foundation reinforcement calcs & connection calcs
TRANSCRIPT
W01.JNB.000682 Gokwe Water Tank
1 BENDING REINFORCEMENT CALCULATION
1.1 Moment diagram giving Max Sagging Moment: See Elastic Beam design calculations Strip A (DL + LL)
1.1.1 Required reinforcement area for Max Sagging Moment:
Mmax = 416.1 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 32mm deff = 500 – 30 – 32/2 = 454mm k = Mmax / (b x deff
2 x fcu) = 0.1 (1m strip: b=1000mm)
y = 0.5 + √0.25 − 𝑘/0.9 = 0.87
z = y x deff = 395mm As = Mmax / (0.87 x fy x z) = 2691 mm2/m Adopt Y25 @175mm c/c: As = 2810 mm2/m’
1.1.2 Required reinforcement area for Additional Sagging Moment:
Mmax = 235 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 32mm deff = 500 – 30 – 32/2 = 454mm k = Mmax / (b x deff
2 x fcu) = 0.057 (1m strip: b=1000mm)
y = 0.5 + √0.25 − 𝑘/0.9 = 0.93
Max Sagging Moment
Additional Sagging Moment
W01.JNB.000682 Gokwe Water Tank
z = y x deff = 422mm As = Mmax / (0.87 x fy x z) = 1422 mm2/m Adopt Y20 @200mm c/c: As = 1570 mm2/m
1.2 Moment diagram giving Max Hogging Moment: See Elastic Beam design calculations Strip C (DL + WL)
1.2.1 Required reinforcement area for Max Hogging Moment:
Mmax = 52.82 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 32mm deff = 500 – 30 – 32/2 = 454mm k = Mmax / (b x deff
2 x fcu) = 0.013 (1m strip: b=1000mm)
y = 0.5 + √0.25 − 𝑘/0.9 = 0.985 Adopt y = 0.95
z = y x deff = 431mm As = Mmax / (0.87 x fy x z) = 313 mm2/m Adopt Y12 @ 250mm c/c: As = 452 mm2/m
Max Hogging Moment
W01.JNB.000682 Gokwe Water Tank
1.3 Reinforcement sketch
1.3.1 Bottom Reinforcing – B1
1.3.2 Bottom Reinforcing – B2
Y20 @ 200 Y20 @ 200 Y20 @ 200
Y20 @ 200 Y20 @ 200
Y20 @ 200 Y20 @ 200 Y20 @ 200
Y20 @ 100
Y20 @ 200 Y20 @ 200 Y20 @ 200
Y20 @ 200 Y20 @ 200
Y20 @ 200 Y20 @ 200 Y20 @ 200
Y20 @ 100
W01.JNB.000682 Gokwe Water Tank
1.3.3 Top Reinforcing – T1 & T2
Y12 @ 250 Y12 @ 250 Y12 @ 250
Y12 @ 250 Y12 @ 250
Y12 @ 250 Y12 @ 250 Y12 @ 250
Y12 @ 250
W01.JNB.000682 Gokwe Water Tank
2 UPLIFT OF FOUNDATION DUE TO COLUMN & SOIL LOADING FROM
ABOVE
2.1 Strip A (1m Strip width)
2.1.1 Uniformly Distributed Load from Column & Soil
From the reactions output (pg 1 of the foundation design): F = 361.8 kN + 489 kN + 361.8 kN = 1212.6 kN
Length of strip A: L = 10 mm
Thus the uniformly distributed load from the 3 columns located on Strip A: UDLstrip A = F/L = 121.3 kN/m
The uniformly distributed load from the 0.5m layer soil ontop of the foundation: UDLsoil = 18 x 1 x 0.5 = 9 kN/m
2.1.2 Moment Diagram giving Max Hogging Moment
Refer to the Elastic Beam Design for Strip A: Uplift due to Column & Soil Loads from the Top (no soil underneath) for the calculation of the moments.
2.1.3 Required reinforcement area for Hogging Moment:
Mmax = 33.55 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 20mm
Hogging Moments form here due to downward load of the 3 columns and the 0.5m layer soil on top of the
foundation
Hogging
Moments
W01.JNB.000682 Gokwe Water Tank
deff = 500 – 30 – 20/2 = 460mm k = Mmax / (b x deff
2 x fcu) = 0.008 (1m strip: b=1000mm)
y = 0.5 + √0.25 − 𝑘/0.9 = 0.99 Adopt y = 0.95
z = y x deff = 437mm As = Mmax / (0.87 x fy x z) = 196 mm2/m Adopt Y10 @ 250mm c/c: As = 314 mm2/m
2.2 Strip B (1m Strip width)
2.2.1 Uniformly Distributed Load from Column & Soil
From the reactions output (pg 1 of the foundation design): F = 375.8 kN + 489 kN + 375.8 kN = 1240.6 kN
Length of strip A: L = 12 mm
Thus the uniformly distributed load from the 3 columns located on Strip A: UDLstrip A = F/L = 103.4 kN/m
The uniformly distributed load from the 0.5m layer soil ontop of the foundation: UDLsoil = 18 x 1 x 0.5 = 9 kN/m
The uniformly distributed self-weight of the foundation slab = UDLself = 25 x 1 x 0.5 = 12.5 kN/m
2.2.2 Moment Diagram giving Max Hogging Moment
Refer to the Elastic Beam Design for Strip B: Uplift due to Column & Soil Loads from the Top (no soil underneath) for the calculation of the moments.
Hogging Moments form here due to downward load of the 3 columns and the 0.5m layer soil on top of the
foundation
Hogging
Moments
W01.JNB.000682 Gokwe Water Tank
2.2.3 Required reinforcement area for Hogging Moment:
Mmax = 59.6 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 20mm deff = 500 – 30 – 20/2 = 460mm k = Mmax / (b x deff
2 x fcu) = 0.014 (1m strip: b=1000mm)
y = 0.5 + √0.25 − 𝑘/0.9 = 0.98 Adopt y = 0.95
z = y x deff = 437mm As = Mmax / (0.87 x fy x z) = 325 mm2/m Adopt Y12 @ 250mm c/c: As = 452 mm2/m
2.3 Strip C (1m Strip width)
2.3.1 Uniformly Distributed Load from Column & Soil
From the reactions output (pg 1 of the foundation design): F = -77.3 kN +(-87.6) kN + (-77.3) kN = -242.2 kN
Length of strip A: L = 12 mm
Thus the uniformly distributed load from the 3 columns located on Strip A: UDLstrip A = F/L = -20.2 kN/m
The uniformly distributed load from the 0.5m layer soil ontop of the foundation: UDLsoil = 18 x 1 x 0.5 = 9 kN/m
2.3.2 Moment Diagram giving Max Hogging Moment
Refer to the Elastic Beam Design for Strip C: Uplift due to Column & Soil Loads from the Top (no soil underneath) for the calculation of the moments.
Hogging Moments form here due to the dominant upward load of the 3 columns (caused by dominant
wind force.
W01.JNB.000682 Gokwe Water Tank
2.3.3 Required reinforcement area for Hogging Moment:
Mmax = 22.4 kNm fcu = 20Mpa; fy = 450Mpa cover = 30mm Thickness of the beam: 500mm Assumed diameter of reinforcement: d = 20mm deff = 500 – 30 – 20/2 = 460mm k = Mmax / (b x deff
2 x fcu) = 0.005 (1m strip: b=1000mm)
y = 0.5 + √0.25 − 𝑘/0.9 = 0.99 Adopt y = 0.95
z = y x deff = 437mm As = Mmax / (0.87 x fy x z) = 131 mm2/m Adopt Y10 @ 250mm c/c: As = 314 mm2/m
Thus Y12 @ 250mm c/c will be sufficient
Hogging
Moments
W01.JNB.000682 Gokwe Water Tank
3 CONNECTION DESIGN
3.1 Detail 1 (Fixed Connection) Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched) connects into beam 1. Beams 3 & 4 will then be welded to the column.
3.1.1 Column End Plate
The axial load of the beam shear force in the connection
The axial load in the column axial load in the connection
The moment in the beam or column (the biggest one in order to be conservative) the moment in the
connection
See Attached beam-col connection design done in Prokon.
Beam 2 (Supported Beam)
Beam 1 (Supporting Beam)
Beam 3 & 4 (Walkway Supporting Beams)
FORCES & MOMENT IN THE CONNECTION:
V = 21.8 kN
Axial: P = 164.7 kN (Compression)
M = 38.5 kNm
V M
P
W01.JNB.000682 Gokwe Water Tank
3.1.2 Top Plate (to make the connection a fixed connection)
Detail 1 requires to be a fixed connection hence a top plate needs to be bolted to the top flanges of beam 1 and beam 2 in order to fix the beam to beam connection. The concept shown below will be used for the top plate design. A normal beam-col connection will be done in Prokon and the plate thickness and bolt sizes obtained from that design will be used for the top plate thickness and bolt specs.
See the attached beam-col connection design for the calculation of the top plate thickness and bolt size.
3.1.3 Cleat Design
Beam 2 will notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both sides) and then bolted to beam 1.
Beam 2
Beam 1
V M
P FORCES & MOMENT IN BEAM 2
(see beam element end forces table for connection 1)
V = 71.23 kN
Axial: P = 13.34 kN
M = 39.77 kNm
Beam 2
Beam 1
W01.JNB.000682 Gokwe Water Tank
The following assumptions were made:
M16 Bolts
3 Bolts in a row
90 x 90 x 8 Angles
Cleat dimensions as follows: Shear and Bearing Resistance of Bolts in Supported Beam
Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 71.23 kN OK
Br = 3Øtwdboltnfubr = 299 kN > V = 71.23 kN OK
Shear and Bearing Resistance of Bolts in Supporting Beam
Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 71.23 kN OK
Br = 3Øtwdboltnfubr = 599 kN > V = 71.23 kN OK
Shear and Bearing Resistance of Angle Cleats (2 angle cleats)
Vr = 2(0.5ØLntfu) = 473 kN > V = 71.23 kN OK
Br = Øtnafu = 289 kN > V = 71.23 kN OK
Tension in Bolts of Supported Beam
50
50
80
80
50 40
Øvr bolt = 0.8 Øbr bolt = 0.67 n = 3 m = 2 Ab = 201 mm2
fuvr = 420 x 10-3 tw = 6.9 mm dbolt = 16 mm fubr = 450 x 10-3
Øvr bolt = 0.8 Øbr bolt = 0.67 n = 6 m = 1 Ab = 201 mm2
fuvr = 420 x 10-3 tw = 6.9 mm dbolt = 16 mm fubr = 450 x 10-3
Øvr = 0.9 Øbr = 0.67 n = 3 a = 40
fu = 450 x 10-3 t = 8 mm Ln = 200 – (3x18) = 146 mm
Øb = 0.8 Ab = 201 fu = 800 x 10-3 (Grade 8.8 Bolts
M = 39.77 kNm
Top bolt is in Tension
Bottom bolt is in Compression
16
0m
m
W01.JNB.000682 Gokwe Water Tank
T = C = M/distance between top bolt and bottom bolt from the centre T = C = 39.77 / 0.08m = 497 kN Tu = P + T = 13.34 + 497 = 510.5 kN there are 2 cleats (on either side of beam 2’s web) Thus: Tu = 510.5 / 2 = 255 kN Tr = 2(0.75ØbAbfu) = 192 kN < Tu = 255 kN NOT OK Tr = 301 kN (with M20 bolts) > Tu = 255 kN OK
Combined Shear and Tension of Bolts
Vu / Vr + Tu / Tr = (71.23 / 170) + (255 / 301) = 1.27 < 1.4 OK
Tension and Shear Block Failure of Cleat
Tr + Vr = ØAntfu + 0.6ØAnvfy = 506 kN > Tu = 255 kN OK
Use M20 Bolts
Ø = 0.9 fu = 450 x 10-3
fy = 300 x 10-3 Ant = (160 – 1x18)(8) = 1136 mm2 Agv = (40)(8) = 320 mm2 Anv = (40 – 0.25(18))(8) = 284 mm2
Thus Use M20 Bolts for Detail 1: Cleat Connection
W01.JNB.000682 Gokwe Water Tank
3.2 Detail 2 (Pinned Connection) Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched top and bottom) connects into beam 1. Beam 3 will then be welded to the column or to beam 2.
3.2.1 Column End Plate
The axial load of the beam shear force in the connection
The axial load in the column axial load in the connection
The moment in the beam or column (the biggest one in order to be conservative) the moment in the
connection
See Attached beam-col connection design done in Prokon.
Beam 2 (Supported Beam)
Beam 1 (Supporting Beam)
Beam 3 (Walkway Supporting Beams)
FORCES & MOMENT IN THE CONNECTION:
V = 33.78 kN
Axial: P = 293.93 kN (Compression)
M = 76 kNm
V M
P
W01.JNB.000682 Gokwe Water Tank
3.2.2 Cleat Design
Beam 2 will notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both sides) and then bolted to beam 1.
The following assumptions were made:
*Note: the same bolt sizes, bolts in a row and cleat dimensions were chosen on order to keep all the cleat connections uniform so as to simplify operations on site.
M16 Bolts
3 Bolts in a row
90 x 90 x 8 Angles
Cleat dimensions as follows: Shear and Bearing Resistance of Bolts in Supported Beam
Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 50.5 kN OK
Br = 3Øtwdboltnfubr = 299 kN > V = 50.5 kN OK
Shear and Bearing Resistance of Bolts in Supporting Beam
V M
P FORCES & MOMENT IN BEAM 2
(see beam element end forces table for connection 1)
V = 50.5 kN
Axial: P = 3.11 kN
M = 0 kNm (beam 2 pinned to beam 1)
Beam 2 (Supported Beam)
Beam 1 (Supporting Beam)
50
50
80
80
50 40
Øvr bolt = 0.8 Øbr bolt = 0.67 n = 3 m = 2 Ab = 201 mm2
fuvr = 420 x 10-3 tw = 6.9 mm dbolt = 16 mm fubr = 450 x 10-3
Øvr bolt = 0.8 Øbr bolt = 0.67 n = 6 m = 1 Ab = 201 mm2
fuvr = 420 x 10-3 tw = 8 mm dbolt = 16 mm fubr = 450 x 10-3
W01.JNB.000682 Gokwe Water Tank
Vr = 0.6ØnmAb0.7fuvr = 170 kN > V = 71.23 kN OK
Br = 3Øtwdboltnfubr = 694 kN > V = 50.5 kN OK
Shear and Bearing Resistance of Angle Cleats (2 angle cleats)
Vr = 2(0.5ØLntfu) = 473 kN > V = 50.5 kN OK
Br = Øtnafu = 289 kN > V = 50.5 kN OK
Tension in Bolts of Supported Beam
Tu = P = 3.11 kN there are 2 cleats (on either side of beam 2’s web) Thus: Tu = 3.11 / 2 = 1.56 kN Tr = 2(0.75ØbAbfu) = 192 kN < Tu = 1.56 kN OK
Combined Shear and Tension of Bolts
Vu / Vr + Tu / Tr = (50.5 / 170) + (1.56 / 192) = 0.31 < 1.4 OK
Tension and Shear Block Failure of Cleat
Tr + Vr = ØAntfu + 0.6ØAnvfy = 506 kN > Tu = 255 kN OK
Øvr = 0.9 Øbr = 0.67 n = 3 a = 40
fu = 450 x 10-3 t = 8 mm Ln = 200 – (3x18) = 146 mm
Øb = 0.8 Ab = 201 fu = 800 x 10-3 (Grade 8.8 Bolts
P
16
0m
m
Ø = 0.9 fu = 450 x 10-3
fy = 300 x 10-3 Ant = (160 – 1x18)(8) = 1136 mm2 Agv = (40)(8) = 320 mm2 Anv = (40 – 0.25(18))(8) = 284 mm2
W01.JNB.000682 Gokwe Water Tank
3.3 Detail 3 (Fixed Connection) Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched) connects into beam 1. Beams 3 will then be welded to the column or beam 2.
3.3.1 Column End Plate
The axial load of the beam shear force in the connection
The axial load in the column axial load in the connection
The moment in the beam or column (the biggest one in order to be conservative) the moment in the
connection
See Attached beam-col connection design done in Prokon.
Beam 2 (Supported Beam)
Beam 1 (Supporting Beam)
Beam 3 (Walkway Supporting Beam)
FORCES & MOMENT IN THE CONNECTION:
V = 12.6 kN
Axial: P = 508 kN (Compression)
M = 74.6 kNm
V M
P
W01.JNB.000682 Gokwe Water Tank
3.3.2 Top/Splice Plate (to make the connection a fixed connection)
Detail 3 requires to be a fixed connection hence a top plate needs to be bolted to the top flanges of beam 1 and beam 2 in order to fix the beam to beam connection. The concept shown below will be used for the top plate design. A normal beam-col connection will be done in Prokon and the plate thickness and bolt sizes obtained from that design will be used for the top plate thickness and bolt specs.
See the attached beam-col connection design for the calculation of the top plate thickness and bolt size.
3.3.3 Cleat Design
Beam 2 will be notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both sides) and then bolted to beam 1.
Beam 2
Beam 1
V M
P FORCES & MOMENT IN BEAM 2
(see beam element end forces table for connection 1)
V = 260 kN
Axial: P = 39 kN
M = 112.73 kNm
Beam 2
Beam 1
W01.JNB.000682 Gokwe Water Tank
The following assumptions were made:
M20 Bolts
4 Bolts in a row
90 x 90 x 8 Angles
Cleat dimensions as follows: Shear and Bearing Resistance of Bolts in Supported Beam
Vr = 0.6ØnmAb0.7fuvr = 354.5 kN > V = 260 kN OK
Br = 3Øtwdboltnfubr = 578 kN > V = 260 kN OK
Shear and Bearing Resistance of Bolts in Supporting Beam
Vr = 0.6ØnmAb0.7fuvr = 354.5 kN > V = 260 kN OK
Br = 3Øtwdboltnfubr = 1157 kN > V = 260 kN OK
Shear and Bearing Resistance of Angle Cleats (2 angle cleats)
Vr = 2(0.5ØLntfu) = 686.9 kN > V = 260 kN OK
Br = Øtnafu = 385.9 kN > V = 260 kN OK
Tension in Bolts of Supported Beam
45
70
70
70
50 40
Øvr bolt = 0.8 Øbr bolt = 0.67 n = 4 m = 2 Ab = 314 mm2
fuvr = 420 x 10-3 tw = 8 mm dbolt = 20 mm fubr = 450 x 10-3
Øvr bolt = 0.8 Øbr bolt = 0.67 n = 8 m = 1 Ab = 314 mm2
fuvr = 420 x 10-3 tw = 8 mm dbolt = 20 mm fubr = 450 x 10-3
Øvr = 0.9 Øbr = 0.67 n = 4 a = 40
fu = 450 x 10-3 t = 8 mm Ln = 300 – (4x22) = 212 mm
Øb = 0.8 Ab = 314 fu = 800 x 10-3 (Grade 8.8 Bolts
M = 112.73 kNm
Top 2 bolts is in Tension
Bottom 2 bolts is in Compression
21
0m
m
45
W01.JNB.000682 Gokwe Water Tank
T = C = M/distance between top bolt and bottom bolt from the centre T = C = 112.73 / 0.105m = 1073.6 kN per bolt and 2 bolts per cleat are in tension T = C = 1073.6 / 2 = 536.8 kN Tu = P + T = 39 + 536.8 = 575.8 kN there are 2 cleats (on either side of beam 2’s web) Thus: Tu = 575.8 / 2 = 288 kN Tr = 2(0.75ØbAbfu) = kN < Tu = 301 kN OK
Combined Shear and Tension of Bolts
Vu / Vr + Tu / Tr = (260 / 345.5) + (288 / 301) = 1.7 < 1.4 NOT OK Please advise what to do
Tension and Shear Block Failure of Cleat
Tr + Vr = ØAntfu + 0.6ØAnvfy = 618 kN > Tu = 255 kN OK
Ø = 0.9 fu = 450 x 10-3
fy = 300 x 10-3 Ant = (210 – 1.5x22)(8) = 1416 mm2 Agv = (40)(8) = 320 mm2 Anv = (40 – 0.25(22))(8) = 276 mm2
W01.JNB.000682 Gokwe Water Tank
3.4 Detail 4 (Pinned Connection) Beam 1 lies on top of the column (connected to the column with a column end plate) and beam 2 (notched) connects into beam 1.
3.4.1 Column End Plate
The axial load of the beam shear force in the connection
The axial load in the column axial load in the connection
The moment in the beam or column (the biggest one in order to be conservative) the moment in the
connection
See Attached beam-col connection design done in Prokon.
Beam 1 (Supporting Beam)
Beam 2 (Supported Beam)
Beam 1 (Supporting Beam)
FORCES & MOMENT IN THE CONNECTION:
V 33.57 kN
Axial: P = 766.4 kN (Compression)
M = 151.43 kNm
V M
P
W01.JNB.000682 Gokwe Water Tank
3.4.2 End Plate Design
Beam 2 will be notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both sides) and then bolted to beam 1.
The following assumptions were made:
M20 Bolts
3 Bolts in a row
12mm End Plate
End Plate dimensions as follows:
See attached excell sheet for end plate calculations.
V M
P FORCES & MOMENT IN BEAM 2
(see beam element end forces table for connection 1)
V = 226.42 kN
Axial: P = 38.33 kN
M = 0 kNm (pinned connection)
Beam 2 (Supported Beam)
Beam 1 (Supporting Beam)
50 50
50
100
100
50
150
W01.JNB.000682 Gokwe Water Tank
3.5 Detail 5 (Pinned Connection) Beam 1 land beam 2 (horizontal members) will be welded to and end plate and bolted to the column web and flanges respectively.
3.5.1 End Plate Design
Beam 2 will be notched at the top and bottom in order to fit into beam 1. Beam 2 will be bolted to an angle (both sides) and then bolted to beam 1.
The following assumptions were made:
M16 Bolts
2 Bolts in a row
10mm End Plate
End Plate dimensions as follows:
See attached excell sheet for end plate calculations.
Beam 1 (Horizontal Member)
Beam 2 (Horizontal Member)
V M
P
FORCES & MOMENT IN BEAM 2
(see beam element end forces table for connection 1)
V = 0.3 kN
Axial: P = 52 kN
M = 0.65 kNm
Beam 2 (Horizontal Member)
Beam 1 (Horizontal Member)
50
150
50
40 40 70
End Plate
W01.JNB.000682 Gokwe Water Tank
3.6 Detail 5 (Weld Check) Beam 2 (walkway supporting beam) will be fully welded to beam 1 (secondary beam).
3.6.1 Weld Check
See attached excell sheet for weld check.
Beam 1 (Secondary Beam)
Beam 2 (Walkway Supporting Beam)
W01.JNB.000682 Gokwe Water Tank
3.7 Detail 6 (Corner Connection of Channels (walkway ringbeam))
PC 230 x 90 Channels
80 x 80 x 6 Angle
2 x M12 Bolts
W01.JNB.000682 Gokwe Water Tank
3.8 Detail 7 (Walkway Supporting Beams) Beam 1 (secondary beams), beam 2 (secondary 2 beams) and beam 3 (primary beam) are all flush at the top. The walkway supporting beams are not flush with beam 1, beam 2 and beam 3. Spacers will be used in order to obtain an equal level for the mentis grid at the top.
Walkway Supporting Beams
Primary Beam
Secondary 2 Beams
Secondary Beams
W01.JNB.000682 Gokwe Water Tank
3.9 Detail 8 (Mentis Grid Detail) RS40 Rectagrid with 30x4.5 Nominal Bearer Bar Size