for offshore wind farms - tu delft ocw · for offshore wind farms ... • technological preferences...

90
2007-2008 1 Design considerations For offshore wind farms Offshore Wind Farm Design Michiel Zaaijer DUWIND

Upload: vuhuong

Post on 05-Aug-2018

244 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

1

Design considerations

For offshore wind farms

Offshore Wind Farm Design

Michiel Zaaijer

DUWIND

Page 2: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 2

Overview

• Introduction

• Overall system and planning

• Considerations per part or phase

• Cost of energy

Page 3: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

3

Introduction

Page 4: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 4

Offshore wind turbines Rotor-nacelle assembly

Support structure

Electrical infrastructure Power collection system

Power transmission system

Facilities (& remainder) Central platform

Met-mast

Auxiliary equipment

Onshore premises

Hardware components of the farm

Page 5: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 5

Exploitation Operation

Maintenance(Service, repairs and overhaul)

Post-exploitation Refurbishment

Dismantling

Implementation Procurement, assembly and logistics

Installation

Commissioning

Procedures

Page 6: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 6

Design as part of development phase

• Feasibility study, project identificationConceptual design (cost-benefit, showstoppers)

• Permitting, financing, investment decisionSystem layout (costs, EIA, visual impact)

• ContractingPreliminary design (reference, budgeting)

• Go aheadFinal design, specifications, planning

Page 7: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 7

“The example”

Throughout this lecture “Horns Rev” will be used to exemplify the design of a state-of-the-art large scale

offshore wind farm

The pictures and illustrations of this wind farm, developed by Elsam and Eltra, are taken from the

website www.hornsrev.dk. Copyright: Elsam A/S

Page 8: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

8

Overall system and planning

Page 9: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 9

General considerations

• Company / consortium skills (needed and available)

• Requirements, standards and recommended practices

• Legal framework

• (International) developments and policy

• Safety / risk / lifetime

• Environmental impact

• Technological preferences or constraints

• General targets (e.g. size, indication of location)

• Cost-benefit (see next slide)

Page 10: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 10

Cost-benefit considerations

• Costs

• Tax incentives

• Financing and insurance

• Energy quality and quantity, including availability and controllability

• Predictability (particularly wind forecast)

• Market value

• Other revenues (green certificates, subsidy)

Page 11: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 11

Know (and show) what you’re talking about

Parties with different

conventionsDeadline stress

‘please yourself’interpretations

Miscommunication and inconsistencies

Clear and complete definition

Or:

Page 12: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 12

Definition of terms

Foundation?

Wind turbine?

Page 13: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 13

Sea bottom

N

WS

E

YSWL

XSWL

ZSWL

g

ZSB

Sea bottom

YLAT

XLAT

ZLAT

XSB

YSB

Still Water Level(SWL)

Lowest Astronomical Tide(LAT)

ZSB

XSB

YSB

YT

XT

ZT

centre yaw bearing

g

α t

N

W S

E

X N

φ t u r b

d x H

Y N

Z,Z T N

Z H

d z N

Y H

X H X T

Y T

Wind Speed V

LAT (installation)Seabed (structural loads)

SWL (hydrodynamic loads)Tower top (interface WT)

NacelleHub (non-rotating)

Definition of used reference system

Page 14: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 14

Reference report

“Terminology, reference systems and conventions”

Available on blackboard in folder ‘Course Documents’

(Report used in the project “Design methods for offshore wind turbines at exposed sites (OWTES)” under contract with the European commission)

Page 15: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 15

Interactions in the design process

Rotor-nacelle assembly

Support structure

Maintenance

Installation

Farm layout

Grid connection

Operation

Page 16: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 16

General considerations (example)

Page 17: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 17

General considerations (example)

• Total investment: 2 GDKK (270 M€)

• Total energy yield: 600 GWh/year � around 150.000 households

• Fixed price: 0.33 DKK/kWh (0.045 €/kWh) (up till energy production of around 10 years)

• Green certificate trading: 0.10-0.27 DKK/kWh (0.014-0.036 €/kWh)

Page 18: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 18

General considerations (example)

Safety• Yellow lights at outer turbines• Two red warning lights on each nacelle• Orange blade tips

Page 19: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 19

General considerations (example)

Seal monitoring programme

Page 20: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

20

Site selection

Page 21: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 21

Site selection

Design choices:

•Location

•General size and shape

Considerations:

•Resources/potential

•Planning (users/infrastructure)

•Indication of costs and technical feasibility

•Relevant developments

•Regulations

Page 22: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 22

Site selection (example)

• Studies started in 1993• 4 preferred areas• 1997: “Action plan for offshore windfarms in Danish waters”• 1998: Contract negotiations with electricity suppliers• 1999: Preliminary go-ahead for 4 sites

Page 23: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 23

Site selection (example)

• Hard sand reef of moraine gravel of early ice ages• Water depth between 1 and 10 m• But… harsh sea conditions: “The Devil’s Horn”

Page 24: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

24

Wind farm layout

Page 25: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 25

Wind farm layout

Design choices:

•Number of turbines and turbine rating

•Outline shape•Spacing•Relative positions•Positions w.r.t. geographical marks

•Number of support structure designs

Considerations:

•Wake losses

•Electrical losses and costs E-infrastructure

•(Annual) Energy yield

•Indication of costs and technical feasibility

•Planning (users/infrastructure)

Page 26: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 26

Wind farm layout (example)

Filling the shallow with a 10x8 array (6-14 m depth, 560 m spacing, 20 km2)

160 MW = 80 x 2 MW

Page 27: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 27

Wind farm layout (example)

VisualisationWake losses

Page 28: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 28

Wind farm layout (example)

Indication of energy yield, site optimisation, orientation w.r.t prevailing wind direction

Page 29: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 29

Wind farm layout (example)

Stable bank, consisting of:• Sand• Gravel• Pebble gravel• Stones

Variation within farm resulted in single monopile design, with variable length.

Page 30: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

30

Rotor-nacelle assembly

Page 31: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 31

Rotor-nacelle assembly

Design choices: (Generally selection and not design)

•Rating, power and thrust•Control concept•Electrical system•Gearbox / direct drive•Rotor size, number of blades and bending

•Hoisting systems

•Climate conditioning

Considerations:

•Efficiency / yield•Controllability•Loading and dynamics

•Minimum hub height and tip clearance

•Reliability / maintainability / serviceability

•Installation

Page 32: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 32

Rotor-nacelle assembly (example)

Vestas V80

2 MW, 80 m rotor, variable speed, pitch control, rated wind speed 13 m/s, doubly fed generator

Page 33: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

33

Support structure

Page 34: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 34

Support structure

Design choices:

•Concept and material

•Hub height

•(Element) shape and size

•Access facilities

•Cable tie-in

•Transition piece

Considerations:

•Rotor clearance / air gap•Energy yield w.r.t. shear•Structural reliability and lifetime

•Seabed scour•Manufacture and onshore logistics

•Installation•(Turbine) maintenance

Page 35: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 35

Support structure (example)

• 4 m foundation piles• Wall thickness 5 cm• 22 - 24 m penetration• Transition piece

• 4.6 m diameter• 6 m grout

• Platform 9 m above sea• 61 m conical tower• 70 m hub height• Total mass 340-390 ton

Page 36: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 36

Support structure (example)

Environmental conditions: wind, waves AND correlation (scatter diagram)

Page 37: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 37

Support structure (example)

Transition piece with boat landing and platform Cable tie-in and J-tubes

(1x, 2x or 3x, PVC)

Page 38: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

38

Scour protection

Page 39: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 39

Scour protection

Design choices:

•Apply or not?

•Concept

•Overall size

•Specification of elements (rock)

Considerations:

•Necessity

•Support function of soil

•Filter effect

•Stability (self and surrounding soil)

•Installation

Page 40: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 40

Scour protection (example)

Gravel mattress (soil filter)0.5 m, grading 0.03-0.2 mGravel/stone armour layer0.8 m, grading 0.35-0.55 m

Specialised installation equipment (existing)

27 m width �

Page 41: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

41

Electrical collection

Page 42: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 42

Electrical collection

Design choices:

•Topology•Voltage level•AC or DC•Cable type and size•Transformers, inverters, rectifiers, switches, …

•Cable protection•Connections (above/below surface)

Considerations:

•Installation

•Risks (switch/re-route)

•Hydrodynamic conditions

•Capacity and losses

•Necessary conversions

•Controllability

Page 43: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 43

Electrical collection (example)

5 double strings, AC36 kV (Medium Voltage)No submerged connections (connections in turbines)

Triple-core copper cable with lead shielding houses fibre optics for

communication

Page 44: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

44

Electrical transmission

Page 45: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 45

Electrical transmission

Design choices:

•Route•Voltage level•AC or DC•Cable type, size and number

•Transformers, inverters, rectifiers, switches, shunt inductors, …

•Cable protection

Considerations:

•Installation

•Planning

•Risks (cable ploughing)

•(Extreme) hydrodynamic conditions

•Capacity and losses

•Necessary conversions

•Controllability

Page 46: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 46

Electrical transmission (example)

AC, 150 kV (High Voltage) - Triple-core trenched cable

Page 47: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

47

Other structures

Page 48: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 48

Other structures

Design choices:

•Met-mast

•Transformer platform

•O&M base

•Shunt inductor platforms (electrical transmission)

Considerations:

•Necessity

•Possible combinations (also with turbine support structures)

•Function

•Structural reliability

•Moment of installation (met-mast)

Page 49: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 49

Other structures (example)

Installed spring 1999Stand-alone (energy, data tx)1.7 m monopile, square lattice15, 30, 45, 62 m met. sensors58 m extra, separate system2 wave riders + Doppler radar

Storm, 3/12/99

Page 50: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 50

Other structures (example)

20 x 28 m substation, housing• Transformer 36/150 kV• Electronic systems• Emergency diesel generator• Fire extinguisher (sea water)• Staff facilities• Helipad• Crawler crane• Man over board boat

Existing installation equipment (oversized for turbines)

Page 51: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

51

Installation

Page 52: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 52

Installation

Design choices: (installation of structures, cables and (scour) protection)

•Equipment

•Adaptations

•Logistics

•Procedures

•Workability limits

Considerations:

•Duration (w.r.t. season)

•Workability

•Stability of equipment as working platform

•Component weights, dimensions, connections

•Equipment availability

Page 53: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 53

Installation (example)

1. Foundation2. Transition piece3. Lower tower4. Upper tower5. Nacelle with two blades6. Third blade

Modified container carrier ‘Ocean Hanne’

FromA2SEA

Page 54: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 54

Installation (example)

Pile, scour protection and transition piece installation sequence

1. 2.

3. 4.

Page 55: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 55

Installation (example)

Pile driving of 4 m pile with existing equipment

Page 56: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 56

Installation (example)

Specialised installation equipment (existing)

Page 57: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 57

Installation (example)

The overall schedule

Page 58: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 58

Installation (example)

Installation and commissioning in

groups of 16 turbines

Page 59: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

59

Operation

Page 60: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 60

Operation

Design choices:

•Periods for scheduled service

•Farm/power plant control

•Spot market strategy

Considerations:

•Service needs

•Controllability

•Value of energy quantity, power and control quality

•Persistence of power

•Predictability of wind

Page 61: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 61

Operation (Example)25

20

15

10

5

0

Win

dsp

eed

atH

ub

hei

gh

t (m

/s)

10

8

6

4

2

01000 1100 1200 1300 1400 1500 1600 1700 1800 1900 2000 2100 2200

Far

m p

ow

er(M

W)

Time (sec)

ENERCON

(Not taken from Horns Rev wind farm)

Page 62: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

62

Maintenance

Page 63: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 63

Maintenance

Design choices:

•Equipment

•Logistics

•Procedures

•Workability limits

•Crew deployment

•Decision support

Considerations:

•Component reliability

•Difference and similarity of maintenance needs

•Accessibility/workability

•Duration of procedures (w.r.tdowntime and weather windows)

Page 64: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 64

Maintenance (example)

Scada – Supervisory control & data acquisition

Page 65: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 65

Maintenance (example)

Access of personnel and small parts

Combination of boat and helicopter access

Page 66: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 66

Maintenance (example)Two annual general service inspections planned per turbine

In addition 1-3 service checks after failure

(Prototype at Tjæreborg)

Page 67: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 67

Maintenance (example)

Weather climate used to predict general workability

Weather forecast used to plan activities. Here:Wave conditions according to DMI (Danmarks MeteorologiskeInstitut)

Page 68: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

68

Dismantling

Page 69: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 69

Dismantling

Design choices:

•Equipment

•Adaptations

•Logistics

•Procedures

•Workability limits

Considerations:

•Duration (w.r.t. end of license)

•Workability

•Reusable components

•Waste and pollution

•Off-season for equipment (less time critical)

Page 70: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 70

Dismantling (example)

Fortunately no example of dismantling for Horns Rev!

Page 71: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

71

Cost of energy

Page 72: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 72

Levelised Production Cost

( )

( )∑

=

=

+

+=

T

t

tt

T

t

tt

rE

rC

LPC

0

0

1

1C = costsE = energy productionr = real interest ratet = year in lifecycleT = economic lifetime

(Actualised-nominal values)

(Weighted for amortisation benefit)LPC =

Page 73: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 73

Distribution of costs and yield

0.0

0.2

0.4

0.6

0.8

1.0

1.2

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20Time (years)

Costs:

Yield:

Weight (-)

Investment

Operation and Maintenance

Decommissioning

Page 74: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 74

Typical contributions to LPC (1)

• Start-up of entire farm after construction

• Annual O&M costs are constant

• Annual energy production is constant

• Decommissioning after shut-down of farm

( )y

TD

y

MO

y

invest

aE

rC

E

C

aE

CLPC

'& 1' −+++=

(a = Annuity factor)

Assumptions

Page 75: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 75

Typical contributions to LPC (2)

Decommissioning3%Operation

and Maintenance

23%

Investment74%

Page 76: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 76

Cost component breakdown

Power collection

13%

Project management

2%Wind

turbine45%

Support structure

25%

power transmission

8%

OWEC installation

7%

Investmentcost breakdown

Page 77: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 77

Detailed breakdown

transformers13%

transformer support structure

2%

switchgears8%

cable material39%cable laying

38%

Power collection and transmission cost breakdown

Page 78: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008

78

Appendix

Necessary information for design considerations

Page 79: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 79

Site selection

Necessary information:

• Wind speed distribution – general wind farm scale

• General water depth – bathymetry (w.r.t. structure and offshore equipment)

• General environmental conditions (w.r.t loading, accessibility, lightning, …)

• Location and specification of grid connection points, landfalls,harbours, consumers (end-clients)

• Other users and infrastructure (incl. other wind farms)

• General developments in these issues

Page 80: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 80

Wind farm layout

Necessary information:

• Size (rating) of the wind farm

• Possible preferences/restriction for turbine selection

• Wind speed distribution

• Aerodynamic properties of the turbine (thrust/power)

• Trends of costs and losses of the E-infrastructure

• Variation of water depth, soil conditions and other issues w.r.t. support structure design within the area

• Other users and infrastructure

Page 81: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 81

Rotor-nacelle assembly

Necessary information:

• Available turbines, preferences or pre-selection

• Turbine data

• Configurability (design adaptations or options)

• Precise environmental conditions w.r.t. design requirements (wind, lightning, …) and yield

• Installation and maintenance options

Page 82: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 82

Support structure

Necessary information:

• Rotor diameter, tilt and cone angle, blade bending

• Precise water depth

• Precise environmental conditions (w.r.t loading)

• Precise soil conditions

• Turbine loading characteristics (extremes, fatigue, damping, dynamic behaviour, mass, …)

Page 83: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 83

Scour protection

Necessary information:

• Effect of omitting scour protection

• Volume of soil active in resistance of loading

• Soil grading

• Water depth

• Dimensions of support structure

• Wave and current conditions

Page 84: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 84

Electrical collection

Necessary information:

• Soil conditions

• Wind farm layout

• Quantity and variation of electricity per turbine

• Properties of electrical transmission and turbine electrical system

• Existing technology (power electronics, subsea connectors and installation options)

Page 85: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 85

Electrical transmission

Necessary information:

• Soil conditions

• Other users and infrastructure

• Distance and location of public grid and landfalls

• Quantity and variation of electricity supply

• Properties of public grid and farm grid

• Existing technology (power electronics)

Page 86: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 86

Other structures

Necessary information:

• Functional requirements

• Precise environmental conditions

• Precise soil conditions

• Possibility to adapt turbine support structures

• (For met-mast:) Existence and quality of data on environmental conditions (w.r.t. loading and energy)

Page 87: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 87

Installation

Necessary information:

• Dimensions and properties of components that will be installed (masses, cable bending and pull strength, …)

• Connections and sequence of assembly

• General environmental conditions (w.r.t. workability)

• Equipment options (which types of equipment exist)

• Equipment data: availability, mobilisation times, workability limits/dynamic behaviour

• Facilities and location(s) of harbour(s)

Page 88: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 88

Operation

Necessary information:

• Periodicity and duration of service

• Turbine controllability and park-grid controllability

• Availability and power output

• kWh prices on spot market

• Penalties for not meeting Unit Commitment

• Regulations and compensation for power control

• Wind prediction accuracy (function of prediction time, weather conditions, …)

Page 89: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 89

Maintenance

Necessary information:

• Failure modes and maintenance requirements: properties of (spare) parts, replacement prescriptions

• Onshore logistics: spare part storage and ordering

• General environmental conditions (w.r.t. workability)

• Equipment options (which types of equipment exist)

• Equipment data: availability, mobilisation times, workability limits/dynamic behaviour

• Facilities and location(s) of harbour(s)

Page 90: For offshore wind farms - TU Delft OCW · For offshore wind farms ... • Technological preferences or constraints ... (Report used in the project “Design methods for offshore wind

2007-2008 90

Dismantling

Necessary information:

• Dimensions and properties of components

• Handling requirements for reusable components

• Policy and regulations for waste (e.g. cut-off piles)

• General environmental conditions (w.r.t. workability)

• Equipment options

• Equipment data: availability, mobilisation times, workability limits/dynamic behaviour