evaluation of runway bearing capacity: in-situ ... · evaluation of runway bearing capacity:...
TRANSCRIPT
Evaluation of Runway Bearing Capacity: In-SituMeasurements and Laboratory Tests
A. Graziani1, F. Cardone1, E. Santagata2, S. Barbati2
1Dipartimento di Idraulica, Strade, Ambiente e ChimicaUniversità Politecnica elle Marche
2Dipartimento di Idraulica, Trasporti e Infrastrutture CiviliPolitecnico di Torino
Eighth International Conference on the Bearing Capacity of Roads,Railways, and Airfields.
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 1 / 35
Outline
1 BackgroundThe AirportProject outline
2 ConstructionMain PhasesQuality control
3 EvaluationPavement responseResidual life calculation
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 2 / 35
The Raffaello Sanzio AirportAeroporto delle Marche, Ancona.
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 4 / 35
The Raffaello Sanzio AirportAeroporto delle Marche, Ancona.
0
100000
200000
300000
400000
500000
600000
1984 1989 1994 1999 2004
YEAR
PASSENGERS
0
5000
10000
15000
20000
25000
OPERATIONS
OPERATIONS N
PASSENGERS N
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 5 / 35
The Raffaello Sanzio Airport
flexible pavement;rigid pavement (RWY heads);width: 45 m + shoulders (7.5 m);declared distances:Table 1. Basic runway physical characteristics _______________________________________________________________________
Runway TORA TODA TODA LDA Width Designation m m m m m _______________________________________________________________________
04 2962 2992 2992 2766.5 45 22 2962 3022 3022 2812 _______________________________________________________________________
ICAO Reference Code: 4D
2 PROJECT OUTLINE
The structural design for the full-depth reconstruction was based on the CBR method as de-scribed by Federal Aviation Administration AC 150/5320-6D (FAA, 2004). The design traffic fleet, over a 20 years pavement life, was converted to 1778 yearly departures of a Boeing 747-200 aircraft (Design Aircraft) with a Takeoff Weight of 368,000kg (810,000lb). Using routine geotechnical tests the subgrade soil was classified as a silty clay of variable compressibility (CL-CH), with a design CBR of 7 (obtained as the 85th percentile of the values coming from DCP tests results). A lime stabilization was adopted to improve subgrade strength, assuming a design CBR value of 20. A crushed aggregate subbase layer was placed over the stabilized sub-grade, underneath a Cement Treated Base course. Considering that the construction operations had to proceed as rapidly as possible, this intermediate granular layer was deemed necessary to separate two layers where pozzolanic reactions were (supposedly) developing in their peak phase.
The spreadsheet F806FAA.xls (FAA, 2005) was used for the calculations (Fig. 1). The final structure (Fig 1.b) was designed considering the locally available materials and construction techniques. The asphalt surfacing was further subdivided in a Stone Mastic Asphalt wearing layer (30mm), a binder layer (40mm) and a base layer (80mm). All asphalt mixtures were speci-fied according to the current European Norm (EN 13108), and the use of a modified asphalt was required. The Cement Treated Base course was a “low-stiffness mixture”, typically used in Ital-ian motorways, with an unconfined compression strength (UCS) between 2.5 and 4.5MPa.
The full-depth reconstruction project was completed in 23 days, during this period the run-way was used with a displaced threshold. The residual field length (1805m) allowed to safely manage operations of the B737 aircraft, as requested by Aerdorica. New non-precision instru-ment approach procedures were developed since the ILS glide slope was not available during the working period. Temporary horizontal signs were provided and a Precision Approach Path Indicator (PAPI) was installed to assure a more accurate approach to the touchdown zone.
The working area was divided in 2 zones (construction lots). In the “Green Zone” located 350m apart from the displaced threshold all the construction activities were carried out during the daylight, without disturbing the traffic flow. In the “Red Zone”, located 160m to 350m apart from the displaced threshold, the construction activities were carried out, from 11:30 pm to 6:00 am. During this period the runway was closed to avoid penetration of the obstacle limi-tation surfaces.
3 MATERIALS CHARACTERIZATION
3.1 General remarks
An extensive experimental program was carried out to achieve a careful characterization of ma-terial properties, particularly for the stabilized subgrade. The following tests were part of con-struction quality control: ! Dynamic Cone Penetrometer tests (DCP); ! Dynamic Plate Bearing tests (DPBT); ! Static Plate Load tests (SPT). Cores obtained from compacted asphalt layers were tested for composition and voids. In addi-tion a detailed laboratory characterization of the asphalt mixtures, including dynamic modulus estimation and fatigue performance, was performed using both laboratory compacted specimens and pavement cores.
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 6 / 35
Structural evaluation!"#$%&
'#$"%(#)*"%+)$,%)&
-)."%.,
/$%,0,1"
!"#$%&'#()*+,-.'/.)+'+01-&%22"!"#$%&'#()*+,-.'/.)+'+01-&%22"!"#$%&"'"(#)*+,
-#("./0'#1"%0/)23/&&"4"3/
! 5#6#''/6"&'"78/)9/33#)&%(6#&'6:'':6#);&/1"%0/)3%0<"':9"0#3/=
!"#$%"&'()*"+,-*.&-#"/"
!%/+&)$(" 0-'*(-/1)*)+,-*.&)*)
2"#3)4-"#'
!
"#"""!
$%&'()*)!+,-*)!
.!/"'0!
$%&'()*)!+,-*)!
.1/"'0!
2344-5)!
6(-&3,-(!0-*)(7-,!.!/8'0!
$9:1;"!
234<(-=)!
>?!@57,*A!
$9:1B"!
"#CD"!
C!
"#8E"!
E!
"#FG"!
2344-5)!
6(-&3,-(!0-*#!
.!/8'0!
$9:1;"!
"#F""!
H>I!
.!/C#8'0!
$)0)&*)=!
.!B;'0!
B!
"#BDF!
/!
"#CG"!
2344-5)
6(-&3,-(!0-*#!
.!8"'0!
$9:1;"!
!!
.!//'0!
!!
.!BG'0!
8!
B#"/"!
!!
.!B8#8'0!
!!
.!/E#8'0!
234<(-=)
>?!@57,*A!
$9:1B"!
;!
B#/;"!
!!
.!//#8'0!
!!
.!BF'0!
F!
B#8""!
!!
.!/"#"'0!
!!
.!B8'0!
234<(-=)!>?!@57,*A!
$9:1;!
G!
B#D8"!
.!E8'0!
$9:1;"!
!!
.!/C#"'0!
!!
.!B8'0!
.!C"'0!
$9:18"!
234<(-=)!
>?!@57,*A!
$9:1B"!
D!
/#B;"!
234<(-=)!
>?!@57,*A!
$9:1G!
!!
.!/C#"'0!
!!
.!B8'0!
.!B"'0!
$9:18"!
!!
.!/C#"'0!
B"!
/#E""!
!!
.!/"#"'0!
!!
.!B8'0!
.!E"'0!
$9:1;"!
234<(-=)!
>?!@57,*A!
$9:1B8!
BB!
/#8/"!
B/!
/#F;"!
/#;/8!
$%&'()*)!+,-*)
.!/"'0!
$%&'()*)!+,-*)!
.!/"'0!
:J6J.! K?LMJ9?L! :J6J.
2344-5)!
6(-&3,-(!0-*)(7-,!.!C8'0!
$9:1;"!
$%&5*(3'*7%&!
N%7&*! $%&5*(3'*7%&!
N%7&*!
C#"""
0)(*'+50)(*'+60)(*'+7 0)(*'+8
structurally weak area;inadequate pavement thickness;
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 7 / 35
Project Outline
Area A: 520mfull-depth pavementreconstruction;area NOT USABLE forTake-off/Landing;2.085 m of pavement stillavailable;after enforcement of all safetyrequirements (strip, RESA)residual field length allowsoperations up to the B737airplane;airport fully operative.
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 8 / 35
Project Outline
Area B: 280mreconstruction of damagedAsphalt Layers;SAMI interlayer to preventreflective cracking;works carried out night–timeclosures
Area C: 1425mResurfacing with SMA (3cminlay);works carried out night–timeclosures
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 9 / 35
Area A – Pavement designCross section
based on FAA AC 150/5320–6D (CBR-Empirical)Subgrade CBR = 7%Design aircraft: B747–200 (1778 TO/year)
First line of second page
Last line of second page
Stabilized section
5.5” Subbase layer (P-208)
22” Subbase (P-154) CBR = 20
11” Base layer (P-209)
5” Asphalt Surfacing (P-401)
19.5” Lime stabilization CBR = 20
6.5” CTB layer (P-304)
5” Asphalt Surfacing (P-401)
10cm (4”) Crushed Ag-gregate Subbase CBR =
40cm (16”) Lime stabilization CBR = 20
20cm (8”) Cement Treated Base
15cm (6”) (Modified) Asphalt Surfacing
a. F806FAA.xls Flexible Pavement Design
Standard section
b. Actual Pavement Design
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 10 / 35
Area A – Pavement designCross section
based on FAA AC 150/5320–6D (CBR-Empirical)Subgrade CBR = 7%Design aircraft: B747–200 (1778 TO/year)
First line of second page
Last line of second page
Stabilized section
5.5” Subbase layer (P-208)
22” Subbase (P-154) CBR = 20
11” Base layer (P-209)
5” Asphalt Surfacing (P-401)
19.5” Lime stabilization CBR = 20
6.5” CTB layer (P-304)
5” Asphalt Surfacing (P-401)
10cm (4”) Crushed Ag-gregate Subbase CBR =
40cm (16”) Lime stabilization CBR = 20
20cm (8”) Cement Treated Base
15cm (6”) (Modified) Asphalt Surfacing
a. F806FAA.xls Flexible Pavement Design
Standard section
b. Actual Pavement Design
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 10 / 35
Area A – Pavement designMaterials Specifications
non-standard (FAA) constructionstandard Italian materials and construction techniques
2 PROJECT OUTLINE
The structural design for the full-depth reconstruction was based on the CBR method, as de-scribed by the Federal Aviation Administration AC 150/5320-6D (FAA, 2004). The design traf-fic fleet (Tab. 2), was converted to 1778 yearly departures of a Boeing 747-200 aircraft (Design Aircraft) with a Takeoff Weight of 368,000kg (810,000lb). The spreadsheet F806FAA.xls (FAA 2005a) was used for calculations.
The final structure was designed considering locally available materials and construction techniques (Tab. 3). Lime stabilization was adopted to improve subgrade strength (3% hydrated lime). A crushed aggregate subbase was placed over the stabilized layer and below a Cement Treated Base (CTB) course. The CTB was a “low-stiffness” mixture, typically used in Italian motorways. Considering that construction had to proceed as rapidly as possible, the intermediate unbound granular layer was deemed necessary to separate two layers where pozzolanic reac-tions were (supposedly) developing in their peak phase. The asphalt surface course was further subdivided into a Stone Mastic Asphalt wearing layer (30mm), a binder layer (40mm) and a base layer (80mm). All asphalt mixtures were specified according to the current European Norm (EN 13108), and the use of a modified asphalt was required.
The full-depth reconstruction project was completed in 23 days, during this period the run-way was used with a displaced threshold. The residual field length (1805m) allowed the opera-tions of the B737 aircraft to be safely managed, as requested by Aerdorica. New non-precision instrument approach procedures were developed as the ILS glide slope was not available during the working period. Temporary horizontal signs were provided and a Precision Approach Path Indicator (PAPI) was installed to assure a more accurate approach to the touchdown zone.
The working area was divided in 2 zones (Figure 1). In the “Green Zone” located 350m from the displaced threshold all the construction activities were carried out during the daylight, with-out disturbing traffic flow. In the “Red Zone”, located 160m to 350m from the displaced thresh-old, construction activities were carried out from 11:30 pm to 6:00 am. During this period the runway was closed to avoid penetration of the obstacle limitation surfaces.
Table 2. Design traffic ___________________________________________________________________________________________
Aircraft Annual Takeoff Tire ACN Departures Weight Pressure Subgrade Category N kg kPa
A B C D
____________________________________________________________________________________________
B747-200 100 379,000 1410
52 58 71 93 B737-800 1400 79,000 1470
44 46 51 56
B757-200 300 100,250 1160
26 29 35 47 BAe 146-200 250 41,000 880
22 23 26 29
ATR-72 4000 23,000 550
11 12 14 15 ____________________________________________________________________________________________
Table 3. Summary of pavement design and specifications __________________________________________________________________________________________________________
Layer Thickness Aggregate Air Asphalt Strength* Modulus** Dmax Voids content mm mm % % MPa __________________________________________________________________________________________________________
AC Stone Mastic Asphalt 30 10 2÷6 6.5÷7.5 AC Binder Course 40 20 4÷6 4.5÷5.5 AC Base Course 80 31.5 4÷6 4.0÷5.0 Cement Treated Base 200 2.5!UCS!4.5 " 100 Crushed Aggr. Subbase 100 CBR " 40 " 60 Lime Stabilization 400 CBR " 30 " 50 Natural Subgrade (CL-CH) CBR = 7 __________________________________________________________________________________________________________
*UCS: Unconfined Compression Strength (MPa); CBR on 4 days soaked samples ** Measured in Static Plate Load Test, 1
st cycle (see Section 3.3)
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 11 / 35
Outline
1 BackgroundThe AirportProject outline
2 ConstructionMain PhasesQuality control
3 EvaluationPavement responseResidual life calculation
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 12 / 35
Construction scheduleAreas A and C
Aeroporto di Ancona-Falconara
Riqualifica pista di volo
Conto finale dei lavori
Relazione sull'andamento dei lavori
N. DESCRIPTION 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
Jul-06 Aug-06
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 -
AREA A LAVORI PRELIMINARI RUNWAY TEMPORARY CONFIGURATION
1 Temporary PAPI 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
2 Displacement of THR 22
3 Change of Runway Lights Configuration
4 Change of Runway Signs Configuration
5 CL Signals Removal
6 Installation af CL Lights bases and cables
7 Installation af CL Lights
8 Change of Runway Lights Configuration
9 Change of Runway Signs Configuration10 Original PAPI
11 Change of Runway Signs Configuration
12 Horizontal Signs: painting temporary signs
13 Horizontal Signs: obscuring with black paint
14 Horizontal Signs: obscuring with black plastic sheet
15 Horizontal Signs: painting new signs in Area A
16 Horizontal Signs: re-painting ereased signs
17 Horizontal Signs: erasing temporary18 Horizontal Signs: remouve covering sheets
19 Milling AC layers
20 Milling lean concrete layer
21 Milling existing sub-bse
22 Clay Stabilization of Subgrade
23 Sub-base construction
24 Cement treated course construction
25 AC base layer construction
26 AC binder layer construction27 SMA wearing course construction
AREA C (night time)
36 Milling37 SMA wearing course construction
PAPI electrical testing
PAPI test flight by ENAV
Works suspended:i
wait for AIP Supplemet diffusion
1st P
hase b
egin
s
Diagramma di Gantt Allegato 1 -1/4
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 13 / 35
Construction scheduleAreas A and C
Aeroporto di Ancona-Falconara
Riqualifica pista di volo
Conto finale dei lavori
Relazione sull'andamento dei lavori
N. DESCRIPTION
AREA A
1 Temporary PAPI
2 Displacement of THR 22
3 Change of Runway Lights Configuration
4 Change of Runway Signs Configuration
5 CL Signals Removal
6 Installation af CL Lights bases and cables
7 Installation af CL Lights
8 Change of Runway Lights Configuration
9 Change of Runway Signs Configuration10 Original PAPI
11 Change of Runway Signs Configuration
12 Horizontal Signs: painting temporary signs
13 Horizontal Signs: obscuring with black paint
14 Horizontal Signs: obscuring with black plastic sheet
15 Horizontal Signs: painting new signs in Area A
16 Horizontal Signs: re-painting ereased signs
17 Horizontal Signs: erasing temporary18 Horizontal Signs: remouve covering sheets
19 Milling AC layers
20 Milling lean concrete layer
21 Milling existing sub-bse
22 Clay Stabilization of Subgrade
23 Sub-base construction
24 Cement treated course construction
25 AC base layer construction
26 AC binder layer construction27 SMA wearing course construction
AREA C (night time)
36 Milling37 SMA wearing course construction
PAPI electrical testing
PAPI test flight by ENAV
Works suspended:i
wait for AIP Supplemet diffusion
Temporary configuration OPERATIVE
1st P
hase b
egin
s
2nd P
hase b
egin
s
29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45
Aug-06 Sep-06
28 N 29 N 30 N 31 N 1 N 2 3 4 N 5 N 6 N 7 N 8 9 10 11 N 12 N 13 N
LAVORI PRELIMINARI RUNWAY TEMPORARY CONFIGURATION
1
1
1
1
1 1 1 1 1
1
1
1
1
1 1 1 1 1
1 1 1 1 1
1 1 1 1 1
1 1 1 1 1 1
1 1 1
1 1 1
1 1 1 1
1 1
1 1 1 1 1 1 11 1 1 1 1 1 1
Temporary configuration OPERATIVE
2nd P
hase b
egin
s
Diagramma di Gantt Allegato 1 -2/4
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 13 / 35
Construction scheduleAreas A and C
Aeroporto di Ancona-Falconara
Riqualifica pista di volo
Conto finale dei lavori
Relazione sull'andamento dei lavori
N. DESCRIPTION
AREA A
1 Temporary PAPI
2 Displacement of THR 22
3 Change of Runway Lights Configuration
4 Change of Runway Signs Configuration
5 CL Signals Removal
6 Installation af CL Lights bases and cables
7 Installation af CL Lights
8 Change of Runway Lights Configuration
9 Change of Runway Signs Configuration10 Original PAPI
11 Change of Runway Signs Configuration
12 Horizontal Signs: painting temporary signs
13 Horizontal Signs: obscuring with black paint
14 Horizontal Signs: obscuring with black plastic sheet
15 Horizontal Signs: painting new signs in Area A
16 Horizontal Signs: re-painting ereased signs
17 Horizontal Signs: erasing temporary18 Horizontal Signs: remouve covering sheets
19 Milling AC layers
20 Milling lean concrete layer
21 Milling existing sub-bse
22 Clay Stabilization of Subgrade
23 Sub-base construction
24 Cement treated course construction
25 AC base layer construction
26 AC binder layer construction27 SMA wearing course construction
AREA C (night time)
36 Milling37 SMA wearing course construction
PAPI electrical testing
PAPI test flight by ENAV
Works suspended:i
wait for AIP Supplemet diffusion
Temporary configuration OPERATIVE Permanente Configuration Restored
1st P
hase b
egin
s
2nd P
hase b
egin
s
46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62
Sep-06
14 N 15 N 16 17 N 18 N 19 N 20 N 21 N 22 23 24 25 26 27 N 28 N 29 30
RUNWAY TEMPORARY CONFIGURATION
1 1 1 1 1 1
1
11
1 1
1
11
1 11 1
1 1 1 11 1 1 1
Permanente Configuration Restored
Diagramma di Gantt Allegato 1 -3/4
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 13 / 35
Day one. . .
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 14 / 35
Lime stabilizationArea A
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 15 / 35
Meanwhile, during the nights. . .Area C
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 16 / 35
Sub-base and CTB constructionArea A
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 17 / 35
HMA constructionArea A
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 18 / 35
Quality control programsublots
stabilized subgrade� Dynamic Cone Penetrometer (DCP), Dynamic Plate Bearing (DPBT);
granular sub-base� Static Plate Load (SPL), DPBT
CTB course� Static Plate Load (SPL)
HMA courses� Volumetric properties, Stiffness, Fatigue
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 19 / 35
DCP Tests
36-48h after mixing;CBR within specs (will improve);thickness deficiency.
data will be used to help backcalculation.
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 20 / 35
Plate load testsStatic and Dynamic
subgrade and sub-base exhibit similar stiffness;CTB has higher stiffness (will improve);
data will be used to help backcalculation.
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 21 / 35
HMA composition and volumetrics
High Air Voids content;
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 22 / 35
HMA StiffnessUniaxial Cyclic Compression tests
Master Curve @20°C
1.0E+03
1.0E+04
1.0E+05
1.0E-03 1.0E-02 1.0E-01 1.0E+00 1.0E+01 1.0E+02 1.0E+03 1.0E+04 1.0E+05
Reduced Frequency (Hz)
Sti
ffn
es
s |
E*|
(M
Pa
)
Laboratory compacted specimens
Base course cores
useful data to help backcalculation. . . ;. . . and frequency/temperature corrections;
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 23 / 35
HMA fatigue4–Point Bending test
Figure 2. Master curve of Stiffness Modulus.
Figure 3. Experimental Vs literature fatigue lines (for EA=5000MPa)
4 STRUCTURAL RESPONSE
4.1 General Remarks
The structural response of the “as-built” pavement was evaluated using an Heavy-Falling Weight Deflectometer. Tests were carried out with a 30cm loading plate, at a nominal vertical force of 160kN. Deflections were collected using a 9-sensor configuration, with a constant spac-ing of 300mm. The HWD survey, carried out 72 days after construction end, comprised a total of 42 measurement points, positioned on 4 parallel alignments (±3 and ± 6m offsets from the Center Line). The pavement temperature was measured at three different depths and a mean value of 8°C was calculated.
The shape of the measured deflection basins were initially examined and 3 homogeneous sec-tions were found, closely matching the 3 construction lots. The back-calculation analysis was performed with the linear-elastic based program BACKFAA (FAA 2006), using the 85%-reliability deflection profiles of each homogeneous section. The asphalt stiffness modulus were referred to a reference temperature of 20°C using the stiffness-temperature relationship obtained in the laboratory, in particular the 20Hz isochrone curve was used (Eq. 3 & Tab. 6).
not only “fatigue”. . . still very good performance;modified asphalt does his job.
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 24 / 35
Outline
1 BackgroundThe AirportProject outline
2 ConstructionMain PhasesQuality control
3 EvaluationPavement responseResidual life calculation
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 25 / 35
HWD testsGeneral data
72 days after construction (november 2006);30 cm plate, 9 sensors configuration;160 kN load;temperature 8◦C;42 test points.
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 26 / 35
HWD testsHomogeneous section
0
100
200
300
400
500
600
700
800
0 300 600 900 1200 1500 1800 2100 2400
Sensor offset (mm)
De
fle
cti
on
s (
mm
)
Sublot G1
Sublot G2
Sublot R
3 homogeneous sections, matching construction sub-lots;
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 27 / 35
HWD testsBackcalculation – BACKFAA
4 layers;stiffness of stabilized subgrade is underestimatedstiffness of untreated subgrade is overestimated;
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 28 / 35
HWD testsSurface Modulus
0
300
600
900
1200
1500
1800
2100
2400
0 300 600 900 1200 1500 1800
Surface Modulus (MPa)
Se
ns
or
off
se
t (m
m)
Sublot G1
Sublot G2
Sublot R
surface modulus increases with depth;subgrade stiffness increases with depth;subgrade sub-layering is necessary.
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 29 / 35
HWD testsBackcalculation – BACKFAA
stiffness matches quality control data;poor quality CTB in sub-lot Rno “flexural behaviour” can be expected.
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 30 / 35
Analytical approachdesign section: sub-lot R4 design seasons:
5.2 FAA empirical method
The actual section was converted into an equivalent “standard” FAA section using appropriate equivalency factors. A total thickness of 90mm (32in) was determined for the equivalent section and the B747 aircraft design curves were used to estimate the bearing capacity. The key parame-ter of the evaluation procedure was the subgrade CBR value. The DCP results (Tab. 4) indicated an average CBR of 6 and a design value as low as 4 (85% percentile). As a consequence, a bear-ing capacity of 172,000kg (380,000lb) was estimated. It was an exceedingly low value if com-pared with the MTOW of the design aircraft. This mainly derived from the fact that the pave-ment was built using materials that differed, somewhat considerably, from the FAA standard.
5.3 Analytical-empirical approach
An elastic multi-layered model was used to calculate stresses and strains produced by the design traffic loads. These were then compared to the correspondent “critical values” to compute pavement damage. Asphalt concrete fatigue cracking and subgrade rutting criteria were consid-ered. Damage calculations were performed following the procedure described by Monismith (Monismith et al. 1987). With this approach it was possible to directly take into account the lat-eral traffic wander.
5.3.1 Pavement design temperature and traffic Using a 30 years database of temperature data, 4 design periods were selected (Tab. 10). For each season two different design air temperatures were determined (USACE, 2001), respec-tively for the analysis of the vertical strain at the top of subgrade (!v,SG) and the horizontal ten-sile strain at the bottom of asphalt concrete surface (!h,A). The corresponding design pavement temperatures were obtained with the relationship developed by Witczak (Witczak 1972).
The design traffic previously used for design (Tab. 2) was considered and departures were distributed between the four design periods according to the actual airport schedule. The traffic load frequency is normally assumed at 10Hz for runways and 2Hz for taxiways. At the airport, because of the absence of a parallel taxiway, aircrafts normally use the runway to taxi from/to the apron, thus a “midway” design frequency of 5Hz, was selected. According to HoSang (Ho-Sang 1978), the lateral wander was characterized with a standard deviation of 2,4m.
5.3.2 Pavement structures and material properties As previously noted, the weakest pavement structure was selected for evaluation (Tab. 9). For each design pavement temperature, asphalt concrete design stiffness values were calculated cor-recting the back-calculated stiffness for frequency and temperature (Tab. 10). The correction factors were determined using the same stiffness-temperature relationship previously used to re-fer stiffness values to the reference temperature (20Hz isochrone). A total of 8 structures were considered in the analysis.
Transfer functions adopted by the FAA were used to compute the allowable number of strain repetitions for asphalt concrete (NA) and subgrade (NSG) failure criteria (FAA 2005b).
Table 10. Design periods characterization ____________________________________________________________________________________
Design Period AC Design Modulus Percent of !v,SG analysis !h,A analysis total traffic MPa MPa % ____________________________________________________________________________________
1 June, July, August & September 2263 3005 45 2 May & October 3841 4653 15 3 March, April & November 5591 6340 20 4 December, January & February 7101 7721 20 ____________________________________________________________________________________
traffic: same as in design;� load frequency: 5Hz; lateral wander: 2.4 m
cumulative damage calculation (Miner’s rule) for each airplane:
ni =�
k
ni,k
Ni,k
� ni = actual number of strain repetitions of magnitude �i,k =;� Ni = corresponding number of allowable repetitions, computed using the
given transfer functions.
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 31 / 35
Cumulative damageAsphalt fatigue
5.3.3 Structural analysis and damage computations A linear-elastic multi-layer computer program (BISAR) was used for the (forward) calculation of stresses and strains. For each landing gear the maximum strain locations were initially deter-mined and a critical cross section identified. Along this section the strain distribution was com-puted using a total of 81 points with a 0.25m spacing. At each point, the damage produced by each single aircraft was computed using Miner’s accumulation law (Monismith et al. 1987).
The damage calculations were repeated for all the design conditions described above and the results were summed to obtain the damage produced by each single aircraft. The cumulative damage was then calculated summing the effects of all the aircrafts (Fig. 4). Maximum values of 0.165 and 0.002 were found, respectively for the asphalt and subgrade strain criteria.
Cumulative damage values are extremely low and fatigue in the asphalt layer is the critical condition, yielding a residual life of 121 years. This result is mainly a consequence of the direct evaluation of aircraft wander. In addition, a major contribution in limiting strain values can be credited to the stiffness properties of the modified asphalt layers obtained using HWD and labo-ratory testing.
Figure 4. Cumulative damage for asphalt strain criterion
6 CONCLUSION
The paper presents a case history regarding the structural evaluation of a runway pavement. The project involved the structural rehabilitation of a 520m long asphalt concrete section through full-depth reconstruction.
A careful characterization of the pavement materials was achieved through an extensive ex-perimental program. Static and dynamic plate tests showed that the lime stabilized soil and the unbound granular subbase had similar stiffness, while a higher figure could be estimated for the cement treated base. Moreover, the combined use of DCP and plate tests allowed to identify the depth of the stabilized layer and define a reference stiffness range for the interpretation of de-flection tests.
The properties of the asphalt concrete layers were measured both on cores and laboratory compacted specimens. In particular, stiffness characteristics have been assessed using cyclic uniaxial compression tests. Even if laboratory compacted specimens showed somewhat higher stiffness values than cored samples, similar rheological behavior could be predicted and a single master curve was used. In addition 4 point bending tests performed in controlled stress condi-tion showed a good fatigue performance of the mixtures.
Data from in situ and laboratory tests was used to assist the back-calculation of pavement de-flections. This was of invaluable importance in identifying a consistent representation of the
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 32 / 35
Cumulative damageSubgrade Strain
Cumulative Damage - Subgrade vertical strain
0.0E+00
5.0E-02
1.0E-01
1.5E-01
2.0E-01
2.5E-01
0.00 2.00 4.00 6.00 8.00 10.00
Distance from center line
Da
ma
ge
TOTAL
747-200-f
747-200-r
737-800
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 33 / 35
Summary
keys to obey the tight construction schedule:� realistic specifications (“ad-hoc” specs);� “on-line” quality control;� close coordination between “pavement team” and the Operative personnel.
integration between NDT and Destructive tests (quality control);
use of polymer modified binder:� requires the Mastrer Curve to be measured;� enhance fatigue life
analytical evaluation, necessary when using non–standard section andnon–standard materials.
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 34 / 35
Thank you!
Questions?
Graziani, Cardone, Santagata, Barbati (CIRS) Evaluation of Runway Bearing Capacity BCR2A Conference, 6/29–7/2, 2009 35 / 35