foundation reinforcement calcs & connection calcs

26
W01.JNB.000682 Gokwe Water Tank 1 BENDING REINFORCEMENT CALCULATION 1.1 Moment diagram giving Max Sagging Moment: See Elastic Beam design calculations Strip A (DL + LL) 1.1.1 Required reinforcement area for Max Sagging Moment: Mmax = 416.1 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 32mm deff = 500 30 32/2 = 454mm k = Mmax / (b x deff 2 x fcu) = 0.1 (1m strip: b=1000mm) y = 0.5 + √0.25 − /0.9 = 0.87 z = y x deff = 395mm As = Mmax / (0.87 x fy x z) = 2691 mm 2 /m Adopt Y25 @175mm c/c: As = 2810 mm 2 /m’ 1.1.2 Required reinforcement area for Additional Sagging Moment: Mmax = 235 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 32mm deff = 500 30 32/2 = 454mm k = Mmax / (b x deff 2 x fcu) = 0.057 (1m strip: b=1000mm) y = 0.5 + √0.25 − /0.9 = 0.93 Max Sagging Moment Additional Sagging Moment

Upload: magdel-kotze

Post on 14-Apr-2017

70 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

1 BENDING REINFORCEMENT CALCULATION

1.1 Moment diagram giving Max Sagging Moment: See Elastic Beam design calculations Strip A (DL + LL)

1.1.1 Required reinforcement area for Max Sagging Moment:

Mmax = 416.1 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 32mm deff = 500 – 30 – 32/2 = 454mm k = Mmax / (b x deff

2 x fcu) = 0.1 (1m strip: b=1000mm)

y = 0.5 + √0.25 − 𝑘/0.9 = 0.87

z = y x deff = 395mm As = Mmax / (0.87 x fy x z) = 2691 mm2/m Adopt Y25 @175mm c/c: As = 2810 mm2/m’

1.1.2 Required reinforcement area for Additional Sagging Moment:

Mmax = 235 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 32mm deff = 500 – 30 – 32/2 = 454mm k = Mmax / (b x deff

2 x fcu) = 0.057 (1m strip: b=1000mm)

y = 0.5 + √0.25 − 𝑘/0.9 = 0.93

Max Sagging Moment

Additional Sagging Moment

Page 2: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

z = y x deff = 422mm As = Mmax / (0.87 x fy x z) = 1422 mm2/m Adopt Y20 @200mm c/c: As = 1570 mm2/m

1.2 Moment diagram giving Max Hogging Moment: See Elastic Beam design calculations Strip C (DL + WL)

1.2.1 Required reinforcement area for Max Hogging Moment:

Mmax = 52.82 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 32mm deff = 500 – 30 – 32/2 = 454mm k = Mmax / (b x deff

2 x fcu) = 0.013 (1m strip: b=1000mm)

y = 0.5 + √0.25 − 𝑘/0.9 = 0.985 Adopt y = 0.95

z = y x deff = 431mm As = Mmax / (0.87 x fy x z) = 313 mm2/m Adopt Y12 @ 250mm c/c: As = 452 mm2/m

Max Hogging Moment

Page 3: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

1.3 Reinforcement sketch

1.3.1 Bottom Reinforcing – B1

1.3.2 Bottom Reinforcing – B2

Y20 @ 200 Y20 @ 200 Y20 @ 200

Y20 @ 200 Y20 @ 200

Y20 @ 200 Y20 @ 200 Y20 @ 200

Y20 @ 100

Y20 @ 200 Y20 @ 200 Y20 @ 200

Y20 @ 200 Y20 @ 200

Y20 @ 200 Y20 @ 200 Y20 @ 200

Y20 @ 100

Page 4: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

1.3.3 Top Reinforcing – T1 & T2

Y12 @ 250 Y12 @ 250 Y12 @ 250

Y12 @ 250 Y12 @ 250

Y12 @ 250 Y12 @ 250 Y12 @ 250

Y12 @ 250

Page 5: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

2 UPLIFT OF FOUNDATION DUE TO COLUMN & SOIL LOADING FROM

ABOVE

2.1 Strip A (1m Strip width)

2.1.1 Uniformly Distributed Load from Column & Soil

From the reactions output (pg 1 of the foundation design): F = 361.8 kN + 489 kN + 361.8 kN = 1212.6 kN

Length of strip A: L = 10 mm

Thus the uniformly distributed load from the 3 columns located on Strip A: UDLstrip A = F/L = 121.3 kN/m

The uniformly distributed load from the 0.5m layer soil ontop of the foundation: UDLsoil = 18 x 1 x 0.5 = 9 kN/m

2.1.2 Moment Diagram giving Max Hogging Moment

Refer to the Elastic Beam Design for Strip A: Uplift due to Column & Soil Loads from the Top (no soil underneath) for the calculation of the moments.

2.1.3 Required reinforcement area for Hogging Moment:

Mmax = 33.55 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 20mm

Hogging Moments form here due to downward load of the 3 columns and the 0.5m layer soil on top of the

foundation

Hogging

Moments

Page 6: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

deff = 500 – 30 – 20/2 = 460mm k = Mmax / (b x deff

2 x fcu) = 0.008 (1m strip: b=1000mm)

y = 0.5 + √0.25 − 𝑘/0.9 = 0.99 Adopt y = 0.95

z = y x deff = 437mm As = Mmax / (0.87 x fy x z) = 196 mm2/m Adopt Y10 @ 250mm c/c: As = 314 mm2/m

2.2 Strip B (1m Strip width)

2.2.1 Uniformly Distributed Load from Column & Soil

From the reactions output (pg 1 of the foundation design): F = 375.8 kN + 489 kN + 375.8 kN = 1240.6 kN

Length of strip A: L = 12 mm

Thus the uniformly distributed load from the 3 columns located on Strip A: UDLstrip A = F/L = 103.4 kN/m

The uniformly distributed load from the 0.5m layer soil ontop of the foundation: UDLsoil = 18 x 1 x 0.5 = 9 kN/m

The uniformly distributed self-weight of the foundation slab = UDLself = 25 x 1 x 0.5 = 12.5 kN/m

2.2.2 Moment Diagram giving Max Hogging Moment

Refer to the Elastic Beam Design for Strip B: Uplift due to Column & Soil Loads from the Top (no soil underneath) for the calculation of the moments.

Hogging Moments form here due to downward load of the 3 columns and the 0.5m layer soil on top of the

foundation

Hogging

Moments

Page 7: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

2.2.3 Required reinforcement area for Hogging Moment:

Mmax = 59.6 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 20mm deff = 500 – 30 – 20/2 = 460mm k = Mmax / (b x deff

2 x fcu) = 0.014 (1m strip: b=1000mm)

y = 0.5 + √0.25 − 𝑘/0.9 = 0.98 Adopt y = 0.95

z = y x deff = 437mm As = Mmax / (0.87 x fy x z) = 325 mm2/m Adopt Y12 @ 250mm c/c: As = 452 mm2/m

2.3 Strip C (1m Strip width)

2.3.1 Uniformly Distributed Load from Column & Soil

From the reactions output (pg 1 of the foundation design): F = -77.3 kN +(-87.6) kN + (-77.3) kN = -242.2 kN

Length of strip A: L = 12 mm

Thus the uniformly distributed load from the 3 columns located on Strip A: UDLstrip A = F/L = -20.2 kN/m

The uniformly distributed load from the 0.5m layer soil ontop of the foundation: UDLsoil = 18 x 1 x 0.5 = 9 kN/m

2.3.2 Moment Diagram giving Max Hogging Moment

Refer to the Elastic Beam Design for Strip C: Uplift due to Column & Soil Loads from the Top (no soil underneath) for the calculation of the moments.

Hogging Moments form here due to the dominant upward load of the 3 columns (caused by dominant

wind force.

Page 8: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

2.3.3 Required reinforcement area for Hogging Moment:

Mmax = 22.4 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 20mm deff = 500 – 30 – 20/2 = 460mm k = Mmax / (b x deff

2 x fcu) = 0.005 (1m strip: b=1000mm)

y = 0.5 + √0.25 − 𝑘/0.9 = 0.99 Adopt y = 0.95

z = y x deff = 437mm As = Mmax / (0.87 x fy x z) = 131 mm2/m Adopt Y10 @ 250mm c/c: As = 314 mm2/m

Thus Y12 @ 250mm c/c will be sufficient

Hogging

Moments

Page 9: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

3 CONNECTION DESIGN

3.1 Detail 1 (Fixed Connection) Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched) connects into beam 1. Beams 3 & 4 will then be welded to the column.

3.1.1 Column End Plate

The axial load of the beam shear force in the connection

The axial load in the column axial load in the connection

The moment in the beam or column (the biggest one in order to be conservative) the moment in the

connection

See Attached beam-col connection design done in Prokon.

Beam 2 (Supported Beam)

Beam 1 (Supporting Beam)

Beam 3 & 4 (Walkway Supporting Beams)

FORCES & MOMENT IN THE CONNECTION:

V = 21.8 kN

Axial: P = 164.7 kN (Compression)

M = 38.5 kNm

V M

P

Page 10: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

3.1.2 Top Plate (to make the connection a fixed connection)

Detail 1 requires to be a fixed connection hence a top plate needs to be bolted to the top flanges of beam 1 and beam 2 in order to fix the beam to beam connection. The concept shown below will be used for the top plate design. A normal beam-col connection will be done in Prokon and the plate thickness and bolt sizes obtained from that design will be used for the top plate thickness and bolt specs.

See the attached beam-col connection design for the calculation of the top plate thickness and bolt size.

3.1.3 Cleat Design

Beam 2 will notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both sides) and then bolted to beam 1.

Beam 2

Beam 1

V M

P FORCES & MOMENT IN BEAM 2

(see beam element end forces table for connection 1)

V = 71.23 kN

Axial: P = 13.34 kN

M = 39.77 kNm

Beam 2

Beam 1

Page 11: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

The following assumptions were made:

M16 Bolts

3 Bolts in a row

90 x 90 x 8 Angles

Cleat dimensions as follows: Shear and Bearing Resistance of Bolts in Supported Beam

Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 71.23 kN OK

Br = 3Øtwdboltnfubr = 299 kN > V = 71.23 kN OK

Shear and Bearing Resistance of Bolts in Supporting Beam

Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 71.23 kN OK

Br = 3Øtwdboltnfubr = 599 kN > V = 71.23 kN OK

Shear and Bearing Resistance of Angle Cleats (2 angle cleats)

Vr = 2(0.5ØLntfu) = 473 kN > V = 71.23 kN OK

Br = Øtnafu = 289 kN > V = 71.23 kN OK

Tension in Bolts of Supported Beam

50

50

80

80

50 40

Øvr bolt = 0.8 Øbr bolt = 0.67 n = 3 m = 2 Ab = 201 mm2

fuvr = 420 x 10-3 tw = 6.9 mm dbolt = 16 mm fubr = 450 x 10-3

Øvr bolt = 0.8 Øbr bolt = 0.67 n = 6 m = 1 Ab = 201 mm2

fuvr = 420 x 10-3 tw = 6.9 mm dbolt = 16 mm fubr = 450 x 10-3

Øvr = 0.9 Øbr = 0.67 n = 3 a = 40

fu = 450 x 10-3 t = 8 mm Ln = 200 – (3x18) = 146 mm

Øb = 0.8 Ab = 201 fu = 800 x 10-3 (Grade 8.8 Bolts

M = 39.77 kNm

Top bolt is in Tension

Bottom bolt is in Compression

16

0m

m

Page 12: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

T = C = M/distance between top bolt and bottom bolt from the centre T = C = 39.77 / 0.08m = 497 kN Tu = P + T = 13.34 + 497 = 510.5 kN there are 2 cleats (on either side of beam 2’s web) Thus: Tu = 510.5 / 2 = 255 kN Tr = 2(0.75ØbAbfu) = 192 kN < Tu = 255 kN NOT OK Tr = 301 kN (with M20 bolts) > Tu = 255 kN OK

Combined Shear and Tension of Bolts

Vu / Vr + Tu / Tr = (71.23 / 170) + (255 / 301) = 1.27 < 1.4 OK

Tension and Shear Block Failure of Cleat

Tr + Vr = ØAntfu + 0.6ØAnvfy = 506 kN > Tu = 255 kN OK

Use M20 Bolts

Ø = 0.9 fu = 450 x 10-3

fy = 300 x 10-3 Ant = (160 – 1x18)(8) = 1136 mm2 Agv = (40)(8) = 320 mm2 Anv = (40 – 0.25(18))(8) = 284 mm2

Thus Use M20 Bolts for Detail 1: Cleat Connection

Page 13: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

3.2 Detail 2 (Pinned Connection) Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched top and bottom) connects into beam 1. Beam 3 will then be welded to the column or to beam 2.

3.2.1 Column End Plate

The axial load of the beam shear force in the connection

The axial load in the column axial load in the connection

The moment in the beam or column (the biggest one in order to be conservative) the moment in the

connection

See Attached beam-col connection design done in Prokon.

Beam 2 (Supported Beam)

Beam 1 (Supporting Beam)

Beam 3 (Walkway Supporting Beams)

FORCES & MOMENT IN THE CONNECTION:

V = 33.78 kN

Axial: P = 293.93 kN (Compression)

M = 76 kNm

V M

P

Page 14: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

3.2.2 Cleat Design

Beam 2 will notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both sides) and then bolted to beam 1.

The following assumptions were made:

*Note: the same bolt sizes, bolts in a row and cleat dimensions were chosen on order to keep all the cleat connections uniform so as to simplify operations on site.

M16 Bolts

3 Bolts in a row

90 x 90 x 8 Angles

Cleat dimensions as follows: Shear and Bearing Resistance of Bolts in Supported Beam

Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 50.5 kN OK

Br = 3Øtwdboltnfubr = 299 kN > V = 50.5 kN OK

Shear and Bearing Resistance of Bolts in Supporting Beam

V M

P FORCES & MOMENT IN BEAM 2

(see beam element end forces table for connection 1)

V = 50.5 kN

Axial: P = 3.11 kN

M = 0 kNm (beam 2 pinned to beam 1)

Beam 2 (Supported Beam)

Beam 1 (Supporting Beam)

50

50

80

80

50 40

Øvr bolt = 0.8 Øbr bolt = 0.67 n = 3 m = 2 Ab = 201 mm2

fuvr = 420 x 10-3 tw = 6.9 mm dbolt = 16 mm fubr = 450 x 10-3

Øvr bolt = 0.8 Øbr bolt = 0.67 n = 6 m = 1 Ab = 201 mm2

fuvr = 420 x 10-3 tw = 8 mm dbolt = 16 mm fubr = 450 x 10-3

Page 15: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 71.23 kN OK

Br = 3Øtwdboltnfubr = 694 kN > V = 50.5 kN OK

Shear and Bearing Resistance of Angle Cleats (2 angle cleats)

Vr = 2(0.5ØLntfu) = 473 kN > V = 50.5 kN OK

Br = Øtnafu = 289 kN > V = 50.5 kN OK

Tension in Bolts of Supported Beam

Tu = P = 3.11 kN there are 2 cleats (on either side of beam 2’s web) Thus: Tu = 3.11 / 2 = 1.56 kN Tr = 2(0.75ØbAbfu) = 192 kN < Tu = 1.56 kN OK

Combined Shear and Tension of Bolts

Vu / Vr + Tu / Tr = (50.5 / 170) + (1.56 / 192) = 0.31 < 1.4 OK

Tension and Shear Block Failure of Cleat

Tr + Vr = ØAntfu + 0.6ØAnvfy = 506 kN > Tu = 255 kN OK

Øvr = 0.9 Øbr = 0.67 n = 3 a = 40

fu = 450 x 10-3 t = 8 mm Ln = 200 – (3x18) = 146 mm

Øb = 0.8 Ab = 201 fu = 800 x 10-3 (Grade 8.8 Bolts

P

16

0m

m

Ø = 0.9 fu = 450 x 10-3

fy = 300 x 10-3 Ant = (160 – 1x18)(8) = 1136 mm2 Agv = (40)(8) = 320 mm2 Anv = (40 – 0.25(18))(8) = 284 mm2

Page 16: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

3.3 Detail 3 (Fixed Connection) Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched) connects into beam 1. Beams 3 will then be welded to the column or beam 2.

3.3.1 Column End Plate

The axial load of the beam shear force in the connection

The axial load in the column axial load in the connection

The moment in the beam or column (the biggest one in order to be conservative) the moment in the

connection

See Attached beam-col connection design done in Prokon.

Beam 2 (Supported Beam)

Beam 1 (Supporting Beam)

Beam 3 (Walkway Supporting Beam)

FORCES & MOMENT IN THE CONNECTION:

V = 12.6 kN

Axial: P = 508 kN (Compression)

M = 74.6 kNm

V M

P

Page 17: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

3.3.2 Top/Splice Plate (to make the connection a fixed connection)

Detail 3 requires to be a fixed connection hence a top plate needs to be bolted to the top flanges of beam 1 and beam 2 in order to fix the beam to beam connection. The concept shown below will be used for the top plate design. A normal beam-col connection will be done in Prokon and the plate thickness and bolt sizes obtained from that design will be used for the top plate thickness and bolt specs.

See the attached beam-col connection design for the calculation of the top plate thickness and bolt size.

3.3.3 Cleat Design

Beam 2 will be notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both sides) and then bolted to beam 1.

Beam 2

Beam 1

V M

P FORCES & MOMENT IN BEAM 2

(see beam element end forces table for connection 1)

V = 260 kN

Axial: P = 39 kN

M = 112.73 kNm

Beam 2

Beam 1

Page 18: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

The following assumptions were made:

M20 Bolts

4 Bolts in a row

90 x 90 x 8 Angles

Cleat dimensions as follows: Shear and Bearing Resistance of Bolts in Supported Beam

Vr = 0.6ØnmAb0.7fuvr = 354.5 kN > V = 260 kN OK

Br = 3Øtwdboltnfubr = 578 kN > V = 260 kN OK

Shear and Bearing Resistance of Bolts in Supporting Beam

Vr = 0.6ØnmAb0.7fuvr = 354.5 kN > V = 260 kN OK

Br = 3Øtwdboltnfubr = 1157 kN > V = 260 kN OK

Shear and Bearing Resistance of Angle Cleats (2 angle cleats)

Vr = 2(0.5ØLntfu) = 686.9 kN > V = 260 kN OK

Br = Øtnafu = 385.9 kN > V = 260 kN OK

Tension in Bolts of Supported Beam

45

70

70

70

50 40

Øvr bolt = 0.8 Øbr bolt = 0.67 n = 4 m = 2 Ab = 314 mm2

fuvr = 420 x 10-3 tw = 8 mm dbolt = 20 mm fubr = 450 x 10-3

Øvr bolt = 0.8 Øbr bolt = 0.67 n = 8 m = 1 Ab = 314 mm2

fuvr = 420 x 10-3 tw = 8 mm dbolt = 20 mm fubr = 450 x 10-3

Øvr = 0.9 Øbr = 0.67 n = 4 a = 40

fu = 450 x 10-3 t = 8 mm Ln = 300 – (4x22) = 212 mm

Øb = 0.8 Ab = 314 fu = 800 x 10-3 (Grade 8.8 Bolts

M = 112.73 kNm

Top 2 bolts is in Tension

Bottom 2 bolts is in Compression

21

0m

m

45

Page 19: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

T = C = M/distance between top bolt and bottom bolt from the centre T = C = 112.73 / 0.105m = 1073.6 kN per bolt and 2 bolts per cleat are in tension T = C = 1073.6 / 2 = 536.8 kN Tu = P + T = 39 + 536.8 = 575.8 kN there are 2 cleats (on either side of beam 2’s web) Thus: Tu = 575.8 / 2 = 288 kN Tr = 2(0.75ØbAbfu) = kN < Tu = 301 kN OK

Combined Shear and Tension of Bolts

Vu / Vr + Tu / Tr = (260 / 345.5) + (288 / 301) = 1.7 < 1.4 NOT OK Please advise what to do

Tension and Shear Block Failure of Cleat

Tr + Vr = ØAntfu + 0.6ØAnvfy = 618 kN > Tu = 255 kN OK

Ø = 0.9 fu = 450 x 10-3

fy = 300 x 10-3 Ant = (210 – 1.5x22)(8) = 1416 mm2 Agv = (40)(8) = 320 mm2 Anv = (40 – 0.25(22))(8) = 276 mm2

Page 20: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

3.4 Detail 4 (Pinned Connection) Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched) connects into beam 1.

3.4.1 Column End Plate

The axial load of the beam shear force in the connection

The axial load in the column axial load in the connection

The moment in the beam or column (the biggest one in order to be conservative) the moment in the

connection

See Attached beam-col connection design done in Prokon.

Beam 1 (Supporting Beam)

Beam 2 (Supported Beam)

Beam 1 (Supporting Beam)

FORCES & MOMENT IN THE CONNECTION:

V 33.57 kN

Axial: P = 766.4 kN (Compression)

M = 151.43 kNm

V M

P

Page 21: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

3.4.2 End Plate Design

Beam 2 will be notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both sides) and then bolted to beam 1.

The following assumptions were made:

M20 Bolts

3 Bolts in a row

12mm End Plate

End Plate dimensions as follows:

See attached excell sheet for end plate calculations.

V M

P FORCES & MOMENT IN BEAM 2

(see beam element end forces table for connection 1)

V = 226.42 kN

Axial: P = 38.33 kN

M = 0 kNm (pinned connection)

Beam 2 (Supported Beam)

Beam 1 (Supporting Beam)

50 50

50

100

100

50

150

Page 22: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

3.5 Detail 5 (Pinned Connection) Beam 1 land beam 2 (horizontal members) will be welded to and end plate and bolted to the column web and flanges respectively.

3.5.1 End Plate Design

Beam 2 will be notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both sides) and then bolted to beam 1.

The following assumptions were made:

M16 Bolts

2 Bolts in a row

10mm End Plate

End Plate dimensions as follows:

See attached excell sheet for end plate calculations.

Beam 1 (Horizontal Member)

Beam 2 (Horizontal Member)

V M

P

FORCES & MOMENT IN BEAM 2

(see beam element end forces table for connection 1)

V = 0.3 kN

Axial: P = 52 kN

M = 0.65 kNm

Beam 2 (Horizontal Member)

Beam 1 (Horizontal Member)

50

150

50

40 40 70

End Plate

Page 23: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

3.6 Detail 5 (Weld Check) Beam 2 (walkway supporting beam) will be fully welded to beam 1 (secondary beam).

3.6.1 Weld Check

See attached excell sheet for weld check.

Beam 1 (Secondary Beam)

Beam 2 (Walkway Supporting Beam)

Page 24: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

3.7 Detail 6 (Corner Connection of Channels (walkway ringbeam))

PC 230 x 90 Channels

80 x 80 x 6 Angle

2 x M12 Bolts

Page 25: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

3.8 Detail 7 (Walkway Supporting Beams) Beam 1 (secondary beams), beam 2 (secondary 2 beams) and beam 3 (primary beam) are all flush at the top. The walkway supporting beams are not flush with beam 1, beam 2 and beam 3. Spacers will be used in order to obtain an equal level for the mentis grid at the top.

Walkway Supporting Beams

Primary Beam

Secondary 2 Beams

Secondary Beams

Page 26: Foundation Reinforcement Calcs & Connection Calcs

W01.JNB.000682 Gokwe Water Tank

3.9 Detail 8 (Mentis Grid Detail) RS40 Rectagrid with 30x4.5 Nominal Bearer Bar Size