hawaii water environment association kailua regional...

26
Kailua Regional WWTP and Collection System Odor Control Improvements Hawaii Water Environment Association February 15, 2011

Upload: phamkien

Post on 29-May-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Kailua Regional WWTPand Collection SystemOdor Control Improvements

Hawaii Water Environment Association

February 15, 2011

Overview

• Background

• Existing Conditions/Challenges

• Project Strategy and Goals

• Design Improvements

• Current Project Status

Brown and Caldwell

Background

Brown and Caldwell

• Hydrogen Sulfide (H2S)• <0.5 ppb Detection threshold (lab conditions)• 2 to 5 ppb Practical threshold in open atmosphere• 20 to 30 ppb Complaint level

• 10 ppm OSHA limit• 10 to 50 ppm Eye, nose, throat irritation• 50 to 300 ppm Eye/respiratory injury• >300 ppm Life threatening

• Hydrogen sulfide production

Sulfuric acid corrosion

Background

Brown and Caldwell

H2S

SO4

H2S

Sulfate Reducing Bacteria (Desulfobacter / Desulfovibrio)Conversion of Sulfate to Sulfide

Deposits

• Sulfuric acid (H2SO4) production

Background

Brown and Caldwell

Sulfate Oxidizing Bacteria (Thiobacillus thioxidans or Thiobacillus

concretivorous)Conversion of Sulfide back to Sulfate

Deposits

SO4

H2S H2S H2SO4

• Sulfuric acid damage• Ferrous metals• Concrete

Sulfuric acid corrosion

Background

Brown and Caldwell

• ROSE Program• Wastewater Odor Master Plan• Preliminary Engineering Report

• Sampling/Data CollectionH2S concentrationsDissolved sulfide testingAir flow measurementsStatic pressure measurementsSmoke tests

• Identification of Problem Areas• Design Recommendations

Background - History

Brown and Caldwell

Static Pressure Testing

Smoke Testing

Background – Project Sites

Brown and Caldwell

Ahuimanu Pretreatment Facility

Kaneohe Pretreatment Facility

Background – Project Sites

Brown and Caldwell

Kailua Road WWPS

Kailua Regional WWTP

Kailua Regional Wastewater Treatment Plant

Background – Project Sites

Brown and Caldwell

• Headworks Odor Control (HOC)• Influent pump station, headworks• Stage 1 - single chemical scrubber

• Proprietary chemicals

• Monthly cleaning – sulfur deposition

• Stage 2 - two activated carbon vessels• Single bed

• Operation in parallel

• Actual air flow measured lower than designed

Headworks Odor Control System

Existing Conditions and Challenges

Brown and Caldwell

• Primary Odor Control (POC)• Primary clarifiers, biotower pump station, DAFTs

Primary Odor Control System

Existing Conditions and Challenges

Brown and Caldwell

• Stage 1 - two chemical scrubbers• Proprietary chemicals

• Monthly cleaning – sulfur deposition

• Stage 2 - three activated carbon vessels• Single bed

• Operation in parallel

• Actual air flow measured lower than designed

• Secondary Odor Control (SOC)• Biotowers, solids contact tanks

Secondary Odor Control System

Existing Conditions and Challenges

Brown and Caldwell

• Stage 1 - two chemical scrubbers• Proprietary chemicals

• Minimal cleaning due to much lower H2S concentrations

• Stage 2 - four activated carbon vessels• Single bed

• Operation in parallel

• Actual air flow measured lower than designed

• Dewatering Building Odor Control (DOC)• Dewatering building second floor only

Secondary Odor Control System

Existing Conditions and Challenges

Brown and Caldwell

• Activated carbon• Fugitive emissions during

operation (open louvers, open doors, open truck rollup door, open rear enclosure)

• Key Areas• Primary clarifiers• DAFTs• Dewatering building

• Why?• Extended collection system to

generate high sulfides• Containment issues – missing

gaskets, open covers, doors open• Inadequate exhaust ventilation rate

– not achieving a negative pressure under process tank covers

Smoke test

Existing Conditions and Challenges

Brown and Caldwell

• Implement odor improvements• Chemical addition• Improved containment• Improved air flow• Improved treatment

• Meet regulatory requirements

• Reduce nuisance odors for neighbors

• Simplify odor system operation and maintenance

• Improve operator safety

Project Strategy and Goals

Brown and Caldwell

• Chemical Addition• 3 collection system sitesGoal – 0.5 mg/l dissolved sulfide conc entering

Kailua RWWTP

Jar testing – selection of chemicals for pilot testing

Pilot testing – testing of effectiveness, estimation/optimization of dosage

Calcium nitrate selected

• Headworks system• Polishing/emergency system

• Sodium hypochlorite selected

Design Improvements

Brown and Caldwell

• Headworks Odor Control (HOC)• New, larger ductwork and fans• Two new biotrickling filters (replaces chemical scrubber)• Two new activated carbon vessels (four total)• Odor exhaust stack extension

Design Improvements

Brown and Caldwell

• Biotrickling Filter Schematic

Design Improvements

Brown and Caldwell

• Primary Odor Control (POC)• ABANDONED• DAFT air flow diverted• PC air flow diverted• Biotower PS air flow diverted

Design Improvements

• Biotower Pump Station Odor Control (BOC)• New packaged carbon

system

Brown and Caldwell

• Secondary Odor Control (SOC)• New, larger ductwork and fans• Conversion of biotowers (replaces chemical scrubbers)• Primary clarifier air flow directed to biotowers • Odor exhaust stack extension

Design Improvements

Brown and Caldwell

• Biotower Schematic

Design Improvements

Brown and Caldwell

• Dewatering Building Odor Control (DOC)• Enclosure of first and second floors,

including truck bay• New supply and exhaust air system for

second floor• New two-speed supply and exhaust air

system in first floor truck bay• New activated carbon vessels (one for

each floor)

Design Improvements

Brown and Caldwell

Short dewatering truck

Long dewatering truck

• DAFT Improvements• Reroute of DAFT overflow to Biotower

Pump Station• Piping improvements of primary sludge

line to allow bypass of DAFT• Replace access hatches• Installation of brush attachments to

facilitate weir cleanings

• New enclosed digester waste gas burner

• New odor monitoring system

Design Improvements

Brown and Caldwell

DAFT access hatch

Existing waste gas burner

• Phase 1• Construction started Nov 2010• Completion early 2012• Construction cost ~$12 million

• Phase 2• Currently out to bid• Completion end of 2012• Construction cost estimated ~$4 million

Current Project Status

Brown and Caldwell

Questions?

Kailua Regional WWTP and Collection System Odor Control Improvements

Brown and Caldwell