failures and maintenance of foudations structureskps.fsv.cvut.cz/upload/files/foundation.pdf ·...
TRANSCRIPT
Failures and maintenance of foudations structures
Diversion of tower – craks in sill wall, head, cornice,
Castle Zleby
settlement of outside
part - pier – flushing
of foundation soil
Castle Valdštejn
settlement of
middle part –
flushing or
terrain
roughness
settlement of
right marginal
part –
flushing
settlement of
middle part –
flushing
flushing of
footing
bottom –
shear craks in
head and sill
of wall
Building in vacant space –
failure of an existing building
tensile and shear cracks
Settlement of part of structure
during building pipe tunnel settlement of the left part of building
due to the movement of soil below
foundation
cracks in the facade of buildings caused by defects in the subsoil
undermine of the gable wall
during foundation of
neighboring house
Romance structure – foundation masonry was realist as hand placed rockfill or stone masonry with clay binder, width 1,5 m till 2,5 m and
depth about 1,2 m Gothic structure – foundation was built from hand placed rockfill, wood grid placing on piles, masonry well, as waterproofing was used clay
(50 – 70 mm)
Renaissance and folowing period was used foundation from stone masonry with
lime mortar. For high depth was built masonry piers with masonry vaulting strip
From half of 19–th century was foudation realist from freestone, brick
masonry and concrete
From 20-th years of 20-th century was using for design foundation
structure method permissible stress of foundation soil
Pit foundation
Pier foundation
Historical development (evolutional)
Base strip:
a) stone quarry, h > 0.5 m
b) Concrete, h > 0.3 m
c) on compacted gravel bed (thick of
layers 0.15-0.2 m)
d) two-stage foot of plain concrete
e) Reinforced concrete foot
f) Base strip – wood grid, piles, stones
Non –
loadbearing
capacity
layer
Non –
loadbearing
capacity
layer
Historical foundation – difficult conditions
level of underground water
level of underground water
level of underground
water wooden
pile
wooden
grid
wooden
grid
wooden „grid“
wooden
pile
wooden
pile
logitudinal
beam
transversal
beam
Load bearing capacity soil Soil without load bearing capacity
Load bearing capacity soil
clay
direction of move
rock
moisture
rock
clay
sand
water level
Increased levels of water
Load bearing capacity soil
Less load bearing capacity soil
rock
Permeable
soil
Accumu
lation of
water
rubble
character of
deformation
deformation
deformation
clay
rock
road
water rain
original terrrain
compressibility
stlačitelnost
unsuitable soil
unsuitable soil
character of deformation
Typical cracks – dymanic load Typical cracks – load by nearby
blast
a) Desintegration of front face by oblique tension cracking (move in footing subsoil by oblique impermeable bed of
clay), b) subsidence of right marginal part (incorect drainage), c) subsidance of middle part (curvature shape of footing
bottom by transportation - traffic), d) subsidence of right marginal pier (built a new structure near-by the original
structure)
Meansure during design structure:
•Raft-foundation, pile foundation, mini
pile (root pile) foundation
•Underpinning foudations „original“
structure by mini pile (root pile)
•Using JET Grouting
•Choice of load-bearing system –
foundation
Building in vacant space
Cantilever span
Extension of foundation strip
parallel normal
extension´s
strip
extension
of strip
Original
structure
new
structure declination of structure
failures
of
structures
area of summation
of stresses
compressible subsoil
declination of new structure declination of
new structure
non-consolidated
cohesive subsoil
(clay)
area of
consolidated
subsoil
response of
original
structure
Cause of failures:
„small“ depth of foundation
(longtime compress of footing
subsoil, slushy of footing bottom,
freezing of footing bottom
Maintenance:
Deeping of footing bottom
backfill
clay soil
sand (S) or
gravel (G)
rock
level of underground water
Deepening of foundation with desitegrated foundation structure
Deepening of foundation
original level
deepening
excavation
new deepening foundation –
brick (concreting) in parts
concrete base
reinforce
by net
New deepening
foundation
base concrete reinforce
with net
hydraulic
press
deeped level
Upper
structure
1. phase 2. phase
concrete base
3. phase
concrete +reinfor.
Geological profile
(Geological cross-section)
chess-board process
dep
th
soil
original
found.
masonry structure
Steel beams - steel grid bolt
failure strip foundation
Static protection during deepening and extension of foundation –
during of all action of foundation
brace
brace
brace
brace
brace
struts
new part – brick,
concreting
• deepening of foundation by mini pile (root pile)
backfill
clay soil
rock
level of
underground
water
dep
th Cause of failures:
„small“ depth of foundation
(longtime compress of footing
subsoil, slushy of footing bottom,
freezing of footing bottom
Maintenance:
Deeping of footing bottom - mini
pile (root) pile
Secure of gable wall by mini pile – tension pile
soil
foundation of new internal structure to micropiles (mini pile)
microp
ile
1. level of old piles, 2. footbridge, 3. crown weir, 4.
bottom of the weir, 5. sand-gravel, 6. gravel, 7. slate
Geological profile
(Geological cross-section)
diaphragm wall
sheet pile wall
Working area Steel tie
anchor
Sand-gravel
muddy alluvium
loamy
slate
Secure of wall of excavation by mini pile
• Scheme implementation of jet grouting
backfill made land
clay soil
rock
level of
undergroun
d water
Cause of failures:
„small“ depth of foundation
(longtime compress of footing
subsoil, slushy of footing bottom,
freezing of footing bottom
Maintenance:
Deeping of footing bottom – JET
grouting
1. rotation boring
2. finish of boring
3. jetting of mixture
4. extracting of boring rod
Pile from mixture of cement and
soil
dep
th
soil
jetting
of
mixture
jetting of
mixture
cement mixture
cement
mixture
Geological profile
(Geological cross-section)
Buttons of excavation and support of
existing foundation by JET
GROUTING
Lower surface of
wall after demolition
silt sand
Cement grouting
clay
Chemical grouting
JET grouting
Grout hole
gravel
grain dimension in
Using of diffrent type of grouting
rati
o o
f w
eig
ht
Grout hole
Cause of failures:
Increased loads
Maintenance:
Extension of foundation
• examples of extension of foundations
sand or gravel
rock
level of
underground
water
backfill
Shear claw of
original
structure
additing
concrete
part
reinforce
steel
reinforce
steel
additing concrete part reinforce steel of
claw
ring reinforce
dep
th
soil
hole reinf
orce
ment
reinforce steel
of claw
Reinforcement
of new
foundation
Maitenance of
column
Ring reinforcement
Geological profile
(Geological cross-section)
concrete
• join adaptation of extension of foundation
clean
hacked
surface
Join with claw
Join with reinforce steel bar
Join with hacked surface
Join with reinforce net
loop
vertical
loop
claw
Reinfor
cement
net
Loop with hooks
Double loop
Nu
mb
er o
f cl
aw
Cause of failures: leaching of soil particles (fines)
Maintenance: Deeping of foundation structure
–JET grouting, mini pile (root
pile) grouitng of soil
• examples of grouting of soil
clay soil
rock
level of
undergroun
d water
sand or
gravel
made land, backfill
clay soil
rock
level of
underground
water
Cause of failures: leaching of soil particles (fines)
Maintenance: Deeping of foundation structure,
grouitng of soil
dep
th
soil
injecting the soil under the existing foundation
dep
th
soil
made land, backfill
Geological profile
(Geological cross-section)
Underpinning by bored piles Changes of foundation soil (footing subsoil)
Méně používané metody sanace základů staveb
Other using methods
Concreting
Steel beam
Original
foundation
bea
ring
soil
Non b
eari
ng
soil
New reinforced concret
strip foundation Wall
column
pier
Gravel-sand
compaction layer
Non
bearing soil
reinforced concrete
bored piles
original
foundation
Excavation – length
0,9 – 1,2 m
• podchycení stěny na nové základy
underpinning of loadbear wall by new founadtion
•oplášťování základových pasů
facing of foundation strip
concrete block
cement
mortar
steel beam
new foundation
strip
Original
foundation
var. for desintegration or little of bearing
capacity of wall structure
Desintegrated
part
additing
concrete
part;
hacked
surface
claw in original
structure resin
Desintegrated masonry and concrete of foundation must be mechanical removed
additing
concrete part
steel
pad
gap anticorrosive
protection
steel pad
Steel wedges
• spřažení základů deskou a skořepinou
connection of foundation by RC vaults or RC slab
Connection of foundation by reinforce concrete
vaults
Connection of foundation strip by
grid slab
Connection of foundation by
concrete slab
reinforcement in
anchor pocket
reinforce
concrete slab
reinforce
concrete slab ban
k
concrete concrete
•Dodatečné provádění zedních kleštin (sepnutí zdiva)
Additing wall tie (anchor)
crack
forces in tie
point of rotation
crack
forces in tie
settlement
point of rotation
weight of piers
Historical development of Charles Bridge
Foundation of bridge piers (documentation of 1900)
Staré Město Malá Strana
1432
1496
1784
1890
bridge partsdamagedduring thefloods
a...založení na kesonechb...kesonové věncec...původní založení
ab
c
a
b
•Schema založení mostních pilířů Karlova mostu
•Schem of foudation of bridge piers of Charles bridge
•Foundation of new bridge piers of Charles bridge after flood in 1892
•Zabezpečení základů mostních pilířů „kesonovou obezdívkou“
•Safety of foundations of bridge piers by „caisson facing“
1. sand and gravel, 2. coarse gravel,
3. intermediate layers, 4. slate
1st floor level floor
level of foundation base
Cathedral in Mexico City consolidated and unconsolidated soil
bottom of the lake, Pyramid
Stabilization of the settlement of the cathedral by the "extraction" of soil (shaft with radially arranged holes and
pipes)
Failures
insufficient load-bearing capacity in footing bottom (absence or wrong geological surveying of footing subsoil)
different type of footing subsoil (main different geotechnical property – bearing capacity, compressibility, water
infiltrations, consolidation, …)
changes of geotechnical, hydrological (changes of level of underground water, near-by terrain, new biulding
structures in neighbourhood)
improving the load carrying capacity of existing structural foundation to handle increased loads
changes of climatic conditions (exposing foundation, changing to near-by terrain, excavation, drying-out and frost
penetration of footing bottom),
bad (wrong) design of foundation structures (insufficiency dimenzion, design without dilatation, different depth of
foundation),
desintegration of materials (agents of deterioration: vegetation)
analyse of interaction between subsoil and structure
undermining
shaking
1. Extension of foundation
Higher resistance
Limited setting no sutaible (especially in less compressible soil)
Level of footing bottom
Shearing force – ensure interaction
2. Deeping and underpinning
Non bearing soil is replaced by better (less sompressible), reduce settlement
Foundation in freezing depth
Adaptation
Strat from the most loaded part
3. Underpinning
Load from alod founadtion is transfered to new foundation
(bored piles, jet grouting, mini (micro) piles)
4. Strengthening of disintegrated foudation
http://kps.fsv.cvut.cz/index.php?lmut=cz&part=vyuka&sub=pdre
Main important cause of failures
• insufficient load-bearing capacity in footing bottom (absence or wrong geological surveying of footing
subsoil)
• different type of footing subsoil (main different geotechnical property – bearing capacity, compressibility,
water infiltrations, consolidation, …)
• changes of geotechnical, hydrological (changes of level of underground water, near-by terrain, new biulding
structures in neighbourhood)
• improving the load carrying capacity of existing structural foundation to handle increased loads
• changes of climatic conditions (exposing foundation, changing to near-by terrain, excavation, drying-out and
frost penetration of footing bottom)
• bad (wrong) design of foundation structures (insufficiency dimenzion, design without dilatation, different
depth of foundation)
• desintegration of materials (agents of deterioration: vegetation)
• analyse of interaction between subsoil and structure
• undermining
• shaking
Rehabilitation (rebuilding) and maintenance of foudations
structures
Before design rehabilitation (renovation) and maintenance of foudations structures is necessary:
- Verification state of foundation structure
- Analysis cause of failures
- Check up (verify) geotechnical conditions
- Determinate real load of foundation
- Determinate real calculation model of load bearing system of structure (include foundation)
Possible rehabilitation (rebuilding) and maintenance:
- rehabilitation (rebuilding) foundation structure,
- modification of property of footing subsoil,
- rehabilitation (rebuilding) „top“ part of structure,
- combination of list (describe) possibility
Rehabilitation (rebuilding) of foundation:
- Increace of load bearing capacity of founadation
- Reduce settlement or different settlement
- Eliminate of failures
- Protection of foundation structure before temperature, changes of level of underground water,
- Protection of foundation structure before effects of near-by structures,
- Protection of foundation structure before desintegration of structure and materials.
Subsidence of right
marginal part
Subsidence of both
marginal parts
Subsidence of middle
State of stress of load bearing capacity wall
pressure trajectory
main pressure
tension trajectory
main tension (direction of
larger subsidence, lower
stiffness of support , etc. )
larger subsidence
(settlement)
Foudation of outside stair
Right
solution
Wrong
solution
Foudation of non bearing
wall on foudation strip
unrammed gravel fill
foundation
beam
fixed joint between outside
stair and foundation of
structure
•Zabezpečovací opatření při provádění sanace základů
•Securing of structure during maitenance of foundation
Load transfer on assitent
foundation
brace tie
Underpinning walls and
piers Reinforce
concrete
beam
Steel
beam
Supporting bearing wall
assitent foundation
Securing of middle piers during
maitenance of foundation
•Securing of bearing structure during deppening of
lower floor
•Horizontal waler of near houses by crossbeam
Start from
the most
loaded part
•Postup sanace skeletové konstrukce
Maintenance of frame structure
settlement of midle
column
tie tie
supporting of middle beam by help
(additing) beam
Coupling of column by diaphragm
craks in
beam
partly hanging out of middle column
red
uct
ion
of
load
on
mid
dle
fo
ot