forensic investigations of pavement pre-mature failure of a national highway pavement due to poor...

Upload: end-end

Post on 03-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 Forensic Investigations of Pavement Pre-Mature Failure of a National Highway Pavement Due to Poor Sub-Surface Drainage

    1/14

    FORENSICINVESTIGATIONSOFPAVEMENTPRE-MATUREFAILUREOFANATIONAL HIGHWAY 153

    PAVEMENTDUETOPOORSUB-SURFACEDRAINAGE

    Journal of the Indian Roads Congress, July-September 2010

    Paper No. 562

    FORENSIC INVESTIGATIONS OF PAVEMENT PRE-MATURE

    FAILURE OF A NATIONAL HIGHWAY PAVEMENT DUE TO

    POOR SUB-SURFACE DRAINAGEA. VEERARAGAVAN* & LT. COL. SHAILENDRAGROVER**

    ABSTRACT

    This Paper presents investigations of premature failure of a section of a national highway pavement due to poor sub-surface drainage.

    Forensic investigation to ascertain the cause for the failure was carried out by testing the different pavement layers in the field and through

    laboratory tests on core samples of various pavement component layer materials. The contributing factors for the pre-mature failure were

    identified as inadequate compaction of subgrade/ embankment, excess fines and high plasticity index in the Granular Sub-Base (GSB) layers,

    low binder content in the bituminous layers, etc. The laboratory tests on GSB layer materials and permeability tests indicate that the

    dramatic pavement failures may be attributable to poor sub-surface drainage and also due to the heavy commercial traffic allowed on the

    dense bituminous macadam layers.

    Benkelman Beam Deflection (BBD) survey was carried out for structural evaluation of the pavement. Dynamic Cone Penetration (DCP)

    test data was used in the analysis. Empirical relations from published literature were used to compute the resilient moduli of various

    pavement layers. The moduli values were used as input in MICHPAVE (Michigan Flexible Pavement Design System) computer program to

    compute the stresses and strains in the pavement layers. The tensile strain values in the bituminous layers and vertical compressive strain

    values on top of the subgrade were calculated. The computed strain values were used to predict the performance of the pavement section in

    terms of cracking and rutting. These predicted pavement distresses were then compared with the field performance data to validate the test

    results. The analysis shows that the theoretically computed stresses and strains can be advantageously used to predict the field performance.

    Remedial measures to repair the pavement section and to improve the sub-surface drainage are presented.

    1 INTRODUCTION

    Indian road network at over 3.3 million km falls under

    one of the world's longest road networks. Most of the

    highways and airfield pavements built in our country in

    the past 30 years or so, have very slow draining systems,

    largely because standard design practices emphasizes on

    density and stability but place little importance on sub-

    surface drainage. The poor sub-surface drainage on these

    roads leads to large amount of costly repairs or

    replacements long before reaching their design life. Not

    much importance has been given to this aspect in India.The current practices of pavement construction in India

    consider the Granular Sub-Base (GSB) as a drainage

    layer. However, the gradation and properties of layermaterials seldom permit the layer to be an effective

    drainage layer, leading to entrapment of water within the

    pavement causing a "bathtub" condition, resulting in

    premature failures and chronic pavement distresses.

    The present study is an investigation of the pre-mature

    failure of a National Highway pavement section

    constructed as part of the National Highway Development

    Programme (NHDP). The construction of pavement

    layers upto the second layer of Dense Bituminous

    Macadam (DBM) was completed on this road stretchduring the last week of December 2003 and the road

    was opened to traffic movement by January 2004. The

    * Professor of Civil Engineering,

    ** Former M.Tech Student.Indian Institute of Technology Madras, Chennai - 600 036.}

  • 8/11/2019 Forensic Investigations of Pavement Pre-Mature Failure of a National Highway Pavement Due to Poor Sub-Surface Drainage

    2/14

    Journal of the Indian Roads Congress, July-September 2010

    154 VEERARAGAVAN& GROVERON

    annual average rainfall in the region varied between 384

    and 949 mm per year during the ten years period 1996-

    2005. The traffic was allowed on the Dense Bituminous

    Macadam layer before the Bituminous Concrete (BC)

    surface course was laid. Premature failures wereobserved on this stretch within one year after opening to

    traffic with pavement showing signs of distress in the

    form of deformation, cracks, potholes, ravelling and

    rutting. The forensic investigation was carried out to

    study the effect of sub-surface drainage on the pre-mature

    failures and suggest possible remedial measures to prevent

    subsequent failures.

    OBJECTIVES

    The purposes of this investigation are as follows:

    (i) To identify the causes of the premature problems

    of the national highway pavement section.

    (ii) Compare the computed pavement performance

    based on laboratory studies with the field

    performance values and validation of results.

    (iii) To make suggestions for rectification of the

    failure and for the improvement of the pavement

    section.

    1.1 Failure Investigation

    To reduce the probability of recurring premature pavement

    failures, the causes of problems need to be identified and

    the lessons learnt incorporated into future project designs.

    Investigations of pavement failures are hence critical, as

    the information gained can be used to identify the

    underlying cause of the problem and develop an optimal

    rehabilitation strategy. In conducting investigation, a

    thorough review and analysis of existing construction

    records and tests was required. Field tests, such as, BBD,

    Dynamic Cone Penetration (DCP), coring, and laboratory

    testing were also conducted, to validate/confirm the initial

    hypothesis.

    1.1.1 Pavement Composition

    A typical pavement cross section of the failed pavement

    section is as shown in Fig. 1. The composition of the

    pavement is as follows:

    a) Subgrade-500 mm (Min CBR value 10 %)

    b) GSB-300 mm in two layers (0-10% passing 75

    micron sieve; LL < 25 %; PI < 6 %)

    c) Wet Mix Macadam- 250 mm in two layers

    d) Bituminous Macadam-75 mm

    e) Dense Bituminous Macadam-110 mm in two layers

    f) Bituminous Concrete-50 mm

    1.1.2 Observations of the Failures

    Extensive deformation and cracking of the pavement

    surface was observed near pavement edge along median

    portion. Potholes and ravelling, interconnected cracks and

    rutting were observed along wheel path. It was observed

    that water had entered the pavement layers through the

    wide cracks and resulted in further rapid deterioration of

    the dense bituminous macadam surface. Fig. 2 to 7 show

    different types of pre-mature failures observed on the

    pavement section.

    Fig. 1. Typical Pavement Cross- Section of National Highway Failed

    Section

  • 8/11/2019 Forensic Investigations of Pavement Pre-Mature Failure of a National Highway Pavement Due to Poor Sub-Surface Drainage

    3/14

    FORENSICINVESTIGATIONSOFPAVEMENTPRE-MATUREFAILUREOFANATIONAL HIGHWAY 155

    PAVEMENTDUETOPOORSUB-SURFACEDRAINAGE

    Journal of the Indian Roads Congress, July-September 2010

    Fig. 3(a). Ravelling at Few Locations

    Fig. 2(b). Longitudinal Cracks Along Median

    Fig. 2(a). Wide Cracks Towards Median

    Fig. 3(b). Ravelling on DBM Layer

    Fig. 4(a). Hair Line Cracks on DBM Layer

    Fig. 4(b). Extensive Cracks and Ravelling

  • 8/11/2019 Forensic Investigations of Pavement Pre-Mature Failure of a National Highway Pavement Due to Poor Sub-Surface Drainage

    4/14

    Journal of the Indian Roads Congress, July-September 2010

    156 VEERARAGAVAN& GROVERON

    Fig. 5(a). Fill Soil in the Median Slopes Towards the Depressed

    Carriageway

    Fig. 5(b). Fill Soil in the Median Slopes Towards the Depressed

    Carriageway

    Fig. 6(a). Segregation in DBM Mixes

    Fig. 6(b). Cracks in DBM Layers

    Fig. 7(a). Test Pit Showing Pavement Component Layers

    Fig. 7(b). Rutting on DBM Layer

  • 8/11/2019 Forensic Investigations of Pavement Pre-Mature Failure of a National Highway Pavement Due to Poor Sub-Surface Drainage

    5/14

    FORENSICINVESTIGATIONSOFPAVEMENTPRE-MATUREFAILUREOFANATIONAL HIGHWAY 157

    PAVEMENTDUETOPOORSUB-SURFACEDRAINAGE

    Journal of the Indian Roads Congress, July-September 2010

    The ravelling in the bituminous layer may be due to the

    weathered rock aggregates that were used in the

    construction. It may also be due to the reason that the

    binder content was low or due to the fast traffic over the

    newly laid DBM layer. This needs further detailedinvestigation.

    1.1.3Embankment and Subgrade Soil Test Results

    Field investigation and laboratory tests are carried out on

    the gradation and other properties of the materials used

    in the embankment and subgrade soil used in the

    construction. The results are given in Table 1 and

    Table 2.

    Table 1 Test Results of Fill/Embankment

    (Average of Three Samples)

    Properties Pavement Edge

    Field m/c % 9.2

    LL 41

    PI 10

    Dry Density kg/m3 1700

    % Compaction 87.6

    Gradation

    Size mm % finer

    > 4.75 17.34

    > 0.075 < 4.75 41.54

    < 0.075 41.12

    Table 2 Test Results of Subgrade (Average of three samples)

    Properties Pavement Pavement Edge

    Failed Location Sound Location

    Field M/c % 9.2 5.5

    LL 35 33

    CBR, % 9.0 11

    PI 10 7

    Dry density kg/m3 1590 1900

    % Compaction 81.96 97.9

    Gradation

    Size mm % Finer % Finer % Finer

    > 10 36.5 53.1

    > 4.75 16.0 14.7 17.3

    > 0.075 < 4.75 22.9 20.3 25.3

    < 0.075 24.7 11.9 57.3

    It is found that the dry density values and the degree of

    compaction achieved on the embankment just below the

    subgrade layer were much lower than the desirable limits.

    The density of the fill soil at the failed location was as

    low as 1.7 g/cc and the degree of compaction achieved

    was only about 88 per cent near the edge of the pavement,

    whereas, this should be more than 95 per cent (MORTH

    Specifications, 2001). The density of compaction of the

    subgrade soil at the failed locations was around

    82 per cent which was much lower than the desirable

    value of 97 per cent (MORTH Specifications, 2001).

    However, at sound locations, the degree of compaction

    of the subgrade was over 97 per cent. This indicates the

    erratic compaction controls exercised in the fill and

    subgrade layers during the construction.

  • 8/11/2019 Forensic Investigations of Pavement Pre-Mature Failure of a National Highway Pavement Due to Poor Sub-Surface Drainage

    6/14

    Journal of the Indian Roads Congress, July-September 2010

    158 VEERARAGAVAN& GROVERON

    1.1.4 Granular Subbase Layer Test Results

    The results of the tests carried out on Granular sub-base

    layer material as part of failure investigation of the

    pavement is as given in Table 3.

    It is observed that the material used in GSB layercontained excessive fines. The percentage of material

    passing through 75 micron sieve varied from 14 per cent

    Table 3 Tests Results of GSB layers (Average of three locations)

    Properties Pavement Pavement Edge

    Failed Location Sound Location

    Field M/c % 8.5 6.2 15.3

    LL 31 35 40

    PI 10 10 8Gradation of GSB

    Sieve Size mm Specified % Finer at % Finer at sound % Finer at pavement

    Limits failed locations locations edge and shoulder

    > 10 100 100 100 100

    > 4.75 55-75 97.3 64.06 100

    > 0.075 < 4.75 10-30 56.4 36.04 92.61

    < 0.075 0-10 25.3 14.24 75.10

    Table 4 Variation of Permeability with Percentageof Fines

    Type of fines Permeability, m/day

    Percent passing 75 micron sieve

    0 5 10 15

    Silica or 3 0.021 0.024 0.009

    limestone

    Silt 3 0.024 0.0003 0.000 06

    Clay 3 0.003 0.000 15 0.000 027

    Re f: AASHTO Guide for Design of Pavement

    Structures, 1986

    NOTE- The coefficient of permeability for impervious soils such

    as stiff clay, semi-pervious soil such as silty clay

    and pervious soil such as sand and gravel are

    1 x 10-5 m/ sec respectively as per IRC:SP:42-1994

    to as high as 25 per cent. The GSB layer has to serve as

    a drainage layer. The permeability and drainage

    characteristics of the GSB layer depends on the

    percentage passing through 75 micron sieve. The

    permeability characteristics of dense graded aggregatesdrastically reduces with the increase in the percentage

    of fines as can be seen in the table given in Table 4.

    The permeability test results are shown in Table 5:

    Table 5 Permeability Test Results

    Test Test Results

    WMM GSB

    material Material

    Modified Proctor Compaction

    Test Results:

    Optimum Moisture Content, % 5.9% 6.25%

    Maximum Dry Density, kg/m3 2400 2360

    Permeability by falling weight 2.47 2.35

    method, m/day

    It can be inferred that the gradation of the material to be

    used in the granular subbase layer as per Ministry's

    specification Table 400-1 (per cent passing 75 micron

  • 8/11/2019 Forensic Investigations of Pavement Pre-Mature Failure of a National Highway Pavement Due to Poor Sub-Surface Drainage

    7/14

    FORENSICINVESTIGATIONSOFPAVEMENTPRE-MATUREFAILUREOFANATIONAL HIGHWAY 159

    PAVEMENTDUETOPOORSUB-SURFACEDRAINAGE

    Journal of the Indian Roads Congress, July-September 2010

    sieve upto 10 per cent) has a permeability of 0.03 x 10-3

    cm/sec whereas the minimum permeability requirements

    of a drainage layer is 0.023 cm/sec. (20 m/day)

    (AASHTO, 1986)

    The very high percentages of fines in the GSB layers

    have prevented efficient drainage. The high value of

    plasticity index added to the problem. Soils with higher

    plasticity have higher clay content. Higher the percentage

    of clay content, lower will be the permeability. If the

    percent passing 75 micron sieve is restricted to 3 to 5 per

    cent, the permeability increases to 7.6 x 10-3 cm/sec (250

    times permeability when compared to MoRTH

    Specifications of Table 400-1). When the percent of fines

    lesser than 2.0 mm sieve are zero, the permeability

    increases to 12 x 10-3 cm/sec (400 times permeability

    when compared to MoRTH specifications of

    Table 400-1)

    During the investigation the percent of fines in the drainage

    layer was found to vary from 14 per cent to as high as 75

    per cent towards the pavement edge and shoulders,

    indicating poor drainage characteristics of the granular

    sub-base layer, particularly towards the shoulders This

    has prevented effective drainage of water to the drains.

    This has also resulted in the rising of water level entering

    the pavement layers to rise through the WBM and BM

    layers. The field moisture content of the layer used at

    the pavement edge is as high as 15.3 per cent. It is seen

    that the gradation of material used at sound location is

    better than at failed location.

    1.1.5Bituminous Macadam Layer Test Results

    The samples of the Bituminous Macadam mix taken from

    test pits at failed and sound locations during the field

    investigations were tested. The results of bitumen content

    and aggregate gradation and mix properties of BM layer

    are as given in Table 6.

    Table 6 Test Results of Bituminous Macadam

    Layer (Average of three samples)

    Properties of Test pits from Standard

    BM layer Failed Sound values as per

    Location Location MoRTH

    Specifications

    Bitumen

    Content % 2.83 4.14 3.3-3.5

    AIV % 17.67 Max 30%

    Bulk Density,

    kg/m3 2380 2440

    VMA, % 13 11

    Gradation

    Sieve Size mm % Finer % Finer26.5 97.47 100 100

    19 89.47 79.43 90-100

    13.2 74.27 73.86 26-88

    4.75 41.33 48.29 16-36

    2.36 35.07 38.71 4-19

    0.3 16.4 17.14 2-10

    0.075 7.47 6.31 0-8

    However, some core samples could not be taken as the

    BM specimen samples crumbled while extraction, due to

    stripping and consequent loss in strength of BM layers,

    as can be seen in Fig. 8. Substantial stripping of the

    Fig. 8. Core Samples of BM

  • 8/11/2019 Forensic Investigations of Pavement Pre-Mature Failure of a National Highway Pavement Due to Poor Sub-Surface Drainage

    8/14

    Journal of the Indian Roads Congress, July-September 2010

    160 VEERARAGAVAN& GROVERON

    bitumen was observed in the BM layer. The percentage

    of bitumen in the BM layer is higher than the specified

    limits of 3.3 and 3.5 per cent. Higher bitumen was used

    as the mix was harsh with more percentage of fine

    material passing 2.36 mm sieve viz., about 35 to 38 percent when compared to the desirable percentage in the

    range of 4-19 per cent. This indicates inconsistent values

    of bitumen content and poor gradation in the BM layer

    and poor implementation of quality control during

    construction.

    1.1.6Dense Bi tuminous Macadam Layer Test

    Results

    The average bitumen content extracted from the core

    samples of DBM first layer was 3.62 per cent, whereas

    the bitumen content required as per the mix design was4.5 per cent. The binder content in the second layer of

    DBM was 3.08 per cent at the failed location.

    Table 7 shows the gradation of the dense bituminous

    macadam layer at the failed location as well as sound

    location.

    Table 7 Test Results of Dense Bituminous Macadam Layer

    Properties Pavement Standard Values as per

    Failed Location Sound Location MoRTH

    Bitumen Content % 3.62 Min 4.5%

    Bulk Density, kg/m3 2390 2470

    Effective bitumen content, % 4.18 4.5

    Bulk sp. Gravity of aggregates 2.695 2.745

    Air voids, % 3.98 4.5

    Gradation

    Sieve Size mm Limits % Finer % Finer

    45 100 100 100 100

    37.5 100 100 100 100

    26.5 90-100 100 100 90-100

    19 71-95 100 94.67 71-95

    13.2 56-80 86.27 74.4 56-80

    9.5 - 71.07 61.6 -

    4.75 38-54 56.53 44 38-54

    2.36 28-42 50.4 34.8 28-42

    1.18 - 37.6 25.47 -

    0.6 - 31.33 19.47 -

    0.3 7-21 26.13 14.4 7-210.15 - 20.93 9.47 -

    0.075 2-8 18.8 4.53 2-8

    Lower values of bitumen content and higher proportion

    of fines in the aggregate mix of DBM layer was noticed

    at the failure locations. This also indicates inconsistent

    quality control measures in the DBM layer during

    construction.

  • 8/11/2019 Forensic Investigations of Pavement Pre-Mature Failure of a National Highway Pavement Due to Poor Sub-Surface Drainage

    9/14

    FORENSICINVESTIGATIONSOFPAVEMENTPRE-MATUREFAILUREOFANATIONAL HIGHWAY 161

    PAVEMENTDUETOPOORSUB-SURFACEDRAINAGE

    Journal of the Indian Roads Congress, July-September 2010

    Table 8 Classified Daily Traffic Volume

    Day Cars, Buses Trucks, LCV, Two Animal Drawn Cycles Tractor

    jeeps, vans Multi-axle wheelers vehicles

    1 1369 646 2785 1190 38 758 523

    2 1610 605 3034 1447 51 1025 556

    3 1439 618 3131 1359 106 1150 569

    4 1398 618 3182 1316 100 1175 484

    5 1401 582 3082 1312 95 1216 580

    6 1354 638 3165 1233 101 1391 560

    7 1438 607 3058 1484 165 1321 534

    Total 10009 4314 21437 9341 656 8036 3806

    AADT 1430 616 3062 1334 94 1148 544

    Table 9 Test Results of Benkelman Beam Deflection Study

    Sl No. Chainage MSA Characteristic Benkelman beam Required equivalent of BM

    Rebound Deflection, mm overlay, mm

    Outer lane Inner lane Outer lane Inner lane

    LWP RWP LWP RWP LWP RWP LWP RWP

    1 370.4-371.3 52 0.993 2.109 0.853 0.915 100 205 80 90

    2 371.42 - 372.3 52 1.520 0.949 1.212 0.742 160 90 130 60

    3 372.4 - 373.3 52 1.185 1.090 0.921 0.762 125 110 90 60

    4 373.4 - 374.4 52 0.990 1.121 1.080 0.714 100 110 110 80

    2 TRAFFIC DETAILS

    The details of the daily traffic along the section are given

    in Table 8.

    2.1 Benkelman Beam Deflection Studies

    Benkelman beam deflection studies were carried out as

    per IRC:81-1997. The results of the Benkelman beam

    deflection studies are given in Table 9.

    The thickness of overlay required varies from 50 to 140

    mm. Therefore, an additional overlay thickness

    requirement of 75 to 80 mm dense bituminous macadam/

    bituminous concrete overlay is indicated over the existing

    DBM layer depending on the location. But, if the overlay

    or next layer is directly laid over failed stretches, even

    this overlay will fail pre-maturely.

    2.2 Observations during Test Pit Studies

    a) The subgrade CBR of the soil was found to be

    more than 10 per cent and varied in the range

    12.4 per cent to 21 per cent.

    b) The CBR value of the GSB layer was found to be

    in the range 36 to 44.5 per cent.

  • 8/11/2019 Forensic Investigations of Pavement Pre-Mature Failure of a National Highway Pavement Due to Poor Sub-Surface Drainage

    10/14

    Journal of the Indian Roads Congress, July-September 2010

    162 VEERARAGAVAN& GROVERON

    c) Substantial stripping of the bituminous macadam

    layer was observed.

    d) No clear indication of the crack width with varying

    depth was observed in the dense bituminous

    macadam layer.

    e) The field moisture content in the wet mix macadam

    layer was found to be high. The percentage of fines

    (finer than 75 micron) was high even in the wet

    mix macadam layer and this has resulted in poor

    drainage.

    f) The granular sub-base layer consisted of only

    moorum soil. The soil used in the GSB layer had

    high percent of fines passing 75 micron sieve and

    also high plasticity index. This is the primary cause

    for poor drainage.

    g) The field moisture content of the GSB layer was

    above 10 per cent, which was due to poor drainage

    characteristics of the GSB layer.

    h) The soil used in the sub-base layer and the subgrade

    layer appeared to have similar properties.

    i) The field moisture content of the subgrade is above

    the optimum moisture content.

    2.3 Summary of the Observations on Various

    Tests Results

    a) The field density value in the fill/embankment

    portion of the road stretch was 1.7 g/cc, which is

    low. This corresponds to 88 per cent of the

    maximum dry density, resulting in settlement of till

    during heavy rains and consequent damages to

    pavement layers

    b) The field density values on the subgrade layer at

    the locations where cracks were observed was

    found to be 1.59 g/cc. This corresponds to 82 per

    cent of maximum dry density. This also results in

    settlement of subgrade and failure of pavement

    layers. However, the field density values were

    higher at locations which are not cracked/failed.

    c) The granular sub-base layer has excessive fines,

    ranging from 14 to 25 per cent. The proportion of

    fines in the GSB layer at shoulder portion was much

    higher. The plasticity index value was also found

    to be high, ranging from 8 to 10 per cent. This has

    resulted in poor drainage characteristics of the GSB

    layer.

    d) The binder content in the bituminous macadam layerwas found to be inconsistent. Due to ingress of

    water, stripping of the aggregates was found in the

    layer materials. The core samples could not be taken

    out and the samples crumbled.

    e) The binder content in the dense bituminous

    macadam layer was found to be 3 to 3.62 per cent

    which was lower than the specified values.

    Segregation of aggregates during construction was

    observed.

    f) The median along the embankment portion was

    found to be sloping filled with uncompacted soil.

    Due to lack of lateral confinement, wide cracks

    were observed all along the central median.

    g) The results of the Benkelman beam deflection

    studies indicate the structural inadequacy and the

    need for a strengthening layer, after removal and

    reconstruction of failed portions in large patches.

    2.4 Primary Causes of Premature Pavement

    Failure

    a) Grossly inadequate compaction of soil in the filland subgrade at the failed locations, resulting in

    settlement and yielding of pavement layers on failed

    locations

    b) High proportion of fines and PI value in GSB layer,

    particularly very high proportion of fines and PI

    values in the portion of GSB layer towards the

    pavement edge and shoulders. This has resulted in

    GSB layer to be totally ineffective as a drainage

    layer, particularly at locations where premature

    failure of the DBM layer occurred. There was no

    possibility for the water to drain out of the pavement

    layers.

    c) Porous/open textured locations on the top of the

    DBM layer at several locations due to segregation

    of mix that has occurred during various stages of

    construction. This has resulted entry of rain water

    from the surface also.

  • 8/11/2019 Forensic Investigations of Pavement Pre-Mature Failure of a National Highway Pavement Due to Poor Sub-Surface Drainage

    11/14

    FORENSICINVESTIGATIONSOFPAVEMENTPRE-MATUREFAILUREOFANATIONAL HIGHWAY 163

    PAVEMENTDUETOPOORSUB-SURFACEDRAINAGE

    Journal of the Indian Roads Congress, July-September 2010

    d) The water which entered into the pavement layers

    during rains from (a) loose soil fill in the median (b)

    shoulders and (c) pervious surface at some

    locations of the DBM layer, could not drain out

    through the impervious GSB layer and thus theentrapped water level increased within the

    pavement, saturating the WMM and BM layers.

    Consequently, the BM layer and part of DBM

    layers got deteriorated and failed as a result of

    stripping and weakening of the bituminous mix.

    2.5 Other Contributing Factors for Pavement

    Failure

    a) Inconsistent quantity of binder in the bituminous

    macadam layer and poor gradation of materials

    b) Low quantity of binder in the dense bituminous

    macadam layer and gradation of aggregates not

    fulfilling the specifications

    c) Inadequate compaction and poor quality of materials

    used in the median

    d) Permitting heavy commercial vehicles to use the

    partly completed carriageway over the DBM layer.

    The DBM layer is a binder course and traffic should

    not have been allowed on this layer before theconstruction of the wearing course.

    3 COMPUTED PAVEMENT PERFORMANCE

    BASED ON DCP FIELD DATA

    The effect of inadequate sub-surface drainage on

    pavement performance has been quantified by using the

    Dynamic Cone Penetrometer data of failure section to

    calculate the resilient modulus of the different layers and

    then using these material layer properties as input in

    MICHPAVE program the maximum tensile strain in

    asphalt layer and compressive vertical strain at top of

    subgrade are calculated and these values are compared

    with the laid down limits, hence predicting the performance

    of pavement in terms of cracking and rutting. These

    predicted pavement distresses are then compared with

    the field performance values for validation of results

    3.1 Calculation of Resilient Modulus from DCP

    data

    On the failed pavement stretch a total of 28 test pits were

    dug at known chainages where DCP test has been

    carried. This DCP data is analysed and resilient modulus(MR) is calculated using PR-MR Relationship (Chen et

    al., 2005): MR = 537.8 X PR0.664where, PR (Penetration

    Rate) is in mm/blow and MR is in MPa. The value of

    CBR is calculated by TRL relationship (1993):

    CBR = 302 X PR1.057 .The results of calculated resilient

    modulus of various layers of pavement are as shown in

    Fig. 9. It is to be mentioned that the above empirical

    relation is valid only for the range of values that were

    considered in the model development and are not the

    actual values of resilient moduli values. Repeated load

    triaxial tests are to be conducted to get the resilient modulivalues in the laboratory. However, the laboratory moduli

    values are dependent on the specimen size, aggregate

    size, confining pressure, load, frequency, rest period, etc.

    The traffic was allowed to ply for a period of four months

    before the failure was observed.

    3.2 Calculation of Stresses and Strains in

    Pavement Layers Using MICHPAVE

    The calculated resilient moduli from the DCP data areused as an input in MICHPAVE (Michigan State

    University 2000) (Michigan Flexible Pavement Design

    System) computer program, which uses nonlinear finite

    element program for analysis of flexible pavements. After

    giving the various inputs data the program is run for all

    the 28 test locations and stresses and strains in various

    pavement component layers were determined.

    Fig. 9. Resilient Modulus Variations at Different Pit Locations

  • 8/11/2019 Forensic Investigations of Pavement Pre-Mature Failure of a National Highway Pavement Due to Poor Sub-Surface Drainage

    12/14

    Journal of the Indian Roads Congress, July-September 2010

    164 VEERARAGAVAN& GROVERON

    Cracking occurs when the tensile (radial) strain in the

    asphalt layer exceeds the allowable limit of 538 micro-

    strains under 106 load applications (Shell, 1978). A graph

    showing the calculated radial tensile strains along with

    the laid down permissible limit, and cracking observed at

    various pit locations is shown in Fig. 10

    Rutting occurs when the compressive (vertical) strain at

    the top of subgrade exceeds the permissible limit of 885

    micro-strains under 106 load applications (Shell, 1978).

    A graph showing the calculated vertical compressive

    strains along with the laid down permissible limit, and

    rutting observed at various pit locations is shown in

    Fig. 11

    locations and it is seen in the field that cracking has

    occurred in field at these locations of the failed stretch

    (Fig. 10) in the intensity that is proportional to the

    calculated tensile strains using MICHPAVE. When the

    observed cracking in field is plotted against calculated

    radial tensile strain, we get an R2of 0.83 as shown in

    Fig. 12.

    The values of compressive strains at top of subgrade

    exceed the permissible compressive strain limit at 16 of

    the 28 pit locations and it is seen in the field that rutting

    has occurred in field at these locations of the failed stretch

    (Fig. 13.) in the intensity that is proportional to the

    calculated compressive strains using MICHPAVE.

    3.3 Validation of MICHPAVE Results

    The material properties considered in the analysis are as

    follows:

    a) Bituminous layer - 1377 MPa

    b) Wet Mix Macadam -864 MPa

    c) Granular sub-base- 195 MPa

    d) Subgrade soil - 93 MPa

    The values of calculated tensile strains in asphalt layer

    exceed the permissible tensile strain limit at all the 28 pit

    Hence, from the plot of observed field cracking vs

    calculated radial tensile strain as shown in Fig. 12., and

    observed field rutting vs calculated vertical compressive

    strain in Fig. 13, it is inferred that the results of

    MICHPAVE are validated.

    4 RECOMMENDATIONS FOR IMPROVE-

    MENT OF PAVEMENT PERFORMANCE

    It is recommended that the following measures be taken

    to improve the sub-surface drainage of the pavement

    section at the edge in order to improve the performance

    of the pavement:

    Fig. 10. Radial Tensile Strain Calculated and Cracking Observed at

    Different Pit Locations on Failed StretchFig. 12. Cracking Observed vs Radial Tensile Strain

    Fig. 13. Rutting Observed vs Vertical Compressive StrainFig. 11. Vertical Compressive Strain Calculated and Rutting

    Observed at Different Pit Locations on Failed Stretch

  • 8/11/2019 Forensic Investigations of Pavement Pre-Mature Failure of a National Highway Pavement Due to Poor Sub-Surface Drainage

    13/14

    FORENSICINVESTIGATIONSOFPAVEMENTPRE-MATUREFAILUREOFANATIONAL HIGHWAY 165

    PAVEMENTDUETOPOORSUB-SURFACEDRAINAGE

    Journal of the Indian Roads Congress, July-September 2010

    a) Construction of longitudinal aggregate drains by

    digging trenches at the pavement edge on the

    shoulder portion with a minimum width of 500 mm

    at the bottom as shown in Fig. 14. The aggregate

    drain should fulfill the requirements of drainage asgiven in Table 10 (Type A grading of Table 300-4

    of MORTH Specifications for Road and Bridge

    Works).

    b) Transverse aggregate drains (shoulder drains)

    of width 500 mm and depth 500 mm connecting

    the longitudinal aggregate drains as shown in

    Fig.14, to be provided at 10 m intervals on the

    straight portion and at 5 m intervals at the curve

    portion.

    Table 10 Grading Requirements for Aggregate

    Drains (MORTH Specifications, 2001)

    Sieve Size, mm Percent Passing by Weight

    63 -37.5 100

    19 -

    9.5 45-100

    3.35 25-80

    600 micron 8-45

    150 micron 5-10

    75 micron < 5

    c) In the straight portion, where, both the carriageways

    are at the same level, longitudinal aggregate drainsof width 500 mm and required depth upto the top

    of the subgrade level to be installed by excavating

    trenches in the median (Fig. 15, along the kerb and

    filled with the aggregates as per the above table

    specifications upto the top of the median fill to

    prevent water from the fill to enter into the

    Fig. 14. Construction of Longitudinal and Transverse Aggregate

    Drains at Pavement Edge

    Fig. 15. Construction of Longitudinal Aggregate Drain in the

    Median

  • 8/11/2019 Forensic Investigations of Pavement Pre-Mature Failure of a National Highway Pavement Due to Poor Sub-Surface Drainage

    14/14

    Journal of the Indian Roads Congress, July-September 2010

    166 VEERARAGAVAN& GROVERON

    pavement layers. Alternatively, a cut-off may be

    constructed along the kerb upto the GSB layer

    which could also serve as a retaining wall of the

    median fill. Retaining walls with provision for drains

    are to be constructed to prevent shear failure. The

    drains should have weep holes at the bottom levelof the sub-base layer to facilitate internal drainage.

    d) The cracked areas of the DBM surface (having

    wide, medium and fine cracks) should be marked

    into large rectangular areas. The cracked DBM

    layer/or both layers of DBM should be milled and

    removed and patched up and compacted well using

    DBM mix, before the overlay is constructed.

    e) The entire road stretch may be divided into two

    sets of sub-stretches (A) the stretch, where, the

    failures and cracking has been extensive and (B)

    stretches where only longitudinal cracks and some

    fine cracks have developed in less than 10 per cent

    of paved area. The damaged portion is to be marked

    and cut to the depth to which the cracks have

    propagated, loose material to be removed and

    cleaned using compressed air and later, tack coat

    to be applied both to the sides and bottom of the

    cut portion and patched with pre-mixed material

    with DBM gradation and compacted to the required

    density and profile using suitable rollers. After

    patching, it is suggested that:

    1. Sub-stretches of category A may be overlaid

    with (i) 50 mm thick DBM layer and (ii) 50

    mm thick BC layer using 2 per cent by weight

    of lime as a filler and SBS polymer modified

    bituminous binder using good quality SBS

    polymer modified binder from the refinery.

    2. Sub-stretches of category 'B' may be overlaid

    with 50 mm thick BC layer as above.

    5 CONCLUSIONS

    a) The forensic investigations of the pre-mature failureof the highway pavement helped the researchers

    to identify the root cause of the problem, which

    was poor sub-surface drainage. There is a need to

    revise the specifications for the granular sub-base

    layers. The specification should consider the

    permeability of the layer as an essential

    requirement.

    b) The comparison of the computed stressed and

    strains in the pavement layers based on the field

    data with the observed performance validated the

    findings of the investigation.

    c) There is a need to study the effect of construction

    quality on the performance of all the highway

    pavements constructed so far and incorporate the

    lessons learnt in the revised guidelines/

    specifications for pavement construction.

    d) The suggested remedial measures are likely to

    retard the rate of deterioration due to good sub-

    surface drainage.

    e) The lessons learned from this study may be

    incorporated in future road project designs.

    REFERENCES

    1 AASHTO (1986). "Pavement Design Guide."

    American Association of State Highway and

    Transportation Officials.

    2 Chen D.H., Lin D.F., Liau P.H., and Bilyen J.

    (2005). "A Correlation Between Dynamic Cone

    Penetrometer Values and Pavement Layer Moduli."

    Geotech. Test. Journal, 28(1), pp 42-49.

    3 IRC:81-1997, Guidelines for Strengthening of

    Flexible Road Pavements Using Benkelman Beam

    Deflection Technique, First Revision, Indian RoadsCongress, New Delhi.

    4 Michigan State University (2000), MICHPAVE

    User Manual, Department of Civil and

    Environmental Engineering, Michigan State

    University, East Lansing, USA.

    5 MORTH Specifications for Road and Bridge Works

    (2001). Ministry of Road Transport and Highways,

    Government of India, New Delhi.

    6 Shell (1978). "Shell Pavement Design Manual -

    Asphalt Pavements and Overlays for Road

    Traffic." Shell International Petroleum Company

    Limited, London, UK.

    7 Transport Research Laboratory (TRL) (1993).

    "Overseas Road Note 31: A Guide to the Structural

    Design of Bitumen-Surfaced Roads in Tropical and

    Subtropical Countries." Transport Research

    Laboratory, Crowthorne, U.K.

    166 VEERARAGAVAN& GROVERONFORENSICINVESTIGATIONSOFPAVEMENTPRE-MATURE

    FAILUREOFANATIONAL HIGHWAYPAVEMENTDUETOPOORSUB-SURFACEDRAINAGE