hazen value determination

Upload: ah-leng-lau

Post on 02-Jun-2018

233 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 Hazen Value Determination

    1/30

    CONTENTS

    1. INTRODUCTION................................................................................................................................1

    2. SYSTEM CHARACTERISTIC AND PUMP DUTY POINT..........................................................1

    3. DATA ACQUISITION........................................................................................................................3

    4. HAZEN WILLIAM C VALUE AND PUMP DUTY POINT ........................................................3

    4.1. DANGI PUMPING SYSTEM..............................................................................................................4

    4.2. PASIR BESARRAW WATER PUMPING SYSTEM ............................................................................6

    4.3. SILANG PUMPING SYSTEM ............................................................................................................8

    4.4. PALONG PUMPING SYSTEM .........................................................................................................10

    5. CONCLUSION ..................................................................................................................................12

    List of Graphs

    Graph 1: - Dangi Pressure VS Flow1.85

    ............................................................................... 4

    Graph 2: - System Characteristic Curve for Dangi Pump................................................... 5

    Graph 3: - Intake Pressure VS Flow1.85

    ............................................................................... 6

    Graph 4: - System Characteristic Curve for Intake Pump .................................................. 7

    Graph 5: - Sialang Pressure VS Flow1.85

    ............................................................................. 8

    Graph 6: - System Characteristic Curve for Sialang Pump ................................................ 9

    Graph 7: - Palong Pressure VS Flow1.85

    ........................................................................... 10

    Graph 6: - System Characteristic Curve for Palong Pump ............................................... 11

  • 8/11/2019 Hazen Value Determination

    2/30

    List of Tables

    Table 1: - Sources of Design data ..................................................................................... 12

    Table 2: - Summaries of Pumps Duty Point and Target Flow......................................... 12

    Appendix A: -Dangi Pumping System

    Pipe Profile by GPS tracking A-i

    Data for C value computations A-ii

    Photos A-iii

    Appendix B: -Intake Pumping System

    Pipe Profile by GPS tracking A-i

    Data for C value computations A-ii

    Photos A-iii

    Appendix C: -Sialang Pumping System

    Pipe Profile by GPS tracking A-i

    Data for C value computations A-ii

    Photos A-iii

    Appendix D: -Palong Pumping System

    Pipe Profile by GPS tracking A-i

    Data for C value computations A-ii

    Photos A-iii

  • 8/11/2019 Hazen Value Determination

    3/30

    1

    1.

    Introduction

    New pumps are proposed to be installed to replace the existing old pumps. To ensure that

    the required design flows can be achieved with the new pumps, the existing systems

    characteristic need to be established. The parameters required to confirm system charac-

    teristic are the pipeline parameters, pump characteristic curves and static lifts. Therefore,

    this report shall investigate the availability of existing data and carry out necessary tests,

    if necessary, to collect the missing data to establish the system characteristic curve to

    confirm the achievable duty flows from the proposed new pumps.

    2. System Characteristic and Pump Duty Point

    The duty points on any pump are the flow rate against the total head along the designated

    pump curves. Therefore pump curves are needed to determine the duty point. The duty

    flow rate is the flow that is pushed through the conveying pipes from start end to delivery

    end, against the total head, which is the sum of static lift and the friction loss in the con-

    veying pipes. Therefore, the system characteristic parameters are required to determine

    the duty point on a pump curve. The system characteristic is a function of various pa-

    rameters as described below:

    a) Pipe size the size of pipe or pipes if there are many different sizes involved

    b) Pipe length the length of the pipeline from pump end to receiving reservoirs.

    c) Pipe friction factor using Hazen William formula, this factor is termed as C.

    d) Static head the different in water levels between suction and delivery.

    The pipe frictional head loss is given by Hazen William formula as:

    87.485.1

    85.1

    *

    **67.10

    dC

    QLHl -----------------------------(1)

    Where,

    L length of pipe in m

    Q Flow rate in m3/sec

  • 8/11/2019 Hazen Value Determination

    4/30

    2

    d Pipe diameter in m

    C Hazen William friction factor

    Pump total head (Ht) is the sum of static head (Hs) plus pipe friction head loss (Hl), as

    shown below:

    slt HHH

    or

    st HdC

    QLH

    87.485.1

    85.1

    *

    **67.10-------------------------(2)

    Let87.485.1 *

    *67.10

    dC

    LK

    st HQKH 85.1* ---------------------------------(3)

    Which is in the form of y= mx + c

    Therefore, the plot ofHtagainst Q1.85will be a straight line, where the y-intercept will be

    the static headHs, and with gradient K. The Hazen William C can be calculated as shown

    below.

    85.187.4*

    *67.10dK

    LC -------------------------------------(4)

    Hence, the valve of C will depend on L length of pipe and d diameter of the pipe. If

    the pumping main have mix of pipe sizes in parallel and/or series, the actual C valve of

    each pipe cannot be determined. But the duty point still can be determined base on sys-

    tem characteristic equation (3), with K as the combined pipe characteristic, provided the

    field measurements are accurate.

  • 8/11/2019 Hazen Value Determination

    5/30

    3

    3.

    Data Acquisition

    In Section 2 above, to obtain the C valve, the flow against the pressure readings at the

    pipes are required (at least 3 point to confirm the set is straight line). The flow and pres-

    sure reading will be taken from pumping system with calibrated flow and pressure meas-

    urement equipment. For the pumping system without any or all the flow and pressure

    measurement equipment, then new equipment shall used to take the readings.

    For the pumping system without flow meter to measure the flow rate, externally mount

    on flow meter will be used to measure the flow in the pipe. A good location and condition

    of the exposed pipe are necessary for attaching the external flow meter to read accurately.

    For pumping system without pressure meter, digital pressure meter shall be used to read

    the pumping head. Provided an existing tapings on the pipe are available for attaching the

    pressure meter.

    Having collected the flow and pressure reading for a pumping system, verification on the

    correctness of the data collected is necessary. From equation (3), the static head (Hs) can

    be obtained from the graph of total head (Ht) against flow1.85

    . This static head (Hs) can be

    verified, if the level of suction tank and receiving reservoir are known.

    4.

    Hazen William C value and Pump Duty Point

    The size and length of the pumping main is necessary to calculate the C value for the

    flow and pressure reading obtained. Therefore, as-built drawings of the pumping main are

    necessary. In the event that the as-built drawings are not available, field collection of

    these data will be necessary. The pipe length and profile can be estimated using GPS

    tracking, and the pipe size will be determined by site measurement on exposed pipe, or be

    informed by the operators.

  • 8/11/2019 Hazen Value Determination

    6/30

    4

    4.1. Dangi Pumping System

    As-built drawings on the pipelines are not available, and GPS tracking is used to deter-

    mine the length of the pumping main. The plot of the pipeline profile, using GPS tracking

    is shown in Appendix A-1, and the length of the pipe is 2300m. The pipe size is obtainedfrom the sign board displayed at the entrance to the WTP, and it is shown as twin 380mm

    diameter MS pipe.

    The flow reading were taken form the flow meter in the control room, and the pressure

    readings were taken using digital pressure meter connected to a tapping at the surge ves-

    sel. The analysis of the flow-pressure readings and the graph of pressure against flow1.85

    is plotted in Graph 1.

    Graph 1: - Dangi Pressure VS Flow1.85

    Nine (9) reading are taken and the plot shows a good straight line with correlation of

    0.9988. The y-intercept, which is the static head, is 78.1m. The reservoir levels are TWL

    Static head = 78.094 m (y-intercept)

    Gradient K = 843.67 (Gradient)

    C = (10.67*2300.00/ 843.67/0.38^4.87)^(1/1.85)

    = 78.96

    PLOT of Q^1.85 VS H

    y = 707.29x + 78.094

    R2= 0.9988

    70.000

    72.000

    74.000

    76.000

    78.000

    80.000

    82.000

    84.000

    86.000

    88.000

    0.000 0.002 0.004 0.006 0.008 0.010 0.012

    Q^1.85

    H,m

  • 8/11/2019 Hazen Value Determination

    7/30

    5

    Pumping System Characteristic Curve

    0.00

    20.00

    40.00

    60.00

    80.00

    100.00

    120.00

    0 50 100 150 200 250 300

    Flow rate in l/sec.

    H

    eadinm

    4 pumps

    System curve

    with min. lift

    C=140

    System curve

    with max. liftC=78.96

    pump duty pointat max. head

    pumps Duty point

    at min. head

    189 232

    = 158.5m and BWL = 152.4m as shown on a sign board at the reservoirs gate. The suc-

    tion tank does not have any recorded levels, but site survey plan has indicated the ground

    level is around 77m. The suction tank TWL and BWL are assumed to be 79m and 76m

    respectively. Therefore, the static head calculated is between 79.5m to 82.5m, which is

    close to the computed value. Hence, the static head obtained from the test is acceptable.The calculated C value is 78.96, assuming the pipe is twin 380mm in diameter and

    2300m long, without any branched pipes.

    Based on the data collected, the system curves are plotted on the pump curves as shown

    in Graph 2, to determine the duty points. The suction pipeworks from suction tank to the

    pumps are buried, and detail record drawings are not available, hence, the station loss

    cannot be calculated and is assumed to be 2m.

    Graph 2: - System Characteristic Curve for Dangi Pump

    The minimum duty flow rate is 189 l/s (=680 m3/hr) when four (4) new pumps are run-

    ning. The flow will increased to 232 l/s (=835 m3/hr), if the pipes are replaced with new

    pipe. The target flow, with 4 pump running is 555 m3/hr; as indicated in drg.

    PAAB/NOO9-3/BWP-MIO-DG/PS/M/5001, which is less that the minimum flow of 680

    m3/hr, Hence, the selected pumps is able to delivery the target flow.

  • 8/11/2019 Hazen Value Determination

    8/30

    6

    Static head = 45.393 m (y-intercept)

    Gradient K = 149.34 (Gradient)

    C = (10.67*270.00/ 149.34/0.40^4.87)^(1/1.85)

    = 55.25

    PLOT of Q^1.85 VS H

    y = 149.34x + 45.393

    R2= 0.9926

    50.500

    51.000

    51.500

    52.000

    52.500

    53.000

    53.500

    54.000

    54.500

    0.000 0.010 0.020 0.030 0.040 0.050 0.060 0.070

    Q^1.85

    H,m

    4.2. Pasir Besar Raw Water Pumping System

    As-built drawings on the pipelines are not available, and GPS tracking is used to deter-

    mine the length of the pumping main. The plot of the pipeline profile, using GPS tracking

    is shown in Appendix B-1, and the length of the pipe is 270m. The pipe size, as told bythe operator, is 400mm diameter MS pipe.

    There is no existing flow measurement at site and suitable location to attach the flow me-

    ter cannot be found around the intake. Therefore, the flow measurement was taken at the

    aerator by attaching the flow sensors to the vertical aerator pipe. The pressure readings

    were taken using digital pressure meter connected to a tapping at the surge vessel. The

    analysis of the flow pressure readings and the graph of pressure against flow1.85

    is plotted

    in Graph 3.

    Graph 3: - Intake Pressure VS Flow1.85

    A total three (3) reading were registered and the plot shows a straight line with correla-

    tion 0.9928. The y-intercept, which is the static head, is 45.4m. There is no record for

    river maximum and minimum levels, and also the level at aerator outlet are not available

  • 8/11/2019 Hazen Value Determination

    9/30

    7

    as well. Therefore, based on the site survey plan and observation by the operators, the

    maximum and minimum river water levels are assumed to be 30m and 22m respectively.

    The aerator outlet also assumed to be 45.0m, based on ground survey plan of the WTP.

    The static head calculated is between 23m to 15m, which do not agree with the static

    head computed based on field test reading. A second field test was conducted on 4

    th

    , Dec.2012, and the operator has in deed confirmed that the surge vessel at the intake is for the

    old intake (ABJV) and hence the pressure readings taken in previous is not the pressure

    represent the new intake pump. There is not tapping on the existing pipe and hence, sec-

    ond round of test to take the pressure reading is not possible. This confirmed that the

    pressure readings taken are not valid.

    Since the tests for C value of the raw water pipe is not successful, the investigation of

    pump duty point was carried out based on common engineering practice. The pipe lengthof 270m as indicated by GPS tracking is taken as correct. Assuming that the old raw wa-

    ter pipe is 400mm diameter MS pipe; with C value of 90, and it is generally agreed that

    any pipe with C value less than 90 is not cost effective to continue using, because of

    the high energy loss from frictional losses. In addition, the suction pipeworks from river

    to the intake are buried, and detail no record drawings are not available. Therefore actual

    station losses cannot be calculated and station loss is assumed to be 2m. The system

    curves are plotted on the pump curves as shown in Graph 4, and the duty point is 272 l/s

    (=979 m3/hr), which is more than the target duty point of 227 l/s (=818 m

    3/hr).

    Graph 4: - System Characteristic Curve for Intake Pump

    Pumping System Characteristic Curve

    0.00

    20.00

    40.00

    60.00

    80.00

    100.00

    0 50 100 150 200 2 50 3 00 3 50 4 00

    Flow rate in l/sec.

    Headinm

    1 pumps

    System curve

    with min. lift

    C=120

    System curve

    with max. lift

    C=90

    pump duty pointat max. head

    pumps Duty point

    at min. head

    313

    INTAKE SYSTEM

    272

  • 8/11/2019 Hazen Value Determination

    10/30

    8

    4.3.

    Silang Pumping System

    As-built drawings on the pipelines are not available, and GPS tracking is used to deter-

    mine the length of the pumping main. The plot of the pipeline profile, using GPS tracking

    is shown in Appendix C-1, and the length of the pipe is 3700m. The operator informed

    that the pipe size is 250mm in diameter.

    There is no existing flow measurement at site and flow measurements were recorded by

    attaching the flowmeter to exposed manifold outside the pumping station. The pressure

    readings were taken using digital pressure meter connected to a tapping at the surge ves-

    sel. The analysis of the flow pressure readings and the graph of pressure against flow1.85

    is plotted in Graph 5.

    Graph 5: - Sialang Pressure VS Flow1.85

    Nine (9) reading are taken and the plot shows a good straight line with correlation of

    0.9982. The y-intercept, which is the static head, is 73.4m. The reservoir levels are TWL

    = 112.77m and BWL = 108.5m as shown on a sign board at the reservoirs gate. The suc-

    Static head = 73.448 m (y-intercept)

    Gradient K = 5928.6 (Gradient)

    C = (10.67*3700.00/ 5928.6/0.25^4.87)^(1/1.85)

    = 107.14

    PLOT of Q^1.85 VS H

    y = 5928.6x + 73.448

    R2= 0.9962

    74.000

    76.000

    78.000

    80.000

    82.000

    84.000

    86.000

    0.000 0.001 0.001 0.002 0.002

    Q^1.85

    H,m

  • 8/11/2019 Hazen Value Determination

    11/30

    9

    tion tank does not have any recorded levels, but site survey plan has indicated the ground

    level is around 36m. The suction tank TWL and BWL are assumed to be 35m and 37m

    respectively. Therefore, the static head calculated is between 75.77m to 77.77m. Hence,

    the static head obtained from the test is acceptable. The calculated C value is 107.14,

    assuming the pipe is 250mm in diameter and 3700m long, without any branched pipes.

    Based on the data collected, the system curves are plotted on the pump curves as shown

    in Graph 6, to determine the duty points. The suction pipeworks from suction tank to the

    pumps are buried, and detail no record drawings are not available, hence the station loss

    cannot be calculated and is assumed to be 2m.

    Graph 6: - System Characteristic Curve for Sialang Pump

    The minimum flow rate is 34 l/s (=122 m3/hr) when solo pump is running. The flow will

    increased to 43 l/s (=155 m3/hr), if the pipes are replaced with new pipe. The target flow,

    for solo pump running is 160m3/hr; 24% short off the target flow. Hence, the selected

    pump is unable to delivery the target flow.

    Pumping System Characteristic Curve

    0.00

    20.00

    40.00

    60.00

    80.00

    100.00

    120.00

    0 10 20 30 40 50 60

    Flow rate in l/sec.

    Headinm

    1 pumps

    System curve

    with min. lift

    C=140

    System curve

    with max. lift

    C=107.1

    pump duty point

    at max. head

    pumps Duty point

    at min. head

    34 43

    Sialang System

  • 8/11/2019 Hazen Value Determination

    12/30

    10

    4.4. Palong Pumping System

    As-built drawings on the pipelines are not available, and GPS tracking is used to deter-

    mine the length of the pumping main. The plot of the pipeline profile, using GPS tracking

    is shown in Appendix D-1, and the length of the pipe is 10,000m. The operator informedthat the pipe size is 380mm in diameter.

    There is no existing flow measurement at site and the manifolds are buried under ground

    outside the pumping station. Similarly, there are no suitable tapings on any of the ex-

    posed pipe for measuring of pressures. Therefore, both the flow and pressure measure-

    ments are taken at the exposed pipe crossing outside the WTP. The analysis of the flow

    pressure readings and the graph of pressure against flow1.85

    is plotted in Graph 7.

    Graph 7: - Palong Pressure VS Flow1.85

    Four (4) reading are taken and the plot shows a good straight line with correlation of

    0.9961. The y-intercept, which is the static head, is 35.7m. There were neither record

    drawings of Palong reservoir nor any sign board at the gate showing the TWL and BWL

    of the reservoir. Hence, the TWL and BWL of Palong reservoir are estimated using GSP

    Static head = 35.698 m (y-intercept)

    Gradient K = 1844 (Gradient)

    C = (10.67*10000.00/ 1844/0.38^4.87)^(1/1.85)

    = 114.51

    PLOT of Q^1.85 VS H

    y = 1844.9x + 35.698

    R2= 0.9961

    62.000

    64.000

    66.000

    68.000

    70.000

    72.000

    74.000

    0.000 0.005 0.010 0.015 0.020 0.025

    Q^1.85

    H,m

  • 8/11/2019 Hazen Value Determination

    13/30

    11

    tracking as 101m and 96m respectively. Similarly, the suction tank does not have any re-

    corded levels, but site survey plan has indicated the ground level is around 36m. The suc-

    tion tank TWL and BWL are assumed to be 35m and 37m respectively. Therefore, the

    static head calculated is between 64m to 66m, which is almost twice that obtained from

    site measurements. Therefore, this confirmed that the readings taken are not valid.

    A second field test was conducted on 4th

    , Dec. 2012, to repeat the test again, but the sec-

    ond test recorded the pumping head was only 40+m only, which is lower than the previ-

    ous test of 70+m. Therefore, the system characteristic curve cannot be determined.

    Since the tests for C value of the pipe is not successful, the investigation of pump duty

    point was carried out based on common engineering practice. The pipe length of 10,000m

    as indicated by GPS tracking is taken as correct. Assuming that the old pumping main is

    250mm diameter MS pipe; with C value of 90. It is generally agreed that any pipe with

    C value less than 90 is not cost effective to continue using, because of the high energy

    loss from frictional losses. In addition, the suction pipeworks from the suction tank to the

    pumping station are buried, and detail no record drawings are not available. Therefore

    actual station losses cannot be calculated and station loss is assumed to be 2m. The sys-

    tem curves are plotted on the pump curves as shown in Graph 8, and the duty point is 80

    l/s (=288 m3/hr), which is more than the target duty point of 72 l/s (=260 m

    3/hr).

    Graph 8: - System Characteristic Curve for Palong Pump

    Pumping System Characteristic Curve

    0.00

    20.00

    40.00

    60.00

    80.00

    100.00

    120.00

    0 30 60 90 120

    Flow rate in l/sec.

    Headinm

    1 pumps

    System curve

    with min. lift

    C=140

    System curve

    with max. lift

    C=90

    pump duty point

    at max. head

    pumps Duty point

    at min. head

    80 96

    Palong System

  • 8/11/2019 Hazen Value Determination

    14/30

    12

    5. Conclusion

    Ideally, all the data for estimation of pump duty flows should be available from record

    drawings or inventory database. But almost non are available, and these data are obtained

    by means of estimation or through mouth of experience operators. Therefore, the accu-

    racy of the computed duty points are compromised. Table 1 below summarized the

    source of data used in this report.

    Table 1: - Sources of Design data

    Out of the four (4) pumping system investigated, only one (1), Sialang pumping system,

    is not able to achieve the target flow. Table 2 below tabulated the computed duty flows

    and the targeted flow for all the four (4) pumping systems.

    Table 2: - Summaries of Pumps Duty Point and Target Flow

    Pumping

    System

    Pipe length,

    m

    Pipe size,

    mm Reservoir Levels, m Suction Tank Levels, m

    2300 380dia. X2 158/152 76/ 79

    GPS Operator Sign Board Ground Survey plan

    270 400 45 (areator) 22 / 30 (river)

    GPS Operator Ground Survey plan Ground Survey plan

    3700 250 112/ 108.5 35/37GPS Operator Sign Board Ground Survey plan

    10000 380 101/96 35/37

    GPS Operator GPS Ground Survey plan

    Dangi

    Intake

    Sialang

    Palong

    Pumping

    System

    Duty flow,

    m3/hr

    Target flow,

    m3/hr Diff. (%)Dangi 680 555 123%

    Intake 979 818 120%

    Sialang 122 160 76%

    Palong 288 260 111%

  • 8/11/2019 Hazen Value Determination

    15/30

    Appendix A: -Dangi Pumping System

  • 8/11/2019 Hazen Value Determination

    16/30

  • 8/11/2019 Hazen Value Determination

    17/30

    Dangi Pipe 'C' Value Computation:

    Pipe size = 0.38 mPipe length = 2300.00 m

    Q, cum/hr Q, (1 pipe) P, bars Q, cum/s Q.

    H,m

    545.0 272.5 8.689 0.0833 0.010 85.283

    538.0 269.0 8.676 0.0822 0.010 85.155

    530.0 265.0 8.65 0.0810 0.010 84.900

    428.0 214.0 8.41 0.0654 0.006 82.544

    423.0 211.5 8.4 0.0646 0.006 82.446

    414.0 207.0 8.376 0.0633 0.006 82.210

    138.4 69.2 8.022 0.0211 0.001 78.736

    137.1 68.6 8.017 0.0209 0.001 78.687134.0 67.0 8.014 0.0205 0.001 78.657

    Static head = 78.094 m (y-intercept)

    Gradient K = 843.67 (Gradient)

    C = (10.67*2300.00/ 843.67/0.38^4.87)^(1/1.85)

    = 78.96

    Measured Computed

    PLOT of Q^1.85 VS H

    y = 707.29x + 78.094

    R2= 0.9988

    70.000

    72.000

    74.000

    76.000

    78.000

    80.000

    82.000

    84.000

    86.000

    88.000

    0.000 0.002 0.004 0.006 0.008 0.010 0.012

    Q^1.85

    H

    ,m

  • 8/11/2019 Hazen Value Determination

    18/30

    Dangi Suction Tank

    Dangi Reservoir

  • 8/11/2019 Hazen Value Determination

    19/30

    Appendix B: -Intake Pumping System

  • 8/11/2019 Hazen Value Determination

    20/30

  • 8/11/2019 Hazen Value Determination

    21/30

    Pasirt Besar Raw Water Pipe 'C' Value Computation:

    Pipe size = 0.40 m, area = 0.13 sq.mPipe length = 270.00 m

    Measured Computed

    Q, cum/hr Q, (1 pipe) P, bars Q, cum/s Q1.85

    H,m V, m/s

    768.0 768.0 5.51 0.2133 0.057 54.081 1.70

    746.0 746.0 5.438 0.2072 0.054 53.374 1.65

    619.0 619.0 5.213 0.1719 0.039 51.166 1.37

    Static head = 45.393 m (y-intercept)

    Gradient K = 149.34 (Gradient)

    C = (10.67*270.00/ 149.34/0.40^4.87)^(1/1.85)

    = 55.25

    PLOT of Q^1.85 VS H

    y = 149.34x + 45.393

    R2= 0.9926

    50.500

    51.000

    51.500

    52.000

    52.500

    53.000

    53.500

    54.000

    54.500

    0.000 0.010 0.020 0.030 0.040 0.050 0.060 0.070

    Q^1.85

    H,m

  • 8/11/2019 Hazen Value Determination

    22/30

    Intake

    Aerator

  • 8/11/2019 Hazen Value Determination

    23/30

    Appendix C: - Sialang Pumping System

  • 8/11/2019 Hazen Value Determination

    24/30

    C

  • 8/11/2019 Hazen Value Determination

    25/30

    C

    Sialang Pipe 'C' Value Computation:

    Pipe size = 0.25 mPipe length = 3700.00 m

    Measured Computed

    Q, cum/hr Q, (1 pipe) P, bars Q, cum/s Q1.85

    H,m

    119 119.0 8.571 0.0331 0.002 84.124

    116.8 116.8 8.578 0.0324 0.002 84.193

    119.7 119.7 8.574 0.0333 0.002 84.154

    65.82 65.8 7.819 0.0183 0.001 76.743

    64.48 64.5 7.817 0.0179 0.001 76.724

    34.95 35.0 7.615 0.0097 0.000 74.741

    86.32 86.3 8.096 0.0240 0.001 79.462

    83.89 83.9 8.08 0.0233 0.001 79.30583.53 83.5 8.068 0.0232 0.001 79.187

    Static head = 73.448 m (y-intercept)

    Gradient K = 5928.6 (Gradient)

    C = (10.67*3700.00/ 5928.6/0.25^4.87)^(1/1.85)

    = 107.14

    PLOT of Q^1.85 VS H

    y = 5928.6x + 73.448

    R2= 0.9962

    74.000

    76.000

    78.000

    80.000

    82.000

    84.000

    86.000

    0.000 0.001 0.001 0.002 0.002

    Q^1.85

    H,m

  • 8/11/2019 Hazen Value Determination

    26/30

    C

    Sialang Suction Tank

    Sialang Reservoir

  • 8/11/2019 Hazen Value Determination

    27/30

    Appendix D: - Palong Pumping System

  • 8/11/2019 Hazen Value Determination

    28/30

    D

  • 8/11/2019 Hazen Value Determination

    29/30

    D

    Palong Pipe 'C' Value Computation:

    Pipe size = 0.38 m

    Pipe length = 10000.00 m

    Measured Computed

    Q, cum/hr Q, (1 pipe) P, bars Q, cum/s Q1.85

    H,m

    430.5 430.5 7.3 0.1196 0.020 71.650

    423.3 423.3 7.25 0.1176 0.019 71.159

    420.2 420.2 7.18 0.1167 0.019 70.472

    368.2 368.2 6.4 0.1023 0.015 62.816

    Static head = 35.698 m (y-intercept)Gradient K = 1844 (Gradient)

    C = (10.67*10000.00/ 1844/0.38^4.87)^(1/1.85)

    = 114.51

    PLOT of Q^1.85 VS H

    y = 1844.9x + 35.698

    R2= 0.9961

    62.000

    64.000

    66.000

    68.000

    70.000

    72.000

    74.000

    0.000 0.005 0.010 0.015 0.020 0.025

    Q^1.85

    H,m

  • 8/11/2019 Hazen Value Determination

    30/30

    Palong Pumps

    Palong Reservoir