geotechnical investigation report for proposed

34
GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED RECONSTRUCTION OF THE DFO-SLCC STORAGE BUILDING NIPIGON, ONTARIO MARCH 24 TH , 2017 TS-NO-027467 PREPARED FOR: DEPARTMENT OF FISHERIES AND OCEANS CANADA SEA LAMPREY CONTROL CENTRE (DFO-SLCC) 1219 QUEEN STREET EAST SAULT STE. MARIE, ONTARIO P6A 2E5 CANADA 3 Copies Department of Fisheries and Oceans 1 Copy DST Consulting Engineers Inc., Thunder Bay, ON DST CONSULTING ENGINEERS INC.

Upload: others

Post on 25-Apr-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED RECONSTRUCTION

OF THE DFO-SLCC STORAGE BUILDING NIPIGON, ONTARIO

MARCH 24TH, 2017 TS-NO-027467

PREPARED FOR: DEPARTMENT OF FISHERIES AND OCEANS CANADA

SEA LAMPREY CONTROL CENTRE (DFO-SLCC) 1219 QUEEN STREET EAST

SAULT STE. MARIE, ONTARIO P6A 2E5 CANADA

3 Copies – Department of Fisheries and Oceans 1 Copy – DST Consulting Engineers Inc., Thunder Bay, ON

DST CONSULTING ENGINEERS INC.

Page 2: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 i

DST CONSULTING ENGINEERS INC.

Table of Contents

1 INTRODUCTION ................................................................................................................ 1

2 PROJECT DESCRIPTION .................................................................................................. 1

3 FIELD INVESTIGATION AND LABORATORY TESTING ................................................... 2

4 GEOTECHNICAL INVESTIGATION ................................................................................... 5

4.1 Methodology ................................................................................................................ 5

4.2 Laboratory Testing ....................................................................................................... 5

5 GEOTECHNICAL DESCRIPTION OF SUBSURFACE CONDITIONS ................................ 6

5.1 Soil .............................................................................................................................. 6

5.2 Topsoil ......................................................................................................................... 6

5.3 Sand ............................................................................................................................ 6

5.4 Groundwater ................................................................................................................ 6

6 GEOTECHNICAL INVESTIGATION - DISCUSSION AND RECOMMENDATIONS ............ 7

6.1 Foundation ................................................................................................................... 7

6.2 Shallow Foundation ..................................................................................................... 7

6.3 Strip Footings ............................................................................................................... 8

6.4 Slab-On-Grade Construction ........................................................................................ 9

6.5 Backfill Material ............................................................................................................ 9

6.6 Frost Protection ..........................................................................................................10

6.6.1 Frost Penetration Depth .................................................................................... 10

6.6.2 Frost Protection for Foundation Footing ............................................................ 10

6.7 Excavation ..................................................................................................................11

6.8 Dewatering .................................................................................................................11

6.9 Site Preparation and Grading ......................................................................................11

6.10 Pipe Bedding, Backfill and Drainage Requirement ......................................................12

6.10.1 Pipe Installations .......................................................................................... 12

6.10.2 Pipe Bedding ............................................................................................... 13

6.10.3 Trench Backfill and Compaction Standard ................................................... 13

7 CONCRETE SLAB ASSESSMENT ....................................................................................14

8 REFERENCES ..................................................................................................................19

9 LIMITATIONS OF REPORT ...............................................................................................20

Page 3: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 ii

DST CONSULTING ENGINEERS INC.

List of Tables

Table 3-1 Test Pit UTM Coordinates ...................................................................................... 4

Table 5-1 Test Pit groundwater elevations ............................................................................. 6

Table 6-1 Soil Profile and Geotechnical Parameter Used for Foundation Analysis ................. 7

Table 6-2 Geotechnical Resistances and Reactions for Strip Footings ................................... 8

Table 7-1 Concrete Cylinder Laboratory Test Results .......................................................... 16

List of Figures

Figure 3-1: View of the Site facing southwest at Storage Building Site, Nipigon, ON ................... 2

Figure 3-2: View of Test Pit 1 at DFO-SLCC Storage Building Site, Nipigon, ON ........................ 3

Figure 3-3: View of Test Pit 2 at DFO-SLCC Storage Building Site, Nipigon, ON ........................ 3

Figure 3-4: View of Test Pit 3 at DFO-SLCC Storage Building Site, Nipigon, ON ........................ 4

Figure 7-1: Concrete drilling equipment .................................................................................... 15

Figure 7-2: Concrete core completed and slab bedding material samples................................. 15

Figure 7-3: Concrete patching of concrete floor......................................................................... 16

Figure 7-4: View of Concrete Cylinder C1 at DFO-SLCC Storage Building Site, Nipigon, ON ... 17

Figure 7-5: View of Concrete Cylinder C2 at DFO-SLCC Storage Building Site, Nipigon, ON ... 17

Figure 7-6: Concrete floor crack ................................................................................................ 18

Figure 7-7: Detail - Concrete floor crack .................................................................................... 18

Appendices

LIMITATIONS OF REPORT ...................................................................................................... ‘A’ DESCRIPTION OF THE TERMS .............................................................................................. ‘B’ DRAWINGS - PROJECT SITE PLAN AND TEST PIT LOCATION PLAN ............................... ‘C’ ENCLOSURES ........................................................................................................................ ‘D’

Page 4: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 1

DST CONSULTING ENGINEERS INC.

1 INTRODUCTION

DST Consulting Engineers Inc. (DST) has been retained by the Department of Fisheries and

Oceans Canada - Sea Lamprey Control Centre (DFO-SLCC) to conduct a geotechnical

investigation for the proposed reconstruction of the DFO-SLCC storage building in Nipigon,

Ontario (“Site”). The footprint of the existing building is approximately 45 m2 and will be replaced

with a steel storage structure of 81 m2. The Site location is shown on Drawing No. 1 in Appendix

C. This report presents the results of the geotechnical investigation carried out in general

accordance with DST proposal dated October 28th, 2016.

This report presents the factual results of the geotechnical investigation and provides

geotechnical recommendations for the design and construction of the proposed reconstruction of

the DFO-SLCC storage building.

2 PROJECT DESCRIPTION

DFO-SLCC is proposing to replace an existing storage building with a footprint of approximately

45 m2 with a steel storage structure of 81 m2 in Nipigon, ON (Latitude: 49°1'12.51" N, Longitude:

88°15'13.02" W). If possible, DFO-SLCC is looking to extend the existing concrete pad to

accommodate the larger footprint of a new building. The proposed site is within the property of

CN Rail near the Township of Nipigon, and DFO-SLCC received authorization from CN Rail to

conduct a geotechnical investigation at the site.

Page 5: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 2

DST CONSULTING ENGINEERS INC.

3 FIELD INVESTIGATION AND LABORATORY TESTING

Before carrying out the field investigation, DST marked out the test pit locations at the Site. Field

investigation was carried out on October 28th, 2016 utilizing a hydraulic excavator (Model: JD

200D LC). The field investigation was supervised on a full-time basis by DST personnel.

The field investigation consisted of three (3) test pits outside the perimeter of newly proposed

building footprint. The test pits were excavated to depths ranging from 1.1 to 3.0 m below existing

grade in the locations shown on Drawing No. 1 (Appendix C). Representative disturbed soil

samples were obtained from the excavator bucket at regular intervals. The photos of the Site and

test pits are illustrated in Figures 3-1 to 3-4. Photos were taken during the field investigation by

DST personnel.

Figure 3-1: View of the Site facing southwest at Storage Building Site, Nipigon, ON

Page 6: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 3

DST CONSULTING ENGINEERS INC.

Figure 3-2: View of Test Pit 1 at DFO-SLCC Storage Building Site, Nipigon, ON

Figure 3-3: View of Test Pit 2 at DFO-SLCC Storage Building Site, Nipigon, ON

Page 7: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 4

DST CONSULTING ENGINEERS INC.

Figure 3-4: View of Test Pit 3 at DFO-SLCC Storage Building Site, Nipigon, ON

DST recorded test pit locations in Universal Transverse Mercator (UTM) coordinates (NAD 1983)

using a handheld GPS receiver (Table 3-1). Test Pit logs can be found in Appendix D.

Table 3-1 Test Pit UTM Coordinates

Location Elevation, m Easting Northing

TP1 99.9 408340 5430458

TP2 100.0 408349 5430455

TP3 99.7 408353 5430446

The test pit ground surface elevations were surveyed by DST personnel, using a local benchmark

with an assumed elevation of 100.00 m. The benchmark was located at 2.4 m south-east from

the north-west corner of the building on the concrete floor of the building (Appendix C - Drawing

1).

Page 8: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 5

DST CONSULTING ENGINEERS INC.

4 GEOTECHNICAL INVESTIGATION

4.1 Methodology

Hand push cone penetration testing was conducted at Test Pit 3. This involved advancing a cone-

shaped probe into the soil and measuring the resistance to the cone penetration. Groundwater

conditions were observed and recorded during test pit excavations.

Soil samples were identified in the field, placed in labelled plastic bags and transported to DST’s

laboratory in Thunder Bay for further laboratory analysis.

4.2 Laboratory Testing

Soil samples returned to the laboratory were subject to visual examination and additional

classification by geotechnical engineer.

Selected soil samples were tested in the DST laboratory for natural moisture content and sieve

analyses. Laboratory results are presented on the Test Pit logs as well as on the grain size

distribution graph (Appendix D).

Page 9: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 6

DST CONSULTING ENGINEERS INC.

5 GEOTECHNICAL DESCRIPTION OF SUBSURFACE CONDITIONS

5.1 Soil

Details of the subsurface conditions are given in the Test Pit logs (Appendix D) and the sections

below.

5.2 Topsoil

A topsoil layer was encountered at the surface in Test Pit 1 and Test Pit 3 locations with a

thickness ranging between 200 and 300 mm.

5.3 Sand

A layer of brown to grey sand with some to trace of gravel and trace of silt was encountered in all

test pits within the limits of excavation, the thickness of this sand layer is unknown. The sand layer

contains fine to coarse grained well-graded sand.

The sand material has a loose to compact condition with hand-pushed cone penetration data

indicated as 1000 kPa. Sieve analysis tests were conducted on soil samples from Test Pit 1 and

Test Pit 3 (Enclosure 4, Appendix D). The moisture content tests carried out for this sand material

resulted in moisture contents ranging from 2% to 7%.

5.4 Groundwater

All three test pits remained dry on completion and there was no sign of seepage in any of these

test pits. It should be noted that groundwater levels may fluctuate seasonally and in response to

climatic conditions.

Table 5-1 Test Pit groundwater elevations

Test Pit Groundwater Depth (m) Groundwater Elev. (m)

Test Pit 1 Dry on completion Lower than 96.9

Test Pit 2 Dry on completion Lower than 98.9

Test Pit 3 Dry on completion Lower than 97.2

Page 10: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 7

DST CONSULTING ENGINEERS INC.

6 GEOTECHNICAL INVESTIGATION - DISCUSSION AND RECOMMENDATIONS

6.1 Foundation

The proposed reconstruction Site of the DFO-SLCC storage building is underlain by a sand layer

within the investigation depths of 1.1 to 3.0 m below existing grade. Based on the limited

information from the test pits, soil and/or bedrock types below the depths of 1.1 to 3.0 m existing

grade are unknown.

Based on the in situ and laboratory test results from this investigation, the following parameters

are suggested as design parameters for the soil type encountered in the test pits. The

geotechnical soil design parameters are summarized in Table 6-1.

Table 6-1 Soil Profile and Geotechnical Parameter Used for Foundation Analysis

Material Depth, m Bulk Unit Weight,

(kN/m3)

Internal drained friction angle (deg)

Interface Friction Angle, δ (deg)

Sand 0.0 –3.0 21 30 20

6.2 Shallow Foundation

Foundation design parameters are given for static, vertically and concentrically loaded

foundations in compression unless noted otherwise. Dynamic, lateral, eccentric and uplift design

parameters can be provided at request if applicable.

All foundation design recommendations presented in this report are based on the assumption that

an adequate level of construction monitoring during foundation excavation and installation will be

provided. An adequate level of construction monitoring is considered to be: a) for shallow

foundations, examination of all excavation surfaces prior to backfilling as to ensure the integrity

of the subgrade; and b) for earthwork, full-time monitoring and compaction testing.

A conventional foundation system utilizing strip footings founded on a compacted sand layer is

suitable for the structural loadings anticipated. A compacted granular base of engineered fill below

the footing shall be a minimum of 150 mm thick. Any topsoil or organic material encountered must

be removed. The bearing capacities were estimated for the ultimate limit state (ULS) and

serviceability limit state (SLS) for a maximum settlement of 25 mm (Table 6-2). The resistance at

ULS was calculated by applying load resistance factor of 0.5 according to the Canadian

Page 11: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 8

DST CONSULTING ENGINEERS INC.

Foundation Engineering Manual.

6.3 Strip Footings

Strip Footing elements for the proposed building can be founded on the inorganic native sand

layer. Strip footings may be designed using the limit state static bearing pressures listed in Table

6-2. A total maximum length of 10 m was considered for the strip footing geotechnical resistances

estimate. For these estimated bearing pressures to be realized, soil cover of 0.2 m above the

footing is required as described below. Minimum and maximum footing widths of 0.2 m and 0.5

m are recommended, respectively. A minimum distance of one footing width is also required

between adjacent footings.

Table 6-2 Geotechnical Resistances and Reactions for Strip Footings

Depth of footing, D (m)

Width of Strip Footing, B (m)

Ultimate Bearing Capacity (kPa)

Factored Resistance at ULS (kPa)

Factored Reaction at SLS (kPa)

0.2

0.2 100 50 50

0.3 120 60 60

0.5 150 75 75

Any soft or weak soils such as peat below foundation areas, shown or not shown by the test pits

and which are encountered during construction should be excavated under the direction of the

geotechnical engineer to competent material and then backfilled either with Granular ‘B’ Type I

material compacted to 100% standard Proctor maximum dry density (SPMDD) or with a lean

concrete mix. The backfilling material should be compacted to 100% SPMDD and should be

placed and compacted immediately following excavation to design grades.

Bearing areas will require very careful preparation. Following excavation all bearing surfaces

should be cleaned of all organic, loose, disturbed, or slough material prior to concreting or placing

compacted backfill material. Bearing surfaces should be protected at all times from rain, freezing

temperatures and the ingress of groundwater before, during and after construction. Backfill

against foundation walls should consist of an engineered fill material. All foundation excavations

and bearing surfaces should be inspected by a qualified geotechnical engineer to confirm the

integrity of the bearing surface. All constructed foundations should be placed on unfrozen soils,

which should be at all times protected from frost penetration.

Page 12: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 9

DST CONSULTING ENGINEERS INC.

6.4 Slab-On-Grade Construction

The floor slab designed and constructed as a slab-on-grade construction is considered feasible,

provided certain precautions are undertaken. The existing sand layer material is considered

suitable for supporting the slab-on-grade. Therefore, the floor slab may be designed and

constructed as a slab on grade placed on an engineered fill pad constructed on the native sand

layer. The engineered fill pad should be compacted to at least 98% SPMDD. Non-woven

geotextile should be used as separation between native soil and engineered fill.

Once the slab subgrade has been prepared, the floor slab may be constructed on a 150 mm thick

well packed bed of 19 mm clear stone or on OPSS Granular A compacted to 98% SPMDD.

The slab should be structurally independent from walls and columns which are supported on

foundations. This is to reduce any structural distress that may occur as a result of differential soil

movement. If it is intended to place any internal non-load bearing partitions directly on the slab-

on-grade, such walls should also be structurally independent from other elements of the building

founded on the conventional foundation system so that some relative vertical movement of the

walls can occur freely.

The subgrade beneath slab-on-grade should be protected at all times from rain, snow, freezing

temperatures, excessive drying and the ingress of water. This applies during and after the

construction period.

Some relative movement between floor slab-on-grade and adjacent walls or foundation and

differential movement within the slab should be anticipated. Generally, if the recommendations

outlined in this report are followed, these movements are estimated to be, less than 10 mm.

6.5 Backfill Material

Backfill against foundations and foundation walls should consist of non-frost susceptible

engineered fill material such as Granular B Types I or II. The existing native soil which consists

of sand material is considered to be non-frost susceptible and is suitable for use as backfill

material. Exterior backfill against foundation walls should be capped with an impervious layer

(existing native material is not suitable to be used as impervious material). It is anticipated that

the majority of material used for the impervious layer will have to be imported to the Site. The final

grade should be sloped to promote surface drainage away from the structure.

Page 13: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 10

DST CONSULTING ENGINEERS INC.

6.6 Frost Protection

6.6.1 Frost Penetration Depth

Based on the graph prepared jointly by the Division of Building Research, National Research

Council, and the Atmospheric Environment Service, Dept. of the Environment, Canada for the

period 1931 and 1960 published data, for an 85% probability level, the design freezing index for

the Nipigon area has been estimated as 1,750o Celsius days (3,150°F days Fahrenheit). The

design depth of frost penetration for an area that has been kept clear of snow cover should be

taken as 2.9 m for sand soil cover. Frost penetration depth will vary with type of soil cover. The

whole investigation area of the Site is underlain by sand and therefore a 2.9 m frost penetration

depth should be assumed.

The Site is underlain by well-graded sand and none or minimal ground surface heaving is

expected. Pavement, drainage, underground services and side walk designs should include frost

protection consideration. Services such as sewer and water lines should be located below the

depth of frost penetration or be protected with synthetic insulation.

6.6.2 Frost Protection for Foundation Footing

The DFO-SLCC building is an unheated building. For the unheated isolated foundations, to

prevent frost heave of the underlying soils, the foundation should be placed with 2.9 m of soil

cover, underlain by a frost depth layer of non-frost susceptible material (granular soil with less

than 8% of fines/silt) or, if less soil cover is provided, foundations may be underlain with Styrofoam

HI insulation or equivalent.

The results of the sieve analyses carried out on three samples indicate that the soil profile in the

vicinity of the existing building consists of non-frost susceptible material up to the frost depth. The

foundation can be placed on native inorganic soil above frost level. For the conditions

encountered at the Test Pits TP1 to TP3, frost movements are expected to be negligible to none.

Nevertheless, under certain extreme precipitation conditions, where part of the soil saturates and

freezes, it is possible that the footing could be submitted to frost heave as much as 20 mm. In

order to mitigate such effects of the frost heave, for this option, which is the most practical, it is

important that the low content of silt (less than 8%) within the frost zone be confirmed at the time

of construction with 3 additional grainsize analyses. Should any zones with excess silt be

encountered (grain size less than 0.075 mm), these should be sub-excavated and replaced with

Granular ‘B’ Type 1 material compacted to 98% SPMDD.

Page 14: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 11

DST CONSULTING ENGINEERS INC.

6.7 Excavation

Based on the Test Pit logs TP1 to TP3, the base of excavations will occur within the sand deposit.

Excavations must be undertaken in accordance with the requirements of the Occupational Health

and Safety Act of Ontario (OHSA). The subsurface soils are considered to be Type 3 and in

accordance with the OHSA, the excavation side slopes will have to be cut back at 1H:1V. Local

flattening of the side slopes may be required for excavations below the groundwater level, if any,

and in zones of persistent seepage. The stability of the excavation side slopes will be highly

dependent on the contractor’s methodology and ability to effectively dewater the excavation.

No surface surcharges should be placed closer to the edge of the excavation than a distance

equal to twice the depth of the excavation, unless the excavation support system has been

designed to accommodate such surcharge.

Attention should be paid to structures or buried service lines close to the excavation. A general

guideline is that if a line projected down, at 30 degrees from the horizontal from the base of

foundations of adjacent structures intersects the extent of the proposed excavation, underpinning

or special shoring techniques may be required to avoid damaging earth movements.

6.8 Dewatering

It is anticipated that excavations will not extend below the groundwater level and groundwater

control will not be a concern. However, if groundwater control becomes necessary during

construction, it may be achieved by conventional sump pump techniques.

It is to be noted that dewatering effort will depend on a number of factors, including excavation

depth, season and weather conditions, and the length of time the excavations are open. It should

be left to the contractor to determine the means and methods of dewatering necessary to meet

the project requirements and align with their construction methodology and schedule.

6.9 Site Preparation and Grading

The final Site grading should be provided to direct water to areas remote of the proposed

structure. Minimum landscape gradients of 2% are recommended to reduce the risk of runoff

ponding in localized areas or against the building.

Landscaping within a zone of approximately two metres of the exterior perimeter of any structure

should be graded to drain away from the structure at a minimum gradient of 3%. Downspouts

should be positively directed away from the building to beyond the building backfill.

Page 15: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 12

DST CONSULTING ENGINEERS INC.

Subsurface drainage below the floor slab is not required, providing the interior floor elevation is

at least 100 mm higher than adjacent exterior grades and exterior surface drainage is maintained.

If this is not the case, then subsurface drainage should be provided.

Where drainage is required, perforated drainage pipes surrounded with clear stone are

recommended around the perimeter of the foundation. To prevent the ingress of fines into the

drainage stone, the stone should be surrounded with a non-woven geotextile.

Prior to general Site grading for pipe layout, any debris, existing improvements, vegetation, roots,

pavements, or rubble, should be removed and disposed outside the construction limits. Any

shrubs or trees should be completely removed and all roots larger than 0.60 cm diameter should

be grubbed out. The resulting disturbed zones should be properly excavated and backfilled with

compacted structural fill. All active or inactive utilities within the construction limits should be

identified for relocation, abandonment, or protection prior to grading.

The bottoms of any broad, mass excavation areas should be proof-rolled with a rubber-tired

loader or other heavy equipment to locate any soft or loose zones. Any loose/soft or otherwise

unsuitable areas should be removed or compacted in-place. If the disturbed zone is greater than

about 0.30 m in depth, in-place compaction will be difficult, and additional over-excavation and

compaction will be needed. Site preparation for pavement and equipment loading areas should

include over-excavation and re-compaction of native soils. Upon completion of the required over-

excavation and proof-rolling, fills and backfills should be placed and compacted to 95 % of

maximum density from the proctor compaction test result.

6.10 Pipe Bedding, Backfill and Drainage Requirement

6.10.1 Pipe Installations

Installation of services will likely occur in sand. Trenching and pipe installations should be carried

out expeditiously. Care should be taken to prevent excessive disturbance of the subgrade soils

during construction. Sufficient equipment should be available for timely installation to minimize

construction difficulties. Excavating only short trench sections at one time can minimize such

disturbances.

The possibility of bottom heave in the trench exists below the water table. Note that once heaved,

a trench base would be considered unsuitable for pipe support. The base of the excavation should

be closely monitored for vertical movements and disturbance. Backfilling of the trench should

proceed as soon as possible after excavation.

Page 16: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 13

DST CONSULTING ENGINEERS INC.

6.10.2 Pipe Bedding

Pipe bedding should be in accordance with the following Ontario Provincial Standard Drawings

(OPSD) design standards for the class and size of pipe being used as well as manufactures

recommendations. Depending on the type of pipe, as well as on ground conditions (e.g.,

groundwater level, moisture content of the soils, etc.) at the time of construction, one or more of

the following OPSD design standards may be applicable:

OPSD 0802.010 Flexible Pipe Embedment and Backfill – Earth Excavation

OPSD 0802.030 Rigid Pipe Bedding, Cover and Backfill – Type 1 and 2 Soil – Earth

Excavation

OPSD 0802.031 Rigid Pipe Bedding, Cover and Backfill – Type 3 Soil - Earth Excavation

Other OPSD Standards or manufacturer requirements may apply to the construction of the buried

services and the designer should consult these as appropriate for the materials being employed.

It is recommended that the design include a minimum 300 mm of compacted bedding below the

pipe. In the case of over-excavation, the material to bring the trench back to the required subgrade

level should consist of a well graded granular material compacted to 95% of SPMDD.

The trench base should not be founded in or on organics. If organics are found at the base

elevation of a trench, the trench should be extended through the organics (for a width equal to

twice the depth plus the pipe diameter) and the grade restored, as noted above.

6.10.3 Trench Backfill and Compaction Standard

Compaction of the trench backfill will be necessary for the following reasons:

1. To control settlement of the trench fill;

2. To provide lateral support to the trench sidewall; and

3. To minimize soil loads on the pipe.

Inorganic soils at the Site can be used for trench backfill above the pipe levels provided it meets

the OPSS specification for backfill. Alternatively, Granular B Type I material could be used for the

back fill above the pipe levels.

Trench backfill within the footprint of the roadway or parking lot should be compacted to 95% of

standard Proctor maximum dry density for the full depth of the trench. Heavy compaction

equipment should not be used until at least 1 m of compacted backfill exists above the pipe.

Page 17: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 14

DST CONSULTING ENGINEERS INC.

During backfilling, care should be taken to ensure the backfill proceeds in equal stages

simultaneously on both sides of the pipe. No frozen material should be used as backfill; neither

should the trench base be allowed to freeze. The quality and workmanship in the construction is

as important as the compaction standards themselves. It is imperative that the guidelines for the

compaction be followed for the full depth of the trench to achieve satisfactory performance. Clay

seal should be installed along the service trenches in accordance with OPSD 802.095.

7 CONCRETE SLAB ASSESSMENT

Two concrete core samples (C1 and C2) were obtained from the Site from the existing concrete

slab using a portable concrete drilling equipment shown in Figure 7.1, the thickness of the cores

and the concrete slab were measured on site. Also, the type of the material under the slab was

sampled and identified as engineered fill - sand and gravel (Figure 7.2). The concrete core

sampling and an excavation outside the building, beside the concrete slab determined that no

artificial insulation (Styrofoam) has been placed under the building. Concrete core C1 shows

evidence of reinforcing wire mesh for concrete.

The holes in the slab were backfilled with concrete (ready mix) as can be seen in Figure 7-3.

The locations on Site of the two cores samples taken are shown on Drawing No. 1 (Appendix C).

The lab test results are summarized below in Table 7-1. Note that only compressive strength

testing was completed on cylinder C2.

Page 18: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 15

DST CONSULTING ENGINEERS INC.

Figure 7-1: Concrete drilling equipment

Figure 7-2: Concrete core completed and slab bedding material samples

Page 19: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 16

DST CONSULTING ENGINEERS INC.

Figure 7-3: Concrete patching of concrete floor

The lab test results, thicknesses and quality of the cores sampled indicate that the concrete slab

is in good condition and it has of a suitable thickness for continued use as floor slab of a storage

building. The service loading to be applied to the concrete slab should be confirmed by a structural

professional engineer licenced in the Province of Ontario.

Table 7-1 Concrete Cylinder Laboratory Test Results

Core No.

Dry Wt. (g)

Bulk Unit Weight, (kN/m3)

Diameter (mm)

Height /thickness

(mm)

Testing Load (lb.)

Compressive Strength (MPa)

C1 1,774.3 21.90 100.5 105.9 - -

C2 1,832.6 21.29 104.0 90.3 58,220 27.58

The concrete core recovered do not have the required height to diameter ratio of 2 to 1 to obtain

a valid/certified concrete strength, however it gives a qualitative indication of the axial strength

resistance of the material.

Page 20: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 17

DST CONSULTING ENGINEERS INC.

Figure 7-4: View of Concrete Cylinder C1 at DFO-SLCC Storage Building Site, Nipigon, ON

Figure 7-5: View of Concrete Cylinder C2 at DFO-SLCC Storage Building Site, Nipigon, ON

Page 21: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 18

DST CONSULTING ENGINEERS INC.

Observations of the surface conditions of the existing concrete slab indicate that its frost

performance has been relatively good with a few cracks (less than 1 mm).

Figure 7-6: Concrete floor crack

Figure 7-7: Detail - Concrete floor crack

Page 22: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Geotechnical Investigation Report Proposed Reconstruction of the DFO-SLCC Storage Building, Nipigon, Ontario DST Reference No.: TS-NO-027467 19

DST CONSULTING ENGINEERS INC.

8 REFERENCES

Braja M. Das, 2006, Principles of Geotechnical Engineering, Sixth Edition.

Canadian Geotechnical Society (2006). Canadian Foundation Engineering Manual.

Canadian Standards Association, July 2009, A23.1-09/A23.2-09, Concrete Materials and

Methods of Concrete Construction/Test Methods and Standard Practices for Concrete.

Ontario Building Code, 2006, Part 4.1.8.4, Site Properties.

Roy E. Hunt, 2005, Geotechnical Engineering Investigation Handbook, Second Edition.

Page 23: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED
Page 24: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Appendix A

LIMITATIONS OF REPORT

DST CONSULTING ENGINEERS INC.

Page 25: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

L I M I T A T I O N S O F R E P O R TGEOTECHNICAL STUDIES

The data, conclusions and recommendations which are presented in this report,and the quality thereof, are based on a scope of work authorized by the Client.Note that no scope of work, no matter how exhaustive, can identify all conditionsbelow ground. Subsurface and groundwater conditions between and beyond thetestholes may differ from those encountered at the specific locations tested, andconditions may become apparent during construction which were not detected andcould not be anticipated at the time of the site investigation. Conditions can alsochange with time. It is recommended practice that DST Consulting Engineersbe retained during construction to confirm that the subsurface conditionsthroughout the site do not deviate materially from those encountered in thetestholes. The benchmark and elevations used in this report are primarily toestablish relative elevation differences between the testhole locations and shouldnot be used for other purposes, such as grading, excavation, planning,development, etc.

The design recommendations given in this report are applicable only to theproject described in the text and then only if constructed substantially inaccordance with details stated in this report. Since all details of the design maynot be known, we recommend that we be retained during the final stage to verifythat the design is consistent with our recommendations, and that assumptionsmade in our analysis are valid.

Unless otherwise noted, the information contained herein in no way reflects onenvironmental aspects of either the site or the subsurface conditions.

The comments given in this report on potential construction problems andpossible methods are intended only for the guidance of the designer. Thenumber of testholes may not be sufficient to determine all the factors that mayaffect construction methods and costs, e.g. the thickness of surficial topsoil or filllayers may vary markedly and unpredictably. The contractors bidding on thisproject or undertaking the construction should, therefore, make their owninterpretation of the factual information presented and draw their own conclusionas to how the subsurface conditions may affect their work.

Any results from an analytical laboratory or other subcontractor reported hereinhave been carried out by others, and DST Consulting Engineers Inc. cannotwarranty their accuracy. Similarly, DST cannot warranty the accuracy ofinformation supplied by the client.

DST CONSULTING ENGINEERS INC.

Page 26: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Appendix B

DESCRIPTION OF TERMS

DST CONSULTING ENGINEERS INC.

Page 27: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

EXPLANATION OF TERMS USED IN REPORT

SPT ‘N’ VALUE: THE STANDARD PENETRATION TEST (SPT) N VALUE OF THE NUMBER OF BLOWS REQUIRED TO CAUSE ASTANDARD 51 mm O.D. SPLIT BARREL SAMPLES TO PENETRATE 0.3 m INTO UNDISTURBED GROUND IN A BOREHOLE WHENDRIVEN BY A HAMMER WITH A MASS OF 63.5 kg, FALLING FREELY A DISTANCE OF 0.76 m. FOR PENETRATION OF LESS THAN 0.3m N VALUES ARE INDICATED AS THE NUMBER OF BLOWS FOR THE PENETRATION ACHIEVED. AVERAGE N VALUE IS DENOTEDTHUS Ñ.

DYNAMIC CONE PENETRATION TEST (DCPT): CONTINUOUS PENETRATION OF A CONICAL STEEL POINT (51 mm O.D. 60° CONEANGLE) DRIVEN BY 475 J IMPACT ENERGY ON ‘A’ SIZE DRILL RODS. THE RESISTANCE TO CONE PENETRATION IS MEASUREDAS THE NUMBER OF BLOWS FOR EACH 0.3 m ADVANCE OF THE CONICAL POINT INTO THE UNDISTURBED GROUND.

SOILS ARE DESCRIBED BY THEIR COMPOSITION AND CONSISTENCY OR DENSENESSTEXTURAL CLASSIFICATION OF SOILS

BOULDERS COBBLES GRAVEL SAND SILT CLAY

GREATER THAN 200 mm 75 TO 200 mm 4.75 TO 75 mm 0.075 TO 4.75 mm 0.002 TO 0.075 mm LESS THAN 0.002 mm

COARSE GRAIN SOIL DESCRIPTION (50% GREATER THAN 0.075 mm)TERMINOLOGY TRACE OR OCCASIONAL SOME WITH ADJECTIVE (e.g. SILTY OR SANDY) AND (e.g. SAND AND SILT)

LESS THAN 10% 10 TO 20% 20 TO 30% 30 TO 40% 40 TO 60%

CONSISTENCY*: COHESIVE SOILS ARE DESCRIBED ON THE BASIS OF THEIR UNDRAINED SHEAR STRENGTH (CU) AN D SPT ‘N ’ V A LU E S AS FOLLOWSCU (kPa) 0 – 12 12 – 25 25 – 50 50 - 100 100 - 200 > 200

N (BLOWS / 0.3 m) <2 2 - 4 4 - 8 8 - 15 15 - 30 >30VERY SOFT SOFT FIRM STIFF VERY STIFF HARD

DENSENESS: C O H ESIO N LE S S SO IL S A R E D ESC R IB ED O N TH E B A SIS O N D EN S E N ES S A S IN D IC A TED B Y SPT ‘N ’ V A LU E SA S FO L LO W SN (BLOWS / 0.3 m) 0 – 5 5 – 10 10 – 30 30 – 50 > 50

VERY LOOSE LOOSE COMPACT DENSE VERY DENSE

ROCKS ARE DESCRIBED BY THEIR COMPOSITION AND STRUCTURAL FEATURES AND/OR STRENGTHRECOVERY: SUM OF ALL RECOVERED ROCK CORE PIECES FROM A CORING RUN EXPRESSED AS A PERCENT OF THE TOTAL LENGTH OF THECORING RUNMODIFIED RECOVERY: SUM OF THOSE INTACT CORE PIECES, 100 mm+ IN LENGTH EXPRESSED AS A PERCENTAGE OF THE LENGTH OF THE CORINGRUN.

THE ROCK QUALITY DESIGNATION (R.Q.D) FOR MODIFIED RECOVERY IS:R.Q.D (%) 0 – 25 25 – 50 50 – 75 75 – 90 90 – 100

VERY POOR POOR FAIR GOOD EXCELLENT

LEGEND OF RECORDS FOR BOREHOLES: SYMBOLS AND ABBREVATIONS FOR SAMPLE TYPESS SPLIT SPOON SAMPLE WS WASH SAMPLETW THIN WALL SHELBY TUBE SAMPLE AS AUGER (GRAB) SAMPLE

PH SAMPLER ADVANCED BY HYDRAULIC PRESSURE TP THIN WALL PISTON SAMPLE

WH SAMPLER ADVANCED BY SELF STATIC WEIGHT PM SAMPLER ADVANCED BY MANUAL PRESSURE

SC SOIL CORE RC ROCK CORE

WATER LEVEL

*HIERARCHY OF SOIL STRENGTH PREDICTION: 1) LABORATORY TRIAXIAL TESTING. 2) FIELD INSITU VANE TESTING.3) LABORATORY VANE TESTING. 4) SPT VALUES. 5) POCKET PENETROMETER.

Page 28: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Appendix C

DRAWINGS

DST CONSULTING ENGINEERS INC.

Page 29: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

NIPIGON

RIVER

T

R

A

N

S

-C

A

N

A

D

A

H

IG

H

W

A

Y

0

SCALE

25 50 75 100 m

A

C

C

E

S

S

R

O

A

D

0 5 m

SCALE

TEST PIT

CONCRETE CORE

THUNDER BAY, ONTARIO

www.dstgroup.com

consulting engineers

TS

-N

O-027467 D

FO

S

torage B

uilding.dw

g

DRAWING 1

JANUARY 2017

Nipigon, Ontario

Proposed Reconstruction of Storage Building

Geotechnical Investigation

TESTPIT LOCATION PLAN

TS-NO-027467

Fisheries and Oceans

Department of

N

KEY PLAN

SITE

LEGEND

A

C

C

E

S

S

R

O

A

D

TP1

TP2

TP3

C1

C2

DFO-SLCC

STORAGE BUILDING

Page 30: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

Appendix D

ENCLOSURES

DST CONSULTING ENGINEERS INC.

Page 31: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

TOPSOIL

SAND, trace of GRAVEL, trace of SILT,grey, dry, fine to coarse

SAND, some GRAVEL, grey, dry, fine tocoarse

END OF TESTPIT at 3.0 m.

19 81 (0)

Cave at 2.5 m

Testpit remains dry oncompletionn

W

Sym

bol

300 600 1200

Wa

ter

Dat

a

DE

PT

H(m

) 120

Bulk Sample

'N' V

ALU

E

WI

PAGE 1 OF 1

8040

MATERIAL DESCRIPTION

ENCLOSURE 1

SA

MP

LE

TY

PEW

20

p

60

99

98

97

96

95

EL

EV

.(m

)

LOG OF TESTPIT TP1

% MOISTURE

SAMPLE TYPE LEGEND

VANE (kPa)

GR SA SI CL

& GRAINSIZEDISTRIBUTION (%)

REMARKS

900

CPT (kPa)60 90

1

2

3

4

0.2

0.4

0.6

0.8

1.0

1.2

1.4

1.6

1.8

2.0

2.2

2.4

2.6

2.8

3.0

3.2

3.4

3.6

3.8

4.0

4.2

4.4

4.6

4.8

Testpit DataMETHOD: EXCAVATORDATE: 10/28/2016COORDINATES: 5430458 m N, 408340 m E

DST REF. No.: TS-NO-027467CLIENT: DEPARTMENT OF FISHERIES AND OCEANSPROJECT: GEOTECHNICAL INVESTIGATIONLOCATION: NIPIGON, ONTARIOSURFACE ELEV.: 99.9 metres

DST CONSULTING ENGINEERS INC.605 HEWITSON STREET

THUNDER BAY, ON, P7B 5V5PH: 1-807-623-2929FX: 1-807-623-1792

Email: [email protected]: www.dstgroup.com

30

DE

PT

H(m

)

TE

ST

PIT

(S

TA

ND

AR

D)

TS

-NO

-027

467

DF

O S

TO

RA

GE

.GP

J D

AT

A T

EM

PLA

TE

.GD

T 4

/1/1

7

Page 32: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

SAND, brown, dry, fine to coarse

SAND, trace of GRAVEL, trace of SILT,grey, dry, fine to coarse

END OF TESTPIT at 1.1 m. Testpit remains dry oncompletionn

W

Sym

bol

300 600 1200

Wa

ter

Dat

a

DE

PT

H(m

) 120

Bulk Sample

'N' V

ALU

E

WI

PAGE 1 OF 1

8040

MATERIAL DESCRIPTION

ENCLOSURE 2

SA

MP

LE

TY

PEW

20

p

60

99

98

97

96

EL

EV

.(m

)

LOG OF TESTPIT TP2

% MOISTURE

SAMPLE TYPE LEGEND

VANE (kPa)

GR SA SI CL

& GRAINSIZEDISTRIBUTION (%)

REMARKS

900

CPT (kPa)60 90

1

2

3

4

0.2

0.4

0.6

0.8

1.0

1.2

1.4

1.6

1.8

2.0

2.2

2.4

2.6

2.8

3.0

3.2

3.4

3.6

3.8

4.0

4.2

4.4

4.6

4.8

Testpit DataMETHOD: EXCAVATORDATE: 10/28/2016COORDINATES: 5430455 m N, 408349 m E

DST REF. No.: TS-NO-027467CLIENT: DEPARTMENT OF FISHERIES AND OCEANSPROJECT: GEOTECHNICAL INVESTIGATIONLOCATION: NIPIGON, ONTARIOSURFACE ELEV.: 100 metres

DST CONSULTING ENGINEERS INC.605 HEWITSON STREET

THUNDER BAY, ON, P7B 5V5PH: 1-807-623-2929FX: 1-807-623-1792

Email: [email protected]: www.dstgroup.com

30

DE

PT

H(m

)

TE

ST

PIT

(S

TA

ND

AR

D)

TS

-NO

-027

467

DF

O S

TO

RA

GE

.GP

J D

AT

A T

EM

PLA

TE

.GD

T 4

/1/1

7

Page 33: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

TOPSOIL

SAND, trace of GRAVEL, trace of SILT,brown, loose to compact, dry, fine tocoarse

SAND, some GRAVEL, trace of SILT,brown, dry, fine to coarse

END OF TESTPIT at 2.5 m.

4

11

94

88

(2)

(1)

Testpit remains dry oncompletionn

W

Sym

bol

300 600 1200

Wa

ter

Dat

a

DE

PT

H(m

) 120

Bulk Sample

'N' V

ALU

E

WI

PAGE 1 OF 1

8040

MATERIAL DESCRIPTION

ENCLOSURE 3

SA

MP

LE

TY

PEW

20

p

60

99

98

97

96

95

EL

EV

.(m

)

LOG OF TESTPIT TP3

% MOISTURE

SAMPLE TYPE LEGEND

VANE (kPa)

GR SA SI CL

& GRAINSIZEDISTRIBUTION (%)

REMARKS

900

CPT (kPa)60 90

1

2

3

4

0.2

0.4

0.6

0.8

1.0

1.2

1.4

1.6

1.8

2.0

2.2

2.4

2.6

2.8

3.0

3.2

3.4

3.6

3.8

4.0

4.2

4.4

4.6

4.8

Testpit DataMETHOD: EXCAVATORDATE: 10/28/2016COORDINATES: 5430446 m N, 408353 m E

DST REF. No.: TS-NO-027467CLIENT: DEPARTMENT OF FISHERIES AND OCEANSPROJECT: GEOTECHNICAL INVESTIGATIONLOCATION: NIPIGON, ONTARIOSURFACE ELEV.: 99.7 metres

DST CONSULTING ENGINEERS INC.605 HEWITSON STREET

THUNDER BAY, ON, P7B 5V5PH: 1-807-623-2929FX: 1-807-623-1792

Email: [email protected]: www.dstgroup.com

30

DE

PT

H(m

)

TE

ST

PIT

(S

TA

ND

AR

D)

TS

-NO

-027

467

DF

O S

TO

RA

GE

.GP

J D

AT

A T

EM

PLA

TE

.GD

T 4

/1/1

7

Page 34: GEOTECHNICAL INVESTIGATION REPORT FOR PROPOSED

0

5

10

15

20

25

30

35

40

45

50

55

60

65

70

75

80

85

90

95

100

1.18mm

Coarse

GRAVEL

Fine Coarse

19.0mm

BH

2.50

0.60

1.70

SYMBOL60

22

425µm

600µm

850µm

2"

PE

RC

EN

T

RE

TA

INE

D

75.0mm

" 3"

100

215 10 "

MINISTRY SIEVE DESIGNATION ( Imperial )

70

80

90

140 100 60 50

30 40 50

TP1

TP3

TP3

40

26.5mm

"

PE

RC

EN

T

PA

SS

ING

0

10

20

30

40

50

CLAY & SILTSAND

Fine

" 12

53µm

75µm

106µm

20 30 40 270 200

1 2 3 4 5

12

10 20 37.5mm

53.0mm

63.0mm

30 20 16 10 8 34" 1" 1

LEGEND

150µm

250µm

300µm

3 4

DEPTH

2.00mm

2.36mm

4.75mm

9.5mm

13.2mm

Medium

UNIFIED SOIL CLASSIFICATION SYSTEM

4 381

GRAIN SIZE IN MICROMETERS

CLAY & SILT

GRAIN SIZE DISTRIBUTION

SAND

T-T

IME

GR

AIN

SIZ

E T

S-N

O-0

2746

7 D

FO

ST

OR

AG

E.G

PJ

DA

TA

TE

MP

LAT

E.G

DT

30/

12/1

6

ENCLOSURE 4DST REF # TS-NO-027467

NIPIGON, ONTARIO