally low except around the

Hamuns and the colour of the soil is typically ligFtt brown to yellowish

brown. Soil profiles are typically uniform over considerable distances.

Textures range from clay to very fine sand, with silt loams and silty

clay loams being dominant. The silt loam surface soils are friable and

easily worked and where finer texture occurs, they are well aggregated

and relatively easy to work. Although the area is generally having probelms

of drainage, the soils of medium texture have good drainability character-

istics. Surface infiltration rates are medium to moderately slow and

deep percolation rates are good. Soils in the area are saline to varying degrees.

The eaias however-:, exhibit good soil structure and permeability characteris-

tics probably on account of gypsum being washed down from the desert soil

surrounding the area. In general the soils of Chakhansur area are inherently

fertile, easily worked and well adapted to a wide range of climatically

adapted crops. They are probably the more fertile soils found any where

along the Helmand river.

Recent alluviam along several streams is subject to inundation,

scouring and deposition during flood periods and very little has been

under cultivation for long periods. For the most part they are loamy

fine sands to loams, uniform to stratified profiles. The surface is very

irregular. Numerous old stream channels meander through the area. Wind

erosion has left much of the land in badly hummocked condition. Scouring

and re- deposition has resulted in frequent gravel and sand bars. These

areas for the most part are covered with jarru grass and salt cedar. The

land has water tables varying from a few inches to 3 -4 meters below the

surface. Salinity is generally high.

5-6

Av5.3 Land potential

Rejection of lands for irrigation on grounds of poor drainage,

salinity, alkalinity etc.,Inay leave very limited extent of land for

irrigated agriculture. With the rapid progress achieved in the field of

agricultural science and technology, measures have to be deviced to bring

as large an area as possible under irrigated agriculture by adopting

suitable ameliorative measures. It is therefore aimed at identifying areas

that o-an be commanded in different locations of the basin with the construc-

tion of various irrigation works, on the assumption that they can be brought

under cultivation. A reasonable percentagef the area so identified is

excluded to cover certain areas that are inevitably not fit for cultivation

and towards areas to be occupied by villages, roads, canals, distributary

and drainage systems and other infrastructural facilities.

In the upper Helmand basin irrigation is practised thro two systems of

canals. The project canals taking off from river diversion works and which

get their assured supplies from the storages above, come in first category.

Under the second category are included the various channels taking off

directly from the river with open heads. These cams draw their Lupplies

often by constructing temporary diversion works made of stone, brushwood,

earth etc. Such structures are of limited value in the sense that adequate

withdrawals into canals can only be maintained if the river water levels are

sufficiently high and not otherwise. The additional areas that are potent -

tially irrigable under the above two categories in the upper Helmand basin

are assessed to be 332000 ectares after taking into account the existing

irrigation of 77,00Dhectares.

In the lower basin particulars in respect of actual extents being

presently cultivated are not available, except for the lands in Chakhansur

.5-7 17

area and to a limited extent for the Biyaban area. An assessment of the

land that can be brought under command in the lower basin in the present

plan is therefore made based on the preliminary locations of the river

diversion works and alignments of canals taking off from these diversion

works marked on the topographic maps. Table No. 5 -1 gives areas that are

now irrigated and areas that can be commanded with the aid of irrigation works,

in respect of upper Helmand basin. But the figures given in the statement

under the potentially cultivable land in respect of lower basin represent the

gross areas part of which may not be commandable. It will be seen from the

table that the total land potential of the basin is as much as 518,000 hectares.

In the lower Helmand basin,about 50% of the gross area including

the areas presently under irrigation is considered for the present plan as

irrigable command. . xcluding the areas presently being irrigated, the add-

itional areas that are considered for development are taken as 145,000 hectares

the total irrigable command in the lower basin thus being taken at this stage

as 200,000 hectares. Table No. 5 -2 gives the particulars of the pres

irrigation potential of the entire Helmand basin, which is taken as 310,000

hectares.

5.4 Cropping pattern

The present practice in the basin is to raise mostly winter cereals.

Wheat and barley are grown over a large percentage of the area. Other

crops grown on a small percentage of the area are corn, mung- beans,cotton,

vegetables, fruit, etc.

In the -.project area of the upper Helmand valley, the percentage

of the area on which wheat is grown has reduced and cotton, corn and

mung -beans are being grown over larger areas. However in the Chakhansur

5-83o

area where the irrigation is done from river channels with open heads,

crops like cotton and corn are sown over a small fraction of the irrigated

area. The existing crop pattern in the upper Helmand and Chakhansur areas

is given below :

Name of crop Percentage of actual areacultivated

Remarks

10%.inlheat

Corn

Yung beans

Cotton

Vegetables

Fruits

Alfalfa

Others

Upper Helmandvalley project

59.9

13.3

2.3

18.6

0.2

1.3

1.9

2.5

Chakhansurarea

83.03

7.6--*

0.1

0.3

9.0

*includesbarley

-3; includes

Sorghum

Total 100__

100

The intensity of cultivation in the project areas of the upper

Helmand valley is at present low. The Helmand Arghandab valley Authority

are making efforts to attain higher intensities of irrigation and to in-

troduce suitable crop pattern in the irrigation project command. It is

anticipated that an intensity of 132/ :4 wdth the following crop pattern

could be achieved gradually in the next few years:

Name of crop Percent_äreácoveredPercent _area-Wheat

Cor9n 30Mting beans 10Cotton 25Vegetables 1

Alfalfa 15Fruits 6Other crops 5

Total 132

5 -9 7!The revised crop pattern aims at reducing the percentage of the

area under wheat and correspondingly increasing the same under crops like

cotton,corn etc., With the extension of irrigation facilities over larger

areas, the area under wheat will increase though its percentage may be

less and will meet the demands of the growing population. At the same time,

production of cash crops will bring in larger returns to the farmers

enabling them to raise the standard of living. It will also encourage

growth of agro-based industries. In view of the above, the following

crop pattern with an intensity of 140 is proposed for the upper Helmand

valley:

Crop Percent of area

Wheat 40

Barley 5

Corn 25

Mung beans 20

Cotton 30

Vegetables 2

Vine yards 4

Tree fruits 4

Melons 1

Alfalfa 5

Perennial grass 4

Total 140

But the - climatic conditions, soil characteristics etc., may not

permit the adoption of such intensities of irrigated agriculture in the

lower Helmand valley. Hence the following crop pattern with an intensity

5-10 2.2

of 12TY% is proposed for the lower valley

Crop Percent of area

Wheat 35

Barley 5

Corn 25

Mung beans 16

Cotton 24

Vegetables i

Vine yards 4

Tree fruits 4

Melons 1

Alfalfa 4'

Perennial grass i

Total 120

5.5 Irrigation requirements of crops

The quantity of water now being diverted at Bogra and Darweshan

for irrigating the project area does not serve as a guide for estimating

the crop water requirements in the basin. Earlier projects in the Helmand

basin have uniformly adopted the Blaney -Criddle procedure for estimating

the evapo- transpiration requirements of crops, using the vaialbie data on

mean air temperature and monthly percentage of sunshine hours applicable

to the latitude of the area. The same is applicable for the lower Helmand

basin and has been worked out and given in the earlier reports on

Chakhnasur. The monthwise irrigation requirements for each crop, taking

into account the crop coefficient applicable and the utilisable rainfall

are also given in the previous reports. The same data is therefore proposed

to be used, making provisions for leaching requirements. The monthly crop

5 -11

consumptive use requirements for each crop are given in table No.5 -3.

?.3

Based on the above data, the weighted average irrigation requirements

have been worked out for the two crop patterns proposed and given in tables

No. 5-Lf, 5-5 and 5 -6. The annual requirements for the crop pattern

proposed for upper Helmand valley works out to meters and for the

crop pattern proposed for the lower valley works out to11.41jmeters. It is

proposed. line the main canals and branches and therefore an allowance

of 20% is made towards losses. The Tables referred to above give the

monthly and yearly irrigation requirements. The total quantity of

water required in Afghanistan as per the resent plan is estimated to be

4664 million cubic meters. Apart from this, a quantity of 820 million

cubic meters is to be taken into account towards lower down uses. The

releases from storages for diverting the various requirements at various

points along the length of the river will be regulated depending on

the river yields, return flows etc.

5 -12

Table 5 - 1

9Land Potential of Helmand Basin(Hectares

Area under Potential Totalirrigation cultivable'at_present" commended area

T. Upper Helmand

Sit

a) Project areas

ii. Bogra

ii. Nad-i -Aliand Marja

8,000

18,000

- )

10,000

8,000

G28,000

iii. Shamalan 16,000 - 16,000

iv. Darweshan

b) Non project area

14,000 10,000 24,000

Jr. Ka jakai to ,I

Shamalan 6,000 + '` 4,000 ,5 =" 10,000ii. Seraj 15,00Òa f 9,000, 4`' 24,000

Total upper Helmand 77,-5667 33,000 110,00-

II. Lower Helmand

Proposed project areas

i. Khanneshin

ii. Qala Fateh-

14,000 25,E 39,000

Khwabgah 13,E 51,000 64,000

iii. Sherabad andChakhansur 9,000 121,000 130,000

iv. Sikhsar 14,500 25,500 40,000

v. Bander 4,000

vi. Taraku and

10,500 14,500

Khushk ti 500 120,000 120,500

Total lower Helmand 55,E 353,E 408,000 4r°"

Total for the entire basin132,000 386,000 518,000

5 -13

Table 5 - 2

Irrigation Potential of the Helmand Basin

Area under Additionalirrigation irrigable Total

at present area

I. Upper Helmand

a) :Project areas

i. Bogra 8,000

ii. Nad -i -Ali

- 8,000,.

and Marja 18,000 10,000 28,000

iii. Shamalan 16,000 - 16,000

iv. Darweshan 14,E

b) Non project areas

i. Kajakai to

10,000 24,000

Shamalan 6,000 4,000 10,000

ii. Seraj 15,000 9,000 24,000

Total for upper Helmand 77,000 33,E 110,000

II. Lower Helmand

a) Proposed project areas

i. Khanneshin

ii. Qala Fateh

14,000 12,000 26,000

Khwabgah

iii- Sherabad &

13,000 25,000 38;000

Chakhansur 9,000 51,000 60,000

iv. Sikhsar 14,500 12,000 26,500

v. Bander

vi. Taraku &

4,000 5,000 9,000

Khushk 500 40,000 40,500

Total for lower Helmand 55,000 145,ö 200,000

Total for the entire basin 132,E 178,000 310,000

?4"

5 -14

Table 5 -3

Monthly Crop Consumptive

Use Requirements

etab

les

Vineyards Tree

Melon Alfa- Perennidl

Wheat

Whe

atB

arle

y C

orn

Man

gbe

ans

Cot

ton

gy

Month

Oct 15

Nov 15

Oct 15 to

to Apr

tcApr.

to Apr.

mm

MM

man

MM

mm

30 r

an30 -arms

2 mm

January

27i2

7.4

20.6

February

67.5

67.5

76.5

March

128.5

128.5

126.5

April

108.8

108.8

52.9

May

June

July

August

September

'ctober

50.8

50.8

November.

50.8

50.8

50.8

December

16.3

50.8

1.8

Total

449.9

413.8

379.9

101.5

24.5

129.8

1.8

52.9

83.5

165.0

148.0

103.5

101.5

121.0

21.0

162.5

199.5

90.2

212.5

92.2.

184.0

201.5

140.5

238.0

1364

181.8

127.0

95.0

158.2

134.0

108.5

94.6

103.3

82.4

61.5

39.6

726.1

427.2

1046.3

873.8

923.9

fruit

lfa

grass

mm 31.5

68.6

mm

mm

IIun

101.8.

,

96;ÿ,

46.5

83.0

120.0

170.0

87.613.3

193.0

196.4

163.5

234.0

189.0

226.0

177.6

230.0

214.5

155.0

167.0

260.0216.3

75.0

251.0

141.8

167.0

104.5

124.0

962.5

697.5

1497.3

1308.6

5 -15

Table 5 -4

Irrigation Water Requirements Crop

Intensity - 140°0

J"°

Crop

%of

water requirement sin

mm

cropped

Jan

Feb

Mar

Apr

May

Junk

Jul

Aug.

Sep

Oct

Nov

Dec

Total

area

Wheat

(Oct- 15- Apr30)

20.

5.4

13.5

25.7

21.8

`Wheat

f

(Nov 15- Apr30) 20

1.5

13.5

25.7

21.8

/ Barley

51.0

3.8

6.3

2.7

Corn

Mung beans

Cotton

Vegetables

Vine yards

Tree fruits

Melons

Alfalfa

Perennial grass

Total

25

20

30 2 4 4 1 5 4

140

7.9

1.9

132.7

Allow 75% for farm

efficiency

11

44

Allow 20% for losses

in the distribution

system1.4

55

38.9

25.1

25.9

50.0

18.0

63.8

50.4

28.1

71.4

20.3

36.3

2.0

0.1

3.3

2.4

1.8

2.7

1.0

2.1

5.9

6.5

7.4

7..3

1.3

2.7

6.8

7.9

9.0

7.8

1.0

O.9

1.6

1.8

1.7

4.8

6.8

11.7

11.5

13.0

3.3

4.8

7.7

7.6

7.6

8.6

65.3

100.7

56.5

120.2

171.9

191.1

87

134

75

160

229

255

109

168

94

200

286

319

31.8

19.0

47.5

2.7

4.3

J.0

.5

10.1

2.5

23.6

31.0

1.7

2.5

'D

10.1

10.1

2.5

0.8

3 7

3.3

V ctS

10.1

0.1

89.9

I

87.7'

18.9

181.7

85.4

314.0

17.5

37.0

38.5

13.)

71)

19- 1. . ?,

7.0

12.6

8.4

6.2

75.0

8.7

5:.7

4:2

..1

126.6

84..0

29.7

13.5

1000.1

169

112

40

18

1334

211

140

50

23

1669 or say

1.67 m.

_--%

f. _.._

Crop

cropped

area

Jan

Irrigation

Water

Feb

Water Requirements - Crop Intensity

requirements in mm

Mar

Apr

May

Jun

Jul

Aug

- 120%

Sep

Oct

Table 5

- 5

Total

Nov

Dec

Wheat

Oct15 -Apr30

.20

5.4

13.5

25.7

21.8

10.2

10.2

3.3

90.1

Wheat

Nov 15 -Apr30 15

1.1

10.2

19.3

16.3

7.6

7.6

62.1

Barley

51..0

3.8

6.3

2.6

2.5

2.5

0.1

18.8

Corn

25

25.9

50.0

50.1

3.1.8

23.6

181.7

Mung beans

16

16.2

14.4

22.5

15.2

68.3

Cotton

24

31.1

20.1

29.0

51.0

57.2

33.0

24.8

15.2

261.4

Vegetables

11.0

-1.7

1.2

0.9

1.4

1.3

0.8

0.4

8.7

Vine yards

41.0

2.1

5.9

6.5

7.4

7.3

4.3

2.5

37.0

Tree fruits

41.3

2.7

6.8

7.9

9.0

7.8

3.0

38.5

Melons

11.0

0.9

1.6

1.8

1.7

7.0

Alfalfa

43.8

5.4

9.4

9.2

10.4

10.0

6.7

4.7

59.6

Perennial grass 1

10.5

0.9

1.2

1.9

1.9

2.2

2.1

1.4

1.1

13.2

Total

120

7.5

28.0

55.5

82.E

;_

Z99.6

145.9

160.8

100.0

72.2

40.6

11.0

846.4

Allowing 75% for

farm efficiency

10

37

75

11g

57

133

195

214

133

96

54

15

1129

09

Allow 20% for losses

in the distribution system

12

48

94

108

71

166

244

268

166

120

68

19

1414 or say

1 :41 m

5 -17

Table 5 -6

Monthly total water requirements for the area

proposed for irrigation

Water requirements in million cubic

Jan

Feb

Mar

Apr

May

Aug

Sep

Oct

Area in

iectare3

meters

Jun

Jul

Nov

Dec

Total

Upper Helmand

basin

130,000

15.4

60.5

120.0

185.0

103.4

220.0

314.6

350.9

232.1

154.0

55.0

25.1

1836

Lower Helmand

basin

200,000

24.0

96.o

188.0

276.0

42.0

332.0

488.0

536:0

332.0

240:0

136.0

38.0

2828

Total

requirements

310.

0010

39.4

156.5

308.0

461.0

245.4

552.0

802.6

886.9

564.1

394.0

191.063.0

4664

400

6-1 -70

CHAPTER 6

PROPOSAIS FER DEVELOPMENT

6.1 Irrigation

It has been brought out in the earlier chapters that there is

considerable land fit for irrigated agriculture in the lower Helmand

valley. It could be developed if suitable measures are taken to re-

claim them, extend irrigation facilities, provide inputs and create

the necessary infrastructure facilities for agricultural development,.The

water could be made available in a quantity as to meet the irrigation

requirements of the area contemplated by adopting suitable cropping

pattern with an intensity of 140% in the upper Helmand basin and 120%

in the lower basin. The irrigable area in the lower Helmand basin

can be irrigated mostly by gravity flow.

The first pre -requisite for development in the lower basin is

to reclaim the land from flooding and submersion. This is proposed

to be achieved by constructing a flood diversion dam at Kamal Khan

with all related works, and diverting the excessive flood flows of

Helmand river into Gaudi- Zirreh. It would also serve as a diversion

dam for irrigating the areas both on the right side and left side.

A storage reservoir on Helmand river upstream of Kajakai near

Olumbagh, another on Arghandab and possibly a third on Musa Qala will

create a total live storage of about 3,$00 million cubic meters, in-

eluding that of Kajakai reservoir, required to meet the proposed irri-

gation demand and other uses lower down and to step up the j rdro

power potential. It is therefore proposed to construct a reservoir

6-2

yi

on Helmand river upstream of Kajakai reservoir, one on Arghandab

river and possibly a third on Musa Qala.

The regulated releases let down from the storage dams higher

up are therefore to be diverted for irrigation at suitable points

lower down by constructing a series of diversion works.

It is considered that a minimum of two diversion dams, at

Khanneshin and Taghaz on the upstream of Kamal Khan dam and two

diversion dams Khwabgah and Sikhsar downstream of Kamal Khan dam

will be necessary. At these four diversion dams, there will be one canal

each, while at Kamal Khan diversion dam, there will be two canals

taking off from it. A fifth diversion dam upstream of Kamal Khan

dam but below Taghaz diversion dam may also be constructed. A

diversion dam below Kajakai dam at Garmab will have to be

constructed along with the necessary irrigation network for irrigating

the new areas in the upper Helmand valley.

Studies show that about 500 kms length of main canal system

would be needed to serve the area. In addition, there would be 2,000

km of laterals and sub l aLcrals .

The existing irrigation and drainage system covering an area

f about 30,000 hectares in the upper Helmand valley needs improvements

and these will have to be attended to.

The irrigation potential thus created can be utilised success-

fully, if there is agricultural development simultaneously. It is

therefore proposed to provide the necessary inputs and create the

infrastructure facilities in the command area.

6-3

6.2 Power

At Kajakai dam installation of two hydro generating units each

of 16.5 M.Ws capacity is nearing completion. With the increased storage

that will be created in the next two or three years at Kajakai dam as a

result of erection of spillway gates, it will be possible to utilise

it to step up power generation by installing additional unit with a

capacity of 116.5 M.Ws without clashing with the present irrigation

interests. This could. be done including erection of transmission lines

within five years, as what is needed is only the extension of power

house, installation of additional power units, enlarging the switchyard,

laying the transmission lines, construction of sub -stations etc., The

quickest way to meet the urgent needs of the valley in general and of

areas around Kandahar, Herat and Kabul in particular which have great

potential for rapid industrialisation, if only electric power, the

essential requirement for industrial growth is available, is by complet-

ing the installation of additional power units at Kajakai .dam and laying

the transmission lines to various load centres in the next 5 years.

Generation of power at the proposed diversion dams is not contem-

plated at present. It is however proposed to generate power at Kamal

Khan flood diversion dam,, where a low head power plant could be ins -

talled. The power generation would fluctuate between g to 2 T .Ws. /

At the upper Kajakai dam (at Olumbagh) it is however possible to

operate the reservoir for maximising firm power generation, as the

power releases from this dam are re-regulated at the Kajakai damn lower

down to suit the irrigation releases.! 0 2M.Ws of firm power with a

system load factor of 0.5 can be generated at this dam. It is therefore

proposed to have a power plant with an installed capacity of 90 M.Ws

6-4 9?at this darn by the time the power generated at Kajakai is fully utilised

and demand for additional power grows.

The additional storage space created at Kajakai, the proposed

complex of additional storage reservoirs, diversion dams, canal systems

would ensure the following benefits :

Firm power of 120 M.Ws at 0.5 load factor at Kajakai dam'

with an installed capacity of 150 M.

2. :Immunity to the lands to an extent of about 1100,000 hectares

in the lower Helmand basin from flooding and inundation;

3. Irrigated agriculture over 233,000 hectares of land in

addition to the existing 77,000 hectares of land in upper

valley;

4. Additional firm power of 60 M.Ws at 0.5 load factor at upper

Kajakai dam with an installed capacity of 90 M.Ws.

3

7 -1

CHAPTER 7

KAMAL KHAN FLOOD DIVERSION DAN" AND RELATED WORKS

vy

7.1 General

The yields of the Helmand river particularly in the months of March,

April _And may in about one at of there v rs. II .Kajakai are very much

more than what the storages can absorb, with the result the excessive

floods flow down the reservoirs. In the water year 1956 -57 the river

yields in the months of March, April, May and June at Kajakai were

1440, 2990, 3120 and 1270 million cubic meters respectively. Again in

the water year 1964 -65, the river yields in the months of March, April,

May and June at Kajakai were 1185, 2164, 2360_ and 1110 til1ion'cub a 'meters

respectively. The yields of Musa Qala river and those of Arghandab river

in 1956 -57 are also considerably high. Such excess flood volumes empty

into Hamuns lower down, the water levels of which backup flooding large

areas.

The peak flood discharges of the Helmand river at Darweshan in the

years 1957, 1961, 1965 and 1967 varied between 3760 m3 /sec and 2180 m3/

sec. The corresponding peaks at Chahar Burjak also varied between

3300 m3 /sec and 2180 m3 /sec., even after the construction of the Kajakai---

reservoir. Large areas to an extent of about 100,000 hectares in the

reaches below Khwabgah are reported to have been flooded during these

years. It is reported that flood protection dykes breached whenever

there were flood inflows. Re-construction of these dykes is reported

'0

7 -2

to be a recurring feature involving heavy cost and labour. About 100,000

hectares of land is said to suffer in most of the years due to flooding

and inundation on account of excess flood volumes and peaks.

A large number of flood protection works and more costly diversion

structures are to be constructed all along the river channel course to

prevent flooding. And large storages are to be created to absorb large

flood volumes to prevent inundation. Both or either of these measures

will be prohibitively costly. A natural depression like Gaudi- Zirreh

which has a large storage space can only absorb such excess flood volumes

and flood peaks without flooding and inundating valuable lands.

Two alternative sites one at Rodbar and the other at Kamal Khan

were investigated for diversion of excessive flood waters to Gaudi- Zirreh.

The diversion at Kamal Khan takes advantage of the natural channels,

Rud-i-Biyaban and Rud -i- Khushk thro which excess flood flows could be

economically led into Gaudi- Zirreh. The alternative of flood diversion

at Kamal Khan is therefore selected.

The flood control scheme is to divert excess flood flows of the

Helmand river westward into Rud -i- Biyaban then south into Gaudi- Zirreh

thro Rud -i- Khushk. The water diverted into Gaudi- Zirreh would dissipate

by evaporation. Flows are diverted into Hud -i Biyaban by Kamal Khan dam

and into Rud -i- Khushk by Qala Afzal dam. A control weir is proposed at

the point of diversion into Rud-i-Biyaban to maintain diversion levels at

the outlet structures in Kamal Khan dam. A road bridge over the control

weir and taken over the Kemal Khan dam would connect the left and right

banks of Rud-i-Biyaban and both the banks of Helmand. A law dyke on the

right bank of Rud-i-Biyaban provides access to Qala Afzal dam, apart from

protecting low lying lands against flooding. An irrigation outlet at

7 -3

the right abutment of the Kamal Khan dam would let down the discharge

into the right bank canal which irrigates areas down to Khwabgah diversion.

Similarly another outlet on the left side would supply water for irrigating

the lands in Taraku and Khushk.

The two flood control dams, (Kamal Khan and Qala Afzal dam) and the

C6htrol weir

Rud-i-Khushk.

to be designed to pass a flood of about 24,000 m3 /sea into

7.2 Kamal Khan dam

N"'

The main component of the flood diversion complex is Kamal Khan

dam which is to be located near the village (Deh) Ghulam Haider. It is

proposed to be a zoned earth dam tied into the high ground on the right,

while on the left it will be connected to the dyke leading to Qala Afzal

dam. The crest of the dam will be 8 meters wide and 6,700 meters long.

Though this dam is not meant to store water, its height and the diversion

level are to be finalised with reference to the hi hest command levels

and power generation. The embankment consists of an impervious core with

pervious to semi- pervious random -fill zones upstream and down stream of

the core and outer shells of porous gravels. An impervimts6utoff is to be

provided to intercept the gravel layers below the stream bed.

The river outlet works will be located at the right bank of the river,

close to the present Qala Fateh canal. The existing Qala Fateh canal

passes thro the proposed dam site on the right bank of the river. The

proposed right bank canal taking off,from the dam will take over the

irrigation of the existing Q4a Fateh canal and irrigate all the command

on the right bank upto the Khwabgah diversion dam. Another outlet work

will be provided on the left bank to feed the areas in Taraku and Khushk.

i

7-l+

97

A low head power plant at the toe of the dam can generate power

with the irrigation and river releases from the dam.

7.3 Qala Afzal dam

It will also be a zoned embankment like the Kamal Khan dam. Its crest

will be 8 meters wide and will be 1660 meters. The embankment

consisté of an impervious core, random -fill zones and upstream and down

stream gravel shell. An impervious cutoff is proposed below the river

bed.

7.4 Control weir

A control weir is proposed at the entrance of the Rud- i- Biyaban

to maintain the required diversion levels at the outlet structures of

Kamal Khan dam. The weir elevations mostly conform to the existing

channel bed levels. The structure is designed to pass a maximum discharge

of/ 4249 pubic meters per second over the concrete overflow structure.

Flood peaks in excess of this volume could overtop and erode the earth

dyke on the left flank of the weir..rowavsor*

8 -1

L/7

CHAPTER 8

UPPER KAJAKAI DAM AT OLUMEAGH

8.1 General

Possibility of locating a dam upstream of Kajaki reservoir is explored

by a study of the topographic maps. Three sites were considered of which

the one at Olumbagh is situated between the other two. The upper site

is not considered suitable as the yields of the river will not be large

compared to the flows at Olumbagh for interception and regulation. In

addition it involves submersion of a large extent of ozàltivated land.

The site below the one at Olumbagh is not considered quite suitable from

considerations of surface geology. An earial reconnaissance survey of the

valley revealed that the site at Olumbagh is suitable. Based on the

available topographic maps a pre- feasibility study of the dam is made.

8:2 Location

The dam is proposed to be located on Helmand river near Olumbagh

village about 75 kilometers upstream of Kajakai dam, at latitude 32° -

52'N and longitude 65° - 30'.

8.3 Hydrology

There is no gauging station in the vicinity of the proposed dam

site. However there is a gauging station at Dehraout about 15 kris down

stream of the-proposed site and upstream of the confluence of tributary

Tirin. As there aré no major streams joining the Helmand river in the reach

between the proposed dam site abd the gauging site, the river flows at

y9 8 -2

Dehraout are taken to represent the flows at Olumbagh. The drainage area

is 35,000 square kilometers. The dependable flow of the river at Kajakai

for 75% of the period has been estimated to be 4690 million cubic meurs.

The yield of the river at Kajakai in the water year 1954 -55 is 4673 m. m3

which very pearly represents the 75% dependable yield. The corresponding

river yield at Olumbagh is 4397 114 m?

. The yield fran the bate

catchment is mostly due to the flows of Titan river.

8,4 Design flood

The Kajakai design flood was reviewed in the feasibility study

for installation of spillway gates at Kajakai reservoir and was computed

to reach a maximum of 12,500 m3 /sec (440,000 cfs.). For the purpose

of the present studies, the design flood of Helmand river at Olumbagh

is also taken to be 12,500 m3 /sec.

8.5 Area -capacity of the proposed reservoir

In the absence of topographic maps with contours at closer intervals,

the water spread area at contours 1100, 1150 and 1200 are planimetered

and areas and volumes at 10 meter intervals are computed from A = k. do

where k and n represent valley characteristics and d is the height of the

contour from the river bed. Based on this the water spread area and

storage volumes at different elevations are computed and plotted.

The gross storage capacity of the upper Kajakai reservoir (at Olumbagh)

is fixed as 1800 m. m3 for purposes of this study of which 600 m. m3 will

be dead storage. The gross storage capacity of the reservoir is 1758

million cubic meters at elevation 1150 and hence the full reservoir level

8-3

is fixed as 1150 meters. With the construction of the upper Kajakai

reservoir the volume of silt that gets deposited in the Kajakai reservoir

would be -much less than what is now estimated.

8.6 Lay -out

The flanking abutment hills of the valley get closer at the proposed

site, expanding suddenly towards the upstream. The left abutment hill is

very nearly vertical with exposed rock face. On the right side the abutment

hill has a milder slope covered by talus. The average bed level is at

about El 1100. as could be judged from the topographic map.

The geology of the dam site may be said to be dolomitic lime stone01.101NNXIMINesseepaa.

with gently tilted bedding planes. It is considered to be similar to what

is obtaining at Kajakai dam site. Pending investigations of the surface

and subcurface geology, a rockfill dam is considered to be a suitable

choice at the proposed site.

The crest of the dam is proposed at El 1155 which provides 5 meters

of free board. The length of the dam at crest is 1250 meters. The height

of the dam above the deepest bed level and the assumed foundation level

is 55 meters and 65 meters respectively. The top width of the dam is

10 meters. The upstream and down stream slopes are 2(H) to 1(v). The e,,.,01;

section is made of an impervious hearting zone compacted in 0.2 meter

layers. Zone 2 consists of two sub -zones of pervious filter made of fine

and coarse material. Zone 3.fonn ing.the outer shell is again made of two

sub- zones, 3A and 3B. Zone 3A is made of rock 0.6 m3 max. size vibrated

8-4 5f

in one meter layers and sluiced with high pressure water jet. Zone 3B

is made of rock 2.25 m3 max. size dumped in layers upto 10 meters height

and sluiced with high pressure water jet.

The spillway is located on the right side. An approach channel and

a spillway channel 1400 m long is to be excavated. The need or otherwise

of an energy dissipator at the exit end of the spillway channel will have

to be deáided based on geological investigations and hydraulic model studies.

The spillway channel is 200 m wide. The spillway structure consists of 15

vents of 10 m x 11,5 m. The crest of the spillway is proposed at 1138.50

while the gate crest is to be at E11150.15 m so as to maintain the full

reservoir level at El 1150 meters. The spillway regulator is tentatively

designed to discharge 12,500 m3 /sec at full reservoir level, with all the

gates fully open. Possibilities of reducing the number of vents are to be

explored at the time of preparing feasibility studies by designing the

structure with increased depth of flow over the crest,M.W.L. being kept

2 to 3 meters higher than the F.R.L. and by taking into consideration the

effect of flood routing.

The maximum discharge gauged in the years from 1952 to 1960 in the

months of October, November, December, January, February, Jane, July,August

and September is 830 m3/sec (29,200 cfs). The max. discharge observed in

the other three months March, April and May for the same period is 1220m3/

sec. The rockfill dam takes minimum of 2 years to be raised upto a level

above the spillway crest. During the construction stage the entire flood

will have to be diverted without overflowing the rockfill dam section.

Two tunnels of 9 meter dia each are tentatively proposed to dispose c"

52

3a flood of about 1600 m /sec, with each tunnel carrying 800 m /sec. During

detailed investigations, possibilities of providing only one tunnel will

have to be examined. The length of each tunnel is 750 m with approach and

exit open cuts. The sill level of the tunnels at entrance and exit will be

1100 m and 1099 m. The tunnels will be concrete lined and are so aligned as

to have a minimum rock cover required for pressure tunnels. One of the two

tunnels will be converted into a pressure tunnel for power generation, after

it serves itspurpose as a diversion tunnel. The intake leva -of the pressure

tunnel will be at El 1125 and so the horizontal tunnel and the intake at

El 1125 will be connected by a sloping tunnel. A control shaft of 11 m

dia with control gates will be provided for each of the tunnels to regulate

the discharges during construction and operation stages.

A power house with power plant having an installed capacity of 90 M.Ws

(3 units of 30 M.Ws each) will be constructed on the left side at the exit

end of the tunnel.

The lay -out of the dam, the spillway channel, diversion tunnels and

other relevant design details are shown in figures 8 -3, 8-4, 8 -5 and

8-6. Figure 8 -1 is the water spread area map and figure 8 -2 contains

the area capacity curves.

8 -7. Salient features:Following are the salient features of the dam and other related

works:

1. Location

i.. River Helmand at Olumbagh village about

75 kms upstream :of Kajakai

ii. Latitude

iii. Longitude

dr -7521

650 - 30r

1

8 -6

6-3

2. Hydrology

i. Drainage area 35,000 sq kms

ii. Annual runoff at Dehraout

a) Max observed for the water years 53-60 10,500 m.m3

b) Min n n n rr rr 4,270 n

iii. Flood discharge

a) Max discharge for the ears 53 -60 1880 m3 /sec

b) Min "n n If tr 44 m3/sec

iv. Design flood 12,500 m3 /sec

v. Deep bed level of the river El 1099.00(Estimated)

vi. Tail water level(min) El 1101.00

3. Reservoir

i. Full reservoir level El 1150.00

ii. Min draw down level El 1130.00

iii. Dead storage level El 1125.00

iv. Gross storage capacity 1758 m.m3

v., Live storage capacity betweenEl 1150 and El 1130 1194 mmrP

vi. Water spread area at F.R.L.1150.00 8300 hectares:e...-

vii. Extent of cultivated land comingunder submersion at F.R.L, elbout 2000 hectares

4. Diversion arrangements

a) Two diversion tunnels

size of each

Length of each

9 m dia(circular)

750 meters

Invert level at start El 1100.00

Invert level at exit end El 1099.00 )\

r..

8-7

Main dam

i. Type

ii. Top of dam

Rookfill dam

El 1155.00

iii. Height above the deepestbed level 55 m

iv. Height above thedeepest foundation level 65 m

!v. Total length of dam at top 1250 m

vi. Quantities

Zone 1 1.4 m.m3

Zone 2 1.3 m.m3

Zone 3 6.0 m.m3

6. Spillway

i. Max discharging capacity overthe spillway at F.R.L. 12,500 m3 sec

ii. Gross length between abutments 192 m

iii. Number ad size of spillwaygates 15 Nos

(w)

10mx11.5m(H)

1400 miv. Length of spillway channel

7. Power potential

Firm power

8. Power plant installed capacity

60 M.Ws at 0.5 L.F.

3 units of 30 M.Ws each.

9 -1

CHAPTER 9

IRRIGATION WORKS

9.1 Upper Helmand valley

As per the present assessment, about 33,000 hectares of land is

potentially irrigable in the upper Helmand valley. A diversion dam at

Garmab is required to feed a large proportion of these lands through an

irrigation and drainage network on the left bank.

An extent of about 30 000 hectares under the existing irrigation

system lacks adequate irrigation and drainage facilities. The existing

network is to be improved and modernised to derive full benefits.

9.2 Lower Helmand valley

There are large extents of ggricultural land along the right bank

of the river from Khanneshin upto Deshu. On the left bank in this reach

there are small pockets of cultivable land. But below Deshu village

there are large extents of cultivable area along the left bank of the

river, extending upto Dew, In this stretch again the right margin

is cutup with vertical escarpments. In the lower reaches opposite

Khawaja Ali village, sand dunes occupy the flood plain. It may not

therefore be possible to develop irrigated agriculture on the right bank

opposite to Khawaja Ali village.

The irrigable areas on the right and left banks below Rodbar upto

Kamal Khan and Bander respectively can be commanded by two canals

taking off on either bank from a suitable diversion structure located

between Rodbar and Chahar Burjak. At Kamal Khan flood diversion dam,

the left side canal commands the lands beyond Qala Afzal while the right

side canal commands the lands upto Khwabgah. The irrigation water

9 -2

required for the areas on the right bank below Khwabgah and for other

uses lower down will be released into the river at Kamal Khan flood

diversion dam.

A diversion dam in the vicinity of Khwabgah and a canal taking

off on the right side will be able to command most of the areas towards

the east in the Chakhansur region beyond Khwabgah. These areas include

those at present irrigated by the Shahi canal, the Marangi canal, Rafiq

Khan canal, Jerokhi canal, ,00-.c. and the areas around Ziarat, Sherabad

and Chakhansur extending as far as the limits of Hamuns. Similarly

the land that is being irrigated bybthe Sikhsar canal and the areas

beyond it upto Hamun -i Puzak and extending towards the east to the

swampy areas and to the west of Chakhansur can be commanded by the

existing Sikhsar canal suitably remodelled with a diversion structure.

The irrigation development will therefore consist of the

following :

1. A diversion dam at Garmab and an irrigation network on the

left bank of the river.

2. A diversion dam across Helmand river near Khanneshin village i

with a right bank canal goingupto Deshu on the right bank.

3. A diversion dam near Taghaz village upstream of Deshu and a4./1

left bank canal to cover the lands in the Khawaja Ali

villages.

4. A diversion dam at a suitable place between Rodbar and

Chahar Burjak with a right bank canal irrigating, .aras

in Chahar Burjak and upto Kamal Khan and a left bank canal

irrigating the lands in the Bander area.

9 -3

5. Kamal Khan flood diversion dam at Kamal Khan with a right

bank canal irrigating lands upto Khwabgah. This canal

will feed the Lashkary canal now being executed. The left

bank canal taking off from this dam irrigates the lands

in Taraku and Khushk regions.

6. A diversion dam near Khwabgah with outlet arrangements for

releases to downstream areas and for the Sikhsar area and

a right bank canal to cover the Ziarat, Sherabad and

Chakhansur areas.

7. A diversion dam across the Nad -i -Ali river at the point

of offtake of the existing Sikhsar canal to irrigate lands

to the north of Shela C,harkh channels.

The proposed irrigation projects are briefly described as

follows:

9.3 Khanneshin diversion dam

A diversion dam is proposed across Helmand river a few kilometers

upstream of the Khanneshin village. Approximate bed level of the river

is lE2.t meters and the crest of the structure is proposed at elevation

648. A right bank canal taking off from this diversion structure will

irrigate lands lying along the right bank of the river upbo Deshu

village. The full supply level of the canal at the head will be El 648.

The approximate length of the canal will be 64 kms. It will command

a gross area of about 26,000 hectares while the areas to be irrigated

will be about 17,000 hectares.

IC t, .r+ M

? oo,G1 a... r: e

. ` )-41y{f tl ,..

i Ì}#/

9 -4

57

9,4 Taghaz diversion dam

This diversion dam is proposed near village Taghaz. The appro- y 9

ximate river bed is at E1 596 and crest of the structure will be at El

602 meters. A 70 kms 1eí t bank canal is proposed from this diversion

structure, to irrigate lands lying along the left bank of the river,

covering Khawaja Ali village and extending upto Rodbar. The canal has

a gross ;command of 13,000 hectares with an irrigable area of about

9,000 hectares. The full supply level of the canal at its head will be

at El 602 meters.

9.5 A low dam between Rodbar and Chahar Burjak wt,nrre the average bed

level of the river is at about El 538.00. The crest of the structure

may be kept at El 540.50. The right bank ¡anal taking off from this

dam will have a gross command of about 14,000 hectares while the irrigable

area will be about 8,000 hecta es. The left bank canal will have a grc-

command of about 14,500 hectares while the irrigable area will be about

9,00') hectares. The full supply levels of both the canals may be at

elevation 540.00.

9.6 Kamal Khan diversion damk

The right bank canal will be nearly 80 kms. It will command a 1ft.,

gross area of about 50,000 hectares while the area to be irrigated will

be about 30,000 hectares lying in Qala Fatah and Khwabgah areas. This

a,.,

canal will terminate n'ar Khwabgah. The left bank canal will command b,r

a gross area -of 120,000 hectares while the irrigable area will be about

40,500 hectares.

9 -5

9.7 Khwabgah diversion dam

This diversion dam is proposed across the Helmand river just below

Khwabgah. A right bank canal taking off from this structure will command

a gross area of 130,000 hectares and provide irrigation to about 60,000

hectares in Shahi, Ziarat, Sherabad and Chakhansur areas. It will be

about 115 kms long with its full supnly level at head at elevation 501

meters.

9.8 Sikhsar _ diversion dam S

The Sikhsar diversion dam is proposed to be'located on Mad--1411" river

near the existing Marangi canal intake. This dam will feed the Sikhsar

canal for irrigatingthe lands lying on the north of Shela Charkh. The

dam will be nearly 200 meters long. The Sikhsar canal will be 40 kms

long. It will command a gross area of about 40,000 hectares while irrigable

area will be 26,500 hectares.

9.9 Lashkary canal.

The Lashkary canal is taken up for execution in the Chakhansur

area of the lower Helmand basin to extend assured irrigation supplies

to the lands under the command of the traditionally age -old systems

comprising of Khwabgah and Nari - Shahi canals etc., and to bring in

additional areas under irrigation. The area to be benefitted is

18,400 hectares. The intake of the canal is proposed at about 200 meters

from the right margin of the river. Its carrying capacity at head is

20.6 m3/sec. Its bed level and full supply level at the intake are 502.92

and 504 The canal length is about 45 kms. It is proposed to feed

the Lashkary canal at its head from the proposed right bank canal taking

off from Kamal Khan dam. The irrigable area under this canal forms a part

of the irrigable areas under Kamal Khan right bank canal and the Khwabgah

canal.

1u -1

CHAPTER 10

COMMAND AREA DEVELOPMENT

CO

Creation of irrigation potential is not an end by itself. It is

only a means to achieve the goals of planned development of agriculture.

The former involves mostly works of engineering, But the agricultural

development requires multi -disciplinary efforts. Since the development

plan extends over an extensive potential land area, it is necessary

that adequate and timely attention is paid to the latter.

The following are some of the important aspects that require

attention :

i. It is understood that a limited number of families in the area

control most of the presently cultivated land, owning the land, water

rights, villages as well as most of the live -stock. The farming is carried

on largely by farm labour on direct employment or in return for a share of

the crop. Large scale development of irrigated agriculture, however,

needs settlement of increased number of agriculturists. Consolidation

of holdings, thus acquires a special relevance. Such consolidation includes

earmarking of areas required for roads, channels, drains, etc., and

redistribution of remaining area among the holders of land in such a way as

to make individual holdings more compact.

ii. Irrigation practices for different crops, particularly high

yielding varieties vary according to the habit of the crop, climatic

conditions and the nature, texture and depth of the soil. These factors

vary from place to place. Therefore, there is need for agricultural re-

search programme to develop suitable cropping patterns and manurial and

10 -2 62

agricultural practices. Other factors which call for attention are the

consumptive use of water for crops, water losses, the movement of water

and salts in the soil, control óf weeds, methods of irrigation and drainage

and selection of crops for saline, alkaline and water logged soils. It

would therefore be necessary to organize agricultural research and

demonstration farms in the command area.

iii. Efficient irrigated farming is not possible without adequate

supply of inputs like better seeds, fertilisers, pesticides etc.

Adequate arrangements for introducing seeds of new strains, fertilizers,

pesticides and insecticides and their storage and marketing are necessary

and therefore to be provided.

iv. Irrigated agriculture on such extensive areas has to be

necessarily market oriented. It creates large supplies for export and

sale. Roads within the command area, inter provincial highways, marketing

centres, ware-housing and storages at the marketing centres ate to be

constructed.

v. Live-stock raising is yet another aspect that needs to be

given serious thought. A few farmers pursue this activity along the

foreshores of the Hamuns. There is still extensive land potentially

suited for production of fie provided dependable water supply is,a.

ensured. When the entire area proposed under irrigation develops, possible

conjunctive use of ground water and surface water will help in the

raising of sheep and cattle and the development of sheep and cattle

industry. Coverage of the land with forage will also prevent soil erosion.

The cost of land levelling /shaping constitutes one of the major

items in the total cost of the area development in a project of this

10-3

magnitude. Levelling operations need implements and machinery.

They need technical guidance. This item of work which needs

engineering skills will have to be therefore executed along with

other engineering works. Suitable provision for the same is made

in the project cost.

Command area development is a very important task. It

requires a high degree of organizational and administrative co-

ordination between different disciplines and institutions. Broadly

a programme of area development needs the assistance of various disciplines,

irrigation, power, agriculture, animal husbandry, co- operation and

community development, various institutions such as ware - housing co-

operatives, government and or private banking corporations etc.

It even makes demands on communications, health and education services.

In effect the development of the command area calls for all the services

that are needed to build a new social and economic order. It may

therefore be necessary to have a special administrative agency for the

co- ordinated and expeditious development. Such an agency should exist

for the period of development.

,7CHAPTER 11

POWER POTENTIAL

The country's economic progress is not limited to the development

of agricultural sector only. Industrialisation is a must for improving

the living standards of the people and for making the country self -

reliant. Agricultural development opens up new horizons for setting'

up a large number of agro based and animal bye- product industries. The

region abounds in other untapped natural resources. All these need

electric energy. In the provinces covering the Helmand valley,the

total installed power (diesel and hydro) is onlyt 9.5 M.Ws which is

just an insignificant fraction of even 'the dôestic needs. A hydio° power

station with two units of 16.5 M.Wb each is being executed at the toe

of the Kajakai dam and is to be 'acmpleted a d eonuiasioned in the near

future.

With a shift in priorities for rapid industrial growth,the power

station at Kajakai with an installed capacity of 33 M .W,rwill not be

able to meet the rapidly growing power demand in the valley and other

important places like Kandahar, Herat, Kabul etc., where there are a

number of plans for industrial development in the next few years.

Kajakai is the only place where the power generation can be stepped

up with minimum effort, investment and time, as the available storage

is being increased by installing spillway crest gates and where water

conductor system,intake etc., were already completed at the time of

construction of the dam.

e

11 -2

Power studies show that firm power of 60 M.Ws at 100% load factor

(120 M.Ws at 0.5%L.F) could be generated with`the irrigation releases

in most of the months and by releasing additional power draft in the

two or three non -irrigation months of December, January and February..

The annual energy that will be available at Kajakai is assessed

to be 600 million KwHs. This power is to be transmitted to Kandahar,

Herat, Kabul and other load centres thro transmission lines of suitable

capacity. The transmission lines connecting Kajakai to Kandahar and to

Lashkargah are already under erection.

In the initial stages of development the power generated at Kajakai

will be transmitted for utilisation in the main power consuming centres

like Kandahar, Herat, Kabul etc., In the ultimate stage, however, when

the power projects on Harirud and Farahrud and those in the north are

completed, all the generating stations will be inter -connected forming

a national grid. In the context of formation of such a national grid,

the hydro pr plant at Kajakai and another at the proposed upper

Kajakai (Olumbagh) dam which have a commanding geographical disposition,

are considered very important.

As a first step towards promoting the industrial development of

the region, it is proposed to increase the installed capacity at Kajakai

dam by 116.5 M.Ws and lay the transmission lines extending to Herat,

Kabul, etc.,

The Kajakai reservoir was constructed to serve more than one

function, Led irrigation, power and possibly flood moderation. It

was also recognised at the same time that there will be a clash of

interests in trying to optimise any one particular use in the ultimate

stage of development. With the construction of the upper Kajakai dam

11 -3 65and one or two more each on Arghandab river and Musa Qala river,such

a situation is expected to be remedied to a large extent by the integrated

operation of the reservoirs. The upper Kajakai reservoir being located

only about 75 kms upstream and with the yields from the intermediate... _catchment being small, can be operated to intercept and regulate the

flows for maximising the prime power output.

The power releases from this dam can be with-held and re- regulated

at Kajakai dam primarily to meet the irrigation demands which could

be used for power generation. Hydro power station at upper Kajakai

( Olumbagh) dam has thus an important role to play in the power systemc' l

of the region and irrigation development in the valley.

A typical reservoir operation table(Tablell -1) for the water year?

1954 -55 which corresponds to a 75%dependability indicates that 7014.Ws xof firm power at 50% load factor can be generated. This station could be

used for peaking the power requirements in the system. Even in a year pf

90% dependability, nearly 60 M.Ws of firm power at 50% L.F. can be had,

fi

as it is mainly dependent on the flows in the eight non -flood months

and the live storage capacity of the reservoir. It is therefore proposed

to construct a hydro -power station at the proposed upper Kajakai(0lumba-

dam with an installed capacity of 90 M.Ws. It s anticipated that the4. 46.

annual energy generated at this staion would be 250 million KwHs in a

year of 90% dependability.

Detailed integrated reservoir operation studies will have to

be made to lay down the operation rule for maximising the combined

benefits of irrigation, power and flood control.

A transmission line will be laid from Olumbagh to Kajakai inter-

connecting the system laid ''for the transmission of l ajákai power.

11 -4

66

With the construction of the upper Kajakai (Olumbagh)dam, the

power benefits otherwise anticipated to accrue at Kajakai will

considerably improve.

Apart from the sizable power that can be generated at Kajakai

dam and upper Kajakai dam and fed into the regional grid, it will

be possible to install a low head hydro power plant at Kamal Khan flood

diversion dam where power upto 8 M.Ws could be generated from the

irrigation and other releases. The power so generated will be of

immediate benefit to the Chakhansur area.

Water Year - Oct

Power

fl

Month

Starting Starting

Infi

level -m

s orage

m. m

vols

em

.m

Upp

er K

ajak

ai D

amQ

Olu

mba

gh)

Typical Reservoir Operation

1954 - Sep 1955 Annual/Inflow - 43

Outflows

Closing

Spillway Eva- Eva- Total storage

outflows por-

por-

out-

vol.

m.m3 m.m

ation ation flows

m.1713

Oct 1954

Nov

Dec

Jan

1144.0

1142.5

1141.0

1140.0

1350

1243

1143

1017

205

214

203

188

302

308

327

370

1955

Feb

1135.5

833

177

380 4

Mar

1131.0`3 627

4$0

393

Apr

May

1137.0

1144.0

910

1355

767

1010

314

592

fl )

June

1150.0

1758

491

471

July

1150.0

1758

211

262

-

Aug

1149.0

1686

129

280

Sep

1146.5

1518

122

278

4397

4277

m. m

m

0,15

10

0.09

6

0.04

2

0.04

2

0.06

3

0.,08

40.13

8

0.19

15

0.25

20

0.27

21

0.23

17

0.17

12

1.70

120

Table

.

97 m.m3

Reservoir

level at

end of

Table 11 -1

Min.Drawdown level 1132,0 -

F.R.L.

. t00

Power Av.headPower

Tail

flow

mpoten- water

inm/

month

sec

m

312

1243

1142.5

314

1143

1141

3 ?9

1017

1140

372

833

1135.5

383

627

1131

397

910

1137/

322

1355

1144

607

1758

1150

491

1758

1150

283

1686

1149.0

297

1518

1146.5

220

1350

1144.0

4397

NOTE: The inflows are based on

tbe data

t D hraout,a gauge

and u/s of Kajakai

reservoir

and

u/s

ofthe confluence

* 14'1 ,1

36.ou v 7'4'31

3 i 3

x

e,¡

i:.r

s

113'

b

39.5 '

119

37.0

122

36.0

138

34.0

157

29.0

tial

'leve

lat

(assumed)

100%

.

35,500

1102

35,200

1102

35,100

1102

37,Ó00

1102

157

1102

1102

I.4

714a

"ó. 0

35,2

00/-

'

12f

36.5

35,400

220

43.0

75,8oa

195

46.0

72,000

97.5

45.5

,

35,50o

104.0

43.5 /

36,000

107.0

41.0'

35,000

station d/s of the proposed dam

site

of river Tirin.

)bt4

a?

,

1102

-1102

1102

1102

1102.,l

1102

ry

11 -6

UPPER KAJAKAI DAM(OLUMBAGH DAM)

Typical reservoir operation table for

a dry year

Water year 61 -62 with an

annual flow of only 3565

m..m3

is assumed to follow a 75% year

Month

Starting Starting

level

storage

mvolme

m. m

Inflows

m.m3

Outflows

_.._

Spillwa,yEvapo-

outglow ratjlon

m.m

m.m

Reservoir

level at

the end of

the month

Closing

Power

flows

m.m

Total storage

out- vol ne

f lowsm. m

Oct 61

1144.00

1350

33

270

-10

280

1103

1140.75

Nov

1140.75

1103

221

270

6276

1048

1140.00

Dec

1140.00

1048

126

294

2296

878

1136.50

Jan 62

1136.50

, P70

226

318

2320

784

1135.00

Feb

1135.00

784

236

303

3306

714

1133.00

March

1133.00 -> 714

382

340

4344

752

1134.00

AP?'.

1134.00

752

853

280

8288

1317

1143.50

May

1143.50

1317

748

292

15

307

1758

1150.00

June

1150.00

1758

344

324

20

344

1758

1150.00

July

1150.00

1758

149

228

21

249

1658

1148.50

Aug

1148.50

1658

116

234

17

251

1523

1146.50

Sep

1146.50

1523

131

234

12

246

1408

1145.00

Note:There is no

evaporation

Table 11 - 2

F.R.L. 1150.00

Min. Drawdown le-

.t

vel 1130.00

Average Power

Tail water

head

potential elevation

at 10T%

(assumed)

mkws.

k s .

101.0

38.25

303000

104.0

36.38

30,3Q0

1102

110.0

34.25

30,100

119.0

31.75

30,100

125.0

30.00

30,000

l29.50

30,000

i°11-.0

34.75

30,000

109.0

72715

37,200

125.0

45.00

,

461000.

85.0

45.25

30,800

87.3

43.50

30,400

90.3

41.75

30,100

35

3387

1102

1102

1102

1102

1102

1102

1102

1102

1102

1102

1102

54_520

3507

A minimum of 30 M.Ws at 100% L.F. can be had

th .oughout the year

data for thid dry year at Dehraout.

Hence the inflows into Kajakai minus the

in Kajakai reservoir are taken to represent the inflows into upper Kajakai

reservoir.

12 -1

CHAPTER 12

ESTIMATE OF COST

The estimate of cost of development of the Helmand basin relates

to the execution of the following works :

A. Irrigation

1. Kamal Khan flood diversion dam with related works;

2. (a) Lashkary canal scheme;

(b) Area development under Lashkary canal scheme,covering

an area of 18,400 hectares;

3. Improvements to the existing irrigation system in the

upper Helmand valley;

4. Six diversion dams, two on the down stream and four on

the to stream of the Kamal Khan dam;

5. (a) Irrigation and drainage network to irrigate an area

a \

(b) Area development of 214,600 hectares;1 ;..a

6. Construction of upper Kajakai dam (at Olumbagh) on

f 4,60ç hectares;

1,

Helmand river and two more dams one each on Arghandab

river and Musa Qala.

B. Power

1. Installing additional hydro generating units with

a capacity of 116.5 M.Ws at Kajakai, laying transmission

lines to Kandahar, Kandahar to Kabul via Ghazni and

Kajakai to Herat, constructing sub- stations,distribution

network, etc.,

12 -2

2. Construction of power house and installation of power

plant consisting of three units of 30 M.Ws each and

transmission lines from upper Kajakai dam to Kajakai

dam.

An abstract of the cost of the above works is given in

Table 12 - 1.

12 -3

Abstract of Cost

Name of work

A. Irrigation

1, Kamal Khan flood diversion dam and related

works

2. Lashkary canal scheme

3. Improvements to the existing irrigation system

in upper Helmand valley

Six diversion dame

5. Irrigation and drainage network,land levelling,

7/Table 12 - 1

roads, etc., to irrigate an area of t 214,600

hectares

6. a) construction of upper Kajakai dam at

Olumbagh

b) imo dams one ori Arghandab and the other on

Musa Gala

Total for irrigation and area development

B. Power

1. Installing additional hydro generating,

units with a capacity of 116.5 }.Ws at

Kajakai; laying transmission lines to

Kandahar,Kandahar to Kabul via Ghaani. and

Kajakai to Herat, constructing sub -stations

distribution network, etc.,

Cost in million Afs

900

1472

1000

)Cí',?

2040

171.'468

62501

.

3179

32,400 million Afs.

10,300 million Afs

12 -4

2. Construction of power house, installation

of 90 M.Ws capacity power plant and

constriction of transmission lines

and sub- stations

72_

2' 00 M. Afs

Total for power development 13,E million Afs.

IRBIGATIÜN

12 -5

ABSTRACT ESTIMATES

J 1. Kama1 Khan flood diversion dam and

7.2

related works

1. Kamal Khan flood diversion dan ''` 470 million Afs

2. Control weir 270

3. Gala Afzal dam including dykes 160 " "

Total 900- " "

2. Lashkary canal scheme

Main canal, laterals and sub-laterals

drainage, land levelling ,road ,etc.,

for 18,400 ha at 80,000 Afs per hectare 1472

t1 3. Improvements to the existing irrigation

P, t,.4

system in the upper Helmand valley 1000

4 Average cost of 1 diversion dam 340 m. Afs

Cost of 6 diversion dams 340 x 6 2040

5. Irrigation and drainage network land

levelling, roads, etc. ,covering 2144500

hectares at 80,000 Afs per hectare 17168

6. Construction of upper Kajakai dam

at Olumbagh

A.Rockfill dam Rte Unit Amountinm.Afs

1.0 m. m3 stripping 100 m3 100.0foundat on

.. 4 m. m," zone 1

(impe3rvious) 150 " 210.01.3 m.m zone 2

(filtgrs) 210 " 273.06.0 U6 M) zone 3

(rock) 210 " 1260.0

It

r, It

It

It

r,,(01S4.1"°

grout curtainincluding grouting

L. S. De watering

L. S. coffer dams

12-6

Rate Unit

2400..

7Amount

Afs

9.6 m.Afs

12.4"

35.0Total direct costs 1900.00

Add 400 towards indirect 7.4r1.0

costs

n

260.0 m. Afs

B.SpillwayRate Un'e t Amountin m.Afs

5.0 m.m3 excavation 100 m 500.0

15,000 m drilling,grouting,anchoring,etc.1200 m 18.0

64000 m grouting ' in

foundation and abutment 1600 m 9.6

50,000 m °concrete for piers,abutment,wings ,crest,floor,etc 3

3000 m 150.0

1.0 in kgs reinforcing steel at0. 5°f in abutments ,piers , and

110 in floor,crest,etc. 50 kg 50.0

0.1 m.kgs structural steel 60 ," 6.0

1800 m2 gates & hoists 100,000 m2 180.0(15x10x12)Lining the spillway channel L. x.251.4

Other miscellaneous items at 5% L.S. 35.0

Total direct cost

Add indirect cost at 401,(apn.)

Total

1200.0

t80.0_.._

1680.0 m. Afs

12 -7

C. Diversion tunnels,control shaft

sloping tunnel and approach and

exit ort.s

76"

1. diversion tunnels 750 m Af s

2. control shafts300

3. sloping power /irrigation tunnels 100 " "

4. approach and exit cut

Total direct cost

Add indirect cost at 40%

,t ,r

1200 m. Afs

_._ 500.0 ...

Total 1700.0 m. Afs

Total cost of dam and related works

Drym

Spillway

Diversion /outlet tunnels

Compensation for the cultivable lands coming

under reservoir submersion

2000 hectares at 100,000 Afs per hectare

Rehabilitation of displaced families

(assumed 500 families at 20,000 Afs

per family)

2660 m. Afs

1680 It I,

1700 m. Afs

200 m. Afs

10. m. Afs

Total 6250 m. Afs

128

PC)WER

7C

1. Power generation at Kajakai,transmissionto load centres and distribution system

a) Power house, including power plant

auxiliary equipment,switchyard,i4,,,o4>

transformers, etc. ,at Kajakai dam

b)Transmission lines:

3000 m. Afs

i. Kajakai to Kandahar 400

ii. Kandahar to Kabul via Ghazni 3000

iii. Kajakai to Herat

c) Distribution system

i. Kabul

2500

600

5900 m. Afs

ii. Logar 200

iii. Ghazni 200

iv. Kandahar 200

v. Herat 200 = 1400 m. Afs

Total 10300 m. Afs

A

2. Power house, power plant and transmissionlines at upper Kajakai dam

a)iPower house 80 m x 22 m 1600 m2 at50,000 _.Afs per m

ii*. Penstocks,regulating rangemen ....

b)Power plant including all auxiliary

80mAfs22 m. Afy -- }

equipment 90,000 kws at 22;Afs /kw2025 m.

-c)Switchyard and transformers90,000 kws at 2700Af s /kw

d)Transmissi.on lines & sub-stations220 KV(from Olumbagh to Kajakai

(2 lines of 110 KV)

Af s

243 m. Af s

m.Afs

3304 = 2700 m. Afs

4/

13 -1

CHAPTER 13

'7 7

PHASED PROGRAMME OF IMPLEMENTATION ix

i!Q, r.ai, .i)

Out of the total proposed irrigation potential of 310,000 hectares

in the Helmand basin-, nearly 77,000 hectares are getting assured and timely

irrigation supplies in the upper Hélinand valley. Area development in the

upper valley is generally being undertaken in a systematic way and on lates

practices. This has in fact served to create confidence in the people that

they could take their agricultural economy to commanding heights, if they

are assured of timely and adequate quantities of water, agricultural inputs

and infrastructural facilities. An extent of about 30,000 hectares of land ---

in the above existing irrigation system lacks adequate irrigation and

drainage facilities and needs certain improvements and modernisation.

The necessary improvements are therefore proposed to be carried out

;. ..!e,, Vte isubstantially in the first four years of the lan. -- u --, --)

9 i

-t - 70,1.1$ . /c'c.. r/' ,,, ti +,°" (......:;--- .J jF

There are vast potentially irrigable areas available in the lower

valley. They can be brought under irrigated agriculture, if only measures

are taken to abai.e the ravages of floods and inundation and irrigation,

drainage and other related facilities are created. The living coed 4'

in the area are minimal. Hence development of this lower valley needs

greater attention, so that its economy may catch up with the rest of the

region. The present Kajakai dam whose gross storage capacity is being

increased to 2720 million cubic meters, would serve to meet the needs of

development of about 1OOE,,,Z;,jectares of land in addition to the existing

irrigation. What is, therefore, needed to be executed first are the

13 -2

flood diversion works at Kamal Khan, completion of the Lashkary canal scheme

which is under execution, linkdñg it up with the right bank canal taking off

from Kemal Khan flood diversion dam, constructing the two diversion dams,

one at Khwabgah and the other at Sikhsar, the irrigation distribution system

under the Sikhsar diversion dam and parts of the system under Khwabgah

diversion dam to bring in assured irrigation benefits to those areas which

are traditionally under irrigated farming. It is therefore proposed to take

up the above works first and complete the same substantially by end of fourth

year of the plan. ,

In the upper Helmand valley, the Garmab -Seraj area is considered to

have great potentialities for rapid development and so it is proposed to take

up the construction of G armab diversion dam, the irrigation distribution system

and the preparation of the irrigable lands in the second year of the plan and

complete the same by end of sixth year. The other irrigation works contem-

plated then follow as generally indicated in Table 13 - 1.

The programme contemplates a more or less uniform rate of land

development during the period of construction activity, but fixing priori-

ties for the more needy areas and areas that could be developed quickly.

Similarly the phasing of construction activity aims at the possibility of

making proper use of construction equipment, technical know -how, construc-

tion experience, by way of staggering the construction of works of similar

nature such as diversion dams etc., to the extent practicable.

By the time considerable part of irrigation potential proposed develops,

it is considered neceaaary to complete the upper Kajakai dam and possibly

the other two, one on Arghandab and the other on Musa tala, so that all the

13 -3

reservoirs could be operated in the best manner possible to optimise the

benefits. With this in view, it is proposed to take up the construction

of upper Kajakai dam in the fourth year of the plan and complete it by end

of nineth year. Similarly the construction of the other two dams could

start from the sixth year and be completed by end of tenth year of the plan.?i

The need for stepping up power generation at Kajakai and its

transmission in the first five years is dealt with in earlier chapter on

power potential. Hence it is programmed to take up the works relating to

additional power generation at Kajakai, its transmission and distribution

at the load centres such as Kandahar, Herat, Kabul etc., from the first

year of the plan and complete in all respects by end of fifth year. It

is anticipated that the entire power at Kajakai would be fully utilised by

the 10tr of the plan and there would be demand for additional power.

Hence the works relating to power generation at upper Kajakai (Olumbagh)

dam and its transmission to Kajakai are proposed to be completed by tenth

year of the plan to meet the growing power demands.

It is programmed to bring the plan to fruition in 10 years. The

work involved for the successful completion of the project is stupendous

and needs concerted action in all directions and there should be no

h sicalconstraint on availability of finances, management, /and man-power resources.;

The phased programme of expenditure for implementation is shown

in Table 13 - 1. The year -wise programme of expenditure will be as

follows

13 -4

Fa

Irrigationm. Af s

Powerm. Af s

Totalm. Afs

F±3, year 2000 1300 3300

Séc nd.; year 3330 2500 5530

Third year 3200 3000 6200

Fourth year 3700 2500 6200

Fifth year 3500 1000 4800

Sixth year 3500 300 4100

Seventh year 3500 600 4100

Eighth year 3500 600 4100

Nineth year 2970 600 3570,

Tenth year 2200 600 280?

TOTAL 32,000 13,000 45,000

13 -5

PHASING OF CONSTRUCTION ACTIVITY AND LAND DEVELOPMENT FOR IRRIGATION

S.

Name of work f

Estima-

No.

Activity

ted cost

in

m. Afs

1.i.Improvements to the

existing irrigation

system in upper nelmand

1000

.350

250

200

150

50

ii.Area of irrigable land

Table 13 - 1

Sheet - i

Area

1st

2nd

4th

5th

6th

7th

8th

9th

10th 11th

propo-

year

year

year

year

year

year year

year

year year year Remarks

sed for

irriga -

tion

m.Afs

m.Afs

m.Afs

m.Afs m.Afs m.Afs

m.Afs m.Afs m.Afs m.Afs m. Afs

Hectares

2a)KamalKhan Flood divers -

sion dam and related

900

works

b)i.Right Bank Canal

30,0

00(4

000)

(600

0)(7

500)

(800

0)(4

500)

250

409

250

works

.1600

,m-4,

650

'4Q0'i

150

ii.Area of irrigable land

c) i. Lashkary canal

ii. Area of irrigable land

d) i. Left Bank canal

ii. Area of irrigable land

3.a)Sikhsar diversion dam

b) i. Canal works

ii.Area of irrigable land

4.a)Khwabgah diversion dam

b)i. Canal works

ii.Area of irrigable land

5.a)Garmab diversion dam

b) Canal works

ii.Area of irrigable land

'

20,000

1472.4 - .- ÷,.up!

1814400

3240

40,500

6414J_4400)

.4/2

500

(4400)

(7000)

4 _

'

;(7500500

(7000)

270

50

150

2120

a,

`'428

492

570

26,500

(5000)

(70Q0)

(7000)

270

50.

150

70

4128

,,.,

228

300

51,600

(.600)

(20oo)

410

170

240

2640

`-

340

600

33,000

(3000)

(4000)

1500)

240

_(3000)

500

(4500)

630

---

(7500)

500

500

500 500

500

(7000)(8000)(6000)(600Ó)(6000)

400

400

500

500

600

600

60O.

(5000) (6000) (7000)(7000)(8000)(8000){7000)

,ébo

600

300

(90) (11000)(6000)

Figures

in bra -

ckets

indicate

the land

area to

be

developed

for irri-

gation

1 U.S.

dollar

=57 Afs

S.

Name of work f

Esti-

No.

Activity

mated

cost

> J m. Afs

'6.a)Khanneshin diversion

.dam

340

b)1. Canal works

1360

ii.frea

of irrigable

17,000

an

7.a)Rodbar diversion dam

340

b)i.Canal works

1360

ii.Area of irrigable

'

land

8.a)Taghaz diversion dam

410

b)i.Canal works

720

ii.Area of irrigable

land

Total million Afs

22580

Total Hectares ty

i!i.

y

1805

0

Area

1st

2nd

3rd

propo-

year

year

year

sed

m.Afs

for irr-

m.Afs

m.Afs

gation

hectare

220,000

2000

3330

3200

2370

1550

1300

1000

1100

1156

1100

Sheet 2

4th

5th

6th

7th -! nth

9th

10th

11th

year year

year year

year

year

year

year Remarks

m.Afs m.Afs m.Afs

hi.Afs

m.Afs m.Afs

m.Afs m.Afs

9. Upper Kajakai dam

6250

(10.Dams on Arghandab and

Musa Qala rivers

3170

Total(Irrigation)

32000

VO 41.Power at Kajakai dam

10300

,.(generation & transmi-

ssion)

12. Power at upper Kajakai dam

(generation & transmiss-

2700

ion)

Total (Power)

13000

Total(Irrigation + Power)45000

17,0

00

!k.

29,000

A3

2000

3330

3200

2700

2020

1900

1800

170

170

160

300

300

300

300

(1000) (4000)(4000) (4000) (4000)

170

170

130

330

(1000) (4000)

300

(400

0)

170

300

(400

0)

240

300

(400

0)

130

290

300

(1000)

(4000)

(4000)

2000

1930

1700

233,000 (14000)(25000)(275D0) (27000) (25500)(250 (23000)(23000)

+ 3

0 ,0

00+4000) +6000) +7500)

+8000)

+4500)

1000- ,:1780

1400

1000

50

2000

3330

1300

2500

1

,.....

7'-

500

700

750

3200

3700

3800

3800

3500

3500

3000

2500

10008._

329

__

___600

__.600

1120

2500

3000

2500

1000

300

600

600

600

600

3300

5830

6200

620C

4800

4100

4100 4100

3570

2850

(22000)(21000)

720

500

2970

2200

Figures

in bra-

ckets

indicate

the land

area to

be deve-

loped

for

irriga-

tion

1 U.S.

dollar

=57 Afs

14 -1

CHAPTER 14

ECONOMIC EVALUATION

F

14.1 Appraisal

The project consists of three components, irrigation, hydro power

and flood control. However the benefits accruing from flood control are

not quantified for purpose of this pre-feasibility study, while the

costs of flood diversion works at Kamal Khan and all three storages to

be constructed are taken into account. Similarly the cost of storages

is not apportioned to the three facilities separately for evaluating the

benefits and economic viability of wach component. The economic viability

of the entire plan is assessed from two considerations

1) benefit -cost ratio indicating the relation between the

total investment and the benefits that accrue after the

project is completed, and

2) internal rate of return.

The plan of development including construction of capital works is

assumed to be completed in 11 years. It is proposed to parry out improve-

ments to the irrigation and drainage network for an area of about 30,000

hectares out of th .- tt- t.ng irrigation in the upper

Helmand 2,43 -± ,the,, benefits that accrue on account of the

improvementa._.are taken into consideration. The existing irrigation of

about 55,000 hectares of land in the lower Helmand valley which is not

at present assured Of unfailing supplies will be stabilised and the

benefits from the project will accrue to these lands.. The rate of

irrigation and agricultural development is indicated in Table 13 -1

14-2

under Chapter 13 on Phased Programme of Implementatio .t

iccThe existing cropping pattern over the 5 0 ,,,hectares of land,

the average yields, the average production costs and the net revenue are

given in Tables 14 -1 and 14 -2. After completion of the project and area

development, assured and regulated irrigation supplies will be available,

improved seeds, fertilizers etc., and other infrastructural facilities

will be introduced. Hence the crop yields should improve considerably.

Tables 14 -4 and 14 -5 gire the cropping pattern, intensity of irrigation,

the yields, the production costs and the net revenue after the project.

Similar data in respect of the 30,000 hectares of land for which irrigation

drainage and other facilities are to be improved, is given in the Tables

14 -6, 14 -7, 14-e and 14 -9.

It is programed to complete the installation of additional hydro-

power generating units at Kajakai and erection of transmission lines to

various load receiving centres and distribution network by the end of

y`" fifth dear. The first stage of power benefits will therefore start

accruing from the sixth year. When the other power stations on Hari Rud,

Farah Rud and in the north are completed, commissioned and interconnected

with Kajakai power by forming a national grid, the transmission lines now

proposed to be laid will serve to transmit the loads from various generating

stations in a bi- directional way. Hence the cost of transmission lines is

to be apportioned ultimately to more than Kajakai system. For the present,

the entire cost of transmission is however proposed to be charged to

this project.

14 -3 7"

The power at the upper Kajakai dan is programmed to be made

available in the 11th year. Benefits from this will therefore accrue

from llt ear. -'i /1 `.

tic c. >,

The benefit -cost ratio for the entire project (irrigation and

power) is worked out. Estimated cost of one KWH of hydro -electric

energy at load centres is worked out, taking the annual costs of

power generation and transmission and the total energy that could be

generated and consumed annually.

The annual costs for irrigation and power are worked out on

the following basis :

i) the total investment costs at the end of the construction

and development activity are arrived at by adding the

interest that accrues during the period of activity at

2 interest;

ii) the cost of annual maintenance and operation of the

irrigation and power components of the project is taken

as 1`% of the investment cost;

iii) amortization of the investment is based on a capital recovery

factor corresponding to a 50 year life and interest rate of 2-14

in respect of irrigation works and storages. In the case of

hydro -power component it is based on a recovery factor correspond..

ing to a 35 year life and interest rate of 2. Provision for

renewals and replacements of electrical plant etc. is also made.

14 -4

14.2 Benefit cost ratio

Present net revenue from crop production is estimated to be

133.00 + 166.43 = 299.43 M. Afs- (Tables 14-2 and 14 -7). Future net revenue

from crop production, after the completion of the project is assessed

to be 4800.00 + 735.15 = 5535.155t m. Afs (Tables 14 -5 and 14 -9).

Irrigation benefits due to/project = 5535.15 - 299.43 = 5235.72 M. Afs

Total units of energy that can be

generated at Kajakai and utilised = 600 x 106 KIREs.

Allowing 10% losses in transmission

and distribution,net energy = 540 x 106 KuHs.

Total units of energy that can be generated

at upper Kajakai dam and utilised = 250 x 106 KWHs

Allowing 10% losess in transmission

and distribution, net energy = 225 x 106 KWHs

Total net energy = 540 x 106 + 225 x 146 =765 x 106

Assuming that the selling rate of electrical

energy in the region is 1.3 Afs per rill

Gross revenue from power = 765 x 106 x 1.3 = 994.5 m. Afs

Allowing 10% towards administration

and collection charges, net revenue

from power = 895.05 million Afghanis

14-5

Construction Costs

Irrigationm. Afs

Powerm.Afs

Cost 32,000 13,000

Interest during construction 5,44 2,830

Total investment 37,644 15,830

Annual costs m. Afs

Irrizätión

i. Maintenance and operation1% of the total cost of37,644 m.

,

Als = ------ 376.44

ii. Amortization of investmentat 2 interest in 50 yearswith capital recoveryf actor of 0.0353 0.0353 x 37644 = 1328.83

TOTAL .---, 1705.27

=

Power

i. Maintenance and operationat 1% of the total cost '

of 15830 m. Als = 158.30

ii. Amortization of investmentfor plant equipment lifeof 35ars with 2i%rate of interest andcost of replacementand renewals

Capital recovery factor = 0.0432

Coat of replacement factor = 0.0038

7 S 0.0470

0.0470 x 15830 744.01

TOTAL 902.31

14-6

Total annual costs m. Afs

i. Irrigation 1705.27

ii. Power 902.31

Total Annual Cost 2607.58

Total annual benefits

i. Irrigation

ii. Power

5235.72

895.05

Total Annual Benefits 6130.77

Benefit -cost ratio for irrigation and power

combined 6130.222607..58

Estimated cost of power per KWH

at load receiving centres

= 2.34 or say 2.

6= 902.31 x 10765.00 x 106

ek,A1 6»ei,

= 1..18or say 1.2Afs

14.3 Internal rate of return

The internal rate of return is shown in Table 14 -10. The

internal rate of return comes to 10.5 .

141

Table 14 - 1

PRESENT CHOP PRODUCTION AND GROSS REVENUE

S.No Crops Area in Yield in Total pro - Farm gate Total gross

hectares tons per duction price revenue inhectare in tons Afs/ton Af s

1 Wheat 7. 40,000

2 Barley 5,500

3 Cotton , V'' 100

4 Sorghum r', ?; ` 4,000

5 ',Corn pi 50

6 Melons ; m

? 4,000

7

8

9

10

Mung beans M t 50

Vegetables .9! 500

Tree fruits . 7.2' 400

Grapes 400

Total 55,000

0.75 30,000 6,000 180,000

0.70 3,850 5,000 19,25

0.67 67 14,000 0.94

1.00 4,000 2,800 11.20

1.00 50 4,700 0.23.

4.00 16,000 1,750 28.00

0.50 25 5,600 0.14

5.00 2,500 2,300 5.75

3.00 1 ,200 5,900 7.08

3.50 1,400 5,900 8.26

260.84

yq

m. Af s

14-5

Table 14 - 2

PRESENT PRODUCTION COSTS

S.No Crop Area inhectares

Production costAfs /hectare

Total productioncost in m. Afs

1 Wheat 40,000 2,100 84,00

2 Barley 5,500 1,900 10.45

3 Cotton 100 1,400 0.14

4 Sorghum 4,500 1,500 6.00

5 Corn 50 1,500 0.08

6 Melons 4,000 2,500 10.00

7 Mung beans 50 1,500 0.07

8 Vegetables 500 1,400 0.70

9 Tree fruits 400 3,500 1.40

10 Grapes 400 500 0.20

Total 55,E 113.04

Net production value

(Net revenue)

Since the entire 55,000 hectares

260.84 - 113.04

= 147.81 million Afs

are not being successfifily

irrigated every year, the net production value may be taken

as 90% of 147.81 m. Afs = 133.03 or say 133 million Afghanis

14 -9

S.No

Table 14 - 3

CROPPED AREA AFTER COMPLETION OF PROJECT

lyts,,

Crop Upper Helmand Lower'Helmand Total14 intensity 120% intensity hectares

hectares hectares

1 ?meat. 13,200 83 ,200

2 Barley 1,650 10,000 11,650

3 Corn 8,250 50,000 58,250

4 Mung beans 6,600 32,000 38,600

5 Cotton 9,900 48,000 57,900

6 Vegetables 660 2,000 2,660

7 Vine -yards 1,320 8,000 9,320

8 Tree fruits 1,320 8,000 9,320

9 Melons 330 2,000 2,330

10 Alfalfa 1,650 8,000 9,650

11 Perennial grass 1,320 '2,000 3,320

Total 46,200 240,000 2 .86,o00

(Note: This does not include the already developed area of

77,000 hectares of land in the upper Helmand valley).

-

' u 3

14 -10

Table 14 - 4

FUTURE CROP PRODUCTION AND GROSS REVENUE

S.No Crops Area inhectares

Yield inton perhectare

Total pro-duction in

tons

Farm gateprice

Afs / tons

Total grossrevenue in

million Afs.

Wheat 814200--¡"1_/ z Barley - 11,650

3.00

2.60

249,600

30,280

6,000

5,000

1497.6o

151.45

3 Corn 58,250 4.00 233,000 4,700 1095.10

4 Mung beans 38,600 1.20 46,320 5,600 259.39

5 Cotton 57,900 2.50 144,750 14,000 2026.5o

6 Vegetables 2,660 10.00 26,600 2,300 61.18

7 Vine yards 9,320 10.00 93,200 5,900 549.88

8 Tree fruits 9,320 6.00 55,920 5,900 329.93

(4:Melons 2,330

Alfalfa 9,650

12.00

5.00

27,960

48,250

1,750

2,000

48.93

96.50

11 Perennialgrass 3,320

Total 286,200 6116.46

Cfr. J C-_a

14 -11

1

FUTURE PRODUCTION COSTS

Table 14 - 5

S.No Crop Area in Production cost Total production

hectares Afs /per hectare cost in m. Afs

1 Wheat 83,200 4,200 349.44

2 Barley 11,¢50 3,800 44.27

3 Corn 58,250 2,100 122.32

4 Mung beans 38,60o 2,400 92.64

5 Cotton 57 ,900 4,100 ... 237.39

6 Vegetables 2,660 5,800 15.43

7 Vine yards 9,320 100000 93.20

8 Tree fruits 9,320 7,100 66.17

9 Melons 2,330 6 ,000 13.98

10 Alfalfa 9,650 3,000 28.95

11 Perennialgrass 3,320

Total 286,200 ha

Net production value

(Net revenue)

6116.46 - 1063.79

= 5052.67 million Afghanis

Since these benefits accrue in 9 out of 10 years, the average

annual benefits may be taken as 95% of 5052.67 m. Afssay

= 4800.04 or/4800 m. Afs

14.12

Table 14 - 6

Upper Helmand valley(Existing irrigated area requirirg

improver:rPRESENT CROP PRODUCTION AND

GROSS REVENUE

i

Area in Total pro -hectares duction in

tons

S.No. Crop Yield intons perhectare

Farm gateprice

Afs /ton

9f

Total area 0,000hectares

Total grodsrevenue inmillion Afs

1

2

Wheat 60%

Barley 2%

18,000

600

1.2

0.8

21,600

480

6,000

5,000

129.60

2.40

3 Cotton 18% 5,400 0.5 2,700 14,000 37.804 Corn 13% 3,900 1.3 5,070 4,700 23.83

5 Melons 5% 1,500 5.0 7,500 1,750 13.126 Mung beans2% 600 0.6 360 5,600 2.02

7 Vegetables 0.2% 60 6.0 360 2,300 0.83

8 Tree fruits 1% 300 5.0 1,500 5,900 8.859 Grapes 0.5% 150 7.0 1.050 5,900 6.19

Total 30,510 ha224.64 m. Afs

14 -13

q5

Table 14 - 7

Upper Helmand valley(Existing irrigated area requiring improvements)

PRESENT PRODUCTION COSTS

S.No Crop Area inhectares

Production cost Total production costAfs /hectare in million Afs

1 Wheat 18,000 2,100 37.80

2 Barley 600 1,900 1.14

3 Cotton 5,400 1,400 7.56

4 Corn 3,900 1,500 5.85

5 Melons 1,500 2,500 3.756 Mung beans 600 1,500 .90

7 Vegetables 60 1,400 .08

8 Tree fruits 300 3,500 1.05

9 Grapes 150 500 0.08

Total 30,510 58.21

Net value of production 224.64 - 58.21

(Net revenue)

= 166.43 m. Afs

14 -14 lTable 14 - 8

Upper Helmand valley

(Existing irrigated art. requiring improve-ments)

FUTURE CROP PRODUCTION AND GROSS REVENUE

S.No ,Crops Area in Yields in Total pro-

hectares tons /hectare duction intons

Farm gatepriceAfs /ton

Totalgrossrevenuein m.Afs

1 Wheat 12,000 3.00 36,000 6,000 216.00

2 Barley 1,500 2.60 3,900 5,000 19.50

3 Corn 7,500 4.00 30,000 4,700 141.0o

4 Mung beans 6,000 1.20 7,200 5,600 40.32

5 Cotton 9,000 2.50 22,500 14,600 315.00

6 Vegetables 600 10.00 6,000 2,300 13.80

7 Vine yards 1,200 10.00 12,000 5,900 70.80

8 Tree fruits 1,200 6.00 7,200 5,900 42.48

9 Melons 300 12.00 3,600 1,790 6.30

10 Alfalfa /clover 2,700 5.00 13,500 2,000 27.00

Total 42,000 892.20 m.Afs

40s/ 3 e. ?

14-15

q7

Table 14 - 9

Upper Helmand valley

(Existing irrigated area requiring improvements)

FUTURE PRODUCTION COSTS

S.No Crop Area inhectares

Production costAfs /hectare

Total production,cost in m..Afs

i Wheat 120800 4,200 50.40

2 Barley 1,500 3,800 5.,70

3 Corn 7,500 2,100 15.75

4 Mung beans 6,000 2,400 14.40

5 Cotton 9,000 4,100 36.90

6 Vegetables 600 5,800 3.48

7 Mine yards 1,200 10,000 12..00

8 Tree fruits 1,200 7,100 8..52

9 Melons 300 6,000 1.:80

10 Alfalfa /clover 2,700 3,000 8.40

Total 157.05 m: Afs

Net production value = 892.20 - 157.05

(Net revenue) = 735.15 m. Afs--.._.

41,..

Yea

r

Col.1

1 2 3 5 6 7 8 9 10

11 12

13

14

1516

17

18

1920

21

Yearly in-

vestment

(I)

m.

Afs

Value of

Exi

stin

gpr

oduc

-'

value of

tion

production

m.Afs

m.Afs

co1.2

:col.2

,3300

5830

6200

6200

4800

4100

4100

4100

3570

2800

.-.

f3`,

299-

477

971

1611

2295

2959.

3508

3993

4458

4898

5328

5535

14 -

16

INTERNAL RATE OF RETURN

Incremental

value added

due to

irrigation

m.Afs

co1.5

299

299

'4:

178

199

672

299

>\

1312

299 -1%_,

1996

299

c G.K2660

299 "tt

"s3209

299

-.2299

t3694

4159

299

299

299

It tt

:1'),

4599

,4

;.5P29

5236

5236

5236

Jus.

j71.

-Ev4

'

J 1

11

Incremental Total Operation Net in-

value added incre- & maintenu aremental

due to po- mental ance

benefits

wer

value

m.Afs

added

m.Afs

m.Afs

coi.'

co1.7

col.8.

- 178

91-

,-t1>

672

153

',,1312

215

aa),

3 ,,,

,i196

626

363

2 ^;

r7"

3292

304-

632

3841

345

632

4326

386

632 "

4791

422

632

5231

450

895

5924

450

11 it 11 It

6131

450

6131

450

6131

450

6131

450

Table 14 - 10

Sheet 1

AVI

(Av I)

(col. 9-

r=12

°ß(Av)

in.Afs

col.9

87

519

col.2)

m.Afs

co1.10

-3300

-5743

-5681

1097

-5103

1703

-309

72988

-1112

3496

- 604

3940

- 160

4369

+ 799

4781

+1981

5474

+5474

5681

+5681

5681

+ 5681

5681

+5681

5681

+5681

x(1 +r)-t

with

r =11%

colli

co1.12

-2940

-2970

-4570

-4650

-4060

-4150

-3240

-3370

-176

0-1

835

564

- 595

- 272

- 290

-68

-69

+ 288

+ 312

+ 640

+ 700

+1580

+1740

+1460

+1620

+1300

+1460

+1160

+ 1320

+1040

+1180

+ 932

+1070

+ 830

+ 960

+ 740

+ 870

+ 660

+ 805

+ 590

+ 705

+ 525

+ 637

Col. 1

Col.2

Col. 3

Col.4

Col.5

co1.6

co1l7

col.8

co1.9

co1.10

co1.11

co1.12

Sheet 2

Av -I

r=14

22

23242526

27

28 29

30

31 32

33 34

35

36

3738

3940

4150

(Av - I) (l+r)-t

The internal rate of re

5681

470

+1+

572

424

526

376

465

334

417

298

378

2E8

340

240

307

214

277

+ 192

248

+ 1

7122

4+

153

202

+ 1

3518

3+ 121

+ 164

+ 109

147

+98

+ 134

+86

+ 121

+77

+ 109

+69

+98

+62

+87

+54

+79

+19

+34

-1467

+1014

151

CHAPTER 15

CONCLUSIONS AND RECOMMENDATIONS

15.1 Conclusions

The new Regime of Afghanistan have launched on a number of

development plans to improve the Nation's economy and raise the standards

of living. In accordance with the above objectives this report is prepared

outlining an integrated development of the Helmand irrigation and power

potential in about gleven :veaxs commencing from theyear 125.4. It is

based on the data and information contained in the numerous studies made

so far.

i. The Helmand valley is endowed with natural resources for the

economic development of the area, if only they are exploited in a planned

way. There is land potential of about 51$,000 hectares, with large areas

having irrigation potentialities. Only 77,000 hectares of land is presently

being irrigated in the upper Helmand valley with regulated releases from

Kajakai reservoir and a network of irrigation system. Under the present

plan assured irrigation benefits could be extended to an additional extent

of about 33,000 hectares in the Helmand Province and an area of 200,000

hectares of land in the Helmand and Nimruz provinces without shutting the

potentialities of bringing under irrigation larger areas at a later date.

The presently proposed area of 200,000 hectares in the lower valley includes

the 55,000 hectares of land now being irrigated most of which does not get

assured Supplies.

ii. It is equally essential to diversify the development activities

simultaneously in more than one sector, to make the region self-reliant

and to create self generating economy. Industrialisation is one of the most

15 -2 fa 1

important facets of economic development. The Helmand valley and other

areas around Kandahar, Kabul, Ghazni and Herat abound in other untapped

natural resources which could be exploited to great advantage. For this

purpose a number of plans are being finalised for developing varied

industries in the region in the next few years. But the essential pre-

requisite for industrial development is electric power which has to be

made available economically and in the quickeat possible time. It is

therefore most relevant in this context that the power potential at Kajakai

is fully exploited by installing additional hydro - generating units, laying

the transmission lines to load centres such as Kandahar, Herat, Kabul, etc.,

and laying of the distribution network. An additional power of 116.5 J .Ws

may therefore be installed and transmission and distribution network completed

3in the first five years of the plan along with the proposed irrigation

development.rarrn,vv. -. &,, t.P

iii. Vast cultivable commanded areas, at times exceeding 10 hec-

tares in the lower Helmand valley particularly in the Chakhansur area are

subject to constant ravages of floods and inundation. Even after the

creation of additional storages upstream, these areas will be subjected to

rigours of the frequency and intensity of floods in terms of volume as well

as peaks. They could be reclaimed and brought under beneficial use only

by diverting the excessive floodwaters of Helmand river into Gaudi- Zirreh

at Kamal Khan by constructing a flood diversion dam and related works. The

Kamal Khan dam is also located at the most suitable place so as to extend

benefits to irrigable areas under its command. The dam has also power

potential. This complex of works will also provide for two important

bridges in this area.

.%es c.,.' /3 !/

J

15-3 102

iv. The storage reservoirs to be constructed should have adequate

live storage capacity not only to meet the irrigation needs of the extents

nbw proposed but should also be sufficient to meet the future needs of

possible extension of irrigated agriculture. Adequate storage to optimise

the power benefits will also be required without conflict of interests

between power and irrigation. It will also be necessary to provide adequate

wry over /flopd storag9. 'An aggregate total. -of aboutj5,0004nillion cubicpp {i- ; I ,etisI e'-^

Meters of lifë storage including that of Kajdlcai will, therefore, have to

be considered subject to confirmation by feasibility studies of the storage

dams.

v. Pre feasibility studies have indicated that a storage dam near

Olumbagh on Helmand river upstream of Kajakai could be constructed, creating=

a gross storage of 1,75e million cubic meters. The possibility of inereas-

ling the storage capacity of this dam by increasing its height will have to

4 'jf3'exámined at the time of feasibility studies. Similarly it is considered

feasible to construct a storage dam on Arghandab river and possibly a third

on Musa Qala to fulfil the needs referred to in above.

vi. The proposed dam at Olumbagh will in addition create a firm

power potential of nearl .IM.Ws. the

installed capacity bein 9. M fig. This will meet the additional power

demands of the region by the time the power generated at Kajakai is utilised.

vii. The integrated operation of Kajakai reservoir and the proposed

upper Kajakai reservoir along with those proposed on Musa Qala and Arghandab

rivers will be needed to optimise the overall benefits.

viii.. A diversion dam at Garmab along with irrigation and drainage=

network and land levelling /shaping will extend irrigation benefits to a

large proportion of the 33,000 hectares in the upper Helmand valley.

f

15 -4

ix. The existing irrigation network in the upper Helmand valley needs

certain improvements by way of_providing adequate drainage and irrigation

facilities, etc. These improvements will modernise the system.

3

. '" Four diversion dams one each at Khanneshin, Taghaz, Khwabgah and ¡Sikhsar and a fifth one at Rodbar along with an irrigation and drainage )

network and land levelling /shaping etc., will extend irrigation benefits

to about 200.000 hectares.

xi. Agricultural development of the irrigated area needs to be

undertaken simultaneously with the creation of irrigation potential by way

of providing all the necessary infrastructural facilities such as fertilizer

and other inputs, transport facilities, ware -housing, marketing centres,

research and demonstration farms etc.

xii. The estimated cost of development of irrigation and power is

45,000 million Afghanis (790 million U.S. dollars) out of which the power

luSi rind

component is 13,000 million Afghanis (22S million U. S. dollars). The plan

is expected to be completed in 11 years.

xiii. The benefit -cost ratio for irrigation and power combined will

be 2.3 based on the given rate of interest and the internal rate of return

t will be 10.5%. Flood control benefits that accrue on account of the cons -

truction of Kamal Khan flood diversion dam and storages upstream are not

however taken into consideration for economic evaluation. The entire cost

of transmission lines which in the ultimate stage serve not only the two

Kajakai power stations but also others, is charged to this project. If

the economic evaluation is done taking these factors into consideration,

the benefit -cost ratio and the internal rate of return will be higher.

15-5 104'

xiv. The plan of development as envisaged above will increase

agricultural production and make available J. rge blocks of electric power

for the establishment of agro-based, animal bye product and other industries

in the area. This will infuse confidence in the people of the area for a

better future.

15.2 Recommendations

It is recommended that the following activities which constitute

major elements of the plan for the integrated development of the Helmand

basin are to be undertaken in the order of sequence indicated for fulfill-

ing the objectives :

i. The construction of power house and installing of additional

power units with a capacity of 116.5 M.Ws. at Kajakai, laying of tram.-

mission lines to Herat and Kabul and related distribution network are to be14.0-1 6444

taken up and completed in the first five years of the plan.'2

ii. The Kamal Khan flood diversion dam along with other related

works which are thoroughly studied are to be executed in the initial stages

of the plan. The dam and related works are to be so constructed as to maxi-

mise the irrigation and power benefits.

iii. The Lashkary canal scheme now under execution should be completed

in all respects in the first three years of the plan and the agricultural

development of the area should be completed without time lag. This will

serve as a pilot scheme for the overall irrigation and agricultural develop-

ment in. the valley.

iv. Detailed planning and engineering for the irrigation and agri-

cultural development of about 200,000 hectares in the lower Helmand valley

and about 33,000 hectares in the upper Helmand valley should be undertaken.

'IcA ti

15 -6

v. Improvements to the existing irrigation and drainage networks

covering about 30,000 hectares out of 77,000 hectares in the upper Helmand

valley are to be taken up and completed.

vi. Feasibility studies for the upper Kajakai dam (Olumbagh dam)

including power, the dam on Arghandab river and a third dam on Musa Qala

should be made.

vii. Construction of diversion dam at Garmab, Khanneshin, Taghaz,

Rodbar, -Khwabgah and Sikhsar along with the irrigation`añd drainage networks,

land levelling etc., is to be taken up and completed by end of tenth year

btoot :L 'of the plan.

viii. The upper Kajakai dam is to be taken up fay 9,mao.&tIorî in the

fough year of the plan and completed in the rilet-hiear. of plan i.e. by

the time major part of irrigation works referred to in vii above are

completed.

ix. The dams on Musa Qala and Arghandab rivers are to be taken up

for execution and completed. 7

x. The hydro power plant at upper Kajakai dam is to be installed

and the transmission line to Kajakai dam constructed by end of 1,Qth year

of the plan.

xi. The agricultural development of the entire irrigated area is to

be completed by the time irrigation potential is created without time lag.

A chart showing the phasing of activities and expenditure is

attached.

The sudcessful completion of the various works referred to above

will usher in the'following benefits c

i. Firm power of 120 M.Its at 0.5 load factor at Kajakai dam,

the installed capacity being 150 M.Ws;

ii. Immunity to the lands to an extent of about 100,000 hectares

15 -7 G

in the lower Helmand valley against flooding and inundation;

iii. Irrigated agriculture over 233,000 hectares of land in addition

to the existing 77,000 hectares of land in the upper Helmand

valley;

iv. Additional firm power of 60 l.Ws at 0.5 load factor at upper

Kajakai dam, the installed capacity being 90 M.Ws.

1° 9° 3064° 65° 66 67°

33

3 2°

31°

30

29

33

KAJAKAI DAMKAJAKAI

HAMUNSA BARI

QPti

/ I NAD-I-ALMJ ( AREA \GRAN-I-A JIRY `` NAD-LI

i

Q I MARA !. / T

SIKHSAR AREA MARJA AREA joO:(t/ SÁRgALAN IE 1-i/`'%'`/ SHAMA

,

.. , .

I.: CHAKHANSUR } f DARWESHANAREA

I BOGHRAARE4-

32°

ASHK ARG AMKANDAHAR

ST

SERAJ AREADORiRu

31°

TARAKUAREA

KHANNESINAREA

SAFAR

liA L A-1- FATE H

BANDAR AREA

61° 62° 63° 64 65° 66°

290

67°

Fig 5-

PROPOSED UPPER KAJAKlDAM

REPUBLIC OF AFGHANISTAN

WATER AND POWER AUTHORITY

HELMAND RIVER BASINIRRIGABLE AREAS

á.2a 2.0 t cal c

STILLING BASIN

I m. STRIPPING HORIZONTAL DRAINAGEBLANKET ( PERVIOUS)

SECTION A -Astammemessmemina

GATE SLOTSGATE 1-015T

ACCESS BRIDGE

PLAN4441T14T =R S

BRIDGE DECK

DESIGN HEAD WATER --4,

CREST

CONTROL WEIR

APRON L. Sl 0

.---BRIDGE PIER

DESIGN TAIL WATER

COUNTERFOR WALL-

TOP OF SLAB BAFFLE WALLEL.515.0 I EL.5ÌE.0 -j

(Extreme floodç Max.W. S. Et. 530.0

Trash rack slotStop-log slot

51a

OUTLINE OF DAM

TOP OF WALLEL, 520.0

EL.S19.0"...NACIP^

3- 3.0x2.0 Slide gates6-4.0x1.75 Slide yates

úq

NOTE : Seepage ringsnot shown .

SECTION 8-8issemeneweememmew

SECTION D -Dgiemeammonamme

0' z Meters

SCALE

Outline of dam

FLOWS.,

Baffle wall

Max. W. S.El. 525.0

t

L` zz 4 L t t %

tB S

SECTIïïN THRU LA

Outline of dam

0 10 20...... ....4,0 'co t conduit

SCALE

12 Nov. )975

SECTION THRU . CONTROE. WEIRineweamemmetean

SHEET PILING P,r

DNS AND ELEVATIONS

RS .ì ,