Signature of Promoter/Developer No.of corrections Signature of Inviter
1
GOVERNMENT OF MAHARASHTRA
WATER RESOURCES DEPARTMENT
CHIF ENGINEER (ELECT.) HYDRO PROJECTS, MUMBAI-01
PRE-QUALIFICATION DOCUMENT
NO. CE (E)/HP/SHP/CPP/IPP/68A
FOR
DEVELOPMENT OF SHAHANOOR CANAL DROP HYDRO ELECTRIC
PROJECT (0.350 MW) THROUGH PRIVATE SECTOR PARTICIPATION
IN DEVELOPMENT OF SMALL HYDRO ELECTRIC PROJECTS BY
PRIVATE PARTICIPATION
SUPERINTENDING ENGINEER, CHIEF ENGINEER (ELECT.)
VIDARBHA HYDRO ELECTRIC & HYDRO PROJECTS,
LIFT IRRIGATION, CIRCLE H.S.B.C. BUILDING, 4TH
FLOOR
WAINGANGA NAGAR, AJNI, NAGPUR M.G.ROAD, FORT ,
PHONE- 0712-2420922 MUMBAI 400001
Fax- 0712-2440058 PHONE – 022 - 22670074
Email- [email protected] FAX NO. - 022 - 22674867
PRICE Rs. 7000 /-
Signature of Promoter/Developer No.of corrections Signature of Inviter
2
GOVERNMENT OF MAHARASHTRA
WATER RESOURCES DEPARTMENT
PRE-QUALIFICATION DOCUMENT
NO. CE (E)/HP/SHP/CPP/IPP/68A
FOR
DEVELOPMENT OF SHAHANOOR CANAL DROP HYDRO ELECTRIC
PROJECT (0.350 MW) THROUGH PRIVATE SECTOR PARTICIPATION
IN DEVELOPMENT OF SMALL HYDRO ELECTRIC PROJECTS BY
PRIVATE PARTICIPATION
Issued to / Downloaded by :-
Superintending Engineer,
Vidarbha Hydro Electric & Lift Irrigation
Circle,Wainganganagar, Ajni, Nagpur.
Ph. 0712-2420922 Fax- 0712-2440058
Email- [email protected]
Signature of Promoter/Developer No.of corrections Signature of Inviter
3
PRE-QUALIFICATION DOCUMENT FOR DEVELOPMENT OF SHAHANOOR CANAL
DROP HYDRO ELECTRIC PROJECT (0.350 MW) THROUGH PRIVATE SECTOR
PARTICIPATION IN DEVELOPMENT OF SMALL HYDRO ELECTRIC PROJECTS BY
PRIVATE PARTICIPATION
INDEX
CLAUSE DESCRIPTION
PAGE
NO.
SECTION-I Press Notice in English
Press Notice in Marathi
Detailed Tender Notice in English
5
6
7
SECTION-II Instructions to the Promoters/Developers 10
SECTION-III Annexures
i) Annexure-I Procedure for evaluation 16
ii) Annexure-II
Information to be furnished by
Promoter/Developer who has been
earlier allotted the SHP for
development
19
iii) Annexure-III
Information to be furnished by
Promoter/Developer
20
iv) Annexure-IV
State Hydel Policy of the Government
of Maharashtra, Water Resources
Department
24
SECTION-IV A) Salient Features of Shahanoor canal drop H.E. Project 41
B) Project Description of the Shahanoor canal drop H.E.P. 43
C) Appendices
1) Appendix – I Area Capacity Table 49
2) Appendix – II Monsoon Rainfall 52
3) Appendix – III 75% yield working table 54
SECTION-V Drawings
1) Drawing No. I Index map 57
2) Drawing No. II Typical cross section of earth dam at R.D.
2120 M
58
3) Drawing No. III Layout of diversion canal penstock power
house & T R C
59
4) Drawing No. IV Area capacity curve 60
5) Drawing No. V Layout Of Power house 61
Signature of Promoter/Developer No.of corrections Signature of Inviter
4
SECTION - I
1) Press Notice in English
2) Press Notice in Marathi
3) Detailed Press Notice
Signature of Promoter/Developer No.of corrections Signature of Inviter
5
PRESS NOTICE
GOVERNMENT OF MAHARASHTRA
WATER RESOURCES DEPARTMENT
Main Portal : http://maharashtra.etenders.in
WRD Portal: http://wrd.maharashtra.etenders.in
Online Pre-Qualification proposals are invited for and on behalf of
Governor of Maharashtra by the Superintending Engineer, Vidarbha Hydro
Electric & Lift Irrigation Circle, Water Resources Department, Wainganga Nagar,
Ajni, Nagpur-440003 Maharashtra (INDIA), Fax No.: 0712-2440058, Ph.No. :
0712-2420922 , for Prequalification of the Promoters / Developers who intend to
develop SMALL HYDRO ELECTRIC PROJECTS, as Captive Power Producer
(CPP) / Independent Power Producer (IPP) for electricity generation in the State of
Maharashtra by the Promoter / Developer company as stipulated in Hydro Power
Policy declared vide Govt. of Maharashtra, Water Resources Department, G.R.No.
PVT-1204/ (160/2004)/HP, dated 15.9.2005.
The Pre-Qualification Documents are available on web site from
26//09/2011 to 25/10/2011
Sr.
No
Pre-Qualification
Document No.
Name of Hydro Electric Project and capacity
(MW)
1. CE(E)/HP/SHP/CPP/
IPP/67A
Lower Wardha HEP Tal.: Arvi,
Dist.: Wardha (0.750 MW)
2 CE(E)/HP/SHP/CPP/
IPP/68 A
Shahanoor Canal Drop, HEP
Tal. Achalpur, Dist. Amravati (0.350MW)
3 CE(E)/HP/SHP/CPP/
IPP/69 A
Bawanthadi – 1 HEP, Tal. Tumsar,
Dist. Bhandara (0.350 MW)
4 CE(E)/HP/SHP/CPP/
IPP/70 A
Bawanthadi – 2 HEP Tal. Tumsar,
Dist. Bhandara (0.600 MW)
5 CE(E)/HP/SHP/CPP/
IPP/71A
Kalisarar HEP, Tal. Saleksa ,
Dist. Gondia (0.400MW)
The Promoter/Developers participating first time in e-Tendering process will
have to procure Digital Signature Certificate, Username & Password from
competent authorities as per guidelines mentioned on homepage of the website.
All requisite information required for the submission of Pre-Qualification
documents is available in the above said website.
If any assistance is required regarding e-Tendering (upload / download) please
contact Phone No. 020-41466666, e-tendering help desk , [email protected],
The Government reserves the right to reject any or all the proposals or annul
the process without assigning any reason and without being responsible for the
cost incurred by the Promoter / Developer in preparing his P.Q. proposal / Price-
Bid.
Sd/-
Superintending Engineer
Vidarbha Hydro Electric and Lift Irrigation Circle,
Nagpur
Signature of Promoter/Developer No.of corrections Signature of Inviter
6
ÊxÉÊ´ÉnùÉ ºÉÚSÉxÉÉ VɱɺÉÆ{ÉnùÉ Ê´É¦ÉÉMÉ, ¨É½þÉ®úɹ]Åõ ¶ÉɺÉxÉ
Main Portal : http://maharashtra.etenders.in
WRD Portal: http://wrd.maharashtra.etenders.in ¨ ɽþ É® ú ɹ ]ÅõÉSªÉÉ ® ú ÉVªÉ{ÉɱÉÉÆSª ÉÉ ´ Éi ÉÒx Éä, +ÊvÉIÉEò +ʦɪÉÆiÉÉ, Ê´Énù¦ÉÇ VɱÉÊ´ÉtÖiÉ ´É ={ɺÉÉ ËºÉSÉxÉ ¨ÉÆb÷³ý, ´ÉèxÉMÉÆMÉÉ xÉMÉ®ú, +VÉxÉÒ, xÉÉMÉ{ÉÚ®ú-440003 ¨É½þÉ®úɹ]Åõ (¦ÉÉ®úiÉ) nÚù®úv´ÉxÉÒ GÆò. 0712-2420922 , ¡ìòCºÉ Gò. 0712-2440058½äþ ¨ ɽþ É® úɹ ]Åõ ¶Éɺ Éx É , Vɱɺ ÉÆ{É nù É Ê´ É ¦ÉÉMÉ ªÉÉÆx ÉÒ ¶ÉɺÉx É Êx ÉhÉÇªÉ G ò.{ÉÒ´ ½þ Ò] õÒ - 120 4/ (16 0/ 200 4) / BSÉ{ÉÒ ,Ênù. 15- 9- 20 05 +x ´ ɪÉä VÉÉ® ú Ò Eäò ±Éä ±ªÉÉ ±É½þ Éx É VɱÉÊ´ ÉtÖiÉ |ÉE ò±{Éɺ ÉƤ ÉÆv ÉÒ Sª ÉÉ vÉÉä® úhÉÉx ÉÖº ÉÉ® ú VÉä |É´ Éi ÉÇE ò/=tÉä VÉEò JÉɱÉÒ± É ±É½þÉx É VɱÉÊ´ ÉtÖiÉ |ÉEò ±{É Ê´ ÉEòº ÉÒi É E ò¯ û <ÎSU ôiÉÉiÉ + ¶ÉÉ JÉÉVÉM ÉÒ =tÉäV ÉEòÉÆE òbÚ÷x É iª ÉÉÆSÉÒ {ÉÚ ÉÇ +½ Çþ iÉÉ Êx ÉζSÉiÉ E ò® ú hªÉɺ ÉÉ`öÒ +Éìx É ±ÉÉ<Çx É |ɺ iÉÉ´ É ¨ÉÉMÉÊ´ ÉiÉ +ɽäþ iÉ . {ÉÚ ÉÇ +½Çþ iÉÉ Êx ÉÊ´ Énù É º ÉÆS É ´ É® ú Ò±É º ÉÆE ä òiɺ l ɳý É´ É® ú Ênù x ÉÉÆEò 26 /09/ 20 11 iÉä 2 5/10/ 2011 {ɪÉÇx i É = {ɱɤvÉ ½þ Éä> ð ¶ÉE òiÉÒ ±É .
+. G ò.
{ÉÚ ÉÇ +½Çþ iÉÉ nù º iÉB ä ÉVÉ GÆò. |ÉE ò ±{ÉÉ SÉä x ÉÉÆ É ´ É º l ÉÉ{ÉÒiÉ Iɨ ÉiÉÉ (¨ Éä.´ Éì] )
1 º ÉÒ<Ç(<Ç) / BSÉ{ÉÒ / Bº ÉBSÉ{ÉÒ/
º ÉÒ{ÉÒ{ÉÒ/ +ɪÉ{ÉÒ{ÉÒ /6 7 + Êx ɨx É ´ É v ÉÉÇ VɱÉÊ´ ÉtÖiÉ |ÉEò ±{É i ÉÉ .: +É´ ÉÔ÷, ÊVÉ . : ´ É vÉÉÇ (0.7 50 ¨ Éä.´ Éì]õ )
2 º ÉÒ<Ç(<Ç) / BSÉ{ÉÒ / Bº ÉBSÉ{ÉÒ/ º ÉÒ{ÉÒ{ÉÒ/ +ɪÉ{ÉÒ{ÉÒ /6 8+
¶É½þ Éx ÉÚ® ú Eòɱɴ ÉÉ |É{ÉÉiÉ VÉ ±ÉÊ´ ÉtÖiÉ | ÉEò± {É ., i ÉÉ . +SÉ ±É{É Ú® ú ÊVÉ . +¨ É® úÉ´ Éi ÉÒ ( 0 .3 50¨ Éä.´ Éì] õ)
3 º ÉÒ<Ç(<Ç) / BSÉ{ÉÒ / Bº ÉBSÉ{ÉÒ/ º ÉÒ{ÉÒ{ÉÒ/ +ɪÉ{ÉÒ{ÉÒ /6 9 +
¤ÉÉ´ Éx Él Éb÷ý Ò – 1 VɱÉÊ´ ÉtÖiÉ |ÉEò ±{É , iÉÉ - iÉÖ Éº É® ú , ÊVɱ ½þÉ - ¦ÉÆb÷É® ú É (0 .3 50 ¨ Éä.´ Éì] õ)
4 º ÉÒ<Ç(<Ç) / BSÉ{ÉÒ / Bº ÉBSÉ{ÉÒ/ º ÉÒ{ÉÒ{ÉÒ/ +ɪÉ{ÉÒ{ÉÒ /7 0+
¤ÉÉ´ Éx Él Éb÷ý Ò – 2 VɱÉÊ´ ÉtÖi É |ÉEò± {É , iÉÉ - i ÉÖ Éº É® ú , ÊVɱ ½þÉ - ¦ÉÆb÷É® ú É (0 .6 00 ¨ Éä.´ Éì] õ )
5 º ÉÒ<Ç(<Ç) / BSÉ{ÉÒ / Bº ÉBSÉ{ÉÒ/ º ÉÒ{ÉÒ{ÉÒ/ +ɪÉ{ÉÒ{ÉÒ /7 1+
EòɱÉÒº É® úÉ® ú VɱÉÊ´ ÉtÖiÉ |ÉE ò± {É , iÉÉ .- º ÉɱÉäE òº ÉÉ ÊVÉ . MÉÉåÊnù ªÉÉ (0.40 0 ¨ Éä.´ Éì] õ)
VÉä =tÉäVÉEò/ |É´ ÉiÉÇEòú {Éʽþ ±ª ÉÉÆnù ÉSÉ <Ç- Êx ÉÊ´ Énù É |ÉÊG òªÉäiÉ ¦ÉÉMÉ PÉäiÉ +ɽäþ iÉ i ªÉÉÆx ÉÉ ´ É® ú Ò±É º ÉÆEäòiÉ º l ɳ ýÉ´ É® ú Ênù±Éä ±ª ÉÉ ¨ ÉÉM ÉÇnù ¶ÉÇE ò iÉi´ ÉÉx ÉÖº ÉÉ® ú |É l ɨ É Êb÷Z ÉÒ] õ ±É ˺ ÉMÉx ÉäSÉ® ú º É] õ ÔÊ¡òEäò] õ, ªÉÖ VÉ® ú +ɪÉb÷Ò ´ É {Éɺ É´ ÉbÇ÷ |ÉÉ {i É Eò¯ ûx É PÉähÉä +É´ ɶªÉEò +ɽäþ . <Ç- Êx ÉÊ´ Énù É |ÉÊGòª ÉÉ E òɨ Éɺ ÉÆnù ¦ ÉÉÇi É º É´ ÉÇ ¨ ÉÉʽþ iÉÒ ´ É® ú Ò±É º ÉÆEäòiÉ º l ɳ ý É´ É® ú = {ɱɤvÉ +ɽäþ . <Ç- Êx ÉÊ´ Énù É º ÉƤÉÆvÉÒ EòɽþÒ º ɽþ É ªª ÉiÉÉ +É´ ɶªÉE ò +º ɱª Éɺ É (b÷É> ð x É ±ÉÉäb÷ / +{É ±ÉÉäb÷) ¡òÉ äx É x ÉÆ.020-41466666 <Ç- Êx ÉÊ´ Énù É E òɪÉÇ|ÉhÉÉ ±ÉÒ ¨ Énù iÉ EòIÉ , [email protected] ªÉÉÆSªÉɶÉÒ ºÉÆ{ÉEÇ ò º ÉÉ vÉhª ÉÉiÉ ªÉÉ´ ÉÉ . |ɺ iÉÉ´ É º ÉÉnù ® ú E ò® úhª Éɺ ÉÉ` öÒ |É´ ÉiÉÇE ò/ =tÉä VÉE ò ªÉÉÆx ÉÒ E äò±É 䱪ÉÉ + ÉÌ l ÉEò J ÉSÉÉǺ É VɤÉɤÉnù É® ú x É ® ú ɽþi ÉÉ E òÉähÉiÉɽþ Ò B Eò ËEò´ ÉÉ º É´ ÉÇ | ɺ iÉÉ´ É ¡äò] õɳ ý hª ÉÉSÉä ËEò´ ÉÉ º ÉÆ{ÉÚhÉÇ | ɺ iÉÉ´ É |ÉÊGòª ÉÉ ® ú qù E ò® ú hª ÉÉSÉ ä +Ê vÉE òÉ® ú ¶Éɺ Éx ÉÉx Éä ® úÉJ ÉÚx É äö´ ɱÉä +ɽäþ i É.
ºÉ½þÒ/-
+Ê v É IÉE ò +ʦɪ ÉÆi ÉÉ, Ê´ Énù ¦ÉÇ VɱÉÊ´ ÉtÖiÉ ´ É ={ɺ ÉÉ Ëº ÉSÉx É ¨ ÉÆb÷³ ý , x ÉÉMÉ{ÉÚ® ú
Signature of Promoter/Developer No.of corrections Signature of Inviter
7
DETAILED TENDER NOTICE
Govt. of Maharashtra
Water Resources Department
Main Portal : http://maharashtra.etenders.in
WRD Portal: http://wrd.maharashtra.etenders.in
PRIVATE SECTOR PARTICIPATION IN DEVELOPMENT OF SMALL HYDRO ELCETRIC
PROJECTS FOR ELECTRICITY GENERATION
A) Online digital signed Pre-Qualification proposals are invited for and on behalf of Governor of Maharashtra by the
Superintending Engineer, Vidarbha Hydro Electric & Lift Irrigation Circle, Water Resources Department,
Wainganga Nagar, Ajni, Nagpur-440003 Maharashtra (INDIA), Fax No.: 0712-2440058, Ph.No. : 0712-2420922 ,
for Prequalification of the Promoters / Developers who intend to develop SMALL HYDRO ELECTRIC
PROJECTS, as Captive Power Producer (CPP) / Independent Power Producer (IPP) for electricity generation in the
State of Maharashtra by the Promoter / Developer company as stipulated in Hydro Power Policy declared vide Govt.
of Maharashtra, Water Resources Department, G.R.No. PVT-1204/ (160/2004)/HP, dated 15.9.2005.
The Pre-Qualification Documents are available on web site from 26-09-2011 to 25-10-2011
B) The Projects proposed to be offered are as below: --
P.Q.DOCUMENT SCHEDULE
Sr.
No
Pre-Qualification
Document No.
Name of the Hydro Electric Project and
Estimated Installed Capacity
(in MW)
Downloading
(Sale)period
of PQ
Document
Last date and
time of
uploading
(Submission)
of PQ
Proposal
Date and
time of
opening
(If possible)
1 2 3 4 5 6
1 CE(E)/HP/SHP/CPP
/
IPP/ 67A
Lower Wardha HEP
Tal.: Arvi, Dist.: Wardha (0.750 MW)
26/09/2011
to
25/10/2011
02/11/2011
up to
12.00 Hrs.
04/11/2011
at
13.00 Hrs.
2 CE(E)/HP/SHP/CPP
/
IPP/68A
Shahanoor Canal Drop, HEP
Tal. Achalpur, Dist. Amravati
(0.350MW)
26/09/2011
to
25/10/2011
02/11/2011
up to
12.00 Hrs.
04/11/2011
at
14.00 Hrs.
3 CE(E)/HP/SHP/CPP
/
IPP/69A
Bawanthadi – 1 HEP,
Tal. Tumsar,Dist. Bhandara (0.350 MW)
26/09/2011
to
25/10/2011
02/11/2011
up to
12.00 Hrs.
04/11/2011
at
15.00 Hrs.
4 CE(E)/HP/SHP/CPP
/
IPP/70A
Bawanthadi – 2 HEP
Tal. Tumsar, Dist. Bhandara
(0.600 MW)
26/09/2011
to
25/10/2011
02/11/2011
up to
12.00 Hrs.
04/11/2011
at
16.00 Hrs.
5 CE(E)/HP/SHP/CPP
/
IPP/71A
Kalisarar HEP,
Tal. Saleksa , Dist. Gondia (0.400MW)
26/09/2011
to
25/10/2011
02/11/2011
up to
12.00 Hrs.
04/11/2011
at
17.00 Hrs.
1. The Pre-Qualification Documents are available on e-tendering web site of WRD Portal
http://wrd.maharashtra.etenders.in,
2. The cost of each Pre Qualification Document is Rs.7000/- (Rs. Seven Thousand Only) in the form of crossed
D.D. payable at Nagpur in favour of Executive Engineer, Vidarbha Hydro Electric & Lift Irrigation Division,
Nagpur. The D.D. drawn within the downloading period of P.Q. Document will only be accepted.
3. The scanned copy of D.D. should be uploaded alongwith document.
4. Original D.D. and hard copy of the P.Q. document and other information required vide Annexure-II & III of
P.Q. document along with supporting documents should be submitted in the office of the Superintending
Engineer, Vidarbha Hydro Electric & Lift Irrigation Circle, Nagpur on or before the last date and time of
uploading of proposal. The proposal will be rejected if original D.D. and hard copy as mentioned above are not
received within stipulated time.
5. Pre-Qualification Document will be opened in the office of the Superintending Engineer, Vidarbha Hydro
Electric & Lift Irrigation Circle, Nagpur
6. The Promoter/Developer will have to prove his Financial and Technical capability by uploading the necessary
“Information/Documents” as mentioned in Pre-Qualification Document. After scrutiny of the proposals with
supporting document uploaded by the Promoter/Developer on website, a list of qualified Promoter/Developer
will be prepared and only qualified Promoter/Developer will be communicated in this regard. Pre-qualified
Promoters/Developers will be allowed to participate in Price Bids for allotment of project by downloading the
Price Bid document.
Signature of Promoter/Developer No.of corrections Signature of Inviter
8
C) PRICE BID DOCUMENT SCHEDULE
Sr.
No
Price Bid
document No.
Name of the Hydro Electric
Project and Estimated
Installed Capacity
(in MW)
Downloading
(Sale)period of
Price Bid
Document
Last date and
time of
uploading
(Submission) of
Price Bid
Date and time of opening
(If possible)
1 2 3 4 5 6
1 CE(E)/HP/
SHP/CPP/
IPP/67A
Lower Wardha HEP
Tal.: Arvi , Dist.:Wardha
(0.750 MW)
21/11/2011
to
05/12//2011
12/12/2011
up to
12.00 Hrs.
14/12/2011
at
13.00 Hrs.
2 CE(E)/HP/SHP
/CPP/
IPP/68A
Shahanoor Canal Drop, HEP
Tal. Achalpur, Dist.
Amravati
(0.350MW)
21/11/2011
to
05/12//2011
12/12/2011
up to
12.00 Hrs.
14/12/2011
at
14.00 Hrs.
3 CE(E)/HP/SHP
/CPP/
IPP/69A
Bawanthadi – 1 HEP,
Tal. Tumsar,Dist. Bhandara
(0.350 MW)
21/11/2011
to
05/12//2011
12/12/2011
up to
12.00 Hrs.
14/12/2011
at
15.00 Hrs.
4 CE(E)/HP/SHP
/CPP/
IPP/70A
Bawanthadi – 2 HEP
Tal. Tumsar, Dist. Bhandara
(0.600 MW)
26/09/2011
to
25/10/2011
02/11/2011
up to
12.00 Hrs.
04/11/2011
at
16.00 Hrs.
5 CE(E)/HP/SHP
/CPP/
IPP/71A
Kalisarar HEP,
Tal. Saleksa , Dist. Gondia
(0.400MW)
26/09/2011
to
25/10/2011
02/11/2011
up to
12.00 Hrs.
04/11/2011
at
17.00 Hrs.
1. The Price Bid Documents are available on e-tendering web site of WRD Portal http://wrd.maharashtra.etenders.in
2. The cost of each Price Bid Document is Rs. 10000/- (Rs. Ten Thousand Only) in the form of crossed D.D. payable at
Nagpur in favour of Executive Engineer, Vidarbha Hydro Electric & Lift Irrigation Division, Nagpur. The D.D.
drawn within the downloading period of Price Bid Document will only be accepted.
3. The scanned copy of D.D. should be uploaded along with Price Bid document.
4. D.D and EMD in the form of Bank Guarantee in Original along with hard copy of uploaded Documents as per
Envelope No. I & II should be submitted in the office of the Superintending Engineer, Vidarbha Hydro Electric &
Lift Irrigation Circle, Nagpur on or before the last date and time of uploading of Price Bid. The Price Bid will be
rejected if D.D and EMD in the form of Bank Guarantee in Original along with hard copy as mentioned above are not
received within stipulated time.
5. Price Bid Document will be opened in the office of the Superintending Engineer, Vidarbha Hydro Electric & Lift
Irrigation Circle, Nagpur
6. Pre-Bid Conference of pre- qualified Promoter/Developers will be held on 30/11/2011 at 11.00 A.M. in the office of
the Chief Engineer (Electrical), Hydro Projects, Mumbai-01 / Chief Engineer (Civil), Hydro Projects, Sinchan
Bhavan, Barane Road, Mangalwar Peth, Pune-11. All Pre-qualified, Promoters/Developers who have downloaded
Price Bid Document may attend the Pre-bid conference.
D) 1. All subsequent corrigendum/amendment shall be available only on web site. Hence Promoters/Developers are
advised to visit web site until the Pre –Qualification proposal/Price Bid is finally opened.
2. In case of any dispute between uploaded document and copy submitted by Promoter, Pre –Qualification
proposal/Price Bid Documents uploaded by Promoter on web site will be treated as final.
3. Promoters/Developers are not allowed to make any changes in the uploaded document after last date and time of
uploading. If found so, his tender will be rejected outright & he will be liable for other legal action.
4. The Government reserves the right to reject any or all the proposals or annul the process without assigning any
reason and without being responsible for the cost incurred by the Promoter / Developer in preparing his PQ
proposal / Price-Bid.
Sd/-
Superintending Engineer
Vidarbha Hydro Electric and Lift Irrigation Circle,
Nagpur
Signature of Promoter/Developer No.of corrections Signature of Inviter
9
SECTION - II
Instructions to Promoters/Developers.
Signature of Promoter/Developer No.of corrections Signature of Inviter
10
SECTION – II
INSTRUCTIONS TO PROMOTERS / DEVELOPERS
2.1 General Instructions
2.1.1 The Promoters / Developers shall carefully examine the instructions of this Pre-
qualification document No.CE(E)/HP/SHP/CPP/IPP/68A. The Promoters / Developers shall
upload the pre-qualification proposals with supporting documents.
2.1.2 The Promoter / Developer shall bear all costs associated with the preparation and uploading
of his proposals. The Government of Maharashtra, Water resources Department
(GOMWRD) will in no case be responsible or liable for those costs regardless of the
conduct or outcome of the bidding process.
2.2 Requirement of Preparation of Proposal for Pre-qualification
2.2.1 The Promoters / Developers shall upload the pre-qualification proposals duly filled and
signed alongwith all necessary documents. The Promoter / Developer shall upload the pre-
qualification document downloaded by him duly signed on all pages alongwith his proposal.
2.2.2 The uploaded document comprising the proposals for Pre-qualification shall consist of the
following documents: -
i) Scanned copy of Demand draft.
ii) Forwarding letter of the proposal.
iii) The information duly signed as required vide Annexure – II & III, alongwith
supporting documents.
iv) Downloaded Pre-qualification documents
2.2.3 Original Demand Draft and hard copy of the information required vide Annexure-II & III
alongwith supporting documents should be submitted in the office of the Superintending
Engineer, Vidarbha Hydro Electric & Lift Irrigation Circle , Nagpur on or before the last
date and time of uploading of proposal.
2.2.4 In case of any discrepancy / dispute between uploaded Document and hard copy submitted by
Promoter, Pre-qualification proposal uploaded by Promoter on website will be treated as final.
Signature of Promoter/Developer No.of corrections Signature of Inviter
11
2.2.5 Promoter shall submit the information / documents strictly as per requirement of Annexure No.II &
III. Additional supporting document shall not be attached unless called for. If any additional
documents are attached, the same shall be returned to the Promoter as they are. Inviter may obtain
additional information / documents if required from Promoter.
2.2.6 All subsequent corrigendum / amendment shall be available only on website. Hence Promoters /
Developers are advised to visit website until the PQ proposal is finally opened.
2.2.7 Over writing should be avoided. Any wrong word should be scratched by a line over it and
correct word should be written separately. Such a correction should be signed or initialed.
2.2.8 Corrections, made by hand writing should be duly initialed near to such correction. Any such
correction by hand writing will not be accepted if not initialed or signed.
2.2.9 Each page of the proposals shall be signed by Promoters / Developers.
2.2.10 The proposals sent telegraphically or by fax will not be acceptable.
2.2.11 GOMWRD will not be responsible for delay in uploading / receipt of proposals.
2.3 Uploading of proposal for Pre-qualification
2.3.1 The Promoter / Developers shall upload his proposal comprising of all documents stated in
Para 2.2 above.
2.3.2 If the proposals are not uploaded in stipulated time, the GOMWRD will not be responsible.
2.3.3 The proposals shall be uploaded on or before 12.00 Hrs. on 2/11/2011. Proposal uploaded
after the dead line for uploading of proposals will not be accepted.
2.3.4 Submission of Proposal for Pre-qualification
Original Demand Draft and hard copy of the information required vide Annexure – II and III
alongwith the supporting documents should be submitted in the office of the Superintending
Engineer, Vidarbha Hydro Electric & Lift Irrigation Circle , Nagpur on or before the last date
and time of uploading of proposal. The proposal will be rejected if original Demand Draft and
hard copy as mentioned above are not received within stipulated time.
Signature of Promoter/Developer No.of corrections Signature of Inviter
12
2.3 Opening of proposal
2.4.1 The PQ proposals of only those Promoters will be opened who have submitted the Demand
Draft as per requirement of S.No.B(2) of Detailed Tender Notice.
2.4.2 The uploaded copy of Pre-Qualification proposals will be opened in the office of
Superintending Engineer, Vidarbha Hydro Electric & Lift Irrigation Circle, Wainganga
Nagar, Ajni, Nagpur - 440003.
Note for Clause No.2.3 & 2.4: In the event of specified date for opening of proposals,
being declared a holiday for the GOMWRD, the proposals will be opened as per appointed
time on the next working day.
2.5 Evaluation of proposals
2.5.1 Following procedure will be adopted for evaluation of proposal.
2.5.2 A pre-qualification proposals uploaded from the prospective Promoters / Developers will
be evaluated by allotting certain marks for their status, experience, financial position etc.
as given in Annexure-I, II & III enclosed.
2.5.3 This procedure is only for short listing of Promoters / Developers. The qualified Promoters
/ Developers will only be allowed to participate in the price bidding for CPP/ IPP allotment
whenever it will be finalised in future. The pre-qualification does not guarantee any
allotment of CPP / IPP.
2.5.4 Pre-qualified Promoters/Developers shall be communicated to participate in price bidding
for allotment of the project by downloading the price bid Document. The bidding shall be
on the basis of premium offered by the bidder over and above THRESHOLD PREMIUM.
2.5.5 The pre-qualification document will not form the part of agreement to be made with the
successful bidder for allotment of the project.
Signature of Promoter/Developer No.of corrections Signature of Inviter
13
2.5.6 The promoters /developers shall note the following while, participating in uploading of
proposals for pre-qualification and subsequent price bids.
1) The installed capacity and estimated annual generation of the project is indicative
only and GOMWRD does not take any responsibility in this respect.
2) Annual generation figures estimated by GOMWRD are based on available data.
The Promoter may see this data in the office of the Superintending Engineer,
Irrigation Projects Investigation Circle, Nagpur/ Superintending Engineer, Vidarbha
Hydro Electric & Lift Irrigation, Circle, Nagpur. However, it shall be responsibility
of the Promoter to validate the hydrological data made available by GOMWRD in
PQ document or any other GOMWRD document through its consultant and draw
his own inferences only after such validation. Promoter shall estimate installed
capacity/annual generation only by using such validated data. As the upfront
premium to be quoted in price bid needs to be quoted based on such Validated data,
Upfront Premium amount cannot be curtailed at later stage. GOMWRD shall not
take responsibility regarding correctness of data & its consequential losses if any.
No claims for less generation due to any reasons including incorrectness of data,
less rainfall shall be entertained.
Promoter shall note that releases of water shall be strictly as per irrigation /
domestic/ Industrial demands and the generation will have to be synchronised with
these releases. GOMWRD reserves right to decide the release schedule and
modify it from time to time as per the requirement. Further, when the Irrigation /
Domestic/ Industrial requirements is more than discharging capacity of power
outlet GOMWRD may release additional discharge through other outlets. The
decision of GOMWRD in this regard shall be final and binding. No claims of
compensation on these grounds shall be entertained.
3) During the rainy season the GOMWRD shall review the reservoir contents and
trend of mansoon time to time and may allow to release water through power outlet
when spills are likely. However, decision of the GOMWRD shall be final in this
regard.
4) GOMWRD shall not compensate for less generation due to any reasons.
Signature of Promoter/Developer No.of corrections Signature of Inviter
14
5) Generation Restrictions:
In extraordinary circumstances arising out of threat to security of the state, public
order or a natural calamity or such circumstances arising out of public interest, the
developer shall have to operate & maintain generating station in accordance with
the directives of state government subject to the provisions of section 11 of EA,
2003.
6) No Compensation for Grid Failure:
Developer/ Third party consumer/ Captive user/ Licensee (authorised consumer)
shall abide by grid discipline & will not be entitled for any compensation in the
event of grid failure, shut down, interruption in power supply etc.
7) Exclusive Jurisdiction Of MERC:
MERC has exclusive jurisdiction on those provisions of this Policy which are
within its regulatory mandate under the provision of Electricity Act, 2003,
especially regarding electricity sales rates, power purchase agreements and
provisions regarding wheeling, banking distribution and transmission loss charges
etc. Similarly, MERC has jurisdiction as per the provisions of EA 2003 as regards
the promotion of non-conventional energy sources, facilities for transmission of
energy, sale of power to any interested consumer and sharing of purchase of power
amongst the STU/Transmission Licensee/Distribution Licensee. Orders regulations,
directives, guidelines issued by MERC regarding these issues from time to time
shall be binding on all.
In the event of dispute in interpretation of this policy or any clause in the
agreement between developer & GOMWRD or STU/Transmission
Licensee/Distribution Licensee, the same shall be referred to MERC to the extent of
its jurisdiction under section 86(1) and other provisions of EA. 2003.
Signature of Promoter/Developer No.of corrections Signature of Inviter
15
SECTION - III
ANNEXURES
i) Annexure - I : Procedure for evaluation
ii) Annexure - II : Information to be furnished by
Promoter/Developer who has been
earlier allotted the SHP for
development
iii) Annexure – III : Information to be furnished by
Promoter/Developer
iv) Annexure - IV : State Hydel Policy of the
Government of Maharashtra,
Water Resources Department
Signature of Promoter/Developer No.of corrections Signature of Inviter
16
SECTION-III
ANNEXURE – I
PROCEDURE FOR EVALUATION
Each Developer / Promoter shall furnish the information as indicated in Annexure –II
and Annexure – III. An eligibility of Developer / Promoter shall be decided on scrutiny of this
information. The scrutiny shall be based on following criterions. Promoter/Developer who secure
minimum 15 marks in Group A and minimum 5 marks each in Group B1 and Group B2
individually specified hereunder shall be declared eligible for bidding and accordingly Price bid
document will be available for downloading ( sale) /issued to him. Group wise required marks
must be obtained for eligibility fulfillment i.e. if the Promoter/Developer secures 25 marks in
Group A and do not secure any marks in Group B, he is not eligible for bidding.
For Promoters/Developers, who have earlier been allotted SHP projects for development;
those intended Promoters / Developers shall carefully upload the requisite information in
Annexure-II. The evaluation of PQ document will be done only for those intending Promoters /
Developers who are found eligible after the scrutiny of the information uploaded by them in
Annexure-II. The Promoter /Developer who has—
1) Signed the HPDA but not started the work for the period of two years or more from the
date of signing HPDA.
2) Been issued LoA after approval of TEFR but HPDA not signed within the period of two
years or more from the date of issue of LoA.
3) Started the actual execution of work but has not commissioned the project within three
years from the date of starting of work.( except for projects where infrastructure to be
provided by GOMWRD is incomplete)
Will be disqualified and no further evaluation of his qualifying criteria will be done.
Signature of Promoter/Developer No.of corrections Signature of Inviter
17
MARKING SYSTEM MARKS
GROUP A – FINANCIAL CRITERIA
1. STATUS OF THE FIRM
1.1 Unit from Co-Operative sector 10
1.2 Public Limited Company 8
1.3 Private Limited Company 6
1.4 Partnership / Proprietary 5
2. DEBT: EQUITY RATIO
2.1 Less than 1.5:1 10
2.2 1.5 to 1.75:1 6
2.3 More than 1.75 to 2:1 5
2.4 More than 2:1 0
3. PROMOTERS CONTRIBUTION
3.1 60% or more 10
3.2 between 60% to 33 % 5
3.3 Less than 33 % 0
GROUP B- TECHNICAL CRITERIA
1.0 B1) BACK UP OF DESIGN ENGINEERS
1.1
In house Civil & Electrical Designers
(1.1.1) In house Civil Designers - (4Marks)
(1.1.2) In house Electrical Designers -( 4Marks)
8
1.2 Consulting firm having both Civil as well as electrical engineer
is Proposed to be engaged.
(1.2.1 ) Consulting firm having Civil engineers is
proposed to be engaged. - ( 3 Marks)
6
Signature of Promoter/Developer No.of corrections Signature of Inviter
18
(1.2.2 ) Consulting firm having Electrical engineers is
proposed to be engaged. - ( 3 Marks)
1.3 Separate Civil & Electrical design Consultants proposed
(1.3.1) Separate Civil design Consultants proposed -
(2.5 Marks)
(1.3.2) Separate Electrical design Consultants proposed -
(2.5 Marks)
5
2 B2) EXPERIENCE OF H.E.P. CONSTRUCTION /
ERECTION IN E & M WORKS.
A) Experience of civil construction
2.1a Construction of 3 Power Houses completed. 4
2.2a Construction of 2 Power Houses completed 3
2.3a Construction of 1 power house completed 2
B) Experience of E&M works in power house (The experience
shall indicate erection of at least one Turbine- Generator plant)
2.1b Erection of 3 power houses completed
8
2.2b Erection of 2 power houses completed 6
2.3b Erection of 1 power house completed 3
Maximum Marks 50
NOTE 1) Promoter/Developer shall be necessarily a profit making company.
2) The Promoter/Developer shall not be eligible for marks unless necessary supporting
documents as mentioned in Annexure-III are uploaded /furnished.
3) All the terms and conditions of G.R.No. PVT-1204/(160/2004)/HP, dtd.
15th
September, 2005 will be applicable.
4) The previous experience of Promoter for development of small HEP will also be a
criteria as mentioned earlier in the document. All the necessary documents shall be
uploaded/ furnished by Developer / Promoter to qualify the stipulated criteria.
Signature of Promoter/Developer No.of corrections Signature of Inviter
19
Annexure-II
(To be uploaded / furnished by the Promoters/Developers who have been earlier allotted SHPs for
development.)
Sr.
No.
Name of allotted
project
Date of issue
of LoA
Date of
signing of
HPDA
Date of
completion of
project
Remarks
1
2
Signature and seal of
Developer/Promoter
Signature of Promoter/Developer No.of corrections Signature of Inviter
20
ANNEXURE – III
INFORMATION TO BE UPLOADED/FURNISHED BY PROMOTER / DEVELOPER
1. GENERAL INFORMATION
1.1 Name of Promoting Company / Developer.
1.2 Constitution of Company (Enclose registration certificate under companies act
1956)
(Public / Private Limited Company / Co-Operative Society/ Partnership /
Proprietary Concern)
1.3 Date of incorporation / Registration
1.4 Date of Commencement of business.
1.5 Sector
(Public sector / Joint Sector / Private Sector / Co-Operative sector)
1.6 Location
(Indicate Village, Tahasil, District & State)
(a) Registered Office
(b) Controlling / Head Office.
1.7 Postal Address of Promoting Company.
2. PROMOTER’S BIO-DATA
2.1 Give bio-data of main promoters including information on name, address. age,
educational qualification, past industrial / business experience in particular
industry. Brief write up on other companies if any promoted by him or with which
he is associated, together with copy of latest audited balance sheet (to be furnished
separately in case of each Promoter).
2.2 In case the promoter is a limited company, furnish brief write up on the activities &
the past performance of the company.)
(Audited balance sheets and profit loss accounts for the last three years of the
Promoter Company to be enclosed.)
Signature of Promoter/Developer No.of corrections Signature of Inviter
21
3. DETAILS OF CONSUMPTION UNIT.
PROPOSAL OF PROMOTER /DEVELOPER FOR CAPTIVE POWER
PRODUCER (CPP) / INDEPENDENT POWER PRODUCER (IPP).
3.1 Details of existing industrial units for which generated energy would be utilized.
3.1.1 Name & address of registered office of industrial unit / units.
3.1.2 Location of industrial unit / units.
3.1.3 Unit wise energy consumption in MUs per annum for last three years.
3.1.4 Unit wise maximum & minimum demand in KVA for last three years.
3.2 Do you propose to start new industrial unit for consumption of Captive power? If
yes, give following details.
3.2.1 Give nature of unit.
3.2.2 Give location of unit.
3.2.3 Give energy requirements of proposed unit in MUs per annum
3.2.4 Give maximum & minimum demand in KVA.
3.2.5 What would be the estimated cost of this unit?
3.2.6 What would be the promoters equity share capital in this unit.
4. FINANCIAL CAPABILITIES:
4.1 Anticipated cost of the proposed hydroelectric project, duly certified by the
consultant along with brief details of estimate.
4.2 Give the details regarding means of financing.
(The details given by Promoter under Sr.No.4.2.1 to 4.2.3 with documentary proof
will be considered as Equity)
4.2.1 Subscription of the promoter. Give valid details of source along with
documentary proofs.
4.2.2 Arrangements through friends / relatives / associates alongwith commitment
letters.
Signature of Promoter/Developer No.of corrections Signature of Inviter
22
4.2.3 Internal accruals.
4.2.4 Unsecured loans to be arranged by promoters.
4.2.5 Institutional contribution as a Co-promoter if any.
4.2.6 Through Public Issue.
4.2.7 Term Loans.
4.3 Debt: Equity ratio.
5. TECHNICAL ARRANGEMENTS:
5.1 Backup of Design Engineers.
5.1.1. Do you have in house design capabilities for both Civil as well as electrical design
engineers?
If yes, give the organizational set up of design wing, bio-data of design engineers,
particulars of work done in past & work in hand. Give documentary evidence
regarding personnel's engaged in design wing. Documentary evidence for design of
Civil and Electrical works of Hydro Power Projects shall also be furnished.
5.1.2 Do you propose to engage design-consulting firm having both Civil as well as
Electrical design engineers? If yes, give complete credentials as well as past
experience of such firm along with notarized MOU with the consulting firm on
stamp paper of requisite value. Documentary evidence for design of Civil and
Electrical works of Hydro Power Projects carried out by the consulting firm shall
also be furnished.
5.1.3 Do you propose to engage separate consulting firms for Civil & Electrical designs?
If yes, give complete credentials as well as past experience of such firms along
with notarized MOU with the consulting firm on stamp paper of requisite value.
Documentary evidence for design of Civil and Electrical works of Hydro Power
Projects carried out by both the consulting firms shall also be furnished.
Signature of Promoter/Developer No.of corrections Signature of Inviter
23
5.2 Backup of Experienced Construction Firm / Erection Expert
5.2.1 Do you have experience of construction of H.E. Projects / erection of H.E.
Machinery? If yes, give details of projects executed in last 10 years. (State no. of
projects and their details such as Name, location, capacity & status of each project).
Enclose work done certificates certified by an officer not below the rank of
Executive Engineer. The work done certificate shall indicate construction of at
least one power house construction for Civil works and erection of at least one HE
project and commissioned successfully.
5.2.2 Do you propose to engage experienced construction / Erection firm? If yes, give
details of projects executed in last 10 years along with work done certificates
certified by an officer not below the rank of Executive Engineer and notarized
MOU with construction / Erection firm on stamp paper of requisite value (State No.
of projects and their details such as Name, location, capacity & status of each
project). The work done certificate shall indicate construction of at least one power
house construction for Civil works and erection of at least one HE project and
commissioned successfully.
Signature of Promoter/Developer No.of corrections Signature of Inviter
24
ANNEXURE – IV
State Hydel Policy For Development Of
Small Hydro Power Projects through
Private Sector Participation
GOVERNMENT OF MAHARASHTRA
WATER RESOURCES DEPARTMENT
Government Resolution No. PVT-1204/(160/2004)/ HP
Mantralaya, Mumbai 400032
Dated: 15th September 2005.
I. PREAMBLE:
Power is a critical infrastructure on which the socio-economic development of the country
depends. The growth of the economy and its global competitiveness hinges on the availability of
quality power at competitive rates. Therefore, it is imperative that electricity is made available at
globally competitive cost.
The Government of Maharashtra (GoM) has laid maximum emphasis on the full
development of its hydro potential being a clean & renewable source of energy. It has been
therefore decided to encourage private sector participation in development of Small Hydro Projects
( SHPs). Accordingly GoM declared policy vide Water Resources Department’s (previously
known as Irrigation Department’s (ID)) G.R. No. HEP (7/2002)/HP, dated 28th November 2002.
This policy is applicable to CPP through hydropower projects up to 25 MW installed capacity
which is considered as one of the non-conventional energy source.
Electricity Act 2003 (EA 2003) has come into force since 10th June, 2003. This act has
replaced the Indian Electricity Act 1910, the Electricity (Supply) Act 1948 and Electricity
Regulatory Commissions Act, 1998.
The act has delicenced the generation and permitted direct commercial relationship
between generating company and consumer/trader. The act has awarded generating company a
right to open access to State Transmission Utilities (STU) for the purpose of wheeling electricity.
The EA 2003 has also enlarged the definition of Captive user.
Signature of Promoter/Developer No.of corrections Signature of Inviter
25
During the policy implementation process of GoM’s policy dated 28.11.02 number of
suggestions have been received requesting for certain amendments to the provisions in the state
policy in light of provisions of EA 2003.
On this background and with an intention to harmonise the provisions in the state policy
with that in EA 2003 , GoM is pleased to declare revised policy for development of SHPs up to 25
MW capacity, through the private sector participation. This policy seeks to replace the earlier
policy dated 28th November, 2002. The revised policy is intended to encourage the participation of
both the Captive Power Producers (CPPs) and Independent Power Producers (IPPs) in
development of SHP in the state.
II. Objectives :
The objective of the policy is
� to harness the green power with the help of private sector.
� to create suitable environment for attracting private sector investment .&
� to lay down the framework for the implementation of the policy.
Part A : Policy Guide Lines:
A-1 Scope:
The list of identified SHPs (up to 25 MW) sites is available with Government of
Maharashtra , Water Resources Department (GoMWRD). The same shall be updated from time to
time. The projects from this list shall be offered for development as CPP/IPP. Unidentified SHP
sites proposed by the developers for development of CPP/IPP shall also be governed by this
policy.
For the purpose of this policy, Captive Power Plant (CPP) is defined as a SHP set up under
section 9 read with clause (8) of section 2 of EA 2003 and compiling the requirements stipulated in
Electricity Rules 2005 notified by Ministry of Power, Govt. of India (GoI) on 8th June, 2005.
For the purpose of this policy IPP is defined as SHP set by any person as defined in EA
2003 for generating electricity, which can be sold to any consumer located in the state of
Maharashtra or any other willing distribution licensee or any Power Trading Company.
The provisions of this policy are also applicable for any governmental or
semigovernmental organisation of GoM who owns the water reservoirs.
Signature of Promoter/Developer No.of corrections Signature of Inviter
26
A-2 Operative Period:
The policy shall be in operation from the date of publication of this resolution till it is
cancelled/revised. All the projects awarded within this period shall be governed by this policy.
The SHP allotted under this policy shall be on Build, Operate & Transfer Basis (BOT). The
BOT period shall be 30 years. The BOT period shall start from the date of commissioning of the
project. At the end of the BOT period the absolute ownership of the SHP along with land,
switchyard & allied equipment shall automatically stand transferred to GoMWRD free of cost.
MERC has initiated the tariff determination process for SHPs. Tariff and other dispensation
determined through this process may or may not apply for a period coterminus with BOT and/or
lease period agreed to between the developer and GoMWRD.
GoMWRD may extend the BOT period at its discretion. If the period is extended
GoMWRD reserves the right to review the charges specified in section A-14 of this policy.
A-3 The procedure for selection of Developers:
The procedure for selection of developers shall be as under.
A-3.1 The list of sites for SHPs to be offered for privatisation is available with GoMWRD. This
list shall be displayed on the web site of GoMWRD and shall be updated from time to time.
GoMWRD shall offer projects from this list for development through public notification. The
bidding process shall be open to both CPP and IPP.
A-3.2 Prequalification evaluation of the interested developers shall be done. The criteria for pre-
qualification shall be technical & financial capabilities, past experience and other relevant
attributes of the developer. The necessary information regarding attributes to be evaluated, their
inter-se weightage, guidelines for evaluation, passing score on attributes required for pre-
qualification shall be specified in pre-qualification document. Based on the above criteria the
developers shall be pre-qualified.
A-3.3 The bidding procedure shall be as under.
Signature of Promoter/Developer No.of corrections Signature of Inviter
27
A-3.3.1 Main bidding documents shall be issued only to pre-qualified developers. The minimum
threshold premium shall be mentioned in the bidding document. The bidders shall quote a
premium payable to GoM over and above threshold premium and support his bid by Earnest
money Deposit (EMD). Upfront premium will be the primary consideration for allotment of the
project. Upfront premium offered by both IPPs/CPPs will be evaluated. The highest bid so
evaluated will be the criteria for selection.
A-3.3.2 In most of the projects GoMWRD already constructed intake structure hosting trash rack
& sluice gates. Reinforced concrete lined penstock is also laid in the body of the dam. GoMWRD
intends to recover its exclusive investment on power component viz. trash rack and steel penstock
by fixing the threshold premium for bidding. This threshold premium shall be Rs. 50 Lakhs/MW in
case of SHPs in which GoMWRD has already made investment on trash rack and penstock. In
other cases it shall be zero.
A-3.4 The GoMWRD shall intimate developer regarding his selection and Letter of
Permission (LoP) to the developer. This LoP will empower the developer to make necessary
investigations and prepare Techno-Economic Feasibility Report (TEFR). The data available with
GoMWRD if any shall be made available to the selected developer, free of cost. The Developer
shall draw his own inferences from this data.
A-3.5 If the developer comes forward with his own site for development of the project, GoMWRD
shall issue LoP directly provided the proposed project is not already investigated by GoMWRD.
Decision of Secretary (CAD), GoM in this regard shall be final.
A-4 Development of Project:
A-4.1 After receipt of the LoP the developers shall prepare Techno Economic Feasibility Report
(TEFR). The TEFR shall be prepared considering the fact that the release of water shall be strictly
as per irrigation/domestic/industrial demands and the generation will have to be synchronised with
these releases. GoMWRD reserves the right to decide the release schedule and modify it from time
to time as per the requirements. GoMWRD shall make serious efforts to release maximum volume
of water in such a manner that it can be used for generation of electricity at desired time. However,
the decision of GoMWRD in this regard shall be final and binding. No claims of compensation on
these grounds shall be entertained.
Signature of Promoter/Developer No.of corrections Signature of Inviter
28
If the developer is satisfied about the techno-economic viability of the project he shall
submit the TEFR to GoMWRD within three months from the date of LoP alongwith the processing
fees as indicated hereinafter.
Sr. No. Installed Capacity Processing Fees in Rs. lakhs.
1. Up to 999 kW 1
2. 1000 KW to 1999 KW 3.5
3 2000 KW to 4999 KW 5
4. 5000 KW to 25000 KW 10
Under any circumstance (whether the project is viable or not) the developer is not entitled
for any claim for reimbursement of expenditure that he has made on investigations, preparation of
TEFR and its scrutiny.
A-4.2 GoMWRD before concurring with TEFR shall ascertain whether or not in its opinion,
A-4.2.1 Proposed scheme will prejudice the prospect for best ultimate development of the hydro
potential of the site consistent with the requirements of the domestic/irrigation/industrial water,
navigation, flood control or other public purposes.
A-4.2.2 Proposed company exploits the full potential of the site allotted to the developer. In
normal situation development in stages will not be allowed. However, due to any project specific
reasons if stage wise development of the project is necessary, Secretary (CAD), GoM is authorised
to allow stage wise development.
A-4.2.3 Proposed scheme meets the norms regarding dam design & safety.
A-4.3 If the TEFR satisfies all the above prerequisites GoMWRD shall approve the TEFR and
issue Letter of Allotment (LoA) within one month from the date of submission of TEFR or date of
giving all the clarifications by developer, whichever is later. On receipt of LoA developer shall
deposit the Performance Security and sign the Hydro Power Development Agreement (HPDA)
with GoMWRD within eight days. Amount of Security deposit shall be such that yearly charges
payable to GoMWRD on account of water royalty, maintenance charges and land lease charges
could be recovered from it.
Signature of Promoter/Developer No.of corrections Signature of Inviter
29
A-4.4: Developer shall arrange for all the necessary clearances & financial closure within 6
months from the date of signing HPDA. GoMWRD shall facilitate developer in getting clearances.
However, it shall be the primary responsibility of developer to arrange for various clearances
within stipulated time. This period shall be extended if there are valid reasons for such extension,
which shall be decided by Secretary (CAD), GoM. Failure of developer in arranging the various
clearances & finance within a stipulated period will result into automatic cancellation of HPDA
and forfeiture of Performance Security. In case, any of the state level or central level clearance is
denied for a particular reason the performance Security shall be refunded to the developer.
However, cost incurred by developer for investigations, preparing TEFR, getting clearances and
arranging finance shall not be refunded in any case.
A-4.5: After getting necessary clearances & financial closure within stipulated period &
submitting the documentary proof there of GoMWRD shall issue letter to the developer (within 8
days) to deposit the amount of Upfront Premium offered by him within one month.
Failure of developer to deposit amount of Upfront Premium within stipulated period will
result into automatic cancellation of HPDA and forfeiture of Performance Security. GoMWRD
shall authorise the developer to start the development work within 8 days from payment of amount
of Upfront Premium.
A-4.6 In case of surrender of allotment by developer due to any reason he will be penalised as
under and no compensation would be payable to the developer in such instance...
Sr.
No
Stage at which project is
surrendered
Penalty
1 Before signing HPDA Forfeiture of Earnest Money Deposit except in the
event the project is found unviable
2 After signing HPDA Forfeiture of Performance Security except when any
state/central level clearances are denied
3 After permission for
development is given
Forfeiture of Performance Security plus amount of
Upfront Premium.
A-4.7 The project shall be made operational within 24 months from the date of
authorisation for development. However, any project specific issues shall be considered and
project implementation schedule shall be drafted accordingly and incorporated in HPDA. The land
under the possession of the government will be handed over to the developer on lease rent. If no
Signature of Promoter/Developer No.of corrections Signature of Inviter
30
government land is available for setting the unit, the developer has to arrange for land acquisition
from private parties at his cost.
A-4.8: During the project implementation the progress of the developer shall be reviewed
at various milestones & if the progress is not found satisfactory reasons for the delay shall be
called for. If the reasons for the delay are found to be beyond the control of the developer,
necessary time extension shall be given otherwise developer would be liable to pay a penalty as
decided by GoMWRD. The details regarding various milestones and rate of penalty shall be
included in the HPDA.
A-4.9 The developer shall be responsible for carrying out the work with due diligence
with regard to his responsibilities under various Central/ State / Local laws, rules and regulations
& ensure the compliance of the same.
A-4.10 The developer shall insure the assets of the project and keep them insured during
the term of HPDA.
A-5 Consultancy:
In case, the developer opt to utilise the Consultancy services of GoMWRD in respect of
further investigations, preparation of TEFR, estimates, designs & drafting specifications etc. he
can avail the same at mutually agreed rates & conditions. GoMWRD has ISO 9001-2000
recognized design organization which has expertise in this field.
A-6 Generation:
Developer can establish, operate & maintain a generating power plant without any license,
subject to following requirements.
A-6.1 TEFR is approved by GoMWRD.
A-6.2 All the Statutory Clearances are received.
A-6.3 Technical standards relating to connectivity with the grid referred to in clause (b) of
Section 73, provisions in section 10 and other applicable provisions of EA 2003 are
followed.
Signature of Promoter/Developer No.of corrections Signature of Inviter
31
A-7 Grid Interfacing & Evacuation Arrangements:
This will be as per dispensation emerging from the tariff and procurement process
determination exercise initiated by MERC.
A-8 Transmission/Distribution entities:
Developer may construct and maintain dedicated transmission lines as defined in EA, 2003
from the generation plant to the destination of his use. However, he will have the right to access
for existing transmission facilities in the State as per the provisions of EA, 2003 and the
Regulations and other dispensations of MERC regarding Transmission Open Access. The local
distribution licensee shall be permitted to evacuate power from SHP directly if he desires to do so.
The developer shall sign Energy wheeling agreement with Transmission entity / distribution
licensee. When transmission lines of Transmission entities are used, rates of wheeling charges and
transmission losses shall be as decided by MERC from time to time, and wheeling transactions
shall be settled accordingly.
When an open access is provided by MERC under subsection (2) of section 42 of
Electricity Act 2003 the developer shall be responsible for payment of transmission charges &
surcharge thereon as decided by MERC for the energy sold to Third Party Consumer/Distribution
Licensee/Power Trading Company.
The metering of energy generated at generating station and corresponding credit at the
consumption point shall be on ToD (Time of Day) tariff slots.
A-9 Banking :
This will be as per dispensation emerging from the tariff and procurement process
determination exercise initiated by MERC.
A-10 Generation Restrictions:
In extraordinary circumstances arising out of threat to security of the state, public order or a
natural calamity or such circumstances arising out of public interest, the developer shall have to
operate & maintain generating station in accordance with the directives of state government
subject to the provisions of section 11 of EA, 2003.
Signature of Promoter/Developer No.of corrections Signature of Inviter
32
A-11 No Compensation for Grid Failure:
Developer/ Third party consumer/ Captive user/ Licensee (authorised consumer) shall
abide by grid discipline & will not be entitled for any compensation in the event of grid failure,
shut down, interruption in power supply etc.
A-12 Developers to Pay to GoMWRD:
A-12.1 Water royalty : Developer shall pay the water royalty at the rate of Rs.0.05 per
unit of energy generated .
A-12.2 Charges for maintenance of intake structure, penstock etc. at the rate of Rs 0.05 for
every unit generated.
A-12.3 Land lease charges for the GoMWRD land at the rate of Rs.1/kW of installed
capacity/ Year.
A-12.4 The above rates of royalty charges, maintenance charges and lease charges are for
the first year and the same shall be increased in every subsequent years by 5% by compounding.
A-12.5 The above rates of royalty charges , maintenance charges and lease charges shall be
reviewed after 30 years if lease period is extended.
A-12.6 Water royalty charges and maintenance charges shall be invoiced quarterly at the
end of each quarter and land lease charges shall be invoiced at the beginning of every financial
year. All these charges will have to be settled within 30 days after the receipt of the invoice.
Thereafter the interest at S.B.I. prime lending rate plus 2% (Two percent) per annum on delayed
payment for delayed period shall be made applicable.
A-12.7 During first 10 years after commissioning, if in any particular year, 75% of the
75% dependable water could not be made available to the developer, then water royalty charges
and maintenance charges for that year shall be waived off.
Signature of Promoter/Developer No.of corrections Signature of Inviter
33
A-13 Taxes & Duties:
The developer shall pay taxes, duties & other levies as applicable from time to time to the
respective departments of the State & Central and Local Governments unless developers are
specifically exempted from paying such taxes & duties.
It will be presumed that developer has considered all these aspects before bidding.
However, to encourage and promote sale of available surplus captive power within the state
and to avoid undue overburden on CPP with further levy of Electricity Duty, Govt. of Maharashtra
exempt CPPs under this policy from Electricity Duty and Tax on Sale of Electricity.
A-14 Transfer of Allotment:
If the developer wants to transfer ownership of generating unit completely to other
developer he will be permitted to do so on prior approval of GoMWRD. GoMWRD may give such
approval provided,
A-14.1 Financial institution has consented such transfer.
A-14.2 GoMWRD is satisfied that the new developer shall consume the generated energy
primarily for his own use ( in case of CPP only).
A-14.3 Proposed developer agrees to all the terms & conditions agreed to by the original
developer.
A-14.4 And new developer deposits the transfer fees with GoMWRD as RS. 1 Lakhs/MW
of installation. This transfer fee may vary as per prevailing Whole Sale Price Index with base index
of 2003-04. This transfer fees are in addition to transfer fees payable if any, to other authority.
A-15 Sale of Power:
Generated electricity can be sold to any consumer locate in the state of Maharashtra or any
willing distribution licensee or any power trading company. However, Maharashtra Electricity
Distribution Company shall have the first right of refusal. Sale of power shall be as per
dispensation emerging from the tariff and procurement process determination exercise initiated by
MERC.
Signature of Promoter/Developer No.of corrections Signature of Inviter
34
A-16 Inspection of Project :
The GoMWRD engineers before and after the monsoon shall inspect the power project
from safety point of view. The developer shall render all requisite help and cooperation for such
inspection. Similarly, statutory inspection from Factory inspector / Electrical Inspector shall be got
done. The Inspection Reports shall be furnished to GoMWRD annually.
Developer shall maintain all the record regarding capacity, generation, PLF, downtime with
relevant constraints etc. and make available all these records to inspecting authority for inspection.
A-17 Exclusive Jurisdiction Of MERC:
MERC has exclusive jurisdiction on those provisions of this Policy which are within its
regulatory mandate under the provision of Electricity Act, 2003, especially regarding electricity
sales rates, power purchase agreements and provisions regarding wheeling, banking distribution
and transmission loss charges etc. Similarly, MERC has jurisdiction as per the provisions of EA
2003 as regards the promotion of non-conventional energy sources, facilities for transmission of
energy, sale of power to any interested consumer and sharing of purchase of power amongst the
STU/Transmission Licensee/Distribution Licensee. Orders regulations, directives, guidelines
issued by MERC regarding these issues from time to time shall be binding on all.
In the event of dispute in interpretation of this policy or any clause in the agreement
between developer & GoMWRD or STU/Transmission Licensee/Distribution Licensee, the same
shall be refereed to MERC to the extent of its jurisdiction under section 86(1) and other provisions
of EA. 2003.
A-18 : Obligations of GoMWRD:
A-18.1: Nodal officer of GoMWRD shall extend all the possible assistance for getting the
various clearances required.
A-18.2: GoMWRD shall approve the TEFR within 1 month from the date of submission or
date of giving all the clarifications by developer whichever is later.
A-18.3: GoMWRD shall hand over the site for development of the project within 15 days
from the permission accorded to commence the work.
Signature of Promoter/Developer No.of corrections Signature of Inviter
35
A-18.4: Developer shall be allowed to use the approach road to the power house if it is in
possession of GoMWRD . However, the developer at his own cost shall carry out the maintenance
of the same.
A-18.5: GoMWRD shall provide residential quarters of suitable type, if and as available
near the project site for developer for his staff during construction period on rental basis. However,
the developer at his own cost shall carry out the maintenance of the same.
A-18.6: GoMWRD shall make available the piece(s) of land if available to the
developer for construction of residential quarters/office of maintenance staff on reasonable terms
to be agreed between GoMWRD & developer. The period of such agreement shall be the same as
that of HPDA. In such case the developer shall handover such buildings to the GoMWRD at the
end of the agreement free of cost. However, the developer shall not be allowed to make any
commercial use of such land.
Part-B General Provisions:
B-1 The developers to whom CPP is allotted by GoMWRD under previous policy & willing to
opt for the provisions of this policy may apply for the same alongwith the necessary processing
fee. GoMWRD shall accord such permission if requisite requirements are complied by the
developer. The processing fees for this purpose shall be of Rs. 0ne lakh per MW of installation.
This processing fee may vary as per prevailing Whole Sale Price Index with base index of 2003-
04. However, this permission of GoMWRD shall be subjected to provisions of Section A-17 of this
policy and dispensation emerging from the tariff and procurement process determination exercise
initiated by MERC.
B-2: IPPs & CPPs are free to change their option (entity) in due course of time. However, this
permission shall be subjected to provisions of Section A-17 of this policy and dispensation
emerging from the tariff and procurement process determination exercise initiated by MERC.
B-3: Change in option from sale to third party to Licensee and vice versa and switching from
one third party consumer to other third party consumer without change in entity shall also be
governed by provisions of Section A-17 of this policy and dispensation emerging from the tariff
and procurement process determination exercise initiated by MERC.
Signature of Promoter/Developer No.of corrections Signature of Inviter
36
B-4: Provisions in the Policy shall be periodically reviewed in view of the dynamic economics
of the sector. In normal circumstances next review shall be after three years. However, GoM
reserves the right to amend / delete certain provisions of this policy and include additional
provisions, if found necessary for operational ease or to deal with unforeseen issues or if found
necessary due to any further dispensation of GoI or MERC as the case may be. GoM may from
time to time issue orders and practice directions in regard to the implementation of this policy and
matters incidental or ancillary thereto as the GoM may consider appropriate. However, such
amendments shall be made applicable with prospective effects only.
Part-C : Promotional Incentives Offered by GoM
SHPs are the renewable non-polluting energy sources. However, like any other
nonconventional source they are costlier as compared to conventional sources. With an intention to
make available energy from these sources at competitive rates Ministry of Nonconventional
Energy Sources (MNES) GoI has offered some incentive schemes. On the same lines GOM is
pleased to offer following incentives.
C-1 The developer is supposed to commission the project within 24 months from the date of
authorisation. If the developer commissions the project at earlier date, he will be exempted from
water royalty charges & maintenance charges to an extent of units generated before scheduled date
of commissioning.
C-2 CPPs shall be exempted from Electricity Duty on the self consumption of electricity only
for first five years after commissioning if the consumption unit is located in Maharashtra.
C-3 CPPs shall be exempted from tax on Sale of Electricity only if the consumption unit is
located in Maharashtra.
C-4 Technical Consultancy at nominal charges.
C-5 Maharashtra Energy Development Agency, (MEDA), Pune shall assist the developers in
getting incentives for SHPs from MNES, GoI.
This resolution is issued in concurrence of Finance, Energy, Planning and Industry
Departments. This resolution is being in supersession of Irrigation Department's GR No. HEP
(118/99) HP dated, 22nd September 1999 and G.R. No. HEP (7/2002)HP, dt. 28th November,
2002
Signature of Promoter/Developer No.of corrections Signature of Inviter
37
By order and in the name of the Governor of Maharashtra,
Sd/-
(V.M. KulKarni)
Deputy Secretary to Government of Maharashtra.
Copy to:
The P.S. to Hon. Chief Minister, Maharashtra State, Mantralaya, Mumbai-400 032
The P.S. to Hon. Dy. Chief Minister, Maharashtra State, Mantralaya, Mumbai-400 032
The P.S. to Hon. All Ministers, Maharashtra State, Mantralaya, Mumbai-400 032
The P.S. to Hon. All State Ministers, Maharashtra State, Mantralaya, Mumbai-400 032
The Chief Secretary, Maharashtra State, Mantralaya, Mumbai-400 032
The Additional Chief Secretary (Finance), Finance Department, Mantralaya, Mumbai-400032.
The Additional Chief Secretary (Planning), Planning Department, Mantralaya, Mumbai-400 032.
The Principal Secretary (Energy and Environment), Industries, Energy & Labour Deptt.,
Mantralaya, Mumbai-32.
The Secretary (Industries), I.E.& L.Department, Mantralaya, Mumbai-400 032.
The Secretary (Legal Remembrancer), Law & Judiciary Department, Mantralaya, Mumbai-32.
The Secretary (Water Resources), Water Resources Department, Mantralaya, Mumbai-400 032.
The Secretary (CAD), Water Resources Department, Mantralaya, Mumbai-400 032.
All CE & Joint Secretaries, Water Resources Department, Mantralaya, Mumbai-400 032
The Chairman, Maharashtra Electricity Regulatory Commission, Mumbai (By letter)
The Managing Director, MSEB Holding Company Ltd. , Prakashghad, Mumbai-400 051.
The Managing Director, Maharashtra State Transmission Company Ltd. , Prakashghad, Mumbai-400 051.
The Managing Director, Maharashtra State Electricity Distribution Company Ltd. ,
Prakashghad, Mumbai-400 051.
The Managing Director, Maharashtra State Power Generation Company Ltd. ,
Prakashghad, Mumbai-400 051.
Executive Directors and Chief Engineers of all Irrigation Development Corporations
Chief Engineer (Electrical), Hydro Projects, Mumbai-400 023
All Regional Chief Engineers of Water Resources Department.
Directorate General of Information & Public Relations, Maharashtra State, Mantralaya,
Mumbai (2 copies)
Director, Maharashtra Energy Development Agency (MEDA), MHADA Commercial
Complex, 2nd floor, Opp. Tridal Nagar, Yerwada, Pune-411 006
All Superintending Engineers and Executive Engineers in Water Resources Department,
HP Desk (for collection)
Signature of Promoter/Developer No.of corrections Signature of Inviter
38
Modification in clause No. A-15 Sale of Power Of Hydel
Policy dated 15.09.2005, regarding Development of
Small Hydro Projects through private sector
participation.
Government of Maharashtra
Water Resources Department
Government Resolution No. HEP-1209/(143/2009)/HP.
Mantralaya, Mumbai-400032.
Dated: 31/10/2009.
Read : 1) G. R. No. PVT-1204/(160/2004) /HP, dated 15th
September 2005.
2) G. R. No. PVT-1207/(406/2007) /HP, dated 22nd
December 2008.
Preamble:
There is a deepening crisis of power shortage in Maharashtra State. In view of this
following provision “Maharashtra Electricity Distribution Company shall have first right of
refusal” was included in clause No.A-15 “Sale of Power” of Government Resolution dated
15.09.2005 regarding hydel policy for development of small hydro projects through private sector
participation.
The clause “Sale of Power” is further reproduced by MERC in order dated 9th
November
2005 for fixation of tariff for Small Hydro Projects as clause No. 3.58.
In light of the provisions of Electricity Act, 2003, an entrepreneur had filed a petition under
Case No. 85 of 2006 requesting MERC to review the provision of “Maharashtra Electricity
Distribution Company shall have first right of refusal” appearing in the clause No. 3.58 of
MERC’s order dated 9th
November 2005.
Accordingly MERC vide order dated 7th
November 2007 has considered the petitioner’s
request and deleted the provision of “Maharashtra Electricity Distribution company shall have first
right of refusal” from their order dated 9th
November 2005.
In light of these development, clause No.A-15 “Sale of Power” of Hydel Policy dated 15th
September, 2005 was modified, vide G.R.No. PVT-1207/(406/2007)/HP, dated 22nd
December
2008. In view of this modified clause, it is mandatory that fifty percent (50%) of the generated
electricity shall be sold to Maharashtra State Electricity Distribution Company Ltd. (MSEDCL)
and remaining fifty percent (50%) of the generated electricity shall be sold in Maharashtra to any
consumer or distribution Licensee.
Signature of Promoter/Developer No.of corrections Signature of Inviter
39
However, Industry, Energy & Labour Department vide GR No. +{ÉÉ>ð-2009/
|É.Gò.1528/=VÉÉÇ-, ÊnùxÉÉÆEò 03 +ÉìMɺ]õ 2009 has permitted 100% generated electricity from Small
Hydro Projects (upto 25 MW) to be sold in Maharashtra to any consumer or distribution Licensee.
In view of these developments, further modifications to clause No.A-15 “Sale of Power”
of G.R. dated 22.12.2008 are necessary.
RESOLUTION :
Clause No. A-15 “Sale of Power” of Government Resolution, Water Resources
Department dated 22.12.2008 shall be read as under :
A-15 “ SALE OF POWER ”
“ Considering the present acute power shortage situation in Maharashtra, it is necessary
in larger public interest that, the power generated from Hydro projects (upto 25 MW Capacity)
shall be consumed in Maharashtra. Therefore exercising the powers as per provisions of
section 108 of Electricity Act, 2003, it is mandatory that, hundred percent (100%) of generated
electricity shall be sold in Maharashtra to any consumer or distribution Licensee.”
The modified clause is applicable from the date of issue of this Government Resolution.
The Government Resolution is available on the website www.Maharashtra.gov.in of
Government of Maharashtra and its computer code no. is 20091031183927001.
By order and in the name of the Governor of Maharashtra.
sd/-
(S.R.Bavaskar)
Under Secretary
to Govt. of Maharashtra
Copy to :
The P.S. to Hon.Chief Minister, Maharashtra State, Mantralaya, Mumbai - 400032
The P.S. to Hon.Deputy Chief Minister, Maharashtra State, Mantralaya, Mumbai - 400032
The P.S. to Hon.All Minister, Maharashtra State, Mantralaya, Mumbai - 400032
The P.S. to Hon.All State Minister, Maharashtra State, Mantralaya, Mumbai - 400032
The Chief Secretary, Maharashtra State, Mantralaya, Mumbai - 400032
The Additional Chief Secretary (Finance) Finance Department, Mantralaya, Mumbai – 400032
Signature of Promoter/Developer No.of corrections Signature of Inviter
40
SECTION – IV
SHAHANOOR CANAL DROP HYDRO ELECTRIC PROJECT
(0.350 MW)
A) Salient Features of Shahanoor Canal Drop HEP ( 0.350MW)
B) Brief Description & Present Status of Shahanoor Canal Drop HEP
( 0.350MW)
C) APPENDICES
Appendix - I ) Area capacity table
Appendix - II ) Monsoon Rainfall
Appendix – III ) 75 % Dependable yield Working Table
Signature of Promoter/Developer No.of corrections Signature of Inviter
41
SECTION IV
(A) SALIENT FEATURES OF SHAHANOOR CANAL DROP
HYDRO ELECTRIC PROJECT
1) Location of dam
i) Name of project : Shahanoor Canal Drop Hydro Electric
Project
ii) State : Maharashtra
iii) District : Amravati
iv) Taluka : Achalpur
v) Location of site : -
vi) Topo sheet No. : 55 G/3 and 55G/7
vii) Latitude : 21 0 15 ’ 21”
viii) Longitude : 77 0 19 ’ 30”
2) River basin :
i) Name of River : Shahanoor River
ii) Sub basin : Purna
iii) Basin : Tapi
3) Catchment
i) Catchment area : 139.187 Sq. Km.
ii) Intercepted Catchment : -
a) Net catchment area : 139.187 Sq. Km.
b) Classification : Good
4) Rainfall :
i) Average annual rainfall : 781.81mm
ii) Average Monsoon Rainfall : -
iii) 50 % dependable monsoon rainfall : 1350.51mm
iv) 75 % dependable monsoon rainfall : 1066.92mm
Signature of Promoter/Developer No.of corrections Signature of Inviter
42
5) Yield : -
i) 50 % dependable Yield : 103.239 Mm3
ii) 75 % dependable Yield : 62.067 Mm3
iii) Total yield at site : 62.067 Mm3
iv) U/S Reservation : -
v) Net annual utilization : 62.067 Mm3
vi) Saleable energy : 0.98937 Mus
6) Storage Losses : 2.490 Mm3
7) Storage capacity :
i) Dead storage : 2.00Mm3
ii) Live storage : 45.85 Mm3
iii) Gross storage up to F.R.L. : 47.853 Mm3
8) Controlling Levels
i) River bed level : 396.650 m.
ii) M.D.D.L. for irrigation : 415.70 m.
iii) Outlet sill level : 413.66 m.
iv) F.R.L. : 449.50 m.
v) M.W.L. : 450.00 m.
vi) T.B.L. : 452.50m
vii) CBL at start of canal : 412.343m
viii) Penstock level (Center line) : 408.536m
9) Details of Dam :
i) Type of Dam : Rolled filled earth dam
ii) Top width of dam : 6.50m
iii) Maximum height : 56.45m
iv) Length of Dam : 795m (main dam)
(Including spillway) : 702m (Saddle dam)
10) Irrigation cum power outlet :
i) Location : Ch. 145m to 155m
ii) Design discharge for Penstock : 4.0618m3/sec
iii) Peak discharge for power generation : 4.0618m3/sec
iv) Average head : 10.771m
v) Penstock Diameter : 1.65m
vi) Length of penstock : 14.70m
Signature of Promoter/Developer No.of corrections Signature of Inviter
43
B) BRIEF DESCRIPTION & PRESENT STATUS OF SHAHANOOR
CANAL DROP HYDRO ELECTRIC PROJECT
1.0 Project Description:
1.1 Shahanoor Hydro Electric Project is constructed on Shahnoor irrigation dam as
damfoot at shahnoor river. The Shahnoor river is a tributary of the Purna river in the Tapi
basin. The irrigation project is located upstream side of village Wagdoh , Tal. Achalpur in
Amravati dist. The project is at a distance near about 89Km from Amravati District. The
Amravati - Partwada is state highway 55Km & further 25 Km Partwada – Pandhari is
district road. Pandhari to Shahnoor Dam site ( near village Wagdoh ) the distance is 9Kms
& is connected by village road. The power generation of 750KW is started from
11.02.2004 the present power generation of 350KW is proposed at Shahnoor canal drop at
RD 920m of main canal.
1.2 Present proposal:
Main canal runs through a length of 1.22Km & by bifurcates at 8.22Km in left &
right branches to irrigate the command area of 5811Ha. On both side. On main canal there
is a drop of 10.785M at RD 920m. to 120m. To utilize this drop for power generation mini
hydel scheme was proposed at the foot of the drop . The present proposal is for Hydro
Electric generation on canal drop of 10.771m.
The scheme is proposed for construction of following components power
generation.
i) Cross regulator
ii) Gated structure
iii) Diversion channel
iv) Main penstock
v) Power House & switchyard
vi) Tail race channel
The GOMWRD has assessed this potential as 0.350MW. The Promoter/ Developer
is free to Design the installed capacity. However it is obligatory on Promoter/ Developer to
utilize the optimum available Hydro potential.
Signature of Promoter/Developer No.of corrections Signature of Inviter
44
2.0 PRESENT STATUS OF THE SHAHANOOR CANAL DROP HYDRO
ELECTRIC PROJECT
2.1 Approach to site:
Shahanoor Canal Drop Hydro Electric Project is proposed on main canal at
RD 920 m. The Shahanoor Canal Drop located near Wagdoh village , Tal. Achalpur in
Amravati Dist. The project is at a distance near about 89Km from Amravati District. The
Amravati - Partwada is state highway 55Km & further 25 Km Partwada – Pandhari is
district road. Pandhari to Shahnoor Dam site ( near village Wagdoh ) the distance is 9Kms
& is connected by tar road.
The nearest railway station is Sindhi Buzurk about 6Kms. Away from Wagdoh ,
Sindhi Buzurk is a narrow gauge railway station & there are no facilities for handling &
storing the goods.
Achalpur railway station is a terminus for narrow gauge line. Handling & storage
facilities of goods are available here. Dam site is 30Km. away from achhalpur railway
station .
2.2 Construction power:
The construction power supply required during erection stage shall be arranged by the
promoter / Developer at their own cost.
2.3 Other facilities:
All other facilities such as drinking water, office shed, Stores etc. shall be arranged by
Promoter / Developer at their own cost.
2.4 Present status of Work:
The Shahanoor Canal Drop Hydro Electric Project comprises of earthen Dam of 795m long
& 56.45m height. The gross capacity of dam at FRL is 47.853mm3. An ogee type gated
west weir with 4 radial gates of size 12m X 8m is provided on left flank saddle, the length
of which is 702m are provided. The dam & canal is completed in year 1989.
.
3.0 Power outlet and power planning:-
A single penstock of Diameter 1.65m with thickness of 8mm is proposed to be laid
through the cistern structure & leading to power house for power generation based on
irrigation releases . The water released after generation will be diverted for irrigation
through tail race canal.
The power house with installed capacity 1 X 350 KW & power generated will be evacuated
at 11Kv by constructing outdoor switchyard of 11Kv near to power house.
Signature of Promoter/Developer No.of corrections Signature of Inviter
45
4.0 Hydrology and water planning:
4.1 As per Executive Engineer Amravati Irrigation Division, Amravati of GOMWRD
study the 75% dependable yield at Shahnoor dam is 62.067Mm3. The more data can be
obtained from office of The Executive Engineer, Irrigation & Hydro Electric Project
Investigation Division, Nagpur. However Promoter/Developer shall obtain Hydrological
data from their own sources.
4.2 Power generation:-
The releases of water in the canal shall be strictly as per irrigation /domestic/ industrial
water demands. The power generation will have to be synchronized with these releases. To
cope up with variation in irrigation requirements GOMWRD has proposed one unit of 350
KW. The installed capacity is indicative only and GOMWRD doesn’t take any
responsibility in this respect.
GOMWRD reserves right to decide the release schedule and modify it from time to time
depending on yield available in dam and irrigation / domestic / industrial water
requirements.
4.3 The water releases as per irrigation / domestic/industrial requirements will be routed
through power out let to the possible extent. However in exceptional circumstances, if the
irrigation / domestic/industrial water demands is more than that of discharge capacity of
power outlet, the excess irrigation / domestic/industrial water requirements shall be
fulfilled by releasing additional water from other outlet / by passes.
5.0 CROSS REGULATOR, GATED STRUCTURE POWER HOUSE & ALLIED
WORKS:
5.1 CROSS REGUALATOR:
A cross regulator is proposed across main canal to direct the discharge to diversion canal
& to release only excess discharge than that is required for power generation through main
canal & whole discharge in the event of closer of generating plant.
5.2 GATED STRUCTURE:
Gated structure at the off take of penstock is proposed to regulate the discharge in penstock
& to cutoff the discharge in penstock in the event of closer of generating plant ie. for
repairs & maintenance or any other reasons.
Signature of Promoter/Developer No.of corrections Signature of Inviter
46
5.3 PENSTOCK:
A single penstock of Diameter 1.65m with thickness of 8mm is proposed to be laid
through the cistern structure & leading to power house for power generation based on
irrigation releases . The design discharge for penstock is 4.0618m3/sec .
5.4 POWER HOUSE & SWITCHYARD:-
The promoter/developer shall access the location of the power house and shall submit the
detailed proposal for the approval of GOMWRD.
The space available/land acquired by GOMWRD for construction of power house
switchyard etc. is indicated in the drawing attached as Annexure. This space will be handed
over to promoter/developer. If any additional space is required by promoter/developer, he
will have to arrange for it himself. Switchyard of suitable size shall be planed near to the
power house building.
5.5 DRAFT TUBE GATE STRUCTURE:-
The draft tube gate structure shall be provided immediately downstream of the power house
to accommodate. D.T. gates and hoisting arrangement. The D.T. gate structure shall be
R.C.C. structure constructed by promoter/developer. A deck slab shall be provided at
suitable level for repairs and maintenance of gate. The suitable access to the deck slab be
provided.
5.6 TAIL RACE CHANNEL:-
Trapezoidal C.C. lined tail race canal of suitable capacity and length shall be provided by
promoter/developer to let out water after power generation in to the irrigation canal for
further downstream use. The bed shall be of the concrete of suitable grade. Arrangement of
anchorage and for drainage to minimize uplift pressure shall be made.
Prepared by –
Sd/-
A.P.Lakhani
Sect. Engr.
Sd/-
Sub divisional officer
Irrigation & Hydro Electric
Project Investigation Sub-
Dn. No 1, Amravati
Executive Engineer
Irrigation & Hydro Electric Project
Investigation Dn.
Nagpur
Signature of Promoter/Developer No.of corrections Signature of Inviter
47
6.0 INTERCONNECTION WITH GRID:-
The nearest 11 kV substation at Shahnoor HEP which is approximately 1 Km. away from
proposed Hydro Electric Project may be used for interconnection with grid.
Technical standards relating to connectivity with the grid referred to in clause (b) of
section 73 provisions in section 10 and other applicable provisions of EA 2003 shall
followed by the promoter/developers.
Grid interfacing & evacuation arrangement shall be as per dispensation emerging from the
tariff and procurement process determination exercise initiated by MERC.
7.0 SCOPE OF WORK :-
The promoter/developer shall inspect the project site and shall get them- selves satisfied
with all the details of the project site including its area, demarcation, location, access and
geological conditions. The promoter/developer shall be responsible for execution stipulated
in price Bid document No CE(E)/HP/SHP/CPP/IPP/68A. The work covered under the
scope of work shall comprise of but not limited to following works.
7.1 CIVIL ENGINEERING WORKS:
i) Individual Penstock upto power house including concrete encasing etc.
ii) Construction of power house.
iv) Construction of tail race channel.
v) Civil works for switchyard including fencing.
vi) Draft Tube gate, embedments, concreting and D.T. gate hoisting arrangement.
7.2 ELECTRICAL AND MECHANICAL ENGINEERING WORKS:
i) Turbine – Generator plant with Turbine – Generator auxiliaries including main inlet
Valve, control & protection system, excitation system etc.
ii) Power transformer.
iii) Switchyard equipments.
iv) Unit Auxiliary transformer
v) Station Auxiliaries including A. C. Distribution, D. C. D. B., Battery
. charger & Batteries, XLPE cables, Control & L.T. power cables
vi) Inter connection with grid, evacuation arrangements etc.
vii) EOT crane
viii) D. G. Set.
ix) Earthmat, Illumination, Fire fighting equipments.
x) Communication, Air conditioning plant, work shop equipment etc.
Given above details of works are indicative only. The Promoter /Developer
shall have to complete the project with successful commissioning of Generating Plant with
all respect as per Hydro Policy declared vide Government of Maharashtra, Water
Resources Department G. R. No. PVT – 1204/ (160/2004)/HP, dated 15/09/05 and GR.
No. HEP-1209/(143/2009)/HP, Dtd. 31.10.2009.
Signature of Promoter/Developer No.of corrections Signature of Inviter
48
NOTE:
Promoter/Developer shall be deemed to be fully acquainted of all local conditions at
various level availability of labor, electricity, water, present status of works i.e. Dam,
Intake structure, Penstock etc. communication & space available at site and factors which
may have any effect on the execution of the works covered under these documents and
specifications.
7.3 Promoter through its consultant shall validate the hydrological data made available
by the GOMWRD in PQ document / Price bid or in any other GOMWRD document and
draw his own inferences only after such validation. Promoter shall estimate Installed
capacity / annual generation only by using such validated data. GOMWRD shall not
take responsibility regarding correctness of data and its consequential losses if any.
Promoter shall indicate estimated installed capacity along with P.Q. proposal.
Signature of Promoter/Developer No.of corrections Signature of Inviter
49
APPENDIX – I
SHAHANOOR CANAL DROP HYDRO ELECTRIC PROJECT Tq.Achalpur Dist.: Amravati
AREA CAPACITY TABLE SHANANOOR SITE
Sr.No. R.L.in Meter Height of
strip in M
Area in Mm2 Area
Capacity H/3
Strip
Capacity H/3
Cumulative
Capacity
Remarks
1 2 3 4 5 6 7 8 1. 395.90 0.00
2. 396.00 0.10 0.00360 0.018973 0.000097 0.000097
3. 398.00 2.00 0.001164 0.034117 0.001447 0.001544
4. 400.00 2.00 0.024360 0.156077 0.020566 0.022110
5. 402.00 2.00 0.046920 0.216610 0.070059 0.092169
6. 404.00 2.00 0.067160 0.59152 0.113477 0.205646
7. 406.00 2.00 0.107880 0.328451 0.173439 0.379085
8. 408.00 2.00 0.141000 0.375500 0.248142 0.627227
9. 410.00 2.00 0.182240 0.426896 0.322359 0.94586
10. 412.00 2.00 0.2438000 0.403761 0.424550 1.374136
11. 414.00 2.00 0.318020 0.564730 0.561042 1.935178
12. 415.70 1.70 0.365479 0.604569 0.591290 2.516468
13. 416.00 0.30 0.373360 0.611031 0.110824 2.627292
14. 413.00 2.00 0.448800 0.669925 0.821003 3.448295
15. 420.00 2.00 0.495800 0.7044130 0.944210 4.392506
16. 422.00 2.00 0.574960 0.758261 1.069783 5.462289
17. 424.00 2.00 0.641160 0.880725 1.345085 8.022892
18. 428.00 2.00 0.794572 0.891387 1.498091 9.520985
19. 430.00 2.00 0.975560 0.987704 1.767039 11.288022
20. 432.00 2.00 1.020754 1.044391 2.065242 13.353264
21. 434.00 2.00 1.291200 1.136310 2.379137 15.732401
22. 436.00 2.00 1.395200 1.181186 2.685729 18.418130
Signature of Promoter/Developer No.of corrections Signature of Inviter
50
23. 438.00 2.00 1.602032 1.265714 2.9944851 21.412981
24. 440.00 2.00 1.818524 1.348156 3.477291 24.830272
25. 442.00 2.00 2.184800 1.481486 4.0066399 28.836671
26. 444.00 2.00 2.3676000 1.538701 4.5611309 33.397980
27. 446.00 2.00 2.5568840 1.599112 4.9232277 38.321207
28. 447.00
448.00
1.10
0.400
2.65576
2.73900
1.629620
1.654660
2.806700
5.293707
41.187910
43.614914
29. 449.00
449.400
449.500
449.900
0.900
0.400
--
0.500
2.854140
2.90137
2.913286
2.96085
1.689420
1.70334
--
1.7274
2.795819
1.51063
--
1.46556
46.410733
47.56179
47.852512
49.02735
FRL 449.500m.
FRL+1/2 m =
449.00m
30. 450.00
450.100
450.500
0.100
0.100
0.400
2.972800
1.867688
3.012400
1.724181
1.693425
1.735626
0.286655
0.290076
1.175998
49.324002
49.614078
50.789975
MWL = 450.500
31. 452.00
452.500
1.500
0.500
3.131200
3.213770
1.70520
1.792699
5.813239
1.354348
55.427317
56.781657
TBL = 452.500 m
32. 454.00 2.00 3.461480 1.860505 6.589921 62.017236
33. 457.00 2.00 3.849400 1.961989 7.307447 69.324685
34. 458.00 2.00 4.120880 2.029995 7.963739 77.324685
35. 450.00 2.00 4.289200 2.071038 8.409518 85.702942
36. 462.00 2.00 4.618800 2.149339 8.905966 94.608908
Prepared by –
S/D S/D
(A.P.Lakhani) Sub Divisional Engineer
Sect Engr. Hydro Electric Sub Dn. No.7
Amravati.
Signature of Promoter/Developer No.of corrections Signature of Inviter
52
APPENDIX – II
SHAHANOOR RIVER PROJECT TALUKA : ACHALPUR DIST : AMRAVATI
STATEMENT SHOWING THE MONSOON RAINFALL IN
CHRONOLOGICAL FOR ANJANGAON CHIKALDARA AND
BELKUND RAINGUAGE STATIONS
1) Area influenced by Anjangaon raingauge station A1 = 6.89 Sq.Miles
2) Area influenced by Chikhaldara raingauge station A2 = 29.00 Sq.Miles
3) Area influenced by Belkund raingauge station A3 = 17.85 Sq.Miles
Total = 53.74 Sq.Miles --------------------------------------------
Sr.
No.
Year Anjangaon Stn. Chikhaldara Stn. Belkund Stn. Total Col.
4+6+8
Weighted
rainfall
inches
Total C.A.
53.74
C.A.-6.89 Sq.Miles C.A.- 29.00 Sq.Miles C.A.- 17.85 Sq.Miles
Rainfall
(R1) inches
A1 R1
Sq.Miles inches
Rainfall
(R1) inches
A2 R2
Sq.Miles inches
Rainfall
(R1) inches
A3 R3
Sq.Miles inches
1 2 3 4 5 6 7 8 9 10
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
1945
1946
1947
1948
1949
1950
1951
1952
1953
1954
1955
1956
1957
1958
1959
1960
1961
1962
1963
1964
1965
1966
1967
1968
1969
1970
1971
1972
1973
1974
31.01
25.82
26.37
27.25
45.33
18.11
34.90
15.84
21.77
33.95
34.73
37.74
25.78
17.94
36.79
21.53
45.92
24.41
18.23
34.26
20.35
19.36
25.95
19.64
20.86
35.55
18.57
37.93
24.36
24.52
213.659
177.899
181.689
187.752
312.324
124.778
240.461
109.137
149.995
233.915
239.289
260.028
177.624
123.606
253.483
148.340
316.802
168.185
125.605
236.051
140.211
133.390
178.795
135.315
143.347
244.939
127.947
261.337
171.285
168.943
63.56
73.54
47.50
83.70
72.32
47.00
56.44
38.40
38.35
84.65
74.40
70.12
55.32
69.88
90.21
52.04
98.54
74.52
69.29
87.40
51.13
41.59
49.52
34.88
53.94
81.09
45.28
56.52
76.78
48.36
1843.240
2132.660
1377.500
2427.300
2097.280
1363.000
1636.760
1113.600
1112.150
2454.850
2157.600
2033.480
1604.280
2025.07
2616.090
1509.160
2857.660
2161.080
2009.410
2534.600
1482.770
1206.110
1436.080
1011.520
1564.260
2351.610
1313.120
1639.080
2226.620
1402.440
49.94
63.78
27.66
77.87
62.09
26.97
40.06
16.42
14.97
65.32
64.97
57.73
43.10
46.10
92.97
37.12
57.04
21.61
57.88
83.00
32.70
19.47
30.46
10.16
36.59
74.25
24.58
40.17
68.27
28.86
891.25
1138.47
493.730
1389.979
1108.306
481.410
715.070
293.10
267.21
1165.96
1159.71
1030.48
769.36
822.89
1659.51
662.59
1018.16
385.74
1033.16
1481.550
583.70
347.540
543.71
181.36
653.15
1325.36
438.75
717.03
1218.620
515.150
2948.149
3449.029
2050.919
4005.031
3517.910
1969.188
2592.291
1515.837
1529.355
3854.725
3556.599
3323.988
2551.264
2971.566
4529.083
2320.09
4202.622
2715.006
3168.175
4252.211
2206.681
1687.040
2158.585
1328.195
2359.737
3921.909
1879.817
2617.447
3616.525
208.533
54.86
64.18
38.20
74.53
65.46
36.64
48.24
28.21
28.46
71.73
66.18
61.85
47.47
55.30
84.28
43.17
78.20
50.52
58.95
79.13
41.06
31.39
40.17
24.72
43.91
72.93
34.98
43.71
67.30
38.82
Signature of Promoter/Developer No.of corrections Signature of Inviter
53
Sr.
No.
Year Anjangaon Stn. Chikhaldara Stn. Belkund Stn. Total Col.
4+6+8
Weighted
rainfall
inches
Total C.A.
53.74
C.A.-6.89 Sq.Miles C.A.- 29.00 Sq.Miles C.A.- 17.85 Sq.Miles
Rainfall
(R1) inches
A1 R1
Sq.Miles
inches
Rainfall
(R1) inches
A2 R2
Sq.Miles
inches
Rainfall
(R1)
inches
A3 R3
Sq.Miles
inches
1 2 3 4 5 6 7 8 9 10
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
1975
1976
1977
1978
1979
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
30.51
26.06
33.98
34.80
76.65
42.68
37.68
--
--
--
13.16
13.78
13.66
22.98
15.57
26.76
12.30
42.38
53.90
62.65
48.46
22.45
21.96
35.53
33.62
15.27
18.89
14.09
210.21
179.55
234.12
239.77
528.11
294.06
259.61
---
---
---
90.67
94.94
94.11
158.33
107.27
184.37
84.74
291.99
371.37
431.65
333.88
154.68
151.30
244.80
231.64
105.210
130.15
97.080
59.32
53.40
84.55
61.20
64.48
50.46
63.46
42.95
65.53
67.75
45.05
69.10
34.44
76.79
45.96
47.35
46.66
49.61
70.22
78.63
43.26
67.34
60.59
69.95
74.33
36.88
49.25
52.67
1720.280
1548.600
2451.950
1774.800
1869.920
1463.340
1840.340
1245.550
1900.370
1964.750
1306.450
2003.900
998.760
2226.910
1332.840
1373.150
1353.140
1438.690
2036.380
2280.270
1254.540
1952.860
1757.110
2028.550
2155.570
1069.520
1428.250
1527.430
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
--
1930.49
1728.15
2686.07
2014.57
2398.03
1757.40
2099.95
1245.55
1900.37
1964.75
1397.12
2098.84
1092.87
2385.24
1440.11
1557.52
1437.88
1730.68
2407.75
2711.92
1588.42
2107.54
1908.41
2273.35
2387.21
1174.73
1558.40
1624.51
53.78
48.15
74.84
56.13
66.81
48.96
58.51
42.95
65.53
67.75
38.92
58.47
30.45
66.45
40.12
43.39
40.06
48.22
67.08
75.56
44.25
58.72
53.17
63.34
66.51
32.73
43.42
45.26
Prepared by – S/D S./D.
(A.P.Lakhani) Sub Divisional Engineer
Sect Engr. Hydro Electric Sub Dn. No.7 Amaravati
Signature of Promoter/Developer No.of corrections Signature of Inviter
54
APPENDIX – III Mansoon Yield - 59.111188 Mm3
P.M. 5% Yield - 2.95559 Mm3
Total Yield - 62.0675. Mm3
SHAHANUR HYDRO ELECTRIC PROJECT
TALUKA : ACHALPUR DIST : AMRAVATI
Working Table For Reservoir Operation
75% DEPENDABLE WORKING TABLE (REVISED)
M.D.D.L. = 415.700 M
M.D.D.L. Capacity = 2.520 Mm3
M.D.D.L. Area = 0.365 Mm2
F.R.L. = 449.500 M
F.R.L. Capacity = 47.853 Mm3
F.R.L. Area = 2.913Mm2
Sr.
No.
Days Month Operating Condition of
Reservoir
Mansoon
Flow Mm3
Post
mansoon
flow in
Mm3
Total in
Flow
Mm3
Total
Content
Mm3
Crop water
requirement
Evaporation Drinking
water
supply
Mm3
Total with
drawl
Mm3
Water
R.L.
Area
Mm2
Capacity
Mm2
For 1000
Ha. In
Mm3
For 5811
Ha. In
Mm3
Depth
M.
Qty
Mm3
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
2 24 July 415.700 0.365 2.516 28.00 0.00 16.351 19.067 0.03750 0.22 0.170 0.062 1.037 1.317
3 24 August 435.513 1.370 17.750 33.00 0.00 19.507 37.257 0.27994 1.63 0.130 0.178 1.037 2.842
4 24 September 444.421 2.407 54.414 26.00 0.00 15.369 49.784 0.60005 3.49 0.120 0.289 1.037 4.813
5 24 October 448.485 2.794 44.970 7.00 0.00 4.138 49.108 1.67694 9.74 0.130 0.363 1.037 11.145
6 24 November 445.857 2.543 37.963 0.00 60.00 1.773 39.736 0.79829 4.64 0.100 0.254 1.037 5.931
7 24 December 444.169 2.384 33.805 0.00 30.00 0.887 34.692 1.38093 8.02 0.080 0.019 1.037 9.081
8 24 January 440.408 1.895 25.611 0.00 10.00 0.296 25.906 1.24431 7.23 0.080 0.152 1.037 8.420
9 24 February 435.322 1.360 17.487 0.00 0.00 0.000 17.487 0.36566 2.12 0.130 0.177 1.037 3.339
10 24 March 432.696 1.161 14.148 0.00 0.00 0.000 14.148 0.00000 0.00 0.230 0.267 1.037 1.304
11 24 April 431.519 1.063 12.843 0.00 0.00 0.000 12.843 0.50897 2.96 0.270 0.287 1.037 4.282
12 24 May 426.713 0.738 8.561 0.00 0.00 0.000 8.561 0.41120 2.39 0.390 0.288 1.037 3.715
13 24 June 420.895 0.531 4.846 6.00 0.00 3.547 8.393 0.80498 4.68 0.290 0.154 1.037 5.869
Total 100% 62.067 47.12 2.490 12.450 62.060
Gross Utilision
Irrigation - 47.12 Mm3
Water supply - 12.45 Mm3
Evaporation Losses - 2.490 Mm3
Total - 62.060 Mm3
Cont…1 of 2
Signature of Promoter/Developer No.of corrections Signature of Inviter
55
Cont…2 of 2
Closing condition of reservior Spilover
Mm3
Irrigation
Demand in
Mm3
Irrigation Demand converts
in to contionus discharge in
Mm3/ sec.
Col.21 x 106
Days x Hour’s x 60 x 60
Head
in m.
Q.T. Q.H.T. Power
generation
K.W. = 8
Q.H.
Energy
generatio
n
K.W.x 24
days / 106
Remarks
Capacity
Mm3
Area
Mm3
Water
RL
17 18 19 20 21 22 23 24 25 26 27 28
17.750 1.370 435.513 -- 0.220 0.1060 10.771 2.544 27.4014 9.1330 0.005260 Neglected due to low generation
37.414 2.407 444.421 -- 1.630 0.7860 10.771 18.864 203.1841 67.7280 0.039010 Neglected due to low generation
44.970 2.796 448.485 -- 3.490 1.6830 10.771 40.392 435.0622 145.0200 0.083530 Installed capacity 350 K.W.
37.963 2.543 445.857 -- 9.740 4.6971 / 4.0618 10.771 112.7304 /
97.4832
1214.2191 /
1049.9915
404.7390/
350.0000 0.233120 Installed capacity 350 K.W.
33.805 2.384 444.169 -- 4.640 2.2376 10.771 53.7024 678.4285 192.8090 0.111050 Installed capacity 350 K.W.
25.611 1.895 440.408 -- 8.020 3.8676 10.771 92.8224 999.7900 333.2630 0.191950 Installed capacity 350 K.W.
17.487 1.360 435.322 -- 7.230 3.4866 10.771 83.6784 901.3000 300.4330 0.173040 Installed capacity 350 K.W.
14.148 1.161 432.696 -- 2.120 1.0223 10.771 24.5352 264.2686 88.0890 0.050730 Installed capacity 350 K.W.
12.843 1.063 431.519 -- 0.000 0.0000 10.771 0.000 0.0000 0.0000 0.000000
8.561 0.738 426.713 -- 2.960 1.4274 10.771 34.2576 368.9886 122.9960 0.070840 Installed capacity 350 K.W.
4.846 0.531 420.895 -- 2.390 1.1525 10.771 27.660 297.9258 99.3080 0.057200 Installed capacity 350 K.W.
2.524 0.366 415.712 -- 4.680 2.2569 10.771 54.1656 583.4176 194.4720 0.112010 Installed capacity 350 K.W.
Total 508.6968 5479.1728 1.05195
Mus
QHT 5479.1728 Deduct 0.5 % Auxilary consumption 0.00525 Mus
QT 508.6968 Saleable Energy 1.0467 Mus
= 10.77
Prepared by – S/D S/D
(A.P.Lakhani) Sub Divisional Engineer S/D
Sect Engr. Hydro Electric Sub Dn. No.7 Exucutive Engineer
Amravati. Irrigation Project Investigation Dn
Amravati.
Signature of Promoter/Developer No.of corrections Signature of Inviter
56
SECTION - V
DRAWINGS (SHAHANOOR CANAL DROP) HEP)
1) Drawing No. I - Index Map
2) Drawing No. II - Typical cross section of Dam
At R D 2120 M
3) Drawing No. III - Layout plan of Diversion Canal
Penstock, powerhouse, & TRC
4) Drawing No. IV - Area capacity curve
5) Drawing No. V - Layout of Powerhouse.