GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION
( ACKNOWLEDGEMENT RECEIPT )
OWNEER‟S NAME________________________________________________________________
N.I.C NO.________________________________________________________________________
MAILING ADDRESS / TELEPHONE
NO._____________________________________________________________________________
COMPUTER ENTRY NO.__________________________________________________________
DATE OF SUBMISSION.__________________________________________________________
FORM NO._____________________________________________________________________
CHALLAN NO._________________________________________________________________
DATE OF ISSUE OF CHALLAN.___________________________________________________
AMOUNT IN RS._________________________________________________________________
OFFICE ADDRESS & TELEPHONE NO.____________________________________________
(if any)
NAME OF PROFESSIONALS.______________________________________________________
LICENCE NO. / REGISTRATION NO OF THE RESPECTIVE
COUNCIL_______________________________________________________________________
N.I.C NO.________________________________________________________________________
MAILING ADDRESS & TELEPHONE NO.__________________________________________
_________________________________________________________________________________
PFFICE ADDRESS & TELEPHONE NO.____________________________________________
(if any)
_______________________________________________________________________________
FAX NO.________________________________________________________________________
(if any)
2
D. LIST OF THE DOCUMENTS (ATTESTED PHOTO COPIES BY THE
PROFESSIONAL).
…………………………………………………………………………………………………………..
LEASE DEED / SALE DEED.
ALLOTMENT ORDER, MUTATION / TRANSFER
ORDER_________________________________
POSSESSION ORDER. (in case of any approval scheme)_________________________________
ACKNOWLEDGEMENT OF POSSESSION___________________________________________
NOC FROM SOCIETY / LESSOR __________________________________________________
FINAL TRANSFER ORDER _______________________________________________________
OFFICIAL SITE PLAN , DEMARCATION____________________________________________
PLAN FROM CONCERN AUTHORITY _____________________________________________
UNDERTAKING FROM OWNER ___________________________________________________
a- Building plan is accepted with the condition that approval will be accorded as per existing
rules and regulation_________________________________________________________________
the right to reject or accept the building plan..
b- The acceptance for security of the building plan, does not imply that, it will be approved.
( Superintendent )
Building Control Section
GDA
3
F-1
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under Section of Gwadar Development Authority Act 2003)
APPLICATION FOR SUBMISSION OF PROPOSED / ADDITIONAL / ALTERATION
BUILDING PLAN
The Controller of Buildings,
Gwadar Development Authority,
Gwadar .
Sir,
1. In pursuance of the provision of the Gwadar Buildings Regulation 2005 as amended
up to date, I hereby apply for your permission to erect / re-erect / make additions and or
alterations in building on
a. Plot No /Khasra No/ Khatooni No;______________________________
b. Blocks / Sector No / Vicinity___________________________________
c. Category of Plot. ___________________________________________
d. Area of plot. _______________________________________________
e. Scheme.____________________________________________________
f. Status of plot. _______________________________________________
In accordance of Buildings plan enclosed herewith (Three copies} for approval.
2. Description of plans
a) Type of plan (pro./Revised /Addition/Alteration)
b) Previous Approval (if any)._____________________________
3. Description of the proposed construction
a) Type of Building. ____________________________________
b) Total Floor Area. ____________________________________
c) No of Floors.___________________________
d) No. of Units.___________________(For Public Sale Project only)
4
e) Car parking space. __________________________ Sq:ft (Sq.mt)
f) Area of amenity space ______________________ Sq:ft.(Sq.mt)
4. Particulars of licensed professional employed to prepare the plan and supervise work:
(Attach separate sheet if required )
a). Name._____________________________________________
b). License No./professional Registration Number. From the concerned council_______
c). CNIC No.____________________________________________
d). Mailing and permanent address/Telephone No.______________________________
e). Office address and Telephone No._______________________________________
5. Weather the project is indented for public sale ?
Yes / No___________________________________________________________________
5. List of the documents to be attached ( Photo copies duly attested by the professional )
please stick.
Lease Deed / Sale Deed, Allotment order, Mutation / Transfer order / Extract. / Chthonic /
Profession Order
Acknowledgement of possession
Site plan
N.O.C from Society / Laser (where applicable)
CNIC No.
Mr./Mrs./ Miss._______________________S/O,
W/O,D/O._____________________________
5
F-1.1
stamp Paper Rs. 200/=
( Professional Name)
License No./Registration No_____________________________as hereby authorized by
me to complete relevant required in this regard Under Gwadar Building Regulation
2005 and amendment up to date and regulations framed there under for and on my
behalf.
I/We owner (s) /attorney (s) of the above plot as gone through the aforesaid
clauses and I/we undertake to provide plinth certificate notice at the stage of completion of
plinth as required under clause No: 3-2.10 Gwadar Building Regulation 2005 and further
undertake to abide by all the rules and regulations aforementioned
Your faithfully
SIGNATURE:_______________________________________
Name of Owner / Attorney:___________________________
C.N.I.C No.______________________________________________
(Attached Copy)
Email:___________________________________________________
Mailing Address:_________________________________________
_________________________________________
Permanent Address and Telephone No:________________________
_________________________________________________________
6
ARCHITECT / BUILDING DESIGNER ENGINEER
1. Signature of Professional_______________ 1. Signature of _________________
Professional___________________
2. Name of professional __________________ 1. Name of ____________________
Professional______________________
3. Lic No._____________________________ 3. Lic_____________________
No._____________________________
4. CNIC No.___________________________ 4. CNIC___________________
No._____________________________
5. P.C.A.T.P No.________________________ 5.P.E.C____________________
No_________________________
6. Mailing address.______________________ 6. Mailing_________________
address.___________________
.
7
F-1.2
( Undertaking from Professional )
I, Mr. / Mrs. / Miss.___________________________________________________________
S/o, W/o, D/o________________________________________________________________
License /Reg. No.________________(Architect/Engineer /Town planner/Building Designer)
Mailing address _____________________________________________
Phone No.__________________________________________________
Fax No. (If any)____________________________________________do hereby undertake
1). That I have been assigned by (owner/ attorney)
Mr./Mrs./Ms_______________________________________________for the planning, Designation
supervision of construction works of project name, (If any)
Located on plot No.________________________________________
( Complete Address )
2. That I have done planning and design and respect of the above noted plot
according to the Gwadar Building Regulation 2005 and Town Planning Regulation
2004.
3. That I will supervise the construction work through all stages of execution as per
the regulation.
4. That I will not make change in the approve design and specification except as
provide in the regulations.
5. I / We undertake to ensure that not deviation from the approved building plan shall
take place and any case the owner, I / We shall inform G.D.A in due course of time
about the deviation for taking necessary action under provision of Gwadar Building
Regulation 2005 and Town planning Regulation 2004.
6. That I / We also under the provision of Clues No:3-2.2.3 are responsible for the safe &
sound construction of Building.
7. I / We also undertake that if the work is started prior approval of Building plan or if I /
We discontinue supervision of work, I / We shall given immediate intimation therefore
to you as specified under clause No:3-1.5 of Gwadar Building Regulation 2005 and
Town planning Regulation 2004 in case any other penalty as prescribe under the
Gwadar Building Regulation 2005 and Town planning Regulation 2004 may be
processed in terms of GDA Act-2003 amended and the rules framed there under.
ARCHITECT/ BUILDING DESIGER ENGINEER
1. Signature of Professional _____________ 1. Signature of ____________________
professional________________
2. Name of professional_________________ 2. Name of _______________________
professional___________________
3. Lic No.____________________________ 3. Lic _________________________
No.______________________________
8
4. CNIC No.__________________________ 4. CNIC _______________________
No.___________________________
5. P.C.A.T.P No.______________________ 5. P.E.C _______________________
No___________________________
6. Mailing address._____________________ 6. Mailing _____________________
address.______________________
___________________________________
____________________________________
7. Telephone. No_______________________ 7. Telephone ___________________
No._______________________
8. Fax No_____________________________ 8. Fax _________________________
9. No.____________________________
10. Email Add.__________________________ 9. Email _______________________
11. Add._________________________
12. Date_______________________________ 10.
Date.______________________________
9
F-1.3
Stamp papers. Rs. 200/=
Undertaking from professional for township Projects
I, Mr./Mrs./ Miss __________________________________________________________________
planner Registration NO. of the relevant council _______________________________________
mailing address ___________________________________________________________________
Phone NO._____________________Fax No. __________________________________(if any) do
hereby undertake.
1. That I have been assigned by M/s _________________________________________ for the
planning, design and supervision for the township project (If any_____________________
located on Khatoni/ Khasra No._________________________________________________
2. That I have done planning and drawing of the project on the above noted plot/survey No.
In accordance to the Gwadar town planning Regulations, 2004.
3. That the layout plan of the project has been approved by the Master Plan & Environment
control department , GDA wide their latter NO__________________________ dated
___________________
4. That I undertake to supervise the development work of the project through all stage of
execution
5. That I will not make change in the layout plan , design and specification without approval
of the authority expects provided in these regulation.
1. Signature of professional ___________________________________
2. Name of the lic. professional_________________________________
3. N.I.C No. ________________________________________________
4. 4. Mailing and permanent Address __________________________
5. Office address tele.No._____________________________________
6. Date ____________________________________________________
10
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION Building Regulation 2005
( Acknowledgment Reception)
From F-2
Owner‟s Name _________________________________________________________
N.I.C No_______________________________________________________________
Mailing address telephone________________________________________________
Computer Entry _______________________________________________________
Date for Submission ____________________________________________________
Form NO______________________________________________________________
Challan No.____________________________________________________________
Date of issue of chalan ___________________________________________________
Amount in Rs.__________________________________________________________
Contact date__________________________________________________________
Contact No____________________________________________________________
Office Address and telephone .No._________________________________________
Name of the professionals________________________________________________
License No. / Registration No. of the respective council_______________________
N.I.C. No. ____________________________________________________________
Mailing address & telephone ____________________________________________
Office address & telephone NO.__________________________________________
Office Address and telephone No.________________________________________
Fax No. ______________________________________________________________
(if any)
List of Documents (Attested Photo copies by the professional
Lease deed / sale deed,
Allotment order, mutation/ transfer order_________________________________
Possession order_______________________________________________________
Acknowledgement of possession _________________________________________
NOC form society / Lesson______________________________________________
Final transfer order____________________________________________________
Official site plan , Demarcation
Plan ________________________________________________________
UNDERTAKING FROM OWNER_________________________________________
A. Building plan is accepted with the condition that approval will be according as per
existing rules & regulation & GDA 2003 and amendments up-to-date, GDA reserve the
right to reject or accept the building plan.
B. The acceptance for scrutiny of the Building plan, does not imply that, will be approved.
Plan received by Office Superintendent (BCS)
11
FORM F-3
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section: 24)
Building Regulation 2005
No. GDA/BCS/__________________________________ Dated.___________________________
Mr.M/s Mrs._____________________________________ Mr. Miss. Mrs._____________________
(Professional) (Owner)
___________________________________ ____________________________________
___________________________________ ____________________________________
Professional License / Registration No._________________________________________________
Subject: YOUR BUILDING ON PLOT NO / KHASRA / KHATOONI NO.________
Reference:_________________________________ Dated:_______________________________
The Building plan above cited plot has been scrutinized and you are required to reply the following
objects:-
1-
2-
3-
Your case shall further to be processed on receipt of your compliance / reply to this letter.
SIGN_________________________
NAME________________________
(Controller of Buildings)
Building Control Section
GDA
12
FORM F-4
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section :24)
Building Regulation 2005
No._____________________________________________ Dated.___________________________
Mr. M/s Mrs.___________________________________ Mr. M/s Mrs._______________________
(Professional) (Owner)
______________________________________ _________________________________
___________________________________ __________________________________
Professional License / Registration No.________________________________________________
Subject: ARCHITECTURAL CONCEPT APPROVAL IN RESPECT OF PLOT NO
/ KHASRA / KHATOONI NO._______________________
With reference to your application dated:___________________________________
Regarding the approval of purposed concept building plan , in respect of subject plot ; you are hereby
informed that competent authority is pleased to consider and approve your request for architectural
concept for Ground ______________________________________________________ upper floors.
Now you are required to submit the following information for consideration of the authority and for
grand of approval, if compiled with these regulations and permit to construction.
1-
2-
3-
4-
5-
This acceptance does not entitle you to start construction.
Controller of Building
Building Control Section
Gwadar Development Authori
13
FORM F-5
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section :24)
Building Regulation 2005
No.GDA/BCS/___________________________________ Dated.____________________________
T.P NOC No.______________________________________________________________________
(if any)
NOC No._________________________________________________________________________
(if any)
Mr. M/s Mrs._______________________________ Mr. M/s Mrs.____________________________
(Professional) (Owner)
_________________________________ ___________________________
Professional License / Registration No._______________
Subject: PROPOSED BUILDING PLAN & KHASRA / KHATOONI NO
____________________________________________________________
Status of plot _________________ Area of plot_______________ No. of floor________________
The Building plan for the above mentioned plot (Attached) are hereby approved and
you are permitted to carry out construction on the said plot accordingly.
This approval is granted subject to following conditions.
That this holds good only if the construction work is started within two years from the date of
approval. After expiry of this permission it shall be renewable if it is in accordance with current
regulations.
That the professionals shall be jointly and severally responsible for providing architectural /
structural design and specification for execution of the work at site.
The following record / documents shall always be kept ready for production to the officers of
Gwadar Development Authority at the time of inspection.
a). Architectural & Structural Environment plan (approved by GDA)
b). report showing the following
(i) Date of concrete and removal of framework.
(ii) Cube test report from approved lab.
14
The following information shall be displayed at site
(for the public sale project)
(i) Plot No.
(ii) Project Name
(iii) Plan approved by the GDA
(iv) Sale NOC from GDA
(v) All advertising material i.e. model displayed.
At site / printed brochure in conformity with the approval that the quality controls and stability of the
structure shall be jointly & severally responsible of:
(i) Owner Developer (ii) Builder (iii) Architect:____________________________ (iv) Structural
Engineer:________________________ (v) Professional Engineer:___________________________
This approval is liable to be cancelled due to any misrepresentation of facts. That in the event of
withdrawal of supervision by the professional, the permitted approval plan shall be treated as
cancelled, for such time the other professional is appointed in accordance with the regulation.
Notes for verification of building lines (plinth verification certificate, as per form F-7 by the owner /
professional is must for further construction of the structure. If the same is not obtained, structure
beyond plinth shall be treated as unauthorized and liable to be demolished at any stage.
(Controller of Buildings)
Building Control Section
GDA.
Copy to.
15
FORM F-6
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section :24)
Gwadar Building Regulation 2005
No GDA/BCS/.______________________________________ Dated:_______________________
Mr. / Mrs. / Miss.__________________________ Mr. / Mrs. / Miss._________________________
(Professional) (Owner)
Professional License / Registration No.________________________________________
Subject: PROPOSED BUILDING PLAN ON PLOT NO.___________________
______________________________________________________________
Status of plot ______________ Area of plot __________ No. of floor_____________
The building plans for the above for the above mentioned plot (attached), are hereby
approved and you are permitted to carry out construction on the said plot accordingly. This approval
is granted subject to following condition.
That is held good only if the construction work is started within two years from the date of approval.
After expiry of this permission, it shall be renewable if it is in accordance with current regulations.
That the professionals shall be jointly and severely responsible for providing architectural /
Structural design and specification for execution of the work at site.
The following shall always be kept ready for production to the officer of GDA / BCS at the time of
inspection.
Plans approved by BCS
1. Date of concrete and renewal of framework
2. Cube and subtest report form-approved lab.
The following information shall be displayed at site.
(for public sale projects)
1. Plot No. / Khatooni / Khasra No:
2. Project Name
3. Plan approved by the BCS / TPS / GDA.
4. Sale NOC form BCS / TPS / GDA.
5. All advertising material i.a model displayed at site / printed brochure in conformity with
the approval.
16
FORM F-7
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section :24)
Building Regulation 2005
VERIFICATION OF BUILDING LINES
( PLINTH VERIFICATION CERTIFICATE )
( TO BE SUBMITTED ON COMPLETION OF PLINTH ON FOUNDATION OF BASEMENT IF THERE IS ONE)
To,
The Controller of Buildings
Buildings Control Section,
Gwadar Development Authority,
Gwadar.
I / We hereby inform that the plinth / foundation of the basement stage of the building
On plot No. / Khatooni No / Khasra______________________
______________________
______________________
Has been achieved. You are, therefore. Requested to depute a representative to verify the building
lines so as to enable me / us to carry out the building work.
Owner/s
Mailing Address______________________
______________________
(Dated). ______________________
Professional‟s Certificate
I / We hereby certify that the setting out of building/s for plot No. Khatooni / Khasra No. /
Mouza__________________________________________
Has been carried out in accordance with the approve plan/s.
Signature____________________________
Name_______________________________
Professional__________________________
17
FORM F-8
FLOOR CERTIFICATE
To,
The Controller of Buildings
Gwadar Development Authority
Gwadar.
I / We hereby inform that the slab has been cast of _________________________________
On plot No. Khasra / Khatooni No.____________________________________________________
I / We herby certify that all the structural member cast on the said floor are in conformity with the
design and specifications as approved by GDA vide
No._______________________________________
Dated________________________________________.
Signature of Professional
Name_________________________
No.___________________________
C.N.I.C No. Postal / Permanent
Address_______________________
______________________________
Office Address and Telephone No.
______________________________
Dated: _________________________
18
FORM F-9
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section :24)
Gwadar Building Regulation 2005
No GDA/BCS/.__________________________________ Dated:____________________________
Mr. / Mrs. / Miss.___________________________________________________________________
_________________________________________________________________________________
(complete mailing address)
Subject: BUILDING ON PLOT NO.___________________________________
_________________________________________________________________________
(complete address)
Where the structure standing on the above mentioned plot appears to the Authority to
be unauthorized having been constructed in contravention of the approval plan and violation of the
requirements of GDA Act 2003 and the Regulation framed there under.
Description of violation: (Strikes out those are not applicable, and tick those that are applicable)
Demolition of old Structure with GDA / BCS approval.
Construction without and approval plan.
RCC footings / plinth and compulsory open spaces at front / rear / right.
Construction on the cut line / setback for notified road widing of _________________
Road.
Unauthorized extra ____________________________ floors.
Excess cover area on __________________________ floor (s).
Changes structural (column / beam) layout, in contravention of the approval plan.
Changed architectural layout, in contravention of the approval.
Construction without supervision professional /s.
Non-submission of plinth verification certificate / floor certificate at _____________
level / floors.
No prior information given on pouring of concrete for RCC at_________________ level /
floor.
No safety fencing installed between plot and public road / footpath.
You are hereby directed to:
1. Stop further potentially dangerous and unauthorized construction work on plot forthwith.
2. vacate the said unauthorized structure within _______________ hour / days form receipt
here of , failing which you shall be summarily evicted there from.
19
3. Remove the unauthorized structure within_____________ hours / days receipt here of,
failing which the same shall be removed, sealed by the Authority at your expense under
section GDA Act 2003.
4. Explain immediately why you should not prosecuted for violation of the GDA Act 2003
and the Regulation framed there under:
(Controller of Buildings)
Building Control Section
Gwadar Development Authority
Copy to:
1. Mr. / Mrs. / Miss
(Professional/s)_______________________________________
license / Registration No.___________________ explain immediately why
action should not be initiated against under GDA Act amended up to date and
these Regulation.
2. Legal Advisor.
3. Registrar of the Balochistan High Court.
4. Director General GDA.
20
FORM F-10
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section :24)
Gwadar Building Regulation 2005
VERIFICATION OF BUILDING LINES
No GDA/BCS/.______________________________ Dated________________________
Mr./Mrs./Miss.______________________ Mr./Mrs./Miss.______________________
(professional) (Owner)
_________________________________ _________________________________
_________________________________ _________________________________
Professional license /Registration No._________________________
Subject: RENEWAL OF APPROVED PLAN OF PLOT NO.______________________
Status of plot __________________ Area of Plot ______________________________________
No. of floors________________
Reference:________________________________________________________________________
Validity of approval of the above cited building plan granted under
N.O.C NO.___________________dated_____________________ is hereby extended for further
Period of Two years with effect from ____________________________________________
Subject to the condition mention in the letter sanction and on the sanction plan.
You are now permitted to carry out construction strictly in accordance with above
-renewed building plan under the supervision of professional as required under the
regulations.
SIGNATURE________________________
NAME______________________________
(Controller of Buildings)
Building Control Section
Gwadar Development Authority
21
FORM F-11
NOTICE OF DISCONTINUANCE
To.
Controller of Buildings
Gwadar Development Authority
Gwadar
I hereby given notice of my discontinuance from the development work as
professional as per detail given below.
1-Plot No./khatooni/khewaet No.______________________________________
2-Approval number._________________________________________________
3-Effective date of discontinuation.___________________________________
It is certified that I have supervised the construction / development
up to._______________level and the details of works carried out under
My supervision are listed below:-
1-
2-
3-
4-
5-
6-
7-
8-
Signature ______________________________
Name __________________________________
License / Registration No.__________________
Copy to:-
Owner / Developer / Builder.
22
FORM F-12
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section :24)
Gwadar Building Regulation 2005
ENGEGEMENT OF NEW PROFESSIONAL
No GDA/BCS/.__________________________ Dated: ______________________________
To,
The Owner
Mr. / Mrs. / Miss.____________________________
_____________________________
Subject: CONSTRUCTION ON PLOT NO
Since Mr. / Mrs. / Miss.______________________________________ ( Lenience
No. / Rag No. of the council___________________________________________________) has
already discontinued his services from _______________________ on the above-cited plot. You are
hereby directed to stop the work forthwith.
You are also advised to engage a new professional and submit Form F-1.2______
duly signed by him before restarting the work of construction.
(Controller of Buildings)
Building Control Section
Gwadar Development Authority
Gwadar
23
FORM F-13
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section :24)
Gwadar Building Regulation 2005
VERIFICATION OF BUILDING LINES
NOTICE OF COMPLETION
To,
Controller of Buildings
Gwadar Development Authority.
I / we hereby give notice of completion of building works in the building on plot. Khasra /
Khatooni
No_________________________________________________________________________
And apply for permission for occupation of the said building.
The said work has been carried out in accordance with the building plans approved vides No.
__________________Dated: ______________ and variation is recorded on completion plan.
Owner / s Address
_____________________________
_____________________________
Dared: ________________________
FORM F-13
Annexure. I
PROFESSIONAL CERTIFICATE
I hereby certify that the building work in the building on the plot No Khasra / Khatooni No
____________________________ completed under my supervision and to my satisfaction in
accordance with the building plan approve No. __________________________ dated:
______________
With variation as shone on completion plan.
Signature:
Name:
License / Registration No:
Mailing Address:
24
FORM F-14
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section :24)
Gwadar Building Regulation 2005
No GDA/BCS/._______________________Dated:___________________________________
Mr./Mrs./Miss.______________________ Mr././Mrs./Miss.____________________________
(Owner) (License /Registration No.1)
_________________________________ _________________________________
_________________________________ _________________________________
Subject: OBSERVATION ON THE COMPLETION PLAN OF THE BUILDING
CONSTRUCTION ON PLOT NO.___________________________________
__________________________________________________________________
On inspection of the site, following irregularities have been observed :
Your are, therefore, requested to explain the reason as to why the above
Irregularities in existing building should not be demolished .
SIGNATURE________________________
NAME______________________________
(Controller of Buildings)
Building Control Section
Gwadar Development Authority
25
FORM F-15
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section :24)
Gwadar Building Regulation 2005
NO.______________________________________Dated:_________________________________
APPLICATION FOR PERMISSION TO
DEMOLISH BUILDING, STRUCTURE
The Controller of Building
Gwadar Development Authority,
Gwadar.
I / We _____________________________________ apply for permission to demolish the building
on plot Khasra / Khatooni No. _______________________________ The particular of which are
given below and certified to be true:
1- Name(s) of the Building ______________________________________________
2- Location of Building _________________________________________________
3- Date of construction of building ________________________________________
4- Condition of the Building ___________________________________________
5- No. of stories of the building______________________________________________
6- Type and date of leased of plot/building_____________________________________
7- Status of the building i.e. full vacant/partly occupied____________________________
8- Consent of the tenants/present occupiers, if any (please attach)_____________________
9- Further public notice in the largely circulated newspaper (English & Urdu) is attached.
10- Legal status i.e. whether the building is under litigation___________________________
11- Whether any portion for the adjacent building is likely to be affected by demolition? If so,
please submit details and precautionary measures to be adopted ____________________
12- The existing utilities have been removed/will removed and received according to the
Regulations of the utility concerned quarter. However, in case of any misshape due to my
negligence or of Laborer I will be personally responsible for the same, and legal action
may be taken against me.
(1) Electricity (4) Telephone
(2) Gas (5) Water
(3) Sewerage (6) other Services
26
13- I/We ______________________________ undertake to observe all people precaution
as prescribed under the relevant concerned utility agencies and the GDA, Building
regulation 2005,in vogue to ensure safely of the public , of person employed at the site
and at adjacent buildings.
14- Mr.Mrs. Miss______________________________(professional)licensee /Registration N.
or council (_______) has been engaged to supervise the demolition work
15- I / We _______________________________ also further undertake that the digging and
filling of the plot, if any, shall be carried out with in the stipulated time specified in the
latter of permission.
SIGNATURE OF OWNER SIGNATURE OF PROFESSIONAL
NAME ___________________________ NAME _____________________________
LICENSE/REGISTRATION NO.__________________________________________________
27
FORM F-16
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section :24)
Gwadar Building Regulation 2005
No GDA/BCS/.. ___________________________________Dated __________________________
PERMISSION FOR DEMOLITION
Owner. Professional
Mr./Mrs./Miss.______________________ Mr./Mrs./Miss.______________________
_________________________________ _________________________________
Owner License / Registration No. of Council.
________________________________
Permission in herby granted for the demolition of Building No. _________________________
on plot No. Khasra / Khatooni No: ____________________________________________ Gwadar.
The permission is valid for one year during which period the demolition of the building shall be
completed excavation below the ground level is only permitted for removal of existing foundation
which shall be filled again, extension of the period will be granted only in exceptional cases after the
payment of necessary renewal fee, as prescribed form time to time.
This permission is issued with the condition that the professional shall be responsible for talking all
the necessary safety measures during the process of demolition and for ensuring the disconnection of
all utility services before starting the said demolition.
(Controller of Buildings)
Building Control Section
Gwadar Development Authority
28
FORM. F-17
…………………..
Price Rs.________
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section :24)
Gwadar Building Regulation 2005
The Controller of Buildings
Building Control Section
G.D.A Gwadar .
I_________________________Son/Daughter/Wife
of______________________
_____________________ hereby apply for the grant of a license for practice as
____________________ in Gwadar Division under the Gwadar Building and Town
planning Regulation under GDA Act 2003. My particulars are given below.
1. Date of birth_________________________________
2. Resident Address______________________________
3. office Address________________________________
4. Telephone No.________________________________
5. N.I.C No.& N.I.C Address________________________
6. Name of the farm (if any)______________________
7. Nationality____________________________________
8. Technical Education And Qualification
Degree/Diploma /
Certificate
Year University
institute
8. Membership of any other
professional institute_________________________________
(Attached attested copy of membership)
9. Status: practicing independently
Or serving in any professional /Firm_______________________
planning firm with any other organization
Etc._________________________________________________
10. Practical experiences (please attached attested copies of certificates
from firm to whom worked.
Photograph
29
(a) Supervisor work_________________________________
(b) Other experiences in matters relating to building /Town planning
and other related field of building construction.______
11- Dated and No. of previous License No. if any_____________________
12-Sample of the seal& Signature to be used on all plans___________
______________________________________________________________
13- Have you ever been associated in any capacity in any illegal project
Yes /NO.
14- Has your license ever canceled by any other licensing authority
Yes / NO ( in case “yes” please give detail on a separate sheet)
Certified that the statement given above are correct and if any of the
above statement be found incorrect the license can be cancelled and
action can be taken under G.D.A Act 2003 amended up to date rules
/regulation framed there under.
Dated:_______________________ Signature of Applicant_______________
30
FORM. F-18
…………………..
Price Rs.________
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section: 24)
Gwadar Building Regulation 2005
APPLICATION FOR ENLISTMEN AS LICNSED BUILDER / FIRM
To.
Controller of Buildings
Gwadar Development Authority
Gwadar.
I /
We___________________________________________________________hereby
apply for the grant of license for practicing as a Building / promoter in Gwadar
Development
Authority .My / our particulars as follows:
1. Name of company (in block letter)_______________________________________________
2. Registered Business address with ________________________________________________
Telephone No./Fax No.
3. States (prop/partnership/Corporation)_____________________________________________
4. Name of the Director/Managing _________________________________________________
Partner/sole proprietor with residential
address NIC and Extant of share in _______________________________________________
Company (if more then attach
separate sheet). ________________________________________________
5. Detail of capital of company. ___________________________________________________
Attach partnership/shear holders
Of director with detail _______________________________________________________
6. Details of the technical qualification ______________________________________________
Of the proprietor /Director Company /
Society/ partners.________________________________________________________________
7. Has the proprietor / company/ is __________________________________________________
31
Paying income tax?
NTN No. of company ________________________________________________________
8. Has the company / is registered with GDA_______________________________________
/GMC/cantonment or any other body is
Building contractor? If so. Please attach___________________________________________
The Photostat copy of the registration.
9. Does the company / have any
previous experience of construction ____________________________________________
of building or development (Please give
full details of the building built / land ___________________________________________
development so far)
10. a. Proposed date of start. ___________________________________________________
b. Proposed date of completion. _____________________________________________
11. Is the company financially sound
enough? If so, please attach Bank _____________________________________________
certificate address to the Controller
of Buildings, GDA. _____________________________________________
12. Does the Company enjoy credit ______________________________________________
facilities from any Bank, HBFC or
any other agency? If so, please attach
certificate, if net? Method of financing __________________________________________
of the project be described.
13. Details of the qualified staff (full
time site Engineer for the supervision ___________________________________________
of the construction / development and
an undertaking of employment _______________________________________________
of the site Engineer engaged by your
Co. is your site Engineer supervising the
the Project of other Companies as well? __________________________________________
14. Details of the equipment and Machinery
available with the company and state detail ________________________________________
of the Site of placing the machinery. _____________________________________________
15. Does the company own land? If so, ______________________________________________
please submit all the details along-with
attested copies of land ownership. _______________________________________________
16. Named of Structural Engineer and _______________________________________________
Architect with company and certificates
from them that they will be associated
with all projects of company. ___________________________________________________
17. Court cases, if any (against the site
operation, partners etc.).
32
18. Have you ever been associated in any capacity in any illegal project?
19. Has your licensed ever been canceled by any other licensing authority?
Certified that the statement given above are correct and if any of the above statement be
found incorrect, the License can be cancelled and action can be taken under GDA Rules 2003,
amended up-to date and the rules and regulations framed therefore.
SIGNATURE. ____________________ DIRECTOR / PARTNER. _______________________
PROPRITOR OF. ___________________________________________________
33
UNDERTAKING
(SHOULD BE SUBMITTED ON RS. 1000/= STAMP PAPER)
I / We ___________________________________________ S/o. D/o. W/o ______________
do hereby agree to abide by all rules and regulation respect of enlistment of Licensed Builder framed
under GDA Building Regulation 2005, from time to time and shall be fully responsible for all acts
and deeds done under the above cited name and title.
I / We do herby agree with free consent that the Authority reserves full rights to cancel or
suspend the license from a specific time, or permanently for the branch of any terms and conditions
as specified in the regulation.
I / We undertake to intimate any change in my / our address or constitution of the Firm /
Company etc. and shall not hold the Authority responsible for any loss sustained due to wrong
delivery of letter by postal authorities.
I / We do hereby agree to take full responsibilities for the adequacy, stability and safety of all
site operations and methods of construction towards the achievement of safe and sound construction
of building / buildings to be constructed me / us.
SIGNATURE: __________________________
N.I.C NO: _____________________________
(attach copy)
Registered Office Address: ________________
_______________________________________
34
FORM F-19
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section :24)
Gwadar Building Regulation 2005
No GDA/BCS/.. _____________________________Dated ___________________________
BUILDING SUPERVISOR LICENCE
(License No.________________)
Mr./Mrs./Miss.___________________________Addres______________________________
______________________________________________Telephone ____________________
S/o. / W/o. D/o. __________________________N.I.C. No.__________________________is
Hereby licensed to act as BUILDING SUOERVISO, under the GDA Building Regulation
2005 & Town Panning Regulation 2004 and amended from time to time in the Gwadar
Division.
This license is subject to terms and condition printed at
the reverse and will remain valid for the period ending 31st December_______________/
(Controller of Buildings)
Building Control Section
Gwadar Development Authority
Gwadar
Photograph
35
LICENSE No. ___________________
NAME_________________________
TERMS AND CONDITION
1. The licensee shall follow all the regulation farmed under GDA Act. 2003 amended up-to date
and direction issued by the GDA from time to time.
2. The licensee shall not Execute and supervise any unauthorized work or any work which is
being raised without approval of building plan or is not in accordance with the specifications,
plan , design and drawing approved by the GDA.
3. The licensee shall inform in time the GDA for any unauthorized, Work carried out by his
client, which is not in accordance with the plans approved by the GDA.
4. The licensee shall not willfully misrepresent any fact or make any false statement to the GDA
or suppress information of any material fact relating to the work for which he has been
engaged.
5. The licensee shall not disturb, defy to break the discipline of any office of GDA
6. The licensee shall prove to be competent and shall not frequently issue the undertaking for
supervision without any agreement with the client.
7. The licensee shall inform in writing the GDA of his discontinuance of any work (s) which the
client.
8. The licensee shall provide all assistance to the GDA and its officer in carrying out their duties
and provide all facilities in inspecting the building / site shall furnish the required information
from time to time.
36
FORM. F-20
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (GDA Act 2003)
Gwadar Building Regulation 2003
No GDA/BCS/.. _____________________________Dated ___________________________
BUILDER
(Licence No.__________)
M/s ___________________________________________________________
Registered business address ___________________________________________________
___________________________________________________________________________
Telephone No._________________________ Fax No._______________________________
Is hereby licensed to act as BUILDER, in category
_____________________________________
Under the GDA Building Regulation 2005 & Town Planning Regulation, 2004 and amended
from time in the Gwadar Division..
This licensed is subject to terms and conditions annexed herewith and will
remain valid for the period ending 31st December____________/
(Controller of Buildings)
Building Control Section
Gwadar Development Authority
Gwadar
37
LICENSE No. ___________________
NAME_________________________
TERMS AND CONDITION
1. The licensee shall follow all the regulation farmed under GDA Act, 2003 amended up-to date
and direction accordance with GDA. and Regulations issued by the GDA from time to time.
2. The licensee shall not Execute construct any unauthorized work or any work which is being
raised without approval of building plan or is not in accordance with the specifications, plan ,
design and drawing approved by the GDA.
3. The licensee shall not disturb, defy to break the discipline of any office of GDA.
4. The licensee shall provide all assistance to the officers of GDA in carrying out their duties
and provide all facilities in inspecting the building / site shall furnish the required information
from time to time.
5. The licensee shall follow all other term and conditions imposed with the approved building
layout plan. The licensee shall inform the GDA for any change in the project undertaken by
him after its approval.
6. The licensee both in case of individual and n case of registered company and its director/
partners shall be personally and severally held responsible for the breach of any provision of
the GDA Act, 2003 amended up to date and rules and regulations framed thereunder.
7. The licensee shall not willfully misrepresent any fact or make any false statement to the GDA
or suppress information of any material fact relating to the work for which he has been
engaged.
8. The licensee shall liable for penal action under GDA Act, 2003 amended up-to date and rules
and regulations framed thereunder.
38
FORM. F-21
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (GDA Act 2003)
Gwadar Building Regulation 2005
No GDA/BCS/.. _____________________________Dated ___________________________
FIRM LICENSE
(Material testing lab & GEO tech. lab)
(Licence No.__________)
M/s ___________________________________________________________
Registered business address ___________________________________________________
___________________________________________________________________________
Telephone No._________________________ Fax No._______________________________
Is hereby licensed to act as BUILDER, in category __________________________________
Under the GDA Building Regulation 2005 & Town Planning Regulation, 2004 and amended
from time in the Gwadar Division..
This licensed is subject to terms and conditions annexed herewith and will
remain valid for the period ending 31st December____________/
(Controller of Buildings)
Building Control Section
Gwadar Development Authority
Gwadar
39
LICENSE No. ___________________
NAME_________________________
TERMS AND CONDITION
1. The licensee shall follow all the regulation farmed under GDA Act, 2003 amended up-to date
and directions in issued by the GDA from time to time.
2. The licensee shall not willfully misrepresent any fact or make any false statement to the GDA
or suppress information of any material fact relating to the work for which he has been
engaged.
3. The licensee shall not disturb, defy breaking the discipline of any office of GDA.
4. The licensee shall inform in writing the GDA of his discontinuance of any work which were
undertaken by him.
5. The licensee shall provide all assistance to the GDA and its officers I currying out their
duties.
6. The licensee shall be liable for penal action under GDA Act, 2003 amended up-to date and
rules and regulations framed thereunder.
40
FORM F-22
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section :24)
Gwadar Building Regulation 2005
APPLICATION FOR RENEVAL FOR PROFESSIONAL LICENSED
BUILDING DESIGNER (License No.________________
BUILDING SUPERVISOR
I_____________________________S/o. / W/o. D/o. ________________________________
License for practicing as a _____________________________________________________
Gwadar Division
My particular are given below.
1. Residential / Permanent
Address.______________________________________________
2. Office
Address.____________________________________________________________
3. Challan No. And date of payment last made for renewal
of__________________________
________________________________________________________________________
_
4. N.I.C.No.________________________________________________________________
_
5. N.I.C.No________________________________________________________________
_
6. Has any adverse notice been issued by GDA ? if so please attached a copy along with the
decision / status.
Signature of applicant
Dated:
Notice : 1) Strike out whichever is not applicable.
Photograph
41
Stamp Paper Rs. 200/=
UNDERTAKING
(SHOULD BE SUBMETED ON STAMP PAPER)
In consideration of the grant of renewal of license I hereby undertake the following:
I do hereby agree to abide by all rules and regulations in respect of enlistment of
licensed Designer / GDA Building Control Ordinance, 2003 from time to time and shall be fully
responsible for all acts and deeds done under the above cited name and title.
I do hereby agree with free consent that the Authority reserve full rights to cancel or
suspend the license for a specified time or permanently for the breach of any terms and conditions as
specified in the regulation.
I undertake to intimate any change in my / our address or constitution of the firm /
Company ect, and shall not hold the Authority responsible for any loss sustained due to wrong
delivery of letter by postal Authorities.
I do hereby agree to take full responsibility for the adequacy stability and safety of all
site operations and methods of construction towards the achievement of safe and sound construction
of building / buildings to be designed / supervised by me.
I hereby certify that the details supply by me in the application for renewal remain
unchanged except as enclosed.
Signature of the Applicant
42
FORM F-23
GWADAR DEVELOPMENT AUTHORITY
BUILDING CONTROL SECTION (Under GDA Act 2003 Section :24)
Gwadar Building Regulation 2005
APPLICATION FOR RENEVAL OF BUILDER / FIRM LICENSED
BUILDER (License No.________________
FIRM
I / We____________________________ being a partner / Director / proprietor of M/s
__________________________________ hereby apply for the renewal of license for
practicing as a ____________________________________________Gwadar Division
My particular are given below.
1. Residential / Permanent Address of proprietor / partners
/Director__________________________________________________________
2. Registered business Address._________________________________________
3. Telephone No._________________________Fax No. _____________________
4. Challan No. And date of payment last made for renewal of__________________
5. Has any adverse notice been issued by GDA? if so please attached a copy along with the
decision / status.
Signature of applicant
Dated:
Notice : 1) Strike out whichever is not applicable.
2) Separate paper may be used if necessary.
Photograph
43
UNDERTAKING
(SHOULD BE SUBMETED ON STAMP PAPER) Rs. 200/=
In consideration of the grant of renewal of license I hereby undertake the following:
I / We do hereby agree to abide by all rules and regulations in respect of enlistment
of licensed Building / farmed under GDA Ordinance, 2003 from time to time and shall be fully
responsible for all acts and deeds done under the above cited name and title.
I/ We do hereby agree with free consent that the Authority reserve full rights to cancel
or suspend the license for a specified time or permanently for the breach of any terms and conditions
as specified in the regulation.
I/ We undertake to intimate any change in my / our address or constitution of the firm
/ Company etc, and shall not hold the Authority responsible for any loss sustained due to wrong
delivery of letter by postal Authorities.
I do hereby agree to take full responsibility for the adequacy stability and safety of all
site operations and methods of construction towards the achievement of safe and sound construction
of building / buildings to be designed / supervised by me.
I hereby certify that the details supply by me in the application for renewal remain
unchanged except as enclosed.
Signature of the Applicant
44
FORM P.F.S -1
BUILDING CONTROL SECTION
( UNDER GWADAR DEVELOPMENT AUTHORITY ACT 2003 )
The Controller of Buildings,
Gwadar Development Authority,
Governor House Road, GDA Complex,
Gwadar.
APPLICATION FORM
Subject: NO OBJECTION CERTIFICATE FOR SALE AND ADVERTISEMENT OF
HOUSES UNITS, FLATS / SHOPS / OFFICES ETC. UNDER GWADAR
DEVELOPMENT AUTHORIY BUILDING REGULACTION 2005 & TOWN
PLANNING REGULATION 2004.
(Name of Owner)
Working in the capacity of _________________________________________________________________
(Designation)
With M/s.____________________________________ who‟s registered office is situated
(Developer)
At_____________________________________________________________________________________
Address of the owner / Developer
_______________________________________________________________________________________
Hereby apply for grant of “No Objection Certificate” under section GDA Act 2003 for sale and
Advertisement of flats / houses / shops / offices etc. at our project__________________________________
Located on plot No._______________________________________________________________________
(Address of Project)
The required information / documents are supplied on the prescribed Project Design Form
enclosed.
____________________ ____________________ ___________________
Signature of Signature of Builder Signature of Owner /
Architect / Engineer with License No. Developer
Registration No.
Name.________________ Name.________________ Name.________________
_____________________ ______________________ ____________________
Seal of Architect/Engineer Seal of the Builder Seal of the Developer owner
45
INTRODUCTIONS:
Please read the following instructions carefully and follow them strictly while preparing case for NOC for
submission.
1. Incomplete applications or cases shall reject outright.
2. Application for NOC should be made on the original set of forms issued by the Building Control
Section, GDA and no Photostat of Form shall be accepted.
3. In case the applicant is other then the owner than a registered irrevocable power of attorney in favor
of the applicant duly signed by all owners / partners / Managing Directors or forms shall also be
submitted.
4. The form should be filled in very carefully and all entries dully replied and no item left untouched.
5. All enclosures should be according to the permit and order dully flagged.
6. All forms, enclosures, documents papers, etc, should be signed by the Developers and bear seal of the
Developer.
7. In case of insufficient space for entries attached separate sheets for details.
8. Incorrect entries may be crossed and corrections made and initialed but erasure is not permissible.
9. No addition or alteration in the prescribed format of undertaking will be acceptable.
10. While submitting the case in admittance slip shall be issued to the applicant showing his national
identity card no etc. And the same agent shall be authorized to deal with the case in the section and
will be issued Challan of scrutiny fee for payment and delivered NOCs. Proper authority letter from
the Developer in favor of agent shall be provided.
11. After initial scrutiny objection letter shall be issued after _________ days to which strict compliance
will be required. After serving to reminders the case will be closed.
12. Numbers, date and number of floors approved and the final building plan should be mentioned in the
draft of advertisement.
13. Draft of advertisement should be got approved form the GDA.
46
PROJECT DIGEST FORMS.
1- DETAILS OF PROJECT ARE GIVEN BELOW:
_______________________________________________________________________________________
1. NAME OF PROJECT:
_______________________________________________________________________________________
2. LOCATION OF PROJECT:
_______________________________________________________________________________________
3. HOUSING UNITS AVAILABLE: Total Nos.
----------------
Flats
____________________________
House / Bungalows.
____________________________
Commercial Units ( Shops )
____________________________
Offices.
____________________________
Show Rooms.
____________________________
Amenity Units.
____________________________
TOTAL
_________________________________________________________________________________
4. OWNER / DEVELOPER Name
____________________________
Mailing Address
____________________________
____________________________
_______________________________________________________________________________________
5. BUILDER Name / License No.___________
Enclosed copy of Agreement
Of assignment between Address of registered
Builder and Developer
Office______________________
____________________________
_______________________________________________________________________________________
6. PROFESSIONAL SUPERVISIOEN. Name of Architect.
ATTACHED PHOTO COPIES ____________________________
OF PROFESSIONAL LICENCES Name of Structural Engineer
____________________________
Name of Professional Engineer
____________________________
Name of Site Supervisor.
____________________________
SIGNATURE OF THE DEVELOPER
47
WITH SEAL
7. WHETER PROJECT IS NEW/ON GOING New/On going________________
Date. of Start
_______________________________________________________________________________________
8. PLOT CATEGORY Res/Comm.Agricul./Indust,
Plot Category_________________
Area.________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
9. The area falls within the
Jurisdiction of GDA Gwadar:-
_______________________________________________________________________________________
10. ORGANIZATIONAL SET UP OF THE Partnership firm___________________
DEVELOPER / BUILDER
Enclose Memorandum & Limited firm / private or
Article of Association in case Public concern
Of corporate organization or
Certificate from Registrar of firm. _________________________________________
_______________________________________________________________________________________
11. INCOME TAX REGISTRATION N.T No.________________ Date.______________
CERTIFICATE
Enclosed attested copy of _________________________________________
N.T. Registration of Developer /
Builder.
_______________________________________________________________________________________
12. DOCUMENTS.
_______________________________________________________________________________________
1- OWNERSHIP DOCUMENTS.
------------------------------------
Enclose attested copies of the following documents.
Allotment order. No.___________________Date._______________
Possession order No.___________________Date._______________
Ack. of possession _________________________________________
Indenture of Lease ________________________________________
Site Plan ________________________________________
Sale Dead. _________________________________________
SIGNATURE OF THE DEVELOPER
WITH SEAL
48
Transfer / Mutation Order. No.___________________Date._______________
Extract from property Register _________________________________________
From Deputy Commissioner of (or EDO Revenue) ________________________________________
________________________________________
______________________________________________________________________________________
2- APPROVAL OF BUILDING PLAN No.___________________Date._______________
--------------------------------------------
Enclose attested copies of the following
Documents.
Final Approved Building Plan No.___________________Date._______________
/type design for each category No. of storeys allowed:______
of Bungalows Ground Plus____________upper storeys.
Compellation / Occupancy
Certificate. No.___________________Date._______________
Types No OF Main + Ancillary .. Total Covered Area ( Sq.Ft )
Units Area Area
-----------------------------------------------------------------------------------------------------------------------------------
„A‟
„B‟
„C‟
„D‟
„E‟
„F‟
Enclosed plan showing units types
and covered area calculation
for gross and net
area of each unit. _____________________________________________________________
Enclosed plan showing serial No. of units._____________________________________________________
_______________________________________________________________________________________
SIGNATURE OF THE DEVELOPER
WITH SEAL
49
_______________________________________________________________________________________
3- TIME SCHEDULE. Date of Start
of construction:___________________________________
Present stage of construction________________________
_______________________________________________
Reason for delay, if any:____________________________
Enclose copy of the
Proposed / Revised work
Program. Date of compellation:______________________________
________________________________________________
(Annexure-4) Date of handing over possession of the units
-----------------------------------------------------------------------------------------------------------------------------------
4. units for sale: Total units of the project
___________________
Units Nos covered area price
Types main +ancillary demanded
------- ----- ------------------- ------------
A
B
C
D
E
F
Unit price @ Rs . __________per Sq:ft.
Terms and conditions
Of sale.___________
Price : fixed price & no escalation
And includes the price of development
i.e. constriction of Road ,water
supply & sewerage system I / c earth
filling if required.
Enclosed 2 nos of
1. Application form for allottes (Annexure-5).
2. Proposed terms and conditions for allottes
(Annexure-5).
3. schedule of payment ____________
Annexure -6
4.allocation letter , Annexure -7
SIGNATURE OF THE DEVELOPER
50
WITH SEAL.
5. UNDERTAKING FORM Clear title and ownership:
THE DEVELOPER/ BUILER ON
RS.______STAMP PAPER -------------------------------------
IN THE PRESCRIBED FROM construction according to the
(Annexure- 1 & 2) for: approved plan:_____________
Construction according to the
Approved specification: _______
New / original construction.
___________________________
Nos booking done previously.
Committing fixed price.
____________________________
Provision of services and amenities:
______________________________
Not committing excess applications
For booking
_______________________________
Supervision of construction.
Building strength and quality
Control.
_________________________________
Follow provisions of GDA Act 2003
& Gwadar Building Regulation 2005
Enclosed undertaking in
Original. __________________________________
6. UNDERTAKING FROM THE
PROFESSIONALS ON LETTER
HEAD ON THE PRESCRIBED
FORM (F-1.2 )
Construction according to
the approved plan________________________________
Planning & design of
project.________________________________________
Supervision of construction _______________________
Building strength and
Quality control._________________________________
Follow orders and instructions
of the Authority . ______________________________
Enclosed undertaking in
Original in the prescribed
From -----------------------------------------------------------------------
________________________________________________
SIGNATURE OF THE DEVELOPER
51
WITH SEAL.
7. Builder‟s license:
Enclosed attested copy Builder‟s license no._______________________________
Of the license duly
renewed.
Enclosed copy of agreement
of assignment between developer ________________________________________________
and builder.
8. DRAFT OF ADVERTISEMENT
(in English & Urdu only) _____________________________________________________
Enclosed draft of proposed
Advertisement with endorsement
Of the required
information. _____________________________________________________
9. CONTRACTOR „S ALL RISK
INSURANCE POLICY
____________________________________________________
Enclosed copy of insurance
policy
____________________________________________________
SIGNATURE OF THE DEVELOPER
WITH SEAL..
52
P.F.S-1
(Annexure- 1)
(Undertaking on Rs._______ stamp paper)
UNDERTAKING
I. ________________________________________________________________________________
(Name of Developer)
Working in the capacity of ________________________________________________________________
(Designation)
With organization M / s .__________________________________________________________________
Business address ________________________________________________________________________
do hereby undertake :-
1. that we are offering housing / commercial units , for sale to the general public
through advertisement , on the
Project ________________________________________________________________________________
Plot no.________________________________________________________________________________
2. That we will carry out the construction strictly according to the approved plan and
applications .
3. that we will use material for construction as required under the code
of practice specified.
4 That we will not mis-represent the fact in advertisement in respect of plane
specification, and date of completion etc. as approved by the Authority.
5. That we have not started the project as yet and intend to start on________________.
OR
That we started the construction with effect from ___________________ and the present
Stage of construction is as under:-
__________________________________________________________________________
__________________________________________________________________________
6. That we will not escalate the price without approval of the Authority as provided in
the regulations .
7. That the price of unit includes the share of price of development works e . g. Road,
water supply , sewerage system , earth filling etc ,Hence extra charges for the said development
works shall not be claimed.
8. That we shall not book any excess unit then the number provided in the
approved plane .
53
9. That we will honor all our commitments in respect of construction and sale of the
housing / commercial units.
10. That we will provide all requisite services e . g . water supply , sewerage disposal etc.
11 That we will complete the formalities for lease and loan from the relevant departments
and will render assistance to the allottees to get the sub-leases executed and obtain loan form HBFC.
12. The following professionals are assigned to prepare design and supervision of the project.
1. Name of professionals_____________________________________________
2. License / Registration No ._________________________________________
13. That I have assigned M/s_____________________________________________________
Builder
License no ________________________for the execution of construction works for the project.
14. That we will intimate the Authority in case of any change in the above professional set
up at any time.
15. That the ownership and title of the project is clear and no legal processing / dispute of sale
of land or allotment of housing units to buyers is pending in any court of law , or /Government
Agencies etc.
16. That in case of litigation or dispute with the owner / allottee due to which the progress of
work is likely to be affected we will intimate the allottes of the situation and will deal with the
matter according to the provisions of Gwadar Building Regulation under GDA Act 2003.
17. That we will not sell / transfer the plot and the project to any other person without prior
approval of the GDA.
18. That we have not appointed any booking agent for this project.
OR
That we have appointed M / s _____________________________________as Booking agent.
19. That we will carry out all orders and instructions given by the Authority in this regard.
1.Signature of Developer___________________________________________
2.Name of Developer ____________________________________________
3.C.N.I.C No.___________________________________________________
4.Malling address_________________________________________________
_________________________________________________
5.Office address Tele. No._________________________________________
6.Date.__________________________________________________________
54
P.F.S-1
(Annexure-2)
( Undertaking on Rs.200________stamp paper from Builder )
UNERTAKING
I,_______________________________________________________________________________
(Name of Builder)
Working in the capacity of ______________________________________________________________
(Designation)
With organization M / s. _________________________________________________________________
Business address _______________________________________________________________________
License No._____________________________________________________________________________
do hereby undertaking :-
1. That we have been appointed by M / s. ____________________________________________
(Name of the Developer)
for the execution of construction works for the project.______________________________________
_________________________________on the plot no.________________________________________
2. That we will carry out the construction strictly according to the approved plan and
specifications.
3. That we will use material for construction as required under the code of practice specified.
4. That we have not started the project as yet and intend to start on ______________________
OR
That we have started the construction with effect from _________________________and the
present stage of construction is as under:-
___________________________________________________________
___________________________________________________________
5. That in case of litigation or dispute with the owner / Developer due to which the
progress of work is likely to be effected we will intimate the Authority of the situation.
6. That we will carry out all orders and instructions given by the Authority in this regard.
1.signature of Builder__________________________________________________
2.Name of Builder __________________________________________________
3.C.N.I.C No.______________________________________________________
4.Malling address___________________________________________________
5.office address Tele. No._____________________________________________
_________________________________________________________________
6.Date.____________________________________________________________
55
P.F.S-1
(Annexure- 3)
Project”_________________________”
Location_________________________
PRICE ANALYSIS FOR THE PROJECT
Total amount Unit price percentage
For the project
(Rs.) Rs.per sq.m. of total
------------- ---------- ---------------
1. Cast of land, inclusive
Of all charges e. g.
Roads , water supply / sewerage
system , earth filling etc. and
includes all fees paid to any
civic or concerned Authority
@ Rs_______per sq.m.
2. Cost of civil work @Rs per sq.m
3. Cost of plumbing and sanitation
works @ Rs_______per sq.m.
4. Cost of electrical works @ Rs
_____per sq.m.
5. Cost of gas installation works
Rs _______
6. Consultant‟s Fee.
7. Advertisement and Brokerage.
8. Administrative / service charges
Including cost management.
9. Any Misc /overhead expenses
(please specify)
10. Developer‟s profit.
11. Anticipated escalation during
The approved period of construction______________________________________
Total
_______________________________________
With price- total price of the project
------------------------------------------------------
Total lease able are of the units in sq.m
Rs.__________per sq.m
56
NOTE:-
If the flats , bungalows etc are proposed to be constructed on land where development works
of the proposed scheme/ Township / project e. g . construction of Roads , water supply and sewerage
systems , earth filling etc. etc. are to be done by the Developer, the price of development works should be
included in the item No.1 above and in no way should be claimed from the buyers as extra charges for
development works.
SIGNATURE OF DEVELOPER
WITH SEAL
57
P.F.S-1
(Annexure – 4)
WORK PROGRAMME FOR THE
Project ;________________________________________________________________________________
(Name of project)
BEING CONSTRUCTED ON PLOT NO:_____________________________________________________
(Location of project)
DATE OF START :________________________DATE FO COMPLETION:________________________
_______________________________________________________________________________________ Year 20
S.NO ITEM OF WORK START COMPLETION
3 6 9 12 15 18 21 24 27 30
1. Layout &
Foundation works
up to plinth and
Basement if any
2. Plinth work
------------------------------------------------------------------------------------------------------------------------------- 3. Structure work.
-------------------------------------------------------------------------------------------------------------------------------
4. Block Masonry and fixing
of door and windows.
-------------------------------------------------------------------------------------------------------------------------------
5. Plumbing, Sanitation‟s
& Electrification.
-------------------------------------------------------------------------------------------------------------------------------
6. Plastering.
-------------------------------------------------------------------------------------------------------------------------------
7. Flooring with skirting &
dado.
-------------------------------------------------------------------------------------------------------------------------------
8. Painting & Glazing.
-------------------------------------------------------------------------------------------------------------------------------
9. Final finishing.
-------------------------------------------------------------------------------------------------------------------------------
10. Possession.
-------------------------------------------------------------------------------------------------------------------------------
PROGRESS REPORT TO THE SUBMITTED 1st 2
nd 3
rd
FINAL
---------------------------------------------------------------------------------------------------------------------------------
SIGNATURE OF THE DEVELOPER
WITH SEAL
58
P.F.S-1
From -1
( Annexure – 5 )
M/s_________________________
(Name of Developer)
------------------------------------------
Address of the Developer office
Gwadar.
APPLICATION FORM.
Subject :. Application for allotment of flat /shops/of/offices/Bungalow at the
project________________________________ being constructed.
Name of project
On plot No,______________________________________________
(location of the project)
Dear Sir,
I, the undersigned hereby request you to please register my name for the allotment of shop /flat/ office/
bungalow in your
project “_________________________________________ : on plot No.___________________________
Gwadar on cash /cash-cum –loan basic
1. Name:
2. Father‟s name:
3. Address :(i) office
(ii) Residential
4. Telephone No.(i)office (ii) Residential
5. Age:
6. Nationality:
7. Occupation:
8. Income (i) per month Rs. I (For loan applicants only)
9. Employer‟s Name & Address:
10. Assignee:
12. Choice of flat /shop/house/office
No. ________________________
Description of location & floor
No.________________________
13. Total price: Rs._______ +Rs._______=Rs._______
Cash loan , Total
59
14. Whether any loan has been taken by you or in the name of your wife from House Building Finance
Corporation or any other loan given agency or from your Department. Or any application made, if so, with
what results.
I hereby declare that I have read and understood the terms and conditions of the allotment of shop
/flat/house/office etc. and accept the same and further declare that I shall abide by the existing rules and
regulations, conditions, requirement s, etc. which may be prescribed by you and approved by the Authority for
the purchase of residential /commercial unit in this project. I also agree to make payment of the price
according to the approved schedule of payment partly in cash and partly by arranging loan. I also agree to
become a member of the, Association /society .which will be formed to look after the common and general
services and will regularly pay the fee ,etc. as may be decided by the Society /Association .
A cross cheque/pay order bearing No:__________________________ Date.__________________
amounting to Rs.____________________( Rupees____________________________________________ )
as registration fee is attached /paid in cash.
--------------------------------------------
Signature of Applicant.
Dated:
-----------------------------------------------
Signature of Developer.
1. In case of female applicant having no source of income, the Particulars of her husband /guardian
should be given.
60
P.F.S
Form -1
( Annexure-5 )
Project____________
Location___________
TERMS & CONDITION FOR ALLOTMENT OF FLAT / HOUSE / OFFICE/SHOP
------------------------------------------------------------------------------------------------------
1- NAME & LOCATION OF THE PROJECT
The name of the project shall be “_______________________________________________
which is being constructed on plot No.____________________________________________________
______________________________The project will consist of_________storey buildings.
2. BOOKING
The unit is offered for sale on ownership basis and the same shall be booked on, first come
first served‟ basis. The terms and conditions, specification, schedule of payment and
application form etc. shall be signed both by .DEVELOPER and the allottees and will form
part of the contract Agreement for allotment of the unit .The unit No. floor and total price and
specification committed, shall be confirmed by the DEVELOPER in the Allocation letter to
be issued by the developer.
3. TERMS OF OFFER FOR SALE
A unit shall be offered for sale on cash /cash cum loan basis as Per Schedule of payment
described in Annexure -6 and by virtue of sale, sub –lease shall be executed as per sale and
allotment Conditions in favor of allottee who shall own the building Structure or his unit and
shall share the price / rent of loaned of the unit with other allottees above and below.
4. PRICE OF UNIT.
The price of the unit shall not be increased or escalated by the Developer without approval of
the Authority. The Developer while fixing the price of unit shall take into account the
escalation anticipated during the declared construction period.
5. CONFIRMATION OF THE ALLOTMENT
The allocation of the unit shall be confirmed by the DEVELOPER through an allocation letter
to the allottees as specified in Annexure-7, within 45 days of booking. The allocation letter
shall specify the unit No. floor, the total price of the unit, specification committed and details
of other charges.
6. PAYMENT OF INSTALLMENTS
The payment of installments shall be made by the allottees strictly according to the schedule
of payment (Form Annexure-6) attached to the agreement. In case of failure, a 15 days notice
shall be issued by Registered A/D on the last given address and if the allottee fails to make
payment within the above period, another notice shall be issued by Developer extending the
period up to another 30 days. In case of further failure, a cancellation letter shall be issued to
the allottees, a copy of which shall be endorsed to the Authority. The Developer shall not
rebook the cancelled unit within 30 days of receipt of copy of
61
Cancellation letter by the Authority. During this period the Authority shall confirm through
Registered A/D from the allottee regarding the receipt of notices from the Developer and if
the same have not been received, and the allottee intends to continue the booking , the
Developer shall be directed to restore the allotment , after receipt of pending payment and
charging the mark-up on the prevailing rate of profit of the average of three scheduled banks
for the period of delay on unpaid installment. If no response to the Authority is received from
the allottee during the said period, the cancellation of the unit shall be confirmed
automatically. In case the cancellation is made before allocation, the Developer shall refund
the total amount paid till that time by the allottees within 60 days. However, after allocation
of unit, 31 of the total price of the unit shall be retained by the Developer, and the rest of
the amount shall be refunded within 60 days.
In spite of failure to make payment of installments in time, if the Developer does not resort to
cancellation as provided in these Regulations, the Developer may or may not charge markup
on the unpaid installments at the prevailing rate of profit of the average of three
Scheduled banks and the allottee shall be informed accordingly.
7. AVAILABILITY OF LOAN.
The Developer shall make full efforts to arrange the loan as mentioned in the schedule of
payment, if so requested by the allottee from HBFC or some other officially approved, .loan
giving agency .In case of sanction of loan the allottee shall abide by the rules and regulations
of the loan giving agency. If the loan is not granted by HBFC or other agency for any reason,
the allottee shall make arrangement for payment of the loan amount from his own resources
.However extra time of at least six monthly installments shall be given to the allottee to pay
loan component to the Developer.
The allottees must complete all documentation for lease and loan within, 120 days of booking
as written in the agreement and a reminder shall be Issued by the Developer .The repayment
of the loan installments shall be made by the allottee/borrower to HBFC or any other loan
given agency as and when it fails due as per rules of the relevant agency. The allottees /
borrower will abide by the arrangements of loan and will follow rules and regulations and
orders and instructions of HBFC or any other loan giving agency in this regard.
8. DOCUMENTATION & CONNECTION & METER CHARGES.
Documentation charge for sub-lease and loan, and external service connection charge for gas,
electricity , sewerage and water shall be paid in proportion to the unit area in accordance with
the actual payment made to these agencies plus 15% as service charges for their respective
services. This amount should be paid at the time of deposit of Challan. In case any allottee
fails to make this payment he shall pay mark up on the amount at the prevailing rate of profit
of the average of three Scheduled Banks.
9. CONSTRUCTION TO CONFORM TO THE PLAN & SPECIFICATIONS.
The building shall be constructed by the developer strictly according to the approved planned
specifications and minor changes, if any, may be made by the mutual arrangement between
developer and allottee subject to the condition that do not contravene any of the
Regulations.
62
10. SUB-LEASE EXECUTION
The sub- lease of the unit shall be executed in favor of the allottee before handing over the
possession of the unit , provided the allottee has made payment of outstanding amount up
to that time.
11. AVAIABILITY OF SERVICES
It shall be the sole responsibility of the developer to provide all requisite services e.g. water
supply, electricity gas, sewerage disposal system etc. before handing over possession or
completion of the project.
12. PROGRESS OF WORK
The DEVELOPER shall maintain steady progress of work irrespective of the situation of
payment by the individual allottee and availability of loan by loan given agency.
The DEVELOPER shall fulfill the obligations of timely completion of the flat even by
arranging the finances from their own resources .The DEVELOPER shall inform the allottees
every three months regarding progress of the project.
13. WITHDRAWAL OF ALLOTMENT
The allottee if so wishes can withdraw his/her allotment of the unit on surrendering the
original letter of allotment/allocation to the DEVELOPER and in this event the DEVELOPER
will refund to the allottee all the amount deposited till that time. In case the cancellation is
made before allocation the DEVELOPER shall refund total amount paid by the allottee till
cancellation within 60 days. However, after the allocation of the unit 3% of the total price of
the unit shall be retained by the developer and the rest of the amount shall be refunded within
60 days.
14. SUBLET & TRANSFERS OF ALLOTMENT
The allottee will not sublet, transfer or sell his unit to any one before taking possession with
prior written permission of the DEVELOPER. The DEVELOPER may allow such transfer on
receipt of payment of all outstanding dues up to that time and transfer fee of 0.5% of total
price of unit. However not transfer fees shall be charged in case the transfer is required
made within 3 months of allocation.
15. DELALY IN TAKING OVER POSSESSION
The Developer shall, after obtaining occupancy certificate from the Authority, which shall
include the provision of electric, water and sewerage services, issue intimation letters. The
allottee shall take over possession of the unit within 15 days of receipt of such letter from the
builder. In case of delay the Developer shall charge per month as specified in the agreement
from the allottee for care-taking of the unit in good condition.
16. COMPLETION OF THE PROJECT.
The Developer shill completes the project and hand over physical possession of the unit
complete in all respect to the allottee by the time specified by the Authority. In case of delay
in handing over possession, the Developer shell pay markup to the allottee at the rate of profit
of the average of their standard banks on the total, amount paid, from the period of delay, for
the time specified or extension made thereof by the Authority.
63
17. MAINTENANCE CHARGES.
The allottee shall pay in advance 6 months maintenance/service charges to the Developer as
called out in the agreement while taking over possession of unit after issuance of occupancy
certificate to make regular payment of outstanding bills and charges of the various department
.and pay to maintenance staff e.g. .Chowkidar, electrician, sweeper etc. employed for proper
upkeep of the project. However, proper account shall be maintained by the Developer and the
same shell be transferred to the Allottees association as and when formed.
19. ABANDONMENT OF THE PROJECT.
If, for any reason, the project is abandoned by the Developer, the Developer will refund the
total amount received from the purchaser with damages at the rate of profit of the average of
three scheduled banks on the same, for the whole period of retention of the money, along with
an additional compensatory amount equal to 10 % of the amount received from the allottee up
–to –date against the booked unit, within 60 days of the announcement to the effected of the
abandonment of the project.
20. MAINTENANCE PERIOD
The Developer shall assume Defect ability of the unit for a period of 12 months from the date
of offering possession of the unit after obtaining occupancy certificate , and all defects shell
be rectified to the satisfaction of the Authority. However, if defects resulted for reasons of
deviations from design or specifications agreed to between allottees and Developer,
Developer liability shall remain until such deviations are removed.
21. SETTLEMENT OF DISPUTES
All disputes of the Developer and the allottee relating to the unit shall be referred to the
Authority for settlement. The decision of the Authority shall be referred for appeal to the
Public hearing committees, comprising the following members, within 60 days from the
decision of the Authority ( or committee suggested by Director General)
COB Design Secretary.
Chairman PEC or his nominee.
Chairman PCATP or his nominee.
Chairman ABAD or his nominee.
One representative from …………….
In the absence of any such appeal the decision of the Authority shall be binding on all parties.
22. ORDERS AND INSTRUCTIONS OF THE AUTHORITY.
Besides the above Regulations, the orders and instructions of the Authority in accordance
with these Regulations issued from time to time in this regard shall be followed strictly.
23. FORMATION OF ASSOCIATION / SOCIETY.
The maintenance of the services and amenities at the project will be finally looked after by
the allottees who would form an Association/ Society to handle the affairs of the project. The
rights of easement, appurtenances and other common rights shall be transferred to such
Association /society.
64
24 PAYMENTS
All payments shall be made by the allottee by cheque/pay
Order/bank draft / cash in the name of M/s._______________________________________
------------------------------------------------ ------------------------------------------
SIGNATURE OF THE DEVELOPER SIGNATURE OF THE APPLICANT/
WITH DATE. ALLOTTEE WITH DATE
65
P.F.S-1
( Annexure-6 )
SCHEDULE OF PAYMENT
(For Flats / Office etc.)
Project_____________________
Location____________________
___________________
(Amount in Rs.)
S.No. Installment. Flats/ Type ‟A‟ Type „B‟ Type „C‟
offices
--------------------------------------------------------------------------------------------------------------
Cash Cash Cash Cash Cash Cash
Basis cum-loan basis cum-loan, basis cum-loan.
-----------------------------------------------------------------------------------------------------------------------------------
1. On booking 5%
2. On allocation 5%
3. On completion
Of plinth of
Concerned
Block 5%
(As certified by GDA)
4. On casting
Column of
Concerned
Floor---5%
5. On cast of
roof slab
of concerned
floor 5%
(As certified by GDA)
6. On completion
Of block masonry
of the Concreted unit 5%
7. On completion of
sanitary plumb-
ing work of the
concerned units 5%
8. On completion of
plaster of con-
corned units 5%
9. On completion of finishing
of the concerned unit
including doors , window ,
66
Complete book up to
Utility agencies and
Installation of lift (if
Applicable ) 10%
11. On possession 10%
12. Balance 40% shall be paid
in equal quarterly installments
payable after every 3 months
from the date of allocation,
depending upon the time period
of the project, provided that
the construction is in
accordance with the schedule.
Total cash ____________________________________
HBFC Loan ____________________________________
Total average price:
NOTE
--------
1. The above mention prices does not include documentation charges for sublease and loan, and
external services connection charges Gas, Electric city, sewerage and water. This shall be paid in
proportion to the unit area in accordance to the actual payment made to these Agencies plus 15% as
service charges. This amount should be paid at the time of deposition of Challan.
2. The above mention prices do not include the, extra floor corner charges. The amount of above
mentioned charges should be clearly indicated on the application form and obtains the sign of the
allottee at the time of booking. These extra charges shall be realized in the same percentage as
above.
3. The above mentioned prices also include the cost of land and charges of development work e.g. Road,
Water supply & Sewerage systems, earth filling etc.etc. to be done in the proposed sch. / Township /
project.
--------------------------------------------------------
Signature of Applicant
Dated:
----------------------------------------------------------
Signature of Developer.
67
P.F.S-1
(Annexure -6)
SHEDULE OF PAYMENT
(For one Unit Bungalows)
(Amount in Rs.)
Project_____________________
Location____________________
----------------------------------------------------------------------------------------------------------------------------------
S.No. installment. Bungalow Type, A, Type ,B, Type ,C,
------------------------------ ------------------------- ---------------------------------------
Cash Cash Cash Cash Cash Cash
Basis cum-loan . basis cum-loan. Basis cum-loan.
-----------------------------------------------------------------------------------------------------------------------------------
1. On booking 5%
2. On allacation5%
3. On completion
of plinth of
concerned
Bungalow 5%
(As certified by GDA)
4. On casting
foundation of
concerned
Bungalow 5%
5. On casting
roof slabs of
ground floor
of concerned
Bungalow 10%
(As certified by GDA)
6. On casting of
roof slab of
1st floor of
concerned Bungalow 10%
(As certified by GDA)
7. On completion
of block masonry
of the concerned
Bungalow 10%
8. On completion of
sanitary & plumbing
work of the concerned Bungalow 10%
9. On completion of
68
plaster of the
concerned Bungalow 10%
10. On completion
of doors/windows
of concerned
Bungalow 10%
11. On completion of
finishing including complete
hook up to utility agencies 10%
12. On possession 10%
Total cash -----------------------------------------------------------
HBFC loan. -----------------------------------------------------------
Total average Price:
NOTE
--------
1. The above mention. Prices do not include documentation charges for sublease and loan, and external
services connection charges Gas, Electric city, Sewerage and water. This shall be paid in proportion to the unit
area in accordance to the actual payment made to these agencies plus 15% service charges the amount should
be paid the time of deposition of Challan.
2. The above mentioned prices do not include the, extra floor corner charges. The amount of above
mentioned charges should be clearly indicated on the application form and obtains the sign of the allottee at
the time of booking. These extra charges shall be realized in the same percentage as above.
3. The above mentioned prices also include the cost of land and charges of development works e.g.
Roads , Water supply & Sewerage systems , earth filling etc. to be done in the proposed Scheme are /
Township / Project.
--------------------------------
Signature of Applicant
Dated:
----------------------------------
Signature of Developer.
69
P.F.S-1
Form -1
(Annexure -6)
SHEDULE OF PAYMENT
(For Single storey Bungalows)
Project________________________
Location ______________________
_______________________
(Amount in Rs.)
-----------------------------------------------------------------------------------------------------------------------------------
S.No .installment. Bungalow Type „A‟ Type „B‟ Type „C‟
----------------------------------------------------------------------------------------------
Cash Cash Cash Cash Cash Cash
basis cum-loan. basis cum-loan basis cum-loan
-----------------------------------------------------------------------------------------------------------------------------------
1. On booking 5%
2. On allocation 5%
3. On casting foundation
of concerned
Bungalow. 5%
4. On completion of
Plinth of concerned
bungalow 5%
(As certified by GDA)
5. On casting columns
of concerned
Bungalow 5%
6. On casting of
roof slab of
concerned bungalow 10%
(As certified by GDA)
7. On completion of
block masonry of the
concerned Bungalow 10%
8. On completion of sanitary
& plumbing work of the
concerned Bungalow 10%
9 . On completion of
Plaster of the
Concerned Bung. 10%
10. on completion
of doors/windows
of concerned
70
Bungalow 10%
11. On completion of
Finishing
Including complete hook up to utility agencies 10%
12. on possession after obtaining
completion certificate 10%
Total cash -----------------------------------------------------------
HBFC loan. -----------------------------------------------------------
Total average Price:
NOTE
--------
1. The above mention. Prices do not include documentation charges for sublease and loan, and external
services connection charges Gas, Electric city, Sewerage and water. This shall be paid in proportion to the unit
area in accordance to the actual payment made to this at the time of deposition of challan.
2. The above mentioned prices do not include the, extra floor corner charges. The amount of above
mentioned charges should be clearly indicated on the application form and obtains the sign of the allottee at
the time of booking these extra charges shall be realized in the same percentage as above.
3. The above mentioned prices also include the cost of land and charges of development works e.g.
Roads, water supply &Sewerage systems, earth filling etc. to be done in the proposed Scheme. / Township /
Project.
-------------------------------
Signature of Applicant
Dated:
----------------------------------
Signature of Developer.
71
P.F.S-1
From DNP-1
(Annexure- 7)
ALLOCTION RECEIPT.
The application of Mr./Miss/Mrs_________________________for the allotment of
residential / commercial unit in the project___________________ situated on plot
No._________________________ is hereby Accepted and allocation is made under the following
terms and conditions:-
i) Unit No. allotted .
ii) Floor No.
iii) Total floor area of unit.
iv) Committed specification, (as approved by GDA)
(enclosed).
v) Total price of the unit.
vi) Other charges.
(If any specify)
Final allotment letter shall be issued after 3 months
on________________.
SIGNATURE OF DEVELOPER.
Dated:_______________.
72
P.F.S-1
From -1
(Annexure-8)
NAME OF THE PROJECT ____________________________________________
LOCATION :________________________________________________________
SPECIFICATIONS OF CONSTRUCTION FOR RESIDENTIAL /
COMMERCIAL UNITS. (to be provided with details under each of the
following head).
1. STRUCTURE
R.C.C. structure with columns , beams and slab with spread footings and
underground and overhead tanks using min as per approved structural details .
2. PARTITION WALLS.
1:2:6 comment concrete block masonry walls 6 & 4” thick.
3. DOOR , WINDOWS & VENTILATORS SPECIFICATION.
4. PLASTER SPECIFICATION.
5. FLOORING SPECIFICATION.
6. PAINTING & FINISHIGN SPECIFICATION.
7. WATER SUPPLY & SEWERAGE LINES SPECIFICATION.
8. BATHROOM & W. C FITTINGS SPECIFICATION.
9. KITCHEN SPECIFICATION.
10. ELECTRIFICATION SPECIFICATION.
11. GAS SUPPLY SPECIFICATION.
12. EXTERNAL DEVELOPMENT & COMMON FACILITIES.
1) Complete water supply system with U/G and O/H tank with pump and motor including
connection from PHE Gwadar.
2) Complete sewerage system.
3) Paved car parking area between blocks of building.
4) Compound wall and gates.
5) Compound lighting .
6) Fire hydrant ( If Applicable )
7) Landscaping including lawn, tree and plantation.
8) Tube wall with pump installation.
73
P.F.S-1
From -1
GUIDE – LINES REGARDING DRAFT OF ADVERTISEMENT
1. It should be got prepared by the advertiser.
2. It should not be deviated i.e. the actual advertisement
Should be according to draft approved by the Authority
3. It should contain the following necessary endorsements :-
a) Name & address of the Project.
b) Types, Nos., covered area & total price of units
c) Last date of handing over possession.
d) Name of builder/owner/attorney.
e) Number and date of approved building plan.
f) Number and date of NOC for advertisement for sale.
g) Number of floors.
h) Name of professionals.
4. An undertaking on Rs_____________ stamp paper should be produced that deviation from
approved draft advertisement shell not be made in any way and in case of default the N.O.C for
advertisement for sale shall be liable to cancellation /suspension.
74
P.F.S
Form -1
PARTICULARS OF DIRECTORS/PARTNERS/
PROPRIETOR OF CONSTRUCTION BUILDER & DEVELOPER
S.NO NAME OF DIRECTORS / PRESENT RESIDENTIAL PERMANAT ADDRESS TELEPHONE /FAX
NOS.
PARTNERS / PROPIETOR ADDRESS
WITH NIC NO.
75
P.F.S-2
(Annexure -9)
(Undertaking on Rs. /- stamp paper from Builder)
UNDERTAKING
1._______________________________________________________________________________ ( Name of Builder )
working in the capacity of _______________________________________________________________ ( Designation )
with organization M /s. __________________________________________________________________
Business address ________________________________________________________________________
License No .____________________________________________________________________________
do herby undertake :-
1. That we have been appointed by M / s ._______________________________________________ ( Name of the Developer )
for the execution of Development works for the project_______________________________________
_______________________________on the plot / Khatooni Khasra No. ___________________________
2. That we will carry out the Development strictly according to the approved
layout plan and specifications.
3. That we will use material for Development as required under the code of practice
specified.
4. That we have not started the Development works of the project as yet and intend
to start on______________.
OR
That we have started the Development with effect from _____________ and the present
stage of development is as under :-
___________________________________________________
___________________________________________________
5. That in case of litigation or dispute with the owner / Developer due to which the progress
of work is likely to be affected we will intimate the Authority to the situation.
76
P.F.S-2
Form -2
PARTICULARS OF DIRECTORS/PARTNERS/
PROPRIETOR OF CONSTRUCTION BUILDER & DEVELOPER
S.NO NAME OF DIRECTORS / PRESENT RESIDENTIAL PERMANAT ADDRESS TELEPHONE /FAX
NOS.
PARTNERS / PROPIETOR ADDRESS
WITH N.I.C NO.
77
P.F.S-2 FORM -1
BUILDING CONTROL SECTION
( UNDER GWADAR DEVELOPMENT AUTHORITY ACT 2003 )
No GDA/BCS/.______________________________Dated:________________________________
Mr./Mrs./Miss.___________________________________________________________________
(Developer)
Subject: Noc for Construction / Development & Sale of ________________________ at
________________________on Plot No. / Khatono/ Khewat_______________ Khasra
No._________Intekal No._______Block No.___________ Scheme No._____________________
Reference your application No ________________________________ dated ________________
Your above mentioned case is under scrutiny in this Deptt. For issuance of NOC it is
pointed out that the following information / clarification / explanation is also required:-
You are advised to supply the above Information / clarification / explanation within
one week.
Please note final scrutiny shall be done only when you supply the required
information.
( Controller of Buildings )
Building Control Section
Gwadar Development Authority
Gwadar
78
P.F.S-2 FORM -2
BUILDING CONTROL SECTION
( UNDER GWADAR DEVELOPMENT AUTHORITY ACT 2003 )
No GDA/BCS/.______________________________Dated:________________________________
Mr./Mrs./Miss.___________________________________________________________________
(Developer)
Subject: NO OBJECTION CERTIFICATE FOR ADVERTISEMENT FOR SALE
OF________ ________________________ AT ________________________ON PLOT NO.
____________________________________________________ __________________________
Reference your application dated: ____________________________
I have been directed to convey the approval of the proposed advertisement for the
above. It has been approved with the following necessary information:
1- Name & location of the Project.
2- No. And date of issue of N.O.C.
3- Type of Flat / bungalow / office / shops.
4- Area of each flat / bungalow / office / shop.
5- Cost of each type of flat / bungalow including loan.
6- Date of handing over physical possession of flat / bungalow.
7- Number of each type of bungalow / flats offered for sale.
8- Number of floors / plot area.
9- Name of Builders & Professionals.
A copy of the approved advertisement is enclosed herewith. No addition or alteration shall be
made in the approved advertisement.
( Controller of Buildings )
Building Control Section
Gwadar Development Authority
Gwadar
Copy to:
1. M/s. _________________________
(Builder)
2. Professionals.
3. P.S to DG, GDA.
79
P.F.S-3
FORM -3
BUILDING CONTROL SECTION
( UNDER GWADAR DEVELOPMENT AUTHORITY ACT 2003 )
No GDA/BCS/.______________________________Dated:________________________________
Mr./Mrs./Miss.___________________________________________________________________
(Developer)
Subject: NO OBJECTION CERTIFICATE FOR ADVERTISEMENT FOR SALE
OF________ ________________________ AT ________________________ON PLOT NO.
___________________________________________________________________
Reference your application dated: ____________________________
I have been directed to convey the approval of the proposed advertisement for the
above. It has been approved with the following necessary information:
1. Name & location of the Project.
2. No. And date of issue of N.O.C.
3. Type of Plots.
4. Area of each type of plot
5. Cost of each type of plot.
6. Date of handing over physical possession of plot.
7. Number of each type of plot offered for sale.
8. Total area of Township scheme and amenity area.
9. Name of Builders & Professionals.
A copy of the approved advertisement is enclosed herewith. No addition or alteration shall be
made in the approved advertisement.
( Controller of Buildings )
Building Control Section
Gwadar Development Authority
Gwadar
Copy to:
1. M/s. _________________________
(Builder)
2. Professionals.
3. PS to DG, GDA..
80
P.F.S-4 FORM -4
BUILDING CONTROL SECTION
( UNDER GWADAR DEVELOPMENT AUTHORITY ACT 2003 )
No GDA/BCS/.______________________________Dated:________________________________
Mr./Mrs./Miss.___________________________________________________________________
(Developer)
Subject: NO OBJECTION CERTIFICATE FOR SUB LEASE PURPOSE OF
HOUSE / OFFICES / SHOPS / FLATS etc. AT ____________________________PLOT NO.
____________________________ __________________________________________________
Reference your application dated: ____________________________
Mr./Mrs./Miss.______________________________________________________
(Developer)
Whose registered office is situated at________________________________________________ are
hereby granted No Objection Certificate for sub- lease at:-
This No Objection Certificate is subject to terms and conditions as annexed hereto
and shall be exhibited at a conspicuous place in their office for guidance and information of the
public.
( Controller of Buildings )
Building Control Section
Gwadar Development Authority
Gwadar
Copy to:
4. M/s. _________________________
(Builder)
5. Professionals.
6. PS to DG, GDA
81
TERMS & CONDITIONS FOR “NO OBJECTION CERTIFICATE”.
NAME & ADDRESS OF THE PROJECT.
1. THE SELLING PRICES OF THE FLATS / HOUSES / OFFICES / SHOPS etc.
SHALL BE AS UNDER:-
2. The above prices are fixed and are valid up to completion of the project and include cost of
land, cost of development (i.e. water supply / sewerage system, Road, earth filling etc.etc),
cost of construction, plumbing and sanitation and electrification with all items in the
approved specifications excluding connection and the meter charges of water, electricity and
gas and documentation charges for lease and loan.
3. The approved specification for construction shall strictly be followed.
4. The following numbers of unit shall be offered for sale to the public.
Unit type Total Nos.
5. The completion and handing over of physical possession of the flats / houses / shops / offices
etc. shall be done as per the following programme.
6. „Fixed price and No escalation‟ clause shall be incorporated in the terms and conditions of
the agreement.
7. Arrangement for service road, water supply, drainage, electricity and landscaping etc. shall be
made at site by the DEVELOPER at their own cost if required during construction.
8. Provision of Electric sub-station, if required, will be made on the basis of the requirements of
Q.E.S.C.O.
9. The construction shall continuously be supervised by the Professional‟s concerned.
10. The specific terms & conditions of the local authority concerned regarding the plot of land, if
applicable, will also be followed in too.
11. The „No Objection Certificate‟ shall be valid up to:-
12. This „No Objection Certificate‟ shall automatically be cancelled if any of its conditions are
violated.
13. The „No Objection Certificate‟ is liable to be cancelled if at any stage it is found that it is
obtained by misrepresentation of the facts.
82
14. The maintenance of the services and amenities at the project will be finally looked after by
the allottees who would form an Association / Society. The right of easement, appurtenance
and other common rights shall also be transferred to such Association / Society when formed.
15. The flats / houses / shops / offices / etc shall be sold on ownership and with fixed. Price and
no escalation basis and will be delivered on the date as committed in the agreement.
16. No increase in prices shall be made without approval of the authority.
17. Ant extra item, apart form the approved specification, shall be done with mutual agreement
with the buyers.
18. In case of delay in completion and handing over physical possession of the flats the Builder
shall pay the charges as prescribed under section-13 (3) and in case of failure on the part of
the buyer, the buyer shall pay the charges as laid down in section-15 of the Gwadar Building
Regulation Act-2003.
19. The amenities and car parking etc. shall neither be converted nor mis-utilized or rented out
but will be reserved exclusively for the benefit of the residents of the flats.
20. The Developer shall assume Defect Liability of the unit for a period of 12 months from the
date of offering possession of the unit after obtaining occupancy certificate, and all defects
shall be rectified to the satisfaction of the Authority. However, if defects resulted for reasons
of deviations from design or specification agreed to between allottees and Developer,
developer liability shall remain until such deviations are removed.
21. All disputes of the Developer and the allottees relating to the unit shall be referred to the
Authority for settlement. The decision of the Authority shall be referred for appeal to the
Public Hearing Committee, comprising by the competent Authority, within the 60 days from
the decision of the Authority.
In the absence of any such appeal the decision of the Authority shall be binding on all parties.
( Controller of Buildings )
Building Control Section
Gwadar Development Authority
Gwadar
83
P.F.S-5
FORM -5
BUILDING CONTROL SECTION
( UNDER GWADAR DEVELOPMENT AUTHORITY ACT 2003 )
No GDA/BCS/.______________________________Dated:________________________________
Mr./Mrs./Miss.___________________________________________________________________
(Developer)
Subject: NO OBJECTION CERTIFICATE FOR SUB LEASE OF PLOT AT.
____________________________ __PLOT NO. / SURVEY NO.___________________
Reference your application dated: ____________________________
Mr./Mrs./Miss.______________________________________________________
(Developer)
Whose registered office is situated at________________________________________________ are
hereby granted No Objection Certificate for sub- lease at:-
This No Objection Certificate is subject to terms and conditions as annexed hereto
and shall be exhibited at a conspicuous place in their office for guidance and information of the
public.
( Controller of Buildings )
Building Control Section
Gwadar Development Authority
Gwadar
Copy to:
1. M/s. _________________________
(Builder)
2. Professionals.
3. PS to DG, GDA.
84
TERMS & CONDITIONS FOR “NO OBJECTION CERTIFICATE”.
NAME & ADDRESS OF THE PROJECT.
1. THE SELLING PRICES OF THE PLOTS SHALL BE AS UNDER:-
2. The above prices are fixed and are valid up to completion of the project and include cost of
land, cost of development (i.e. water supply / sewerage system, Road, earth filling etc.etc),
cost of construction, plumbing and sanitation and electrification with all items in the
approved specifications excluding connection and the meter charges of water, electricity and
gas and documentation charges for lease and loan.
3. The approved specification for construction shall strictly be followed.
4. The following numbers of plots shall be offered for sale to the public.
Plot type Total Nos.
5. The completion and handing over of physical possession of the plots shall be done as per the
following programme.
6. „Fixed price and No escalation‟ clause shall be incorporated in the terms and conditions of
the agreement.
7. Arrangement for service road, water supply, drainage, electricity and landscaping etc. shall be
made at site by the DEVELOPER at their own cost if required during construction.
8. Provision of Electric sub-station, if required, will be made on the basis of the requirements of
Q.E.S.C.O.
9. The construction shall continuously be supervised by the Professional‟s concerned.
10. The specific terms & conditions of the local authority concerned regarding the plot of land, if
applicable, will also be followed in too.
11. The „No Objection Certificate‟ shall be valid up to:-
12. This „No Objection Certificate‟ shall automatically be cancelled if any of its conditions are
violated.
13. The „No Objection Certificate‟ is liable to be cancelled if at any stage it is found that it is
obtained by misrepresentation of the facts.
14. The maintenance of the services and amenities at the project will be finally looked after by
the allottees who would form an Association / Society. The right of easement, appurtenance
and other common rights shall also be transferred to such Association / Society when formed.
85
15. The plots shall be sold on ownership and with fixed. Price and no escalation basis and will be
delivered on the date as committed in the agreement.
16. No increase in prices shall be made without approval of the authority.
17. Any extra item, apart from the approved specification, shall be done with mutual agreement
with the buyers.
18. In case of delay in completion and handing over physical possession of the flats the Builder
shall pay the charges as prescribed under section-13 (3) and in case of failure on the part of
the buyer, the buyer shall pay the charges as laid down in section-15 of the Gwadar Building
Regulation Act-2003.
19. The amenities and car parking etc. shall neither be converted nor miss utilized or rented out
but will be reserved exclusively for the benefit of the residents of the flats.
20. The Developer shall assume Defect Liability of the unit for a period of 12 months from the
date of offering possession of the unit after obtaining occupancy certificate, and all defects
shall be rectified to the satisfaction of the Authority. However, if defects resulted for reasons
of deviations from design or specification agreed to between allottees and Developer,
developer liability shall remain until such deviations are removed.
21. All disputes of the Developer and the allottees relating to the unit shall be referred to the
Authority for settlement. The decision of the Authority shall be referred for appeal to the
Public Hearing Committee, comprising by the competent Authority, within the 60 days from
the decision of the Authority.
In the absence of any such appeal the decision of the Authority shall be binding on all parties.
( Controller of Buildings )
Building Control Section
Gwadar Development Authority
Gwadar
86
P.F.S-6
FORM -6
MODEL OF AGREEMENT BETWEEN THE DEVELOPER AND THE ALLOTTEE
(FORBOOKING OF APARTMENT / SHOPS / HOUSE / OFFICE) ON STAMP PAPER Rs:1000/=
This Agreement is made on _____________ day of ____________19
Between _______________________________ the DEVELOPER having his head office at
________________________________________ through its Managing Director / Managing Partner /
Proprietor hereinafter referred as the vender and being party of the first party and
Mr./Mrs./Miss_______________________________ S/O, W/O, D/O __________________________
residing at _________________________________________________________________ hereinafter
referred to as the vendee being party of the 2nd
party.
Whereas the Vendor is constructing / developing the Project consisting of flats / shops / houses /
offices on plot No.__________________________________________ as per building plan approved by the
GDA. Vide their letter No. ___________________________________________ for selling the same to the
public as per terms of N.O.C granted by GDA to the vendee vide letter No. __________________________
Whereas the vendee has agreed to purchase the shops / flat / office / house No. _________ on _____
Floor against the total sale consideration of Rs. ___________________ and whereas vendor has agreed to sell
it to the vendee against the above said consideration, now throughout this agreement enter into between the
parties on the terms and conditions set herein below:-
1. That the total consideration payable by the vendor to the vendor shall be Rs. ______________ out
of which the vendee has to pay to the vendor the sum of Rs. ______________ (acknowledgement
whereof has already been issued by the vendor and which the vendor hereby also admits). The
remaining amount of Rs. ________________ shall be payable by the vendee to the vendor as per
schedule of payments attached.
2. That the vendor shall complete the construction of the shops / flats / houses / offices by
_________________________ as specified in the NOC issued by GDA. If the vendor fails to
deliver the possession within the period, the DEVELOPER shall pay markup to the allottees at
rate of the profit of the average of three scheduled banks on the total amount paid, for the period
of delay, by the time specified or extended by the GDA.
3. That the vendor shall assume Defect Liability of the unit for a period of 12 months from the date
of offering possession of the unit after obtaining Occupancy Certificate, and all defects shall be
rectified to the satisfaction of the Authority. However if defects resulted for reason of deviation
from design or specifications agreed to between allottees and Developer, developer liability shall
remain until such deviation removed.
4. That the payments of installments shall be made by the vendee strictly
Schedule of payment annexed:-
To the agreement. In case of failure, a 15 day notice shall be issued
Registered A/D on the last given address and if the allottee fails to make payment within the
above period, another notice shall be issued by the developer extending the period up to another
30 days. In case of further failure, a cancellation letter shall be issued to the allottee, a copy of
which shall be endorsed to the Authority. The Developer shall not rebook the cancelled unit
within 30 days of receipt of copy of cancellation letter by the Authority.
During this period the Authority shall confirm through Registered A/D from the allottee regarding
the receipt of notices from the Developer, and if the same have not been received, and the allottee
intends to continue the booking the Developer shall be directed to restore the allotment, after
receipt of pending payment and charging the mark-up on the prevailing rate of profit of the
average of three scheduled banks for the period of delay on unpaid installment.
87
If no response to the Authority is received from the allottee during the said period, the
cancellation of the unit shall be confirmed, automatically. In case the cancellation is made before
allocation, the Developer shall refund the total amount paid till that time by the allottee within 60
days. However, after allocation of unit 38 of the total price of the unit shall be retained but the
Developer, and the rest of the amount shall be refunded within 60 days.
In spite of failure to make payment of installment in time, if the Developer does not resort to
cancelation as provided in this Regulation, the Developer may or may not charge markup on
unpaid installments at the prevailing rate of profit of the average of three scheduled banks and the
allottee shall be informed accordingly.
5. That the vendee agree to make payment to the vendor on cash-cum-loan basis, if the loan if
sanctioned in vendee‟s favor by any loan giving agency. If the loan is refused or the amount of
loan is reduced due to any reason whatsoever by the loan giving agency, the vendee shall pay the
loan amount from its own resources. However extra time of at least six months shall be given to
vendee to pay the loan competent to vendor.
6. That the vendee if so wishes can withdrew his/her allotment of the unit
By surrendering the original letter of allotment / allocation to the company and in this event the
company will refund to the allottee the amount deposited till that time. In case the cancellation is
made before allocation the Developer shall refund total amount paid by the allottee till
cancellation within 60 days. However, after the allocation of unit 3 of total price of the unit shall
be retained by the Developer and the rest of amount shall be refunded within 60 days.
7. That the vendee undertakes to call at the office of the Vendor / office of the Sub-Registrar as and
when required for any documentation.
8. That the vendee will not sub-let, transfer or sell his unit to any one before taking over the
possession, without proper written permission of the Developer, who may allow such transfer on
receipt of all outstanding dues up to date time and transfer fee of 0.51 of total price of unit.
However no transfer fee shall be charged in case the transfer is made within 3 months of
allocation.
9. That the vendee shall pay to the vendor Documentation charges for sub-lease and loan, and
external service connection charges for gas, electricity, sewerage and water shall be paid on
proportion to the unit area in accordance with the actual payment made to these agencies plus 15
as service charges for their respective services. This amount should be paid at the time of deposit
of Challan. In case any allottee fails to make this payment he shall pay markup on the amount at
the prevailing rate of profit of the average of three scheduled banks.
10. That the vendee agrees to make payment of Rs. ______________ per month to the vendor after
taking over the possession of the flat / shop / office / towards maintenance services till such time
the Vendees Association comes into being.
11. That the vendee agrees to become a member of Association / Society which will be formed to
look after the common and General services of the project and to regularly pay the fees,
subscription etc. as may be decided by the Association / Society.
12. The price shall neither be increased nor escalated by the vendor expect with prior approval of
Gwadar Development Authority, Gwadar.
13. If for any reason, the project is a abandoned by the Developer, the Developer will refund the total
amount received from purchaser with damages at the rate of profit of the average of three
scheduled banks on the same, for the whole period of retention of the money, along with an
additional compensatory amount equal to 10 of the amount received from the allottee up-to-date
88
against the booked unit, within 60 days of the announcement to the effect of the abandonment of
the Project.
14. All disputes of the vendor and vendee relating to the unit shall be referred to the authority for
settlement. The decision of the Authority shall be referred for appeal to the Public Hearing
Committee, comprising the following members, within 60 days from the decision of the Authority
COB Design Secretary
Chairman PEC or his nominee
Chairman PLATP or his nominee
Chairman GDA or his nominee
In the absence of any such appeal the decision of the Authority shall be binding on all
parties
Signature of the
Vendor with their
Official seal:
Signature of Vendee
(Witness: 1)________________________
(Witness: 2)________________________
Note. EACH PAGE OF THIS AGREEMENT SHALL ALSO BE SIGNED BY
BOTH VENDOR & VENDEE.
89
P.F.S-4
FORM -7
MODEL OF AGREEMENT BETWEEN THE DEVELOPER AND THE ALLOTTEE (FOR
BOOKING OF PLOTS IN TOWNSHIP).
This Agreement is made on _____________ day of ____________19
Between _______________________________ the DEVELOPER having his head office at
________________________________________ through its Managing Director / Managing Partner /
Propriter hereinafter referred as the vender and being party of the first party and
Mr./Mrs./Miss_______________________________ S/O, W/O, D/O __________________________
residing at _________________________________________________________________ hereinafter
referred to as the vendee being party of the 2nd
part.
Whereas the vendor is developing the Project __________________________________________
consisting of plots on plot Survey No. ______________________________________________________ as
per layout plan approved by MP & EC vide their letter No. ______________________________________ for
selling the same to the public as per terms of NOC granted by GDA to the vender vide letter
No. ___________________________________________________________
Whereas the venred has granted to purchase the plots No. ____________________ on ___________
against the total sale consideration of Rs. __________________ and whereas vendor has agreed to sell it to
the agreement enter into between the parties on the terms and conditions set herein below:-
1. That the total consideration payable by the vendor to the vendor shall be Rs. ______________ out
of which the vendee has to pay to the vendor the sum of Rs. ______________ (acknowledgement
whereof has already been issued by the vendor and which the vendor hereby also admits). The
remaining amount of Rs. ________________ shall be payable by the vendee to the vendor as per
schedule of payments attached.
2. That the vendor shall complete the development of the project by _________________________
as specified in the NOC issued by GDA. If the vendor fails to deliver the possession within the
period, the DEVELOPER shall pay markup to the allottees at rate of the profit of the average of
three scheduled banks on the total amount paid, for the period of delay, by the time specified or
extended by the GDA.
3. That the vendor shall assume Defect Liability of the plot for a period of 12 months from the date
of offering possession of the plot after obtaining Occupancy Certificate, and all defects shall be
rectified to the satisfaction of the Authority. However if defects resulted for reason of deviation
from design or specifications agreed to between allottees and Developer, developer liability shall
remain until such deviation removed.
4. That the payments of installments shall be made by the vendee strictly
Schedule of payment annexed:-
To the agreement. In case of failure, a 15 day notice shall be issued
By Registered A/D on the last given address and if the allottee fails to make payment within the
above period, another notice shall be issued by the developer extending the period up to another
30 days. In case of further failure, a cancellation letter shall be issued to the allottee, a copy of
which shall be endorsed to the Authority. The Developer shall not rebook the cancelled unit
within 30 days of receipt of copy of cancellation letter by the Authority.
During this period the Authority shall confirm through Registered A/D from the allottee regarding
the receipt of notices from the Developer, and if the same have not been received, and the allottee
intends to continue the booking the Developer shall be directed to restore the allotment, after
90
receipt of pending payment and charging the mark-up on the prevailing rate of profit of the
average of three scheduled banks for the period of delay on unpaid installment.
If no response to the Authority is received from the allottee during the said period, the
cancellation of the unit shall be confirmed, automatically. In case the cancellation is made before
allocation, the Developer shall refund the total amount paid till that time by the allottee within 60
days. However, after allocation of unit 38 of the total price of the unit shall be retained but the
Developer, and the rest of the amount shall be refunded within 60 days.
In spite of failure to make payment of installment in time, if the Developer does not resort to
cancelation as provided in this Regulation, the Developer may or may not charge markup on
unpaid installments at the prevailing rate of profit of the average of three scheduled banks and the
allottee shall be informed accordingly.
5. That the vendee agree to make payment to the vendor on cash-cum-loan basis, if the loan if
sanctioned in vendee‟s favor by any loan giving agency. If the loan is refused or the amount of
loan is reduced due to any reason whatsoever by the loan giving agency, the vendee shall pay the
loan amount from its own resources. However extra time of at least six months shall be given to
vendee to pay the loan competent to vendor.
6. That the vendee if so wishes can withdrew his/her allotment of the unit
By surrendering the original letter of allotment / allocation to the company and in this event the
company will refund to the allottee the amount deposited till that time. In case the cancellation is
made before allocation the Developer shall refund total amount paid by the allottee till
cancellation within 60 days. However, after the allocation of unit 3 of total price of the unit shall
be retained by the Developer and the rest of amount shall be refunded within 60 days.
7. That the vendee undertakes to call at the office of the Vendor / office of the Sub-Registrar as and
when required for any documentation.
8. That the vendee will not sub-let, transfer or sell his unit to any one before taking over the
possession, without proper written permission of the Developer, who may allow such transfer on
receipt of all outstanding dues up to date time and transfer fee of 0.51 of total price of unit.
However no transfer fee shall be charged in case the transfer is made within 3 months of
allocation.
9. That the vendee shall pay to the vendor Documentation charges for sub-lease and loan, and
external service connection charges for gas, electricity, sewerage and water shall be paid on
proportion to the unit area in accordance with the actual payment made to these agencies plus 15
as service charges for their respective services. This amount should be paid at the time of deposit
of Challan. In case any allottee fails to make this payment he shall pay markup on the amount at
the prevailing rate of profit of the average of three scheduled banks.
10. That the vendee agrees to make payment of Rs. ______________ per month to the vendor after
taking over the possession of the flat / shop / office / towards maintenance services till such time
the Vendees Association comes into being.
11. That the vendee agrees to become a member of Association / Society which will be formed to
look after the common and General services of the project and to regularly pay the fees,
subscription etc. as may be decided by the Association / Society.
12. The price shall neither be increased nor escalated by the vendor expect with prior approval of
Gwadar Development Authority, Gwadar.
13. If for any reason, the project is a abandoned by the Developer, the Developer will refund the total
amount received from purchaser with damages at the rate of profit of the average of three
scheduled banks on the same, for the whole period of retention of the money, along with an
additional compensatory amount equal to 10 of the amount received from the allottee up-to-date
91
against the booked unit, within 60 days of the announcement to the effect of the abandonment of
the Project.
14. All disputes of the vendor and vendee relating to the unit shall be referred to the authority for
settlement. The decision of the Authority shall be referred for appeal to the Public Hearing
Committee, comprising the following members, within 60 days from the decision of the
Authority.
Chairman PEC or his nominee.
Chairman PCATP or his nominee.
Chairman GDA of his nominee.
In the absence of any such appeal the decision of the Authority shall be binding on all parties.
In the absence of any such appeal the decision of the Authority shall be binding on all parties.
Signature of the
Vendor with their
Official seal:
Signature of Vendee
(Witness: 1)________________________
(Witness: 2)________________________
Note. EACH PAGE OF THIS AGREEMENT SHALL ALSO BE SIGNED BY
BOTH VENDOR & VENDEE.
92
P.F.S-8
FORM -8
BUILDING CONTROL SECTION
( UNDER GWADAR DEVELOPMENT AUTHORITY ACT 2003 )
No GDA/BCS/.______________________________Dated:________________________________
To,
The Controller of Buildings,
Gwadar Development Authority,
Gwadar.
A P P L I C A T I O N
Subject: EXTENTIOIN IN DATE OF COMPLETION OF THE PROJECT_______
(Name of Project)
____________________________________________ BEING CONSTRUCTED
ON PLOT NO. _________________________________________________________________
(Location of Plot)
Reference: NOC No. ____________________________
Dated: ______________________________
I, ________________________________________________________________ of
M/s.___________________________________________________________________________
(Name of Developer)
Having registered office at: ________________________________________________________
(office address of the DEVELOPER)
_______________________________________________________________________________
Having been granted „NO OBJECTION CERTIFICATE‟ under section 12 of the GDA Act-2003,
hereby apply for grant of Extension in date of completion of the project from _________________
________________________________________________.
All information / details are submitted on the prescribed project Design Form annexed
hereto required.
I hereby declare that the information supplied are correct and true to the best of my
knowledge and belief and if at any stage miss-representation is found then we may be treated under
the previous of GDA Act 2003, & amendment up to date.
SIGNATURE OF DEVELOPER WITH
NAME AND SEAL OF DEVELOPER
93
INSTRUCTIONS
Please read the following instructions carefully and follow them strictly while preparing case for NOC for
advertisement for sale for submission.
1. Incomplete application or cases shall be rejected outright.
2. Application for NOC should be made on the original set of forms issued by the Design Section
and no-photo-state of forms shall be accepted.
3. In case the applicant is other than the Owner or Partners / Managing Director of shall be
submitted.
4. The Forms should be filled in every carefully and all entries duly replied and no item left
untouched.
5. All enclosures should be according to the format in order and dully fledged.
6. All Forms, and enclosures and documents and papers etc. should be signed by the Developer and
bear seal of owner / Housing Society.
7. In case of insufficient space for entries attach separate sheets for details.
8. Incorrect entries may be crossed and correction made and initialed but no erasures is permissible.
9. No addition or alterations in the prescribed format of the undertaking will be acceptable.
10. While submitting the case an Admittance slip shall be issued to the Applicant / agent showing his
national identity card no. etc. and the same agent shall be authorized to deal with the case in
Section and will be issued Challan for security for fee for payment and delivery on NOC. Proper
authority letter from the developer in favor of agent shall be provided.
11. After initial scrutiny objection letter shall be issued after _______ days to which strict compliance
will be required.
After serving two reminders the case will be closed.
94
P.F.S-9
FORM -9
PROJECT DESIGN FORMS.
1- DETAILS OF PROJECT ARE GIVEN BELOW:
------------------------------------------------------------------------------------------------------------------------------
1- NAME OF PROJECT:
------------------------------------------------------------------------------------------------------------------------------
2- LOCATION OF PROJECT:
------------------------------------------------------------------------------------------------------------------------------
3- DEVELOPER:
NAME ---------------------------------
ADDRESS OF REGISTERED OFFICE
------------------------------------------------
------------------------------------------------
------------------------------------------------
-------------------------------------------------------------------------------------------------------------------------------
4- BUILDER:
NAME ---------------------------------
ADDRESS OF REGISTERED OFFICE
------------------------------------------------
------------------------------------------------
------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------------------
5- PROFESSIONAL: NAME OF ARCHIRECT. _______________________________
NAME OF STRUCTURE ENGINEER. _____________________
NAME OF PROFESSIONAL ENGINEER. _________________
NAME OF SITE SUPERVISOR. _________________________
-----------------------------------------------------------------------------------------------------------------------------------
6- NOC GRANTED: NO. ____________________ Date. ___________________
-----------------------------------------------------------------------------------------------------------------------------------
7- UNIT OFFERED FOR SALE: Flats / House / Offices / Shops / Showrooms.
Unit type Total No. Covered price i/c of units. Area
In sqft. Loan Rs.
“A”______________________________________
“B”______________________________________
“C”______________________________________
“D”______________________________________
“E”______________________________________
SIGNATURE OF DEVELOPER WITH SEAL
95
Enclose details of booking
Including date, name & address _____________________________________________________________
Of allottees and price committed. Total:_______________________________________________________
-----------------------------------------------------------------------------------------------------------------------------------
8- DATE OF COMPLETION ____________________________
i) APPROVED IN NOC
ii) COMMITTED WITH THE ALLOTTEES AT
AT THE TIME OF BOOKING ____________________________
-----------------------------------------------------------------------------------------------------------------------------------
9- REASON FOR DELAY: 1-_______________________________________
2-_______________________________________
3-_______________________________________
4-_______________________________________
5-_______________________________________
Enclose update progress of work
And revised work programme. --------------------------------------------------------------
Proposed date of completion --------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------------------
10- UNDERTAKING FROM THE DEVELOPER
ON RS. ____________ STAMP PAPER
ON THE PRESCRIBED FORMAT.
Enclose undertaking _________________________________________
-----------------------------------------------------------------------------------------------------------------------------------
11- BUILDER LICENCE.
Enclose copy of licence. _________________________________________
Enclose agreement of assignment
-----------------------------------------------------------------------------------------------------------------------------------
12- CONSENT OF THE ALLOTTEES:
Enclose copies of consent of
Individual allottees for their
No Objection for proposed _________________________________________
Extension and original
Public notices.
-----------------------------------------------------------------------------------------------------------------------------------
13- SCRUTINY FEE.
Enclose Challan of payment of
Scrutiny fee.
-----------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------
SIGNATURE OF DEVELOPER WITH SEAL
96
( UNDERTKING FROM DEVELOPER ON RS. 2000/= STAMP PAPER )
UNDERTAKING
----------------------
I, ________________________________________ S/o _________________________________________
(Name of the DEVELOPER) (Name of the DEVELOPER)
Whose registered office is situated at: ________________________________________________________
(address of the DEVELOPER)
-----------------------------------------------------------------------------------------------------------------------------------
DEVELOPER hereby undertake on behalf of the DEVELOPER as follows:
1- That we are carrying out construction of our project ______________________________________
Situated on plot No. ______________________________________________________________________
For offering residential / commercial units for public sale.
2- That the date of completion and handing over physical possession on the units is approved in the
N.O.C as___________________________________________ and the construction of our project is
delayed up to__________________________ months.
3- That we have completed already done booking and committee the please date of completion and
handing over possession of the ect., with the buyers.
4- That we have received part payment form the buyers on account of prices of the residential /
commercial units.
5- That we have completed the formalities of documentation for sub-leases & shall be executed in the
name of the buyers before handing over possession.
6- That we have completed the formalities of documentation for H.B.F.C and the loan will be available
in the name of individual allottees by____________________________
7- That we have completed the formalities of documentation of Q.E.S.C.O and the domestic electric
connection and matters are expected to be available in the name of the individual buyers before
completion of the project.
8- That we have completed the formalities of SSGS and domestic Gas connections and meter are
expected to be available before completion of the project.
-------------------------------------------------------------------
SIGNATURE OF THE DEVELOPER WITH THE SEAL
Gwadar:
Dated: _________________
97
P.F.S-10
FORM -10
BUILDING CONTROL SECTION
( UNDER GWADAR DEVELOPMENT AUTHORITY ACT 2003 )
No GDA/BCS/.______________________________Dated:________________________________
To,
The Controller of Buildings,
Gwadar Development Authority,
Gwadar.
A P P L I C A T I O N
Subject: EXTENTIOIN IN DATE OF COMPLETION OF THE PROJECT_______
(Name of Project)
____________________________________________ BEING DEVELOPED ON
PLOT NO / ___________________________________________________
(Location of Plot)
Reference: NOC No. ____________________________
Dated: ______________________________
I, ________________________________________________________________ of
M/s.___________________________________________________________________________
(Name of Developer)
Having registered office at: ________________________________________________________
(Office address of the DEVELOPER)
_______________________________________________________________________________
Having been granted „NO OBJECTION CERTIFICATE‟ under of the GDA Act-2003, hereby
apply for grant of Extension in date of completion of the project from _________________
________________________________________________.
All information / details are submitted on the prescribed project Design Form annexed
hereto required.
I hereby declared that the information supplied are correct and true to the best of my
knowledge and belief and if at any stage miss-representation is found then we may be treated under
the provision of GDA Act 2003, & amendment up to date.
SIGNATURE OF DEVELOPER WITH
NAME AND SEAL OF DEVELOPER.
98
INSTRUCTIONS
Please read the following instructions carefully and follow them strictly while preparing case for NOC for
advertisement for sale for submission.
1. Incomplete application or cases shall be rejected outright.
2. Application for NOC should be made on the original set of forms issued by the Building Control
Section and no-photo-state of forms shall be accepted.
3. In case the applicant is other than the Owner or Partners / Managing Director of shall be
submitted.
4. The Forms should be filled in every carefully and all entries duly replied and no item left
untouched.
5. All enclosures should be according to the format in order and dully fledged.
6. All Forms, and enclosures and documents and papers etc. should be signed by the Developer and
bear seal of owner / Housing Society.
7. In case of insufficient space for entries attach separate sheets for details.
8. Incorrect entries may be crossed and correction made and initialed but no erasures is permissible.
9. No addition or alterations in the prescribed format of the undertaking will be acceptable.
10. While submitting the case an Admittance slip shall be issued to the Applicant / agent showing his
national identity card no. etc. and the same agent shall be authorized to deal with the case in
Section and will be issued Challan for security for fee for payment and delivery on NOC. Proper
authority letter from the developer in favor of agent shall be provided.
11. After initial scrutiny objection letter shall be issued after _______ days to which strict compliance
will be required.
After serving two reminders the case will be closed.
99
P.F.S-11
FORM -11
PROJECT DESIGN FORMS.
DETAILS OF PROJECT ARE GIVEN BELOW:
------------------------------------------------------------------------------------------------------------------------------
1. NAME OF PROJECT:
------------------------------------------------------------------------------------------------------------------------------
2. LOCATION OF PROJECT:
------------------------------------------------------------------------------------------------------------------------------
3. DEVELOPER:
NAME ---------------------------------
ADDRESS OF REGISTERED OFFICE
------------------------------------------------
------------------------------------------------
------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------------------
4. BUILDER:
NAME ---------------------------------
ADDRESS OF REGISTERED OFFICE
------------------------------------------------
------------------------------------------------
------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------------------
5. PROFESSIONAL: NAME OF ARCHIRECT. _______________________________
NAME OF STRUCTURE ENGINEER. _____________________
NAME OF PROFESSIONAL ENGINEER. _________________
NAME OF SITE SUPERVISOR. _________________________
-----------------------------------------------------------------------------------------------------------------------------------
6. NOC GRANTED: NO. ____________________ DT. ___________________
-----------------------------------------------------------------------------------------------------------------------------------
7. PLOTS OFFERED FOR SALE: Plots
Plot type Total No. Area in price of plots. Sq.Yds.
Rs.
“A”______________________________________
“B”______________________________________
“C”______________________________________
“D”______________________________________
“E”______________________________________
Enclose details of booking
Including date, name & address _____________________________________________________________
Of allottees and price committed. Total:_______________________________________________________
100
SIGNATURE OF DEVELOPER WITH SEAL
-----------------------------------------------------------------------------------------------------------------------------------
8. DATE OF COMPLETION ____________________________
i) APPROVED IN NOC
ii) COMMITTED WITH THE ALLOTTEES AT
AT THE TIME OF BOOKING ____________________________
-----------------------------------------------------------------------------------------------------------------------------------
9. REASON FOR DELAY: 1-_______________________________________
2-_______________________________________
3-_______________________________________
4-_______________________________________
5-_______________________________________
Enclose update progress of work
And revised work programme. --------------------------------------------------------------
Proposed date of completion --------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------------------
10. UNDERTAKING FROM THE DEVELOPER
ON RS. ____________ STAMP PAPER
ON THE PRESCRIBED FORMAT.
Enclose undertaking _________________________________________
-----------------------------------------------------------------------------------------------------------------------------------
11. BUILDER LICENCE.
Enclose copy of license. _________________________________________
Enclose agreement of assignment
-----------------------------------------------------------------------------------------------------------------------------------
12. CONSENT OF THE ALLOTTEES:
Enclose copies of consent of
Individual allottees for their
No Objection for proposed _________________________________________
Extension and original
Public notices.
-----------------------------------------------------------------------------------------------------------------------------------
13. SCRUTINY FEE.
Enclose Challan of payment of
Scrutiny fee.
-----------------------------------------------------------------------------------------------------------------------------------
--------------------------------------------------------------
SIGNATURE OF DEVELOPER WITH SEAL
101
P.F.S-12
FORM -12
( UNDERTKING FROM DEVELOPER ON RS. _______________ STAMP PAPER )
UNDERTAKING
----------------------
I, _____________________________________________________________________________________
(Designation)
Of
M/s___________________________________________________________________________________
(Name of the DEVELOPER)
Whose registered office is situated at: ________________________________________________________
(address of the DEVELOPER)
-----------------------------------------------------------------------------------------------------------------------------------
DEVELOPER hereby undertake on behalf of the DEVELOPER as follows:
1- That we are carrying out development of our project ______________________________________
Situated on plot No. ______________________________________________________________________
For offering residential / commercial units for public sale.
2- That the date of completion and handing over physical possession on the units is approved in the
N.O.C as___________________________________________ and the development of our project is
delayed up to__________________________ months.
3- That we have completed already done booking and committed the prices, date of completion and
handing over possession of the plot with the buyers.
4- That we have received part payment form the buyers on account of prices of the residential /
commercial plots.
5- That we have completed the formalities of documentation for sub-leases & shall be executed in the
name of the buyers by_______________________________________________.
6- That we have completed the formalities of Q.E.S.C.O and the electric connections are expected be
available for the project before completion of the project.
7- That we have completed the formalities of SSGS and gas lines for the project are expected be
available before completion of the project.
-------------------------------------------------------------------
SIGNATURE OF THE DEVELOPER WITH THE SEAL
Dated: _________________
102
P.F.S-13
FORM -13
BUILDING CONTROL SECTION
(UNDER GWADAR DEVELOPMENT AUTHORITY UNDER ACT, 2003 )
No GDA/BCS/.______________________________Dated:________________________________
Mr./Mrs./Miss.___________________________________________________________________
(Developer)
Subject: EXTENTION IN VALIDITY OF „NO OBJECTION CERTIFICATE‟ OF
THE PROJECT: _____________________________________________ BEING
CONSTRUCTED ON PLOT NO. _____________________________________
Reference your letter No. ________________________________ dated: ____________________
Please refer your letter on the subject noted above.
In view of the specific conditions enumerated by you in your letter the validity on the
NOC No. _____________________________ dated ____________________ is hereby extended
upto _________________________.
The other terms and conditions of the „NO OBJECTION CERTIFICATE‟ shall
remain unchanged.
( Controller of Buildings )
Building Control Section
Gwadar Development Authority
Gwadar
Copy to:
1. Builder.
2. Professionals.
3. P.S to DG, GDA.
103
(Name of the Authority)
APPLICATION FOR DEVELOPMENT PERMIT FOR MINOR SUB DIVISION UNDER
SECTION
To,
________________________________
________________________________
________________________________
I hereby submit an application along with necessary documents as prescribed under
Building Regulation 2005 & Town planning Regulation, 2004, for a permit for minor sub-division
of the land / plot situated ____________________________ measuring ______________________
acres / yards / Sq.Meter.
Signature of Town Planner
License No:
Date of Expiration: Signature of the Applicant
Address:
Particulars / documents.
1. Name of the applicant.
2. Name of the owner.
3. Address & Telephone No. if any.
4. Location of the land.
5. Particular of the land.
a) Government;
b) Private;
c) By developing agency;
6. Present land use and area of the land.
7. Nature of the proposed land use.
8. Details of the proposed land use.
9. Details of proposed sub-division plan.
10. Reason for sub-division.
Maps and Plans and Documents.
10 a) Certified copy of original layout site plan.
b) Key map of land, if outside of approval developments scheme with width of roads.
11. Certified copy of the documentary evidence of original ownership.
12. 7 copies of the proposed sub-division plan.
13. Original receipt of payment of scrutiny fee.
104
APPLICATION FOR SPECIAL DEVELOPMENT PERMIT FOR MAJOR SUB DIVISION UNDER
SECTION
To,
________________________________
________________________________
________________________________
I hereby submit an application for special development permit for major sub-division
plan, along with necessary particulars / documents in respect of land situated at__________
____________________________ measuring ____________________________ acres / yards /
Sq.Meter.
Signature of the Applicant
Signature of Town Planner
License No:_______________________________
Date of Expiration:__________________________
Address: _________________________________
Particulars / enclosures.
1. Name of the owner or owners of the land.
2. Name of the developer with address.
3. Name and address of the Licensed Town Planner who prepared the Plan.
4. Detailed location of the area.
5. Certified copy of the documentary evidence of rightful ownership or lease.
6. Deputy Commissioner‟s approval of the proposed development. If required.
7. Approval of Defense authorities and other concerned agencies like T&T Fire Protection and other
departments, if required.
8. Compliance report by the Registrar, Co-operative Societies with any provision of or rules or
regulations of Co-operative Societies Act, 1925, if the applicant is Co-operative Housing Society.
9. Details od socio-economic data such as the availability to existing employment in the area, or
accessibility to exiting employment.
10. Maps and Plans.
a) physical survey map, prepared by a qualified surveyor.
b) Copy of Site Plan showing the boundary lines of the site and tract.
c) Official Survey Number.
d) Details of existing structure, water coerces, wood areas, streets, road and other significant
physical features and other adjacent land within 200 meter of site.
e) A topographical survey, with contuses at intervals including the site and adjacent land within
200 meter of the site.
f) I) Copy of Proposed layout Plan at the scale not more then 1:5000 meter or not less
105
then 1:1000 together with block plans:
ii) Dimensions of proposed plots and existing structures:
iii) Locations and dimensions of proposed parks: playgrounds etc.
vi) areas to be set aside from non residential use, including community facilities.
g) Appropriate locations and sizes of proposed water lines, hydrias, sewer lines, storm drainage,
and information regarding their connections with existing or new system.
h) Financial estimates of the project, method of financing and it, phasing.
i) Time scheduled and phasing of development works.
j) Type of sub-lease to individual.
k) Letters of commitments by financials agencies, ( if the finances will be arranged through them
or a financial guarantee on a non-judicial paper, If the finances will be arranged by private
resources.
l) Official receipt of payment of scrutiny fee.
106
FORM STP-1
BUILDING CONTROL SECTION
( UNDER GWADAR DEVELOPMENT AUTHORITY ACT 2003 )
A. CERTIFICATE OF STRUCTUREAL SOUNDNESS
OF BUILDING AND STRUCTURE
We/I certify that:
01. we were/I was appointed Consulting Structural Engineer by M/s ______________________
For the Structural design of the Building / Structure on Plot No. ______________________
On _____________20
Which:
a) Is likely to be constructed from _______________________________ 20
b) Is under construction since __________________________________ 20
c) Has been virtually completed on _____________________________ 20
d) Stage of construction _______________________________________20
02. i) No. of stories designed _________________________________________________
ii) No. of stories approved ________________________________________________
vide Letter No. _______________________________________________________
dated _____________________________ 20
03. The Structural design was based on the following codes / Bye-Laws relationally couples with
Engineering knowledge and adjustment where necessary. (Various blanks can be used for different
lines in case of different codes are used).
CODE:
________________________________________________________________________________
________________________________________________________________________________
________________________________________________________________________________
NOTE:
If necessary, separate sheets may be enclosed for details.
04. a) The Building Structure was designed for the forces generated by the basic wind
Velocity of 130 km/hour (82 Mph).
(In case if the Building is not designed for 4a).
b) The Building Structure was designed for the forces generated by the following basic
wind velocity of:
107
(FOR ON-GOING PROJECT ONLY)
VELOCITY:
BLOCK NO. BLOCK NO. BLOCK NO. BLOCK NO.
_____________ _____________ _____________ _____________
c) The Building was not designed for wind Forces.
d) Present stage of construction of various blocks.
(FOR ON-GOING PROJECT ONLY)
VELOCITY:
BLOCK NO. BLOCK NO. BLOCK NO. BLOCK NO.
_____________ _____________ _____________ _____________
NOTE:
If necessary, separate sheets may be used details.
The present stage of construction of various Block shall be certified by the concerned.
Controller of Buildings after verification at the site.
05. The Building Structure was designed / not designed for the seismic forces generated by an
Earthquake of Intensity VII (Seven) on the Modified Marcella Scale in accordance with
Code. __________________________________________________________________________
Plot No. ____________________________________________________________________
____________________________________________________________________
____________________________________________________________________
06. a) The Sub-Surface Investigation was carried out by M/s. _______________________
During __________________________________20
b) A design soil bearing capacity of ______________ kn/m2 /Tons per Sq:Ft. was
adopted based on ________________________________________________
(Only for On-Going Projects).
c) The design working load capacity of the pile was adopted as ___________________
108
Kn/Ton based on the Sub-Surface Investigation Report of M/s. _________________
______________________________ and actual load test on pile conducted by M/s.
____________________________________________________________________
07. Our (My) contractual responsibilities were / limited to:
a) Structural Analysis and Design.
b) Preparation of working working structural drawings.
c) Preparation of bar bending schedule.
d) Checking bar bending schedule prepared by the Contractors / Constructors /
Builders.
e) The other responsibilities were _______________________________________
i) Set of working structural drawings.
ii) Set of bar bending schedule.
iii) Set of design calculation.
iv) Set of specification relevant to Structural work.
Name of Engineer: ________________________________________
Signature: _______________________________________________
GDA License No: ________________________________________
PEC Registration No: ______________________________________
B. CERTIFICATE OF SUPERVISION OF CONSTRUCTION
We / I certify that our contractual responsibilities were / are limited to:
I. To make such periodic visits to the Site as considered necessary to inspect generally
the progress and quality of the work and to determine in general if the work is
proceeding in accordance with specification, working drawings and instruction
relevant to the structural work and the terms of contract document (If there is any)
between the client and the Constructors / Contractors / Builders. If during any of my
visit I find any thing in connection with the work which might result in in reduction
factor of safety considered by me/us in the Structural Design of the permanent works,
then I will inform the Client in writing of such short-comings and endorse a copy of it
to GDA.
II. We / I shall not be responsible for the Constructors / Contractors / Builders
operational methods, techniques, sequences or procedures, nor for safety precaution in
connection with work, nor shall We / I be responsible for any failure by the
Constructors / Contractors / Builders, to carry out and complete the work in
accordance with terms of the building contract between the client and the
Constructors / Contractors / Builders (If any).
109
III. During our/my on Site inspection made in accordance with clause (i). We / I shall
Endeavour to guard the client against defects and deficiencies in the work of the
Constructors / Contractors / Builders but shall not be required to make exhaustive or
continuous inspection check the quality or quantity of the work.
Executing agency for the project was /is ___________________________________
____________________________________________________________________
OBSERVATION: ____________________________________________________
____________________________________________________
____________________________________________________
NOTE: If necessary, separate sheets may be used.
PLOT NO: ___________________________________________
___________________________________________
___________________________________________
STRUCTURAL ENGINEER ARCHITECT SITE ENGINEER
Signature
Name
Address
C.
CERTIFICATE BY
PROMOTORS/OWNERS/DEVELOPERS/CONSTRUCTURES/BUILDRES/CONTRACTOR
S FOR SOUND AND STABLE OF THE BUILDING WORK.
We / I ___________________________________________________________________ certify
that We / I have taken / shall take due care and diligence to execute and maintain the works and
provide all labor, including the Supervision thereof, materials, constructional plan and all other
things, whether of a temporary or permanent nature, required in ans for such execution and
maintenance, so far as the necessary for providing the same is specified in working drawings,
specifications and instructions of the Licensed Architect / Engineer / Structural Engineer.
We / I _________________________________________________ also take responsibilities for the
adequacy stability and safety of all Site Operations and methods of construction towards the
Achievements of safe and sound construction of Building / Buildings.
PROMOTOR / OWNER / DEVELOPERS:
SIGNATURE: _______________________________
110
NAME: _____________________________________
ADDRESS: _________________________________
TELEPHONE NO: ____________________________
CONSTRUCTURES/BUILDERS/CONTRACTORS:
SIGNATURE: _______________________________
NAME: _____________________________________
ADDRESS: _________________________________
TELEPHONE NO: ___________________________
BUILDING LIC NO: _________________________
111
FORM STP-2
BUILDING CONTROL SECTION
( UNDER GWADAR DEVELOPMENT AUTHORITY ACT 2003 )
VETING REPORT
GUIDE LINE FOR VETTING OF DESIGNS:
PROCEDURE:
1. The calculation (3 copies) headed by the specified design information and all the structural
and architectural drawings (5 copies) of structural drawings and Two copies of Architectural
approved plan dully signed by the respective professional should be submitted to GDA.
2. Two copes of Structural calculation, Five copies of Structural drawings, Two copies if
Approved Architectural Plan and Two copies of Soil Investigation Report, Two copies of
Stability Certificate and Two copies of Vetting Report. Four copies of each of the above
documents shall pass over to the Proof Engineer by GDA.
3. The Proof Engineer shall be the consent of GDA would contact the Original designer to
discuss the problems.
4. The Proof Engineer shall inform GDA about his progress by Bi-weekly Report.
5. Proof Engineer shall mark his comments on the calculations and drawings and send one copy
to GDA with the attached check sheet.
6. Proof Engineer having satisfied himself with corrections made by the Original designer, shall
sign the certificate at the end of the check sheet and return them to GDA.
LIABILITY OF THE PROOF ENGINEER:
The Proof Engineer is primarily concerned with the safety of the structural and the validity
the design documents such as Structural calculations and drawings as per approved Architectural
Plan and Soil Report his responsibilities and liabilities are limited to this design office work only. He
shall be responsible for any construction work or supervision thereof. The fees of the Proof Engineer
does cover his charges and expenses in connection law suits, arbitration proceedings or any litigation
matters initiated by the parties concerned with the work. Proof Engineer should also check the
Structural working drawings to with regards to their correspondence approved. Architectural Plan
and confirm that the Architectural Plans are in accordance with Structural Plan.
CERTIFICATE OF PROOF CHECKING OR STRUCTURAL DESIGN:
DESIGN AND STRUCTURAL DRAWINGS:
SECTION: 1. To be filled and signed by
The Original Consultants.
Plot No. ______________________________________________________
Number of Storey‟s designed: ______________________________________
112
Vide letter No. _________________________________________________
Nature of case: Fresh / On-going / Addition / Completion
____________________________________________
Stage of construction: ___________________________________________
Use of Buildings: _______________________________________________
Building code and other
Reference used: ________________________________________________
1.1 Name and location
Of the Project: _________________________________________________
1.2 Name and Address of
The Owner / Developer: __________________________________________
1.3 Name and Address of
Originator / Consultant: _________________________________________
______________________________________________________________
1.4 Following documents are supplied by
Original Consultant:
a) Five sets of structural working drawings.
b) Two sets of structural design calculation.
c) Two sets of stability certificate.
d) Two sets of soil investigation report.
e) Two sets of vetting report.
SIGNATURE OF ORIGINATOR
2.4 Complete Seismic analysis / Wind analysis
and detailing for Seismic / Wind Forces:
a) Sub-Soil condition: ______________________________________________________
_______________________________________________________
b) Bearing capacity
recommended __________________________________________________ at a depth
________________ of ___________________ from _______________________ level.
Depth of sub surface water level _____________________________________________
113
c) Type of cement recommend by
Soil consultant for foundation ______________________________________________
d) Any other recommendation about
Foundation by Soil consultant /
Original consultant / Proof Engineer. ________________________________________
_______________________________________________________________________
2.5 Complete design has been submitted,
an independent check is performed:
i] Are additional compilations needed Yes No
ii] If independed check is made, is the
Original design consistent and
satisfactory.
Yes No
iii] If a Computer Programme is used by the
Originator give source and availability
and also check on of these items.
Programme verified
By independed agency
by checker
If Programme verified
by independed agency,
checker should self
with the competence
of such agency.
iv] If the programme used by the checker is
different then the Originator‟s
Programme verified
By independent
agency.
Attach verification
certificate or such
credential of the
programme.
SECTION: 2. To be filled and signed by
The Proof Engineer:
Plot No. ______________________________________________________
2.1 Name and Address of
Proof Engineer: ________________________________________________
2.2 Comments about the following:
SI.No. Item Comments.
a] Formal of calculation sheet.
b] General concept of design.
c] Design procedure & assumption.
d] Structural drawings.
e] Soil investigation report.
f] Building code and other reference
114
used by Original Consultant.
_____________________________________________________________________________
2.3 I have the design and drawing of following member] _______________________
Submitted or not:
i] Plan of reinforcement detail of 1st floor slab.
ii] Plan of reinforcement detail of typical floor slab
iii] Beam elevation of 1st floor.
iv] Beam elevation of typical floor slab.
v] Elevation of columns.
vi] Elevation of footing.
vii] Plinth beam elevation.
viii] Complete elevation and reinforcement detail of
shear walls (if any).
115
F-24 FORM -1
BUILDING CONTROL SECTION
( UNDER GWADAR DEVELOPMENT AUTHORITY ACT 2003 )
TO BE SUBMITTED ON COMPLETION OF PLINTH ON FOUNDATION OF BASEMENT. IF THERE IS ONE.
To,
The Controller of Buildings,
Gwadar Development Authority,
Gwadar.
I / e hereby inform that the plinth / foundation of the basement stage of the
building.
On plot No. ______________________________
______________________________
______________________________
Has been achieved. You are, therefore, requested to depute a reprehensive to verify the building lines
so as to enable me/us to carry out the building work.
O W N E R/S
Mailing Address ________________________
________________________
________________________
dated:
PROFESSIONAL‟S CERTIFICATE
I / We hereby certify that the setting out of building/s for plot No. __________________________
Has been carried out in accordance with the approved plan/s.
SIGNATURE-------------------------------
NAME---------------------------------------
Professional---------------------------------
116
SECTION: 3. CHECKING LIST OF MAIN STRUCTURE ITEM
3.0 Plot No. ______________________________________________________
3.1 Slabs: Type of slab.
Detail of slabs more than 140. Span.
Slab Mark Span Thickness Steel short in
direction
Remarks
[acceptable or
not]
3.2 Detail of cantilever slab more than 5.0 span.
Slab Mark Span Thickness Steel short in
direction
Remarks
[acceptable or
not]
117
Plot No. ________________________________________________________________________
a. Beams:
Details of beams more than 150 span.
Grid Span Size Steel Top / Bottom Shear
Reinforcement
Remarks
[acceptable or
not]
b. Cantilever beam more than 60 span.
Grids Span Size Steel Top/Bottom Shear
Reinforcement
Remarks
[acceptable or
not]
118
Plot No. ____________________________________________________________
4.0 Recommendation and Instruction for construction, if any
----------------------------------------------------------------------
NONE
5.0 The design calculation and structural drawings of Plot No. ____________________
____________________________________________________________________
____________________________________________________________________
design for __________________________ No. of stories _____________________
has been vetted by me and where necessary correction amendment were required
have been incorporated by the Originator to my satisfaction. The following
documents so finalized have been signed by me in token of my having vetted the
design and structural drawings subject to observation and remarks notified above.
i] Design calculation Yes No
ii] Working structural drawings. Yes No
SEAL & SIGNATURE OF PROOF ENGINEER
119
GWADAR DEVELOPMENT AUTHORITY
Building Control Section
(Special call for out-door publicity)
No._______________________ Dated_____________
M/S______________________________
______________________________
Gwadar
Subject: ALLOCATION OF SPECE FOR SONG NOARDS / PUBLICITY BANNERS
With reference to your application dated ______________requested for allocation of
spaces ______________boards. The competent authority has been pleased to allow the display of
the board banners of _________________size with effect from __________to____________
1.
2.
3.
4.
1. You are advised to follow the terms and condition attached. The Authority reserved the
right to shift / remove the same after serving days notice.
( Controller of Buildings )
Building Control Section
Gwadar Development Authority
Gwadar
Copy to.
1. The PS to Director General, GDA
2. The Director Town Planning, GDA
3. The Chief Engineer, GDA
4. Master File.
120
GWADAR DEVELOPMENT AUTHORITY
Building Control Section
(Special call for out-door publicity)
No._______________________ Dated_____________
M/S______________________________
______________________________
Gwadar
Subject: INSTALATION OF BOARDS / HOARDINGS
With reference to your application dated ______________for allocation of board size
______________ has been allows.
You are requested to deposit an amount of Rs:_____________in the name M/s
Gwadar Development Authority through pay order within (7) seven days of the receipt of this
letter. The permission letter will be issued after payment publicity charges.
( Controller of Buildings )
Building Control Section
Gwadar Development Authority
Gwadar
Copy to.
1. The PS to Director General, GDA
2. The Director Town Planning, GDA
3. The Chief Engineer, GDA
4. Master File.
121
GWADAR DEVELOPMENT AUTHORITY
Building Control Section
(Special call for out-door publicity)
No._______________________ Dated_____________
M/S______________________________
______________________________
Gwadar
Subject: INSTALATION OF SING BOARDS / HOARDINGS/BANNERS
With reference to your application dated ______________for allocation of board size
______________ has been allowed w.e.f.______________to_________________.
You are requested please follow the terms and conditions attached. The authority
reserved the right to shift /remove the same after serving (7) seven days notice.
Note: your deposit amount of Rs:_______________ Rupees _________________________
( Controller of Buildings )
Building Control Section
Gwadar Development Authority
Gwadar
Copy to.
1. The PS to Director General, GDA
2. The Director Town Planning, GDA
3. The Chief Engineer, GDA
4. Master File.
122
GWADAR DEVELOPMENT AUTHORITY TERMS AND CONDITIONS FOR ALLOCATION OF OUTDOOR DISPLAY
ADVERTISING SPACE (NEON SIGNS & HOARDINGS STC) IN
GWADAR DEVELOPMENT AUTHORITY LIMITS.
1. All places or sites for illuminated Signs, Neon Signs Banners and Hoardings will be
specified by the GDA in the areas under its control.
2. No person shall, without a valid permission form GDA install hoardings/display
boards/neon signs/banners or use a place including electric poles, for advertisement in all
areas under GDA jurisdiction.
3. The owner / occupant of a private property or his agent/attorney may be issued a
permission / NOC to us any part of the property for the purpose of installation of
advertisement material on payment of charge levied by the GDA from time to time as per
approved standard design.
4. On the crossing of important roads, no hoarding or illuminated sign shall be erected
within a distance of 500 ft. from the point of intersection and other road crossings no
hoarding / illuminated sign banners ect. Shall be installed within a distance of 300 ft.
from the point of intersection.
5. No hoarding / illuminated sign / banners shall be allowed in the central dividing strip of
the road, roundabouts, or traffic islands.
6. The design of form and structure of advertising space shall be provided by GDA
Execution on site as per specification of GDA will be the responsibility of the renter /
licensee. These specifications may very from area to area and form advertising space to
advertising space.
7. The content of every advertisement shall be approval of the GDA advertisement
objectionable on social, ethical or moral considerations hall not be permissible.
8. Application Forms for advertising space shall be available on payment from authorized
Bank at GDA for each site/space separate application shall be submitted.
9. 25% of one year rent/ license fee, subject to being not less than 25% of the reserved fee as
may be determined by GDA for said advertising space will be deposited in the form of
pay order draw in favor of GDA alongwith the application. The balance of 75% of rent /
license fee money will have to be deposited within 15 days of approval of the application.
10. Advertising space will be leased on an yearly basis, beginning _______to _________.
11. License / Temporary permission renewal will be at the discretion of GDA and will not be
withheld without a valid reason stated in writing.
123
TERMS AND CONDITIONS
12. An individual or Firm may lease out one or more site/lot without submitting final advertising
matter to GDA However, before utilizing the site/lot for advertisement ,
NOC for the advertisement will have to be obtained from GDA. No refund of the rent /license
fee money will be admitted in case advertising content is rejected under article section 7
above or other relevant Section as may be applicable.
13. Each application will be responded to by GDA within 15 days of from the date of receipt of
such application or in the case of public Announcement by the GDA inviting applications,
within 15 days from the closing date for submission of application.
14. 25% initial deposit is refundable in case of non-acceptance of application.
15. In case of advertising space where electricity is to be used (non-sign, Illuminated sign etc) the
applicant shall comply with all condition imposed by relevant agency.
16. All advertising displays (technical specification give in the Stander Designs) on shops, house,
building, roads, etc shall be charged as per rates given in the Schedule of Rates.
17. Paper maintenance and upkeep of the advertisement shall be the responsibility of the renter/
licensee. Should the tender / licensee fall to maintain properly the advertising space and
terminated after 7 days notice in writing and the advertisement removed at the risk and cost
of the renter/ licensee.
18. GDA shall be under on obligation to provide alternate site or site in exchange.
19. All advertising space used by the advertiser as permitted by GDA shall carry the name,
address, telephone number and the permission number given, at the place designated for it.
20. in the event of violation of any of the terms and conditions of agreement. GDA shall have the
right to withdraw/ cancel the Agreement.
21. The GDA reserves the right to accept or reject any proposal for advertisement without
assigning any reason.
22. any person aggrieved by an order of the GDA, may appeal in writing within thirty days of
such order to the GDA whose decision shall be final.
GDA has the right to change, add, or amend these terms and conditions and frame additional Bay-
Laws for the regulation and operation of this program from time to time, as needed, and as deemed
fit.
124
GWADAR DEVELOPMENT AUTHORITY
Building Control Section
(Special call for out-door publicity)
No._______________________ Dated_____________
M/S______________________________
______________________________
Gwadar
Subject: INSTALATION OF NEON SIGN / HOARDINGS / SIGN BOARDS AT
With regard to the subject referred above you have installed Hoarding, unauthorized
which is a clear violation of the existing rules and regulation of GDA.
It is intimated that illegal boards may be removed within (7) seven days on the receipt
of this letter.
Failing which the same will be removed by GDA at your risk and cost.
( Controller of Buildings )
Building Control Section
Gwadar Development Authority
Gwadar
Copy to.
1. The PS to Director General, GDA
2. The Director Town Planning, GDA
3. The Chief Engineer, GDA
4. Master File.
125
GWADAR DEVELOPMENT AUTHORITY
Building Control Section
(Special call for out-door publicity)
No._______________________ Dated_____________
M/S______________________________
______________________________
Gwadar
Subject: NOTICE FOR OUTSTANDING DUES.
With reference to your letter No.________________________dated _____________
It is requested you to deposit amount Rs:_______________ through pay order within ( 7 ) seven
days on the receipt of this letter. Failing which action will be taken under the GDA rules.
( Controller of Buildings )
Building Control Section
Gwadar Development Authority
Gwadar
Copy to.
1. The PS to Director General, GDA
2. The Director Town Planning, GDA
3. The Chief Engineer, GDA
4. Master File.
126
GWADAR DEVELOPMENT AUTHORITY
Building Control Section
(Special call for out-door publicity)
No._______________________ Dated_____________
M/S______________________________
______________________________
Gwadar
Subject: INSTALATION OF BOARDS / SING BOARD / HOARDINGS.
With reference to your application dated _____________. Your permission subjected
cited above has been expired on.
You are therefore directed to renew the same within ( 7 ) seven days of the receipt of
this letter. Failing which action will be taken under the GDA rules.
( Controller of Buildings )
Building Control Section
Gwadar Development Authority
Gwadar
Copy to.
1. The PS to Director General, GDA
2. The Director Town Planning, GDA
3. The Chief Engineer, GDA
4. Master File.