franklin electronics
DESCRIPTION
Frankilin Electronics Case on Risk Management and Cost ControlTRANSCRIPT
Franklin Electronics
Group#9
Anirudh Kandrika (u113147)
Binoy Lobo(u113148)
Mamsha Rath(u113149)
Mayank Srivastava(u113150)
Md. Ali Tabish(u113151)
Meenakshi Behera(u113152)
Melisha Ghosh(u113153)
Case Overview
In 2003, Franklin won an 18- month
labor intensive product
development contract by
Spokane industries
It was a cost reimbursable contractCost target of $2.66 million and fixed
fee of 6.75% on the target
Contract required usage of Earned Value cost Schedule report which was
new to Franklin
First contract by Spokane Industries that was a
cost reimbursable
contract
Franklin Electronics
Contract HighlightsManagement Group• Project Manager Assigned by Spokane• Local cost Accounting Department was set up• 2 line manager were appointed
Work Breakdown Structure • 45 work packages • 1st four moths : 4 work packages to be implemented
Fewer Interchange meeting• Implementation of earned value measurement• Spokane’s faith in EVM to get necessary and meaningful information
Are the vice president’s comments correct?
The vice president’s comments are reflective of the project status derived from data computed using the EVMS
The trend identified through this method is reflective of actual cost overruns and schedule slippage
The statements are not totally accurate
What information did the vice president fail to analyse ?
The president failed to analyse the variance the variance
Cost Variance CV = BCWP(EV) - ACWP(AC)
Schedule Variance (SV) = BCWP(EV) - BCWS(PV)
• The Cost Variance does not increased by 78%
• The Schedule Variance does not increased by 45%
What additional information should have been included in the status report?To complete the analysis of the status report, it is must to include• Budget at completion (BAC)• Estimate at completion (EAC)• the Critical Path.
Budget at Completion
• The budget at completion is the sum of all BCWS allotted to the project
• here it is 121k for end of month 2 and 299k for end of month 3
Estimate at Completion
• It is the sum of all direct and indirect costs to date plus the estimate of all authorized work remaining
• EAC for month-end-2= 139.82 and EAC for month-end-3= 328.429k
Does Franklin Electronics understood EVM?
Franklin Electronics needs a better understanding of EVMS. Earned value measurement reports need to include other project related parameters such as
Project Plan•Evaluate and manage the
project•Updated throughout the
life-cycle of the project
Recourses Needed•Capital and Human
Resources
Percentage of Work Completed•Report about the
completed work and current status
•The PERT network Diagram
Does Spokane Industries understand the project management?
Earned Value Measurement
Schedule Variance (SV)
Measurement of the schedule performance for a project. Gives an idea whether project is
ahead or behind the baseline schedule.
Cost Variance (CV)Measurement of the
budget performance for a project. Tells the
management whether project is above or
below budget.
Schedule Performance Index
(SPI)Measures the progress achieved against that which was planned.
Cost Performance Index (CPI)
Measures the value of the work completed
compared to the actual cost of the work
completed.
Reports printed out from EVM system
Performance Reports• Indicate physical
progress till date
Status Reports• Analyze project progress
till that point. Calculate SV & CV
Projection Reports• Calculate SPI, CPI as
well as any other forward-looking projection
Exception Reports• Identify exceptions, problems or
situations that exceed the threshold limits on such items as variances, cash flow, resources assigned etc
Continued…Franklin Electronics was implementing EVMS for the first time
The status report prepared by them was extremely simple and should have included more details regarding the project like percentage of work completed. Elements of critical path could have been employed to build a project schedule model.
EVMS is just a tool to analyze the progress of a project
EVMS only covers cost and schedules and, therefore, no quality control is factored into EVMS
EVMS does not tell the whole story on evaluating a project and might not accurately represent what is necessary for a project to achieve specific functionality
Spokane Industries decision to rely only on the EVMS reports was a big NO!!
The EVMS reports could have been used by both Spokane Industries & Franklin Electronics to discuss matters which are hampering the project on the table & come out with mitigation plans
Advantages of EVM over meetings
• Saves time• Gives a more
detailed information about the whole project
• Would give information via the earned value status reports
For Franklin Electronics
• EVM is a new concept
• Cost Accounting group not happy to learn EVM
• EVM would mean lack of communication
For Spokane Industries
• Assigned a consultant to Franklin
• Had tremendous faith in the ability of EVM
• Did not mention EVM would be a part of all contracts
Does EVM serve as a replacement for interchange meetings?
To continue the contract and discuss the current situation in details
Give a complete status report like performance reports, Status reports
Rearrange the schedule
Continue with interchange meetings for first few months till Franklin is familiar with EVM.
Recommendations that Project Manager could Give
Thank You !!!