FAUZAN RUMZI PERSONAL DATA Name : Fauzan Rumzi, ST Address : Jln. Nuh No.10 RT/RW.03/10 Kelurahan: Suka Bumi Utara Kecamatan: Kebun Jeruk Kotamadya: Jakarta Barat DKI Jakarta 11540 - Indonesia E-mail address : [email protected] [email protected] Mobile : Indonesia (+62) 081363335300 or 085215191619 Place, date of birth: Bukittinggi, January 13, 1975 Gender : Male Marital status : Married Nationality : Indonesia Language : Indonesia and English Qualifications and Certificate (Certified): API 653 (Tank Inspector) Quality Management System Auditor/Lead Auditor (IRCA 17399) Welding Inspector CSWIP 3.1 Welding Inspector CSWIP 3.0 Welding Inspector MIGAS - B4T Radiographic Interpreter ASNT Level 2 (NDT- RI) Penetrant ASNT Level 2 (NDT - PT) Magnetic Particle ASNT Level 2 (NDT- MT) General Paint School Generic Type of Points Pre- BlastingPreparation, PreTreatment, Application, Calculationb Jotun Paint Computer Course English Extension Course EDUCATION BACKGROUND: 1996 – 2001 : Graduated from Degree (S-1) University of Eka Sakti In Padang – Indonesia, Majoring Mechanical Engineering 1991 – 1994 : Graduated from Senior High School of SMUN 01 In Bukittinggi – Indonesia 1989 – 1991 : Graduated from Junior High School of SMPN 05 In Bukittinggi - Indonesia 1984 – 1989 : Graduated from Elementary School of SDN 14 In Bukittinggi – Indonesia

Upload: vokhanh

Post on 07-Mar-2018

227 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

FAUZAN RUMZI

PERSONAL DATA Name : Fauzan Rumzi, ST

Address : Jln. Nuh No.10

RT/RW.03/10

Kelurahan: Suka Bumi Utara

Kecamatan: Kebun Jeruk

Kotamadya: Jakarta Barat

DKI Jakarta 11540 - Indonesia

E-mail address : [email protected]

[email protected]

Mobile : Indonesia (+62) 081363335300 or 085215191619

Place, date of birth: Bukittinggi, January 13, 1975

Gender : Male

Marital status : Married

Nationality : Indonesia

Language : Indonesia and English

Qualifications and Certificate (Certified): API 653 (Tank Inspector)

Quality Management System Auditor/Lead Auditor (IRCA 17399)

Welding Inspector CSWIP 3.1

Welding Inspector CSWIP 3.0

Welding Inspector MIGAS - B4T

Radiographic Interpreter ASNT Level 2 (NDT- RI)

Penetrant ASNT Level 2 (NDT - PT)

Magnetic Particle ASNT Level 2 (NDT- MT)

General Paint School Generic Type of Points Pre-

BlastingPreparation, PreTreatment, Application, Calculationb Jotun Paint

Computer Course

English Extension Course

EDUCATION BACKGROUND: 1996 – 2001 : Graduated from Degree (S-1) University of Eka Sakti

In Padang – Indonesia, Majoring Mechanical Engineering

1991 – 1994 : Graduated from Senior High School of SMUN 01

In Bukittinggi – Indonesia

1989 – 1991 : Graduated from Junior High School of SMPN 05

In Bukittinggi - Indonesia

1984 – 1989 : Graduated from Elementary School of SDN 14

In Bukittinggi – Indonesia

Page 2: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

Summary and Qualification: √. API 653 (Tank Inspector)

Conducted by The Welding Institute (TWI) UK, London and PT. Beyond

Training on PT. Chevron Pacific Indonesia to Chevron Center Rumbai – Pekan

Baru/Riau.

√. Quality Management System

Quality Management System Auditor / Lead Auditor (IRCA Certification

A17399).

PT Neville Clarke Indonesia, Graha Indramas 4th Floor, J1.AIPDA KS Tubun

Raya No.77 Jakarta 11410 Email: [email protected]

√. Welding Inspector CSWIP 3.1(Welding Inspector International)

Welding Inspector International Certification of CSWIP 3.1 Training,

Conducted by The Welding Institute (TWI) UK, London and PT. Beyond

Training on

Jl. Kaliurang KM. 5, Ladrang no.4A, CT III, Utara Hotel Vidi 1

Sleman – YOGYAKARTA (55281) Email: [email protected]

Period December 7, 2009 to December 11, 2009. CSWIP 3.1 Certificate no :(

48856)

Welding lecturer & Executive is Mr Mohd Sulaiman Abbas

√. Visual Welding Inspector CSWIP 3.0(Visual Welding Inspector

International)

Visual Welding Inspector International Certification of CSWIP 3.0 Training,

conducted by The Welding Institute (TWI) UK, London .Presented by PT. Dua

Utama Jaya. Jl. Yos Sudarso, Complex Green Town Warehouse No. 2, Bengkong –

Batam. Email: [email protected]

Period November 22, 2007 to November 30, 2007.CSWIP 3.0 Certificate No:

(31758)

Welding lecturer & Executive is Mr Mohd Darus Bin Taib

√. Welding Inspector MIGAS (IWS/International Welding

Specialist) WELDING INSPECTOR ( IWS )

Presented by Balai Besar Bahan and Barang Teknik (B4T- Bandung) supported by

MIGAS

(Oil and Gas Department) and DEPNAKER (Labor Department)

Period November 10, 2002 until February 10, 2003.Certificate no. (0203.12.61)

B4T-Bandung.Jln.Sangkuriang no.14 Bandung – Indonesia

√. ASNT Radiographic Interpreter (RI) Level II

Training & Qualification. Certificate no. (116/RI/N/10)

SNT-TC-1A,2006 edition.

August 10, 2010 toAugust 25, 2010 Duri/Riau – Indonesia.

Edi Padmo, ST. (ASNT/NDT LEVEL III)

√. ASNT Magnetic Particle Test (MT) Level II

Participant ASNT MAGNETIC PARTICLE TESTING LEVEL.II Training &

Qualification. Certificate no.(SMS-MT-08068)

August 10, 2008 toAugust 25, 2008 Jakarta – Indonesia.

Sainal Rapi. (ASNT/NDT LEVEL III)

Page 3: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

√. ASNT Penetrant Test (PT) Level II

Training & Qualification. Certificate no.(SMS-PT-08027)

August 10, 2008 toAugust 25, 2008 Jakarta – Indonesia.

√. General Paint School

Generic Type of Points Pre-Blasting

Preparation, Pre- Treatment, Application, Calculationb

Jotun Paint School Certification of Attendance.

√. COMPUTER COURSE

Windows, Microsoft word, Microsoft Excel and Microsoft Power point, Intro

to Multi Media, Intro to Internet.

Certificate no.2282 C.LPKP-Q.IV.2002. Period November 12, 2001 until April 12,

2002 Presented by Quantum Computer.

Padang – Sumatra Barat. West Sumatra Indonesia

√. English Extension Course

Speaking, Reading, Listening, Writing

Certificate no.1326.E.LPKP-Q.V .2002 Period November 12, 2001 until April

12, 2002 Presented by Quantum Computer.

Padang – Sumatra Barat. West Sumatra Indonesia

MEMBERSHIP: Fellow Member, the International Association of Quality Practitioners. (IAQP)

Member Associate Member, the Welding Institute. (TWI) Member, the

Indonesia Welding Society. (IWS - API)

Graduate Member, the American Institute of Non-Destructive Testing. (ASNT)

Associate Member, the Chartered Quality Institute. (CQI)

EXPERIENCE 11 YEAR. Having more than 11 years in Oil & Gas and Petrochemical Project at EPC and

Flexible Program Management Service and Fabrication Company as Field

Engineer, QC Inspector, QC Tank Inspector, Senior Tank Inspector, QC Piping

Inspector, Welding Inspector, Senior Welding Inspector and QA/QC

Coordinator, Asst QA/QC Manager. Scope of work in piping gas station likes

inspection line check of piping system, review P&ID, prepare test package for

pre-commissioning-commissioning, facilities acceptance line check inspection.

Inspection for mechanical equipment and static equipment fabrication (Pressure

Vessel, Column, Heat Exchanger, Air Cooler, Pig receiver/Launcher, Package

equipment and storage Tank). Other scope as supervision develops and reviewed

procedure for quality management system (QMS), Fabrication Procedure, NDE

procedure, painting-coating procedure, materials inspection and review mill

certificate, WPS/PQR. Familiar with QA/QC document system and traceability

record, ability with computer literate, familiar with standard related with oil &

gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

Petrochemical, Pawer Plan, Oil&LPG Tank Terminal Project,Flexible Program

Management Service.

Page 4: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

Skills:

- Capable to conduct onshore/offshore pre-commissioning, Testing and commissioning activities of piping and

Mechanical systems.

- Capable in fabrication, installation, periodic/annual

Inspection & quality control/assurance of non-destructive

Test for oil & gas production, off shore platform, pressure vessels, heat

Exchanger, boiler, pipeline, all Tank, piping welding inspection,

Tank welding inspection.

- Capable for technical review of document, WPS, drawing and field

Inspection of pressure vessels, storage tank, process piping, pipeline,

Flow line, Prodection line and off shore platform.

- Familiar with international standard and codes such as: AWS, ASME,

API, ANSI, British Standard, NACE and other codes.

- Capable to operate non-destructive test non-radiation and interpreting

Film of Radiographic test.

- I have experience in various welding process and various codes like

ASMEB31.1, ASMEB31.3, ASMEB31.4. ASMEB31.8, ASMESec-IX,

ASMESecVIII, API-1104, API-650, API-653, API-570, API-510.

DUTIES:

Having the aptitude and experience in communicating with personnel and

management of multi disciplined

nationalities, and delegation thereof.

Continued project progression occurs, when one is able to liaise between client,

contractor or third parties,

efficiently and effectively.

GENERAL: (Experienced with the under mentioned welding material and

processes.)

Welding processes: SMAW, GTAW, MIG, SAW, FCAW, CRC, STT.

Materials: Low temperature carbon steel, medium carbon steel,

ferritic/austentic stainless steel,

Titanium metals et cetera, Duplex stainless steel, Inconel, Incoalloy and copper

nickel.

Knowledgeable of quality assurance functions, such as compilation of:

Quality Assurance Manuals Procedures Inspection and Test Plans

Project Completion Dossiers Isometric mark up and line checks

PROFESSIONAL WORKING EXPERIENCE,

Company : PT. Tripatra Fluor Consortium (Client/Owner Representative)

Project and Maintenance: Chevron Pacific Indonesia -

Flexible Program Management Service

Discipline of Work: CGS, GS, POP, Onnflot, offlot and all piping: Stem Line,

Gas Line, Product Line, Flow Line, Pipe Line (Oil and Gas)

Position : QA/QC Senior Piping Inspector

Year : 27 March 2011 to Present

Location : SLN – REM – CMT and IM - LIBO (Duri – Riau)

Client/Owner : Chevron Pacific Indonesia

Page 5: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

DUTIES AND RESPONSIBILITIES:

SCOPE OF DUTY & ACTIVITIES INVOLVED

Reviewing all the procedure WPS, PQR , NDE Procedure and NDE

Technician Certificate , Equipment calibration Certificate., HYDROTEST

Procedure, and Equipment Calibration Certificate & Pigging Procedure.

Witness of Welding Qualification Test by Contractor

Reviewing Material Certificate & Check Quality Material

Reviewing ITP & SOP

Reviewing Drawing & P&ID

Visual Inspection of the pipe to be used (measurement, cutting, beveling,

alignment & Fit-up

Monitoring of Welding Consumable, Handling & Storage

Conduct welding Inspection during Construction, Installation & Tie-in.

Monitoring & Inspecting that the Contractor doing all required, satisfied

and meet to the Requirement of the Standard, Specification as API 5L,

API 1104, ANSI B 31.8 ASME IX, API 650, API 653, API 510, API 2201,

API 570 & Engineering Design.

To take up the spot of Radiography Test & other NDE.

Reviewing & Aproval Welding Records Traceability at QC document

Constractor

Reviewing the Completed document Package for Hydrostatic Test

Line Check/Puch List Check as Per Test Packet

Witness Hydrostatic Test , Pigging & Flushing, Review & Aproved Report

Monitoring & Inspection Aplication Procedure & Standard at Field

Prepared Procedure For Repair Tank According API 653 Standard,

Review Welder Qualification According ASME IX Standard, Witness &

Review Result Wall Thickness measurement According Guid Line for

Repair Tank & Aproved Report Wall Thickness.

Prepared Procedure Pressure Vessel According ASME VIII Standard,

Witness & Review Result Wall thickness Measurement According Guide

Line for Repair Vessel & Aproved Report Wall Thickness.

Prepared Hot Tap Permite for Install Spool MPFM Header Flow Line

Prepared Surveiilance Report send to QA/QC ManagerTF & CPI.

Final Review Completed package Document Constractor Before Approved

CPI.

Conduct Montly Meeting with CPI CMT REM C

- Libo pipe Repalacement : Well Location LIBO # 03, # 20, # 53, # 48 & 6’

Mandar Gas Line

- LIBO GP. Improvement Flare Stack

- Petani pipe Replacement, well Location PETANI # 17, # 25

- Hiu Cucut Pipe Repalcement, well location HIU # 03, CUCUt # 01

- Pematang Pipe Replacement,well location PMTG #16, # 41, # 61,#32

- Pematang 10’ pipe Replacement

- Rangau Gs , Repair Test Tank

- Bekasap GS , Wash Tank Repair III

- Petani GP Improve piping system Corroded

- Petani GP Improve Install VRU

- Pematang GP Improve pematang Dehydration

Page 6: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

Company : PT.Toyo Kanetshu Indonesia

Discipline of Work: Storage TANK / LNG, LPG – Spherical Tank, Water Tank

Position : QA/QC Asst Manager

Year : 30 December 2010 – 21 March 30, 2011

Location : LNG Tangguh WWT/BP - Papua

Client : PT. BP Indonesia

DUTIES AND RESPONSIBILITIES:

SCOPE OF DUTY & ACTIVITIES INVOLVED Witness welding procedure qualification test

Incoming material Inspection and check thickness material inspection

Dimensional control of fabrication

(Cutting and rolling Plate) pipe and all Accessories of storage tank

Dimensional check and visual inspection of steel structure

Control all visual inspection report fabrication

Training of new welder test before WQT.

Welder performance Qualification

Test per approved WPS.

Responsible to weld product and weld sequence

WQT for storage tank and prepare Welder ID and welder list.

Dimensional check: Plamb,Roundness, Levelness, Peking Banding and

Accessories orientation

Checking welding consumable prior to Welding and during welding

Visual inspection completed weld

Perform welding inspection works before, during, and after welding in

accordance with ITP, Project specification, Codes & Standard.

Coordinate the performance the performance of NDT & PWHT works

in accordance with ITP, Project specification, Codes & Standard.

Verify that approved WPS is available; welder is qualified with the

process and AFC drawing.

Ensure full coverage of all Fit-Up, welding works, & NDT/PWHT

activities.

Ensure that QC inspection program is being implemented accordingly.

Perform and or/coordination welder qualification test.

Notification to client of the inspection schedule.

Liaise with client field inspection.

Perform & Supervise performance of material receiving inspection.

Dimensional check storage tank before welding (Plumb, Roundness,

Levelness, Paking and Banding) and fit – up Manhole and Nozzle prior

to welding.

Inspection checks Dimensional orientation shell nozzle and Roof

nozzle and Shell, Roof manhole.

Perform joint Fit-Up inspection & ensure dimensional check.

Check weld end preparation, tacking method, electrode used, pre-heat

requirement, inter-pass temperature & cleaning in accordance with

WPS.

Check welding parameter & welding consumables.

Page 7: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

Perform final welding visual inspection in accordance with acceptance

criteria.

Identify weld requiring NDT & coordinate for NDT performance

Coordinate weld repair work in accordance with the repair procedure.

Review report & ensure that reports are prepared whenever required.

Responsible and Supervision of the Fit up and Erection (check

dimensional, orientation as per drawing) on the shell plate, Bottom

Plate, Bottom Annular, Suspended deck, Roof Plate, Compressor Ring,

Roof Structure, Stiffener Ring.

Responsible and Supervision of the Air Rissing work of Roof included

suspended

deck for Nh 20 Tank

Monitoring of weld rejection rate & NDT performance status.

Prepared Welding MAP

Prepared RT MAP

Prepared thickness MAP

Interpreted RT films & review PWHT charts.

Preparing document test package for Hydro test / Pneumatic test

Witness hydro testing, air leak testing & flushing.

Witness after hydro testing , solution film testing (SFT)

Line check and re-instatement of piping system, punch list and final

acceptance.

Preparing daily inspection report and manufacture data report (MDR.)

Company : PT. URAWA REKAYASA MANDIRI

Engineering –Contractor –Supplier

http://www.urawa.co.id

Discipline of Work: NEW 16’’ & 20’’PROD.LINE FROM TILAN BOOSTER TO

PAGER G.S. AT PAGER FIELD. (Pipe Line, Rood Crossing,

EXP. LOOP)

& NEW 16’’ & 12’’ PIPE PROD.LINE UPGRADE KOTA BATAK

OPERATION. (Pipe Line, Rood Crossing, EXP. LOOP)

Position : QA/QC Coordinator

Year : December 23, 2009 – December 24, 2010

Location : SLS/Duri-TILAN BOSTER # 9 (RIAU) &

SLN/MINAS – Kota Batak /SLS AREA KOPET (RIAU)

Client : PT. CHEVRON

DUTIES AND RESPONSIBILITIES:

SCOPE OF DUTY & ACTIVITIES INVOLVED Witness welding procedure qualification test

Responsibilities Carryout Inspection in accordance with ITP

Inspection of incoming Equipments and Bulk materials

Regular Inspection Construction activities

Inspection of Local fabricators work related to the Project

Verify the agreed corrective actions to Non-conformance Reports

Witness selected NDT activities

Inspection Flange faces serration

Witness of Flanges Bolt tightening

Witness of Hydrostatic and Pneumatic test

Page 8: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

Review the Sub contractors documents

Final review on Test Packs

Inspection of 8",12",16",20",24" dia 32 km Pipe line for SLN or

SLS/Duri-TILAN BOSTER # 9 (RIAU) & SLN/MINAS – Kota Batak

/SLS AREA KOPET (RIAU) cHEVRON Project

Incoming material Inspection and check thickness material inspection

Dimensional control of fabrication

(Cutting pipe and all Accessories of Pipe line.

Dimensional check and visual inspection of steel structure

Control all visual inspection report fabrication

Training of new welder test before WQT.

Welder performance Qualification

Test per approved WPS.

Responsible to weld product and weld sequence

WQT for storage tank and prepare Welder ID and welder list.

Witness welding procedure qualification test piping system

Witness welding procedure qualification test for pipe line

Witness mechanical test for qualification procedure

Monitoring Fabrication Pig Receiver and pig Launcher and review all

document and NDT Report.

Monitoring Fabrication steel structure pipe rack and operation

building.

Visual check, Dimensional face to face, and to end Hydrostatic of

valves.

Monitoring fabrication storage tanks.

Witness PWHT Clean out door for storage tanks.

Witness Various Inspection piping welding activities for various

material verification such as fit-up visual inspection, preheating and

post weld heat treatment, dye leak test line check and Hydrostatic

test.

Witness Calibration pump

Inspection of all incoming material

Witness and dimensional check cold bending pipe

Responsible and supervising of insulation hot & cold in the boiler,

vessel, exchanger, tank, piping, and etc.

Responsible and supervision of painting the tank, vessel, exchanger,

pump & motor, piping, structure and etc.

Review and Record Inspection Report as per Job Specification

Counduct line check and punch list with engineering and owner.

Visual inspection of welding work and verification quality welded by

destructive and non-destructive.

Witness with owner of vacum test, pad Leak Test, penetrant Test and

Hydro Test.

Inspection Coating pipe with holiday detector.

Interpretation RT film

Prepared history sheet for control all report: Material, welding,

trencing, coating, Backlfilling.

Prepared history sheet for complete test Package well flow line and

weld head piping.

Witness Gauging, pigging, flashing, Hydrostatic and pressure test.

Page 9: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

Company : PT.Bangun Bejana Baja

Engineering & Construction (BBB)

Discipline of Work: Storage TANK (MOGAS and DIESEL)

Position : Senior Welding Inspection (WI) /ALL NDT & NDE

Year : July 12, 2008 to 23 October 2009)

Location : Tanjung Priok (PROJECT JAKARTA TANK TERMINAL)

(JAKARTA UTARA)(20 TANK Doom Roof)

Client : PT. VOPAK/JTT (BELANDA)

DUTIES AND RESPONSIBILITIES:

E OF DUTY & ACTIVITIES INVOLVEDSCOP Witness welding procedure qualification test

Incoming material Inspection and check thickness material inspection

Dimensional control of fabrication

(Cutting and rolling Plate) pipe and all Accessories of storage tank

Dimensional check and visual inspection of steel structure

Control all visual inspection report fabrication

Training of new welder test before WQT.

Welder performance Qualification

Test per approved WPS.

Responsible to weld product and weld sequence

WQT for storage tank and prepare Welder ID and welder list.

Dimensional check: Plamb,Roundness, Levelness, Peking Banding and

Accessories orientation

Checking welding consumable prior to Welding and during welding

Visual inspection completed weld

Perform welding inspection works before, during, and after welding in

accordance with ITP, Project specification, Codes & Standard.

Coordinate the performance the performance of NDT & PWHT works

in accordance with ITP, Project specification, Codes & Standard.

Verify that approved WPS is available; welder is qualified with the

process and AFC drawing.

Ensure full coverage of all Fit-Up, welding works, & NDT/PWHT

activities.

Ensure that QC inspection program is being implemented accordingly.

Perform and or/coordination welder qualification test.

Notification to client of the inspection schedule.

Liaise with client field inspection.

Perform & Supervise performance of material receiving inspection.

Dimensional check storage tank before welding (Plumb, Roundness,

Levelness, Paking and Banding) and fit – up Manhole and Nozzle prior

to welding.

Inspection checks Dimensional orientation shell nozzle and Roof

nozzle and Shell, Roof manhole.

Perform joint Fit-Up inspection & ensure dimensional check.

Check weld end preparation, tacking method, electrode used, pre-heat

requirement, inter-pass temperature & cleaning in accordance with

WPS.

Check welding parameter & welding consumables.

Perform final welding visual inspection in accordance with acceptance

criteria.

Identify weld requiring NDT & coordinate for NDT performance

Page 10: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

Coordinate weld repair work in accordance with the repair procedure.

Review report & ensure that reports are prepared whenever required.

Responsible and Supervision of the Fit up and Erection (check

dimensional, orientation as per drawing) on the shell plate, Bottom

Plate, Bottom Annular, Suspended deck, Roof Plate, Compressor Ring,

Roof Structure, Stiffener Ring.

Responsible and Supervision of the Air Rissing work of Roof included

suspended

deck for Nh 20 Tank

Monitoring of weld rejection rate & NDT performance status.

Prepared Welding MAP

Prepared RT MAP

Prepared thickness MAP

Interpreted RT films & review PWHT charts.

Preparing document test package for Hydro test / Pneumatic test

Witness hydro testing, air leak testing & flushing.

Witness after hydro testing , solution film testing (SFT)

Line check and re-instatement of piping system, punch list and final

acceptance.

Preparing daily inspection report and manufacture data report (MDR.)

Company : PT.TIMAS SUPLINDO

Engineering & Construction

Discipline of Work: Mechanical & Piping, Storage TANK

Position : Senior Piping Inspector

Year : Desember, 20, 2007 to Mart, 27, 2008

Location : Project PM#8 & MB#23 Indah Kiat – Perawang

(RIAU).

PROJECT:

Project PM#8 & MB#23 Indah Kiat Process Pabrik / Storage Tank (Construct

and erect, Storage Tank (Double-Tank / Shell Inside Nickel 9%,Paiping

TITANIUM Reactor,Dabel Defuser Tank Pixel,Stinlis Tank ( 13 Tank ),Sat Down

Piping,Tae In Piping ( 7500/Isometrit-Drawing)

DUTIES AND RESPONSIBILITIES:

SCOPE OF DUTY & ACTIVITIES INVOLVED Witness welding procedure qualification test piping system

Witness welding procedure qualification test for pipe line

Witness mechanical test for qualification procedure

Monitoring Fabrication Pig Receiver and pig Launcher and review all

document and NDT Report.

Monitoring Fabrication steel structure pipe rack and operation

building.

Visual check, Dimensional face to face, and to end Hydrostatic of

valves.

Monitoring fabrication storage tanks.

Witness PWHT Clean out door for storage tanks.

Page 11: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

Witness Various Inspection piping welding activities for various

material verification such as fit-up visual inspection, preheating and

post weld heat treatment, dye leak test line check and Hydrostatic

test.

Witness Calibration pump

Inspection of all incoming material

Witness and dimensional check cold bending pipe

Responsible and supervising of insulation hot & cold in the boiler,

vessel, exchanger, tank, piping, and etc.

Responsible and supervision of painting the tank, vessel, exchanger,

pump & motor, piping, structure and etc.

Review and Record Inspection Report as per Job Specification

Counduct line check and punch list with engineering and owner.

Visual inspection of welding work and verification quality welded by

destructive and non-destructive.

Witness with owner of vacum test, pad Leak Test, penetrant Test and

Hydro Test.

Inspection Coating pipe with holiday detector.

Interpretation RT film

Prepared history sheet for control all report: Material, welding,

trencing, coating, Backlfilling.

Prepared history sheet for complete test Package well flow line and

weld head piping.

Witness Gauging, pigging, flashing, Hydrostatic and pressure test.

Company : TKK/TKI (TOYO KANETSHU INDONESIA)

Position : Senior Tank Inspector (All NDT)

Year : April, 04, 2007 to November, 17, 2007

Location : PAPUA – INDONESIA/ PROJECT TANGGUH LNG

BP PROJECT TANGGUH LNG

Client : PT. BP (British Petroleum)

PROJECT:

Tangguh LNG Onshore Project LNG Storage Facilies E P C of LNG Storage Tank

(Construction and erect 11, Storage Tank (Double-Tank / Shell outside plate and

Shell inside Nickel 9%, Double Dome Roof. Roof outside Congrete and Roof

inside Plat Carbons, Deck Floating Roof Almunium. (ALL 11 Tanks/ 2 LNG TANK)

DUTIES AND RESPONSIBILITIES:

SCOPE OF DUTY & ACTIVITIES INVOLVED

Incoming material Inspection

Dimensional control of fabrication

(Cutting and rolling Plate) pipe and all Accessories of storage tank

Control all report fabrication.

Training of new welder test before WQT.

Welder performance Qualification

Test per approved WPS.

Checking welding consumable prior to Welding and during welding.

WQT for storage tank and prepare Welder ID and welder list.

Inspection of welding sequence, Distortion control prior to welding.

Page 12: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

Witness and Prepared all Leak test,Vacum box test report

Witness and Prepared all PENETRANT TESTING (PT) report

Monitoring welding activities and prepared joint number system.

Final visual inspection of welding joint.

Dimensional check storage tank before welding (Plumb, Roundness, Levelness,

Responsible and Supervision of the Fit up and Erection (check dimensional,

orientation as per drawing) on the shell plate, Bottom Plate, Bottom Annular,

Suspended deck, Roof Plate, Compressor Ring, Roof Structure, Stiffener Ring.

Responsible and Supervision of the Air Rissing work of Roof included suspended

deck for Nh 3 Tank.

Paking and Banding) and fit – up Manhole and Nozzle prior to welding.

Prepared Material traceability MAP

Prepared Welding MAP

Prepared RT MAP

Prepared thickness MAP

Prepared PMI MAP

Prepared joint number system/RT film marking system

Coordinate the performance the performance of NDT & PWHT works in

accordance with ITP, Project specification, Codes & Standard.

Verify that approved WPS is available; welder is qualified with the process and

AFC drawing.

Ensure that QC inspection program is being implemented accordingly.

Notification to client of the inspection schedule.

Liaise with client field inspection.

Perform & Supervise performance of material receiving inspection.

Perform joint Fit-Up inspection & ensure dimensional check.

Check weld end preparation, tacking method, electrode used, pre-heat

requirement, inter-pass temperature & cleaning in accordance with WPS.

Check welding parameter & welding consumables.

Perform final welding visual inspection in accordance with acceptance criteria.

Identify weld requiring NDT & coordinate for NDT performance

Coordinate weld repair work in accordance with the repair procedure.

Review report & ensure that reports are prepared whenever required.

Monitoring of weld rejection rate & NDT performance status.

Interpreted RT films & review PWHT charts.

Preparing document test package for Hydro test / Pneumatic test

Witness hydro testing, air leak testing & flushing.

Witness after hydro testing , solution film testing (SFT)

Line check and re-instatement of piping system, punch list and final acceptance.

Preparing daily inspection report and manufacture data report (MDR.)

Company : IHI (Ishikawa jima-Harima Heavy Industries

Co., Ltd.) SHI – QATAR CO.W.L.L.

(Qatar Branch)

Position : QC Tank Inspector

Year : February 12, 2006 to April 01, 2007.

Location : RAS LAFFAN INDUSTRI CITY. (QATAR LIQUEFIED

GAS COMPANY LIMITED (II) / Project Qatar Gas II

Client : PT. QATAR GAS (QATAR.)

PROJECT:

QG II Onshore Project LNG Storage Facilies E P C of LNG Storage Tank

(Construct and erect 05, Storage Tank (Double-Tank / Shell outside Concrete

Page 13: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

and Shell inside Nickel 9%, Double Dome Roof. Roof outside Congrete and Roof

inside Plat Carbons, Deck Floating Roof Almunium.

DUTIES AND RESPONSIBILITIES:

SCOPE OF DUTY & ACTIVITIES INVOLVED

Supervises field engineering lay-out.

Assisting the Project Superintendent for the daily schedule of work.

Assisting the Project Superintendent for the proper distribution of manpower

in different areas.

Coordinate / discuss with the Project Engineer / Project Superintendent the

job priorities, progress of work, materials and equipment needed for the

execution of work.

Maintain an up to date drawing file on each job.

Continually check drawings, specifications, etc., on each job for discrepancies

and deficiencies and report the same to the Project Engineer or Project

Superintendent.

Engineer-in-charge in inspection of tank foundation.

Engineer-in-charge in tank identification mark.

Engineer-in-charge in hydrostatic testing.

Conduct material inspection to assure that they are free from visual defects

with mill certificates and heat numbers prior to fabrication and erection.

Inspect lay-out and edge preparation together with heat number transfer and

assure that the required dimensions are met as per approved drawings.

Assisting the QA/QC Inspector to conduct fit-up and dimensional inspection

both on fabricated and erected structural members.

Assisting the QA/QC Inspector to ensure quality control implementation before

inspection with client and class.

Assisting the QA/QC Inspector for the final documentation of all inspection

reports and certification.

Assisting the QA/QC Inspector in preparation of as-built drawing.

Company : TKK/SHI – QATAR CO, W.L.L.

(Qatar Branch)

Position : QC Tank Inspector

Year : January 05, 2005 – January 21, 2006

Location : Upstream and Compression Facilities

Ras Laffan, Qatar / Dolphin Project Onshore

Energy, Ras Gas (Qatar

Client : PT. DOLPHIN ENERGY (UK)

PROJECT:

Construct and erect 36 Storage Tanks (Cone Roof, Double-Deck Floating Roof

and Dome Roof) for Condensate / Fire Water / Naphtha, Cracker Bottom and

LPG / LNG

DUTIES AND RESPONSIBILITIES:

SCOPE OF DUTY & ACTIVITIES INVOLVED Supervises field engineering lay-out.

Assisting the Project Superintendent for the daily schedule of work.

Page 14: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

Assisting the Project Superintendent for the proper distribution of

manpower in different areas.

Coordinate / discuss with the Project Engineer / Project

Superintendent the job priorities, progress of work, materials and

equipment needed for the execution of work.

Check / monitor the daily progress report from different areas and

discuss with the Project Superintendent to set a schedule according

to priority.

Maintain an up to date drawing file on each job.

Continually check drawings, specifications, etc., on each job for

discrepancies and deficiencies and report the same to the Project

Engineer or Project Superintendent.

Conduct material inspection to assure that they are free from visual

defects with mill certificates and heat numbers prior to fabrication

and erection.

Inspect lay-out and edge preparation together with heat number

transfer and assure that the required dimensions are met as per

approved drawings.

Assisting the QA/QC Inspector to conduct fit-up and dimensional

inspection both on fabricated and erected structural members.

Do visual inspection of welds.

Assisting the QA/QC Inspector to ensure quality control

implementation before inspection with client and class.

Assisting the QA/QC Inspector for requesting and carry out

inspection with client and class.

Assisting the QA/QC Inspector for the implementation of NDT

program.

Assisting the QA/QC Inspector for the final documentation of all

inspection reports and certification.

Company : SHI – QATAR CO., W.L.L.

(Qatar Branch)

Position : Field Tank Engineer

Year : September 15, 2004 - October 25, 2005

Location : Qatar Petroleum Lab Project (QATAR)

Mesaieed State of Qatar.

Client : PT. QATAR PETROLEUM (QATAR)

PROJECT:

Construct and erect 19 Storage Tanks (Cone Roof, Deck Floating Roof and Dome

Roof) for Condensate / Fire Water / Naphtha, Cracker Bottom.

DUTIES AND RESPONSIBILITIES:

SCOPE OF DUTY & ACTIVITIES INVOLVED Engineer-in-charge in field engineering lay-out, preparation of tank

foundation and erection.

Assisting the QA/QC Personnel in conducting material inspection to

assure that they are free from visual defects with mill certificates

and heat number issued.

Assisting the Project Engineer both in field and office work especially

in documentation.

Assisting the Project Superintendent in planning to execute the job.

Page 15: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

Maintain an up to date drawing file on each job.

Assisting the Project Engineer in hydrostatic testing.

Supervises field engineering lay-out, preparation of tank foundation

and erection.

Assisting the Project Superintendent for the daily schedule of work

and for proper distribution of manpower in different areas.

Coordinate / discuss with the Project Engineer / Project

Superintendent the job priorities, progress of work, materials and

equipment required for the execution of work.

Check / monitor the daily progress report from different areas and

discuss with the Project Superintendent to set a schedule according

to priority.

Maintain an up to date drawing.

Continually check drawings, specifications, etc., on each for

discrepancies and deficiencies and report the same to the Project

Engineer or Project Superintendent.

Conduct material inspection to assure that they are free from visual

defects with mill certificates and heat numbers prior to fabrication

and erection.

In-charge in fabrication lay-out of 12 miscellaneous flat bottom tanks.

Assisting the Project Engineer in hydrostatic testing to check if the

foundation settled.

Company: Samsung Corporation Engineering and Construction Group

Position: Field Tank Engineer

Years : August 15, 2003 – August 29, 2004

Location: Additional 3-LPG Tank Project of Qatar Petroleum in

Mesaieed State of Qatar.

Client : PT. QATAR PETROLEUM (QATAR)

PROJECT:

Construct and erect 03 Storage Tank (Construct and erect 03Storage Tank

(Double-Tank / Shell outside Concrete and Shell inside Nickel 15%, DoubleDum-

Roof. Roof outside Congrete and Roof inside Plate Carbons, Deck Floating Roof

Aluminum.

DUTIES AND RESPONSIBILITIES:

SCOPE OF DUTY & ACTIVITIES INVOLVED Incoming material Inspection

Dimensional control of fabrication

(Cutting and rolling Plate) pipe and all Accessories of storage tank

Control all report fabrication.

Training of new welder test before WQT.

Welder performance Qualification

Test per approved WPS.

WQT for storage tank and prepare Welder ID and welder list.

Inspection of welding sequence, Distortion control prior to welding.

Witness and Prepared all Leak test,Vacum box test report

Monitoring welding activities and prepared joint number system.

Page 16: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

Dimensional check storage tank before welding (Plumb, Roundness,

Levelness, Paking and Banding) and fit – up Manhole and Nozzle prior

to welding.

Prepared Material traceability MAP

Prepared Welding MAP

Prepared RT MAP

Prepared thickness MAP

Prepared PMI MAP

Coordinate the performance the performance of NDT & PWHT works

in accordance with ITP, Project specification, Codes & Standard.

Verify that approved WPS is available; welder is qualified with the

process and AFC drawing.

Perform & Supervise performance of material receiving inspection.

Perform joint Fit-Up inspection & ensure dimensional check.

Check weld end preparation, tacking method, electrode used, pre-heat

requirement, inter-pass temperature & cleaning in accordance with

WPS.

Check welding parameter & welding consumables.

Perform final welding visual inspection in accordance with acceptance

criteria.

Coordinate weld repair work in accordance with the repair procedure.

Monitoring of weld rejection rate & NDT performance status.

Interpreted RT films & review PWHT charts.

Preparing document test package for Hydro test / Pneumatic test

Witness hydro testing, air leak testing & flushing.

Line check and re-instatement of piping system, punch list and final

acceptance.

Preparing daily inspection report and manufacture data report (MDR.

Company : PT. TIMAS SUPLINDO

Position : QC INSPECTOR (ALL NDT)

Year : December 10, 2002 to August 10, 2003

Project : Offshore Oil Field of Cnoocses BV. (Ypf Maxuses

Project.

Location : Offshore JAVA

Client : PT. CNOOCSES

DUTIES AND RESPONSIBILITIES:

SCOPE OF DUTY & ACTIVITIES INVOLVED Responsible and supervising plate form / adjacent weld head platform

fabrication and installed.

Responsible and supervising piping work and assuring done according

to drawing with test package limited.

Prepared test package after completion of piping installation and nde

piping.

Visual inspection of welding work and verification quality welded by

distructive and non-destructive.

Visual check of space, beveling and cleaning pipe (blowing).

Page 17: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

Ensuring the correct welding electrode was used.

Marking RT point shall be shoot with owner.

Line check / punh list with engineering and owner. Check welding

traceability record piping.

Check of piping / fitting material with mill certificate before issue to

fabrication and erection.

Prepared test package after completion of piping installation and NDE

work. Make daily welding record and report & marking RT point shall

be shoot.

Check of piping / fitting material with mill certificate before issue to

fabrication and erection.

Review and record inspection report as per job specification.

Visual check of space, beveling & cleaning before weld.

Ensuring the correct welding electrode was used.

Company : PT. ELNUSA PETRO TEKNIK

Position : QC INSPECTOR (ALL NDT)

Year : April 07, 2002 to September 28, 2002

Project/Location: Tambunan Bekasi

DUTIES AND RESPONSIBILITIES:

SCOPE OF DUTY & ACTIVITIES INVOLVED Oversee subcontractor piping activities including fabrication, erection

and review report document.

Controlling the correct welding electrodes was used.

Marking RT point shall be shoot.

Review and record inspection report as per job.

Conduct line check and punc list of piping test package with

engineering and owner.

Counduct line check and punch list wit owner.

Check pipe spools and pipe support shop fabrication.

Supervising Pipe spools and pipe support field installation.

Punch clear execution comment item,

Witness, hydro test, pneumatic test, flushing, blowing and post test

Monitoring pipe spools and pipe support field installation. Coating and

wrapping underground piping.

Punch list execution comment item,

Witness, hydro test, pneumatic test, flushing and blowing, post test,

reinstatement.

PT. Petra minas Engineering Pratama

Period of Service from : October 03, 2001 to April 03, 2002

Project & Location : on Maxus Southeast Sumatra Inc Main

Tenant Service

Classifying (Position) : QC INSPECTOR (ALL NDT)

Page 18: FAUZAN RUMZIxa.yimg.com/kq/groups/4286282/77305876/name/Fauza… ·  · 2011-05-18FAUZAN RUMZI PERSONAL DATA ... gas and Petrochemical regulation, Refinery Tank, Oil & Gas, LNG Tank,

DUTIES AND RESPONSIBILITIES:

SCOPE OF DUTY & ACTIVITIES INVOLVED

Responsible in internal and external punch list of piping test package

of following line with steam line, boiler feed water lines, cooling water

system, instrument air, process line and ECT.

Check of piping / fitting material with mill certificate before issue to

fabrication and erection.

Review and record inspection report as per job specification.

Visual check of space, beveling & cleaning before weld.

Ensuring the correct welding electrode was used.

Visual check of quality weld by destructive and non-destructive.

Responsible and supervision welder active.

Supervising of mechanical completion and reinstatement after

pressure test.

Monitoring spools fabrication and ensuring the sand blasting & primer

paint before pipe spools transfer to site.

Prepared test package after completion of piping installation and NDE

work.

Note: Original copy of certification and other supporting documents may be called for and

presented if and when require

I hereby certify that all statements in this data are true and correct to the best of my

knowledge and belief.

Best Regards,

Fauzan Rumzi, ST