FINAL ENVIRONMENTAL IMPACT ASSESSMENT REPORT FOR PROPOSED UNIT OF M/s. SHREY INDUSTRIES Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat) [Proposed Product: Pigment Green 7 @ 100 MT/M] Schedule-5(f) & Category – A TOR Letter No.: IA-J-11011/369/2018-IA-II(I), Dated-31/12/2018 Study Period: October-November-December, 2018 PREPARED BY BHAGWATI ENVIRO CARE PVT. LTD. [ISO 9001, ISO 14001 & OHSAS: 18001 CERTIFIED COMPANY] (QCI/NABET Certificate No. NABET/EIA/1921/RA 0156) CORPORATE OFFICE 28, 29, 30, Parmeshwar Estate II, Opp. AMCO Bank, Phase I, GIDC Estate, Vatva, Ahmedabad – 382445. Gujarat, India Phone No: +91 79 29295043, 40083051/52 Fax: +91 79 40083053 , Email: [email protected] , [email protected] URL: www.bhagwatienviro.com

Upload: others

Post on 30-Jan-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

  • FINAL ENVIRONMENTAL IMPACT ASSESSMENT REPORT

    FOR

    PROPOSED UNIT

    OF

    M/s. SHREY INDUSTRIES Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol,

    Dist: Gandhinagar (Gujarat)

    [Proposed Product: Pigment Green 7 @ 100 MT/M]

    Schedule-5(f) & Category – A TOR Letter No.: IA-J-11011/369/2018-IA-II(I), Dated-31/12/2018

    Study Period: October-November-December, 2018

    PREPARED BY

    BHAGWATI ENVIRO CARE PVT. LTD. [ISO 9001, ISO 14001 & OHSAS: 18001 CERTIFIED COMPANY]

    (QCI/NABET Certificate No. NABET/EIA/1921/RA 0156)

    CORPORATE OFFICE

    28, 29, 30, Parmeshwar Estate II, Opp. AMCO Bank, Phase I, GIDC Estate, Vatva, Ahmedabad – 382445. Gujarat, India Phone No: +91 79 29295043, 40083051/52 Fax: +91 79 40083053 , Email: [email protected] , [email protected]

    URL: www.bhagwatienviro.com

  • Annexure - A_NABET Accreditation Certificate

    I

  • Prepared By: - Bhagwati Enviro Care Pvt. Ltd.

    INDEX

    Table of Contents

    Clause No. Content Page No.

    ANN - A NABET Accreditation Certificate I

    CHAPTER 1. 1 to 23 INTRODUCTION

    1.1 INTRODUCTION 1

    1.2 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT 1

    1.3 PURPOSE OF THE STUDY 3

    1.4 IDENTIFICATION OF PROJECT PROPONENT 4

    1.5 BRIEF DISCRIPTION OF NATURE SIZE, LOCATION OF THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY, RIGION

    4

    1.6 SCOPE & METHODOLOGY OF STUDY 5

    1.7 STUDY AREA 7

    1.8 APPLICABLE ENVIRONMENT REGULATIONS 8

    1.9 STRUCTURE OF EIA 8

    1.10 COMPLIANCE OF TOR 10

    CHAPTER 2 24 to 88 PROJECT DESCRIPTION

    2.1 INTRODUCTION 24

    2.2 TYPE OF PROJECT 24

    2.3 NEED OF THE PROJECT 25

    2.4 LOCATION 26

    2.5 PHOTOGRAPH OF THE PROPOSED PROJECT SITE 33

    2.6 JUSTIFICATION OF SITE SELECTION 35

    2.7 SIZE OR MAGNITUDE OF OPERATION 36

    2.8 PRODUCT DETAILS 36

    2.9 RAW MATERIAL REQUIREMENT 37

    2.10 RAW MATERIAL STORAGE 38

    2.11 HANDLING OF RAW MATERIAL & PRODUCT 40

    2.12 MODE OF TRANSPORTATION FOR RAW MATERIAL 40

    2.13 MANUFACTURING PROCESS DETAILS, CHEMICALS REACTIONS & MASS BALANCE

    41

    2.14 RESOURCE REQUIREMENT 45

    2.15 LAND USE BREAKUP FOR TOTAL PLOT AREA 46 2.16 LIST OF PLANT MACHINERIES FOR PROPOSED PRODUCTION ACTIVITY 47

    2.17 DETAIL OF MAN POWER REQUIREMENT 47

  • Prepared By: - Bhagwati Enviro Care Pvt. Ltd.

    2.18 POWER REQUIREMENT 48

    2.19 PROPOSED SCHEDULE FOR APPROVAL AND IMPLEMENTATION 48

    2.20 PLANT WATER REQUIREMENT & EFFLUENT GENERATION 50

    2.21 CHARACTERISTICS OF EFFLUENT 53

    2.22 DETAIL OF EFFLUENT TREATMENT PLANT 55

    2.23 FLUE GAS EMISSION 56

    2.24 PROCESS GAS EMISSION 59

    2.25 FUEL REQUIREMENT 59

    2.26 FUGITIVE EMISSION CONTROL 60

    2.27 HAZARDOUS WASTE MANAGEMENT 61

    2.28 NOISE POLLUTION 63

    2.29 LIST OF HAZARDOUS CHEMICALS 64

    2.30 SAFETY & OCCUPATIONAL MEASURE FOR STORAGE &HANDLING OF THE RAW MATERIAL & PRODUCT

    67

    2.31 ACTION PLAN FOR TRANSPORTATION OF RAW MATERIALS AND PRODUCTS INCLUDING HAZARDOUS CHEMICALS

    73

    2.32 COST OF THE PROJECT 75

    2.33 GREENBELT DEVELOPMENT 76

    2.34 SCHEME FOR RAIN WATER HARVESTING 77

    2.35 SOLVENT RECOVERY SYSTEM 84

    2.36 REGULATORY FRAME WORK 86

    2.37 SUMMARY 88

    CHAPTER 3. 89 to 187 DESCRIPTION OF ENVIRONMENT

    3.1 INTRODUCTION 89

    3.2 STUDY AREA & STUDY PERIOD 89

    3.3 METHODOLOGY OF BASELINE STUDY 96

    3.4 FREQUENCY AND METHODOLOGY FOR MONITORING 97

    3.5 ENVIRONMENTAL STANDARDS OF THE REGION 99

    3.6 BASELINE ENVIRONMENT 99

    3.7 AIR ENVIRONMENT 99

    3.7.1 AMBIENT AIR QUALITY (AAQ) IN THE STUDY AREA 99

    3.7.2 THE LOCATION OF AAQ STATIONS 100

    3.7.3 BASE LINE DATA 100

    3.7.4 SAMPLING ANALYSIS 110

    3.8 METEOROLOGY 111

    3.9 BASELINE DATA 111

    3.9.1 AMBIENT TEMPERATURE 111

    3.9.2 WIND SPEED 111

    3.9.3 WIND DIRECTION 111

    3.9.4 RELATIVE HUMIDITY (RH) 116

    3.9.5 CLIMATE & RAIN FALL 116

    3.9.6 TOPOGRAPHY 117

    3.9.7 MIXING HEIGHT 118

  • Prepared By: - Bhagwati Enviro Care Pvt. Ltd.

    3.10 ATMOSPHERIC STABILITY 119

    3.11 NOISE ENVIRONMENT 119

    3.12 WATER ENVIRONMENT 130

    3.13 LAND ENVIRONMENT 136

    3.14 TYPES OF SOIL 137

    3.15 LAND USE PATTERN 144

    3.16 SEISMICITY OF THE STUDY AREA 147

    3.17 HYDROGEOLOGY 148

    3.18 ECOLOGY 151

    3.19 SOCIO ECONOMIC ENVIRONMENT 160

    3.20 ECONOMIC ATTRIBUTES 171

    3.21 AVAILABILITY OF BASIC AMENITIES 177

    3.22 SOCIO ECONOMIC SURVEY 183

    CHAPTER 4. 188 to 245 ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES

    4.1 INTRODUCTION 188

    4.2 IMPACT IDENTIFICATION 189

    4.2.1 ENVIRONMENTAL PARAMETER 189

    4.2.2 IDENTIFICATION MATRIX 191

    4.3 IMPACT PREDICTION AND ASSESSMENT WITH MITIGATIVE MEASURE

    195

    4.4 AIR ENVIRONMENT 196

    4.5 WATER ENVIRONMENT 228

    4.6 SOLID/HAZARDOUS WASTE 231

    4.7 NOISE ENVIRONMENT 233

    4.8 LAND/SOIL ENVIRONMENT 235

    4.9 TOPOGRAPHY 238

    4.10 HYDROLOGY & GEOLOGY 238

    4.11 ECOLOGY 239

    4.12 SOCIO ECONOMIC ENVIRONMENT 241

    4.13 HEALTH & SAFETY 242

    4.14 TRAFFIC STUDY & ITS IMPACT 243

    CHAPTER 5. 246 to 248 ANALYSIS OF ALTERNATIVES (TECHNOLOGY & SITES)

    5.1 SITE ALTERNATIVES 246

    5.2 ALTERNATIVES FOR TECHNOLOGIES 247

    CHAPTER 6. 249 to 261 ENVIRONMENTAL MONITORING PROGRAM

    6.1 PREAMBLE 249

    6.2 MONITORING OF ENVIRONMENT 249

  • Prepared By: - Bhagwati Enviro Care Pvt. Ltd.

    6.3 WORK ZONE MONITORING ARRANGEMENT FOR HAZARDOUS CHEMICALS

    252

    6.4 CHEMICALS WHICH ARE EXPOSED TO WORKERS DIRECTLY OR INDIRECTLY

    254

    6.5 INFRASTRUCTURAL REQUIREMENT & PROCUREMENT SCHEDULES 254

    6.6 CORPORATE ENVIRONMENTAL RESPONSIBILITY 255

    6.7 ENVIRONMENTAL POLICY 256

    6.8 ENVIRONMENTAL MANAGEMENT CELL 257

    6.9 ADMINISTRATIVE ACTIONS & DOCUMENTATION 260

    6.9.1 ANALYSIS 260

    6.9.2 REPORTING SCHEDULE 260

    6.9.3 ENVIRONMENTAL MONITORING EXPENDITURE 260

    CHAPTER 7. 262 to 317 ADDITIONAL STUDIES

    7.1 PUBLIC CONSULTATION 262

    7.2 ACTION PLAN WITH COMMITMENTS IN TIME BOUND MANNER FOR ISSUED RAISED DURING PUBLIC HEARING

    263

    7.3 RISK ASSESSMENT 265

    7.4 IDENTIFICATION OF HAZARDS 267

    7.5 SAFE PRACTICES [HANDLING, STORAGE, TRANSPORTATION AND UNLOADING OF CHEMICALS]

    287

    7.5.1 DRUMS 287

    7.5.2 MEASURES TO AVOID EVAPORATION 287

    7.5.3 SAFETY SYSTEMS 287

    7.5.4 STORAGE & HANDLING OF HAZARDOUS CHEMICAL 287

    7.5.5 TRANSPORTATION/UNLOADING 288

    7.5.6 SAFETY INSTRUCTION FOR TRANSPORTATION OF HAZARDOUS MATERIAL

    288

    7.6 SPILL CONTROL 289

    7.7 EFFECT AND CONSEQUENCE ANALYSIS 289

    7.7.1 OPERATING PARAMETERS 289

    7.7.2 INVENTORY 290

    7.7.3 LOSS OF CONTAINMENT 290

    7.8

    GENERAL SAFETY MEASURES AND SPECIFIC SAFETY MEASURES ADOPTED FOR TRANSPORTATION, STORAGE & HANDLING (SPILLAGE AND LEAKAGE) OF HAZARDOUS CHEMICALS ARE LISTED AS FOLLOWS

    291

    7.9 OCCUPATIONAL HEALTH & SAFETY PROGRAM 292

    7.10 MONITORING PROGRAM 293

    7.11 ONSITE & OFFSITE DISASTER PREPAREDNESS & EMERGENCY MANAGEMENT PLAN OF THE INDUSTRY

    301

    7.12 SOCIAL IMPACT ASSESSMENT 316

    CHAPTER 8. 318 to 326

  • Prepared By: - Bhagwati Enviro Care Pvt. Ltd.

    PROJECT BENEFITS

    8.1 INTRODUCTION 318

    8.2 IMPROVEMENT IN PHYSICAL INFRASTCTURE 318

    8.3 IMPROVEMENT IN SOCIAL INFRASTCTURE 318

    8.4 CORPORATE SOCIAL RESPONSIBILITY (CSR) & SOCIO-ECONOMIC DEVELOPMENT

    319

    8.5 DIRECT REVENUE EARNING TO THE NATIONAL AND STATE EXCHEQUER

    324

    8.6 INFRASTRUCTURAL BENEFIT 325

    8.7 OTHER TANGIBLE BENEFITS 325

    8.8 EMPLOYMENT POTENTIAL 325

    CHAPTER 9. 327 ENVIRONMENTAL COST BENEFIT ANALYSIS

    9.1 COST BENEFIT ANALYSIS 327

    CHAPTER 10. 328 to 377 ENVIRONMENTAL MANAGEMENT PLAN

    10.1 INTRODUCTION 328

    10.2 THE EMP 328

    10.3 OBJECTIVES OF EMP 329

    10.4 PRE- PROJECT ENVIRONMENTAL MANAGEMENT PLAN 332

    10.5 ENVIRONMENTAL MANAGEMENT DURING OPERATION 334

    10.5.1 AIR POLLUTION 341

    10.5.2 STORAGE &TRANSPORTATION OF RAW MATERIAL 342

    10.5.3 FUGITIVE EMISSION 342

    10.5.4 SOLVENT MANAGEMENT PLAN 342

    10.5.5 NOISE POLLUTION 344

    10.5.6 WATER QUALITY 345

    10.5.7 HAZARDOUS/SOLID WASTE MANAGEMENT 347

    10.5.8 ECOLOGY & BIODIVERSITY 348

    10.5.9 SOCIO ECONOMIC ASPECTS 349

    10.5.10 HYDROGEOLOGY, GROUND WATER & WATER CONSERVATION 349

    10.5.11 GEOLOGY 350

    10.5.12 SOIL CONSERVATION 350

    10.5.13 RISK & HAZARDS MANAGEMENT 351

    10.6 GREENBELT DEVELOPMENT 351

    10.7 HEALTH AND SAFETY 355

    10.8 OCCUPATIONAL HEALTH HAZARDS. 355

    10.9 DETAILS OF OCCUPATIONAL HEALTH SURVEILLANCE 362

    10.10 HAZARDOUS IDENTIFICATION AND PREVENTIVE MEASURES 363

    10.11 EXPENDITURE ON ENVIRONMENTAL MATTERS 368

    10.12 CONCEPT OF WASTE MINIMIZATION, RECYCLE / REUSE / 369

  • Prepared By: - Bhagwati Enviro Care Pvt. Ltd.

    RECOVER TECHNIQUES, ENERGY CONSERVATION AND NATURAL RESOURCES CONSERVATION

    10.13 CHECKLIST IN THE FORM OF DO’S AND DON’T 372

    10.14 SOCIO ECONOMIC DEVELOPMENT ACTIVITY 375

    10.15 INFRASTRUCTURE FACILITIES TO THE LABOURS DURING CONSTRUCTION PHASE

    375

    10.16 ODOUR CONTROL MEASURES 376

    CHAPTER 11. 378 to 396 SUMMARY & CONCLUSION OF EIA REPORT

    11.1 SALIENT FEATURES OF THE PROJECT 379

    11.2 AIR ENVIRONMENT. 382

    11.3 WATER ENVIRONMENT 384

    11.4 NOISE ENVIRONMENT 385

    11.5 HAZARDOUS WASTES 387

    11.6 ECOLOGY 387

    11.7 SOCIO ECONOMIC ENVIRONMENT 388

    11.8 LAND USE 388

    11.9 TOPOGRAPHY 389

    11.10 GREENBELT DEVELOPMENT 389

    11.11 SOIL QUALITY 390

    11.12 ENVIRONMENTAL MANAGEMENT PLAN 391

    11.13 CONCLUSION 396

    CHAPTER 12. 397 to 398 DISCLOSURE OF CONSULTANT ENGAGED

  • Prepared By: - Bhagwati Enviro Care Pvt. Ltd.

    List of Figures / Maps

    Fig/Map No. Content Page No.

    CHAPTER: - 1

    1.1 METHODOLOGY OF EIA STUDY 7

    CHAPTER: - 2

    2.1 MAP OF GUJARAT 27

    2.2 MAP OF GANDHINAGAR DISTRICT 28

    2.3 5 KM & 10 KM RADIOS MAP OF THE PROJECT SITE 29

    2.4 LAYOUT PLAN 30

    2.5 GOOGLE IMAGE OF M/S .SHREY INDUSTRIES 31

    2.6 TOPOGRAPHY MAP OF M/S. SHREY INDUSTRIES 32

    2.7 PROJECT IMPLEMENTATION SCHEDULE 49 2.8 WATER BALANCE DIAGRAM 52

    2.9 EFFLUENT TREATMENT PLANT DIAGRAM 55

    2.10 FIRE HYDRANT DIAGRAM 72

    2.11 SYSTEMATIC DESIGN OF THE RW HARVESTING STRUCTURES 81

    2.12 SOLVENT RECOVERY SYSTEM 85

    CHAPTER: - 3

    3.1 STUDY AREA MAP OF BASE LINE STUDY FOR 5 KM RADIUS AND 10 KM RADIUS

    92

    3.2 TOPOSHEET MAP 93

    3.3 SAMPLING LOCATIONS MAP 95

    3.4 WIND ROSE DIAGRAM. 112

    3.5 WIND CLASS FREQUENCY DISTRIBUTION GRAPH 115

    3.6 GEOLOGICAL STRUCTURE OF GUJARAT STATE 137

    3.7 LAND USE / LAND COVER MAP OF 10 KM RADIUS AREA AROUND PROJECT SITE

    146

    3.8 SEISMIC ZONES OF GUJARAT 147

    3.9 FOREST VEGETATION MAP OF GUJARAT 158

    3.10 NATIONAL PARK AND SANCTUARIES OF GUJARAT 159

    3.11 POPULATION DETAILS 167

    3.12 LITERACY DETAILS 167

    3.13 EMPLOYMENT PATTERN 172

    3.14 MAIN WORKER EMPLOYMENT PATTERN 172

    CHAPTER: - 4

    4.1 ISOPLETHS OF SPM 217

    4.2 ISOPLETHS OF SO 2 219

    4.3 ISOPLETHS OF NOx 221

  • Prepared By: - Bhagwati Enviro Care Pvt. Ltd.

    4.4 ISOPLETHS OF HCl 223

    4.5 ISOPLETHS OF Cl2 225

    CHAPTER: - 6

    6.1 ENVIRONMENT MANAGEMENT CELL 258

    CHAPTER: - 7

    7.1 EMERGENCY MANAGEMENT CHART FOR ONSITE EMERGENCY 304

    CHAPTER: - 10

    10.1 FLOW CHART OF EMP 331

    10.2 SCHEMATIC DIAGRAM OF PROPOSED WASTE WATER TREATMENT- ZLD SYSTEM

    346

  • Prepared By: - Bhagwati Enviro Care Pvt. Ltd.

    List of Tables

    Table No. Content Page No.

    CHAPTER:- 1

    1.1 TOR COMPLIANCE 11

    CHAPTER:- 2

    2.1 LOCATION OF THE PROJECT 26

    2.2 SALIENT FEATURES OF THE PROJECT SITE 24

    2.3 NEAREST INDUSTRIES OF THE PROJECT SITE 35

    2.4 LIST OF PRODUCT 36

    2.5 PACKING & FINAL APPLICATION OF PRODUCTS 37

    2.6 DETAIL OF RAW MATERIALS 37

    2.7 CHEMICALS NAME & PHYSICAL FORM OF RAW MATERIAL 38

    2.8 PHYSICAL & CHEMICAL PROPERTIES OF RAW MATERIALS 39 2.9 DETAIL OF SOURCE 45

    2.10 LAND USE BREAK UP FOR TOTAL PLOT AREA 46

    2.11 LIST OF PLANT MACHINERIES FOR PROPOSED PRODUCTION ACTIVITY 47

    2.12 DETAILS OF MAN POWER 48

    2.13 DETAIL OF WATER CONSUMPTION & EFFLUENT GENERATION 50

    2.14 CHARACTERISTICS OF INDUSTRIAL EFFLUENT 53

    2.15 DETAIL OF PROPOSED EFFLUENT TREATMENT PLANTS UNITS 55

    2.16 FLUE GAS STACK DETAIL 56

    2.17 EMISSION RATE OF THE POLLUTANTS 57

    2.18 PROCESS GAS STACK DETAIL 59

    2.19 FUEL DETAIL 59

    2.20 DETAIL OF HAZARDOUS WASTE MANAGEMENT 61

    2.21 TYPICAL NOISE LEVELS OF EQUIPMENT 63

    2.22 LIST OF HAZARDOUS CHEMICALS 64

    2.23 DETAIL OF FIRE EXTINGUISHERS 70

    2.24 DETAIL OF FIRE-WATER PUMP 71

    2.25 DETAIL OF PROVISION FOR FIRE-FIGHTING SYSTEM 71

    2.26 ANTIDOTES OF CHEMICALS 73

    2.27 CAPITAL COST & RECURRING COST OF THE PROJECT FOR EMP 75

    2.28 DETAIL OF SOLVENT RECOVERY 85

    CHAPTER:- 3

    3.1 NAME OF VILLAGES IN THE STUDY AREA 90

    3.2 ENVIRONMENT ATTRIBUTES & FREQUENCY OF MONITORING 97

    3.3 LOCATION OF AMBIENT AIR QUALITY MONITORING STATIONS 100

    3.4 AMBIENT AIR QUALITY RESULTS (MIN, MAX, AVG AND 98%) FOR INDIVIDUAL LOCATIONS

    101

    3.4(a) AMBIENT AIR QUALITY ANALYSIS REPORT FOR THE MONTH OF OCTOBER 103

  • Prepared By: - Bhagwati Enviro Care Pvt. Ltd.

    TO DECEMBER 2018

    3.4 (b) VOC & OTHER GASES ANALYSIS REPORT FOR THE MONTH OF OCTOBER TO DECEMBER 2018

    107

    3.5 DETAILS OF AMBIENT AIR QUALITY MONITORING AND ANALYSIS PROCEDURE

    110

    3.6 WIND ROSE (FREQUENCY DISTRIBUTION DATA) 113

    3.7 WIND ROSE FREQUENCY COUNT 114

    3.8 RELATIVE HUMIDITY 116

    3.9 RAINFALL PATTERN AT GANDHINAGAR RAIN GAUGE STATION 117

    3.10 HOURLY MIXING DEPTH OVER INDIAN REGION 118

    3.11 AMBIENT NOISE LEVELS WITHIN STUDY AREA 120

    3.12 NOISE LEVEL IN THE STUDY AREA 122

    3.13 LOCATION OF WATER QUALITY MONITORING STATION 131

    3.14(a) WATER QUALITY ANALYSIS RESULT FOR GROUND WATER 133

    3.14(b) WATER QUALITY ANALYSIS RESULT FOR SURFACE WATER 135

    3.15 ANALYSIS RESULTS OF SOIL SAMPLE 139

    3.16 STANDARD SOIL CLASSIFICATION 143

    3.17 LAND USE DISTRIBUTION IN STUDY AREA (10 KM RADIAL ZONE) 145

    3.18 HYDRO GEOLOGICAL CHARACTERISTICS AQUIFER 150

    3.19 LIST OF COMMONLY FOUND FLORA IN THE STUDY AREA 153

    3.20 BIRD SPECIES REPORTED DURING THE STUDY 155

    3.21 MAMMALS SPECIES REPORTED DURING THE STUDY 157

    3.22 POPULATION DETAILS 164

    3.23 LITERACY DETAILS 168

    3.24 EMPLOYMENT PATTERN AND MAIN WORKER EMPLOYMENT PATTERN 173

    3.25 MAIN WORKER EMPLOYMENT PATTERN 175

    3.26 AVAILABILITIES OF BASIC AMENITIES ACTIVITIES 177

    3.27 MAIN COMMODITIES IN THE STUDY AREA 181

    3.28 NAME OF VILLAGE FOR SURVEY IN THE STUDY AREA 185

    CHAPTER:- 4

    4.1 IMPACT IDENTIFICATION MATRIX 193

    4.2 IMPACT PREDICTION MATRIX 194

    4.3 BASIS OF EMISSION RATE CALCULATIONS 199

    4.4 MAXIMUM COMPUTED GROUND LEVEL CONCENTRATION 203

    4.5 CUMULATIVE CONCENTRATION DUE TO INCREMENTAL GLC’S 204

    4.6 THE 1ST HIGHEST 24 HR AVERAGE CONCENTRATION VALUES OF PM10 207

    4.7 THE 1ST HIGHEST 24 HR AVERAGE CONCENTRATION VALUES OF SO2 209

    4.8 THE 1ST HIGHEST 24 HR AVERAGE CONCENTRATION VALUES OF NOx 211

    4.9 THE 1ST HIGHEST 24 HR AVERAGE CONCENTRATION VALUES OF HCl 213

    4.10 THE 1ST HIGHEST 24 HR AVERAGE CONCENTRATION VALUES OF Cl2 215

    4.11 TOTAL WATER REQUIREMENT FOR PROPOSED PROJECT 230

    4.12 TOTAL WASTE WATER GENERATION 230

    4.13 SOLID/HAZARDOUS WASTE GENERATION AND DISPOSAL MODE 232

    4.14 TRAFFIC STUDY 243

  • Prepared By: - Bhagwati Enviro Care Pvt. Ltd.

    4.15 ASSESSMENT OF PROPOSED TRAFFIC LOAD 244

    CHAPTER:- 6

    6.1 ENVIRONMENTAL MONITORING PLAN 250

    6.2 CORPORATE ENVIRONMENTAL RESPONSIBILITY 255

    6.3 RESPONSIBILITY OF EMC 259

    6.4 CAPITAL COST & RECURRING COST OF THE PROJECT FOR EMP 261

    CHAPTER:- 7

    7.1 AREA WISE IDENTIFIED HAZARDS, PRECAUTIONS TAKEN WITH MITIGATION MEASURES

    278

    7.2 MONITORING PROGRAM FOR OCCUPATIONAL HEALTH AND SAFETY 294

    7.3 POSSIBLE EMERGENCY - SPILLAGE IN CHEMICAL STORAGE AREA (SPILL CONTROL PLAN)

    297

    7.4 POSSIBLE EMERGENCY – TOXIC GAS RELEASE 300

    CHAPTER:- 10

    10.1 BUDGETARY EXPENDITURE FOR GBD 353

    10.2 PLANT SPECIES FOR GREEN BELT DEVELOPMENT 354

    10.3 DETAILS OF FIRE EXTINGUISHER 359

    10.4 DETAILS OF FIRE WATER PUMP 359

    10.5 DETAILS OF PROVISION FOR FIRE-FIGHTING SYSTEM 360

    10.6 CAPITAL COST & RECURRING COST OF THE PROJECT FOR EMP 368

    CHAPTER:- 11

    11.1 SALIENT FEATURES OF PROJECT SITE 380

    11.2 DETAIL OF SOURCE 382

  • Prepared By: - Bhagwati Enviro Care Pvt. Ltd.

    Annexure

    Annexure No. Topic Page No.

    1 APPROVED TOR FOR EIA STUDY FROM MOEF&CC, NEW DELHI. 399

    2 RISK ASSESMENT STUDY REPORT 408

    3 NATIONAL AMBIENT AIR QUALITY STANDARDS 456

    4 ICMR STANDARD FOR DRINKING WATER 458

    5 NATIONAL AMBIENT NOISE QUALITY STANDARDS AND OSHA’S PERMISSIBLE LIMIT FOR NOISE

    459

    6 LAND SUPPORTING DOCUMENTS 460

    7 UNDERTAKING OF CONSULTANT 488

    8 UNDERTAKING OF M/S. SHREY INDUSTRIES 489

    9 MEMEBRSHIP CERTIFICATE 490

    10 MATERIAL SAFETY DATA SHEET 491

    11 ADEQUACY REPORT OF SCHEDULE II 530

    12 WILD LIFE CONSERVATION PLAN 537

    13 ON SITE EMERGENCY PLAN 545

    14 TREATABILITY STUDY REPORT 586

    15 NABL CERTIFICATE 598

    16 MOEF ACCREDIATION CERTIFICATE 599

    17 FORM – 1 (FILLED DURING APPLICATION FOR TOR) 601

    18 PRE-FEASIBILITY REPORT 617

    19 ADDITIONAL ATTACHMENT 629 20 MOM OF PUBLIC HEARING 720 21 DETAIL OF PUBLIC HEARING 731

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 1

    CHAPTER 1

    INTRODUCTION

    1.1 Introduction

    M/s. SHREY INDUSTRIES is a proposed unit located at Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat). In their proposed unit, they will manufacture Pigment Green 7 @ 100 MT/M. Proposed unit is located outside notified industrial area So, the manufacturing of Synthetic organic chemical (Pigment Green 7) falls under Category “A” of EIA Notification issued in September – 2006. For this the unit needs Environmental clearance from Ministry of Environment Forest & Climate Change. The Final EIA studies are carried out as a part of process to obtain Environmental Clearance Certificate for the proposed project. Unit believes in sustainable development and equally concern about environment preservation and pollution control and proposes to provide adequate Environmental Management System to meet desired norms prescribe by statutory authority. In order to assess the Environmental Impacts of the proposed project, M/s. SHREY INDUSTRIES Entrusted Bhagwati Enviro Care Pvt. Ltd, Ahmedabad (NABET Accredited) to undertake Final Environmental Impact Assessment Study for various components of the Environment viz., Air, Water, Noise, Land and Socio-economics. This Report presents base line data collected for October-November-December 2018 for Air, Water, Noise, Land etc., for identification and assessment of the impacts.

    1.2 Identification of project and project proponent

    Environment Impact Assessment or EIA is a study to predict the effect of a proposed projection or its expansion activity on the environment. It is a management tool to facilitate appropriate decision; an EIA compares various alternatives for a project and seeks to identify the one, which represents the best combination of economic and environmental costs and benefits.

    It helps to identify possible environmental effects of the proposed project, proposes measures to mitigate adverse effects and predicts whether there will be significant adverse environmental effects, even after the mitigation is implemented. By considering environmental effects and mitigation early in the project planning cycle, environmental assessment has many benefits, such as protection of environment, optimum utilization of resources and saves overall time and cost of the project.

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 2

    On 27th January 1994, the Union Ministry of Environment and Forests (MoEF), Government of India, under the Environmental (Protection) Act 1986, promulgated EIA Notification making Environmental Clearance (EC) mandatory for expansion or modernization of any activity or for setting up new projects listed in Schedule of the notification and its subsequent amendments. On 14th September 2006, a new legislation was passed, which has objectives such as “To formulate a transparent, decentralized and efficient regulatory mechanism; to incorporate necessary environmental safeguards at planning stage; to involve stakeholders in the public consultation process and to identify developmental projects based on impact potential instead of the investment criteria”

    The developmental activities requiring Environmental Clearance (EC) are:

    All new projects/activities listed in Schedule;

    Expansion and modernization of existing projects or activities listed in the Schedule to this Notification with addition of capacity beyond the limits specified for the concerned sector, that is, projects or activities which cross the threshold limits given in the Schedule, after expansion or modernization;

    Any change in product - mix in an existing manufacturing unit included in Schedule beyond the specified range.

    The projects or activities shall require prior environmental clearance from the concerned regulatory authority, as the Central Government in the Ministry of Environment and Forests for matters falling under Category „A‟ in the schedule and at State level the State Environment Impact Assessment Authority (SEIAA) for matters falling under Category „B‟ in the said Schedule, before any construction work, or preparation of land by the project management except for securing the land, is started on the project or activity.

    As per the provisions of the new re-engineered EIA Notification of 2006, the company requires to obtain prior Environmental Clearance from the State Level Environmental Appraisal Authority or from the Ministry of Environment & Forests, New Delhi as stated in the said Notification. This Proposed project falls under Synthetic organic Chemical Industry which is listed in Schedule and falls under Clause No. 5 (f) of Category “A” (Located outside notified industrial area / estate) of Schedule as stated in Environmental Impact Assessment Notification published on 14th September 2006 and its vide amendment. As specified in sub paragraph (ii) of paragraph 2, of the stated Notification of the Government of India, Proposed project requires prior environmental clearance from the Ministry of Environment Forest Climate change as, Proposed project is located outside the notified industrial area [Clause No. 5 (f)] of Category “A”. For this the industry is required to submit draft

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 3

    Environmental Impact Assessment Study report to State Pollution Control Board, Gujarat for Public hearing and final EIA report to Ministry of Environment Forest & Climate change, New Delhi.

    In order to assess the Environmental Impacts arising due to the proposed project, the company has appointed M/s. Bhagwati Enviro Care Pvt. Ltd., Ahmedabad to undertake the Environmental Impact Assessment for various components of the Environment.

    The growing demand of the various kinds of Dyes and Dyes Intermediates in the domestic as well as international markets has provided a strong basis to M/s. SHREY INDUSTRIES for their proposed unit located at Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat). The proposed project will help in the following aspects.

    To earn a substantial amount of foreign exchange through business development, manufacturer & sales of fine chemical products.

    To generate adequate employment for people in neighbouring areas.

    To generate indirect employment.

    1.3 Purpose of the study

    The project activities are listed in serial No. 5 (f) of the schedule of EIA Notification, 2006 (synthetic Organic Chemical industries). Since the proposed project is coming up outside the notified industrial area, it is categorized as category „A‟ and needs the Environmental clearance from Ministries of Environment Forest Climate Change.

    The Environmental study undertaken is aimed at identifying existing Environmental conditions; predicting Environmental impacts associated with the proposed unit and suggesting mitigation measures to mitigate the adverse Environmental impacts. The different activities that are likely to take place have been analyzed and proposed mitigation measures are assessed for their adequacy. Proposed mitigation measures have been considered where necessary.

    The study also aims at reflecting the acceptability of the project to different stockholders and at incorporating the concerns raised by them into impact assessment and of the subsequent comprehensive Environmental management Plan and suggest the preventive and mitigative measures to minimize the adverse impacts on the environment and to maximize the beneficial impacts.

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 4

    1.4 Identification of project and project proponent

    M/s. Shrey Industries is located at S. No. 111 & 112, Plot No. 7 & 8, Village- Dhanot, Ta – Kalol, Dist – Gandhinagar, Gujarat. The unit has proposed to manufacture Pigment Green 7 @ 100 MT /M. the Land area is 3366 Sq. meter.

    M/s. Shrey Industries is promoted by 03 partners having more than 20 Year of experience in chemical industries for manufacturing, marketing, Finance etc.

    Sr. No.

    Name Designation Educational Background

    Residential Address

    1. Shree

    Kantilal

    Hirabhai

    Rathod

    Partner BA LLB 10 Devine Bunglows,

    B/h. JBR Arcade,

    Science city road,

    Sola, Ahmedabad

    2. Shree

    Ashishkumar

    Jayantibhai

    Patel

    Partner Dip.

    Pharmacy

    A-402, Vertis flat, B/h.

    Astha bunglows,

    Science city road,

    Sola, Ahmedabad

    3. Shree

    Sanjaykumar

    Bhogilal Patel

    Partner BSc

    Chemistry

    5, Saral Sapphire

    bunglows, vastral,

    Ahmedabad

    1.5 Brief description of nature size, location of the project and its importance to country, region

    Nature & Size of the project: M/s. SHREY INDUSTRIES is a proposed unit located at Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat). In their proposed unit, they will manufacture Pigment Green 7 @ 100 MT/M.

    Propsoed unit is located outside notified industrial area So, the manufacturing of Synthetic organic chemical (Pigment Green 7) falls under Category “A” of EIA Notification issued in September – 2006. For this the unit needs Environmental clearance from Ministry of Environment Forest & Climate Change.

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 5

    Project Location

    The Project Site is located at Survey No. 111 & 112, Plot No. 7 & 8, Village:

    Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat).

    Latitude : 23o18‟13.27” N (23.303687)

    Longitude : 72o25‟38.61” E (72.427391)

    Importance to country, Region:-

    In our country, they had found the high quality of material with low rate compare to others so due to that respective India is having large Market demand in India as well as abroad. Based on their informal survey of the market with our current customers and various traders, they have found that there is a big potential for the range of the products they are planning. To meet the current market requirement M/s. SHREY INDUSTRIES has intended to do proposed manufacturing activity at Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat).

    The final application of the product is in chemical industries and textile industries for printing and dyeing. The supply of CPC Pigment Green 7 is in domestic and industrial market all over India.

    1.6 Scope & Methodology of study:

    An attempt has been made to carry out a Final Environmental Impact Assessment Study for M/s. SHREY INDUSTRIES.The Scope of EIA adopted for SHREY INDUSTRIES is based on the standard TOR approved by MoEF&CC, New Delhi AND generic structure of environmental impact assessment document as stated in the Appendix III of the EIA Notification 2006 (S.O. 1533), Ministry of Environment and Forests, Government of India.. The copy of the same is attached here with.

    Under the scope of EIA, it covers:

    A brief description of project site, its surrounding environment and proposed project facilities.

    To endow with detail description of the raw materials and manufacturing process for proposed product.

    Collection and Assessment of existing environmental baseline status based on the project information, field survey relating to air quality, meteorology, water quality, socio-economic aspects, flora & fauna, existing land use pattern etc. within study area.

    Identification of Impacts due to the proposed project.

    Prediction and evaluation of the environmental impacts that may result from project development.

    Outline the Environmental Management Plan (EMP) to mitigate the adverse impacts due to the proposed project.

    Preparation of Risk Assessment Report.

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 6

    Methodology for EIA:

    The methodology adopted for carrying out the Environmental Impact Assessment for the proposed project has been based on the Guidelines issued by Ministry of Environment and Forest (MOEF). An effective EIA calls for identification of environmental parameters likely to be impacted, depending on the activities to be carried out during construction and operation phase of the project.

    Generation and collection of baseline data for valued Environmental components as per approved TOR.

    Identification and quantification of significant Environmental impacts due to the project and associated activities.

    Evaluation of impacts due to proposed expansion activities and preparation of an Environmental impact statement.

    Preparation of appropriate Environmental Management Plan (EMP) surrounding strategies for minimizing identified adverse impacts along with budgetary provisions to be made by the project authorities for implementation of mitigation measures.

    Delineation of post Environmental Quality Monitoring Programme (EQMP) along with organizational setup required for monitoring the effectiveness of mitigation measures.

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 7

    Figure 1.1: Methodology of EIA Study

    1.7 Study area

    To decide whether proposed action is likely to cause significant adverse environmental effects; the concept of EIA is practiced. Before proceeding the baseline Environmental status, it is important to know the boundary limits and framework where data can be effectively utilized in impact assessment. In keeping with the nature and size of the industry, based on our submitted TOR application and Terms of Reference Issued by MOEF & CC, New Delhi the study area for detailed studies is an area within a radius of 10 Kms with the Project Site at the center. A Map of the Study Area is presented in Figure No. 1.3

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 8

    1.8 Applicable Environment Regulations:

    The project will abide and function under the purview of the following Rules, Acts & Regulations which are formulated by the Govt. of India to protect the environment and development in a sustainable way.

    The Water (prevention & Control of Pollution) Act, 1974

    The Water (Prevention & Control of Pollution) Cess, Act, 1977

    The Air (Prevention & Control of Pollution) Act, 1981

    The Environmental (Protection) Act, 1986

    Environmental Impact Assessment Notification dated 14th September, 2006 and subsequent amendments.

    Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016.

    Solid Waste Management Rules, 2016

    The MSIHC (Manufacture, Storage and Import of Hazardous Chemicals) rules 1989 and amendment in 2000

    Chemical Accident (Emergency Planning, Preparedness and Response) Rules, 1996

    Noise Pollution (Regulation and Control) Rules, 2000 and its amendments

    1.9 STRUCTURE OF EIA:

    This EIA report has been prepared on the basis of available on-site primary data (survey/ monitoring) and secondary/literature data. The EIA report contains project features, baseline environmental setup, assessment of environmental impacts, and formulation of mitigation measures, environmental management and monitoring plan with risk & assessment Report. The report includes 12 Chapters. The structure of the EIA Report with necessary tables, drawings and annexure is as follows:

    Chapter 1: Introduction

    This chapter provides background information on need of project, need of EIA study and brief of the project. The scope and EIA methodology adopted in Preparations of EIA report have also been described in this Chapter. It also covers the identification of project & project proponent, brief description of nature, size, location of the project and its importance to the country and the region. Scope of the study details about the regulatory scoping carried out as per the generic structure given in the EIA Notification, 2006.

    Chapter 2: Project Description

    This chapter deals with the project details of the proposed products, with type of project, need for the project, location, size & magnitude of operation including associated activities required by and for the project, proposed

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 9

    schedule for approval and implementation, including technical details of raw material, quality and quantity etc.

    Chapter 3: Description of the Environment

    This chapter presents the existing environmental status of the study area around the proposed project including topography, drainage pattern, water environment, geological, climate, transport system, land use, flora & fauna, socio-economic aspects, basic amenities etc. Environmental assessment of the project site in regard to its capability to receive the proposed project is also discussed in this Chapter.

    Chapter 4: Anticipated Environmental Impacts and Mitigation

    Measures

    This chapter describes the overall impacts of the proposed project activities and underscores the areas of concern, which need mitigation measures. It predicts the overall impact of the proposed project on different components of the environment viz. air, water, land, noise, biological, and socio-economic.

    Chapter 5:Analysis of Alternatives (Technology & site)

    This chapter describes the site selection criteria and analysis of propsoed alternative technologies.

    Chapter 6: Environmental Monitoring Program

    Technical aspects of monitoring the effectiveness of mitigation measures have been given in this Chapter.

    Chapter 7: Additional Studies

    This chapter deals with the Public consultation & Risk assessment carried out for the proposed manufacturing plant. Unit is not located in notified area so, public consultation is required.

    Chapter 8: Project Benefits

    This chapter deals with the benefits to the local surrounding people due to proposed project.

    Chapter 9: Environment cost benefit Analysis

    During the scoping stage; no recommendation of environmental cost benefit analysis is suggested by the appraisal committee.

    Chapter 10: Environmental Management Plan

    This chapter details the inferences drawn from the environmental impact assessment exercise. It describes the overall impacts of the proposed activities during construction and operation phases and underscores the

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 10

    areas of concern, which need mitigation measures. It also provides mitigation and control measures for environmental management plan (EMP) for minimizing the negative environmental impacts and to strengthen the positive environmental impacts of the proposed project.

    Chapter 11: Summary & Conclusion of EIA Report

    This chapter provides the summary and conclusions of the EIA study of the Proposed project with overall justification for implementation of the project and also explanation of how, adverse effects will be mitigated.

    Chapter 12: Disclosure of Consultants Engaged

    This chapter provides the disclosure of consultants engaged to carry out the EIA study along with other additional studies.

    1.10 COMPLIANCE OF TOR

    As per the requirements of the notification, an application in Form 1 was

    submitted to Ministry of Environment and Forest Climate Change on

    21/11/2018. The „TOR‟ was issued on 31/12/2018 for preparation of EIA/EMP.

    A copy of the TOR is included in Annexure -01 of this EIA Report. As per

    TOR project was considered under “A” category. (Based on the additional

    information, in view of the MoEF & CC‟s OM vide No.IA-J-11011/369/2018-IA-

    II(I) committee asked to prepare EIA – EMP report as per the EIA notification

    2006.)

    The EIA study has been conducted in-line with the Standard ToR given by

    MoEF&CC and taking into consideration the structure of the report given in

    the EIA Notification 2006. The compliance to the same has been presented in

    Table 1.1.

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 11

    Table: 1.1: TOR COMPLIANCE GENERIC TERMS OF REFERENCE (TOR) IN RESPECT OF INDUSTRY SECTOR

    1. Executive Summary (Generic

    Structure as per Appendix III A)

    For Executive summary

    Please Refer Chapter -11

    of EIA Report.

    378-396

    2. Introduction

    i. Details of the EIA Consultant

    including NABET accreditation

    Please Refer Annexure –

    A

    I

    ii. Information about the project

    proponent

    Please Refer Section 1.4

    of Chapter 1.

    4

    iii. Importance and benefits of the

    project

    For Importance, Please

    Refer Section 1.5 & 2.3 of

    Chapter 1 & 2.

    For benefits, please refer

    chapter 8.

    04

    25

    318-326

    3. Project Description

    i. Cost of project and time of

    completion.

    Please Refer Section 2.32

    of Chapter 2.

    Time of Completion: 06

    months after obtaining EC

    & CTE.

    75

    ii. Products with capacities for the

    proposed project.

    Please Refer Section 2.8

    of Chapter 2.

    36

    iii. If expansion project, details of

    existing products with capacities

    and whether adequate land is

    available for expansion, reference

    of earlier EC if any.

    This is a Proposed Unit.

    For Product details,

    Please refer section 2.8 of

    chapter 2.

    For Land breakup, please

    refer Table No.2.10

    36

    46

    iv. List of raw materials required and

    their source along with mode of

    transportation.

    Please Refer Section 2.9

    of Chapter 2.

    37

    v. Other chemicals and materials

    required with quantities and storage

    capacities.

    Please Refer Section

    2.10,2.11 & 2.12 of chapter

    2

    38-40

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 12

    vi. Details of Emission, effluents,

    hazardous waste generation and

    their management.

    For Air Emission: Please

    Refer Section 2.23-2.26 of

    Chapter 2.

    For Water consumption

    & Effluent Generation:

    Please Refer Section 2.20-

    2.22 of Chapter 2.

    For Hazardous Waste

    Generation: Please Refer

    Section 2.27 of Chapter 2.

    56-60

    50-55

    61

    vii. Requirement of water, power, with

    source of supply, status of

    approval, water balance diagram,

    man-power requirement (regular

    and contract).

    Please Refer Table 2.9 of

    Chapter 2,

    For water balance

    Diagram, Please Refer Fig

    2.8 of Chapter 2,

    For manpower details,

    Please Refer table 2.12 of

    Chapter 2.

    45

    52

    48

    viii. Process description along with

    major equipments and machineries,

    process flow sheet (quantities) from

    raw material to products to be

    provided.

    For Process Description &

    for Process flow diagram,

    Please Refer section 2.13

    of chapter 2.

    41

    ix. Hazard identification and details of

    proposed safety systems.

    Please Refer Section

    10.10 of Chapter 10.

    Please refer section 7.4 of

    chapter 7.

    363

    267

    x. Expansion/modernization

    Proposals:

    This is a Proposed Unit. ---

    a. Copy of all the Environmental

    Clearance(s) including Amendments

    thereto obtained for the project from

    MOEF/SEIAA shall be attached as

    an Annexure. A copy of the

    compliance of conditions stipulated

    in all the existing Environmental

    clearances including Amendments

    shall be provided. In addition, status

    of compliance of Consent to

    Operate for the ongoing /existing

    Not Applicable because of

    Proposed unit.

    ---

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 13

    operation of the project from SPCB

    shall be attached with the EIA-EMP

    report.

    b. In case the existing project has not

    obtained Environmental clearance,

    reasons for not taking EC under the

    provisions of the EIA Notification

    1994 and/or EIA Notification 2006

    shall be provided. Copies of

    Consent to Establish/No Objection

    Certificate and Consent to Operate

    (in case of units operating prior to

    EIA Notification 2006, CTE and CTO

    of FY 2005-2006) obtained from the

    SPCB shall be submitted. Further,

    compliance report to the conditions

    of consents from the SPCB shall be

    submitted.

    Not Applicable because of

    Proposed unit.

    ---

    4. Site Details

    i. Location of the project site covering

    village, Taluka/Tehsil, District and

    State, Justification for selecting the

    site, whether other sites were

    considered.

    Please Refer Fig 2.1 to 2.3

    of chapter 2.

    For Justification for

    selecting the site, Please

    Refer Section 2.6 of

    Chapter 2.

    27-29

    35

    ii. A Toposheet of the study area of

    radius of 10km and site location on

    1:50,000/1:25,000 scale on an

    A3/A2 sheet. (Including all eco-

    sensitive areas and environmentally

    sensitive places).

    Please Refer Fig 2.6 of

    chapter 2.

    32

    iii. Details w.r.t. option analysis for

    selection of site.

    Not done. ---

    iv. Co-ordinates (lat-long) of all four

    corners of the site.

    Please Refer Table No. 2.1

    of chapter 2.

    26

    v. Google map-Earth downloaded of

    the project site.

    Please Refer Fig 2.5 of

    chapter 2.

    31

    vi. Layout maps indicating existing unit

    as well as proposed unit indicating

    storage area, plant area, greenbelt

    area, utilities etc.

    Please Refer Fig 2.4 of

    chapter 2.

    30

    vii. Photographs of the proposed and Please Refer Section 2.5 33

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 14

    existing (if applicable) plant site. If

    existing, show photographs of

    plantation/greenbelt, in particular.

    of Chapter 2.

    viii. Land use break-up of total land of

    the project site (identified and

    acquired), government/private -

    agricultural, forest, wasteland, water

    bodies, settlements, etc shall be

    included. (Not required for industrial

    area).

    Please Refer table 2.10 of

    Chapter 2.

    46

    ix. A list of major industries with name

    and type within study area (10km

    radius) shall be incorporated. Land

    use details of the study area.

    For list of major

    industries, Please Refer

    Table 2.3 of Chapter 2.

    For Land Use Details,

    Please Refer section 3.15

    of Chapter 3.

    35

    144

    x. Geological features and Geo-

    hydrological status of the study area

    shall be included.

    For Geological features,

    Please Refer Section 3.13

    of Chapter 3 and

    For Geo-hydrological

    status of the study area,

    Please Refer Section 3.17

    of Chapter 3.

    136

    148

    xi. Details of Drainage of the project up

    to 5km radius of study area. If the

    site is within 1 km radius of any

    major river, peak and lean season

    river discharge as well as flood

    occurrence frequency based on

    peak rainfall data of the past 30

    years. Details of Flood Level of the

    project site and maximum Flood

    Level of the river shall also be

    provided. (Mega green field

    projects).

    Unit will achieve zero liquid

    Discharge by sending

    treated effluent to

    Common Spray Dryer

    Facility at Chhatral

    Environment Management

    System Pvt. Ltd. Dhanot

    for spray drying.

    ---

    xii. Status of acquisition of land. If

    acquisition is not complete, stage of

    the acquisition process and

    expected time of complete

    possession of the land.

    Land Supporting

    Document is enclosed in

    Annexure 06.

    460

    xiii. R&R details in respect of land in line

    with state Government policy.

    Not Applicable ----

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 15

    5. Forest and wildlife related issues (if

    applicable):

    i. Permission and approval for the use

    of forest land (forestry clearance), if

    any, and recommendations of the

    State Forest Department. (If

    applicable).

    Not Applicable

    ii. Land use map based on High

    resolution satellite imagery (GPS) of

    the proposed site delineating the

    forestland (in case of projects

    involving forest land more than 40

    ha).

    For land Use details of

    the study Area, Please

    Refer Section 3.15 of

    Chapter 3.

    144

    iii. Status of Application submitted for

    obtaining the stage I forestry

    clearance along with latest status

    shall be submitted.

    Not Applicable -----

    iv. The projects to be located within 10

    km of the National Parks,

    Sanctuaries, Biosphere Reserves.

    Migratory Corridors of Wild Animals,

    the project proponent shall submit

    the map duly authenticated by Chief

    Wildlife Warden showing these

    features vis-à-vis the project location

    and the recommendations or

    comments of the Chief Wildlife

    Warden-thereon.

    Not Applicable. No,

    National Parks,

    Sanctuaries, Biosphere

    Reserves. Migratory

    Corridors of Wild Animals,

    located within 10 Km of the

    Study Area.

    -----

    v. Wildlife Conservation Plan duly

    authenticated by the Chief Wildlife

    Warden of the State Government for

    conservation of Schedule I fauna, if

    any exists in the study area.

    Wildlife Conservation Plan

    submitted for Schedule I

    species is enclosed in

    Annexure 12

    537

    vi. Copy of application submitted for

    clearance under the Wildlife

    (Protection) Act, 1972, to the

    Standing Committee of the National

    Board for Wildlife.

    6. Environmental Status

    i. Determination of atmospheric

    inversion level at the project site and

    site-specific micrometeorological

    Please Refer Table No. 4.6

    to 4.10 of Chapter 4.

    207-215

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 16

    data using temperature, relative

    humidity, hourly wind speed and

    direction and rainfall.

    Please Refer Fig No. 4.1 to

    4.5 of Chapter 4.

    For Micrometeorology data

    Please Refer Section 3.8

    of Chapter 3.

    217-225

    111

    ii. AAQ data (except monsoon) at 8

    locations for PM10, PM2.5, SO2,

    NOX, CO and other parameters

    relevant to the project shall be

    collected. The monitoring stations

    shall be based CPCB guidelines and

    take into account the pre-dominant

    wind direction, population zone and

    sensitive receptors including

    reserved forests.

    For Monitoring Station,

    Please Refer table No. 3.3

    of Chapter 3.

    AAQ data of 8 locations is

    given in table No. 3.4(a) of

    Chapter 3.

    100

    103

    iii. Raw Data of all AAQ measurement

    for 12 weeks of all stations as per

    frequency given in the NAQQM

    Notification of Nov. 2009 along with

    - min., max., average and 98%

    values for each of the AAQ

    parameters from data of all AAQ

    stations should be provided as an

    annexure to the EIA Report.

    AAQ data of 8 locations is

    given in table No. 3.4(a) of

    Chapter 3.

    Min., Max., Average and

    98% values for each of the

    AAQ parameters from data

    of all AAQ stations is

    shown in table No. 3.4 of

    Chapter 3.

    103

    101

    iv. Surface water quality of nearby

    River (100m upstream and

    downstream of discharge point) and

    other surface drains at eight

    locations as per CPCB/MoEF & CC

    guidelines.

    For Surface water quality,

    please refer table 3.14(b)

    of chapter 3.

    135

    v. Whether the site falls near to

    polluted stretch of river identified by

    the CPCB/MoEF & CC, if yes give

    details.

    Not Applicable ---

    vi. Ground water monitoring at

    minimum at 8 locations shall be

    included.

    Please Refer Table No.

    3.14(a) of Chapter 3.

    133

    vii. Noise levels monitoring at 8

    locations within the study area.

    Please Refer Table No.

    3.12 of Chapter 3.

    122

    viii. Soil Characteristic as per CPCB

    guidelines.

    Please Refer Table No.

    3.15 of Chapter 3.

    139

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 17

    ix. Traffic study of the area, type of

    vehicles, frequency of vehicles for

    transportation of materials,

    additional traffic due to proposed

    project, parking arrangement etc.

    Please Refer Section 4.14

    of Chapter 4.

    243

    x. Detailed description of flora and

    fauna (terrestrial and aquatic)

    existing in the study area shall be

    given with special reference to rare,

    endemic and endangered species. If

    Schedule-I fauna are found within

    the study area, a Wildlife

    Conservation Plan shall be prepared

    and furnished.

    Please Refer Table no.

    3.19 of Chapter 3.

    For, Wildlife Conservation

    Plan please refer

    annexure-12

    153

    537

    xi. Socio-economic status of the study

    area.

    Please Refer Section 3.19

    of Chapter 3.

    160

    7. Impact and Environmental

    Management Plan

    i. Assessment of ground level

    concentration of pollutants from the

    stack emission based on site-

    specific meteorological features. In

    case the project is located on a hilly

    terrain, the AQIP Modeling shall be

    done using inputs of the specific

    terrain characteristics for

    determining the potential impacts of

    the project on the AAQ. Cumulative

    impact of all sources of emissions

    (including transportation) on the

    AAQ of the area shall be assessed.

    Details of the model used and the

    input data used for modeling shall

    also be provided. The air quality

    contours shall be plotted on a

    location map showing the location of

    project site, habitation nearby,

    sensitive receptors, if any.

    For Assessment of ground

    level concentration, Please

    Refer Table 4.4 of chapter

    4.

    AQIP modelling is not

    applicable.

    For Cumulative impact,

    please refer Table 4.5 of

    chapter 4.

    Details of the model:

    AERMOD.

    For input data, please refer

    table No. 4.3 of chapter 4.

    For air quality contours,

    Please refer Fig. 4.1, 4.2,

    4.3, 4.4, 4.5 of Chapter 4.

    203

    204

    199

    217-225

    ii. Water Quality modeling - in case of

    discharge in water body

    Not Done.

    iii. Impact of the transport of the raw

    materials and end products on the

    surrounding Environmental shall be

    Please Refer Section 4.14

    of Chapter 4.

    243

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 18

    assessed and provided. In this

    regard, options for transport of raw

    materials and finished products and

    wastes (large quantities) by rail or

    rail-cum road transport or conveyor

    cum-rail transport shall be

    examined.

    iv. A note on treatment of wastewater

    from different plant operations,

    extent recycled and reused for

    different purposes shall be included.

    Complete scheme of effluent

    treatment. Characteristics of

    untreated and treated effluent to

    meet the prescribed standards of

    discharge under E(P) Rules.

    Please Refer Section 2.20-

    2.22 of Chapter 2.

    50-55

    v. Details of stack emission and action

    plan for control of emissions to meet

    standards.

    Please Refer Section 2.23-

    2.25 of Chapter 2.

    56-59

    vi. Measures for fugitive emission

    control.

    Please Refer Section 2.26

    of Chapter 2.

    60

    vii. Details of hazardous waste

    generation and their storage,

    utilization and management. Copies

    of MOU regarding utilization of solid

    and hazardous waste in cement

    plant shall also be included. EMP

    shall include the concept of waste-

    minimization, recycle/reuse/recover

    techniques, Energy conservation,

    and natural resource conservation.

    For Details of hazardous

    waste generation and

    their storage, utilization

    and management,

    Please Refer Section 2.27

    of Chapter 2.

    Due to proposed unit, we

    had not done any MOU

    with other industries.

    For, concept of waste-

    minimization,

    recycle/reuse/recover

    techniques, Energy

    conservation, and natural

    resource conservation -

    Please Refer Section

    10.12 of Chapter 10.

    51

    369

    viii. Proper utilization of fly ash shall be

    ensured as per Fly Ash Notification,

    2009. A detailed plan of action shall

    be provided.

    There will be no generation

    of fly ash.

    --

    ix. Action plan for the green belt Please Refer Section 10.6 351

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 19

    development plan in 33 % area i.e.

    land with not less than 1,500 trees

    per ha. Giving details of species,

    width of plantation, planning

    schedule etc. shall be included. The

    green belt shall be around the

    project boundary and a scheme for

    greening of the roads used for the

    project shall also be incorporated.

    of Chapter 10.

    Please Refer Section 2.33

    of chapter 2

    76

    x. Action plan for rainwater harvesting

    measures at plant site shall be

    submitted to harvest rainwater from

    the roof tops and storm water drains

    to recharge the ground water and

    also to use for the various activities

    at the project site to conserve fresh

    water and reduce the water

    requirement from other sources.

    Please Refer Section 2.34

    of Chapter 2.

    77

    xi. Total capital cost and recurring

    cost/annum for Environmental

    pollution control measures shall be

    included.

    Please Refer table No.2.27

    of Chapter 2.

    75

    xii. Action plan for post-project

    Environmental monitoring shall be

    submitted.

    Please Refer table No. 6.1

    of Chapter 6.

    250

    xiii. Onsite and Offsite Disaster (natural

    and Man-made) Preparedness and

    Emergency Management Plan

    including Risk Assessment and

    damage control. Disaster

    management plan should be linked

    with District Disaster Management

    Plan.

    Please Refer Section 7.11

    of Chapter 7.

    Risk Assessment Report is

    enclosed in Annexure -02.

    301

    408

    8. Occupational health

    i. Plan and fund allocation to ensure

    the occupational health & safety of

    all contract and casual workers.

    Please Refer table 10.11

    of Chapter 10

    368

    ii. Details of exposure specific health

    status evaluation of worker. If the

    workers' health is being evaluated

    by pre designed format, chest x

    rays, Audiometry, Spirometry, Vision

    Please Refer Section 10.9

    of Chapter 10.

    362

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 20

    testing (Far & Near vision, color

    vision and any other ocular defect)

    ECG, during pre placement and

    periodical examinations give the

    details of the same. Details

    regarding last month analyzed data

    of above mentioned parameters as

    per age, sex, duration of exposure

    and department wise.

    iii. Details of existing Occupational &

    Safety Hazards. What are the

    exposure levels of hazards and

    whether they are within Permissible

    Exposure level (PEL). If these are

    not within PEL, what measures the

    company has adopted to keep them

    within PEL so that health of the

    workers can be preserved.

    Please Refer Section 10.8

    of Chapter 10.

    355

    iv. Annual report of heath status of

    workers with special reference to

    Occupational Health and Safety.

    After Proposed activity of

    the project, all the data of

    the medical checkups of

    workers will be kept as per

    Form 37.

    ----

    9. Corporate Environmental Policy

    i. Does the company have a well laid

    down Environmental Policy

    approved by its Board of Directors?

    If so, it may be detailed in the EIA

    report.

    Please Refer Section 6.7of

    Chapter 6.

    256

    ii. Does the Environmental Policy

    prescribe for standard operating

    process / procedures to bring into

    focus any infringement / deviation /

    violation of the Environmental or

    forest norms / conditions? If so, it

    may be detailed in the EIA.

    Please Refer Section 6.7

    of Chapter 6.

    256

    iii. What is the hierarchical system or

    Administrative order of the company

    to deal with the Environmental

    issues and for ensuring compliance

    with the Environmental clearance

    conditions? Details of this system

    Please Refer Figure 6.1 of

    Chapter 6.

    Please refer Table No. 6.2

    of chapter 6.

    258

    255

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 21

    may be given.

    iv. Does the company have system of

    reporting of non compliances /

    violations of Environmental norms to

    the Board of Directors of the

    company and / or shareholders or

    stakeholders at large? This reporting

    mechanism shall be detailed in the

    EIA report.

    Please Refer Section 6.7

    of Chapter 6.

    Please refer Table No. 6.2

    of chapter 6.

    256

    255

    10. Details regarding infrastructure

    facilities such as sanitation, fuel,

    restroom etc. to be provided to the

    labour force during construction as

    well as to the casual workers

    including truck drivers during

    operation phase.

    Please Refer Section

    10.15 of Chapter 10.

    375

    11 Enterprise Social Commitment (ESC)

    i. Adequate funds (at least 2.5 % of

    the project cost) shall be earmarked

    towards the Enterprise Social

    Commitment based on Public

    Hearing issues and item-wise details

    along with time bound action plan

    shall be included. Socio-economic

    development activities need to be

    elaborated upon.

    The industry will provide

    2.0 % of the project cost

    Towards the Enterprise

    Commitment. Socio

    Economic development

    activities.

    Please section 8.4 of

    chapter 8.

    -----

    319

    12. Any litigation pending against the

    project and/or any direction/order

    passed by any Court of Law against the

    project, if so, details thereof shall also

    be included. Has the unit received any

    notice under the Section 5 of

    Environmental (Protection) Act, 1986 or

    relevant Sections of Air and Water

    Acts? If so, details thereof and

    compliance/ATR to the notice(s) and

    present status of the case.

    There was no any litigation

    pending against the project

    and/or any direction/order

    passed by any Court of

    Law against the project.

    ------

    13. 'A tabular chart with index for point wise

    compliance of above TOR.

    Given herewith in Section

    1.10 of Chapter 1.

    10

    Specific terms of Reference for EIA studies for synthetic organic chemicals Industry

    1. Details on solvents to be used,

    measures for solvent recovery and for

    Please refer Section 2.35

    of Chapter 2

    84

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 22

    emissions control.

    2. Details of process emissions from the

    proposed unit and its arrangement to

    control.

    Please refer Section 2.24

    of Chapter 2

    59

    3. Ambient air quality data should include

    VOC, other process –specific

    pollutants* like NH3*, chlorine*, HCl*,

    HBr*, H2S*, HF*,etc.,(*-as applicable)

    Please refer Table No.

    3.4(a) & (b) of Chapter 3

    101

    4. Work zone monitoring arrangements for

    hazardous chemicals.

    Please refer section 6.3 of

    Chapter 6.

    252

    5. Detailed effluent treatment scheme

    including segregation of effluent

    streams for units adopting

    'Zero' liquid discharge.

    Please refer section 2.20 to

    2.22 of Chapter 2

    50-55

    6. Action plan for odour control to be

    submitted.

    Please refer Section 10.16

    of chapter 10.

    376

    7. A copy of the Memorandum of

    Understanding signed with cement

    manufacturers indicating clearly

    that they co-process organic

    solid/hazardous waste generated.

    Not Applicable. Because

    generated Hazardous

    waste will be sold to

    Authorized industries

    having rule 9 permission &

    ETP waste will be send to

    TSDF site.

    ----

    8. Authorization/Membership for the

    disposal of liquid effluent in CETP and

    solid/hazardous waste in

    TSDF, if any.

    Please refer Annexure: 9

    for Membership

    certificates. Unit will

    become member of nearest

    TSDF site.

    490

    9. Action plan for utilization of MEE/dryers

    salts.

    Not Applicable ----

    10. Material Safety Data Sheet for all the

    Chemicals are being used/will be used.

    Please refer Annexure: 10 491

    11. Authorization/Membership for the

    disposal of solid/hazardous waste in

    TSDF.

    Unit will become member

    Of nearest TSDF site.

    ----

    12. Details of incinerator if to be installed. No any incinerator to be

    installed.

    ----

    13. Risk assessment for storage and

    handling of hazardous

    chemicals/solvents. Action plan for

    handling

    & safety system to be incorporated.

    Please refer Annexure: 2 408

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    Prepared By M/s. Bhagwati Enviro Care Pvt Ltd. 23

    14. Arrangements for ensuring health and

    safety of workers engaged in handling

    of toxic materials.

    Please refer Section 7.5

    of chapter 7.

    287

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    24

    Prepared By M/s. Bhagwati Enviro Care Pvt. Ltd.

    CHAPTER 2

    PROJECT DESCRIPTION

    2.1 Introduction

    M/s. SHREY INDUSTRIES is a proposed unit located at Survey No. 111 &

    112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat). In

    their proposed unit, they will manufacture Pigment Green 7 @ 100 MT/M.

    Considering scale of unit and its categorization, according to EIA notification

    dated 14th September 2006, by Ministry of Environment & Forest (MoEF),

    Government of India, their proposed manufacturing activity is falls under

    Synthetic Organic Chemicals – Schedule 5(f) & cat -A. For that unit needs

    Environmental clearance from Ministry of Environment Forest & Climate

    Change.

    In order to assess the Environment Impacts of the proposed project, M/s.

    SHREY INDUSTRIES entrusted Bhagwati Enviro Care Pvt. Ltd, Ahmedabad

    (NABET Accredited) to undertake Final Environmental Impact Assessment

    Study for various components of the Environment viz., Air, Water, Noise,

    Land and Socio-economics. This Report presents base line data collected for

    October-November-December-2018 for Air, Water, Noise, Land etc., for

    identification and assessment of the impacts.

    2.2 Type of Project

    The project is neither an interlinked project nor an interdependent project. As

    per the EIA Notification, 2006 & subsequent amendments, the proposed

    project comes under category „A‟ listed at item 5(f)“Synthetic organic

    chemicals industry (dyes & dye intermediates; bulk drugs and intermediates

    excluding drug formulations; synthetic rubbers; basic organic chemicals, other

    synthetic organic chemicals and chemical intermediates)”. The project is

    located outside the notified industrial area for manufacturing of Pigment

    Green 7 @ 100 MT /M. Therefore, the category of the proposed project

    comes under category „A‟.

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    25

    Prepared By M/s. Bhagwati Enviro Care Pvt. Ltd.

    2.3 Need for the Project

    These products are widely used in textile industries for printing and dyeing. With a rapid growth of industrialization, the demand of various pigments has also increased significantly over a period of time. Based on the informal survey of the market with potential customers and various traders, the company has found that there is a big demand in the market for the range of the product being planned. Today, increased focus is being laid on environmental friendliness and at the same time the industry is ensuring greater customer focus through technical services and marketing capabilities, in order to face global competition. To meet the current market requirement M/s. SHREY INDUSTRIES has intended to do proposed manufacturing activity at Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat).

    Specific site selection criteria of the unit have been given below.

    Plot size is suitable for proposed project.

    Availability of the set up and the utility and support facilities within the

    same premises.

    The project site is well connected by road to Kadi-Chhatral State

    highway 2.53 km, S away from project site & Ahmedabad-Mehsana

    National Highway 1.0 km, E away from project Site.

    The proposed unit is located in Industrial Estate, including Availability

    of infrastructure facility like power, water supply, road, manpower etc.

    There are no ecological sensitive areas located within 10 km radius of

    the project site.

    No any national park or wild life sanctuary located within 10 km radius

    of the project site.

    Availability of good communication and transport facilities.

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    26

    Prepared By M/s. Bhagwati Enviro Care Pvt. Ltd.

    2.4 Location

    The location of the project is as shown here in Table 2.1.

    Table No. 2.1

    Location of The Project

    Sr. No.

    Description Information

    1 Latitude 23o18‟13.27” N (23.303687)

    North 23.304019 East 23.303480

    South 23.303466 West 23.303728

    2 Longitude 72o25‟38.61” E (72.427391) North 72.427431 East 72.426895

    South 72.427404 West 72.427530

    3 Plot. No. Plot No. 7 & 8, Survey No: 111 & 112

    5 Village Dhanot

    5 Ta Kalol

    6 Dist Gandhinagar

    7 State Gujarat

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    27

    Prepared By M/s. Bhagwati Enviro Care Pvt. Ltd.

    Figure No. 2.1

    Map of Gujarat

    GANDHINAGAR

    DISTRICT

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    28

    Prepared By M/s. Bhagwati Enviro Care Pvt. Ltd.

    Figure No. 2.2

    Map of Gandhinagar District

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    29

    Prepared By M/s. Bhagwati Enviro Care Pvt. Ltd.

    Figure No. 2.3

    5 KM & 10 KM Radios map of the project site

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    30

    Prepared By M/s. Bhagwati Enviro Care Pvt. Ltd.

    Figure No. 2.4

    Layout Plan

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    31

    Prepared By M/s. Bhagwati Enviro Care Pvt. Ltd.

    Figure No. 2.5

    GOOGLE IMAGE OF M/s. SHREY INDUSTRIES.

    Latitude: 23o18‟11.12” N (23.303089), Longitude: 72o25‟37.13” E (72.426981)

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    32

    Prepared By M/s. Bhagwati Enviro Care Pvt. Ltd.

    Figure No. 2.6

    Topography Map of M/s. SHREY INDUSTRIES.

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    33

    Prepared By M/s. Bhagwati Enviro Care Pvt. Ltd.

    2.5 Photographs of the proposed project site.

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    34

    Prepared By M/s. Bhagwati Enviro Care Pvt. Ltd.

    Table No. 2.2

    Salient Features of the Project Site

    Sr. No.

    Features Description

    1 Location Plot No. 7 & 8, S. No. 111 & 112, Village – Dhanot, Ta – Kalol, Dist - Gandhinagar

    2 Geographical Location Elevation above MSL 70.71 m

    Toposheet No. F43A07, F43A08, F43A11, F43A12

    Latitude Longitude

    23.30335 72.42674

    23.30336 72.42727

    23.30375 72.42722

    23.30290 72.42666

    3. Infrastructure Setup (Aerial Distance from project Site)

    Description Distance (Km)

    A Nearest village Dhanot Bileshwarpura Indrad

    1.38 km, S 1.47 km, SE 2.39 km, WSW

    B Nearest town Chhatral 2.72 km, SE

    C Water Body Creek / Nalah / lake /Pond /reservoir /canal/ Rivers / Stream / Estuary / Sea

    Narmada Canal 6.01 km, S

    D Highway Kadi - Chhatral State Highway Ahmedabad - Mehsana National Highway

    2.53 km, S 1.20 km, E

    E Railway Line Ahmedabad - Mehsana

    5.39 km, E

    F Railway Station Pansar 5.39 km. E

    G Airport Ahmedabad 32.89 km, SE

    H Heritage Site No heritage site within 10 km radius --

    I National park / wild life sanctuary / Reserve Forest land

    No National park / wild life sanctuary / Reserve Forest land within 10 km radius.

    --

    J Anganwadi / School / College /Institute etc.

    Dhanot 1.38 km, S

    K Defence Installation None ---

    L Place of interest / None ---

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    35

    Prepared By M/s. Bhagwati Enviro Care Pvt. Ltd.

    Tourist Place

    M Displacement of Population

    None ---

    N Seismic Zone As per the earth quack sensitivity index, the unit is situated in Zone III having moderate Damage Risk (MSK -VII)

    ---

    Table No. 2.3

    Nearest Industries from the Project Site

    2.6 Justification of Site Selection

    In our country, they had found the high quality of material with low rate compare to others so due to that respective India is having large Market demand in India as well as abroad. Based on their informal survey of the market with our current customers and various traders, they have found that there is a big potential for the range of the products they are planning.

    To meet the current market requirement M/s. SHREY INDUSTRIES has intended to do proposed manufacturing activity at Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat).

    Specific site selection criteria of the unit have been given below.

    Plot size is suitable for proposed project.

    Sr. No.

    Name of Industries

    Address Type of Unit

    1 Sonu Industries 71/3, B/H Ravi Estate, GIDC, Gujarat State Hwy 41, Dhanot, Gujarat 382729

    Manufacturer of BOPP Self Adhesive Plain & Printed Tapes

    2 Purnima Enterprise

    Plot No-1 Nilkanth Industrial Estate, At-Dhanot, Ta: Kalol, Dist-Gandhinagar-382729 (Gujarat)

    Chemical Manufacturing Unit

    3 Anju Dye Chem Plot No. 108/3-4, Ravi Industrial Estate, Village- Bileshwarpura Kalol-Mehsana Highway, Gandhinagar-382729,

    Dyes Manufacturing Unit

    4 Bright Resin Pvt. Ltd.

    Ravi Industrial Estate, Bileshwarpura, Ta. Kalol, Dist. Gandhinagar

    Resin Manufacturing Unit

    5. Chhatral Enviro Management System, Pvt Ltd.

    Village – Dhanot, ta – Kalol, dist – Gandhinagar.

    Common Spray Drying facility.

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    36

    Prepared By M/s. Bhagwati Enviro Care Pvt. Ltd.

    Availability of the set up and the utility and support facilities within the

    same premises.

    The project site is well connected by road to Kadi-Chhatral State

    highway 2.53 km, S away from project site & Ahmedabad-Mehsana

    National Highway 1.0 km, E away from project Site.

    The proposed unit is located in Industrial Estate, including Availability

    of infrastructure facility like power, water supply, road, manpower etc.

    There are no ecological sensitive areas located within 10 km radius of

    the project site.

    No any national park or wild life sanctuary located within 10 km radius

    of the project site.

    Availability of good communication and transport facilities.

    2.7 Size or magnitude of operation:-

    The size and magnitude of operation is includes Product profile including

    chemical name of product, Product CAS No. product Qty and Product

    Application , Raw material requirement, raw Material Storage Details,

    Properties of Raw materials etc. All the details are covered in next topics.

    2.8 Product Details:-

    This unit will engaged in manufacturing of Pigment Green 7 with the total

    capacity of 100 TPM. Details of product along with Capacities List of products

    along with capacity and end use are given in below Table No. 2.4 & table

    No. 2.5

    Table No. 2.4

    List of Product

    NAME OF PRODUCT WITH ITS CHEMICAL NAME and QTY

    Sr. No.

    Product Name Chemical Name CAS No.

    Quantity (MT/Month)

    1. Pigment Green 7 Phthalocyanine Green 1328-53-6 100

  • Final Environment Impact Assessment of Proposed Manufacturing unit by M/s. SHREY INDUSTRIES At

    Survey No. 111 & 112, Plot No. 7 & 8, Village: Dhanot, Ta: Kalol, Dist: Gandhinagar (Gujarat)

    37

    Prepared By M/s. Bhagwati Enviro Care Pvt. Ltd.

    Table No. 2.5

    Packing and Final Application of Products

    Sr. No.

    Name of Product CAS No. Type of Packing Final

    application of product

    1. Pigment Green 7 1328-53-6

    HDPE Bags packing of 25 Kg/50 Kg With inner liner & 500 kg jumbo bags

    In chemical industries and textile Industries for printing and dyeing.

    2.9 Raw material requirement:-

    List of Raw Materials, with consumption for manufacturing of Proposed

    Products, is given in Table No. 2.6

    Table No. 2.6

    Detail of Raw Materials

    Sr. no.

    Name of the

    Products

    Name of the Raw Materials

    CAS no. of raw

    materials.

    Quantity

    MT/MT MT/Month

    1 Pigment Green 7

    Aluminum Chloride 7446-70-0 1.825 182.5

    Cupric Chloride 7447-39-4 0.080 8.000

    Salt 7647-14-5 0.397 39.70

    Copper Phthalocyanine blue

    147-14-8 0.555 55.50

    Emulsifier ---- 1.270 127.0

    Caustic flakes 1310-73-2 0.060 6.000

    Mono Chloro Benzene

    108-90-7 0.040 4.000

    Chlorine 7782-50-5 0.079 7.900