geotechnical engineering report · geotechnical engineering report cr 44h structures larimer...

89
Geotechnical Engineering Report CR 44H Structures Approx. 10 miles of CR 44H from Ballard Road east to CR 27 Larimer County, Colorado November 6, 2015 Terracon Project No. 20155038 Prepared for: AVI PC Fort Collins, Colorado Prepared by: Terracon Consultants, Inc. Fort Collins, Colorado

Upload: others

Post on 24-Oct-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

  • Geotechnical Engineering Report CR 44H Structures

    Approx. 10 miles of CR 44H from Ballard Road east to CR 27

    Larimer County, Colorado

    November 6, 2015

    Terracon Project No. 20155038

    Prepared for:

    AVI PC

    Fort Collins, Colorado

    Prepared by:

    Terracon Consultants, Inc.

    Fort Collins, Colorado

  • TABLE OF CONTENTS

    Page

    EXECUTIVE SUMMARY ............................................................................................................ i 1.0 INTRODUCTION .............................................................................................................1 2.0 PROJECT INFORMATION .............................................................................................1

    2.1 Project Description ...............................................................................................1 2.2 Site Location and Description...............................................................................2

    3.0 SUBSURFACE CONDITIONS ........................................................................................2 3.1 Typical Subsurface Profile ...................................................................................2 3.2 Laboratory Testing ...............................................................................................3 3.3 Corrosion Protection ............................................................................................3 3.4 Groundwater ........................................................................................................3

    4.0 RECOMMENDATIONS FOR DESIGN AND CONSTRUCTION ......................................4 4.1 Geotechnical Considerations ...............................................................................4

    4.1.1 Existing, Undocumented Fill .....................................................................4 4.1.2 Shallow Groundwater ...............................................................................4 4.1.3 Foundation Recommendations .................................................................5

    4.2 Earthwork.............................................................................................................5 4.2.1 Site Preparation ........................................................................................5 4.2.2 Excavation ................................................................................................6 4.2.3 Subgrade Preparation ...............................................................................7 4.2.4 Fill Materials and Placement ......................................................................7 4.2.5 Compaction Requirements ........................................................................9 4.2.6 Grading and Drainage ...............................................................................9

    4.3 Foundations .......................................................................................................10 4.3.1 Spread Footings - Design Recommendations .........................................11 4.3.2 Spread Footings - Construction Considerations ......................................12

    4.4 Seismic Considerations......................................................................................12 4.5 Lateral Earth Pressures .....................................................................................13

    5.0 GENERAL COMMENTS ...............................................................................................14

  • TABLE OF CONTENTS (continued)

    Appendix A – FIELD EXPLORATION

    Exhibit A-1 Site Location Map

    Exhibits A-2 to A-13 Exploration Plan

    Exhibit A-14 Field Exploration Description

    Exhibits A-15 to A-46 Boring Logs

    Appendix B – LABORATORY TESTING

    Exhibit B-1 Laboratory Testing Description

    Exhibit B-2 Atterberg Limits Test Results

    Exhibits B-3 to B-9 Grain-size Distribution Test Results

    Exhibits B-10 to B-13 Water-soluble Sulfate Test Results

    Appendix C – SUPPORTING DOCUMENTS

    Exhibit C-1 General Notes

    Exhibit C-2 Unified Soil Classification System

    Exhibit C-3 Description of Rock Properties

    Exhibit C-4 Laboratory Test Significance and Purpose

    Exhibits C-5 and C-6 Report Terminology

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable i

    EXECUTIVE SUMMARY

    A geotechnical investigation has been performed for the proposed CR 44H Structures to be

    constructed along approximately 10 miles of CR 44H from Ballard Road east to CR 27 in Larimer

    County, Colorado. Thirty-two (32) borings, presented as Exhibits A-15 through A-46 and

    designated as Boring No. 1 through Boring No. 32, were performed to depths of approximately 7 to

    22½ feet below existing site grades. This report specifically addresses the recommendations for

    the proposed replacement box culverts. Borings performed in these areas are for informational

    purposes and will be utilized by others.

    Based on the information obtained from our subsurface exploration, the site can be developed for

    the proposed project. However, the following geotechnical considerations were identified and will

    need to be considered:

    Existing, undocumented fill was encountered in the borings performed on this site to depths

    ranging from about 2½ to 9 feet below existing site grades. The fill was likely placed during

    construction of the existing metal culverts, roadway embankments, and/or deposited during

    a recent flood event. We anticipate the proposed foundations will extend to depths below

    the encountered fill materials. If the proposed foundations will not extend below the

    encountered fill materials, the existing fill soils should be removed and replaced with

    engineered fill beneath proposed foundations.

    The proposed culverts may be supported on shallow spread footing foundations bearing

    on properly prepared on-site soils or properly placed imported fill.

    Very hard bedrock was encountered at depths ranging from 6 to 21 feet below the existing

    site grades. Excavation penetrating the bedrock (if any) may require the use of

    specialized heavy-duty equipment, together with ripping or jack-hammering to advance

    the excavation and facilitate rock break-up and removal. Consideration should be given

    to obtaining a unit price for difficult excavation in the contract documents for the project.

    Groundwater was encountered at depths ranging from 4 to 10 feet below the existing site

    grades. We anticipate construction dewatering will be required for construction of the

    foundations of the proposed culverts. AS water flows increase within the drainage area,

    dewatering will require more significant effort.

    The amount of movement of foundations will be related to the wetting of underlying

    supporting soils. Therefore, it is imperative the recommendations discussed in the 4.2.6

    Grading and Drainage section of this report be followed to reduce potential movement.

    The 2012 International Building Code, Table 1613.5.2 IBC seismic site classification for this

    site ranges from C to D. The table in the 4.4 Seismic Considerations section of this

    report presents which structures are classified as site class C or D.

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable ii

    Close monitoring of the construction operations discussed herein will be critical in

    achieving the design subgrade support. We therefore recommend that Terracon be

    retained to monitor this portion of the work.

    This summary should be used in conjunction with the entire report for design purposes. It

    should be recognized that details were not included or fully developed in this section, and the

    report must be read in its entirety for a comprehensive understanding of the items contained

    herein. The section titled GENERAL COMMENTS should be read for an understanding of the

    report limitations.

  • Responsive ■ Resourceful ■ Reliable 1

    GEOTECHNICAL ENGINEERING REPORT

    CR 44H Structures

    Approx. 10 miles of CR 44H from Ballard Road east to CR 27

    Larimer County, Colorado Terracon Project No. 20155038

    November 6, 2015

    1.0 INTRODUCTION

    This report presents the results of our geotechnical engineering services performed for the

    proposed CR 44H Structures to be constructed along approximately 10 miles of CR 44H from

    Ballard Road east to CR 27 in Larimer County, Colorado (Exhibit A-1). The purpose of these

    services is to provide information and geotechnical engineering recommendations relative to:

    subsurface soil and bedrock conditions foundation design and construction

    groundwater conditions earthwork

    grading and drainage lateral earth pressures

    seismic considerations

    Our geotechnical engineering scope of work for this project included the initial site visit, the

    advancement of 32 test borings to depths of approximately 7 to 22½ feet below existing site

    grades, laboratory testing for soil engineering properties and engineering analyses to provide

    box culvert foundation design and construction recommendations.

    Logs of the borings along with an Exploration Plan (Exhibit A-2) are included in Appendix A.

    More detailed, “zoomed in” Exploration Plans for each portion of the alignment are presented as

    Exhibits A-3 through A-13 in Appendix A. The results of the laboratory testing performed on soil

    and bedrock samples obtained from the site during the field exploration are included in

    Appendix B.

    2.0 PROJECT INFORMATION

    2.1 Project Description

    Item Description

    Site layout Refer to the Exploration Plans (Exhibits A-2 through A-13 in Appendix A)

    Proposed construction

    We understand 17 three-sided, concrete box culverts will be constructed

    along CR 44H. The structures will be approximately 10 feet tall by 20

    feet wide.

    Grading We anticipate cuts and fills on the order of 12 to 15 feet will be required

    for the proposed construction.

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable 2

    Item Description

    Cut and fill slopes Assumed to be no steeper than 3H:1V (Horizontal to Vertical)

    2.2 Site Location and Description

    Item Description

    Location

    The 17 structures are planned along approximately 10 miles of CR 44H

    starting approximately 900 feet west of Ballard Road and CR 44H and

    continuing east in Larimer County, Colorado.

    Existing improvements

    CR 44H is a gravel-surfaced roadway with several metal pipe culvert

    crossings. We understand the flood event in 2013 damaged several

    locations along this roadway. Temporary crossings were constructed at

    several locations as well as reconstruction of several sections of the

    roadway.

    Current ground cover The ground is covered with gravel surfacing, native plants, mature trees,

    and some riprap.

    Existing topography The roadway surface is relatively flat with several shear rock

    outcroppings and shoulder drop-offs sloping towards Buckhorn Creek.

    3.0 SUBSURFACE CONDITIONS

    3.1 Typical Subsurface Profile

    Specific conditions encountered at each boring location are indicated on the individual boring

    logs included in Appendix A. Stratification boundaries on the boring logs represent the

    approximate location of changes in soil types; in-situ, the transition between materials may be

    gradual. Based on the results of the borings, subsurface conditions on the project site can be

    generalized as follows:

    Material Description Approximate Depth to Bottom of

    Stratum (feet) Consistency/Density/Hardness

    Gravel surfacing About 4 to 30 inches thick. --

    Fill materials consisting of silt,

    lean clay, sand, gravel, and

    cobbles

    About 2½ to 9 feet below existing

    site grades in Boring Nos. 2, 11, 12,

    17, 21, 22, 24, 25, 26, 27, and 32.

    --

    Sand with silt, gravel, and

    cobbles/boulders

    About 6 to 21 feet below existing

    site grades. Very loose to very dense

    Sandy lean clay About 6 feet below the existing site

    grade in Boring No. 6 only Medium stiff to very stiff

    Schist bedrock To the maximum depth of

    exploration of about 25 feet.

    Hard to very hard (highly

    cemented

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable 3

    3.2 Laboratory Testing

    Samples of site soils selected for plasticity testing exhibited non-plastic to medium plasticity with

    liquid limits ranging from non-plastic to 36 and plasticity indices ranging from 3 to 17.

    Laboratory test results are presented in Appendix B.

    3.3 Corrosion Protection

    Results of water-soluble sulfate testing indicate that ASTM Type I or II portland cement should

    be specified for all project concrete on and below grade. Foundation concrete should be

    designed for low sulfate exposure in accordance with the provisions of the ACI Design Manual,

    Section 318, Chapter 4.

    3.4 Groundwater

    The boreholes were observed while drilling and after completion for the presence and level of

    groundwater. In addition, delayed water levels were also obtained in some borings. The water

    levels observed in the boreholes are noted on the attached boring logs, and are summarized

    below:

    Boring Number Depth to groundwater

    while drilling, ft. Boring Number

    Depth to groundwater

    while drilling, ft.

    1 7 17 7

    2 9 18 9

    3 4 19 5

    4 7 20 8

    5 7 21 7

    6 7 22 9

    7 7 23 9

    8 4 24 8

    9 7 25 9

    10 9 26 10

    11 9 27 8

    12 7 28 10

    13 5.5 29 10

    14 5.5 30 11

    15 10 31 9

    16 7.5 32 9

    These observations represent groundwater conditions at the time of the field exploration, and

    may not be indicative of other times or at other locations. Groundwater levels can be expected

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable 4

    to fluctuate with varying seasonal and weather conditions, and other factors.

    Groundwater level fluctuations occur due to seasonal variations in the water levels present in

    the Buckhorn Creek, amount of rainfall, runoff and other factors not evident at the time the

    borings were performed. Therefore, groundwater levels during construction or at other times in

    the life of the structures may be higher or lower than the levels indicated on the boring logs.

    The possibility of groundwater level fluctuations should be considered when developing the

    design and construction plans for the project.

    4.0 RECOMMENDATIONS FOR DESIGN AND CONSTRUCTION

    4.1 Geotechnical Considerations

    Based on subsurface conditions encountered in the borings, the site appears suitable for the

    proposed construction from a geotechnical point of view provided certain precautions and

    design and construction recommendations described in this report are followed. We have

    identified geotechnical conditions that could impact design and construction of the proposed

    structures and other site improvements.

    4.1.1 Existing, Undocumented Fill

    As previously noted, existing fill was encountered to depths up to about 9 feet in the borings

    drilled at the site. We do not possess any information regarding whether the fill was placed

    under the observation of a geotechnical engineer. The fill was likely placed during construction of

    the existing metal culverts, roadway embankments, and/or deposited during a recent flood event.

    We anticipate the proposed foundations will extend to depths below the encountered fill materials.

    If the proposed foundations will not extend below the encountered fill materials, the existing fill soils

    should be removed and replaced with engineered fill beneath proposed foundations.

    Support of footings on or above existing fill soils is discussed in this report. However, even with

    the recommended construction testing services, there is an inherent risk for the owner that

    compressible fill or unsuitable material within or buried by the fill will not be discovered. This risk

    of unforeseen conditions cannot be eliminated without completely removing the existing fill, but

    can be reduced by performing additional testing and evaluation. However, we anticipate the

    footing elevations will extend below the existing fill materials.

    4.1.2 Shallow Groundwater

    As previously stated, groundwater was measured at depths ranging from about 4 to 10 feet

    below existing site grades. We anticipate construction dewatering will be required for the

    proposed construction. It is also possible and likely that groundwater levels below this site will

    rise as water levels in the Buckhorn Creek rise.

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable 5

    4.1.3 Foundation Recommendations

    The proposed culverts may be supported on spread footing foundation systems bearing on

    properly prepared on-site soils or properly placed imported fill.

    Bedrock was encountered at depths ranging from 6 to 21 feet below existing site

    grades. Without any ground modifications, shallow footing foundations may be partially

    constructed on bedrock and partially constructed on soil. We believe different foundation

    support conditions below various portions of the footing foundations would result in a risk for

    differential foundation movements. The magnitude of the differential movement would depend

    on foundation loading conditions.

    In areas where foundations will bear partially on bedrock and partially on soil, we recommend

    over-excavating the bedrock and replacing with properly prepared on-site soils or imported

    engineered fill to a depth that will allow equal thicknesses of soil between continuous footings

    and bedrock. If half of a culvert (on one side of the creek) will bear on soil and the other half of

    the culvert (on the opposite side of the creek) will bear on bedrock, we recommend over-

    excavating the bedrock a minimum depth of 2 feet, and replacing the excavated bedrock with

    properly placed engineered fill. On-site soils area suitable for use as engineered fill provided

    they are properly prepared as presented in the 4.2 Earthwork section of this report. In areas

    where the footings will bear on the bedrock, the bearing surface of the bedrock should be

    thoroughly cleaned to remove any loose bedrock pieces.

    4.2 Earthwork

    The following presents recommendations for site preparation, excavation, subgrade preparation

    and placement of engineered fills on the project. All earthwork on the project should be

    observed and evaluated by Terracon on a full-time basis. The evaluation of earthwork should

    include observation of over-excavation operations, testing of engineered fills, subgrade

    preparation, subgrade stabilization, and other geotechnical conditions exposed during the

    construction of the project.

    4.2.1 Site Preparation

    Prior to placing any fill, strip and remove existing vegetation (if any), the depth of existing fill, and

    any other deleterious materials from the proposed construction areas.

    Stripped organic materials should be wasted from the site or used to re-vegetate exposed slopes

    after completion of grading operations. Prior to the placement of fills, the site should be graded to

    create a relatively level surface to receive fill, and to provide for a relatively uniform thickness of fill

    beneath proposed structures.

    If fill is placed in areas of the site where existing slopes are steeper than 5:1 (horizontal:vertical),

    the area should be benched to reduce the potential for slippage between existing slopes and fills.

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable 6

    Benches should be wide enough to accommodate compaction and earth moving equipment, and

    to allow placement of horizontal lifts of fill.

    Demolition of the existing steel culverts and temporary crossings should include complete removal

    of all foundation components (if any) within the proposed construction areas. This should include

    removal of any utilities to be abandoned along with any loose utility trench backfill or loose backfill

    found adjacent to existing foundations. All materials derived from the demolition of the existing

    structures should be removed from the site, and not be allowed for use in any on-site fills.

    4.2.2 Excavation

    It is anticipated that excavations for the proposed construction not penetrating bedrock can be

    accomplished with conventional earthmoving equipment. Excavations into the on-site soils will

    encounter weak and/or saturated soil conditions with possible caving conditions.

    Excavation penetrating the bedrock may require the use of specialized heavy-duty equipment,

    together with ripping or jack-hammering to advance the excavation and facilitate rock break-up

    and removal. Consideration should be given to obtaining a unit price for difficult excavation in the

    contract documents for the project.

    The soils to be excavated can vary significantly across the site as their classifications are based

    solely on the materials encountered in widely-spaced exploratory test borings. The contractor

    should verify that similar conditions exist throughout the proposed area of excavation. If different

    subsurface conditions are encountered at the time of construction, the actual conditions should be

    evaluated to determine any excavation modifications necessary to maintain safe conditions.

    Although evidence of underground facilities such as septic tanks, vaults, and basements was not

    observed during the site reconnaissance, such features could be encountered during construction.

    If unexpected fills or underground facilities are encountered, such features should be removed

    and the excavation thoroughly cleaned prior to backfill placement and/or construction.

    Any over-excavation that extends below the bottom of foundation elevation should extend laterally

    beyond all edges of the footings at least 8 inches per foot of over-excavation depth below the

    footing base elevation. The over-excavation should be backfilled to the footing base elevation in

    accordance with the recommendations presented in this report.

    Depending upon depth of excavation and seasonal conditions, surface water infiltration and/or

    groundwater may be encountered in excavations on the site. It is anticipated that pumping from

    sumps may be utilized to control water within excavations. Well points may be required for

    significant groundwater flow, or where excavations penetrate groundwater to a significant depth.

    Groundwater seepage should be anticipated for excavations approaching the level of bedrock.

    The subgrade soil conditions should be evaluated during the excavation process and the stability

    of the soils determined at that time by the contractors’ Competent Person. Slope inclinations

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable 7

    flatter than the OSHA maximum values may have to be used. The individual contractor(s) should

    be made responsible for designing and constructing stable, temporary excavations as required to

    maintain stability of both the excavation sides and bottom. All excavations should be sloped or

    shored in the interest of safety following local, and federal regulations, including current OSHA

    excavation and trench safety standards.

    As a safety measure, it is recommended that all vehicles and soil piles be kept a minimum lateral

    distance from the crest of the slope equal to the slope height. The exposed slope face should be

    protected against the elements

    4.2.3 Subgrade Preparation

    After the existing fill below proposed footings (if any) and any other deleterious materials have

    been removed from the construction area, the top 8 inches of the exposed ground surface

    should be scarified, moisture conditioned, and recompacted to at least 95 percent of the

    maximum dry unit weight as determined by ASTM D698 before any new fill or foundation is

    placed.

    If pockets of soft, loose, or otherwise unsuitable materials are encountered at the bottom of the

    footing excavations and it is inconvenient to lower the footings, the proposed footing elevations

    may be reestablished by over-excavating the unsuitable soils and backfilling with compacted

    engineered fill. Any over-excavation should be performed in accordance with the excavation

    recommendations given below.

    In addition, large cobbles or boulder-sized materials may be encountered beneath footing areas.

    Such conditions could create point loads on the bottom of footings, increasing the potential for

    differential foundation movement. If such conditions are encountered in the footing excavations,

    the cobbles and/or boulders should be removed and be replaced with engineered fill,

    conditioned to near optimum moisture content and compacted.

    After the bottom of the excavation has been compacted, engineered fill can be placed to bring

    the foundations to the desired grade. Engineered fill should be placed in accordance with the

    recommendations presented in subsequent sections of this report.

    The stability of the subgrade may be affected by precipitation, repetitive construction traffic or

    other factors. If unstable conditions develop, workability may be improved by scarifying and

    drying. Alternatively, over-excavation of wet zones and replacement with granular materials

    may be used, or crushed gravel and/or rock can be tracked or “crowded” into unstable subgrade

    surface soils until a stable working surface is attained. Lightweight excavation equipment may

    also be used to reduce subgrade pumping.

    4.2.4 Fill Materials and Placement

    The on-site soils or approved granular and low plasticity cohesive imported materials may be used

    as fill material. The soil removed from this site that is free of organic or objectionable materials,

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable 8

    as defined by a field technician who is qualified in soil material identification and compaction

    procedures, can be re-used as fill for the culvert foundations. Bedrock excavated from the site

    (if any) should be thoroughly processed and broken down to pieces no larger than 4 inches in

    size prior to re-use as fill. It should be noted that on-site soils may require reworking to adjust

    the moisture content to meet the compaction criteria.

    Imported soils (if required) should meet the following material property requirements:

    Gradation Percent finer by weight (ASTM C136)

    4” 100

    3” 70-100

    No. 4 Sieve 50-100

    No. 200 Sieve 15-50

    Soil Properties Value

    Liquid Limit 30 (max.)

    Plastic Limit 5 (max.)

    Maximum Expansive Potential (%) Non-expansive1

    1. Measured on a sample compacted to approximately 95 percent of the maximum dry unit weight as

    determined by ASTM D698 at optimum moisture content. The sample is confined under a 100 psf

    surcharge and submerged.

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable 9

    4.2.5 Compaction Requirements

    Engineered fill should be placed and compacted in horizontal lifts, using equipment and

    procedures that will produce recommended moisture contents and densities throughout the lift.

    Item Description

    Fill lift thickness

    9 inches or less in loose thickness when heavy, self-

    propelled compaction equipment is used

    4 to 6 inches in loose thickness when hand-guided

    equipment (i.e. jumping jack or plate compactor) is used

    Minimum compaction requirements 95 percent of the maximum dry unit weight as determined

    by ASTM D698

    Moisture content cohesive soil (clay) -1 to +3 % of the optimum moisture content

    Moisture content cohesionless soil

    (sand) -3 to +2 % of the optimum moisture content

    1. We recommend engineered fill be tested for moisture content and compaction during placement.

    Should the results of the in-place density tests indicate the specified moisture or compaction limits

    have not been met, the area represented by the test should be reworked and retested as required

    until the specified moisture and compaction requirements are achieved.

    2. Specifically, moisture levels should be maintained low enough to allow for satisfactory compaction

    to be achieved without the fill material pumping when proofrolled.

    3. Moisture conditioned clay materials should not be allowed to dry out. A loss of moisture within

    these materials could result in an increase in the material’s expansive potential. Subsequent

    wetting of these materials could result in undesirable movement.

    The recommendations for placement and compaction criteria presented assume that fill depths

    will be less than 8 feet. Fills on the order of 8 feet in depth, when placed and compacted as

    recommended in this report, will experience some settlement, generally 1 inch or less. The

    amount and rate of settlement will be increased if water is introduced into the fill. It is noted that

    settlement of the fill material due to self-weight is in addition to settlements due to structural

    induced loads. In areas where fill will be placed in thicknesses of 8 feet or more, we

    recommend increasing the minimum compaction requirements to 98 percent of the maximum

    dry unit weight as determined by ASTM D698.

    4.2.6 Grading and Drainage

    All grades must be adjusted to provide effective drainage away from the proposed culverts

    during construction and maintained throughout the life of the proposed project. Infiltration of

    water into foundation excavations must be prevented during construction. Water permitted to

    pond near or adjacent to the perimeter of the structures (either during or post-construction) can

    result in significantly higher soil movements than those discussed in this report. As a result, any

    estimations of potential movement described in this report cannot be relied upon if positive

    drainage is not obtained and maintained, and water is allowed to infiltrate the fill and/or

    subgrade.

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable 10

    Exposed ground (if any) should be sloped at a minimum of 10 percent grade for at least 10 feet

    beyond the perimeter of the proposed culverts, where possible. The use of swales, chases

    and/or area drains may be required to facilitate drainage in unpaved areas around the perimeter

    of the culverts. Backfill against footings and exterior walls should be properly compacted and

    free of all construction debris to reduce the possibility of moisture infiltration. After construction

    of the proposed culverts and prior to project completion, we recommend verification of final

    grading be performed to document positive drainage, as described above, has been achieved.

    4.3 Foundations

    The proposed culverts may be supported on spread footing foundation systems bearing on

    properly prepared on-site soils or properly placed imported fill. Bedrock was encountered at

    depths ranging from 6 to 21 feet below existing site grades. Without any ground modifications,

    shallow footing foundations may be partially constructed on bedrock and partially constructed on

    soil. We believe different foundation support conditions below various portions of the footing

    foundations would result in a risk for differential foundation movements. The magnitude of the

    differential movement would depend on foundation loading conditions.

    In areas where foundations will bear partially on bedrock and partially on soil, we recommend

    over-excavating the bedrock and replacing with properly prepared on-site soils or imported

    engineered fill to a depth that will allow equal thicknesses of soil between continuous footings and

    bedrock. If half of a culvert (on one side of the creek) will bear on soil and the other half of the

    culvert (on the opposite side of the creek) will bear on bedrock, we recommend over-excavating

    the bedrock a minimum depth of 2 feet, and replacing the excavated bedrock with properly placed

    engineered fill. On-site soils area suitable for use as engineered fill provided they are properly

    prepared as presented in the 4.2 Earthwork section of this report. In areas where the footings

    will bear on the bedrock, the bearing surface of the bedrock should be thoroughly cleaned to

    remove any loose bedrock pieces.

    Design recommendations for foundations for the proposed structures and related structural

    elements are presented in the following sections.

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable 11

    4.3.1 Spread Footings - Design Recommendations

    Description Value

    Maximum allowable bearing pressure 1 On-site soils or imported fill: 3,000 psf

    Bedrock: 5,000 psf

    Lateral earth pressure coefficients 2

    Lean clay:

    Active, Ka = 0.41

    Passive, Kp = 2.46

    At-rest, Ko = 0.58

    Granular soil/fill:

    Active, Ka = 0.27

    Passive, Kp = 3.69

    At-rest, Ko = 0.43

    Sliding coefficient 2 Granular soil/fill:

    µ = 0.56

    Moist soil unit weight

    Lean clay:

    ɣ = 120 pcf

    Granular soil/fill:

    ɣ = 130 pcf

    Minimum embedment depth below finished

    grade 3 30 inches

    Estimated total movement 4 About 1 inch

    Estimated differential movement 4 About ½ to ¾ of total movement

    1. The recommended maximum allowable bearing pressure assumes any unsuitable fill or soft soils,

    if encountered, will be over-excavated and replaced with properly compacted engineered fill.

    The design bearing pressure applies to a dead load plus design live load condition. The design

    bearing pressure may be increased by one-third when considering total loads that include wind or

    seismic conditions.

    2. The lateral earth pressure coefficients and sliding coefficients are ultimate values and do not

    include a factor of safety. The foundation designer should include the appropriate factors of

    safety.

    3. For frost protection and to reduce the effects of seasonal moisture variations in the subgrade

    soils. The minimum embedment depth is for perimeter footings beneath unheated areas and is

    relative to lowest adjacent finished grade, typically exterior grade.

    4. The estimated movements presented above are based on the assumption that the maximum

    footing size is 3 feet for continuous footings.

    Footings should be proportioned to reduce differential foundation movement. As discussed,

    total movement resulting from the assumed structural loads is estimated to be on the order of

    about 1 inch. Additional foundation movements could occur if water from any source infiltrates

    the foundation soils; therefore, proper drainage should be provided in the final design and

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable 12

    during construction and throughout the life of the structure. Failure to maintain the proper

    drainage as recommended in the 4.2.6 Grading and Drainage section of this report will nullify

    the movement estimates provided above.

    4.3.2 Spread Footings - Construction Considerations

    Spread footing construction should only be considered if the estimated foundation movement

    can be tolerated. Subgrade soils beneath footings should be moisture conditioned and

    compacted as described in the 4.2 Earthwork section of this report. The moisture content and

    compaction of subgrade soils should be maintained until foundation construction.

    Footings and foundation walls should be reinforced as necessary to reduce the potential for

    distress caused by differential foundation movement.

    Unstable subgrade conditions are anticipated as excavations approach the groundwater

    surface. Unstable surfaces will need to be stabilized prior to backfilling excavations and/or

    constructing the culvert foundations. The use of angular rock, recycled concrete and/or gravel

    pushed or “crowded” into subgrade soils is considered suitable means of stabilizing the

    subgrade. The use of geogrid materials in conjunction with gravel could also be considered and

    could be more cost effective.

    Unstable subgrade conditions should be observed by Terracon to assess the subgrade and

    provide suitable alternatives for stabilization. Stabilized areas should be proof-rolled prior to

    continuing construction to assess the stability of the subgrade.

    Foundation excavations should be observed by Terracon. If the soil conditions encountered

    differ significantly from those presented in this report, supplemental recommendations will be

    required.

    4.4 Seismic Considerations

    Code Used 2012 International Building Code (IBC)1

    Site Classification C 2 Site Classification D 2

    Structure Nos. Structure Nos.

    4, 7, 9, 12, 13, and 16 1, 2, 3, 5, 6, 8, 10, 11, 14, 15, and 17

    1. In general accordance with the 2012 International Building Code, Table 1613.5.2.

    2. The 2012 International Building Code (IBC) requires a site soil profile determination extending a

    depth of 100 feet for seismic site classification. The current scope requested does not include the

    required 100 foot soil profile determination. The borings completed for this project extended to a

    maximum depth of about 22½ feet and this seismic site class definition considers that similar soil and

    bedrock conditions exist below the maximum depth of the subsurface exploration. A geophysical

    exploration could be utilized in order to attempt to justify a more favorable seismic site class.

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable 13

    4.5 Lateral Earth Pressures

    Reinforced concrete walls with unbalanced backfill levels on opposite sides should be designed

    for earth pressures at least equal to those indicated in the following table. Earth pressures will

    be influenced by structural design of the walls, conditions of wall restraint, methods of

    construction and/or compaction and the strength of the materials being restrained. Two wall

    restraint conditions are shown. Active earth pressure is commonly used for design of

    free-standing cantilever retaining walls and assumes wall movement. The "at-rest" condition

    assumes no wall movement. The recommended design lateral earth pressures do not include a

    factor of safety and do not provide for possible hydrostatic pressure on the walls.

    EARTH PRESSURE COEFFICIENTS

    Earth Pressure Conditions

    Coefficient for Backfill Type

    Equivalent Fluid Density (pcf)

    Surcharge Pressure,

    p1 (psf)

    Earth Pressure,

    p2 (psf)

    Active (Ka) Granular soil/fill - 0.27

    Lean Clay - 0.41

    35

    49

    (0.27)S

    (0.41)S

    (35)H

    (49)H

    At-Rest (Ko) Granular soil/fill - 0.43

    Lean Clay - 0.58

    56

    70

    (0.46)S

    (0.58)S

    (55)H

    (70)H

    Passive (Kp) Granular soil/fill - 3.69

    Lean Clay - 2.46

    480

    295

    ---

    ---

    ---

    ---

    Applicable conditions to the above include:

    For active earth pressure, wall must rotate about base, with top lateral movements of about

    0.002 H to 0.004 H, where H is wall height;

    For passive earth pressure to develop, wall must move horizontally to mobilize resistance;

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable 14

    Uniform surcharge, where S is surcharge pressure;

    In-situ soil backfill weight a maximum of 120 pcf;

    Horizontal backfill, compacted between 95 and 98 percent of maximum dry unit weight as

    determined by ASTM D698;

    Loading from heavy compaction equipment not included;

    No hydrostatic pressures acting on wall;

    No dynamic loading;

    No safety factor included in soil parameters; and

    Ignore passive pressure in frost zone.

    To control hydrostatic pressure behind the wall we recommend that a drain be installed at the

    foundation wall with a collection pipe leading to a reliable discharge. If this is not possible, then

    combined hydrostatic and lateral earth pressures should be calculated for lean clay backfill

    using an equivalent fluid weighing 90 and 100 pcf for active and at-rest conditions, respectively.

    For granular backfill, an equivalent fluid weighing 85 and 90 pcf should be used for active and

    at-rest, respectively. These pressures do not include the influence of surcharge, equipment or

    floor loading, which should be added. Heavy equipment should not operate within a distance

    closer than the exposed height of retaining walls to prevent lateral pressures more than those

    provided.

    5.0 GENERAL COMMENTS

    Terracon should be retained to review the final design plans and specifications so comments

    can be made regarding interpretation and implementation of our geotechnical recommendations

    in the design and specifications. Terracon also should be retained to provide observation and

    testing services during grading, excavation, foundation construction and other earth-related

    construction phases of the project.

    The analysis and recommendations presented in this report are based upon the data obtained

    from the borings performed at the indicated locations and from other information discussed in

    this report. This report does not reflect variations that may occur between borings, across the

    site, or due to the modifying effects of construction or weather. The nature and extent of such

    variations may not become evident until during or after construction. If variations appear, we

    should be immediately notified so that further evaluation and supplemental recommendations

    can be provided.

    The scope of services for this project does not include either specifically or by implication any

    environmental or biological (e.g., mold, fungi, and bacteria) assessment of the site or

    identification or prevention of pollutants, hazardous materials or conditions. If the owner is

    concerned about the potential for such contamination or pollution, other studies should be

    undertaken.

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable 15

    This report has been prepared for the exclusive use of our client for specific application to the

    project discussed and has been prepared in accordance with generally accepted geotechnical

    engineering practices. No warranties, either express or implied, are intended or made. Site

    safety, excavation support, and dewatering requirements are the responsibility of others. In the

    event that changes in the nature, design, or location of the project as described in this report are

    planned, the conclusions and recommendations contained in this report shall not be considered

    valid unless Terracon reviews the changes and either verifies or modifies the conclusions of this

    report in writing.

  • APPENDIX A

    FIELD EXPLORATION

  • TOPOGRAPHIC MAP IMAGE COURTESY OF THE U.S. GEOLOGICAL SURVEY

    QUADRANGLES INCLUDE: CRYSTAL MOUNTAIN, CO (1/1/1980) and BUCKHORN

    MOUNTAIN, CO (1977).

    SITE LOCATION MAP

    CR 44H Structures Approx. 5 miles of CR 44H from Ballard Road east towards CR 27

    Larimer County, Colorado

    1901 Sharp Point Drive Suite C

    Ft. Collins, Colorado 80525

    20155038

    DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR CONSTRUCTION

    PURPOSES

    Project Manager:

    Drawn by:

    Checked by: Approved by:

    Project No.

    File Name: Date:

    A-1

    Exhibit

    1”=24,000 SF Scale:

    MRA

    EDB

    EDB

    BCR

    10/26/2015

  • EXPLORATION PLAN

    1901 Sharp Point Drive Suite C

    Ft. Collins, Colorado 80525

    20155038 AERIAL PHOTOGRAPHY PROVIDED BY MICROSOFT BING MAPS

    CR 44H Structures Approx. 5 miles of CR 44H from Ballard Road east towards CR 27

    Larimer County, Colorado DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR CONSTRUCTION

    PURPOSES

    Project Manager:

    Drawn by:

    Checked by: Approved by:

    MRA

    EDB

    EDB

    BCR

    10/26/2015

    Scale:

    Project No.

    File Name: Date:

    AS SHOWN A-2

    Exhibit

  • EXPLORATION PLAN

    1901 Sharp Point Drive Suite C

    Ft. Collins, Colorado 80525

    20155038 AERIAL PHOTOGRAPHY PROVIDED BY MICROSOFT BING MAPS

    CR 44H Structures Approx. 5 miles of CR 44H from Ballard Road east towards CR 27

    Larimer County, Colorado DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR CONSTRUCTION

    PURPOSES

    Project Manager:

    Drawn by:

    Checked by: Approved by:

    MRA

    EDB

    EDB

    BCR

    10/26/2015

    Scale:

    Project No.

    File Name: Date:

    AS SHOWN A-3

    Exhibit

    Structure 1

    Structure 2

    Structure 1

    Structure 3

    Structure 1

  • EXPLORATION PLAN

    1901 Sharp Point Drive Suite C

    Ft. Collins, Colorado 80525

    20155038 AERIAL PHOTOGRAPHY PROVIDED BY MICROSOFT BING MAPS

    CR 44H Structures Approx. 5 miles of CR 44H from Ballard Road east towards CR 27

    Larimer County, Colorado DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR CONSTRUCTION

    PURPOSES

    Project Manager:

    Drawn by:

    Checked by: Approved by:

    MRA

    EDB

    EDB

    BCR

    10/26/2015

    Scale:

    Project No.

    File Name: Date:

    AS SHOWN A-4

    Exhibit

    Structure 4

    Structure 1

    Structure 5

    Structure 1

  • EXPLORATION PLAN

    1901 Sharp Point Drive Suite C

    Ft. Collins, Colorado 80525

    20155038 AERIAL PHOTOGRAPHY PROVIDED BY MICROSOFT BING MAPS

    CR 44H Structures Approx. 5 miles of CR 44H from Ballard Road east towards CR 27

    Larimer County, Colorado DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR CONSTRUCTION

    PURPOSES

    Project Manager:

    Drawn by:

    Checked by: Approved by:

    MRA

    EDB

    EDB

    BCR

    10/26/2015

    Scale:

    Project No.

    File Name: Date:

    AS SHOWN A-5

    Exhibit

    Structure 6

    Structure 1

    Structure 7

    Structure 1

  • EXPLORATION PLAN

    1901 Sharp Point Drive Suite C

    Ft. Collins, Colorado 80525

    20155038 AERIAL PHOTOGRAPHY PROVIDED BY MICROSOFT BING MAPS

    CR 44H Structures Approx. 5 miles of CR 44H from Ballard Road east towards CR 27

    Larimer County, Colorado DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR CONSTRUCTION

    PURPOSES

    Project Manager:

    Drawn by:

    Checked by: Approved by:

    MRA

    EDB

    EDB

    BCR

    10/26/2015

    Scale:

    Project No.

    File Name: Date:

    AS SHOWN A-6

    Exhibit

    Structure 8

    Structure 4

    Structure 1 Structure 4

    Structure 1 Structure 1

    Structure 9

    Structure 4

    Structure 1 Structure 4

    Structure 1 Structure 1

  • EXPLORATION PLAN

    1901 Sharp Point Drive Suite C

    Ft. Collins, Colorado 80525

    20155038 AERIAL PHOTOGRAPHY PROVIDED BY MICROSOFT BING MAPS

    CR 44H Structures Approx. 5 miles of CR 44H from Ballard Road east towards CR 27

    Larimer County, Colorado DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR CONSTRUCTION

    PURPOSES

    Project Manager:

    Drawn by:

    Checked by: Approved by:

    MRA

    EDB

    EDB

    BCR

    10/26/2015

    Scale:

    Project No.

    File Name: Date:

    AS SHOWN A-7

    Exhibit

    Structure 10

    Structure 4

    Structure 1 Structure 4

    Structure 1 Structure 1

  • EXPLORATION PLAN

    1901 Sharp Point Drive Suite C

    Ft. Collins, Colorado 80525

    20155038 AERIAL PHOTOGRAPHY PROVIDED BY MICROSOFT BING MAPS

    CR 44H Structures Approx. 5 miles of CR 44H from Ballard Road east towards CR 27

    Larimer County, Colorado DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR CONSTRUCTION

    PURPOSES

    Project Manager:

    Drawn by:

    Checked by: Approved by:

    MRA

    EDB

    EDB

    BCR

    10/26/2015

    Scale:

    Project No.

    File Name: Date:

    AS SHOWN A-8

    Exhibit

    Structure 11

    Structure 4

    Structure 1 Structure 4

    Structure 1 Structure 1

  • EXPLORATION PLAN

    1901 Sharp Point Drive Suite C

    Ft. Collins, Colorado 80525

    20155038 AERIAL PHOTOGRAPHY PROVIDED BY MICROSOFT BING MAPS

    CR 44H Structures Approx. 5 miles of CR 44H from Ballard Road east towards CR 27

    Larimer County, Colorado DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR CONSTRUCTION

    PURPOSES

    Project Manager:

    Drawn by:

    Checked by: Approved by:

    MRA

    EDB

    EDB

    BCR

    10/26/2015

    Scale:

    Project No.

    File Name: Date:

    AS SHOWN A-9

    Exhibit

    Structure 12

    Structure 4

    Structure 1 Structure 4

    Structure 1 Structure 1

  • EXPLORATION PLAN

    1901 Sharp Point Drive Suite C

    Ft. Collins, Colorado 80525

    20155038 AERIAL PHOTOGRAPHY PROVIDED BY MICROSOFT BING MAPS

    CR 44H Structures Approx. 5 miles of CR 44H from Ballard Road east towards CR 27

    Larimer County, Colorado DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR CONSTRUCTION

    PURPOSES

    Project Manager:

    Drawn by:

    Checked by: Approved by:

    MRA

    EDB

    EDB

    BCR

    10/26/2015

    Scale:

    Project No.

    File Name: Date:

    AS SHOWN A-10

    Exhibit

    Structure 13

    Structure 4

    Structure 1 Structure 4

    Structure 1 Structure 1

    Structure 14

    Structure 4

    Structure 1 Structure 4

    Structure 1 Structure 1

  • EXPLORATION PLAN

    1901 Sharp Point Drive Suite C

    Ft. Collins, Colorado 80525

    20155038 AERIAL PHOTOGRAPHY PROVIDED BY MICROSOFT BING MAPS

    CR 44H Structures Approx. 5 miles of CR 44H from Ballard Road east towards CR 27

    Larimer County, Colorado DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR CONSTRUCTION

    PURPOSES

    Project Manager:

    Drawn by:

    Checked by: Approved by:

    MRA

    EDB

    EDB

    BCR

    10/26/2015

    Scale:

    Project No.

    File Name: Date:

    AS SHOWN A-11

    Exhibit

    Structure 15

    Structure 4

    Structure 1 Structure 4

    Structure 1 Structure 1

  • EXPLORATION PLAN

    1901 Sharp Point Drive Suite C

    Ft. Collins, Colorado 80525

    20155038 AERIAL PHOTOGRAPHY PROVIDED BY MICROSOFT BING MAPS

    CR 44H Structures Approx. 5 miles of CR 44H from Ballard Road east towards CR 27

    Larimer County, Colorado DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR CONSTRUCTION

    PURPOSES

    Project Manager:

    Drawn by:

    Checked by: Approved by:

    MRA

    EDB

    EDB

    BCR

    10/26/2015

    Scale:

    Project No.

    File Name: Date:

    AS SHOWN A-12

    Exhibit

    Structure 16

    Structure 4

    Structure 1 Structure 4

    Structure 1 Structure 1

  • EXPLORATION PLAN

    1901 Sharp Point Drive Suite C

    Ft. Collins, Colorado 80525

    20155038 AERIAL PHOTOGRAPHY PROVIDED BY MICROSOFT BING MAPS

    CR 44H Structures Approx. 5 miles of CR 44H from Ballard Road east towards CR 27

    Larimer County, Colorado DIAGRAM IS FOR GENERAL LOCATION ONLY, AND IS NOT INTENDED FOR CONSTRUCTION

    PURPOSES

    Project Manager:

    Drawn by:

    Checked by: Approved by:

    MRA

    EDB

    EDB

    BCR

    10/26/2015

    Scale:

    Project No.

    File Name: Date:

    AS SHOWN A-13

    Exhibit

    Structure 17

    Structure 4

    Structure 1 Structure 4

    Structure 1 Structure 1

  • Geotechnical Engineering Report CR 44H Structures ■ Larimer County, Colorado November 6, 2015 ■ Terracon Project No. 20155038

    Responsive ■ Resourceful ■ Reliable Exhibit A-14

    Field Exploration Description

    The locations of borings were based upon the location of proposed structures provided by the

    Client. Elevation of the ground surface for Boring Nos. 1 through 22 were interpolated from

    topographic maps provided to us by the Client. The borings were located in the field by

    measuring from existing site features.

    The borings were drilled with a CME-75 truck-mounted rotary drill rig with solid-stem augers.

    During the drilling operations, lithologic logs of the borings were recorded by the field engineer.

    Disturbed samples were obtained at selected intervals utilizing a 2-inch outside diameter split-

    spoon sampler. Penetration resistance values were recorded in a manner similar to the

    standard penetration test (SPT). This test consists of driving the sampler into the ground with a

    140-pound hammer free-falling through a distance of 30 inches. The number of blows required

    to advance the standard split-spoon 18 inches (final 12 inches are recorded) or the interval

    indicated, is recorded as a standard penetration resistance value (N-value). The blow count

    values are indicated on the boring logs at the respective sample depths.

    A CME automatic SPT hammer was used to advance the samplers in the borings performed on

    this site. A greater efficiency is typically achieved with the automatic hammer compared to the

    conventional safety hammer operated with a cathead and rope. Published correlations between

    the SPT values and soil properties are based on the lower efficiency cathead and rope method.

    This higher efficiency affects the standard penetration resistance blow count value by increasing

    the penetration per hammer blow over what would be obtained using the cathead and rope

    method. The effect of the automatic hammer's efficiency has been considered in the interpretation

    and analysis of the subsurface information for this report.

    The standard penetration test provides a reasonable indication of the in-place density of sandy

    type materials, but only provides an indication of the relative stiffness of cohesive materials

    since the blow count in these soils may be affected by the moisture content of the soil. In

    addition, considerable care should be exercised in interpreting the N-values in gravelly soils,

    particularly where the size of the gravel particle exceeds the inside diameter of the sampler.

    Groundwater measurements were obtained in the borings at the time of site exploration. After

    completion of drilling, the borings were backfilled with auger cuttings. Some settlement of the

    backfill and/or patch may occur and should be repaired as soon as possible.

  • 12

    10

    13

    8

    14

    17

    NP

    8025.5

    80058004.5

    7-6-5N=11

    4-4-5N=9

    17-15-19N=34

    10-7-11N=18

    22-50/6"

    0.5

    21.021.5

    GRAVEL SURFACING, about 6 inchesSILTY SAND WITH GRAVEL (SM), trace cobbles, fine to coarse grained, grayto brown, loose to very dense

    BEDROCK, very hardBoring Terminated at 21.5 Feet

    Hammer Type: AutomaticStratification lines are approximate. In-situ, the transition may be gradual.

    GR

    AP

    HIC

    LO

    G

    TH

    IS B

    OR

    ING

    LO

    G IS

    NO

    T V

    ALI

    D IF

    SE

    PA

    RA

    TE

    D F

    RO

    M O

    RIG

    INA

    L R

    EP

    OR

    T.

    GE

    O S

    MA

    RT

    LO

    G-N

    O W

    ELL

    201

    550

    38.G

    PJ

    TE

    RR

    AC

    ON

    2015

    .GD

    T 1

    1/5

    /15

    Approx. 5 miles on CR44H from Ballard Road east toward CR 27 Larimer County, ColoradoSITE:

    Page 1 of 1

    Advancement Method:4-inch solid flight auger

    Abandonment Method:Borings backfilled with soil cuttings upon completion.

    1901 Sharp Point Drive, Suite CFort Collins, Colorado

    Notes:

    Project No.: 20155038

    Drill Rig: CME-75

    Boring Started: 8/19/2015

    BORING LOG NO. 1AVI PCCLIENT:Fort Collins, CO

    Driller: Drilling Engineers, Inc.

    Boring Completed: 8/19/2015

    Exhibit: A-15

    See Exhibit A-3 for description of field procedures.

    See Appendix B for description of laboratoryprocedures and additional data (if any).

    See Appendix C for explanation of symbols andabbreviations.

    PROJECT: CR44H Structures

    PE

    RC

    EN

    T F

    INE

    S

    WA

    TE

    RC

    ON

    TE

    NT

    (%

    )

    ATTERBERGLIMITS

    LL-PL-PISurface Elev.: 8026 (Ft.)

    ELEVATION (Ft.)

    SA

    MP

    LE T

    YP

    E

    WA

    TE

    R L

    EV

    EL

    OB

    SE

    RV

    AT

    ION

    S

    DE

    PT

    H (

    Ft.)

    5

    10

    15

    20

    FIE

    LD T

    ES

    TR

    ES

    ULT

    S

    DEPTH

    LOCATION See Exhibit A-2

    Latitude: 40.572055° Longitude: -105.451864°

    While drilling

    WATER LEVEL OBSERVATIONS

  • 11

    14

    9

    13

    15

    8024.5

    8016

    8005.58005

    4-3-4N=7

    3-3-3N=6

    9-12-21N=33

    14-14-9N=23

    50/5"

    0.3

    9.0

    19.520.0

    GRAVEL SURFACING, about 4 inchesFILL - SILTY SAND WITH GRAVEL , trace cobbles and boulders, dark brown,loose

    SILTY SAND, trace gravel and cobbles, fine grained, gray to brown, mediumdense to very dense

    large cobble

    BEDROCK, very hardBoring Terminated at 20 Feet

    Hammer Type: AutomaticStratification lines are approximate. In-situ, the transition may be gradual.

    GR

    AP

    HIC

    LO

    G

    TH

    IS B

    OR

    ING

    LO

    G IS

    NO

    T V

    ALI

    D IF

    SE

    PA

    RA

    TE

    D F

    RO

    M O

    RIG

    INA

    L R

    EP

    OR

    T.

    GE

    O S

    MA

    RT

    LO

    G-N

    O W

    ELL

    201

    550

    38.G

    PJ

    TE

    RR

    AC

    ON

    2015

    .GD

    T 1

    1/5

    /15

    Approx. 5 miles on CR44H from Ballard Road east toward CR 27 Larimer County, ColoradoSITE:

    Page 1 of 1

    Advancement Method:4-inch solid flight auger

    Abandonment Method:Borings backfilled with soil cuttings upon completion.

    1901 Sharp Point Drive, Suite CFort Collins, Colorado

    Notes:

    Project No.: 20155038

    Drill Rig: CME-75

    Boring Started: 8/19/2015

    BORING LOG NO. 2AVI PCCLIENT:Fort Collins, CO

    Driller: Drilling Engineers, Inc.

    Boring Completed: 8/19/2015

    Exhibit: A-16

    See Exhibit A-3 for description of field procedures.

    See Appendix B for description of laboratoryprocedures and additional data (if any).

    See Appendix C for explanation of symbols andabbreviations.

    PROJECT: CR44H Structures

    PE

    RC

    EN

    T F

    INE

    S

    WA

    TE

    RC

    ON

    TE

    NT

    (%

    )

    ATTERBERGLIMITS

    LL-PL-PISurface Elev.: 8025 (Ft.)

    ELEVATION (Ft.)

    SA

    MP

    LE T

    YP

    E

    WA

    TE

    R L

    EV

    EL

    OB

    SE

    RV

    AT

    ION

    S

    DE

    PT

    H (

    Ft.)

    5

    10

    15

    20

    FIE

    LD T

    ES

    TR

    ES

    ULT

    S

    DEPTH

    LOCATION See Exhibit A-2

    Latitude: 40.572025° Longitude: -105.45172°

    While drilling

    WATER LEVEL OBSERVATIONS

  • 8

    19

    39

    7

    4

    11

    NP

    8012

    8005

    7993

    7989.5

    3-2-1N=3

    1-6-7N=13

    14-9-10N=19

    19-38-12N=50

    50/6"

    0.2

    7.0

    19.0

    22.5

    GRAVEL SURFACING, about 2 inchesPOORLY GRADED SAND WITH SILT (SP-SM), trace cobbles, brown, blackand gray, very loose to medium dense

    SILTY SAND WITH GRAVEL, trace cobbles and boulders, fine to mediumgrained, gray and olive, medium dense to very dense

    SCHIST BEDROCK, gray to olive, very hard, slightly weathered

    Auger refusal at 22.5 Feet

    Hammer Type: AutomaticStratification lines are approximate. In-situ, the transition may be gradual.

    GR

    AP

    HIC

    LO

    G

    TH

    IS B

    OR

    ING

    LO

    G IS

    NO

    T V

    ALI

    D IF

    SE

    PA

    RA

    TE

    D F

    RO

    M O

    RIG

    INA

    L R

    EP

    OR

    T.

    GE

    O S

    MA

    RT

    LO

    G-N

    O W

    ELL

    201

    550

    38.G

    PJ

    TE

    RR

    AC

    ON

    2015

    .GD

    T 1

    1/5

    /15

    Approx. 5 miles on CR44H from Ballard Road east toward CR 27 Larimer County, ColoradoSITE:

    Page 1 of 1

    Advancement Method:4-inch solid flight auger

    Abandonment Method:Borings backfilled with soil cuttings upon completion.

    1901 Sharp Point Drive, Suite CFort Collins, Colorado

    Notes:

    Project No.: 20155038

    Drill Rig: CME-75

    Boring Started: 8/19/2015

    BORING LOG NO. 3AVI PCCLIENT:Fort Collins, CO

    Driller: Drilling Engineers, Inc.

    Boring Completed: 8/19/2015

    Exhibit: A-17

    See Exhibit A-3 for description of field procedures.

    See Appendix B for description of laboratoryprocedures and additional data (if any).

    See Appendix C for explanation of symbols andabbreviations.

    PROJECT: CR44H Structures

    PE

    RC

    EN

    T F

    INE

    S

    WA

    TE

    RC

    ON

    TE

    NT

    (%

    )

    ATTERBERGLIMITS

    LL-PL-PISurface Elev.: 8012 (Ft.)

    ELEVATION (Ft.)

    SA

    MP

    LE T

    YP

    E

    WA

    TE

    R L

    EV

    EL

    OB

    SE

    RV

    AT

    ION

    S

    DE

    PT

    H (

    Ft.)

    5

    10

    15

    20

    FIE

    LD T

    ES

    TR

    ES

    ULT

    S

    DEPTH

    LOCATION See Exhibit A-2

    Latitude: 40.571651° Longitude: -105.450682°

    While drilling

    WATER LEVEL OBSERVATIONS

  • 0

    11

    12

    9

    9

    5

    8009.5

    8002

    7999

    7991.5

    7990.5

    4-3-3N=6

    3-4-5N=9

    16-25-40N=65

    10-16-17N=33

    50/4"

    0.3

    8.0

    11.0

    18.5

    19.3

    GRAVEL SURFACING, about 3 inchesSILTY SAND WITH GRAVEL, trace cobbles, fine grained, dark brown, loose

    POORLY GRADED SAND WITH GRAVEL, coarse grained, yellow, very dense

    SILTY SAND WITH GRAVEL, fine grained, dark brown, dense

    BEDROCK, gray, very hard

    Boring Terminated at 19.3 Feet

    Hammer Type: AutomaticStratification lines are approximate. In-situ, the transition may be gradual.

    GR

    AP

    HIC

    LO

    G

    TH

    IS B

    OR

    ING

    LO

    G IS

    NO

    T V

    ALI

    D IF

    SE

    PA

    RA

    TE

    D F

    RO

    M O

    RIG

    INA

    L R

    EP

    OR

    T.

    GE

    O S

    MA

    RT

    LO

    G-N

    O W

    ELL

    201

    550

    38.G

    PJ

    TE

    RR

    AC

    ON

    2015

    .GD

    T 1

    1/5

    /15

    Approx. 5 miles on CR44H from Ballard Road east toward CR 27 Larimer County, ColoradoSITE:

    Page 1 of 1

    Advancement Method:4-inch solid flight auger

    Abandonment Method:Borings backfilled with soil cuttings upon completion.

    1901 Sharp Point Drive, Suite CFort Collins, Colorado

    Notes:

    Project No.: 20155038

    Drill Rig: CME-75

    Boring Started: 8/19/2015

    BORING LOG NO. 4AVI PCCLIENT:Fort Collins, CO

    Driller: Drilling Engineers, Inc.

    Boring Completed: 8/19/2015

    Exhibit: A-18

    See Exhibit A-3 for description of field procedures.

    See Appendix B for description of laboratoryprocedures and additional data (if any).

    See Appendix C for explanation of symbols andabbreviations.

    PROJECT: CR44H Structures

    PE

    RC

    EN

    T F

    INE

    S

    WA

    TE

    RC

    ON

    TE

    NT

    (%

    )

    ATTERBERGLIMITS

    LL-PL-PISurface Elev.: 8010 (Ft.)

    ELEVATION (Ft.)

    SA

    MP

    LE T

    YP

    E

    WA

    TE

    R L

    EV

    EL

    OB

    SE

    RV

    AT

    ION

    S

    DE

    PT

    H (

    Ft.)

    5

    10

    15

    FIE

    LD T

    ES

    TR

    ES

    ULT

    S

    DEPTH

    LOCATION See Exhibit A-2

    Latitude: 40.571577° Longitude: -105.45061°

    While drilling

    WATER LEVEL OBSERVATIONS

  • 16

    18

    28

    7

    NP

    7991

    7990

    4-4-2N=6

    1-2-3N=5

    19-17-16N=33

    11.0

    12.0

    SILTY SAND, trace gravel, fine grained, brown to black

    with cobbles, loose to dense

    BEDROCK, very hard

    Auger refusal at 12 Feet

    Hammer Type: AutomaticStratification lines are approximate. In-situ, the transition may be gradual.

    GR

    AP

    HIC

    LO

    G

    TH

    IS B

    OR

    ING

    LO

    G IS

    NO

    T V

    ALI

    D IF

    SE

    PA

    RA

    TE

    D F

    RO

    M O

    RIG

    INA

    L R

    EP

    OR

    T.

    GE

    O S

    MA

    RT

    LO

    G-N

    O W

    ELL

    201

    550

    38.G

    PJ

    TE

    RR

    AC

    ON

    2015

    .GD

    T 1

    1/5

    /15

    Approx. 5 miles on CR44H from Ballard Road east toward CR 27 Larimer County, ColoradoSITE:

    Page 1 of 1

    Advancement Method:4-inch solid flight auger

    Abandonment Method:Borings backfilled with soil cuttings upon completion.

    1901 Sharp Point Drive, Suite CFort Collins, Colorado

    Notes:

    Project No.: 20155038

    Drill Rig: CME-75

    Boring Started: 8/19/2015

    BORING LOG NO. 5AVI PCCLIENT:Fort Collins, CO

    Driller: Drilling Engineers, Inc.

    Boring Completed: 8/19/2015

    Exhibit: A-19

    See Exhibit A-3 for description of field procedures.

    See Appendix B for description of laboratoryprocedures and additional data (if any).

    See Appendix C for explanation of symbols andabbreviations.

    PROJECT: CR44H Structures

    PE

    RC

    EN

    T F

    INE

    S

    WA

    TE

    RC

    ON

    TE

    NT

    (%

    )

    ATTERBERGLIMITS

    LL-PL-PISurface Elev.: 8002 (Ft.)

    ELEVATION (Ft.)

    SA

    MP

    LE T

    YP

    E

    WA

    TE

    R L

    EV

    EL

    OB

    SE

    RV

    AT

    ION

    S

    DE

    PT

    H (

    Ft.)

    5

    10

    FIE

    LD T

    ES

    TR

    ES

    ULT

    S

    DEPTH

    LOCATION See Exhibit A-2

    Latitude: 40.571452° Longitude: -105.449521°

    While drilling

    WATER LEVEL OBSERVATIONS

  • 10

    13

    6

    7989

    7988

    5-6-4N=10

    5-3-3N=6

    12-32-23N=55

    12.0

    13.0

    SILTY SAND WITH GRAVEL, olive to dark brown

    trace cobbles, loose to very dense

    BEDROCK, very hard

    Auger refusal at 13 Feet

    Hammer Type: AutomaticStratification lines are approximate. In-situ, the transition may be gradual.

    GR

    AP

    HIC

    LO

    G

    TH

    IS B

    OR

    ING

    LO

    G IS

    NO

    T V

    ALI

    D IF

    SE

    PA

    RA

    TE

    D F

    RO

    M O

    RIG

    INA

    L R

    EP

    OR

    T.

    GE

    O S

    MA

    RT

    LO

    G-N

    O W

    ELL

    201

    550

    38.G

    PJ

    TE

    RR

    AC

    ON

    2015

    .GD

    T 1

    1/5

    /15

    Approx. 5 miles on CR44H from Ballard Road east toward CR 27 Larimer County, ColoradoSITE:

    Page 1 of 1

    Advancement Method:4-inch solid flight auger

    Abandonment Method:Borings backfilled with soil cuttings upon completion.

    1901 Sharp Point Drive, Suite CFort Collins, Colorado

    Notes:

    Project No.: 20155038

    Drill Rig: CME-75

    Boring Started: 8/19/2015

    BORING LOG NO. 6AVI PCCLIENT:Fort Collins, CO

    Driller: Drilling Engineers, Inc.

    Boring Completed: 8/19/2015

    Exhibit: A-20

    See Exhibit A-3 for description of field procedures.

    See Appendix B for description of laboratoryprocedures and additional data (if any).

    See Appendix C for explanation of symbols andabbreviations.

    PROJECT: CR44H Structures

    PE

    RC

    EN

    T F

    INE

    S

    WA

    TE

    RC

    ON

    TE

    NT

    (%

    )

    ATTERBERGLIMITS

    LL-PL-PISurface Elev.: 8001 (Ft.)

    ELEVATION (Ft.)

    SA

    MP

    LE T

    YP

    E

    WA

    TE

    R L

    EV

    EL

    OB

    SE

    RV

    AT

    ION

    S

    DE

    PT

    H (

    Ft.)

    5

    10

    FIE

    LD T

    ES

    TR

    ES

    ULT

    S

    DEPTH

    LOCATION See Exhibit A-2

    Latitude: 40.57141° Longitude: -105.449399°

    While drilling

    WATER LEVEL OBSERVATIONS

  • 5

    0

    18

    14

    8

    7925.5

    7924.5

    8-10-14N=24

    4-24-45N=69

    7-13-28N=41

    10-12-13N=25

    50/6"

    18.5

    19.5

    SILTY SAND WITH GRAVEL, trace cobbles and boulders, fine to mediumgrained, brown, medium dense to very dense

    SCHIST BEDROCK, gray, very hard

    Boring Terminated at 19.5 Feet

    Hammer Type: AutomaticStratification lines are approximate. In-situ, the transition may be gradual.

    GR

    AP

    HIC

    LO

    G

    TH

    IS B

    OR

    ING

    LO

    G IS

    NO

    T V

    ALI

    D IF

    SE

    PA

    RA

    TE

    D F

    RO

    M O

    RIG

    INA

    L R

    EP

    OR

    T.

    GE

    O S

    MA

    RT

    LO

    G-N

    O W

    ELL

    201

    550

    38.G

    PJ

    TE

    RR

    AC

    ON

    2015

    .GD

    T 1

    1/5

    /15

    Approx. 5 miles on CR44H from Ballard Road east toward CR 27 Larimer County, ColoradoSITE:

    Page 1 of 1

    Advancement Method:4-inch solid flight auger

    Abandonment Method:Borings backfilled with soil cuttings upon completion.

    1901 Sharp Point Drive, Suite CFort Collins, Colorado

    Notes:

    Project No.: 20155038

    Drill Rig: CME-75

    Boring Started: 8/19/2015

    BORING LOG NO. 7AVI PCCLIENT:Fort Collins, CO

    Driller: Drilling Engineers, Inc.

    Boring Completed: 8/19/2015

    Exhibit: A-21

    See Exhibit A-3 for description of field procedures.

    See Appendix B for description of laboratoryprocedures and additional data (if any).

    See Appendix C for explanation of symbols andabbreviations.

    PROJECT: CR44H Structures

    PE

    RC

    EN

    T F

    INE

    S

    WA

    TE

    RC

    ON

    TE

    NT

    (%

    )

    ATTERBERGLIMITS

    LL-PL-PISurface Elev.: 7944 (Ft.)

    ELEVATION (Ft.)

    SA

    MP

    LE T

    YP

    E

    WA

    TE

    R L

    EV

    EL

    OB

    SE

    RV

    AT

    ION

    S

    DE

    PT

    H (

    Ft.)

    5

    10

    15

    FIE

    LD T

    ES

    TR

    ES

    ULT

    S

    DEPTH

    LOCATION See Exhibit A-2

    Latitude: 40.572955° Longitude: -105.443517°

    While drilling

    WATER LEVEL OBSERVATIONS

  • 7

    38

    16 NP

    7942.5

    7937

    7936

    5-9-5N=14

    3-5-6N=11

    0.4

    6.0

    7.0

    GRAVEL SURFACING, about 5 inchesPOORLY GRADED SAND WITH SILT AND GRAVEL (SP-SM), with cobblesand boulders, black, brown and reddish-brown, medium dense

    BEDROCK, very hard

    Auger refusal at 7 Feet

    Hammer Type: AutomaticStratification lines are approximate. In-situ, the transition may be gradual.

    GR

    AP

    HIC

    LO

    G

    TH

    IS B

    OR

    ING

    LO

    G IS

    NO

    T V

    ALI

    D IF

    SE

    PA

    RA

    TE

    D F

    RO

    M O

    RIG

    INA

    L R

    EP

    OR

    T.

    GE

    O S

    MA

    RT

    LO

    G-N

    O W

    ELL

    201

    550

    38.G

    PJ

    TE

    RR

    AC

    ON

    2015

    .GD

    T 1

    1/5

    /15

    Approx. 5 miles on CR44H from Ballard Road east toward CR 27 Larimer County, ColoradoSITE:

    Page 1 of 1

    Advancement Method:4-inch solid flight auger

    Abandonment Method:Borings backfilled with soil cuttings upon completion.

    1901 Sharp Point Drive, Suite CFort Collins, Colorado

    Notes:

    Project No.: 20155038

    Drill Rig: CME-75

    Boring Started: 8/19/2015

    BORING LOG NO. 8AVI PCCLIENT:Fort Collins, CO

    Driller: Drilling Engineers, Inc.

    Boring Completed: 8/19/2015

    Exhibit: A-22

    See Exhibit A-3 for description of field procedures.

    See Appendix B for description of laboratoryprocedures and additional data (if any).

    See Appendix C for explanation of symbols andabbreviations.

    PROJECT: CR44H Structures

    PE

    RC

    EN

    T F

    INE

    S

    WA

    TE

    RC

    ON

    TE

    NT

    (%

    )

    ATTERBERGLIMITS

    LL-PL-PISurface Elev.: 7943 (Ft.)

    ELEVATION (Ft.)

    SA

    MP

    LE T

    YP

    E

    WA

    TE

    R L

    EV

    EL

    OB

    SE

    RV

    AT

    ION

    S

    DE

    PT

    H (

    Ft.)

    5

    FIE

    LD T

    ES

    TR

    ES

    ULT

    S

    DEPTH

    LOCATION See Exhibit A-2

    Latitude: 40.573001° Longitude: -105.44342°

    While drilling

    WATER LEVEL OBSERVATIONS

  • 3

    8

    13

    8

    0

    NP

    7991.5

    7984

    79757974.5

    7-12-11N=23

    5-6-7N=13

    23-21-21N=42

    50/1"

    0.7

    8.0

    17.017.5

    GRAVEL SURFACING, about 8 inches

    SILTY SAND WITH GRAVEL, trace cobbles, fine grained, brown to gray,medium dense

    POORLY GRADED GRAVEL WITH SAND, trace cobbles, fine to coarsegrained, brown, gray and black, dense to very dense

    BEDROCK, very hardAuger refusal at 17.5 Feet

    Hammer Type: AutomaticStratification lines are approximate. In-situ, the transition may be gradual.

    GR

    AP

    HIC

    LO

    G

    TH

    IS B

    OR

    ING

    LO

    G IS

    NO

    T V

    ALI

    D IF

    SE

    PA

    RA

    TE

    D F

    RO

    M O

    RIG

    INA

    L R

    EP

    OR

    T.

    GE

    O S

    MA

    RT

    LO

    G-N

    O W

    ELL

    201

    550

    38.G

    PJ

    TE

    RR

    AC

    ON

    2015

    .GD

    T 1

    1/5

    /15

    Approx. 5 miles on CR44H from Ballard Road east toward CR 27 Larimer County, ColoradoSITE:

    Page 1 of 1

    Advancement Method:4-inch solid flight auger

    Abandonment Method:Borings backfilled with soil cuttings upon completion.

    1901 Sharp Point Drive, Suite CFort Collins, Colorado

    Notes:

    Project No.: 20155038

    Drill Rig: CME-75

    Boring Started: 8/19/2015

    BORING LOG NO. 9AVI PCCLIENT:Fort Collins, CO

    Driller: Drilling Engineers, Inc.

    Boring Completed: 8/19/2015

    Exhibit: A-23

    See Exhibit A-3 for description of field procedures.

    See Appendix B for description of laboratoryprocedures and additional data (if any).

    See Appendix C for explanation of symbols andabbreviations.

    PROJECT: CR44H Structures

    PE

    RC

    EN

    T F

    INE

    S

    WA

    TE

    RC

    ON

    TE

    NT

    (%

    )

    ATTERBERGLIMITS

    LL-PL-PISurface Elev.: 7992 (Ft.)

    ELEVATION (Ft.)

    SA

    MP

    LE T

    YP

    E

    WA

    TE

    R L

    EV

    EL

    OB

    SE

    RV

    AT

    ION

    S

    DE

    PT

    H (

    Ft.)

    5

    10

    15

    FIE

    LD T

    ES

    TR

    ES

    ULT

    S

    DEPTH

    LOCATION See Exhibit A-2

    Latitude: 40.574997° Longitude: -105.442395°

    While drilling

    WATER LEVEL OBSERVATIONS

  • 11

    10

    10

    15

    10

    NP

    7991

    79777976.5

    4-5-2N=7

    2-1-1N=2

    5-7-19N=26

    29-37-33N=70

    1.0

    15.015.5

    GRAVEL SURFACING, about 12 inches

    POORLY GRADED SAND WITH SILT AND GRAVEL, trace cobbles andboulders, fine to coarse grained, dark brown, very loose to medium dense

    SCHIST BEDROCK, black and gray, hardBoring Terminated at 15.5 Feet

    Hammer Type: AutomaticStratification lines are approximate. In-situ, the transition may be gradual.

    GR

    AP

    HIC

    LO

    G

    TH

    IS B

    OR

    ING

    LO

    G IS

    NO

    T V

    ALI

    D IF

    SE

    PA

    RA

    TE

    D F

    RO

    M O

    RIG

    INA

    L R

    EP

    OR

    T.

    GE

    O S

    MA

    RT

    LO

    G-N

    O W

    ELL

    201

    550

    38.G

    PJ

    TE

    RR

    AC

    ON

    2015

    .GD

    T 1

    1/5

    /15

    Approx. 5 miles on CR44H from Ballard Road east toward CR 27 Larimer County, ColoradoSITE:

    Page 1 of 1

    Advancement Method:4-inch solid flight auger

    Abandonment Method:Borings backfilled with soil cuttings upon completion.

    1901 Sharp Point Drive, Suite CFort Collins, Colorado

    Notes:

    Project No.: 20155038

    Drill Rig: CME-75

    Boring Started: 8/19/2015

    BORING LOG NO. 10AVI PCCLIENT:Fort Collins, CO

    Driller: Drilling Engineers, Inc.

    Boring Completed: 8/19/2015

    Exhibit: A-24

    See Exhibit A-3 for description of field procedures.

    See Appendix B for description of laboratoryprocedures and additional data (if any).

    See Appendix C for explanation of symbols andabbreviations.

    PROJECT: CR44H Structures

    PE

    RC

    EN

    T F

    INE

    S

    WA

    TE

    RC

    ON

    TE

    NT

    (%

    )

    ATTERBERGLIMITS

    LL-PL-PISurface Elev.: 7992 (Ft.)

    ELEVATION (Ft.)

    SA

    MP

    LE T

    YP

    E

    WA

    TE

    R L

    EV

    EL

    OB

    SE

    RV

    AT

    ION

    S

    DE

    PT

    H (

    Ft.)

    5

    10

    15

    FIE

    LD T

    ES

    TR

    ES

    ULT

    S

    DEPTH

    LOCATION See Exhibit A-2

    Latitude: 40.575048° Longitude: -105.442305°

    While drilling

    WATER LEVEL OBSERVATIONS

  • 1

    8

    7

    9 NP

    7667

    7659

    7654.57654

    5-7-7N=14

    4-4-2N=6

    10-10-9N=19

    1.0

    9.0

    13.514.0

    GRAVEL SURFACING, about 12 inches

    FILL - SILTY SAND WITH GRAVEL , trace cobbles, gray to brown, loose tomedium dense

    POORLY GRADED GRAVEL WITH SAND (GP), with cobbles, olive and black,medium dense

    BEDROCK, very hardAuger refusal at 14 Feet

    Hammer Type: AutomaticStratification lines are approximate. In-situ, the transition may be gradual.

    GR

    AP

    HIC

    LO

    G

    TH

    IS B

    OR

    ING

    LO

    G IS

    NO

    T V

    ALI

    D IF

    SE

    PA

    RA

    TE

    D F

    RO

    M O

    RIG

    INA

    L R

    EP

    OR

    T.

    GE

    O S

    MA

    RT

    LO

    G-N

    O W

    ELL

    201

    550

    38.G

    PJ

    TE

    RR

    AC

    ON

    2015

    .GD

    T 1

    1/5

    /15

    Approx. 5 miles on CR44H from Ballard Road east toward CR 27 Larimer County, ColoradoSITE:

    Page 1 of 1

    Advancement Method:4-inch solid flight auger

    Abandonment Method:Borings backfilled with soil cuttings upon completion.

    1901 Sharp Point Drive, Suite CFort Collins, Colorado

    Notes:

    Project No.: 20155038

    Drill Rig: CME-75

    Boring Started: 8/19/2015

    BORING LOG NO. 11AVI PCCLIENT:Fort Collins, CO

    Driller: Drilling Engineers, Inc.

    Boring Completed: 8/19/2015

    Exhibit: A-25

    See Exhibit A-3 for description of field procedures.

    See Appendix B for description of laboratoryprocedures and additional data (if any).

    See Appendix C for explanation of symbols andabbreviations.

    PROJECT: CR44H Structures

    PE

    RC

    EN

    T F

    INE

    S

    WA

    TE

    RC

    ON

    TE

    NT

    (%

    )

    ATTERBERGLIMITS

    LL-PL-PISurface Elev.: 7668 (Ft.)

    ELEVATION (Ft.)

    SA

    MP

    LE T

    YP

    E

    WA

    TE

    R L

    EV

    EL

    OB

    SE

    RV

    AT

    ION

    S

    DE

    PT

    H (

    Ft.)

    5

    10

    FIE

    LD T

    ES

    TR

    ES

    ULT

    S

    DEPTH

    LOCATION See Exhibit A-2

    Latitude: 40.569185° Longitude: -105.428371°

    While drilling

    WATER LEVEL OBSERVATIONS

  • 4017

    8

    36-19-17

    7664.5

    7661

    7659.57659

    2-2-2N=4

    4-3-4N=7

    1.5

    5.2

    6.57.0

    GRAVEL SURFACING, about 18 inches

    FILL - CLAYEY GRAVEL WITH SAND (GC), brown, loose

    SILTY SAND WITH GRAVEL, fine to medium grained, reddish-brown

    BEDROCK, very hardAuger refusal at 7 Feet

    Hammer Type: AutomaticStratification lines are approximate. In-situ, the transition may be gradual.

    GR

    AP

    HIC

    LO

    G

    TH

    IS B

    OR

    ING

    LO

    G IS

    NO

    T V

    ALI

    D IF

    SE

    PA

    RA

    TE

    D F

    RO

    M O

    RIG

    INA

    L R

    EP

    OR

    T.

    GE

    O S

    MA

    RT

    LO

    G-N

    O W

    ELL

    201

    550

    38.G

    PJ

    TE

    RR

    AC

    ON

    2015

    .GD

    T 1

    1/5

    /15

    Approx. 5 miles on CR44H from Ballard Road east toward CR 27 Larimer County, ColoradoSITE:

    Page 1 of 1

    Advancement Method:4-inch solid flight auger

    Abandonment Method:Borings backfilled with soil cuttings upon completion.

    1901 Sharp Point Drive, Suite CFort Collins, Colorado

    Notes:

    Project No.: 20155038

    Drill Rig: CME-75

    Boring Started: 8/19/2015

    BORING LOG NO. 12AVI PCCLIENT:Fort Collins, CO

    Driller: Drilling Engineers, Inc.

    Boring Completed: 8/19/2015

    Exhibit: A-26

    See Exhibit A-3 for description of field procedures.

    See Appendix B for description of laboratoryprocedures and additional data (if any).

    See Appendix C for explanation of symbols andabbreviations.

    PROJECT: CR44H Structures

    PE

    RC

    EN

    T F

    INE

    S

    WA

    TE

    RC

    ON

    TE

    NT

    (%

    )

    ATTERBERGLIMITS

    LL-PL-PISurface Elev.: 7666 (Ft.)

    ELEVATION (Ft.)

    SA

    MP

    LE T

    YP

    E

    WA

    TE

    R L

    EV

    EL

    OB

    SE

    RV

    AT

    ION

    S

    DE

    PT

    H (

    Ft.)

    5

    FIE

    LD T

    ES

    TR

    ES

    ULT

    S