    The ra in b o w suiteThe 1999 FIDIC suite

    This is a series of articles being published in CES1 with the post 1999 editions of theFIDIC suite of contracts being the overall subject matter.

    Following an introduction to FIDIC and its 1999 suite of contracts the joint authors,Paul Battrick 2 and Phil Duggan 3 of Driver 4 will discuss many practical issues of using FIDICcontracts. Their thoughts and opinions are based upon actual working experiences ofworking with many FIDIC contracts both past and present.

    Paul Battrick Managing Director (International)FRICS MCIArb CEDR AccreditedMediator

    Phil Duggan Director (International)BSc MSc MCIArb

    A Brief History

    FIDIC is the French acronym for theInternational Federation of ConsultingEngineers. It was formed in 1913 by threenational associations of consultingengineers. From its base in Geneva it nowhas members from some 86 memberassociations worldwide.

    Whilst best known for drafting contractsbetween an Employer and a Contractor,FIDIC also drafts model agreements forprofessional services:

    Client and Consultant

    Client and Architect

    Joint Ventures between Consultants

    Sub-consultant Agreement

    Representatives Agreement

    Indeed FIDIC provides many otherpublications and is involved in manyinitiatives in an attempt to fulfil its statedmission; To improv e the business climateand promote the interests of consultingengineering firms globally and locally,

    consistent with the responsibility to providequality services for the benefit of societyand the environment. FIDIC s vision is tobe the industries recognised global voice.

    FIDIC s Employer / Contractor contracts,first issued in 1957, have a distinctly Britishfeel to them. These early contracts werework style based such that the Red Bookwas relative to civil engineering works; theYellow book was relative to electrical andmechanical works with erection at site;and the Orange Book was relative toturnkey or design and build projects.

    The Red Book first issued in 1957, and

    having four major revisions, was borrowedmuch from the ICE forms of contract whilstthe Yellow book leant upon the forms ofcontract drafted by the IMechE / IElecE.

    The Orange book was published in 1995due to a growing trend towards designand build projects and at that time FIDICrecognised that the world of contractdrafting was moving on, indeed theOrange Book contained DisputeAdjudication Board (DAB) provisions; the

    Red Book had, in 1996, a DAB supplementpublished by FIDIC.

    The drafting committee of mostlyconsulting engineers and its many advisorsbegan to work and in 1999 the FIDIC 1999suite of contracts were born.

    The FIDIC 1999 Suite of Contracts

    At this juncture it is worth noting that theFIDIC 1999 contracts are not a revision of

    previous forms; hence First Edition withintheir titles.

  • 8/13/2019 FIDIC Rainbow Suite 2012

    2/44

    Sponsored by perhaps a desire to createthe dominant forms of contract relative toall forms of construction project coupledwith the changing face of construction acomplete overhaul took place.The most fundamental change to the newcontracts being the abandonment of thework based contract; it being replaced bycontracts that recognised which party wasto be responsible for the design of theWorks (or the vast majority of the Works)and where risk would be allocated.

    FIDIC issued three contracts for majorworks and one for minor works. It is thethree major work contracts that havebecome synonymous with the term FIDICContract. Those being:

    The Red Book = Conditions ofContract for Construction for Buildingand Engineering Works Design bythe Employer, also known as theConstruction Contract

    The Yellow Book = Conditions ofContract for Plant and Design Buildfor Electrical and Mechanical Plant,and for Building and EngineeringWorks Designed by the Contractor,also known as the Plant and Design-Build Contract

    The Silver Book = Conditions ofContract for EPC/Turnkey Projects,also known as the EPC/TurnkeyContract

    The fourth contract to be issued was theShort Form of Contract to be known asthe Green Book.

    To avoid any confusion it may have beenbetter to avoid the repeated use of RedBook and Yellow Book and adopt atotally new range of colours from theoutset since many contracts are still letbased upon pre-1999 FIDIC contracts.

    In 2001 FIDIC published a Contracts Guideto the three major forms of contract; it has

    become known as the Rainbow Book andFIDIC has perpetuated the rainbow themeby encouraging all of its subsequentlyissued contracts to be known by thecolour of their covers.

    The New Red, Yellow and Silver Books

    As previously noted a fundamentalchange adopted by FIDIC when draftingthese contracts was to move away from awork style to a contract that reflectedwhere the responsibility for design wouldbe allocated.

    These contracts were also intended to beused both on the international market anddomestic markets, although it is suspectedthat the vast majority of sales of thevarious forms relate to projects where thenationalities of the contracting partiesdiffer.

    FIDIC not only sought to issue a new suiteof contracts but also, and to its credit,sought to make the contracts user friendlyand create a best practice manual forcontract administration. The latter being atopic for a subsequent article.

    To aid all users the task group drafting thecontracts were instructed to standardisethe three new major forms. The resultsbeing that, unless differences wereessential, definitions, layout, clausenumbering, and clause wording wereidentical.

    Accordingly the Red, Yellow and SilverBooks contain only twenty clauses; the lastedition of the old Red Book containedseventy two clauses whilst the old YellowBook fifty one clauses.

    An example of standardisation being,whereas in the old Red Book clause 67 washeaded Dispute, Engineer s Decisionsand in the old Yellow Book clause 50 washeaded Disputes and Arbitration the1999 suite of contracts, at clause 20,

    prescribe the conditions under which theContractor, the Engineer and the

  • 8/13/2019 FIDIC Rainbow Suite 2012

    3/44

    Employer should act through the Claims,Disputes and Arbitration procedure.

    First impressions of the 1999 suite maybe offputting since the purchased documentappears to be much larger than previouseditions, for instance the new Yellow Bookhas, in total, over 100 pages whereas theold Yellow Book has less than 50 pages.This is all part of the F IDIC s desire toproduce a document that is easier to usethan previous FIDIC contracts and alsoother contracts from which Employers andEngineers can choose.

    The general layout of the Contracts is asfollows:

    General Conditions; including anAppendix entitled GeneralConditions of Dispute AdjudicationAgreement which includes theProcedural Rule for a DAB

    A section giving guidance for thepreparation of any ParticularConditions; this section also includesexamples of guarantees, securitiesand bonds that are commonplaceon international projects

    A section entitled Forms; here FIDICprovide examples of:

    Letter of Tender with supportingAppendix to Tender

    Contract Agreement DAB Agreements (either a one-

    person DAB or three person

    DAB)

    Whilst the above can be considered to bethe most important elements within aContract, FIDIC have continued to behelpful to those using its contracts. Withinthe very useful Forward to the Contractthere are three graphics indicatingtimelines relative to:

    1. Principle events from invitation totender to return of the PerformanceSecurity

    2. Payment procedures under clause14 Contract Price and Payment

    3. The sequence of events underclause 20 Claims, Disputes andArbitration following either Partygiving notice of its intention to refer adispute to a DAB

    All in all a very complete document thatshould require few amendments however,as we shall see in a later article thedocument is not only used but is abused.

    The Engineer

    Before noting some specifics regarding theRed, Yellow and Silver Books it is worthnoting that FIDIC have amended the roleof the Engineer in the Red and YellowBooks (the Silver Book has an Employer sRepresentative) from the impartial, quasiarbitral role of previous editions. TheEngineer is clearly stated to act for theEmployer. He is no longer required to beimpartial but whenever required to makea determination in respect of value, costor time related matter he has to make hisdetermination fairly, and in accordancewith the Contract, having taken intoconsideration all relevant circumstances.

    The FIDIC 1999 First Edition Red Book

    The main features of this Contract can besummarised as: It is suitable for all types of project

    where the main responsibility fordesign lies with the Employer (or itsEngineer) although provision is madefor the Contractor to designelements of the Works

    The administration of the Contractand approval of work is carried outby the Engineer as is certification ofpayments and determination ofextensions of time

    Payment to the Contractor is based

    upon work done and rates as per aBill of Quantities (a Standard Method

  • 8/13/2019 FIDIC Rainbow Suite 2012

    4/44

    of Measurement should be stated);thus reflecting the likely on sitenature of the Works (a reflection thatthe Red Book will most likely be usedfor building and civil engineeringprojects)

    Risk sharing is balanced betweenParties such as the Employer takingthe risks of adverse physicalconditions and the operation ofthe forces of nature that areconsidered to be unforeseeable

    Claims by both Parties have to followprocedures, albeit the conditionsimposed upon the Contractor areharsher with the inclusion of a fatalnotice provision

    The Contractor has some financialprotection in that it can requestevidence from the Employer that ithas the finances to pay theestimated Contract Price

    Materials can be paid for both onand off site if strict criteria arefollowed, including the listing ofmaterials for which payment maybesought within the Contractor stender

    The FIDIC 1999 First Edition Yellow Book

    The main features of this Contract can besummarised as:

    It is suitable for all projects where themain responsibility for design lies withthe Contractor based upon theEmployer s Requirements althoughprovision is made for the Employer(or his Engineer) to design elementsof the Works

    The administration of the Contractand approval of work is carried outby the Engineer as is certification ofpayments and determination ofextensions of time

    Payment to the Contractor is basedupon a Lump Sum price andnormally against a schedule ofmilestones to be achieved by theContractor. This reflects that theYellow Book will most likely be usedfor process plants and the like wherea high degree of offsitemanufacture of plant andequipment is foreseen and paymentterms can be drafted to recognisethis situation subject to the listing ofsuch plant and equipment within theContractor s tender as within theRed Book

    Testing procedures leading tocompletion are likely to be morecomplicated than within the RedBook, again reflecting the likelynature of the project

    The Yellow Book shares with the RedBook the provisions noted aboverelative to:

    Risk sharing Claims by both Parties . Financial protection for the

    Contractor

    The FIDIC 1999 First Edition Silver Book

    The Red and Yellow Books are said toprovide contracts with a balanced view ofrisk sharing meaning:

    The Employer pays the Contractoronly when specific risks occur

    The Contractor does not have toinclude within its tender for risks thatare difficult to value

    The above means that the Employer has agreat degree of uncertainty in respect ofthe final price and the final time forcompletion.The Silver Book reflects a market desire forcertainty of cost and time; perhaps by aone off Employer or a totally risk adverseEmployer willing to pay the price or

  • 8/13/2019 FIDIC Rainbow Suite 2012

    5/44

    potentially by lenders who crave certaintyof price and time, such that the riskallocation is far from balanced.

    The Contractor is asked to allow within itstender for a wide range of risks relative tocost and time; such risks will most likelyinclude all ground conditions (potentiallyin a country of which the Contractor willhave little knowledge) and the completionof the Works will be based upon a strictbut often brief performance relatedspecification.

    The Employer will still bear some risks suchas those related to war, terrorism andForce Majeure but the unbalanced riskprofile of this Contract will undoubtedly bea higher price; a factor that Employer smust accept.

    The main features of the Silver Book canbe summarised as:

    Design liability rests solely with theContractor, the Employer willprovide its requirements but theseare often in the form of a briefperformance specification

    The Contractor carries out allengineering, procurement andconstruction often includingperformance tests after completion;a turn -key project allowingoperation of the facility uponcompletion

    There is not an Engineer within the

    Contract; the Employer may appointan Employer s Representative

    It is lump sum Contract withpayment terms most likely similar tothose envisaged under the YellowBook

    Given the above circumstances underwhich an Employer may select a SilverBook, Employer s should recognise thesignificant costs for a Contractor to

    produce a tender. Accordingly it is hopedthat Employer s recognise this and select

    only a small number of Contractors totender.

    Similarly Employers have chosen a turnkeystyle of contract and therefore shouldallow the Contractor complete freedomto carry out the Works in its chosen mannerin order to reach any performance criterialaid down by the Employer.

    If the Employer cannot grasp such factors,or the tender time is too short to allow theContractor to compile an adequatetender, or considerable amounts of work

    are underground, or difficult to inspect theEmployer may be better off using a Yellowbook, accepting some additional risks andreceiving a lower tender price.

    The FIDIC 1999 First Edition Green Book

    The final contract to be issued in 1999 wasthe Green Book or Short Form of Contract.This Contract recognised a need for amuch simpler and shorter contract to suitprojects with a relatively low ContractPrice and short time duration.

    The Contract itself is very flexible, anyreader will however recognise theContract as being from the same familyalbeit it has only fifteen clauses and a totalof ten pages.

    The clauses are short and easilyunderstood; whilst design can be carriedout by either party an Engineer is notforeseen, however the Employer mayappoint a Representative. Payment canbe made on either a lump sum orremeasured basis.

    As with the major forms the Contractincludes guidance notes (noted as notforming part of the Contract) as well as anAgreement together with its Appendix andRules for Adjudication. The noticeableabsentee being the Particular Conditionssection; in this respect FIDIC consider thatthe Green Book can work without suchconditions however, a cautionary note is

    provided should an Employer deem itnecessary to amend the drafted Contract.

  • 8/13/2019 FIDIC Rainbow Suite 2012

    6/44

  • 8/13/2019 FIDIC Rainbow Suite 2012

    7/44

    Introduction

    First a brief introduction followed by anoverview of various forms.

    The White Book

    As previously noted FIDIC also drafts, aswell as contracts between an employerand contractor, many agreementsbetween client and consultant. TheClient / Consultant Model ServicesAgreement, now in its fourth edition,issued in 2006, it has become known as theWhite Book.

    The Blue Book (or Turquoise Book as itis sometimes called)

    This form is designed specifically for use inconnection with dredging andreclamation projects. It differs from themajor forms in many ways but perhapsmost importantly that it was drafted inclose collaboration with the InternationalAssociation of Dredging Companies(IADC) and as such has a great input fromcontractors from the outset. The currentversion of the Form of Contract forDredging and Reclamation Works is the

    fourth edition issued in 2006.

    The Pink BookWhilst funding agencies adopted theversions of old and new Red Books formany years it became standard practiceto amend certain clauses. In response to

    the Multilateral Development Banks(MDBs) desire to harmonise their biddocuments including a standard form ofcontract, FIDIC responded by issuing theConditions of Contract for ConstructionMDB Harmonised Edition; the latest versionbeing issued in 2010.

    The Gold Book

    This form of contract is probably the mostradical of the new colours; it represents acontract period of over 20 years! It is adesign, build and operate (DBO) contractthat the industry has needed for sometime to reflect the ever growing trend thatcontractors no longer construct somethingthen go away but also maintain andoperate the facility for many years tocome. It has been described as a YellowBook with an operate and maintenancecontract bolted on; the First Edition of theConditions of Contract for Design, Buildand Operate Projects was issued in 2008.

    No colour as yet, but a subcontract

    FIDIC has often issued a new form ofcontract as a test edition such that theconstruction industry can review theproposed conditions of contract whilstperhaps using them in a real life situation.The latest test edition again is a departurefrom the engineer driven FIDICorganisation since it delves into the worldof the contractor and subcontractor,although it is noted that advice was

  • 8/13/2019 FIDIC Rainbow Suite 2012

    8/44

    sought from many working for and withcontracting organisations.

    The results being the Conditions ofSubcontract for Construction for Buildingand Engineering Works designed by theEmployer issued in 2009. As the title of thisform suggests it is for use with the Red Bookand the Pink Book. It is the secondattempt at creating a subcontract sinceFIDIC issued one in 1994 relative to the oldRed Book

    Overview of the various forms

    The White Book

    The drafters of the White Book arepredominately engineers who within thisform sought to create conditions ofagreement that would span the life cycleof an engineer s or consultant sinvolvement.

    Accordingly the document is suitable foruse during:

    pre-investment and feasibility studies

    the design phase

    the administration of a contract

    As with FIDIC contracts there are bothgeneral and particular conditions ofcontract which combined set out thescope of the consultant s work, paymentterms and the like.

    The White Book incorporates the samefinancial protection as afforded tocontractors in that the consultant too canask the Client (as opposed to theEmployer) if it has the ability to pay theConsultant s fees. In a similar vein, andmaybe not surprising to some, the WhiteBook limits the consultant s responsibilities,and therefore liabilities, to exercisereasonable skill, care and allegiance in theperformance of his obligations under the

    Agreement. This limitation is furtherqualified since nothing else in theagreement, or any legal requirement ofthe Country or any other jurisdiction canimpose a greater risk upon the consultant.Thus the consultant/engineer has a limitedrisk that, it is suggested, is not in accordwith the thoughts of employers andcontractors alike.

    The Blue (Turquoise) Book

    The Blue Book is like the Green Book in thatit is abbreviated and flexible. In terms ofbeing a smaller document the generalconditions are only 16 pages and fifteenclauses long. The format has alsochanged from the major forms with theagreement and appendix to the contractbeing the first section. Perhaps it is themajor forms that have the order incorrectsince it is those particular terms that arethe most important to recognise especiallyin such a flexible form as the Blue Book.

    Similarities with the major forms are in theinclusion of standard forms, such assecurities, a section on adjudication (aone or three person DAB) with rules andthe adjudicator s agreement and the allimportant guidance section.

    The engineer is still recognised within thecontract however design responsibility canrest with either the employer (and itsengineer) or the contractor. Paymentterms are extremely flexible and a list ofoptions, such as lump sum,

    remeasurement and cost plus are allnoted within the appendix.

    It is perhaps apparent that a greater inputo f a contractor s organisation hasinfluenced some of the general conditions,as has perhaps the use of other formswithin the industry as a whole:

    Notices by the contractor in respectof a claim must be given within 28days but there is no fatal provision.

  • 8/13/2019 FIDIC Rainbow Suite 2012

    9/44

    Claim items are listed as defined riskswhich may entitle the contractor tomonetary or time compensation.

    The defined risks, recognising the likelyimpacts of weather upon thecontractor s ability to make progress,potentially soften the usual clausewording on one hand, entitling thecontractor to make a claim if anyoperation of the forces of natureaffecting the Site/and or the Works,which was unforeseeable or againstwhich an experienced contractor

    could not reasonably have beenexpected to ta ke precautions butgive the employer (and contractor)less room for debate by also definingthe employer s risk to be climaticconditions more adverse than thosespecified in the Appendix.

    If disputes are not settled amicablythey are to be settled by referral toadjudication by a DAB and, ifdissatisfied with the DAB s decision (orif no decision is made within the settimescale) the dispute can bereferred to Arbitration.

    The Blue Book is a model of a contractdrafted by those with a particular sectionof the industry in mind and with theknowledge to incorporate the necessaryvariations to standard forms that mayhave been considered for use in the past.

    The Pink Book

    As previously noted the Pink Book wascreated as a derivative of the Red Book.This reflecting the usual nature of a projectthat would require funding from lending oraid agencies and would deploy from theoutset an engineer to assist in all phases ofthe project, especially design.

    Those projects normally beinginfrastructure types of projects as opposedto industrial, power, process plants and thelike where funds would normally be fromthe employer s o wn resources and the

    contractor would design the facility; inother words a Yellow or Silver Book project.

    The MDBs include in their number suchorganisations as:

    The World Bank

    The European Bank for Reconstructionand Development

    African Development Bank

    The MDBs in fact represent lendingagencies that fund projects on a globalbasis and as such play a crucial role in thedev elopment of the planet s lastinginfrastructure. With this level ofimportance in mind it was crucial thatFIDIC participated in amending the RedBook to provide a contract not only thatadhered to the wishes of the MDBs butalso gave borrowers, engineers andcontractors some consistency in format,leading to fewer ad-hoc and poorlythought through amendments.

    Those faced with a Pink Book will haveoften been used to the Red Book andtherefore will be familiar with the generallayout of the contract, the twenty clausesare still there but there have beenamendments which some may think arefor the better, and others otherwise.Examples being when compared to theRed Book:

    Minor amendments have taken place

    to definitions of which one is worthy ofbeing noted:

    Cost no longer refers toreasonable profit but statesprofit since at clause 1.2 profit isfixed at 5% unless statedotherwise in the contract data.

    clause 1.5, is a new clause that allowsthe lender s representati ves to inspectthe site and audit the contractor s

    accounts and records relative to theproject

  • 8/13/2019 FIDIC Rainbow Suite 2012

    10/44

    clause 2.1, access to the site must be

    given such that the programme canproceed without disruption

    clause 2.4, the employer has todemonstrate its ability to pay thecontract price before thecommencement date and alsopunctual ly

    clause 2.5, the employer must nowgive notice of its claims within 28 daysbut whilst more onerous there is still nocondition precedent

    clause 3.1, the engineer has to gainthe employer s approval beforedealing with matters under clausesdealing with claims in respect ofunforeseeable physical conditionsand the issue of variations

    clause 3.5, the engineer now has togive its determination within 28 daysfrom receipt of the corresponding

    claim or request

    clause 6.2, there is an obligation uponthe contractor to inform its personnelof their liability to pay local incometax

    clause 8.1, the project cannotcommence unless:

    the contract agreement hasbeen signed by both parties

    the contractor has reasonableproof that funding is in place

    the advance payment hasbeen received by thecontractor

    clause 8.6, the contractor can bepaid for acceleration measures toovercome employer delays

    clause 13.1, the contractor is not

    bound to carry out a variation if itwould trigger a substantial change in

    the sequence or progress of theworks.

    clause 15.5, whilst the employer canterminate for convenience it cannotterminate to pre-empt a justtermination by the contractor.

    clause 15.6, is a new clause thatattempts to deal with corrupt and/orfraudulent practices.

    clause 16.2, the contractor must nowdemonstrate that the employer sfailures must materially and adverselyaffect the economic balance of thecontract and/or the ability of thecontractor to perform the contractprior to termination. There arehowever two further grounds allowingthe contractor to terminate:

    Failure of the funder to providefunds.

    The absence of the engineer sinstruction to commence work

    180 days after the letter ofacceptance.

    clause 19.2, in order to claim forcemajeure the claiming party mustdemonstrate that it has beenprevented from performing itssubstantial obligations

    clause 20.6, arbitration rules may differaccording to the origin of the lendingagency.

    The amendments to the Red Book appearto be a mixed bag providing support tothe contractor in terms of guaranteedfunding but also apparently allowing theemployer influence over the engineer inrespect of claims for unforeseeableground condition and variations.

    The latter is not considered to be prudentespecially when considering thatborrowing countries may not have thesophistication necessary to deal with suchmatters.

  • 8/13/2019 FIDIC Rainbow Suite 2012

    11/44

    The Gold Book

    The Gold Book without doubt fills one ofthe last gaps in FIDIC s toolbox ofcontracts. Its use is growing especially asgovernment departments such as waterauthorities warm to the idea of havingforeign contractors bring their knowledgeof providing water treatment and supplyat a profit but also having to beresponsible for remedying defects whilstremaining in the country rather than beingon the side of the globe.

    Accordingly FIDIC has not only respondedto employers who crave to outsource butalso the changing face of contractorswho are now operators too. Any potentialdisputes between contractors carrying outa design and build contract toquestionable standards leading to poorperformance, defects and disputes whilstleaving the employer to struggle through a20 year life time of a plant have,potentially, been negated. That is,provided the whole scheme is fully thought

    through and both parties, as with allcontracts, are willing and able to actresponsibly towards each other such thata balance is struck between theconstruction and operating elements ofthe contract.

    The contract s ethos and key features are:

    Design, build plus operation andmaintenance for 20 years by thecontractor on a green field site.

    Design and build phase risk allocationsimilar to the Yellow Book withexacting completion criteria but alsoa cut off date should the contractorbe 182 days late leading totermination if desired.

    Payment on a lump sum basis but adefined asset replacement fund andschedule that notes the timing andcost of the replacement of certainassets. Costs of replacing plant andequipment outside of the schedule

    will be the responsibility of thecontractor, as is a cost over thatstated on the schedule. Any surplus inthe fund at the end of the twentyyears is divided equally.

    The employer is entitled to deduct 5%from payments during the operationservice period (OPS ) in case thecontractor does not fulfil itsmaintenance obligations. The fund isto be released, if not spent, within thefinal payment to the contractor. Thecontractor being responsible for its

    own defects arising from design andconstruction in this period.

    An independent audit body is jointlyappointed for the duration of the OPSto monitor the performance of thecontractor and employer. Whilsthaving no power, the parties areintended to give due regard tomatters raised by the audit body.

    A joint inspection is required at leasttwo years before the end of the OPS;

    any works identified must be carriedout by the contractor who will alsoface completion tests similar to thoseat the end of the design and buildphase. Defaulting contractors risklosing the 5% maintenance retentionfund.

    A standing DAB is established from aset date for the design and buildphase and a new one every 5 yearsduring the OPS.

    The key to success appears to be with thecontractor who must design and build aquality plant with low operating andmaintenance costs; fit for purpose andbuilt to last.

    However, like any relationship time givesrise to change and only time will tell ifFIDIC have considered all factors such aschanges in the deliverables required bythe employer. FIDIC has very recentlyissued its guide to this form.

  • 8/13/2019 FIDIC Rainbow Suite 2012

    12/44

    The Subcontract to the Red and PinkBooks

    As noted this form is a test edition with thefirst edition arriving sometime later.

    The contract seeks to be back to backwith the Red Book, in this respect selectedhighlights or lowlights are:

    The subcontractor is required tocomplete its scope of works such thatno act or omission shall constitute orcause a breach under the Red Book.

    The contractor is entitled to make afair decision in respect of its claimstowards the subcontractor anddeduct monies accordingly.

    Payments are back to back (wherelegal to do so) such thatsubcontractors may find contractorsusing this as a shield to avoid payingfor their own problems

    The subcontractor is apparentlyresponsible for the care of its worksuntil the main contract works aretaken over. This situation will alwaysrequire careful managementwhatever the form of contract

    Notice provisions are passed throughto the subcontractor but with areduction in time to 21 days to allowthe contractor to fulfil its obligationsunder the main contract.

    A subcontract that allows both fairpayment provisions for the subcontractorfor all liabilities of the contractor whilstobliging the subcontractor to allow thecontractor to make claims upwards willalways be a tough ask; has FIDIC really gotit right? Perhaps the absence ofsubcontractors from the draftingcommittee is a clue.

    A final thought

    FIDIC has continued to broaden itspotential customer base by these furthercontracts. The next stop could be a targetprice contract but it is understood that wewill see a complete overhaul of the 1999suite in the not too distant future.

  • 8/13/2019 FIDIC Rainbow Suite 2012

    13/44

    This is the third in a series of articles being published in CES1. The first introduced the rainbowsuite, the second provided insight into the continued growth of the suite.

    In this the third article by joint authors, Paul Battrick 2 and Phil Duggan 3 of Driver 4, commentingupon the FIDIC forms of contract the programming requirements are considered inconjunction with the procedures in respect of progress reporting. The Parties to the Contractand the Engineer, but in particular the Contractor, all have clear obligations in respect of theprogramming and reporting functions within the FIDIC forms.

    Programming and ReportingA Benefit or Burden for the Contractorand the Employer and its Engineer?

    In this the third article commenting uponthe FIDIC forms of contract theprogramming requirements areconsidered in conjunction with theprocedures in respect of progressreporting. The Parties to the Contract andthe Engineer, but in particular theContractor, all have clear obligations inrespect of the programming and reportingfunctions within the FIDIC forms.

    It is considered that these obligations areintended to be considered in tandem withthe provisions for considering claimssubmitted by the Contractor such that anyContractor who neglects, or is allowed toneglect, its obligations may face a moredifficult task to establish its entitlementsthan a Contractor who has fully compliedwith its obligations.

    For the purposes of this article allreferences to Sub-Clause are taken from

    the Yellow Book; in simple terms theContract for design and build projects

    where the design is carried out by theContractor.

    The drafters of the FIDIC suite of contracts,and many commentators, say that theFIDIC contracts not only provide themechanisms for dealing with risks,responsibilities, payment terms, changeand all the other good things necessary toallow a project to be completed in amanaged and (hopefully) equitablefashion but they also act as a bestpractice project management handbook.

    The project management handbook is

    most prevalent within the programmingand reporting provisions and no doubt theFIDIC drafters consider what they thoughtthe Contractor and the Engineer shouldbe aware of in order that control of theproject was to the fore and certainty ofoutcome, especially in respect of progress,was assured.

    Many of us, and perhaps some FIDICdrafters, will have received lectures inmanagement at some stage of our

    careers and many will know themnemonic.

    Family Planning O ften Means C arefulC hoice of C ontraceptives

    Management handbooks quite rightly lookto the perfect world however the realworld is one of harsh commercial realitiesand shortcomings in performance in manyrespects where, should a Contractor allowwithin its bid for every risk and obligation it

    would certainly lead to lost tenders. Aswith all things compromise is often the

  • 8/13/2019 FIDIC Rainbow Suite 2012

    14/44

    solution however, to compromise inrespect of programming and reportingmay not be such a wise course of action.

    The FIDIC Yellow Book envisages thetypical procedure to be expected inestablishing a contract for a design andbuild project:

    Invitation to bid (ITB) withEmployer s Requirement included,no doubt a timescale for thecompletion of the project wasstated.

    Contractor s bid complying orotherwise with the ITB, including atimescale which was probablydetailed to some degree notingany required milestones and/orthose of importance to theContractor, such as the provision offeedstocks .

    The coming together of theEmployer and the Contractor to

    create a contract detailing withoutambiguity a shared understanding.

    It is now that Clause 8, Commencement,Delays and Suspension takes over, and forthe purpose of this article Sub-Clause 8.3Programme in particular.

    The Contractor, will have agreed oraccepted the Time for Completion notedwithin the Appendix to Tender and theEngineer will have issued a notice of the

    Commencement Date. Assuming all otherformalities are in place, such as theprovision of the Performance Security, thedates for commencement andcompletion of the Works, including anySections, are now anchored.

    Sub-Clause 8.3 Programming

    Now Sub-Clause 8.3 takes over!

    It is suggested that all programmes inexistence at this point in time should be

    cast to one side as from now on only oneprogramme will matter; the Sub-Clause 8.3programme and of course the revisions toit.

    This programme will be, or should be, abaseline against which the performanceof the Contractor and the Employer, ifappropriate, will be monitored, claims forextensions of Time for Completion will bebased upon and Engineer s instructions toexpedite progress will be based. Itsimportance cannot be stressed enough.

    However, the requirements upon theContractor of Sub-Clause 8.3 goes furtherthan producing a programme; theContractor is required, for the first time tobear its soul before the Engineer forscrutiny. Whilst the details to accompanythe programme may seem quite normal tomost they are an obligation upon theContractor.

    The Contractor has to submit, to theEngineer, its detailed programme within 28

    days after receiving the notice of theCommencement Date. Realising that theprogramme will not be perfect and will besubject to revision not only to takeaccount of actual progress but also totake account of other factors such as sub-suppliers and sub-Contractorsprogrammes being agreed as orders andcontracts are placed, the FIDIC draftersplaced a further obligation upon theContractor to submit a revisedprogramme whenever the previous

    programme becomes, in effect, out ofdate and does not reflect the manner inwhich the Contractor will achieve itsobligations.

    Every time the Contractor submits arevised programme it must include:

    the order in which the Works will becarried out

    the timing of each stage of design,

    preparation of Contractor sDocuments, procurement,

  • 8/13/2019 FIDIC Rainbow Suite 2012

    15/44

    manufacture, inspection, deliveryto site, construction, erection,testing, commissioning and trialoperation

    the periods allowed for theEngineer to review documentssubmitted by the Contractor (Sub-Clause 5.2) and any similarsubmissions, approvals andconsents specified in theEmployer s Requirements

    the sequence and timing ofinspections and tests specified inthe contract

    a supporting report which includes:

    a method statement notingthe major stages ofexecution of the Works

    the Contractor sreasonable estimate of thenumbers of each class of

    Contractor s Personnel andeach type of Contractor sEquipment required at Sitefor each major stage of theWorks

    Having received all of this information atthe outset of the project and every timethe programme is updated the Engineerhas 21 days in which to state, by a issuingnotice, that it does not comply with thecontract; note that the Engineer does not

    have to approve programme should theEngineer not issue such a notice theContractor must proceed in accordancewith the programme; in doing so theContractor should be aware that theEmployer will rely upon that programme inarranging any feedstocks and other inputsit has to facilitate the completion of theWorks.

    FIDIC is silent as to what should happen ifthe Engineer gives notice that the

    programme does not comply with thecontract; as to what non -compliance

    with the contract actually means maybeleft to the Engineer s interpretation. It isconsidered that it should meancompliance with dates and periods oftime stated within the contract includingworking hours and periods for approvalsetc by the Engineer but should aninvestigation take place into the level ofresources and methods the Contractorintends to use, probably not. Neverthelessthe Contractor has provided to theEngineer an insight into such things as itsintended resources which, as we all know,is also often the starting point for many aclaim prepared by a Contractor.

    As noted the Sub-Clause 8.3 programme isthe baseline against which the Engineerwill monitor the Contractor s progress andthe Contractor s ability to meet the Timefor Completion and decide whether or notto issue instructions to the Contractor toprepare and issue a revised programmeand supporting report detailing how theContractor will accelerate the Works, as itsown cost and potentially with claims from

    the Employer to complete with the Timefor Completion.

    There is one other obligation of Sub-Clause8.3 that is worth nothing; the Contractor isto inform the Engineer of:

    specific future events orcircumstances which may diverselyaffect the work (note the Works isnot used)

    increase the Contract Price

    delay the execution of the Works

    It is also worth noting that the Employerdoes not have a similar obligation.

    The Contractor has to submit estimatesrelative to these occurrences and/or aproposal under the Variation Procedure ifapplicable.

  • 8/13/2019 FIDIC Rainbow Suite 2012

    16/44

    Early warning clauses such as this are nowcommonplace and there is no notedsanction for non-compliance by theContractor however, Contractors shouldconsider this provision in the light of thefatal notice provisions under Sub-Clause20.1 (a topic for later discussion).

    Sub-Clause 4.21 Progress Reports

    Having given the Engineer an insight intoits initial and revised programmes andresourcing levels the Contractor is obligedto prepare reports, on a monthly basis,that reveal yet more of the Contractor sprogress towards Completion.

    The monthly reports can be quite a timeconsuming exercise to complete sincethey require a considerable amount ofdetail, let alone six copies to be issued.Each report must include:

    charts and detailed descriptions ofprogress including:

    each stage of design(possibly relevant to themajor stages identifiedwithin the Sub-Clause 8.3programme)

    Contractor s Documents (adefined term includingcalculations, computerprogrammes, drawings andmodels)

    procurement, manufactureand delivery to site

    erection, commissioningand trial operations

    photographs showing the status ofmanufacture and of progress onthe Site

    for the manufacture of each main

    item of Plant (apparatus,machinery and vehicles to be

    incorporated into the Works) andMaterials (things of all kinds, otherthan Plant) to be incorporated intothe Works)

    the name of themanufacturer

    the manufacturer s location

    percentage progress

    actual or anticipated datesof:

    commencement ofmanufacture

    Contractor sinspections

    Tests

    shipment and arrivalat site

    records of the numbers of theContractor s Personnel (theContractor s staff, Sub -contractorstaff and anyone else working atthe Site)

    records of the Contractor sEquipment (types and details ofplant and vehicles used by theContractor, its Sub-contractors andanyone else working at the Site)

    copies of quality assurancedocuments, test results andcertificates of Materials

    list of Variations, notices given bythe Employer of its intention tomake a claim towards theContractor and notices of claimissued by the Contractor

    safety statistics, including details ofhazardous incidents, activities

    relating to environmental aspectsand public relations

  • 8/13/2019 FIDIC Rainbow Suite 2012

    17/44

    comparisons of actual and

    planned progress

    details of any events orcircumstances that may jeopardisethe Contractor s ability to meet theTime for Completion or any interimmilestones (it is noted that this isanother opportunity for an earlywarning of potential delay by theContractor)

    measures being adopted or to beadopted by the Contractor toovercome delays (it is not certain ifthis relates to recovery measuresbeing adopted as a result of anEngineer s instruction and/ormeasures voluntarily adopted; thelatter is most likely given therequired comparison in respect ofprogress)

    Whilst most Contractors will readily have tohand, whether allowed for in the bids or

    not, the resources and managementstructure to comply with the reportingobligations within Sub-Clause 4.21 it is clearthat those working for the Contractor, Sub-contractors, Sub-suppliers and specialistdesign houses must also provide thecountless pieces of information required toallow the Contractor to conform.

    It is suggested that perhaps Contractorswho are not used to FIDIC, such as thosefrom Eastern Europe, who may find

    themselves working on externally fundedprojects may find these obligations outsideof their normal reporting capabilities.Similarly some Engineer s may also find theadministration of this aspect of FIDICsomewhat difficult to achieve, albeit itgives the Engineer the perfect platform toreport to the Employer.

    Benefit or Burden?

    To consider whether or not theprogramming and reporting obligations

    are a benefit or burden for the Contractor,a simple question must be asked, whatdoes the Contractor (and all other partiesinvolved for that matter) really want froma project?

    After the difficulties of bidding and winninga project the Contract will desire certaintyand to construct with control. That being,amongst other things, certainty of:

    Contribution to overheads andprofit, the lifeblood of any business

    Timely completion, to allow theplanned movement of resourcestowards the next project

    Completion to the required qualitystandards, to enhance reputations

    A dispute free project, to avoid thetime consuming and expensive useof resources

    Whilst far easier to say than to achieve; to

    obtain certainty it requires all involved withthe Employer s, Engineer s andContractor s organised to fulfil theirobligations to the standards required andat the right time.

    The initial Sub-Clause 8.3 programme notonly provides the Engineer with a yardstickto measure projects against but it alsoallows the Contractor to inform theEmployer when critical inputs such as freeissue materials, electricity, gas, water or

    feedstocks are required. It is thereforesomething for the Contractor to measurethe Employer s performance against andevery updated programme and reportshould therefore contain a statementregarding the progress of th e Employer sobligations as well as the requiredinformation regarding the Contractor sprogress. There should be no hindrancefrom either the Employer or the Engineer tothe Contractor taking a proactive stancein relation to a desire to complete the

    Wor ks without delay from the Employer squarter.

  • 8/13/2019 FIDIC Rainbow Suite 2012

    18/44

    It is clear however, that the focus, on theSub-Clause 8.3 programme and itsrevisions is on the Contractor sperformance. Despite this opportunity toset out a clear statement of intent that iscapable of demonstrating cause andeffect in respect of delay to the Time forCompletion all too often Contractor sproduce programmes that areinadequate at the outset, possibly due toa lack of information from suppliers etc,and continue to be inadequate whenrevised.

    A good programme that is properlymaintained is without doubt, a doubleedged sword; it allows the Contractor toidentify its own shortcomings and takeinstant remedial action as well as identifydelay that falls under the risk area of theEmployer such that an extension to theTime for Completion can be instantlyrequested and hopefully determined bythe Engineer such that the risks ofcompletion fall back towards the

    Contractor.

    The reporting requirements within Sub-Clause 4.21 are a great motivator for theContractor to have at its fingertips all thedata to allow time to be properlymonitored and adjusted to suit deviationsfrom any intended programme. In doingso the Contractor can once again feedinto those responsible for preparing theprogramme data indicating the rate ofprogress of all concerned allowing the

    programme to be adjusted to takeaccount of either work being completedearlier than scheduled or likely delays suchthat resources can be deployedeconomically and claims, if appropriatewill have strong foundations based uponfact.

    In a similar fashion the Engineer, byreviewing the available data and earlywarnings given by the Contract, canforesee areas of work where delays are

    likely to occur and take appropriateaction by alerting the Employer, especially

    if the Employer is culpable, but moreimportantly communicating with theContractor to mitigate the impacts ofdelay and issue a Variation if desired andrequired.

    Whilst, with all this data to hand, theContractor should be able to constructwith control and take the appropriateaction when and if delay occurs,Contractors should also neverunderestimate that the data; resourcinglevels, duration of work operations etc etcis also with the Engineer who will use thisagainst any Contractor that submits ahasty and ill-prepared claim for whatcould be a very just entitlement.

    There is doubt that in the minds of theFIDIC drafters that all involved intended tofulfil their obligations to the standardsrequired and in a timeous manner but inthe event that this did not happen anddelay occurred the Engineer and theContractor would have a wealth ofinformation to hand to prepare claims for

    just entitlements that could be determinedwithout question under Clause 20,although that Clause is a topic for anotherday.

    Sadly all concerned have frailties either asindividuals and/or organisations howeverthis should not prevent at least the firmfoundations of good programming frombeing achieved.

    A final thought

    Perhaps the FIDIC drafters did attend thesame lectures as it is not too difficult to seethat with any FIDIC contract there areelements of; Forecasting, Planning,O rganisation, Motivation, C oordination,C ontrol and C ommunication

  • 8/13/2019 FIDIC Rainbow Suite 2012

    19/44

    This is the fourth in a series of articles being published in CES 1 with the post 1999 editions of

    the FIDIC suite of contracts being the overall subject matter.

    The first article discussed the birth of FIDIC s rainbow suite, the second provided a brief insight

    into continued growth of the rainbow, the third article looked at programming and reporting

    requirements. In this, the latest article, joint authors Paul Battrick 2 and Phil Duggan 3 of

    Driver 4 look at studying project contracts themselves.

    It is easy to tell all involved with the

    management of any construction project toread and fully understand the Contract. No

    matter how experienced we are there is

    always the potential for an amendment to

    a previous form, a new revision or an

    Employer removing some well understood

    elements that may fundamentally alter any

    previous understanding.

    Please do not adopt the attitude of Ive

    seen that form before or we always do it

    like this as one particular client did to i ts

    detriment. Whilst not involving a FIDIC

    Contract the story highlights a totally

    incorrect attitude to adopt; in short:

    A specialist Contractor asked forassistance, the pressure vessel it

    had spent 1000s of hours

    manufacturing in Europe had been

    rejected at site in the Far East.

    It had been rejected as it was

    constructed using steel and not

    stainless steel as required by the

    specification.

    When asked why an alternative

    material was used the reply was

    we always make these vessels

    from steel.

    The specialist Contractor was forced

    to make a new vessel constructed

    out of the specified material

    resulting in losses and delay

    damages being levied a true story.

    All this could have been avoided had

    someone considered the pertinent

    documentation.

    A clause that is within most contracts that

    is similarly misunderstood relates to Force

    Majeure. Perceived lists of relevant eventsare carried from one project to another

    without considering if the events change; if

  • 8/13/2019 FIDIC Rainbow Suite 2012

    20/44

    the list is exhaustive, since the word

    include is often within the clause or if the

    events carry monetary entitlements as well

    as time benefits.

    Definitions can vary from contract type to

    contract type and, in practical terms, from

    work scope to work scope. Consider for

    yourselves suitable definitions relative to

    remeasurable and lump sum contracts and

    also completion requirements for a road as

    opposed to a multi phased power plant.

    FIDIC conveniently provides definitions

    firstly in the body of the Contract in

    respect of topics:

    The Contract Parties and Persons

    Dates, Tests, Period and Completion Money and Payments Works and Goods Other Definitions

    and also in alphabetical order noting the

    particular Sub-Clause.

    For the purpose of this article onedefinition is selected, that of Cost. It often

    has differing meanings under various forms

    of Contract, especially bespoke forms, and

    is often translated when claims are being

    prepared to what those preparing the claim

    would like it to mean.

    In earlier additions of standard forms,including FIDIC forms, whether or not the

    Contractor was entitled to add profit to its

    cost claims remained silent. Now in the

    FIDIC forms Cost expressly excludes profit

    but profit is still an entitlement under

    certain circumstances as will be explained.

    FIDIC defines Costs as:

    Cost means all

    expenditure reasonably

    incurred or to be incurred),

    whether on or off the Site,

    including overhead and

    similar charges, but does not

    include profit.

    All those dealing with entitlement (a

    preferable word to claim) understand that

    success depends upon the creation and

    maintenance of the appropriate records

    and in doing so can fulfil the requirements

    of FIDIC in both submitting claim

    documents and adjudicating upon those

    documents. The definition of Cost provides

    a starting point in respect of monetary

    entitlements and clause 20 (Claims,

    Disputes and Arbitration) provides the end

    point; in between there are many clauseswithin FIDIC which give rise to a monetary,

    and often time, entitlements to the

    Contractor.

    It pays to understand all of these clauses

    which can be classed as claims under the

    Contract as opposed to claims under the

    governing law of the Contract.

  • 8/13/2019 FIDIC Rainbow Suite 2012

    21/44

    Briefly, and in respect of the latter type of

    claim, FIDIC does not contain an exclusive

    remedies clause and also appears to

    foresee such claims, but still governed by

    clause 20, by the use of the word

    otherwise within the opening paragraph

    of Sub-Clause 20.1.

    Below is a list of the Sub-Clauses which

    entitle the Contractor to claim additional

    money (and possibly time) noting when the

    definition of Cost remains as per the

    definition or the Contractor is also entitled

    to a reasonable profit.

    Sub-Clause 1.9 Delayed Drawings or

    Instructions (Red Book only)

    If delay or disruption is caused or likely to

    be caused as a result of late drawings or

    instructions the Contractor is entitled to

    claim:

    Cost plus a reasonable profit

    Extension of time

    Sub-Clause 1.9 Errors in the

    Employers Requirements (Yellow Bookonly)

    If delay is caused or Cost is incurred as a

    result of errors in the Employers

    Requirements which were not previously

    discoverable the Contractor is entitled to

    claim:

    Cost plus a reasonable profit

    Extension of time

    Sub-Clause 2.1 Right to Assess to the

    Site

    If delay is caused or Cost incurred as a

    result of the Employer failing to give the

    Contractor access to the Site at the

    prescribed time the Contractor is entitled

    to claim:

    Cost plus a reasonable profit Extension of time

    Sub-Clause 4.7 Setting Out

    If delay is caused or Cost incurred as a

    result of errors in the original setting out

    points and levels of reference notified by

    the Engineer the Contractor is entitled to

    claim:

    Cost plus a reasonable profit Extension of time

    Sub-Clause 4.12 Unforeseeable

    Physical Conditions

    If delay is caused or Cost incurred as aresult of the Contractor encounteringphysical conditions which areUnforeseeable the Contractor is entitled toclaim:

    Cost (only)

    Extension of time

    It is worth noting that Unforeseeable is adefined term meaning not reasonably

  • 8/13/2019 FIDIC Rainbow Suite 2012

    22/44

    foreseeable by an experienced contractorby the date for the submission of theTender.

    Sub-Clause 4.24 Fossils

    If delay is caused or Cost incurred as aresult of the Contractors compliance withinstructions issued by the Engineer to dealwith the discovery of fossils and the likethe Contractor is entitled to claim:

    Cost (only)

    Extension of time

    Sub-Clause 7.4 Testing

    If delay is caused or Cost incurred as aresult of testing being delayed by theEmployer or on behalf of the Employer theContractor is entitled to Claim:

    Cost plus a reasonable profit

    Extension of time

    Sub-Clause 8.5 Delays caused byAuthorities

    If delay or disruption is caused or Costincurred as a result of the actions or nonactions of Authorities the Contractor isentitled to claim:

    Cost, with or without profit, appearsnot to have been specificallyconsidered

    Extension of time

    Sub-Clause 8.9 Consequences ofSuspension

    If delay is caused or is likely to be causedor Cost incurred as a result of theEngineers instructions to suspend work theContractor is entitled to claim:

    Cost (only)

    Extension of time

    Sub-Clause 10.2 Taking Over ofParts of the Works

    If the Contractor incurs Cost as a result ofthe Employer taking over or using a part ofthe Works the Contractor is entitled toclaim:

    Cost plus a reasonable profit

    Sub-Clause 10.3 Interference withTests on Completion

    If delay is caused or Cost incurred as aresult of tests being delayed by a reason

    for which the Employer is responsible theContractor, amongst other remedies, isentitled to claim:

    Cost plus a reasonable profit

    Extension of time

    Sub-Clause 11.8 Contractor to Search

    If the Contractor incurs Cost as a result ofsearching for a defect for which it was not

    liable the Contractor is entitled to claim:

    Cost plus a reasonable profit

    Sub-Clause 12.2 Delayed Tests (YellowBook only)

    If the Contractor incurs Cost as a result ofcarrying out Tests delayed by the Employeruntil after Completion the Contractor isentitled to claim:

    Cost plus a reasonable profit

    Sub-Clause 12.4 Failure to Pass Testsafter Completion (Yellow Book only)

    If the Contractor incurs Cost as a result ofthe Employer delaying access to allowTests to be carried out the Contractor isentitled to claim:

    Cost plus a reasonable profit

  • 8/13/2019 FIDIC Rainbow Suite 2012

    23/44

    Sub-Clause 13.7 Adjustments forChanges in Legislation

    If delay is caused or is likely to be causedor Cost incurred or likely to be incurred asa result of changes in the Laws of theCountry the Contractor is entitled to claim:

    Cost (only)

    Extension of time

    It is worth noting that Country is a definedterm meaning the Country in which theSite (or most of it) is located, where the

    Permanent Works are to be executed.Thus this definition is very limited in thefield of international contracting whereContractors, Suppliers and Sub-Contractorsmay all have originated from Countriesother than where the project is beingcarried out and may suffer as a result ofchanges in legislation.

    Sub-Clause 16.1 Cont ractorsEntitlement to Suspend Work

    If delay is caused or Cost incurred as aresult of the Contractor properlysuspending work (or reducing the rate ofwork) the Contractor is entitled to claim:

    Cost plus a reasonable profit

    Extension of time

    Sub-Clause 19.4 Consequences ofForce Majeure

    If delay is caused or Cost incurred as aresult of Force Majeure events theContractor is entitled to claim:

    Cost (only) in respect of the eventslisted at Sub-Clauses 19.1 (ii), 19.1(iii) and 19.1 (iv)

    Extension of time

    The above list is not exhaustive as towhere the Contractor can gain paymentsand/or entitlements within the FIDIC

    contracts; the list refers to Sub-Clausesspecifically referring to Cost as defined.

    In terms of monetary entitlements, Sub-Clauses not referenced include Evaluation(in respect of the Red Book) and Variationsas well as Payment on Termination wherean alternative set of rules come into being.The provisions of Sub-Clause 8.4 in respectof extensions of time should be thoroughlyconsidered in respect of entitlements to

    time extensions.

    The subtle differences between thecontents of the listed Sub-Clauses areinteresting if not explainable. The mostinteresting of which may be the addition ornot of a reasonable profit to theContractors Cost.

    Contractors will argue that they are notcharities and all expenditure properlyincurred as a result of others deserves /should be required to return a profit.Similarly many of the claim events, had thescope been fully understood at the time oftender by both parties, would have beenincluded within the Contractors bid and theContractor would have had the opportunityto add profit to its foreseen costs.

    Contractors and their advisers may wish toseek an adjustment to the definition ofCost when negotiating the Contract in thefuture.

    The influence of whether or not a Costattracts profit may also extend to thepreparation of claims for extensions oftime. Whilst many will say that at all timesthe causes of delay should be capable ofbeing clearly identified, this is often not thecase. There is also the propensity forContractors to establish claims around

    events that appear to have the best chanceof success or line of least resistance fromthe Engineer; perhaps even a global style

  • 8/13/2019 FIDIC Rainbow Suite 2012

    24/44

    claim is submitted to gain relief from thededuction of Liquidated Damages.

    In any event at some juncture theContractor and the Engineer, or perhaps aDAB or Arbitral Tribunal, have to considerthe causes of delay, establish periods ofextension of time against those causes andlastly establish if there are any monetaryentitlements to accompany those periodsof delay.

    The addition, or not as the case may, be ofprofit to a Contractors elements of aprolongation claim maybe considerableamount in these days where mega projectsexist and delays run into years not justdays or weeks. Contractors therefore mayselect, if possible, delay events that couldmaximise their potential financial returns.

    In respect of the Contractor declaring itsrequired profit, it is suggested that insteadof waiting until such time as a claim existsand the Employer and itsEngineer/Representative may be seeking tolimit expenditure against claims, theparties follow the lead given by FIDICwithin the MDB Harmonised Edition (thePink Book).

    The Pink Book at Sub-Clause 1.2 differsfrom the Red Book by the addition of twoparagraphs, in this context the importantone being:

    In these Conditions, provisions including theexpression Cost plus profitrequire this profit to be one-twentieth (5%) of this Costunless otherwise indicated inthe Contract Data.

    It will therefore be up to the Contractor toconsider that he may wish to declare ahigher profit than 5% at the pre-contractstage or accept that 5% profit whereapplicable on its entitlements listed withthe Contract. It may be that the

    Contractors actual bid margin was lessthan 5% and so it would gladly accept thaton offer.

    A further interesting subtlety is the use ornot of the phrase is likely to cause. Itmay have been more prudent upon thepart of the FIDIC drafters, whenconsidering the Employers interests to usethis phrase within all entitlement clausesso as to be consistent with the earlywarning obligations upon the Contractor interms of time within Sub-Clause 4.21 andthe general notice provisions of Sub-Clause

    20.1. This may also aid the earlyconclusion of claim issues.

    Contractors, when drafting sub-contractsshould take note of the differing provisionswithin the entitlement clauses such thatthe variants, especially in respect of therecovery of profit, are incorporated intoSub-Contracts so as not to cause ashortfall in recovery or lengthy discussionsconcerning the right or otherwise to profit

    in respect of claim monies. Although, inpractice it appears that Engineers onlydeny profit on the Contractors element ofa claim.

    It is noted that Sub-Clause 11.8 Contractorto Search, does not give a specificentitlement to a time extension albeitcircumstances can be imagined where adelay to completion may occur. Underthese circumstances the Contractor has

    two further options to obtain anyentitlement within Sub-Clause 8.4Extension of Time for Completion:

    Sub-Clause 8.4(b), where anextension of time may be claimedas a result of any cause under aSub-Clause of the Contract.

    Sub-Clause 8.4(e), where anextension of time may be claimed

    as a result of any delay impedimentor prevention caused by orattributable to the Employer, the

  • 8/13/2019 FIDIC Rainbow Suite 2012

    25/44

    Employers Personnel or theEmployers other contractors on theSite.

    FIDIC having been thorough in respect ofthe Contractors claims towards theEmployer have not carried through thisthoroughness in respect of claims from theEmployer to the Contractor.

    There is no definition of cost relative to theEmployers claims towards the Contractor and therefore it must be left to theEmployers agent or the Engineer, todetermine if profit should be passed on asa legitimate claim item.

    Finally, a brief reference was made aboveto claims made under the governing law asopposed to under the Contract. This isobviously an option open to the Contractorhowever, it is considered that claimsproperly made under the Contract will havea greater chance of speedy resolution. Itmay also be quite a time consumingexercise for a Contractor to take thenecessary legal advice before commencinga claim under the governing law. Shouldthis be the case the initial and fatal noticeprovisions of Sub-Clause 20.1 may comeinto play a topic for another article.

  • 8/13/2019 FIDIC Rainbow Suite 2012

    26/44

    This is the fifth in a series of articles being published in CES 1 .

    Following an introduction to FIDIC and its 1999 suite of contracts the joint authors, Paul

    Battrick 2 and Phil Duggan 3 of Driver 4 will discuss many practical issues of using FIDIC

    contracts. Their thoughts and opinions are based upon actual working experiences of working

    with many FIDIC contracts both past and present.

    Risk and Responsibility Clause 17 andbeyond

    If the phrase risk and responsibility is

    mentioned in respect of the FIDIC suite of

    contracts many, possibly new to the FIDIC

    forms, would consider clause 17 and

    possibly 18 and 19, of the major forms and

    close out their thought processes.

    This article reflects upon the allocation ofrisk and responsibilities within the major

    forms introduced in 1999 (the Red, Yellow

    and Silver Books) beyond the words

    contained within clause 17; but first a

    consideration of clause 17 as contained

    within the Red, Yellow and Silver Books.

    Clause 17 Risk and Responsibility

    This clause is typical of clauses that

    allocate risk and responsibility to events

    that are generally, but not always,

    insurable events; the likeness to clause 18

    Insurance can be readily viewed. The

    wording within the three major forms is

    considered to be clear and not in need of

    great explanation saves for the overview

    below.

    Sub-clause 17.1 provides for the

    indemnities that the Employer and the

    Contractor must provide to each other in

    case injury to people and/or property

    occurs as a result of the actions of

    personnel or other for which they are

    responsible during t he design, execution

    and completion of the Works. Property

    excludes the Works itself which is dealt

    with separately at Sub-clause 17.2.

    Generally unless specifically allocated to

    the Employer and those defined as being

    under its responsibility, events are the risk

    and responsibility of the Contractor.

    Sub-clause 17.2 provides for the

    Contractors care of the Works, for which it

    is fully responsible until such time as theTaking-Over Certificate (or Taking-Over

    Certificates in the case of sectional

  • 8/13/2019 FIDIC Rainbow Suite 2012

    27/44

    completion) is issued or deemed to be

    issued in accordance with Sub-clause 10.1,

    save for those items listed within Sub-

    clause 17.3 which are Employers Risks.

    Whilst this Sub-clause specifically deals

    with the care of the Works until a Taking-

    Over Certificate has been issued it does not

    mention suspension by either the

    Contractor or the Employer possibly

    leading to termination. It is suggested that

    the obligations of the Contractor to care for

    the Works remain throughout a

    suspension, irrespective of responsibility

    for the events leading to the suspension,

    until such time as work recommences and

    a Taking-Over Certificate is issued or

    Termination takes place and the Contractor

    is released from its obligations in this

    respect.

    This may be considered somewhat unjust if

    the Contractor has not been paid, the

    Employer cannot demonstrate that it has

    the arrangements in place to pay and the

    suspension leading to termination is

    lengthy thus resulting in a high cost burden

    for say the protection of the Worksincluding materials stored on and off site.

    The Contractor that relies upon the

    argument that it was not the cause of the

    suspension and consequent termination

    and therefore had no responsibility to care

    for the Works - may find itself unable to

    justify its claims for the work completed or

    partially completed and materials handed

    over to the Employer should termination

    take place.

    Sub- clause 17.3 is entitled Employers

    Risks which, in other words, are the risks

    that the Contractor has no control over.

    The Red and Yellow Books have identical

    lists and it is suggested that these are

    cross referenced with the list of typical

    events that may be classed as a Force

    Majeure within clause 19. It is also

    suggested that the defined term

    Unforeseeable within Sub-clause 17.3(h) is

    fully understood as so many have

    difficulties in separating what is unforeseen

    from what is unforeseeable when making

    claims.

    The FIDIC guide confirms the definition of

    unforeseeable to be not reasonably

    foreseeable by an experienced contractor

    by the date for submission of the Tender.

    It goes on to suggest that the frequency of

    natural events relative to the duration of

    the Time for Completion may provide

    guidance as to what should be considered

    as unforeseeable. Taking this suggestionperhaps a five minute discussion and

    survey with your colleagues could take

    place noting the following:

    Two projects adjacent to each other;

    same Contractor, Engineer and

    Employer.

  • 8/13/2019 FIDIC Rainbow Suite 2012

    28/44

    Duration of project A is eight years

    and project B is two years with

    identical commencement dates.

    Statistically the natural event

    occurs every ten years.

    The last event happened nine

    years ago and occurred one year

    after commencement of the

    projects.

    Which event falls within the definition of

    unforeseeable?

    The Silver Book has a shortened list losing

    the following:

    Use or occupation by the Employer

    of any part of the Permanent

    Works, except as may be specified

    in the Contract - should this occur

    it would be a breach by Employer

    of Sub-clause 10.2 and therefore

    not a risk.

    Design of any part of the Works by

    the Employers Personnel or by

    others for which the Employer is

    responsible the Silver Book

    foresees the Contractor beingresponsible for the total design of

    the Works, however this may be

    compromised by Sub-clause 5.1

    where the Employer retains some

    responsibilities for information that

    can affect design carried out by

    the Contractor.

    Any operation of the forces ofnature which is Unforeseeable

    unless such events can be justified

    as being a Force Majeure such

    events are deemed to be at the

    risk of the Contractor.

    Sub-clause 17.4 allows the Contractor to

    put forward its claims in respect of time

    and money in the event that the

    Employers Risks noted within Sub -clause

    17.3 result in loss or damage to the Works,

    Goods or Contract ors Documents.

    As with all other claims submitted by the

    Contractor in respect of a perceived

    entitlement either under the Contract or by

    law, the procedure within Sub-clause 20.1

    must apply or the Contractor risks losing

    any entitlement. The Engineer (or the

    Employer in the case of the Silver Book)

    must then proceed in accordance with Sub-

    clauses 20.1 and 3.5 to determine any

    entitlement. In terms of any monetary

    entitlement the Contractor is entitled to

    Cost or Cost plus a reasonable profit as

    detailed.

    Sub-clause 17.5 considers intellectual and

    industrial property rights and providesprotection to both the Contractor and the

    Employer from claims issued by third

    parties related to patents, registered

    designs, copyright and the like where the

    intellectual or industrial property rights

    have been allegedly infringed by either

    party. Whilst it is suggested that the

    claims procedure of Sub-clause 20.1applies to claims made under this clause

  • 8/13/2019 FIDIC Rainbow Suite 2012

    29/44

    (line two stating under any clause) the

    FIDIC drafters have seen fit to repeat,

    albeit in slightly different terms, the fatal

    nature of a 28 day notice period should

    either party wish to submit a claim.

    Sub-clause 17.6 deals with the limits of

    certain liabilities under the Contract.

    However, it is perhaps the most important

    clause that must be considered in the light

    of the provision of the governing law

    prescribed within the Contract. Various

    jurisdictions, either common law or civil

    law jurisdictions may affect matters

    concerning the length of any period in

    respect of defects liability, the

    commencement date for such liabilities can

    even negate the clause in its entirety in

    respect of the limit of financial liability in

    the event that gross negligence can be

    established to have taken place. This

    latter point being reflected within the FIDIC

    forms which confirms that there is no limit

    of liability in any case of fraud, deliberate

    default or reckless misconduct by the

    defaulting Party. This statement being

    particularly relevant during the bid phase

    and it is likely that the limit of liability to bestated within the Particular Conditions will

    be the subject of intense negotiations

    between the Employer and Contractor prior

    to the award of the Contract. If no sum is

    agreed and stated the Accepted Contract

    Amount will be the limit.

    The Sub-clause is intended to limit theContractors liability towards the Employer

    relative to the Contractors failed

    performance in respect of progress

    resulting in delay damages and, in respect

    of the Yellow and Silver Books, inadequate

    design, workmanship and the failure of

    materials etc., resulting in non-

    performance damages and non-availability

    damages if noted within the Particular

    Conditions. It also excludes any liability,

    by either party, in respect of loss of use of

    any Works, loss of profit, loss of any

    Contract or for any indirect or

    consequential loss or damage other than in

    respect of a termination or indemnities as

    per Sub-clause 17.1.

    There is no limit of liability upon the

    liability of the Employer towards the

    Contractor and any limitations by the

    Contractor towards the Employer excludes

    the supply of utilities (Sub-clause 4.19),

    Employers equipment and free issue

    material whilst in the care of the

    Contractor (Sub-clause 4.20), indemnities

    (Sub-Clause 17.1) and intellectual and

    industrial property rights (Sub-clause

    17.4).

    Risk and Responsibilities elsewhere

    The opening paragraph of this article

    suggested that many people, possibly new

    to the FIDIC forms, will limit their thoughts

    in respect of risks and responsibilities to

    clause 17 and possibly clauses 18 and 19.

    Those to whom that statement may applyare invited to consider that the contract,

  • 8/13/2019 FIDIC Rainbow Suite 2012

    30/44

    whether Red, Yellow or Silver Book, is in its

    entirety a fine balance of risks and

    responsibilities allocated between the

    Employer (and its Engineer or

    Representative) and the Contractor.

    Whilst opinions may differ as to the

    fairness, and validity in law, of conditions

    such as the fatal 28 day notice with Sub-

    clause 20.1, the FIDIC drafters will have

    considered such a period in the light of

    other obligations placed upon the

    Contractor within the Contract; such as the

    required monitoring of the programme and

    related matters (as discussed in the third

    article of this series).

    A viewpoint being that any Contractor who

    is not aware within 28 days that an event,

    for which the Employer is culpable, has a

    time or money impact does not deserve to

    receive any entitlement!

    The FIDIC suite of contracts, as with any

    other contract, can be considered to be no

    more than a rule book detailing the

    potential consequences should a defined

    event take place.

    If in a game of soccer someone is caught

    handling the ball the referee will give a free

    kick or penalty to the other side. If at the

    outset of a contract it is considered that all

    of the risks and responsibilities are

    allocated and the key elements of scope,

    time and price are defined then any eventthat may affect those key elements will

    cause the applicable rules to be consulted

    to establish which party is carrying the risk

    of that event.

    The FIDIC drafters have taken great care

    when dealing with the allocation risk such

    that internationally and less likely

    nationally Employers and Contractors can

    establish working relationships for the first

    and perhaps the only time based upon a

    considered set of rules.

    Those rules provide some certainty at the

    outset to both parties and, if triggered and

    operated well, can restore certainty in

    respect of the various risks and allocation

    of those risks following any necessary

    adjustments to all or any of the key factors

    of scope, time and price.

    The most obvious differences in risk

    allocation between Red, Yellow and Silver

    Books is in respect of design responsibility

    and the consequent risks of time and

    money impacts should design and

    therefore scope be amended at some point

    in time after the contract award.

    Design can be translated to mean choice;

    those with design responsibility have the

    ability to choose, affect the scope and

    potentially the time required to complete

    the project and the price for the project.

    Accordingly, and in overall terms, the risks

    associated with design responsibility underthe Red Book rests with the Employer,

  • 8/13/2019 FIDIC Rainbow Suite 2012

    31/44

    whilst the Contractor carries the risks

    under the Yellow and Silver Books. In all

    contracts for the Contractor to gain any

    entitlement it has to comply with at least

    the provisions of Sub-clause 20.1 in

    respect of the issue of notices and the

    subsequent provision of a detailed claim.

    The risk of failing to establish contractual

    relationships with Sub-Contractors and

    others to allow compliance with these

    periods rests with the Contractor. In this

    respect the periods stated within Sub-

    clause 20.1 may be considered short or the

    minimum required to gain adequate data

    and input from others.

    There are many areas that are common to

    the Red, Yellow and Silver Books that

    provide protection and therefore less risk

    to the Contractor.

    In the context of perhaps the Contractor

    making a bid to perhaps a special purpose

    vehicle it is important to know that that

    entity cannot change overnight once the

    Contract Agreement has been signed. At

    Sub-clause 1.7 Assignment it is stated that

    neither party shall assign the Contract orany part of the Contract without the prior

    agreement of the other Party; accordingly

    the Contractor (perhaps with the most to

    lose) is protected from the Employer being

    changed to some party it would never have

    contemplated to be its contracting partner.

    The Contractors cash flow may beprotected to some degree by the provision

    of an advance payment linked to an

    Advance Payment Guarantee. However,

    regular and timely payments to the

    Contractor remain its lifeblood; should the

    Engineer fail to certify a payment (if

    appropriate) and/or the Employer fail to

    make payments at the prescribed time as

    per Sub-clause 14.7 the Contractor can

    either reduce the rate of work or suspend

    work provided not less than 21 days notice

    has been given. This being in accordance

    with Sub-clause 16.1. Should the

    situation not change within the timescales

    prescribed within Sub-clause 16.2 the

    Contractor can terminate the Contract.

    The option of suspension or reducing the

    rate of progress followed by termination

    also applies if the Employer cannot provide

    reasonable evidence that financial

    arrangements have been made and are

    being maintained which will enable the

    Employer to pay the Contract Price (as

    estimated at the time) as stated with

    Sub-clause 2.4. It is not confirmed whose

    estimated Contract Price should be used as

    a reference point; the views of the

    Contractor and the Employer may differgreatly in this respect especially if the

    Contractor has the tendency to inflate its

    claims to unrealistic values. Nevertheless

    the FIDIC drafters have made provisions to

    reduce the risk of a Contractor suffering

    from an uncertain payment regime.

    For the purpose of this article there is onemore major factor to be considered in

  • 8/13/2019 FIDIC Rainbow Suite 2012

    32/44

    terms of risk allocation; that being the

    ability of the Contractor to achieve

    completion. It is not uncommon for

    Employers to take occupation of a project

    and subsequently receive income but find

    reasons not to accept that the Contractor

    has achieved completion as defined.

    Accordingly the Employer gains income and

    is possibly continuing to deduct delay

    damages whilst the Contractor cannot

    obtain any of the financial benefits of

    attaining completion, the responsibility for

    maintenance, wear and tear and the like

    remain with the Contractor whilst any

    defects liability period cannot commence.

    The FIDIC drafters have considered such

    circumstances and provided, within Sub-

    clause 10.1, the ability for the Contractor

    to attain Completion. Sub-clause 10.1,

    states in general terms, that when the

    Contractor has completed the Works (or

    Sections) in accordance with the Contract

    such that no minor outstanding work or

    defects prevent the use of the Works for

    what they were intended, the Contractor

    may apply by notice to the Employer for a

    Taking-Over Certificate. The Engineer (orEmployer as appropriate) will respond

    within 28 days either by issuing the

    Taking-Over Certificate or confirming why

    no certificate can be issued. The latter

    providing the criteria for the Contractor to

    fulfil prior to issuing a further notice for a

    Taking-Over Certificate.

    Should the Engineer (or Employer as

    appropriate) fail to either issue the Taking-

    Over Certificate or give reasons for not

    issuing the Certificate within the period of

    28 days, the Taking-Over Certificate shall

    be deemed to have been issued on the

    twenty eighth day.

    Sub-clause 10.2 in all forms provides

    further support for the Contractor by

    confirming that the Employer shall not use

    any part of the Works prior to Completion.

    Sub-clause 10.3 within the Red and Yellow

    Books gives further protection to the

    Contractor. In the event that the

    Contractor is prevented from carrying out

    any tests necessary to attain Completion

    by a cause for which the Employer is

    responsible for a period of 14 days the

    Employer will be deemed to have taken

    over the Works and the Engineer must

    issue a Taking-Over Certificate; the

    relevant date being that on which the tests

    would have been completed.

    The defined timescales of every phase of

    the dispute resolution procedure withinClause 20 seek to offer the Contractor

    some certainty and lessen risk in the event

    that a DAB and Arbitration are necessary,

    but they are the subject of a different

    article as is the abuses to the allocation of

    risk and responsibility so carefully

    considered by the FIDIC drafters.

  • 8/13/2019 FIDIC Rainbow Suite 2012

    33/44

    This is the sixth in a series of articles being published in CES 1 .

    Following an introduction to FIDIC and its 1999 suite of contracts the joint authors, Paul

    Battrick 2 and Phil Duggan 3 of Driver 4 will discuss many practical issues of using FIDIC

    contracts. Their thoughts and opinions are based upon actual working experiences of working

    with many FIDIC contracts both past and present.

    A Risk too far for the EPC Contractor

    This article considers the step change in

    respect of the allocation of risks between

    the Yellow and Silver books of the FIDIC

    1999 suite of Contracts and poses the

    question for a traditional EPC contract are

    those risks a step too far.

    Traditionally

    International contracting possess a vast

    number of contractors that use the term

    EPC contractor to describe how they

    operate and what services they can provide

    to their potential Employers; in simple

    terms they Engineer or design the works,

    Procure all that is necessary to complete

    the works and finally Construct the works.

    This regime is very similar to that utilised

    by a Design and Build contractor and is

    appl