final compliance report-check - nromoef.gov.innromoef.gov.in/smpr/06082015/61.pdfstp technology :...
TRANSCRIPT
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 1
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
PROJECT INTRODUCTION:
“Greenopolis” is a residential group housing colony situated at sector-89, village Hyatpur,
Gurgaon, Haryana. The project is developed by Orris Infrastructure Pvt. Ltd. Total plot area of the
project is 1,91,085.25 sq. m. (47.218 acres) and the built up area is 5,10,080.92 sq. m. The project
has been granted Environmental Clearance by State Environment Impact Assessment Authority,
Haryana vide letter no. SEIAA/HR/2013/587 dated 4th
September 2013. Copy of environmental
Clearance is enclosed as Annexure I.
PROJECT DESCRIPTION:
Location : Sector-89, Village Hyatpur, Gurgaon, Haryana.
Category : B1 under Item 8 (b) (as per EIA Notification)
Plot Area : 1,91,085.25 sq. m.
Built up Area : 5,10,080.92 sq. m.
Capacity : The building will comprise of 54 blocks, 2 Basements + GF +
Maximum 24 Floors
Number of Dwelling units : 2739
Servant Units : 236
Water Demand : 2848 KLD (Fresh Water: 1312 KLD; Treated water: 1536 KLD)
(Revised water demand as per condition no. 38 of the EC letter)
Power Demand : 20876 kVA (20.8 MVA)
STP Capacity : 1900 KLD
STP Technology : Moving Bed Bio Reactor (MBBR)
PROJECT STATUS:
The project is in construction phase. About 4,14779.95 sq. m. built up area has been constructed
at site. Photographs showing the same are enclosed as Annexure II. The company has invested
about 625.24 crore towards the project till 31st march. The breakup of the same is given below:
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 2
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
Particulars Amount (Rs. In Cr.)
Land & Related Cost including EDC/IDC 194.03
Construction/Development Expenses
• Civil/Site Development 417.48
• Consultancy & Designing Fees 12.38
• Other Misc. Expenses 1.35
Total 625.24
Copy of Certificate of Capital Investment is enclosed as Annexure III
OBJECTIVES:
• To analyze the outcomes of EIA studies.
• To monitor the environmental data that has been collected in the assessment with the standards,
predictions and expectations outlined prior to the projects’ commencement.
• To evaluate taking into account the findings of the project in relation to standards, pre-project
predictions and expectations.
• To establish the links between pre-project goals and targets and post project achievements.
• Control of project and environmental impacts
METHODOLOGY:
1. Monitoring – Collection of Environmental data (one day) post project scenario during
construction phase. The parameters include:
a. Ambient Air Monitoring
b. DG stack emissions
(Total no. of DG set deployed: 9; Cumulative capacity : 3095 kVA)
• 500 kVA : 2 nos.
• 400 kVA : 1 no.
• 380 kVA : 3 nos.
• 250 kVA : 1 no.
• 125 Kva : 1 no.
• 180 kVA : 1 no.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 3
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
c. Ambient Noise levels at the project boundary
d. Soil analysis
e. STP Treated water report
Other related information was collected during site visits as well as compliance of the
conditions were monitored and recorded during site visits.
2. Evaluation – the appraisal of the conformance with standards, predictions or expectations as
well as the environmental performance of the activity.
3. Management – making decisions and taking appropriate action in response to issues arising
from monitoring and evaluation activities.
4. Communication – informing the stakeholders about the results of EIA follow-up in order to
provide feedback on project/plan implementation as well as feedback on EIA processes.
AGENCY:
The study has been collectively carried out by Gaurang Environmental Solutions, Jaipur & M/s
Aqura Labs Pvt. Ltd. (NABET approved EIA Consultant Organization) &. The environmental
parameters were recorded by M/s Eko Pro Engineers Pvt. Ltd. (NABL accreditated & MOEF
recognized Environmental Laboratory)
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 4
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
COMPLIANCE OF THE CONDITIONS LAID IN THE ENVIRONMENTAL
CLEARANCE
PART A: SPECIFIC CONDITION
1. CONSTRUCTION PHASE
S. No. Condition in EC Compliance status
1. Consent for Establishment shall be
obtained from Haryana State Pollution
Control Board under Air and Water Act
and a copy shall be submitted to the
SEIAA, Haryana before the start of any
construction work at site.
Consent to Establish has been obtained vide letter
no. HSPCB/ Consent/: 2821213 GUSOCTE
301558 dated 27.11.2013. Copy of the CTE is
enclosed as Annexure IV.
2. A first aid room as proposed in the
project report shall be provided both
during construction and operational
phase of the project.
The first aid facility has been provided at site and
will be maintained throughout the construction and
post construction phase. Photographs showing the
same are enclosed as Annexure V.
3. Adequate drinking water and sanitary
facilities should be provided for
construction workers at the site.
Provision should be made for mobile
toilets. Open defecation by the labours is
strictly prohibited. The safe disposal of
waste water and solid waste generated
during the construction phase should be
ensured.
Safe drinking water: Effective arrangements for
sufficient supply of wholesome drinking water
have been provided at suitable points conveniently
situated for all persons employed. Photographs
showing the same are enclosed as Annexure VI.
Toilet Facility: Separate temporary toilets have
been provided for male and female workers at site.
The toilets are conveniently situated so that they
are accessible to the building workers at all times.
Photographs showing the same are enclosed as
Annexure VII. Further, the contractors are abided
to ensure that there is no open defecation by the
labours.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 5
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
Waste Water Disposal: Waste water generated
during construction phase is being routed to septic
tank followed by soak pit.
Solid Waste Disposal:
a. Municipal solid waste generated (168 kg/day)
is being sent to Municipality disposal site.
b. Construction waste: About 30,600 MT of the
construction waste is estimated to be generated
(Source: TIFAC report). Details of the same
are summarized as under:
S.
No.
Particulars Waste generation as
per standard (MT)
Actual Waste
Generation till date
Disposal
1. Wood 14688 Nil Sold to vendors
2. Dry Wall
6120
1731 MT Reused within project site
(photographs enclosed as
Annexure VIII)
3. Concrete 2754 6000 cu. m. Reused for filling purposes
4. Metal Scrap
612
329 MT Sold to vendors (Details
enclosed as Annexure IX )
5. Cardboard 4590 Nil Sold to vendors
6. Plastics 612 Nil Sold to vendors
7. Electronic Scrap 612 Nil Disposal site.
8. Misc.(Paint,
Ceramic etc) 612
Nil Disposal site.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
EIA Coordinator
4. All the topsoil excavated during
construction activities should be stored
for use in horticulture/landscape
development Within the project site.
5. The project proponent shall ensure that
the building material required during
construction phase is properly stored
within the project area and disposal of
construction waste should not create
any adverse effect on the
communities and should be disposed of
after taking necessary precautions for
general safety and health aspects of
people, only in approved sites with the
approval of competent authority.
Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to
P a g e | 6
For Orris Infrastructure Pvt. Ltd.
All the topsoil excavated during
construction activities should be stored
for use in horticulture/landscape
development Within the project site.
The topsoil excavated during construction phase
has been preserved and stock piled. Photographs
showing the same are enclosed as
Temporary seeding, mulching
preserve the top soil. The same will be reutilized
later within the project site for landscaping
purposes.
The project proponent shall ensure that
the building material required during
construction phase is properly stored
within the project area and disposal of
should not create
any adverse effect on the neighbouring
and should be disposed of
after taking necessary precautions for
general safety and health aspects of
people, only in approved sites with the
approval of competent authority.
Building material storage:
required for construction is being
designated storage area within the project premises.
Photographs showing the same are enclosed as
Annexure XI. Capacity of storage for various
building materials are as follows :
S. No. Material
1. Steel
2. Cement
3. Sand
4. Aggregate
5. Admixtures
6. Fly ash
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
The topsoil excavated during construction phase
has been preserved and stock piled. Photographs
showing the same are enclosed as Annexure X.
Temporary seeding, mulching has been done to
The same will be reutilized
project site for landscaping
terial storage: Building material
is being properly stored in
designated storage area within the project premises.
Photographs showing the same are enclosed as
Capacity of storage for various
follows :
Storage Capacity
1000 MT
45,000 bag
6500 MT
13000 MT
22,000 kg
100 MT
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 7
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
Construction Waste Management :
The construction waste generated during
construction phase is being managed effectively by
the contractors and site engineers. Instructions have
been given to the contractor to dispose-off the solid
waste with prior permission at the municipality
disposal sites only. However, efforts have been
made to reduce the quantity of the waste generated
by proper management of the construction material
and judicious use of the resources. The
management has been given at point no. 3 above.
6. Construction spoils, including
bituminous material and other
hazardous materials must not be
allowed contaminant water courses at
the dump sites for such material must be
secured so that they do not leach in to
the ground water and any hazardous
waste generated during construction
phase, should be disposed off as per
applicable rules and norms with
necessary approval of the Haryana State
Pollution Control Board.
There will be no hazardous waste including
bituminous waste generated during the
construction phase as define under HWM Rules,
2008. However, the construction waste generated
during construction phase is being managed
effectively by the contractors and site engineers.
Instructions have been given to the contractor to
dispose- off the solid waste with prior permission
at the municipality disposal sites only. However,
efforts have been made to reduce the quantity of
the waste generated by proper management of the
construction material and judicious use of the
resources.
7. The diesel generator sets to be used
during construction phase should be of
low sulphur diesel type and should
conform to Environment (Protection)
Rules prescribed for air and noise
emission standards.
D.G. set conforming to the applicable rules for air
and noise emissions has been deployed at the site.
Total 9 DG sets have been deployed at site of
cumulative capacity 3095 kVA. Photographs
showing the same are enclosed as Annexure XII.
Analysis report for stack emission is enclosed as
Annexure XIII.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 8
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
Low sulphur fuel (sulphur content: 0.05%) is being
used in the DG sets during construction phase.
Copy of HSD bills are enclosed as Annexure XIV.
8. The diesel required for operating DG
Sets shall be stored in underground
tanks and if required, clearance from
Chief Controller of Explosive shall be
taken.
Diesel used for D.G. sets is being and will be stored
in plastic drums. Photographs showing the same are
enclosed as Annexure XV. Further, the same is
placed on impervious base to avoid contamination
of soil or ground water due to spillages.
9. Ambient noise level should conform to
the residential standards both during
day and night. Incremental pollution
loads on the ambient air and noise
quality should be closely monitored
during construction phase. Adequate
measures should be taken to reduce
ambient air and noise level during
construction phase, so as to conform to
the stipulated residential standards.
All necessary measures have been adopted to
ensure that air & noise levels conform to residential
standards laid down by CPCB. The same are listed
as under:
• Unnecessary idling has been avoided through
the use of auxiliary power units, electric
equipment, and strict enforcement of idling
limits.
• Heavy vehicles carrying construction material
are being and will be operated during night time
to avoid traffic congestions especially during
the peak hours.
• Minimum use of DG set (only at the time of
power cuts or failure).
• Regular sprinkling to minimize the fugitive
emissions.
• PUC Certified vehicles are being used. Copy of
PCU certificates are enclosed as Annexure
XVI.
Ambient noise monitoring has been carried out at
site and the results are well within the permissible
standards. Copy of monitoring reports enclosed as
Annexure-XVII.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 9
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
10. Fly ash should be used as building
material in the construction as per the
provisions of fly ash notification of
September 1999 and as amended on 27th
August 2003.
Fly ash has been used as building material as
mentioned under:
S.
No.
Building
Material
Fly Ash
content
Quantity used
(till 31.03.2015)
1. Portland
Pozzolana
Cement (PPC)
15-35% 2105.5 MT
(42,113 bags)
2. Fly ash bricks 60-80% 4,09,928 nos.
3. Fly ash (for
RMC)
100% 17,397.75 MT
Separate records of the same are being maintained
at site. Copy of Stock Summary is enclosed as
Annexure-XVIII.
11. Storm water control and its reuse as per
CGWB and BIS standards for various
applications should be ensured.
Storm water control and rain water harvesting will
be done as per the standards laid down by CGWA
& BIS. Following measure will be adopted for the
same:
Construction Sequencing: Construction
sequencing (involves disturbing only part of a site
at a time to prevent erosion from dormant parts)
has been done at site. Grading activities and
construction are completed and soils are effectively
stabilized on one part of the site before grading and
construction commence at another part.
Compost Blankets: A compost blanket is a layer
of loosely applied composted material placed on
the soil in disturbed areas to reduce storm water
runoff and erosion. This material fills in small rills
and voids to limit channelized flow, provides a
more permeable surface to facilitate storm water
infiltration, and promotes re-vegetation.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 10
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
12. Water demand during construction
should be reduced by use of pre mixed
concrete, curing agents and other best
practices.
Best construction practices has been adopted to
reduce the water demand for construction
activities:
• Use of curing water: Spraying of curing water
and after liberal curing, all concrete structures
are covered with gunny bags, followed by
spraying of water. Photographs & bills of the
same are enclosed as Annexure --XIX.
• Use of polymer dispersion and air entraining
agents to reduce the construction water demand.
• Admixtures are being used to reduce water
demand during construction. Bills of admixtures
are enclosed as Annexure XX.
• Ready mix concrete is being used to the extent
possible, for construction purposes to reduce
the water demand.
• Discouraging the washing of vehicles and
equipment on the construction site. Workers are
not allowed to wash their personal vehicles on
site. Vehicles and equipment that regularly
leave the construction site should be washed
offsite.
13. In view of the severe constrains in
water supply augmentation in the region
and sustainability of water resources,
the developer will submit the NOC from
CGWA specifying water extraction
quantities and assurance from HUDA/
utility provider indicating source of
water supply and quantity of water with
details of intended use of water –
Drinking water (Potable): is being met through
tanker water supply of HUDA. Copy of bills
enclosed as Annexure XXI.
Construction water (Non-potable): The water
demand is being met from STP treated waste water
supply from HUDA (primary & secondary treated)
treated) which is being treated in STP of capacity
125 KLD (secondary & tertiary treatment) and then
reused for construction activities.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 11
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
potable and non-potable. Assurance is
required for both construction and
operation stages separately. It shall be
submitted to the SEIAA and R.O.,
MoEF, Chandigarh before the start of
construction.
Related records:
a. HUDA water supply bills: Annexure XXI.
b. No Objection Certificate from HUDA,
Gurgaon: Annexure XXII.
c. Details of STP (invoice, AMC bills, drawings
and other details): Annexure XXIII.
Ground water is not being used for construction
activities.
During operational phase of the project water
demand will be met through water supply from
HUDA. Ground water will not be used for the
project.
14. Roof should meet prescriptive
requirement as per energy conservation
building code by using appropriate
thermal insulation material.
Thermal characteristics of the roof assembly shall
be as under:
Climate zone: Composite*
Building Type: 24 hrs. used building
U value (W/m2-°C) 0.409
R value (m2°C/W) 2.1
*Source:ECBC CODE 2007
Following measures will be adopted to reduce the
heat ingress into the building:
• The solar panels will be provided on the roof
which will help to reduce exposed area, thereby,
reducing the heat gains inside the building.
• Energy efficient materials, heat reflecting terrace
surface and roof (by using broken white china
tiles & heat reflecting paint) will be provided to
reduce heat gains.
• Broken bricks will be used for roof insulation.
15. Opaque wall should meet prescriptive
requirement as per Energy Conservation
Thermal characteristics of the wall assembly shall
be as under:
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 12
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
Building Code which is proposed to be
mandatory for all air conditioned spaces
while it is desirable for non-air
conditioned spaces by use of
appropriate thermal insulation material
to fulfil requirement.
Climate zone: Composite*
Building Type: 24 hrs. used building
U value (W/m2-°C) 0.352
R value (m2°C/W) 2.35
*Source:ECBC CODE 2007
The project is multi storied non central air
conditioned group housing. The wall will be made
with fly ash bricks, AAC blocks, plastered outside
and water proofing paint. Shading devices provided
to shade to windows and external façade.
Following measures will be adopted to reduce the
heat ingress inside the building:
• Recessed windows and Covered balconies to
limit direct heat gains.
• Use of fly ash based cement having lower u &
R values.
16. The approval from competent authority
shall be obtained for structural safety of
the building on account of earthquake,
adequacy of fire fighting equipments,
etc. As per National Building Code
including protection measures from
lightening etc. If any forest land is
involved in the proposed site, clearance
under Forest Conservation Act shall be
obtained from the competent authority.
Structural Stability: The entire building has been
designed as per the provisions of National Building
Code-2005 for structural safety of the building
against any possible earthquakes. Copy of the
Structural Stability Certificate is enclosed as
Annexure- XXIV.
Fire NOC: Proper fire fighting arrangements have
been made at site. Photographs showing the same
are enclosed as Annexure XXV. Details of Fire
extinguishers are enclosed as Annexure XXVI.
Fire NOC from Municipal Corporation, Gurgaon
has been obtained vide letter no FS/MCG/ 2013/
564 dated 01.03.2013. Copy of the same is
enclosed as Annexure-XXVII.
Height Clearance form AAI: NOC has been
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 13
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
obtained from Airport Authority of India vide letter
no. AAI/NOC/2012/120/77 dated 17.04.2012.
Copy of the same is enclosed as Annexure
XXVIII.
Further, Forest Clearance under Forest
Conservation Act is not applicable as there is no
forest land involved in the project. The copy of
certificate obtained from Divisional Forest Officer,
Gurgaon is enclosed as Annexure XXIX.
17. Overexploited groundwater and
impending severe shortage of water
supply in the region requires the
developer to redraw the water and
energy conservation plan. Developer
shall submit details of good practices
that have been included in the project to
reduce the overall footprint of the
proposed development including a
detailed water balance along with
source and quantities of potable and
non-potable water requirement
(including water requirement during
construction phase) incorporating water
efficiency / saving measures as well as
water reuse / recycling within 3 months
to the SEIAA, Haryana and R.O. MoEF,
GOI, Chandigarh.
During construction phase water demand is being
met through treated water supply from HUDA.
Water conservation measures (Construction
Phase): has been detailed at point 12 above.
Post construction Phase:
Revised water balance as per condition no. 38 of
the environmental clearance has been prepared on
the basis of 135 lpcd. As per revised water
demand calculation the total water demand
including source and quantities of fresh and
treated water requirement is given in table below:
Total Water Demand : 530 KLD
Type Quantity Source
Fresh water 1312 KLD HUDA water supply
Treated water 1536 KLD STP treated water
Detailed water balance along with water
demand calculation is given in point no. 38.
The water and energy conservation plan is given
below:
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 14
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
Water conservation measures (Post Construction phase):
• Dual plumbing system has been proposed for the project to utilize the treated waste water for
flushing (658 KLD), landscaping and general washing (878 KLD). This will help in reducing the
fresh water demand by 54% (1536 KLD)
• Dual flushing fixtures will be used to allow different volumes of water for solid and liquid
flushing which will help in conserving the water demand for flushing significantly.
• Landscape design & management of irrigation systems:
• Drought tolerant species will be selected.
• Turfs will be avoided to the extent possible.
• Central shut off valve will be provided
• Drip irrigation/ sprinkler irrigation system will be used to conserve water
• Water meters will be installed for the following:
• Potable water consumption
• Landscape water consumption
• Hot water consumption through solar systems, at building level
• Treated waste water consumption
• DG cooling water make up
Energy Conservation Measures (Construction Phase):
• Efficient work scheduling and methods that minimise equipment idle time and double handling of
material
• Switching off construction equipment when not in use
• Switching off site office equipment and lights and using optimum lighting intensity for security
and safety purposes
• Regular maintenance of equipment to ensure optimum operations and fuel efficiency.
18. The project proponent shall construct
47 nos. Rain water harvesting pits for
recharging the ground water within
the project premises. Rain water
harvesting pits shall be designed to
Rain water harvesting (RWH) system for roof run-off
and surface run-off has been designed and
implemented as per the submitted plan & GOI manual.
47 nos. of rain water harvesting pits will be provided
for rain water harvesting during operational phase of
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 15
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
make provisions for silting chamber
and removal of floating matter before
entering harvesting pit. Maintenance
budget and persons responsible for
maintenance must be provided. Care
shall also be taken that contaminated
water do not enter any RWH pit.
the project.
Design of Rain Water Harvesting :
For good design of rainwater harvesting, following
points are to be kept under consideration:
• Ideal location with good ground slope.
• The location has adequate subsurface permeability
of the aquifer to accommodate maximum recharge
of rainwater through injection well.
• Rate of filtration should exceed average rainfall
intensity.
• Clogging of filtration media should be cleaned
periodically.
• Ground water pollution does not take place.
• There will be provision of silting chamber to
remove floating matter before entering harvesting
pit.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 16
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
Contamination from different sources may affect the quality of runoff water. Contaminants commonly found in
storm water runoff and their likely sources are summarized in Table below:
S. No. Contaminant Sources Impact Mitigation
1. Sediment &
Floatables
Streets, lawns, driveways,
roads, construction
activities,
During construction, sediment fencing or
other erosion control devices will be used
to mitigate the short-term adverse impacts
of sedimentation.
2. Oil & Grease Roads, driveways, parking lots
etc.
Oil & Grease trap will be provided to
remove oil & grease, suspended matter,
and ensure the quality of water.
19. The project proponent shall provide for
adequate fire safety measures and
equipments as required by Haryana Fire
Service Act, 2009 and instructions issued
by the local Authority / Directorate of fire
from time to time. Further the project
proponent shall take necessary permission
regarding fire safety scheme/NOC from
competent Authority as required.
The same will be complied with.
Fire NOC: Fire NOC from Municipal
Corporation, Gurgaon has been obtained vide
letter no FS/MCG/ 2013/ 564 dated 01.03.2013.
Copy of the same is enclosed as Annexure-
XXVII. Adequate fire safety measure has been
adopted at site :
a. Good construction practises
b. All Safe construction practices &
precautionary measures will be adopted and
use of PPE will be mandatory.
c. Adequate fire-fighting arrangements will be as
per National Building Code - 2005 &
conditions laid in fire NOC.
d. All applicable IS standards for electricity will
be followed during construction phase.
e. Indian Electricity Act of 1910 and rules issued
there under revised up to date will be
followed.
f. Regulations for electrical equipment in
building issued by The Bombay Regional
Council of Insurance Association of India will
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 17
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
be followed.
20. The project proponent shall submit
assurance from the DHBVN for supply of
20876 kVA of power supply before the
start of construction. In no case project
will be operational solely on generators
without any power supply from any
external power utility.
Copy of Assurance letter issued form DHBVN
regarding power supply to the project is enclosed
as Annexure XXX.
DG sets will be used as power back source only
during the power cuts & failure only and the
project will not be operational solely on generators
without any power supply from any external
power utility.
21. Detail calculation of power load and
ultimate power load of the project shall be
submitted to DHBVN under intimation to
SEIAA Haryana before the start of
construction provisions shall be made for
electrical infrastructure in the licensed
area.
Detailed calculation of power load has been
submitted to DHBVN on the basis of which power
supply assurance letter has been issued from
DHBVN. Copy of letter is enclosed as Annexure
XXX.
22. The project proponent shall not raise any
construction in the natural land depression
/ Nallah / Water course and shall ensure
that the natural flow from the Nallah/
Water course is not obstructed.
The same is noted and no construction will be
carried out in the natural land/ nallah or water
course.
23. The project proponent shall keep the
plinth level of the building blocks
sufficiently above the level of the
approach road to the group housing
project as per prescribed by-laws. Levels
of the other areas in the group housing
project shall also be kept suitably so as to
avoid flooding.
The plinth level of the building blocks is
constructed sufficiently above the level of the
approach road.
24. Construction shall be carried out so that
density of population does not exceed as
The maximum density of population due to the
proposed project will not exceed the approved
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 18
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
approved by Director General Town and
Country Department, Haryana.
density of population by Director General Town
and Country Department, Haryana. The same is
summarized as under:
Max. Population density as per
approved zoning plan
Population Achieved Population density
as per design
Population
300 ppa 14,165 290 13,695
25. The project proponent shall submit an
affidavit with the declaration that ground
water will not be used for construction
and only treated water should be used for
construction.
During construction phase of the project water
demand is being met from treated water from
HUDA. Copy of Certificate in this regards issued
from HUDA, Gurgaon, is enclosed as Annexure -
XXII--. The affidavit in this regard was submitted
during the EIA stage. We would like to assure that
ground water is not being used for construction
activities.
26. The project proponent shall not cut any
existing tree and project landscaping plan
should be modified to include those trees
in green area.
The content of para 30 are noted and will be
followed.
27. The project proponent shall provide
helipad facility as required under NBC
norms and shall seek permission of
helipad from AAI accordingly.
The same is not applicable on the project as the
maximum height of the building will be 50 meter.
Helipad facility needs to be provided when
building height is more than 60 meters.
28. The project proponent shall ensure that
ECBC norms for composite climate zone
are met. In particular building envelope,
HVAC service, water heating, pumping,
lighting and electrical infrastructure must
meet ECBC norms.
The same will be complied with. Thermal
characteristics of the building envelope (roof, wall
and vertical fenestration) for composite climate
zone will be as under:
Building Type: 24 hrs. used building
Roof Assembly
U value (W/m2-°C) 0.409
R value (m2°C/W) 2.1
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 19
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
Wall Assembly
U value (W/m2-°C) 0.352
R value (m2°C/W) 2.35
Vertical Fenestration:
Maximum U-
factor
Maximum
SHGC
Maximum
VLT
3.30 W/m2-°C 0.25 0.27
*Source:ECBC CODE 2007
29. The project proponent shall provide 3
meter high barricade around the project
area, dust screen for every floor above
the ground, proper sprinkling and
covering of stored material to restrict
dust and air pollution during
construction.
The same will be complied with. Following
measures have been adopted for mitigating dust
pollution during construction phase:
• Minimise dust generating activities
• The site has been covered from all four sides.
• Water sprinkling on haul roads.
• Water or Dust suppressants which are more
effective than water, will be applied judiciously
• Covering the stockpiles to prevent wind whipping
• Storage pile activity will be conducted downwind
• Unpaved roads will be properly maintained.
• Minimizing the haul roads by construction of semi
pucca roads during construction phase (photographs
of the same are enclosed as Annexure XXXI.
30. The project proponent shall construct
sedimentation basin in the lower level of
the project site to trap pollutant and other
wastes during rain.
The content of para 30 are noted and will be
followed.
31. The project proponent shall provide
proper rasta of proper width and proper
strength for the project before the start of
construction.
The same has been complied with.
32. The project proponent shall provide all Following measure has been adopted for safety of
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 20
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
the safety measures for the workers
during construction of high rise building.
construction workers:
• All Safe construction practices & precautionary
measures has been adopted and use of PPE is
mandatory. Details of PPE are enclosed as
Annexure –XXXII.
• First-aid measures are provided at site.
Photographs of the same are enclosed as
Annexure -V
• Adequate fire-fighting arrangements will be as
per National Building Code - 2005 & conditions
laid in fire NOC.
• All applicable IS standards for electricity will be
followed in construction phase
33. The project proponent shall ensure that
the U value of the glass is less than 3.177
and maximum solar heat gain co-efficient
is 0.25 for vertical fenestration.
The same will be complied with. However, as per
ECBC 2007, the thermal characteristics of the
vertical fenestration will be as under:
Maximum U-factor Maximum SHGC Maximum VLT
3.30 W/m2-°C 0.25 0.27
Source:ECBC CODE 2005
34. The project proponent shall ensure
structural integrity of high rise building
during any seismic activity.
The entire building has been designed as per the
provisions of National Building Code-2005 for
structural safety of the building against any
possible earthquakes. Copy of the Structural
Stability Certificate is enclosed as Annexure-
XXIV.
35. The project proponent shall adequately
control construction dust like silica dust,
non-silica dust and wood dust. Such
dusts shall not spread outside project
premises. Project Proponent shall
The same will be complied with. Following
measures have been adopted for mitigating dust
pollution during construction phase:
• Cutting and grinding operations on site should
be conducted using equipment and techniques
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 21
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
provide respiratory protective
equipments to all construction workers.
that suppress and reduce dust emissions
• Respiratory protective equipments has been
provided to the construction workers. Bills of
personal protective equipments are enclosed as
Annexure XXXII.
36. The project proponent shall ensure that
the plinth level of the building block to
be 1.5 meter above 100 years flood
level.
The same is noted and will be followed.
37. The site for solid waste management
plant to be earmarked on the layout plan
and the detailed project for setting up
the solid waste management plant shall
be submitted to the Authority within one
month.
The same has been complied with. Solid waste
generated during construction phase is being
handled as per rules and norms.
Detailed solid waste management plan during
construction & post construction phase given at
point no. 3 above.
38. The project proponent shall design
water requirement @135 lpcd for EWS
blocks and shall submit revised water
requirement, STP capacity, waste water
generation and water balance diagram
before the start of the construction.
The water demand calculation and revised water
balance showing quantity of fresh and treated
water demand is given below:
Water Demand Calculation:
S.
No.
Particulars Population Fresh water demand Treated water demand Total water
demand
Residential development
1. Residents 13695 @ 90 LPCD: 1233 KLD @45 LPCD: 616 KLD 1849 KLD
2. Servants 472 @ 90 LPCD: 43 KLD @ 45 LPCD: 21 KLD 64 KLD
3. Staff 500 @ 30 LPCD: 15 KLD @ 15 LPCD: 8 KLD 23 KLD
4. Visitors 2150 @ 9 LPCD: 19 KLD @ 6 LPCD: 13 KLD 32 KLD
5. Swimming pool 2 KLD -- 2 KLD
Others
5. Landscaping -- 870 KLD 870 KLD
6. General washing -- 8 KLD 8 KLD
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 22
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
Total 1312 KLD 1536 KLD 2848 KLD
Revised Water Balance:
Fresh
water
1312 KLD
Residential 1276 KLD
Staff & visitors 34 KLD
STP
treated water
1536 KLD
Flushing 658 KLD
Landscaping 870 KLD
1706 KLD
Waste water
S
T
P
Capacity
1800 KLD
Sludge &
evaporation
losses
170 KLD
Recycled/ reused for flushing, landscaping & general washing
1021
27
658
Daily water demand: 2848 KLD
{1312KLD (fresh) + 1536 KLD (recycled/ reused water)}
general washing 8 KLD
Swimming pool 2 KLD
Source: Fresh Water : HUDA Water Supply; Treated Waste water: STP Treated Water
39. The project proponent shall provide one
refuse area till 24 meter, one till 39
meter and one each after 15 meter as per
National Building Code.
The same will be complied with. Refuge areas
will be provided as per National Building Code
2005.
40. The project proponent shall provide fire
control room and fire officer for
building above 30 meter as per National
Building Code.
Proper fire fighting arrangements has been made
as per NBC 2005.
41. The project proponent shall obtain
permission of Mines & Geology
Department for excavation of soil before
the start of construction.
The same has been complied with. Copy of
mining approval obtained from Department of
Mines & Geology is enclosed as Annexure
XXXIII.
42. The project proponent shall ensure that
no construction activity is undertaken on
No construction activity has been/ will be carried
out on revenue rasta passing through the project
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 23
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
surface of revenue rasta passing through
the project area.
area.
43. The project proponent shall indicate the
width and length of revenue rasta
passing through the project area on sign
board and shall display the same at both
the ends of revenue rasta stretch, for
awareness of public. Sign board shall
also display the message that this is
public rasta/road and any citizen can use
it. There shall not be any gate with or
without guards on revenue rasta and
passage through the revenue rasta shall
remain fully unobstructed.
The content of para 43 are noted and will be
followed.
44. The project proponent shall develop
complete civic infrastructure of the
group housing colony including internal
roads, green belt development, sewerage
line, rain water harvesting arrangements,
storm water drainage system, solid
waste management site and provision
for treatment of bio-degradable waste,
STP, water supply line, dual plumbing
line, electric supply lines etc. and shall
offer possession of the units/flats
thereafter.
The same will be complied with. Complete
infrastructural facilities will be provided before
operational phase of the project.
• Proper internal roads with adequate width will
be provided.
• Greenbelt development: About 65,875.6 sq. m.
(34.5%) area will be under landscape during
operational phase of the project.
• Sewerage Line: separate pipeline will be
provided for sewage generated from the project.
• Rain water harvesting: rain water harvesting
will be done in the project. About 47 nos. of
rain water harvesting pits will be provided to
recharge the ground water aquifer.
• Solid waste management: Solid waste generated
from the project will be handled as per
Municipal Solid Wastes (Management and
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 24
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
Handling) Rules, 2000 and amended Rules,
2008. The same is described at point no. (e) of
operational phase conditions.
• STP: for waste water treatment 5 STPs of
cumulative capacity 1900 KLD will be provided
at site.
• Duel plumbing will be done during operational
phase of the project.
45. The project proponent shall not raise
any construction activity in the ROW
reserved/acquired for High Tension
Wire passing through the project area
and shall maintain horizontal and
vertical ROW as required under Indian
Electricity Rules, 1956/ DHBVN latest
instruction.
The content of para 45 are noted and will be
followed.
46. The project proponent shall ensure that
natural flow of existing nallah is never
obstructed and shall seek NOC from
irrigation department / HUDA regarding
this before the start of the construction.
The flow of existing nallah will not be obstructed
due to upcoming of the project.
47. The project proponent shall ensure that
in case of excessive flow of water in
nallah, the structural integrity of
building along-side the nallah is not
breached in any circumstances.
The contents of para 47 are noted and will be
complied with.
48. The project proponent shall ensure that
sewerage pipe line will not cross over
the nallah and project proponent shall
maintain separate STP in the plot area
across the nallah.
The sewerage pipeline will not cross over the
nallah. There will be 5 STPs of cumulative
capacity 1900 KLD (340 KLD, 500 KLD, 500
KLD, 520 KLD, 40 KLD) provided at site.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 25
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
49. The project proponent shall ensure that
sewerage line shall be planned by taking
into account the natural slope and
gravity of original land.
The same will be complied with.
50. The project proponent shall ensure that
bed of nallah is not encroached in any
manner, while constructing the culvert
over the nallah. For construction of any
culvert over/ crossing the nallah
permission / NOC from the concerned
department shall be obtained.
The contents of para 50 are noted and will be
complied with.
51. The project proponent shall get
inspection of nallah done before the
onset of monsoon season every year
from irrigation department.
The same will be complied with.
52. The project proponent shall provide
pervious surface instead of impervious
and hard surface in order to reduce
overflow water in nallah.
Hard paving (imperviousness) on the site will be
minimized to the extent possible. An area of
about 65875.6 sq. m. (34.5%) will be under
landscape. Further, the storm water system has
been designed on the basis of peak intensity of
rainfall, therefore, the possibility of overflow in
the event of heavy downpour will be minimized.
53. The project proponent shall not
discharge untreated water in the nallah
and also shall not throw any solid waste
in the nallah.
The same will be followed. No treated or
untreated water will be discharged in to the
nallah. Solid waste generated will be handled as
per MSW rules. No waste will be dumped in to
the nallah or any other water body.
54. The project proponent shall provide one
refuse area till 24 meter, one till 39
meter, and one each after 15 meters as
per National Building Code.
The same will be complied with. Refuge areas
will be provided as per National Building Code
2005.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 26
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
55. The project proponent shall provide fire
control room and fire office for building
above 30 meter as per National Building
Code.
Proper fire fighting arrangements has been made
as per NBC 2005.
56. The project proponent shall design
water requirement @135 lpcd for EWS
blocks and shall submit revised water
requirement, STP capacity, waste water
generation and water balance diagram
before the start of the construction. All
system of water supply, sewerage
system, STP etc. Shall be provided
based on revised requirement of 135
lpcd.
We have prepared a revised water balance at the
basis of 135 lpcd instead of 86 lpcd. The water
demand calculation and revised water balance
showing quantity of fresh and treated water
demand is given at point no. 38.
57. The project proponent shall ensure that
there should not be any water logging
and obstruction of flow in nallah. The
width of the nallah to be kept shall be
got approved from concerned authority
i.e. irrigation department/ HUDA
keeping in view past records and
proposed future requirements.
The same will be followed.
2. OPERATIONAL PHASE
a. “Consent to Operate” shall be obtained
from Haryana State Pollution Control
Board under Air & Water Act and a
copy shall be submitted to the SEIAA,
Haryana.
Consent to Operate will be obtained before
operational phase of the project.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 27
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
b. The sewage treatment plant shall be
installed for the treatment of the sewage
to the prescribed standards including
odour and treated effluent will be
recycled. The installation of STP should
be certified by an independent expert
and a report in this regard should be
submitted to the SEIAA Haryana before
the project is commissioned for
operation. Tertiary treatment of waste
water is mandatory. Discharge of treated
sewage shall conform to the norms and
standards of HSPCB, Panchkula. Project
Proponent shall implement such STP
technology which does not require filter
backwash.
The STP will be commissioned under the
guidance of an expert. Sewage treatment plant
scheme will be approved by HSPCB. The treated
effluent conforms to the standards laid down by
HSPCB. The treated effluent from STP will be
reused for flushing – 658 KLD, landscaping – 870
KLD, & general washing – 8 KLD.
The STP will be based on the MBBR technology
with capacity of 1900 KLD.
Characteristics of the treated effluent shall be as
under:
Parameters Influent Treated
effluent
pH 7.5 - 8.5 7 - 8
Suspended solids 200- 225 mg/l <50 mg/l
BOD 200 - 250 mg/l <10 mg/l
COD 350 - 400 mg/l <250 mg/l
Oil & Grease 20-25 mg/l <5 mg/l
Coliform (CFU
/100 ml)
103- 10
5 50-500 or less
c. Separation of the grey and black water
should be done by the use of dual
plumbing line. Treatment of 100% grey
water by decentralized treatment should
be done ensuring that the re-circulated
water should have BOD maximum upto
10 mg/lit and the recycled water will be
used for flushing, gardening and DG set
cooling to achieve zero exit discharge.
The same will be complied with. Dual plumbing
will be done during the operational phase of the
project. The STP treated water will be
recycled/reuse for flushing landscaping and
general washing purposes.
d. For disinfection of the treated waste
water ultra-violet radiation or
ozonization process should be used.
The same will be complied with. Ozone treatment
or UV radiation process will be used for
disinfection of treated waste water.
e. The solid waste generated should be The solid waste generated from the project will be
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
EIA Coordinator
properly collected and segregated. Bio
degradable waste shall be decomposed
at site and dry / inert solid waste should
be disposed off to approved sites for
land filling after recovering recyclable
material.
S.
No.
Bins Particulars
1. Green
(households)
Compostable waste
• Kitchen
• Garden waste
2. Dark grey
bins
(households)
Non – biodegradable
+ recyclable waste:
• Plastics
• Metal cans
• Glassware
• Misc.
3. Blue
(households)
Paper waste
• Paper
• Newspaper
• Cardboards
• Packing material
Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to
P a g e | 28
For Orris Infrastructure Pvt. Ltd.
properly collected and segregated. Bio
degradable waste shall be decomposed
/ inert solid waste should
be disposed off to approved sites for
land filling after recovering recyclable
mainly domestic waste and estimated quantity of
the same is approx. 6121 kg per day
arrangements will be made at the site in
accordance to Municipal Solid Wastes
(Management and Handling) Rules, 2000 and
amended Rules, 2008.
Particulars Quantity Treatment
Compostable waste
Kitchen waste
Garden waste
4896 kg/day No in-situ treatment.
Collected and stored at
designated places.
biodegradable
+ recyclable waste:
Metal cans
Glassware
797 kg/day
• 658 kg/day
• 31 kg/day
• 77 kg/day
• 31 kg/day
No in-situ treatment.
Collected and stored at
designated places.
Paper waste
Newspaper
Cardboards
Packing material
428 kg/day
Efforts to recycle to the
best possible extent.
Will be collected on daily
basis.
Collection and Segregation of waste:
• A door to door collection system
will be plastic bags from household units.
• The vendors will be hired to provide
separate plastic bags for dry
Bio-Degradable waste.
• For commercial waste collection,
adequate number of colour coded bins
(Green and Blue & dark grey separate for
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
mainly domestic waste and estimated quantity of
kg per day. Following
arrangements will be made at the site in
accordance to Municipal Solid Wastes
(Management and Handling) Rules, 2000 and
Disposal
situ treatment.
Collected and stored at
Will be sent
to
municipality
disposal site.
situ treatment.
Collected and stored at
Efforts to recycle to the
best possible extent.
Will be collected on daily
Sent to the
vendors for
recycling.
Collection and Segregation of waste:
A door to door collection system
will be plastic bags from household units.
The vendors will be hired to provide
separate plastic bags for dry recyclables and
Degradable waste.
For commercial waste collection,
adequate number of colour coded bins
(Green and Blue & dark grey separate for
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
EIA Coordinator
Bio-degradable and Non Bio-degradable) are proposed to be provided at the strategic locations of
the commercial area.
• Litter bin will also be provided in open areas like parks etc.
Treatment of waste:
� Bio-Degradable wastes:
• STP sludge will be used for horticultural purposes as manure.
• Horticultural Waste will be composted and will be used for gardening
� Recyclable wastes:
Recyclable wastes like paper, plastic, metals etc. will be sold off to vendors.
Figure: Solid waste management scheme (
f. Diesel power generating sets proposed
as source of backup power for lifts,
common area illumination and for
domestic use should be of enclosed type
and conform to rules made under the
Environment (Protection) Act, 1986.
The location of DG sets should be in
basement as promised by the project
proponent with appropriate stack height
Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to
P a g e | 29
For Orris Infrastructure Pvt. Ltd.
degradable) are proposed to be provided at the strategic locations of
Litter bin will also be provided in open areas like parks etc.
STP sludge will be used for horticultural purposes as manure.
Horticultural Waste will be composted and will be used for gardening purposes.
Recyclable wastes like paper, plastic, metals etc. will be sold off to vendors.
Figure: Solid waste management scheme (Post Construction phase)
Diesel power generating sets proposed
as source of backup power for lifts,
common area illumination and for
domestic use should be of enclosed type
and conform to rules made under the
Environment (Protection) Act, 1986.
The location of DG sets should be in the
basement as promised by the project
proponent with appropriate stack height
D.G. set of cumulative capacity
nos.) will be deployed at the site.
DG sets of capacity < 1000 kVA:
in inbuilt acoustic enclosure designed to meet the
applicable CPCB standards by the manufacturer
(as per the CPCB mandate)
DG sets of capacity > 1000 kVA:
in a room/ enclosure designed to meet the
applicable CPCB standards.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
degradable) are proposed to be provided at the strategic locations of
purposes.
Construction phase)
capacity 29,840 kVA (28
nos.) will be deployed at the site.
of capacity < 1000 kVA: will be housed
in inbuilt acoustic enclosure designed to meet the
applicable CPCB standards by the manufacturer
DG sets of capacity > 1000 kVA: will be housed
in a room/ enclosure designed to meet the
applicable CPCB standards.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 30
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
i.e. above the roof level as per the CPCB
norms. The diesel used for DG sets
should be of low sulphur contents
(maximum upto 0.25%)
The DG sets will be equipped with acoustic
enclosure with proper stack height to minimize
the emission and noise generation.
Low sulphur fuel (sulphur content: 0.05%) will be
used in the DG sets. The details are as under :
S. No. DG Capacity Minimum Stack
height
1. 1500 kVA- 14 nos. 30 m.
2. 1010 kVA-4 nos. 30 m.
3. 750 kVA -3 nos. 5.5 m.
4. 625 kVA- 1 no. 5.0 m.
5. 500 kVA-3 nos. 5.0 m.
6. 160 kVA- 1 no. 5.0 m.
7. 140 kVA- 1 no. 3.5 m.
8. 125 kVA- 1 no. 3.5 m.
g. Ambient noise level should be
controlled to ensure that it does not
exceed the prescribed standards both
within and at the boundary of the
proposed residential complex.
All necessary measures will be adopted to ensure
that noise levels conform to residential standards
laid down by CPCB. The same are listed as
under:
• DG set conforming to the CPCB standards for
noise will be used.
• D.G. sets will be housed in an inbuilt acoustic
enclosure, which will help to contain the noise
within the permissible standards.
• The driveways will have sufficient width so that
there is no congestion of vehicles during peak
hours which lead to increase in the noise levels
• Adequate parking including provisions of
visitors parking.
• Multiple entry/ exits will be provided to ensure
congestion free traffic movements.
• Entry & exits will be manned with trained &
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 31
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
efficient security to ensure smooth flow of
vehicles.
• There will be less starting and stopping and the
vehicles will be speed restricted to ensure the
noise within the permissible limits.
• The area will cover 65,370 sq. m. (34.5%) area
under landscape, which will help to absorb
noise.
h. The project proponent should maintain
at least 34.2% sq. m. As green cover
area for tree plantation especially all
around the periphery of the project and
on the road sides preferably with local
species so as to provide protection
against particulates and noise. The open
spaces inside the plot should be
preferably landscaped and covered with
vegetation / grass, herbs & shrubs. Only
locally available plant species shall be
used.
An area of about 65,875.6 sqm (34.5%) will be
under landscaping. The breakup of the same will
be as under:
Area under tree plantation
(including avenue plantation)
38,217.05 sq. m.
(20%)
Area under water bodies 8,550 sq. m.
(4.5%)
Area under herbs/ shrubs,
climbers
19,108.55 sqm
(10%)
The plantation will be done with native species
only. Total of about 5100 nos. of trees will be
planted in the project.
Suggested list of tree plantation is as under:
S. No. Botanical Name Total Nos. of Trees
Landscaping
1. Anthocephalus cadamba 120
2. Plumeria alba 90
3. Plumeria rubra 70
4. Citrus aurantifolia 68
Total 348
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 32
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
Schedule of Palms
1. Caryota urens 150
2. Cycas 200
Total 350
Shelter Belt
1. Acacia auriculiformis 358
2. Azhadirachta indica 320
3. Ficus benjamina 410
4. Ficus onfectoria 76
5. Peltophorum ferrugineum 308
6. Putranjiva roxburgil 126
7. Schleichera trijuga 105
Total 1703
Avenue Plantation
1. Alstonia scholaris 520
2. Grevillea robusta 500
3. Kigerla pinnata 500
4. Spathodea campanulata 350
5. Tabebuia spectabilis 136
6. Cassia fistula (Indian laburnum) 100
7. Cassia nodosa (pink cassia) 120
8. Chorisea speciosa 96
9. Delonix regia 168
10. Jacaranda mimosifolia 73
11. Erythrina indica (Indian coral tree) 136
Total 2699
Grand Total 5100
i. The project proponent shall strive to
minimize water in irrigation of
landscape by minimizing grass area,
The same will be complied with. Following
measures will be adopted to minimize water
requirement for landscaping :
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 33
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
using native variety, xeriscaping and
mulching, utilizing efficient irrigation
system, scheduling irrigation only after
checking evapo-transpiration data.
• Native & xeriscaping plant species: Choose
native plant species that need less water (list
of the same is provided at point h above).
• Creating Hydrozones: Grouping of plant
according to their water needs to provide
adequate water to all plants without over or
under-watering.
• Maintain Healthy Soil: Healthy soils are the
basis for a water-smart landscape; they
effectively cycle nutrients, minimize runoff,
retain water, and absorb excess nutrients,
sediments, and pollutants.
• Mulching: Incorporate mulch around shrubs
and garden plants to help reduce evaporation,
inhibit weed growth, moderate soil
temperature, and prevent erosion. Adding
organic matter and aerating soil can improve
its ability to hold water.
• Avoid watering during the heat of the day.
Water early in the morning to reduce the
evaporation rate
• Turfs will be avoided to the extent possible
• Central shut off valve will be provided
• Drip irrigation/ sprinkler irrigation system
will be used to conserve water
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 34
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
j. Rain water harvesting for roof run-off
and surface run-off, as per plan
submitted should be implemented.
Before recharging the surface run off,
pre-treatment through sedimentation
tanks must be done to remove
suspended matter, oil and grease. The
bore well for rain water recharging shall
be kept at least 5 mts. above the highest
ground water table. Care shall be taken
that contaminated water do not enter any
RWH pit. The project proponent shall
avoid rain water harvesting of first 10
minutes of rain fall. Roof top of the
building shall be without any toxic
material or paint which can contaminate
rain water. Wire mess and filters should
be used wherever required.
Rain water harvesting (RWH) system for roof
run-off and surface run-off has been designed and
implemented as per the submitted plan & GOI
manual.
Surface run off from the roof top and the paved
areas will be channelized through storm water
network after pre-treatment to remove oil &
grease to remove suspended matter, oil & grease
and ensure the quality of water.
Details of rain water harvesting structures are as
under:
Design Parameters
Average annual rainfall 723 mm
Peak intensity of rainfall 60 mm/hr
Details of structures
Number of structures 47
k. The ground water level and its quality
should be monitored regularly in
consultation with Central Ground Water
Authority.
The ground water monitoring will done and
piezometric well will be constructed in
consultation with Central Ground Water
Authority.
l. There should be no traffic congestion
near the entry and exit points from the
roads adjoining the proposed project
site. Parking should be fully internalized
and no public space should be utilized.
Adequate parking will be provided to avoid traffic
congestion near the entry and exit points. The
movement pattern inside the project area will be
guided traffic ways with one-way traffic
movement to avoid traffic congestion. Fully
internalized parking facilities will be provided at
basement, stilt and open surfaces at well
designated parking places and no public space
will be utilized for the same.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 35
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
m. A report on the energy conservation
measures conforming to energy
conservation norms finalized by Bureau
of Energy Efficiency should be prepared
incorporating details about building
material & technology, R&U Factors etc
and submitted to the SEIAA, Haryana in
three months time.
The detailed report on the energy conservation
measures conforming to energy conservation
norms finalized by Bureau of Energy Efficiency
shall be prepared submitted as desired with
subsequent compliance reports. Energy
conservation measures are detailed below:
• Solar geysers will be used for meeting hot water requirement (top two floors).
• Energy efficient compact Fluorescent Lamps will be used as these CFL gives same illumination
with less wattage compare to GLS Lamps.
• Automatic Power Factor correction panel with capacitor will be used for Common Load & Fixed
Capacitor for Transformer to minimize the losses
• Day light integrated to reduce artificial lighting demand.
• Emphasis will be given on low maintenance, low wattage and longer life in selection of chokes
and lamps for all common area and external light fixtures.
• Use of VF drives in lifts, pumps and other equipments to conserve energy to the tune of 23%
(min)
• Following measures will be adopted to reduce the heat ingress inside the building:
o Recessed windows and Covered balconies to limit direct heat gains.
o The wall will be made with fly ash bricks, AAC blocks, plastered outside and water proofing
paint.
o Shading devices are being provided to shade to windows and external façade.
o Optimizing building envelop & window design to reduce cooling demand (by selecting
energy efficient low U value materials for envelop is application of high reflecting white
china mosaic tiles to terrace).
• Total energy savings:
S. No. Description Saving
1. LED based lighting in basement and parking
lighting
137.44 KVA
2. LED based Lighting will be done in the common 122.85 KVA
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 36
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
areas, landscape areas, signage, entry gates and
boundary walls etc.
3. Solar Lighting is proposed for open spaces and
signage
222.0 KVA
4. Use of solar water heater system 5074.01 KVA
Total energy saving 5556.3 KVA
Total energy consumption 22836 KVA
Energy saved through various provisions 1199.9 KVA
Total Energy Saving 24.33%
n. Energy conservation measures like
installation of LED for lighting the areas
outside the building should be integral
part of the project design and should be in
place before project commissioning. Use
of solar panels must be adapted to the
maximum extent possible for energy
conservation.
LED lights will be used for lighting the areas
outside the building.
Solar Panels will be installed on the terrace
floor and will be used for meeting hot water
requirement.
o. The project proponent shall use zero
ozone depleting potential material in
insulation, refrigeration, air-conditioning
and adhesive. Project proponent shall also
provide halon free fire suppression
system.
The same will be complied with.
p. The solid waste generated should be
properly collected and segregated as per
the requirement of the MSW Rules, 2000
and as amended from time to time. The
bio degradable waste should be
composted by vermin composting at the
site ear marked within the project area and
dry/inert solid waste should be disposed
About 6121 kg/day municipal solid waste will
be generated during the operational phase of the
project which will be collected and segregated
as per the Municipal Solid Waste Rules. The
same is detailed in point no. d. above.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 37
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
off to the approved sites for land filling
after recovering recyclable material.
q. The provision of the solar water heating
system shall be as per norms specified by
HAREDA and shall be made operational
in each building block.
The same will be complied with. Solar water
heating system will be installed as per
guidelines of Haryana Renewable Energy
Development Agency (HAREDA).
r. The traffic plan and the parking plan
proposed by the PP should be adhered to
meticulously with further scope of
additional parking for future requirement.
There should be no traffic congestion near
the entry and exit points from the roads
adjoining the proposed project site.
Parking should be fully internalized and
no public space should be used.
Adequate parking will be provided to avoid
traffic congestion near the entry and exit points.
The movement pattern inside the project area
will be guided traffic ways with one-way traffic
movement to avoid traffic congestion. Fully
internalized parking facilities will be provided
at basement, stilt and open surfaces at well
designated parking places and no public space
will be utilized for the same.
s. The project shall be operationalized only
once HUDA will provide domestic water
supply system in the area.
The contents of para (s) are noted and will be
followed.
t. Operation and maintenance of STP, solid
waste management and electrical
infrastructure, pollution control measures
shall be ensured even after the completion
of sell.
The same will be complied with.
u. Different type of waste should be
disposed off as per provisions of
municipal solid waste, biomedical waste,
hazardous waste, e-waste, batteries &
plastic rules made under Environment
Protection Act, 1986. Particularly E-
Waste and Battery waste shall be disposed
off as per existing E-Waste management
Hazardous waste or bio medical waste will not
be generated from the project. However, the
municipal solid waste generated from the
project will be handled as per the Municipal
Solid Waste (Management & Handling) Rules.
The same is detailed in point number d. above.
E-Waste and battery waste generated from the
project will be disposed off as per norms and
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 38
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
rules 2011and Batteries Management
Rules 2001. The project proponent should
maintain a collection center for E-Waste
and it should be disposed of to only
registered and authorized dismantler /
recycler.
rules.
v. Standards for discharge of environmental
pollutants as enshrined in various
schedules of rule 3 of Environment
Protection Rule 1986 shall be complied
with.
The same will be complied with.
w. Water supply shall be metered in the
project area.
The same will be complied with. Water meter
will be installed to monitor the water usage at
the following points:
� Fresh water intake
� Inlet of flushing tanks
� STP inlet
� STP outlet
� Landscaping
x. The project proponent shall ensure that
the stack height of DG sets is as per the
CPCB guide lines and also ensure that the
emission standards of noise and air are
within the CPCB prescribed limits. Noise
and emission level of DG sets greater than
800 kVA shall be as per CPCB latest
standards for high capacity DG sets.
The same will be complied with. DG sets will
be provided with effective stack height as per
the norms of CPCB. Details of DG Sets and
stack heights is given at point no. (f) above.
y. All electric supply exceeding 100 amp, 3
phase shall maintain the power factor
between 0.98 lag to 1 at the point of
connection.
The same are noted and will be followed.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 39
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
z. The project proponent shall use only
treated water instead of fresh water for
DG cooling. The project proponent shall
also use evaporative cooling technology
and double stage cooling system for
HVAC in order to reduce water
consumption. Further temperature,
relative humidity, during summer and
winter seasons should be kept at optimal
level. Variable speed drive, best
coefficient for performance, as well as
optimal integrated point load value and
minimum outside fresh air supply may be
resorted for conservation of power and
water. Coil type cooling DG sets shall be
used for saving cooling water
consumption for water cooled DG sets.
The same will be complied with.
aa) The project proponent shall ensure that
the transformer is constructed with high
quality grain oriented, low loss silicon
steel and virgin electrolyte grade copper.
The project proponent shall obtain
manufacturer’s certificate also for that.
The contents of para aa are noted and will be
complied with.
ab. The project proponent shall ensure that
exit velocity from the stack should be
sufficiently high. Stack shall be designed
in such a way that there is no stack down-
water under any meteorological
conditions.
The same will be complied with.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 40
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
PART B: GENERAL CONDITION
i. The project proponent shall ensure the commitments
made in Form-1, Form-1A, EIA/EMP and other
documents submitted to the SEIAA for the protection
of environment and proposed environmental
safeguards are complied with in letter and spirit. In
case of contradiction between two or more
documents on any point, the most environmentally
friendly commitment on the point shall be taken as
commitment by project proponent.
The contents of para i are noted and
will be complied with.
ii. Six monthly compliance reports should be submitted
to the HSPCB and Regional Office, MoEF, GOI,
Northern Region, Chandigarh and a copy to the
SEIAA Panchkula, Haryana.
The contents of para ii are noted and
will be complied with.
iii. STP outlet after stabilization and stack emission shall
be monitored monthly. Other environmental
parameters and green belt shall be monitored on
quarterly basis. After every 3 months, the project
proponent shall conduct environmental audit and
shall take corrective measures, if required, without
delay.
The same will be complied with.
iv. The SEIAA Haryana, reserves the right to add
additional safeguards measures subsequently, if
found necessary. Environmental Clearance granted
will be revoked if it is found that false information
has been given for getting approval of this project.
SEIAA reserves the right to revoke the clearance if
conditions stipulated are not implemented to the
satisfaction of SEIAA/MoEF.
The content of para iv are noted and
are undisputed.
v. The project proponent shall not violate any judicial
orders/ pronouncements issued by any court/tribunal.
We will try to the best possible
extent not to violate any judicial
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 41
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
orders/ pronouncements issued by
the Hon’ble Supreme Court/High
Courts.
vi. All other statutory clearances such as the approvals
for storage of diesel from Chief Controller of
Explosive, Fire Department, Civil Aviation
Department, Forest Conservation Act, 1980 and
Wildlife (Protection) Act 1972, Forest Act 1927,
PLPA 1900, etc. shall be obtained, as applicable by
project proponents from the respective authorities
prior to construction of the project.
The same will be complied with as
per applicability on the project.
Fire NOC from Municipal
Corporation, Gurgaon has been
obtained vide letter no FS/MCG/
2013/ 564 dated 01.03.2013. Copy
of the same is enclosed as
Annexure-XXVII.
Forest Clearance under Forest
Conservation Act is not applicable
as there is no forest land involved in
the project. The copy of certificate
obtained from Divisional Forest
Officer, Gurgaon is enclosed as
Annexure XXIX.
vii. The project proponent should inform the public that
the project has been accorded Environmental
Clearance by the SEIAA and copies of the clearance
letter are available with the State Pollution Control
Board & SEIAA. This should be advertised within 7
days from the date of issue of the clearance letter at
least in two local news papers that are widely
circulated in the region and the copy of the same
should be forwarded to SEIAA Haryana.
The copy of the newspaper
advertisement is enclosed as
Annexure XXXIV.
viii. Under the provisions of Environmental (Protection)
Act 1986, legal action shall be initiated against the
project proponent if it was found that construction of
the project has been started before obtaining prior
The content of para viii are noted
and undisputed.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 42
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
Environmental Clearance.
ix. Any appeal against this Environmental Clearance
shall lie with the National Green Tribunal, if
preferred, within a period of 30 days as prescribed
under Section 16 of the National Green Tribunal Act,
2010.
The content of para ix are noted and
undisputed.
x. The project proponent shall put in place Corporate
Environment Policy as mentioned in MoEF, GoI OM
No. J-11013/41/2006-IA II (I) dated 26.04.2012
within 3 months period. Latest Corporate
Environment Policy should be submitted to SEIAA
within 3 months of issuance of this letter.
The same will be complied with.
xi. The fund ear-marked for environment protection
measures should be kept in separate account and
should not be diverted for other purposes and year
wise expenditure shall be reported to the SEIAA/RO
MoEF GoI under rules prescribed for Environmental
Audit.
The same will be complied with.
xii. The project proponent shall ensure the compliance of
Forest Department, Haryana Notification no. S.O.
121/PA2/1900/S.4/97 dated 28.11.1997.
The same will be complied with.
xiii. The project proponent shall ensure that no vehicle
during construction/operation phase enter the project
premises without valid “Pollution Under Control”
Certificate from competent authority.
The same will be complied with.
PUC certified vehicles are being
used during construction phase of
the project. Copies of PUC
Certificates are enclosed as
Annexure XVI.
xiv. The project proponent is responsible for compliance
of all conditions in Environmental Clearance letter
and project proponent can not absolve himself/
herself of the responsibility by shifting it to
The project proponent is responsible
for compliance of all conditions in
Environmental Clearance letter.
Project : Greenopolis
Promoter : Orris Infrastructure Pvt. Ltd.
Compliance Report of the conditions laid in the
Environmental Clearance: up to May’2015
EIA Coordinator
P a g e | 43
For Orris Infrastructure Pvt. Ltd.
(Authorized Signatory)
contractor engaged by project proponent.
xv. The project proponent shall seek fresh Environmental
Clearance if at any stage there is change in the
planning of the proposed project.
The same will be followed.
For Orris Infrastructure Private Limited
(Authorized Signatory)
***********