estimating & costing

Upload: srinath-bonakurthi

Post on 19-Feb-2018

299 views

Category:

Documents


3 download

TRANSCRIPT

  • 7/23/2019 Estimating & Costing

    1/83

    Structure

    1.0 Introduction

    1.1 Definition

    1.2 Need for estimation and costing

    Learning Objecyives

    After studing this unit, student will be able to

    Have an idea of the introduction to estimating and costing.

    1.0 Introduction

    In the civil engineering field, the construction activity contains the

    following three steps.

    1. Plans : Preparation of drawings plan, section, elevation, with full

    dimension and detailed, specifications meeting the requirements of the proposed

    structure.2. Estimation : Preparation of an estimate is for arriving the cost of

    the structure to verify the available funds or to procure the required funds for

    completion of the proposed structure.

    3. Execution (construction) : It is a grounding the proposed structure,

    for construction as per the provision contained in drawings and estimation..

    Introduction

    1UNIT

  • 7/23/2019 Estimating & Costing

    2/83

    Construction Technology152

    The plans contains size of room and dimensions of the work and the estimate

    contains the quantity and quality aspects of the structure.

    1.1 Definition

    Estimation and costing there are two basic points involved in

    construction of structures are :

    1. Quantity : The quantity aspects is with reference to the measurement

    in the drawings (plan, elevation, section)

    2. Quality :The quality aspects is with reference to the specifications,

    i.e properties of materials, workmanship etc.

    Note : The estimation and costing of any structure is defined as the

    process of determination of quantities of items of work, and its cost forcompletion.

    2. Estimate of a project is therefore, a forecast of its probable cost.

    1.2 Need for Estimation and Costing

    The object of preparing the estimate for any civil engineering structure is

    1. To know the quantities of various items of work, a material and

    labour and their source of identification.

    2. To decide whether the proposal can match the available funds to

    complete the structure.

    3. To obtain the administrative and technical sanction of estimate

    from the competent authorities to release the funds for construction.

    4. To invite tenders or quotations based on the estimate quantities for

    entrust of works to the execution.

    Short Answer Type Questions

    1. What is meant by Estimating and Costing ?

    2. State need for Estimation and Costing.

  • 7/23/2019 Estimating & Costing

    3/83

    Structure

    2.0 Introduction

    2.1 Units of measurements

    2.2 Rules For Measurement

    2.3 Different methods of tasking out quantities

    Learning Objectives

    After the studying this unit student will be able to

    To measure various quantities as per rules.

    2.0 Introduction

    The units of differents works depends on their nature, size and shape..In general, the units of different items of works are based on the followingprinciple.

    1. Massive or volumetric items of work such as earth work, conceretefor foundations, R.R Masonry , Brick Masonry etc. The measurements oflength, breadth , height or depth shall be taken to compute the volume or cubicalcontents.

    2. Shallow, thin and surface work shall be taken in square unit or inarea. The measurements of length and breadth or height shall be taken tocompute the area, Ex. Plastering, white washing etc.

    Measurement of Materialsand Works

    2UNIT

  • 7/23/2019 Estimating & Costing

    4/83

    Construction Technology154

    3. Long and Thin work shall be taken in linear or running units and

    linear measurement shall, be taken. Ex : Fencing, Rainwater pipes,

    ornamental borders etc.

    4. Single units of work are expressed in numbers. Ex. Doors, Windows,

    Rafters, Trusses etc.

    2.1 Units of measurement for various items of CivilEngineering Works

    Sl.No

    1.

    2.

    3.

    4.

    5.

    Unit of

    payment

    10.00cum

    1.00cum

    1.00rmt

    10.00cum

    10.00cum

    1.00cum

    1.00cum

    1.00cum

    1.00cum

    Particulars of items

    (a) Earth work excavation in all

    types of soils except rock re-

    quiring blastering.

    (b) Earth work excavation in

    the soils hard rock requirng

    blastering.

    (c) Excavation of pipe line

    through of specified width and

    depth inall types of soils

    (d) Earthwork for road for-

    mation ,bund formation etc.

    cutting , embankment.(e) Refilling of foundations ,

    basements, pipe lines, trenches

    with excavated soils.

    Plain cement concrete for

    foundation.

    R.R.masonry or brick ma-

    sonry for foundation base-

    ment, super strucrture, parapet

    wall etc.

    Filling the basement with

    sand.

    (a) RCC 1:2: 4 with normal

    reinforcement for plinth beam ,

    columns, lintels, verandah

    beam- T beam etc.

    Units of measure-

    ments

    10.00cum

    1.00cum

    1.00 rmt

    10.00cum

    10.00cum

    1.00cum

    1.00cum

    1.00cum

    1.00cum

  • 7/23/2019 Estimating & Costing

    5/83

    Paper - II Estimating and Costing 155

    10.00sqm

    10.00sqm

    10.00sq m.

    1.00Rmt

    1.00No

    1.00No

    1.00Rmt

    1.00Rmt

    kg/unit

    1.00cum

    1.00cum

    1.00sqm

    1.00cum

    6.

    7.

    8.

    9.

    10

    11.

    12.

    13.

    14.

    15.

    (b) R.C.C 1: 2: 4 for slabs of

    specified thickness .Plastering pointing, flooring,

    weather proof coarse, white

    washing, colour washing, paint-

    ing.

    Roofing with A.C sheets, tiled

    roofing, Kurnool trerrace, Ma-

    dras terrace etc.

    D.P.C specified width and thick-

    ness

    Wooden and steel trusses

    Doors, windows, ventilators.

    Ornamentel border of speci-

    fied width and thickness.

    R.C.C pipes, A.C pipes GI or

    C.I pipes, stone ware pipes

    etc.

    Steel reinforcement in R.C.C.

    Rough stone pitching revet-

    ment and soiling of specified

    thickness.

    (a) Roads works : Metal col-

    lections , gravel collections,

    solving stones, pitching any

    stones, revetment stones etc.

    (b) Road works : Spreadingmetal gravel and consolidation

    with roller of specified thick-

    ness.

    (c) Cement concrete pay-

    ments of specified thickness.

    10.00sqm

    1.0.00sqm1.00sqm

    10.00sq m.

    1.00Rmt

    1.00No

    1.00 No

    1.00Rmt

    1.00Rmt

    Kg/unit

    1.00cum

    1.00cum

    10.00sqm

    10.00cum

  • 7/23/2019 Estimating & Costing

    6/83

    Construction Technology156

    2.2 Rules For Measurement

    Measurement of works occupies a very important place in the planningand execution of any work or project, from the time of the first estimate are

    made until the completion and settlement of payments. The methods followed

    for the measurement are not uiform and the practices or prevalent differ

    considerably in between the states. Even in the same state different departments

    follow different methods. For convernience a uniform method should be followed

    throughout the country. The uniform methods of measurement to be followed

    which is applicable to the preparation of the estimates and bill of quantities

    and to the side measurement of completed works have been described below.

    General Rules

    1. Measuremet shall be item wise for the finished items of work and the description of each items shall be held to inculde materials, transport,

    labour, fabrication, hoisting, tools and plants, over hands and other

    incidental charges for finishing the work to the required shape, size,

    design and specifications.

    2. In booking dimensions the order shall be in the sequence of length,

    breadth and height or depth or thickness.

    3. All works shallbe measured not subject to following tolerances unless

    otherwise stated.

    (a) Dimensions shall be measured to the nearest 0.01 meter i.e 1cm(1/ 211).

    (b) Areas shall eb measured to the nearest 0.01 sq.m (0.1 sqft).

    (c) Cubic contents shall be worked up to the nearest 0.01 cum(0.1cuft)

    4. Same type of work under different condition and nature shall be

    measured separately under separate items.

    5. The bill of quantities shall fully describe the materials proportions

    and work-manships and accurately represent the work to be executed.

    Work which by its nature cannot be accurately taken off or which

    requires site measuremets shall be described as provisional.

    6. In case of structureal concrete, brick work or stone masonry, the

    work under the following categories shall be measured separately

    and the heights shall be described.

    (a) From first floor level

  • 7/23/2019 Estimating & Costing

    7/83

    Paper - II Estimating and Costing 157

    (b) From plinth level to first floor level.

    (c) From first level to second floor level and so on.

    The parapet shall be measured with the corresponding items of the

    story next below.

    Principle of units :The units of different works depend on their nature,

    size and shape. In general the units of different item of work are based on the

    following principle.

    (i) Mass, voluminious and thick works shall be taken in cabic unit or

    volumne. The measurement of length, breadth, and height or depth shall be

    taken to compute the volume cubic contents(cum).

    (ii) Shallow, thin and surface work shall be taken in separate units orin area. The measurement of length and breadth or height shall be taken to

    compute the area (sq.m).

    (iii) Long and thin work shall be taken in linear or running unit and

    linear measurement shall be taken(running meter).

    (iv) Piece work, job work etc taken in number

    2.3 Different methods of taking out quantities

    The items of work like earth work in excavation in foundation, foundation

    concrete stone masonry in foundation and basement, stone or brick masonry in

    super stucrture may by estimated bu either of the following methods.1. Long wall and short wall method (or) General method

    2. Centre line method

    2.3.1 Long wall and short wall method

    In this method measure or find out the external lengths of walls running

    in the direction generally the long walls out-to-out and the internal length of

    walls running in the transverse direction in-to-in i.e. of cross or short wall in-

    to-in and calculate quantities multiplying the length by the breadth and height of

    wall. The same rule applicable to the excavation in foundation, to concrete in

    foundaiuon and to masonry.

    The simple mehtod is to take the long walls of short or erros walls

    separately and to find out the centre to centre lengths of long wall anf short

    walls from the plan. For symmetrical footing on either sides, the centre line

    remians same for suepr structure and for foundation and plinth.

  • 7/23/2019 Estimating & Costing

    8/83

    Construction Technology158

    For long walls add to the center length one breadth of wall, which

    gives the length of the wall out-to-out ,multiplying this length by the breadth and

    height and get the quantities,. Thus for finding the quantities of earth work inexcavation, for the length of trench out-to-out add to the centre length one

    breadth of foundaiton. Adopt the same process for foudation conceret and for

    eacth footing. It should be noted that each footing is to be taken separately and

    the breadth of the particular footing is to be added to the centre length.

    Long wall length out-to-out = centre to centre length + half breadth on

    one side + half breadth on the other side = centre to centre length + one breadth.

    For short or cross walls sub tract ( instead of adding) from the centre

    length one breadth of wall, which gives the length in-to-in, and repeat the same

    process as for the long walls, subtracting one breadth instead of adding.

    Short wall length in-to-in= Centre to centre length - one breadth.

    That is, in case of long wall add one breadth and in case of short wall

    substract one breadth from the centre length to get the corresponding lengths.

    It will be noticed that by taking dimensions in this ways, the long walls

    are gradually decreasing in length from foundation to superstructure, while the

    short walls are increasing in length.

    This method is simple and accurate and there is no chance of any mistake.

    This method may be named as long wall and short wall method, or general

    method.

    2.3.2 Centre line method

    In this method known as centre line method. This method is easy and

    quick in calculations. In this method sum total length of centre lines of all walls,

    long and short has to be found out. This method is well suitable for walls of

    similar cross sections. In this method the total centre line multiplied by breadth

    and depth of concerned item gives the total quantity of each item. In this method,

    the length will remain same for excavation in foundation for concrete in foundation,

    for all footings and for super structure (with slight difference where there are

    cross walls or number of junctions). It requires special attention and consideration

    at the junctions, meeting points of partition or cross walls, etc.

    For rectangular, circular polygonal (hexagonal, octagonal etc) building

    having no inter or cross walls, this method is quite simple. For each junction half

    breadth of the respective items or footings is to be deducted from the total

    centre length. Thus in the case of a building with one partition wall or cross wall

    having two junctions, for earthwork in foundation trench and foundation concrete

    deduct one breadth of trench or concrete from the total centre length (half breadth

  • 7/23/2019 Estimating & Costing

    9/83

    Paper - II Estimating and Costing 159

    for one junction and the breadth ( 2 x 1/2 = one) for two junctions. For footings,

    similarly deduct one breadth of footing for two junctions from the total centre

    length and so on. If two walls come from opposite directions and meet a wall atthe same point, than there will be two junctions.

    In the case of a building having different type of walls, suppose the other

    (main) walls are of A type and inter cross walls are of B type, then all A type

    walls shall be taken jointly first , and then all B type walls should be taken

    together separately. In such cases no deductions of any kind need be made for

    A type walls, but when B type walls are taken, for each junction deducting of

    half breadth of A type wall (main wall) shall have to be made from the total

    centre length of walls.

    It may be noted that at corners of the building where two walls are

    meeting no substraction or addition is required.

    Note : Student should practice method I first and when they have become

    sufficiently acquainted with method I, then only they should take up the method

    II.

    Short Answer Type Questions

    1. Write the unit of measurements. Earthwork, P.C.C, R.C.C, Masonary,

    Plastering, Flooring, Fencing, Ornamental border, Door, Windows,

    Trusses etc.

    2. Write general rules for measurement.

    3. Write different methods of taking out quantities and describe.

  • 7/23/2019 Estimating & Costing

    10/83

    Construction Technology160

    Structure

    3.0 Introduction

    3.1 Detailed estimate

    3.2 Preliminary or approximate estimate

    3.3 Problems in preliminary estimate

    Learning Objectives

    After studying this unit student will be able to

    Understand the definition of detailed estimate, stages of preparation

    of estimate, Data required for an estimate and types of estimate.

    3.0 Introduction

    An estimate is a probable cost of a work. It is usually prepared before

    the construction is taken up. The primary object of an estimate is to know

    beforehand the cost of the work. The actual cost of the work is known after thecompletion of the work. If the estimate is prepared carefully and correctly there

    will not be much difference in the estimated cost and actual cost. The estimator

    should be fully acquainted with the methods of construction, skilled and

    experienced for accurate estimating.

    3UNIT

    Types of Estimates

  • 7/23/2019 Estimating & Costing

    11/83

    161Paper - II Estimating and Costing

    3.1 Detailed estimate

    The estimate may be approximate or preliminary estimate or accurateestimate. In approximate estimate the approximate cost of the work is estimated.

    In the accurate estimate the details of various items are taken and calculated.

    3.1.1 Definition

    The estimate prepared by dividing the work into different items, taking

    detailed measurements of each item of work and calculating their quantities is

    known as detailed estimate.

    3.1.2. Stages of preparation

    To prepare the complete estimation of the project, besides the estimated

    cost of different main items of work, The cost of preliminary works and surveying,cost of land and its acquisition, cost of leveling and preparation of ground and

    the cost of external services are to be provided. Provision of supervision charges

    and contractors profit are to be provided in the estimate.

    Data required for preparing an estimate : To prepare an estimate

    for a work the following data are necessary.

    Drawings : The detailed drawings of plan, elevation and section, drawn

    to a scale are necessary to take the details of measurements of various items of

    work.

    Specifications : The specifications gives the nature, quality and classof materials, their proportion, method of execution and workmanship and the

    class of labour required. The cost of the work varies with its specifications. The

    cement mortar with 1:3 is more costlier than cement mortar with 1:6.

    Rates :The rates for various items of work, the rates of various materials

    to be used in construction, the wages of different categories of labour should be

    available for preparing an estimate. The location of the work and its distance of

    source of materials and cost of transport should be known. These rates may be

    obtained from the Standard Schedule of Rates prepared by the engineering

    departments.

    3.1.3 Details of measurements and calculation of quantities and abstract of estimated cost

    To prepare an accurate estimate, a detailed estimate of quantities of

    various items of work and an abstract estimate of the quantities and their unit

    rates are required.

  • 7/23/2019 Estimating & Costing

    12/83

    Construction Technology162

    Detailed Estimate

    Abstract estimate

    3.2. Preliminary or approximate estimate

    Preliminary or approximate estimate is required for preliminary studies

    of various items of work or project , to decide the financial position and policy

    for administrative sanction by the competent authority. The preliminary estimate

    is prepared by different methods for different types of works. The various

    methods of preparing the preliminary estimate are plinth area estimate, cubical

    rate estimate and estimate per unit base.

    3.2.1 Plinth area estimate

    The plinth area rate is calculated by finding the plinth area of the building

    and multiplying by the plinth area rate. The plinth area rate is obtained by

    comparing the cost of the cost of similar building having similar specifications in

    the locality.

    3.2.2. Cubic area estimate

    The cubic rate estimate is prepared on the basis of the cubical contents

    of the building. The cubic rate is obtained from the cost of the similar building in

    the locality having similar specifications. The cost of the building is estimated by

    multiplying the volume of the building with the cubic area rate. Cubic rate estimate

    is more accurate as compared to the plinth area estimate.

    3.2.3 Estimate per unit base

    The preliminary estimate may be prepared for different structures and

    works by various ways. For schools and hostels, per class rooms for schools,per bed for hospitals, per seat for theater halls, etc. For roads and highways and

    for irrigation works, the preliminary estimate is made per kilometer. For bridges

    and culverts per running meter. For sewerage and water supply projects on the

    basis of per head of population served.

    S.no Description of work No Length Breadth Height/Depth Quantity Remarks

    S.No. Description of work Quantity Rate Per Amount

  • 7/23/2019 Estimating & Costing

    13/83

    163Paper - II Estimating and Costing

    3.3. Problems in preliminary estimate

    1. If the cost of school building per student is Rs. 25000. Calculate thecost of school building for 100 students.

    Cost of the school building for 100 students = Rs.

    25000x100=Rs.2500000.

    2. If the cost of construction of 1 km. length of a highway is Rs.

    10000000. Find the cost of construction for 20 km.

    Cost of construction for 20 km = Rs. 10000000x20=Rs.200000000.

    3. If the plinth area rate of a residential building is Rs.10000/sq m.

    Calculate the cost of construction of a residential building of 100 sq. m.

    Cost of construction of 100 sq. m.= plinth area rate x area =

    10000x100=Rs.1000000

    Summary

    Detailed estimate consists of taking the detailed measurements of length,

    breadth, height and calculating the quantities.

    Data required for estimate :Drawings, specifications and rates.

    Types of preliminary estimates : Plinth area estimate, cubic rate

    estimate and estimate per unit base.

    Short Answer Type Questions

    1. Define detailed estimate.

    2. What are stages for preparation of an estimate?

    3. List out the data required for preparation of an estimate.

    4. Write the tabular form for the detailed estimate.

    5. Write the tabular form for preparation of an abstract estimate.

    Long Answer Type Questions

    1. Describe the various types of preliminary estimates.

  • 7/23/2019 Estimating & Costing

    14/83

    Construction Technology164

    Structure

    4.0 Introduction

    4.1 Single roomed building (load bearing structure)

    4.2 Two roomed building( load bearing type structure)

    4.3 Single storied residential building with number of rooms (load bearing

    type structure)

    4.4 Single storied residential building with number of rooms (framed

    structure type)

    4.5 Primary school building with sloped roof

    4.6 RCC Dog legged open well stairs

    4.7 Two storied residential building (framed structure type)

    4.8 Detailed estimate of compound wall and steps

    Learning Objectives

    After studying this unit student will be able to

    Prepare detailed estimates of single roomed, Building roomed, Doubleroomed buildings, for load bearing walls and Framed structures. Detailed Esti-mate of Primary School Building, Compound walls and steps. Detailed estimateDog legged and Open Well STair case. Preparational estimate for ground andfirst floor.

    4UNITDetailed and AbstractEstimate of Buildings

  • 7/23/2019 Estimating & Costing

    15/83

    165Paper - II Estimating and Costing

    4.0 Introduction

    To estimate the cost of any building or a structure, drawings,specifications and rates are required. Regarding the detailed estimate by long

    wall and short wall method and centre line method, the drawings consisting of

    plan elevation and section are sufficient. The estimator should be able to take all

    the dimensions from the drawings. The length and breadth are taken from the

    plan, while the height or depth are taken from the section and elevations. In long

    wall and short wall method the walls are taken separately, while in the centre line

    method, the centre line lengths of all the walls are combined. The accuracy of

    estimate depends upon the skill of the estimator in studying the drawings. The

    long wall and short wall method is useful for load bearing type structure, but it

    cannot be applied for framed structure.

    4.1 Single roomed building (load bearing structure)

    There are two steps in estimating the cost of a building or a structure.

    1. Taking out quantities and calculation of quantities in detailed estimate.

    2. Determining the cost from the abstract estimate.

    Long wall and short wall method : This method is also called as

    separate or individual wall method. This is simple and it gives accurate values.

    The following procedure is adopted.

    1. The dimensions of long wall and short wall should be taken separately.2. Irrespective of its lengths, the wall which is taken first is long wall and

    the wall which is taken next is the short wall.

    3. The centre line of the wall of the building is considered for determining

    the centre to centre line length of long walls and short walls.

    4. The centre to centre to centre length of long walls or short walls is

    obtained by adding half the width of the wall to the internal length of

    either long wall or short wall.

    5. Centre to centre length of long wall = internal length of long wall +

    width of the wall.

    6. Centre to centre length of short wall = internal length of short wall +

    width of the wall.

    7. To determine the lengths of different quantities such as earthwork,

    c.c. bed in foundation, R.R. masonry etc, length of long wall = centre

  • 7/23/2019 Estimating & Costing

    16/83

    Construction Technology166

    to centre length of long wall + width, the width is the respective

    width of the item in consideration.

    8. Similarly length of the short wall = centre to centre length of the short

    wall width, where the width is the respective width of the item

    such as earthwork, c.c. bed etc.

    Centre line method : In the centre line method, the sum of all the

    centre line lengths of long walls and short walls are added to get the total centre

    line length. At the junctions of two walls, the length is present in both of the

    walls. Hence half of the length of that width is to be subtracted from the total

    centre line length.

    Length = Total centre line length width x number of junctions.

    Fig 4.1 Plan Single Room

    Centre to centre length of long wall = 6.0 + 2x0.3/2 = 6.3 m.

    Centre to centre length of short wall = 4.0 + 2x0.3/2 = 4.3 m.

    Length of Long Wall = Centre to centre Length of Long Wall + Width

    Length of Short Wall = Centre to centre Length of Short Wall width

    For earth work in excavation Length of Long Wall = 6.3 + 1.2 = 7.5 m.

    E L E V A T I O N S E C T I O N

    1. 20. 90. 70. 5

    0.30.60.3

    3.0

  • 7/23/2019 Estimating & Costing

    17/83

    167Paper - II Estimating and Costing

    For earth work in excavation Length of Short Wall = 4.3 1.2 = 3.1 m.

    In cement concrete in foundation the length and width of the long walland short wall are the same, but the height is different from that of the foundation

    For R.R. masonry First footing Length of long wall = 6.3 + 0.9 = 7.2 m.

    Length of Short Wall = 4.3 -0.9 = 3.4 m.

    Similarly for second footing & Third footing, Length of Long Walls are

    7.0 and 6.8 and for short walls are 3.6 m and 3.8 m respectively.

    Detailed estimate of a single roomed building by centre line method

    Centre to centre length of long wall = 6.0 + 2x0.3/2 = 6.3 m.

    Centre to centre length of short wall = 4.0 + 2x0.3/2 = 4.3 m.

    Total centre line length = 2(6.3 + 4.3) = 21.2 m.

    Detailed Estimate

    Quantity

    30.528

    7.63

    11.45

    4.45

    12.72

    28.62

    19.08

    RemarksSl. No.

    1

    2

    3

    4

    Description

    of work

    Earth work in

    excavation

    C.C. bed infoundation

    R.R. masonry

    in foundation

    and plinth

    First footing

    Second footing

    Basement

    Brick work in

    super structure

    No.

    1

    1

    1

    1

    1

    1

    L

    21.2

    21.2

    21.2

    21.2

    21.2

    21.2

    B

    1.2

    1.2

    0.9

    0.7

    0.5

    0.3

    H

    1.2

    0.3

    0.6

    0.3

    1.2

    3

    m m m m3

  • 7/23/2019 Estimating & Costing

    18/83

    Construction Technology168

    Sl.

    No.

    1

    2

    3

    Description of work

    Earth work in

    excavation in

    foundation

    Long Walls

    Short Walls

    Plain cement concrete

    in foundation (1:5:10)

    Long Walls

    Short Walls

    R.R. Masonry in

    foundation

    & basement c.m (1:8)

    First footing

    Long Walls

    Short WaLLS

    Second footing

    Long Walls

    Short WaLLS

    Basement

    Long Walls

    Short Walls

    No.

    2

    2

    2

    2

    2

    2

    2

    2

    2

    2

    L

    m

    7.5

    3.1

    7.5

    3.1

    7.2

    3.4

    7

    3.6

    6.8

    3.8

    B

    m

    1.2

    1.2

    1.2

    1.2

    0.9

    0.9

    0.7

    0.7

    0.5

    0.5

    H

    m

    1.2

    1.2

    Total

    0.3

    0.3

    Total

    0.6

    0.6

    0.3

    0.3

    1.2

    1.2

    Quantity

    m3

    21.6

    8.93

    30.53

    5.4

    2.68

    8.08

    7.78

    3.67

    11.45

    2.94

    1.51

    4.45

    8.16

    4.56

    Remarks

    L=6.3+1.2=7.5

    L = 4 . 3 -

    1.2=3.1

    L=6.3+1.2=7.5

    L = 4 . 3 -

    1.2=3.1

    L=6.3+0.9=7.2

    L = 4 . 3 -

    0.9=3.4

    L=6.3+0.7=7.0

    L = 4 . 3 -

    0.7=3.6

    L=6.3+0.5=6.8

    L = 4 . 3 -

    0.5=3.8

  • 7/23/2019 Estimating & Costing

    19/83

    169Paper - II Estimating and Costing

    4.2 Two roomed building( load bearing type structure)

    Detailed Estimate Of A Double Roomed Building By Long Wall AndShort Wall Method

    Centre to centre length of long wall = 5.0 + 0.3 + 5.0 + 2x0.3/2 = 10.6m.

    Centre to centre length of short wall = 5.0 + 2x0.3/2 = 5.3 m.

    Number of long walls = 2. Number of short walls = 3.

    Length of long wall = centre to centre length of long walls + width

    Length of short wall = centre to centre length of short wall - width

    4 Brick work in super

    structure c.m. ( 1:8)

    Long Walls

    Short Walls

    2

    2

    Totalof

    6.6

    4

    R.R.

    0.3

    0.3

    masonry

    3

    3

    12.72

    28.62

    11.88

    7.2

    19.08

    L=6.3+0.3=6.6

    L = 4 . 3 -

    0.3=4.0

    Sl. No.

    1

    2

    Description of

    work

    Earthwork in

    excavation

    Long Walls

    Short Walls

    C.C. bed in

    foundation

    Long Walls

    No.

    2

    3

    2

    L

    m

    11.8

    4.1

    11.8

    B

    m

    1.2

    1.2

    1.2

    H

    m

    1.2

    1.2

    Total

    0.3

    Quantity

    m3

    33.98

    17.71

    51.69

    8.5

    Remarks

    L= 10.6 +

    1.2 = 11.8

    L = 5.3 -

    1.2 = 4.1

    Total centre to centre line lenght = 10.6 x 2 + 5.3x3 = 37.1 m

  • 7/23/2019 Estimating & Costing

    20/83

    Construction Technology170

    3

    4

    Short Walls

    R.R. masonry in

    foundation &

    plinth

    First footing

    Long Walls

    Short walls

    Second footing

    Long Walls

    Short Walls

    Third footing &plinth

    Long Walls

    Short walls

    Brick work in

    super structure

    Long Walls

    Short Walls

    3

    2

    3

    2

    3

    2

    3

    2

    3

    4.1

    11.5

    4.4

    11.3

    4.6

    11.1

    4.8

    10.9

    5

    1.2

    0.9

    0.9

    0.7

    0.7

    0.5

    0.5

    0.3

    0.3

    0.3

    0.6

    0.6

    0.3

    0.3

    1.2

    1.2

    3

    3

    4.43

    12.93

    312.42

    7.13

    19.55

    4.75

    2.9

    7.65

    13.32

    8.64

    21.96

    49.16

    19.62

    13.5

    33.12

    L = 10.6 +

    0.9 = 11.5

    L = 5.3 - 0.9

    = 4.4

    L = 10.6 +

    0.7 = 11.3

    L = 5.3 -0.7

    = 4.6

    L = 10.6 +

    0.5 = 11.1

    L = 5.3 - 0.5

    = 4.8

    L = 10.6 + 0.3 =

    10.9

    L = 5.3 - 0.3 =

    5.0

    R.R. masonry Total

  • 7/23/2019 Estimating & Costing

    21/83

    171Paper - II Estimating and Costing

    Centre line method

    Fig 4.2 Double Room

    No.

    1

    1

    1

    1

    1

    1

    1

    L

    35.9

    35.9

    36.2

    36.4

    36.6

    36.8

    B

    1.2

    1.2

    0.9

    0.7

    0.5

    0.3

    H

    1.2

    0.3

    0.6

    0.3

    1.2

    Total

    3

    Sl. No.

    1

    2

    3

    4

    Description of

    work

    Earthwork in

    excavation

    C.C. bed in

    foundation

    R.R. masonry in

    foundation

    First footing

    Second footing

    Basement

    Brickwork in

    superstructure

    Remarks

    L= 37.1 -

    2x1/2x1.2

    L = 37.1 -

    2x1/2x0.9

    L = 37.1 -

    2x1/2x0.7

    L = 37.1 -

    2x1/2x0.5

    L = 37.1 -

    2x1/2x0.3

    Quantity

    51.69 m3

    12.93 m3

    19.55 me

    7.65 m3

    21.96 m3

    49.165 m3

    33.12 m3

    E L E V A T I O N S E C T I O N

    5m x 5 m5 m x 5 m

    1. 20. 90. 70. 5

    0.30.60.3

    3.0

  • 7/23/2019 Estimating & Costing

    22/83

    Construction Technology172

    4.3 Single storied residential building with number of rooms (load bearingtype structure)

    Length of long walls = 6.0+0.3+5.0+2x0.3/2=11.6 m.

    Number of long walls = 3

    Length of short wall of 5.0 m. length = 5.0+2x0.3/2=5.3 m.

    Number of 5.0 m shortwalls =3

    Length of 4.0 m. length short walls = 4.0+2x0.3/2=4.3m.

    Number of 4.0 m. length short walls = 3

    Total centre line length = 11.6x3+5.3x3+4.3x3=63.6m.

    Fig 4.3 Plan Section

    6.0 x 5.0 m 5.0 x 5.0 m

    5.0 x 4.0 m5.0 x 4.0 m

    D D

    DD

    D D

    0.30.6

    0.3

    0.9

    0.9

    1.2m

    3.0m

  • 7/23/2019 Estimating & Costing

    23/83

    173Paper - II Estimating and Costing

    56.43

    m mm m3

    5m4m

    5m4m

    5m4m

    5m4m

    Basement

    Basement

  • 7/23/2019 Estimating & Costing

    24/83

    Construction Technology174

    4.4 Single storied residential building with number of rooms (framed structure type)

    Number of columns in a framed structure = 9

    Size of the columns = 230 mmx230 mm

    Length of R.R. masonry, Brickwork, lintels, plinth beam and beams

    under slab = (6+6)x3+(5+4)x3=63 m.

    Length of sunshades and external plastering = (12.9+9.9)x2= 45.6 m.

    Length of slab with 1 m. extension on both sides = 1.0+1.0=2.0 m.

    External Plastering : Area of external plastering = Length x Height

    Length of Plastering = 2x(12.9+9.9)=45.6 m.

    Height of external plastering = 3.0+0.12, where 3.0m is the height of

    the room and 0.12 m. is the thickness of the slab.

    Internal plastering : Area of internal plastering = Length x Height

    Length of plastering = 2(L+B) , Where L and B are the length and

    breadth of the room respectively.

    For 6mx5m room, length = 2(6+5)=22m. Similarly for 5mx4m room,

    length =2(5+4)=18 m.

    Fig 4.4 Residential Building Framed Structure

    6.0 x 5.0 m 5.0 x 5.0 m

    5.0 x 4.0 m6.0 x 4.0 m

    P L A N S E C T I O N

    0.23 x 0.23

    R.C.C Column3.0 m

    1.2 m

    0.9 m

    0.3 m

    0.3 m

    R.C.C.

    Footing

    R.C.C.

    G.L G.L

    100 mm

    thick

    RCC slab

    1.2 m

  • 7/23/2019 Estimating & Costing

    25/83

    175Paper - II Estimating and Costing

    B

    m

    1.2

    0.9

    0.6

    1.2

    0.9

    0.6

    0.7

    0.45

    0.23

    0.23

    0.23

    1.2

    0.23

    S.

    No.

    1

    2

    3

    4

    5

    Description of work

    Earthwork in excavation

    Columns

    In between columns

    Deduct for columns

    C.C. bed in foundation

    Columns

    In between columns

    Deduct for columns

    R.R. masonry in

    foundation

    First footing

    Second footing

    Brickwork in

    superstructure

    Deductions Doors

    Windows

    R.C.C. column footing

    Trapezoidal section

    Stem

    No.

    9

    1

    9

    9

    1

    9

    1

    1

    1

    6

    8

    9

    9

    9

    L

    m

    1.2

    63

    0.6

    1.2

    63

    0.6

    63

    63

    63

    1

    1.2

    1.2

    0.23

    H

    m

    1.8

    0.9

    0.9

    0.3

    0.3

    0.3

    0.6

    1.2

    3

    2

    1.2

    0.3

    0.3

    5.1

    Quantity

    m3

    23.33

    51.03

    -2.92

    71.44

    3.89

    17.01

    -0.972

    19.93

    26.46

    34.02

    60.48

    43.47

    -2.76

    -2.65

    38.06

    3.89

    2.44

    2.43

    8.76

    Remarks

    L=12x3+

    9x3=63

    H=0.9+1.2+

    3.0=5.1

    Net Brickwork in super structure

    (1.44+4x0.985+0.053)/6

  • 7/23/2019 Estimating & Costing

    26/83

    Construction Technology176

    6

    7

    8

    9

    10

    11

    R.C.C. Plinth beam

    R.C.C. inlintels&sunshades

    Lintels

    Sunshades

    R.C.C. slab and beams

    Beams under slab

    1m. Projection from

    slab

    R.C.C. Slab.

    External plastering

    20 mm

    Thick

    Deductions

    Doors

    Windows

    Internal Plastering

    12 mm thick

    Rooms 6mx5m

    Rooms5mx4m

    Sand filling in rooms

    Rooms 6mx5m

    1

    1

    1

    19

    1

    1

    6

    8

    2

    2

    2

    63

    63

    45.6

    63

    1

    14.9

    45.6

    1

    1.2

    22

    18

    6

    0.23

    0.23

    0.7

    0.23

    0.23

    11.9

    5

    0.3

    0.1

    0.07

    0.3

    0.3

    0.12

    3.12

    2

    1.2

    3

    3

    1.2

    4.35

    1.45

    2.23

    3.68

    4.35

    0.62

    21.28

    26.25

    142.27

    -12

    -11.52

    118.75

    132

    108

    240

    72

    L=2(12.9+

    9.9)=45.6

    L=12.9+1.0+

    1.0=14.9

    B=9.9+1.0+

    1.0=11.9

    L=2(12.9+9.9)

    =45.6

    H=3.0+0.12

    L=2(6+5)=22

    L=2(5+4)=18

    Net External plastering area

  • 7/23/2019 Estimating & Costing

    27/83

    177Paper - II Estimating and Costing

    4.5 Primary school building with sloped roof

    Wall thickness = 0.3 m. in brick masonry.

    Width of foundation = 1.2 m. Depth of foundation = 1.8 m.

    Width of first footing = 0.9 m. Depth of first footing = 0.9 m.

    Second footing width = 0.7 m. Depth = 0.6 m.

    Width of third footing and plinth = 0.5 m. Height = 0.9 m.

    Centre to centre length of long walls = 3.0+0.3+3.0+2x0.3/2=6.6 m.

    Centre to centre length of short walls = 3.0+2x0.3/2=3.3 m.

    Total centre line length = 6.6x2+3.3x3=23.1 m.

    Number of junctions = 2.

    Height of the sloping roof =1.0 m.

    12

    13

    14

    Rooms 5mx4m

    C.C. bed in rooms

    Rooms 6mx5m

    Rooms5mx4m

    Flooring in rooms

    Rooms 6mx5m

    Rooms5mx4m

    Fabrication &

    placement of

    steel

    2

    2

    2

    2

    2

    5

    6

    5

    6

    5

    4

    5

    4

    5

    4

    1.2

    0.1

    0.1

    48

    120

    6

    4

    10

    60

    40100

    (8.76+4.35+3.68+26.25)x1.25x87.5/100x1000 78.5x100/100x1000

    tonnes 4.22 t

  • 7/23/2019 Estimating & Costing

    28/83

    Construction Technology178

    Length of the sloping roof = square root of (1.5mx1.5m + 1.0m.x1.0

    m.) = 1.8 m.

    Number of gable rafters at a spacing of 30 cms. Centre to centre =(

    6.0/0.3)+1=21

    Length of the gable rafters = 1.8+1.8+0.5+0.5=4.6 m.

    Number of reapers along a length of 6.05 mts. At a spacing of 10 cms

    each = (4.6/0.1)+1=47

  • 7/23/2019 Estimating & Costing

    29/83

    179Paper - II Estimating and Costing

    ELEVATION

    W W

    DD

    Room

    3.0 x 3.0 m

    Room

    3.0 x 3.0 m

    References

    D - Door 1.00 m x 2.00 m

    W - Window 1.2 m x 1.2 m

    Width of 1st footing : 0.9 m

    Second footing : 0.7 m

    Basement : 0.5 m

    P L A N

    S E C T I O N

    Tiles

    Tiles

    1.2 m

    0.9 m

    0.6 m

    0.3 m

    0.9 m

    0.9 m

    0.6 m

    0.3 m

    0.9 m

    2.0 m

    1.5 m

    0.9 m

    PRIMARY SCHOOL BUILDING WITH SLOPING ROOF

  • 7/23/2019 Estimating & Costing

    30/83

    Construction Technology180

    4.6 RCC Dog legged open well stairs

    Fig 4.5 Dog Legged Stair case

    1650

    250

    150

    Floor

    1650

    2500 1000

    E L E V A T I O N S E C T I O N - A A

    P L A N

  • 7/23/2019 Estimating & Costing

    31/83

    181Paper - II Estimating and Costing

    Sloping side 2 2 0.28 2.4640. 411.264Total

  • 7/23/2019 Estimating & Costing

    32/83

    Construction Technology182

    Length of the inclined flight = Square root of (1.65x1.65+2.5x2.5)=3.0m.

    Size of base of flight = 1.0x0.5x0.25 m3

    Landing at the middle and top floor =2.0mx1.0mx0.15m.

    Length of the hand rail = (2x3.0+0.40)=6.8 m.

    Number of risers = 11

    Height of the first flight = 11x0.15=1.65 m.

    Number of treads = 10

    Length of treads in each flight = 10x0.25=2.5 m.

    Triangular portion of the brick has a base of 0.25 m. and height 0.15 m.

    Area of the brickwork = 1/2x(0.25x0.15) m2.

    4.6.1 Open Well Staircase

    Fig 4.6 Open well Stair case

    Flig

    htNo.

    No.

    ofRisers

    No.o

    fTrea

    ds

    Eac

    hRiser

    Eac

    hTrea

    d

    A

    8

    8

    152

    300

    B

    4

    3

    152

    300

    C

    8

    7

    152

    300

    SECTION AT AA

    Note :

    1. All dimensions are in Milli meters

    2. Follow the written dimensions only

    OPEN WELL TYPE STAIRCASE

    Scale 1:50

    DRG. No. 18

  • 7/23/2019 Estimating & Costing

    33/83

    183Paper - II Estimating and Costing

    Flight No. A

    Horizontal distance of treads = 0.3x8=2.4 m.

    Height of risers = 0.15x9=1.35 m.

    Sloping length of flight = Square root of(2.4x2.4+1.35x1.35)=2.75 m.

    Flight No. B

    Horizontal length of treads = 0.3x3=0.9 m.

    Height of risers = 0.15x4=0.6 m.

    Sloping length of flight= Square root of (0.9x0.9+0.6x0.6)=1.08 m.

    Flight No. C

    Horizontal length of treads = 0.3x7=2.1 m.

    Height of risers = 0.15x8=1.2 m.

    Sloping length of flight = Square root of (2.1x2.1+1.2x1.2)=2.42 m.

  • 7/23/2019 Estimating & Costing

    34/83

    Construction Technology184

    4.7 Two storied residential building (framed structure type)

    Fig 4.7 Two storied residential building

    E L E V A T I O N

    Parpet wall

    Weathering

    course

    Lintel &

    sunshade

    Brick

    masonry

    Roof slab

    C.C. flooring

    R.C.C Mix

    1:4:1Sand filling

    C.C. floring

    1:4:8Elevation

    0.902

    3.05 m

    3.05 m

  • 7/23/2019 Estimating & Costing

    35/83

    185Paper - II Estimating and Costing

    Fig 4.8 Ground Floor & First Floor

    Ground floor

    Number of columns = 15

    Height of columns in ground floor & first floor =

    0.90+0.9+3.05+0.1+3.05+0.1+0.8=8.9 m.

    Height of column in ground floor = 0.9+9+3.05+0.1=4.95 m.

    Height of column in first floor = 3.05+0.1+0.8=3.95 m.

    Length of brickwork, lintels and beams =

    4.21x4+4.20x4+3.05x2+3.00x2+2.00x2+4.00x2+3.34x2 = 64.42 m.

    Openings Main door 1.00mx2.1m -1 No., Door D 0.9x2.1 3Nos., Door D1 0.76x2.1 2 Nos.

    Windows - W 1.8mx1.2m 5 Nos., W1 1.2mx1.2m 2 Nos.

    Length of wall 100 mm. thick = 4.21+3.79+1.5= 9.5 m.

    Length of sunshade = 2.1x5+1.5x2+1.1x1+1.3x1 = 15.9 m.

  • 7/23/2019 Estimating & Costing

    36/83

    Construction Technology186

    Length of slab = 12.68 m., Width of slab = 9.10 m.

    Length of external plastering = 2(12.68+9.10)=43.56 m.

    Trapezoidal section of the column foundation : Area of base A1 =

    1.0x1.0=1.0 m2.

    Area of the column stem = 0.23x0.23=0.0529 m2=A2

  • 7/23/2019 Estimating & Costing

    37/83

    187Paper - II Estimating and Costing

  • 7/23/2019 Estimating & Costing

    38/83

    Construction Technology188

  • 7/23/2019 Estimating & Costing

    39/83

    189Paper - II Estimating and Costing

  • 7/23/2019 Estimating & Costing

    40/83

    Construction Technology190

    4.8 Detailed estimate of compound wall and steps

    Length of the compound wall between the brick columns 230 mm x

    230 mm = 6.0 + 4.0 = 10.0 m.

    Height of the compound wall = 1.5 m.

    Depth of excavation below ground level = 0.9 m.

    Width of the foundation = 0.9 m.

    Thickness of the C.C. bed = 0.3 m.

    Size of the first footing = 0.6 m. x 0.6 m.

    Size of the plinth = 0.45 x 1.0m2.

    Size of the brickwork in columns = 0.23 x 0.23 x 1.5 m.

    Number of brick columns = 3

    Length of the earthwork in excavation =

    6.0+0.23+0.23+4.0+0.23=10.69

    Quantity of earthwork in excavation = 10.69x0.9x0.9=8.66 m3.

    Quantity of C.C. bed in foundation = 10.69x0.9x0.3=2.89 m3.

    R.R. masonry first footing = 10.69x0.6x0.6= 3.85 m3.

    R.R. masonry in plinth = 10.69x0.45x1.0= 4.81 m3.

    R.R. masonry total = 3.85+4.81= 8.66 m.

    Brick masonry in columns = 3x0.23x0.23x1.5=0.24 m3.

    Brickwork in between columns = 10.0x0.10x1.5= 1.5 m3.

    Total brick masonry = 0.24+1.5=1.74 m.

    Deduction for gate 2.0mx1.5m = 2.0x0.1x1.5=0.3 m3.

    Net brickwork in superstructure = 1.74-0.3 = 1.44 m.

    Plastering in columns = 4x0.23x1.5x3=4.14 m2.

    Plastering in between columns = 10x1.5x2=30 m2.

  • 7/23/2019 Estimating & Costing

    41/83

    191Paper - II Estimating and Costing

    Total area of plastering = 4.14+30=34.14 m2.

    Estimate of steps

    Quantity of first step = 1.0x0.9x0.3=0.27 m3.

    Quantity of second step = 1.0x0.6x0.3=0.18 m3.

    Quantity of third step = 1.0x0.3x0.3=0.09 m3.

    Total quantity of brickwork in steps = 0.27+0.18+0.09=0.54 m3.

    1.5 m

    1.0 m0.45

    0.6

    0.9 m

    0.3 m

    0.6 m

    0.23m

    0.23

    4.0 m

    0.23

    6.0m0.23

    0.15

    0.15

    0.15

    0.3

    0.3

    0.3

    1.0 m

    Top view

    Front View

    Side View

    Fig. 4.9 Plan and Section of a compound Wall

  • 7/23/2019 Estimating & Costing

    42/83

    Construction Technology192

    Summary

    To estimate the cost of a building or a structure the steps involved are

    1. Taking out the measurement of various items and calculate the

    quantities as per the detailed estimate.

    2. Determining the cost of the calculated quantities as per Abstract

    estimate.

    The methods of calculating quantities are Long wall and short wall method

    and Centre line method.

    Length of Long wall = Centre to centre length of the long wall + width

    Length of short wall = Centre to centre length of the short wall widthIn centre line method, the length = Total centre line length (number of

    junctions)xwidth/2

    For a double room building, the total centre line length = sum of the

    centre line lengths of two long walls and three short walls. The number

    of junctions = 2.

    For a building with number of rooms, the total centre line length = sum

    of the centre to centre lengths of three long walls, three short walls of length 5.3

    m. and three short walls of length 4.3 m. Number of junctions = 6.

    The long wall short wall method and the centre line method are notapplicable. The lengths of the R.R. masonry, Brickwork in superstructure, Plinth

    beam, lintels and beams under slab are obtained by adding the internal dimensions

    of the rooms.

    The roof for the primary school building is a gable roof, having its slope

    in two directions. The roof under consideration is the roof having its width = 3.0

    m. and its length = 6.0 m.

    Length of the gable rafter = square root of [(width/2)2 + (Rise)2]

    Number of gable rafters = Length of the roof/ spacing of the rafters.

    Area of the tiled surface = 2x(Length of the roof )x Width of the slopingside.)

    Number of risers = Height of the flight/ rise.

    Number of treads = Number of risers 1.

    Treads length = Number of treads x Tread.

  • 7/23/2019 Estimating & Costing

    43/83

    193Paper - II Estimating and Costing

    Horizontal length of the stairs = Treads length + Width of the landing

    Length of the sloping side = Square root of [(Treads length)2 + (Height

    of flight)2].

    Area of brickwork in each step = (Rise x Tread) x .

    Short Answer Type Questions

    1. What are the steps involved in finding the cost of the building?

    2. What are the methods involved in taking measurements in a detailed

    estimate.

    3. Write the tabular formula of a detailed estimate.

    4. Calculate the number of risers in a flight of height 1.50 m. and the rise of 15 cms.

    5. If the number of risers = 10, find the number of treads.

    6. Find the length of the gable rafter for a room of width 6.0 m. and

    length 12.0 m and the rise is 1.5 m.

    Long Answer Type Questions

    1. Find the earthwork in excavation, C.C. bed in foundation, R.R.

    masonry in foundation, Brick work in superstructure and plastering for single

    room building and double room building by long wall short wall method and

    centre line method.2. Detailed estimate of a dog legged stair case.

    3. Detailed estimate of compound wall and steps.

    O.J.T. Type Questions

    1. Detailed estimate of a number of rooms.

    2. Detailed estimate of a framed structure.

    3. Detailed estimate of a Primary school building.

    4. Detailed estimate of an open well stair case.

    5. Detailed estimate of a double storied building.

  • 7/23/2019 Estimating & Costing

    44/83

    Construction Technology194

    Structure

    5.0 Introduction

    5.1 Prepare specifications for different items of work.

    5.2 Find the cost of materials at source and at site.

    5.3 Study of the cost of labor types of labor using standard schedule

    of rates

    5.4 Concept of lead and lift- leads statement

    5.5 Preparation of unit rates for finished items of works

    Learning Objectives

    After studying this unit student will be able to

    Prepare the unit ratio of various items of works. Find the cost of

    materials, specifications of various of various items of works.

    5.0 Introduction

    To estimate the cost of the building, the quantities of various items of

    work are calculated from the drawings. The unit rates of various items of work

    are calculated from the specifications of the various types of materials. The rates

    are calculated as per the rates in the standard schedule of rates. The unit rates of

    various items of work increase considerably with the specifications. The

    5UNIT

    Specifications and Analysis

    of Rates

  • 7/23/2019 Estimating & Costing

    45/83

    195Paper - II Estimating and Costing

    specifications indicate the quality of the work while the drawings are used for

    the quality of the work.

    5.1 Prepare specifications for different items of work

    Specifications specifies or describes the nature and the class of work,

    materials to be used in the work, workmanship etc. From the study of the

    specifications one can easily understand the nature of the work and what the

    work shall be.

    Detailed specifications : Detailed specifications are written to express

    the requirements clearly in a concise form avoiding repetition and ambiguity.

    The detailed specifications for various items of work are as follows.

    Earthwork excavation of foundation

    The following specifications shall be followed in the earthwork in

    excavations in foundations.

    1. Foundation trench shall be dug to the exact width and depth of

    foundation.

    2. Excavated earth shall not be placed within 1 m. of the edge of the

    foundation.

    3. The bottom of the trenches shall be perfectly leveled both

    longitudinally and transversely.

    4. If water accumulates in the trench, it should be pumped out. Care should be taken to prevent water from entering the trench.

    5. If rocks and boulders are found during excavation, they should be

    removed and the bed of the trench should be leveled and

    consolidated.

    6. Foundation concrete should be laid only after the inspection and

    approval by the Engineer in charge.

    Cement concrete in foundation (1:5:10)

    The following specifications should be followed in cement concrete in

    foundation.

    1. Course aggregate should be of hard broken stone, free from dust,

    dirt and foreign matter.

    2. Fine aggregate shall be of coarse sand, consisting of hard, sharp and

    angular grains and shall pass through screen of 5 mm. square mesh.

  • 7/23/2019 Estimating & Costing

    46/83

    Construction Technology196

    3. Sand should be free from dust, dirt and organic matters.

    4. Water shall be clean and free from alkaline and acid matter.

    5. Mixing should be done on masonry platform or sheet iron tray in

    hand mixing.

    6. Coarse aggregate and sand should be mixed by volume and cement

    by weight.

    Random rubble masonry

    The following specifications should be followed in random rubble

    masonry

    1. The stones should be sound, hard and durable. Stones with rounded

    surface shall not be used.

    2. No stone shall be less than 15 cm. in size.

    3. Bond stones should be provided at every 1 m. length.

    4. Cement mortar 1:3 to 1:6 shall be provided.

    5. The joints in the stone masonry shall not be thicker than 2 cm.

    6. The masonry shall be watered for at least 10 days.

    Brick masonry

    The following specifications should be followed in brick masonry firstclass

    1. Bricks of standard size, copper red color, regular in shape, having

    sharp square edges should be used.

    2. The bricks should not absorb more than 20% of water when immersed

    in water for 24 hours.

    3. The mortar used in brick masonry shall be 1:3 to 1:6.

    4. The bricks shall be well bonded and laid in English bond unless

    otherwise specified.

    5. Mortar joints shall not exceed 6 mm. in thickness and the joints shall

    be fully flushed with mortar.

    6. The bricks should be soaked in water before use in masonry.

    7. The brick masonry shall be watered for at least 10 days.

  • 7/23/2019 Estimating & Costing

    47/83

    197Paper - II Estimating and Costing

    Plastering

    The following specifications should be followed in plastering

    1. The materials of mortar, cement and sand used in plastering should

    be as per specifications.

    2. The joints of the brickwork shall be raked for a depth of 18 mm. on

    the surface.

    3. Ceiling plastering should be completed before the start of wall

    plastering.

    4. The thickness of the plastering should not be less than 12 mm. for

    internal plastering and 20 mm. for external plastering.

    5. The plastering work shall be checked for horizontality with a straight edge and for verticality with a plumb bob.

    6. Any defective plastering shall be cut in rectangular shape and replaced.

    7. The plastering should be watered for at least 10 days.

    5.2 Find the cost of materials at source and at site.

    The amount required to purchase the material at the source of its

    production is the cost of materials at the source.

    Cost of materials at site : The cost of materials at site includes the

    cost of materials at source along with the cost of seignories, taxes, royalties,transport, stacking, loading and unloading etc.

    Seignories are collected for materials like sand, stones etc., which are

    under the control of respective local agencies under government control.

    5.3 Study of the cost of labor types of labor using standard schedule of rates

    Labour rates

    Si

    No.

    Category of worker

    S. Rate

    For

    2012-13

  • 7/23/2019 Estimating & Costing

    48/83

    Construction Technology198

    1 2 3

    Skilled catregory

    1 Bar bender 330

    2 Black smith / Tin smith / Rivetor 315

    3 Blaster ( Licensed ) 355

    4 Carpenter Cl- I 315

    5 Electrician ( Licensed ) 355

    6 Fitter Cl- I 315

    7 Floor Polisher / Tile Layer 315

    8 Foreman 355

    9 Gauge reader 300

    10

    Maistry / Work Inspector with Non-technical Qualification

    SSLC/SSC/HSC

    300

    11 Mason Cl- I / Brick layer Cl- I 315

    12 Mechanic Cl- I 315

    13 Operator Air compressor / DG set 315

    14 Operator Batching plant 355

    15 Operator Bus/Ambulance/ Lorry/ Tanker 315

    16 Operator Concrete / Asphalt mixer 315

    17 Operator Concrete / Asphalt paver 315

    18 Operator Concrete pump / Placer/ ice plant 315

    Common SoR 2012 : 13

    280

    Sl

    No.

  • 7/23/2019 Estimating & Costing

    49/83

    199Paper - II Estimating and Costing

    Category of worker

    S. Rate

    for

    2012-13

    1 2 3

    19 Operator Core drilling machine 355

    20 Operator Crane/ Tower crane/ Cable way 355

    21 Operator Drilling jumbo / Loco / Winch 315

    22 Operator Grouting/ Guniting/ Shotcreting 315

    23 Operator Jackhammer/Pneumatic tamper 315

    24 Operator Pump / Ventilation fan 315

    25 Operator Lathe/Drilling/Shearing machine 355

    26 Operator Bending / Planing machine 315

    27 Operator Road roller 315

    28 Operator Shovel / Scraper / Dozer 355

    29 Operator Spillway / Sluice gate 315

    30 Operator Crusher / Conveyor / Mucker 315

    31 Operator Tipper / Dumper / Transit mixer 355

    32 Operator Concrete vibrator 315

    33 Operator Vibratory plain / pad foot roller 315

    34 Operator Wagon drill / Drifter 355

    35 Painter Cl- I 350

    36 Plumber / Pipe fitter 350

    37 Sarang / Khalasi 315

    38 Spun pipe moulder 315

    39 Stone chiseller CI- I / Stone cutter Cl- l 315

    40 Struct. steel Fabricator / Marker / Erector 355

  • 7/23/2019 Estimating & Costing

    50/83

    Construction Technology200

    41 Welder / Gas Cutter 315

    42 Welder (X-ray quality) 355

    II. Semi skilled category

    1. Asphalt Sprayer / Boiler attendant 285

    2. Bhisti 285

    3. Boatman with boat 300

    Common SoR 2012:13

    281

    Sl

    No.

    Category of worker

    S. Rate

    for

    2012-13

    1 2 3

    4 Carpenter Cl- II / Erector shuttering 285

    5 Cartman with double bullock cart 330

    6 Cartman with single bullock cart 310

    7 Chavali / Navagani 285

    8 Crowbarman / Jumper man 285

    9 Fitter Cl- II 285

    10 Gang man / Head / Survey mazdoor 285

    11 Gardener / Trained mali 285

    12 Helper Air compressor / DG set 285

    13 Helper Batching plant 285

    14 Helper Blasting 285

    15 Helper Bus/ Ambulance/ Lorry/ Tanker 285

  • 7/23/2019 Estimating & Costing

    51/83

    201Paper - II Estimating and Costing

    16 Helper Bending/Shearing/Planing machine 285

    17 Helper Carpenter 285

    18 Helper Concrete / Asphalt mixer 285

    19 Helper Concrete / Asphalt paver 285

    20 Helper Core drilling machine 285

    21 Helper Crane/ Tower crane/ Cable way 285

    22 Helper Drilling jumbo / Loco / Winch 285

    23 Helper Fitter / Fabrication/Electrician 285

    24 Helper Grouting/ Guniting/ Shotcreting 285

    25 Helper Jack hammer / Pneumatic tamper 285

    26 Helper Laboratory / Instrumentation 285

    27 Helper Road roller 285

    28 Helper Shovel / Scraper / Dozer 285

    29 Helper Crusher / Conveyor / Mucker 285

    30 Helper Tipper / Dumper/ Transit mixer 285

    31 Helper Vibrator 285

    Common SoR 2012:13

    282

    Sl

    No.

    Category of worker

    S. Rate

    for

    2012-13

    1 2 3

    32 Helper Vibratory plain/ pad foot roller 285

    33 Helper Wagon drill/ Drifter 285

  • 7/23/2019 Estimating & Costing

    52/83

    Construction Technology202

    34 Lineman Electric / Telephone 285

    35 Mason Cl- ll / Brick layer Cl-II 285

    36 Mechanic Cl- II 285

    37 Painter Cl- II 300

    38 Patkari / Neeraganti / Sowdy 285

    39 Stone Chiseller Cl- II 285

    40 Stone breaker / Hammer man 285

    41 Valve man / Canal sluice operator 285

    III. Un-skilled category

    1 Cement / Asphalt handling mazdoor 250

    2 Civic worker 250

    3 Heavy mazdoor 250

    4 Light mazdoor 250

    5 Watchman 250

    IV. Other category

    1 Care-taker / conductor / Lift Attender 300

    2 Cook / Mess man 300

    3 Dhobi 300

    4 Diploma Engineer / Surveyor 450

    5 Diver with headgear 365

    6 Graduate / Laboratory Assistant 350

    7 Graduate Engineer/ Geologist 600

    8 Horticulture Assistant / Photographer 300

    9 ITI certificate holder / Tracer / Printer 350

    10 Literate mazdoor 285

    11 Stenographer / Computer Operator 400

    Common SoR 2012:13

  • 7/23/2019 Estimating & Costing

    53/83

    203Paper - II Estimating and Costing

    283

    Sl

    No.

    Category of worker

    S. Rate

    for

    2012-13

    1 2 3

    12 Telephone / Wireless Operator 350

    13 Typist / Job Typist 350

    14

    CAD operator with Diploma in Engineering/General degree with

    CAD certificate

    500

    15 Jeep Driver 355

    16 Data Processing Operator 500

    Note : 1. The wage should not be less than the minimum wages of

    schedule of employment,

    Subject to out turn. 2. 25% extra over the corresponding labour

    rates in respect of the work to be

    Done during night time subject to issue of certificate accordingly by

    the concerned estimate.

    Sanctioning authority for providing in the data and by concerned

    Executive Engineer in charge of the work for payment. The night time

    allowance is applicable only to the works done under Greater

    Hyderabad Municipal Corporation, Greater Visakhapatnam Municipal

    Corporation and Vijayawada Municipal Corporation limits only.of

    various government agencies.

    Transport cost includes cost of transporting the material from source

    to the site. In S.S.R., the cost of transporting on a mettaled road is

  • 7/23/2019 Estimating & Costing

    54/83

    Construction Technology204

    given. If transport is required on a cart track or a sand track, to reach

    the site, that distance is converted to equivalent metalled road.

    Distance on cart track = Distance on metalled road x 1.1

    Distance on sand track = Distance on metalled road x 1.4

    Stacking includes placing the material in a specified heap for a given

    volume in the case of materials like sand and coarse aggregate. Bricks are stacked

    for a given number. Sometimes are stacking charges are included in loading and

    unloading. Loading and unloading charges are fixed for a given volume or weight

    for different materials.

    The cost of labor wages for each category of labor are given above as

    per Standard schedule of rates 2012-13.

    Standard schedule of rates : In standard schedule of rates (S.S.R.) ,

    the rates of various materials, machinery and hiring charges and wages of labor

    are prepared. It is prepared by the board of chief engineers and approve it for

    that year.

    5.4 Concept of lead and lift- leads statement

    The distance between the source of material to the worksite is known

    as the lead. This lead distance changes from one project to another project

    depending upon the location. The vertical height through which the material is to

    be disposed is known as the lift.

    Lead charges : The conveyance charges of the materials from sourceto the site of work is called lead charge. In S.S.R. the lead charges are given for

    Metalled roads. The equivalent distance of metalled road for cart track = 1.1xlead,

    while for sandy track = 1.4xlead.

    Lead statement :Lead statement gives the cost of various materials at

    site. It includes basic rate, plus conveyance, blasting charges, seignorage charges

    etc.

    Lead Statement

    S.

    No

    Mat-

    erial

    Source Unit Cost at

    source

    Lead

    inKm.

    Equi

    valentmetal

    led

    road

    Blas

    tingchar

    ges

    Seign

    oragechar

    ges

    Cess

    charges

    Cru

    shingchar

    ges

    Deduc

    tionsif any

    Net

    rateat

    site

    Re

    marks

  • 7/23/2019 Estimating & Costing

    55/83

    205Paper - II Estimating and Costing

    5.5 Preparation of unit rates for finished items of works

    Cost of sand as per S.S.R. : For concrete = Rs. 375., For filling =Rs. 288., For plastering = Rs.490.

    Cost of cement = Rs. 5100/ton., = Rs. 255 per bag.

    Mixing charges for mixing 1 m3 of mortar = Rs. 85.

    Cost of preparation of 1 m3 mortar for different proportions

    5.5.1. Cement concrete in foundation (1:5:10)1

    Quantity of cement =(1.52/16)x1=0.095 m3=0.095x1440/50=2.74

    bags.

    Quantity of sand = (1.52/16)x5=0.475 m3

    Quantity of aggregate = (1.52/16)x10=0.95 m3.

    Cost of cement = Rs.255 per bag., Cost of sand=Rs. 375/m3., Cost of

    Coarse aggregate=Rs.588/m3.

    Cost of

    sand

    Rs. 323.40

    Rs. 367.

    50

    Rs. 392.

    00

    Rs. 406.

    70

    Rs.419.95

    Rs. 436.10

    Rs. 445.9

    Mix

    -ing

    charges

    Rs.85

    Rs.85

    Rs.85

    Rs.85

    Rs.85

    Rs.85

    Rs.85

    Mix

    propor

    -tion

    1:2

    1:3

    1:4

    1:5

    1:6

    1:8

    1:10

    Quantity of

    cement in

    bags

    9.5 bags

    7.2

    5.76

    4.79

    4.11

    3.19

    2.62

    Quantity

    of sand

    in m3

    0.66

    0.75

    0.8

    0.83

    0.857

    0.89

    0.91

    Cost of

    cement

    Rs.2422.50

    Rs. 1836.

    00

    Rs. 1469.

    00

    Rs. 1221.

    50

    Rs.1048.

    05

    Rs.813.

    45

    Rs.668.

    10

    Total cost

    2831.50

    2288.50

    1946.00

    1713.20

    1553.00

    1334.55

    1199.00

  • 7/23/2019 Estimating & Costing

    56/83

    Construction Technology206

    R.C.C. (1:2:4) works in Beams, slab, columns etc

    Quantity of cement = 1.52x1/7=0.217 m3 =0.217x1440/50=6.25 bags.

    Quantity of sand = 1.52x2/7=0.434 m3.

    Quantity of coarse aggregate = 1.52x4/7=0.869 m3.

    Quantity of steel =1.1x78.5/100=0.86quintals=86.35 kgs.

    Centering and scaffolding charges with casurina ballies, bamboos,

    wooden reapers, poles etc.

    Lintel = Rs. 1215/m3; Sunshades = Rs. 214/m2., Columns = Rs. 929/

    m2., Beams = Rs. 1637/m2.

    Slabs up to 150 mm. = Rs. 184/m2.

    Particulars

    Materials Cement

    Sand

    Coarse aggregate

    Labor: Head mason

    Mason

    Men mazdoor

    Women mazdoor

    Waterman

    Add 20% for labor

    Quantity

    2.74 bags

    0.475 m3

    0.95 m3

    0.05 No.

    0.15 No.

    1.2 NO.

    1.8 No.

    0.4 No.

    Rate

    Rs. 255/bag

    Rs. 375/m3.

    Rs. 588/bag

    Rs. 350/No.

    Rs. 315/No.

    Rs. 250/No.

    Rs. 250/No.

    Rs. 250/No.

    Total

    Cost

    Rs. 698.70

    Rs. 178.15

    Rs. 558.60

    Rs. 17.50

    Rs. 47.25

    Rs. 300

    Rs. 450

    Rs. 100

    Rs.182.95

    Rs.2533.15

    Particulars

    R.C.C(1:2:4) including cost of

    materials, labour charges,centering charges but excluding

    cost of steel and its fabrication.

    Materials

    Cement

    Quantity

    6.25 bags

    Rate

    Rs. 255/bag

    Amount

    Rs. 1593.75

  • 7/23/2019 Estimating & Costing

    57/83

    207Paper - II Estimating and Costing

    Sand

    Coarse aggregate

    Labour

    Head mason

    Mason

    Men mazdoor

    Women mazdoor

    Waterman

    Total cost of materials & labour

    = Rs.2760.30+1274.40=

    Rs.4034.70

    R.C.C. works in lintel, slab,

    beams and columns

    Centering charges with

    Casuarinas baileys, bamboos,

    poles, wall plates etc.

    Item

    Lintel

    Slab

    Beam

    Column

    0.434 m3

    0.868 m3

    0.05

    0.3

    1.2 No.

    2.0 NO.

    0.6 No.

    Centering

    charges

    including

    materials and

    labourRs.1215

    Rs. 1533.33

    Rs. 1637

    Rs.929

    Rs. 375/m3

    Rs. 1161.80/m3

    Total

    Rs. 350/No.

    Rs. 315/No.

    Rs. 250/No.

    Rs. 250/No.

    Rs. 250/No.

    20% local

    allowance

    Cost of

    materials and

    labour

    Rs. 4034.70

    Rs. 4034.70

    Rs. 4034.70

    Rs. 4034.70

    Rs. 162.75

    Rs. 1003.80

    Rs. 2760.30

    Rs. 17.50

    Rs. 94.50

    Rs. 300.00

    Rs. 500.00

    Rs. 150.00

    Rs. 1062.00

    Rs. 212.40

    Rs. 1274.40

    Total Cost

    Rs. 5249.70

    Rs. 5568.00

    Rs. 5671.70

    Rs. 4963.70

  • 7/23/2019 Estimating & Costing

    58/83

    Construction Technology208

    1 m3 of R.C.C. work requires approximately 90 kgs. of steel. The cost

    of fabrication of steel including bending and placement in position is Rs. 6.00/

    Kg.

    5.5.3 Brick masonry in cement mortar

    The size of the bricks considered are 19 cmx9 cmx9 cm. The volume

    of mortar is 0.32 m3. Cost of brick masonry for 1.0 m3 is considered.

    Number of bricks required = 500

    Mortar with a proportion of 1:6 is considered.

    Quantity of cement = 0.32/7=0.0457 m3=0.0457x1440/50=1.32 bags

    Quantity of Sand = 0.32x6/7=0.274 m3

    Cost of 1000 no. of bricks 19cmx9cmx9cm as per S.S.R. =Rs. 4687,

    Loading and unloading charges=Rs.37.30, Conveyance charges

    =118.65+17.80x10=Rs. 297.( for 15 K.M.)

    Total cost of bricks = Rs.4687+Rs.37.30+297=Rs.5021.30

    Quantity

    500 Nos.

    1.32 bags

    0.274 m3.

    Materials cost

    0.05 No.

    1.0 No.

    0.7 NO.

    1.0 No.

    0.2 No.

    Particulars

    Brick masonry in

    superstructure including cost

    of materials and labour

    Materials

    Bricks

    Cement

    Sand

    Labour

    Head mason

    Mason

    Men mazdoor

    Women mazdoor

    Waterman

    Rate

    Rs. 5021.30per

    1000 Nos.

    Rs. 255 per bag

    Rs. 490/m3.

    Total

    Rs. 350/No.

    Rs. 315/No.

    Rs. 250/No.

    Rs. 250/No.

    Rs. 250/No.

    Amount

    Rs.2510.65

    Rs. 336.60

    Rs. 134.30

    Rs. 2981.55

    Rs. 17.50

    Rs. 315.00

    Rs. 175.00

    Rs. 250.00

    Rs. 50.00

  • 7/23/2019 Estimating & Costing

    59/83

    209Paper - II Estimating and Costing

    5.5.4 Course rubble stone masonry(CRS) in cement mortar

    Quantity of stone required = 1.25 m3. Volume of mortar required=40%=0.4.

    Quantity of cement required for C.M. 1:6 = 0.4/7=0.06 m3=0.06x1440/

    50=1.8 bags.

    Total

    Add 20%

    Rs. 807.50

    Rs.161.50

    Rs. 969.00

    Rs. 3950.55Materials and Labour

    Total Cost

    Particulars

    Materials

    Stone including bond

    stone and wastage

    Cement

    Sand

    Labour

    Head mason

    Mason

    Men mazdoor

    Women mazdoor

    Waterman

    Total cost of materials and

    labour

    Quantity or No.

    1.25 m3.

    1.8 bags

    0.36 m3.

    0.05 No.

    1.6 No.

    1.6 No.

    0.8 No.

    0.15 No.

    Rate

    Rs.535.60/m3

    Rs. 255/ bag

    Rs. 490/m3.

    Rs. 350/No.

    Rs. 315/No.

    Rs. 250/No.

    Rs. 250/No.

    Rs. 250/No.

    Add 20%

    allowance

    Amount

    Rs. 669.5

    Rs. 459

    Rs. 176.40

    Rs. 1304.90

    Rs. 17.50

    Rs. 504.00

    Rs. 400.00

    Rs. 200.00

    Rs. 37.50

    Rs.1159.00

    Rs. 231.80

    Rs. 1390.80

    Rs. 2695.70

  • 7/23/2019 Estimating & Costing

    60/83

    Construction Technology210

    Quantity of sand= 0.36 m3. Cost of rubble stone =

    Rs.293+Rs.74.60+11.20x15 = Rs. 535.60 for a conveyance of 20 K.M.

    5.5.5 Plastering

    External plastering 20 mm. thick and Internal plastering 12 mm. thick.

    Materials for 20 mm. thick plastering in a wall of 100 sq. m.

    Volume of plastering = 100x20/1000=2.0 m3.

    Add 20% for wet volume and increasing 25% dry

    volume=2.0+0.4+0.6=3.0 m3.

    Cost of 1:6 cement mortar = Rs. 1553.00/m3. Cost of 3.0 m3 cement

    mortar=1553.00x3=Rs.4659.00

    Labour charges : Head mason =1/3 no. Cost=(1/3)x350=Rs. 116.70

    Mason=12 Nos. Cost=10x315=Rs. 3150.00 Men mazdoor=15 Nos.

    = 15x250= Rs. 3750.00

    Waterman= No. Cost = (3/4)x250=Rs. 187.50.

    Cost of labour = Rs.116.70+Rs. 3150+Rs.3750.00+Rs. 187.50= Rs.

    7204.20 Add 20% allowance =Rs. 1440.80. Total

    cost of labour = Rs. 7204.20+1440.80=Rs. 8645.00

    Total cost of external plastering=Rs.4659.00+ Rs. 8645.00=Rs.

    13304.00Cost of 20 mm. thick plastering/m2 = 13304.00/100= Rs.133.04

    Materials for internal plastering 12 mm. thick for 100 m2.

    Volume of plastering= 100x12/1000=1.2 m3. Add 30% for uneven

    surfaces and 25% for dry volume.

    Total volume of plastering = 1.2+0.36+0.29=1.95 m3. say 2.0 m3.

    Cost of 1:6 cement mortar for 1 m3= Rs. 1553.00 Cost of 2.0 m3

    mortar = 2x1553.00= Rs.3106.00

    Labour charges = Rs. 8645.00.

    Total cost of plastering 12 mm. thick = Rs. 3106.00+ Rs.8645.00=Rs.

    11751.00

    Cost of plastering 12 mm thick per m2= 11751/100=Rs. 117.51

  • 7/23/2019 Estimating & Costing

    61/83

    211Paper - II Estimating and Costing

    5.5.6 Pointing in cement mortar

    For pointing in brickwork the total dry volume of materials is taken as

    0.60 m3 for 100 m2.

    Pointing with cement mortar of proportion 1:2 : Dry volume of mortar

    = 0.60 m3

    Cost of mortar 1:2 for 1 m3=Rs. 2831.50. Cost of 0.6 m3 mortar =

    0.6x2831.50=Rs. 1699.00

    Labour :Head mason (1/3)x350=Rs. 116.70

    Mason = 10x315=Rs.3150.00; Men mazdoor=10x250=Rs.2500.00;

    Waterman=0.5x250=Rs. 125.00

    l Cost of labour = 116.70+3150+2500+125.00=Rs. 5891.70

    Add 20% allowance=Rs.1178.30; Total cost = 5891.70+1178.30=

    Rs.7070.00

    Total cost of materials and labour = 1699.00+7070.00=Rs.8769.00

    Cost of pointing per m2= 8769.00/100=Rs. 87.70

    5.5.7. Cement concrete flooring

    Considering 2.5 cm. thick concrete for an area of floor = 100 m2.

    Volume of concrete floor = 100x2.5/100=2.5 m3. Add 10% for

    unevenness of concrete

    Quantity of concrete = 2.5+0.25=2.75 m3. Add 50% for dry volume

    of concrete=1.375 m3.

    Total quantity of concrete= 2.75+1.375=4.125 m3.

    Quantity of cement required = 4.125/7=0.60 m3.=0.6x1440/50=18

    bags.

    Quantity of sand= 0.6x2=1.2 m3. Quantity of stone aggregate = 0.6x4

    = 2.4 m3.

    Cement for surface finishing = 100x2/1000=0.2 m3. = 0.2x1440/50=6bags.

    Cost of cement= Rs. 255/ bag; Cost of sand= Rs. 490/m3.; Cost of

    aggregate = Rs.1161.80/m3.

  • 7/23/2019 Estimating & Costing

    62/83

    Construction Technology212

    Cost of cement concrete flooring per sq. meter = 17491.00/100=Rs.174.91/sq m.

    5.5.8. Doors and windows paneled and glazed

    Consider preparation of door frame with Sal wood . The size of the

    door is 1.00 m. x 2.00 m.

    Particulars

    Materials

    Stone aggregate

    Sand (coarse)

    Cement

    Cement for surface

    finishing

    Labour etc.

    Head mason

    Mason

    Men mazdoor

    Women mazdoor

    Waterman

    Total cost of materials

    Total cost of labour

    Side forms for finishing

    Quantity or No.

    2.40 m3.

    1.20 m3.

    18 bags

    6 bags

    no.

    10 Nos.

    5 Nos.

    5 Nos.

    2 Nos.

    Add 20% extra

    Side forms

    Rate per

    Rs. 1161.80/m3.

    Rs. 490/m3.

    Rs. 255/ bag

    Rs. 255/ bag

    Rs. 350/day

    Rs. 315/day

    Rs. 250/day

    Rs. 250/day

    Rs. 250/day

    Lump sum

    Lump sum

    Total cost

    Amount

    Rs. 2788.40

    Rs. 588.00

    Rs. 4590.00

    Rs.1530.00

    Rs. 9496.40

    Rs. 262.50

    Rs. 3150.00

    Rs. 1250.00

    Rs.1250.00

    Rs.500.00

    Rs. 6412.50

    Rs.1282.50

    Rs. 7695.00

    Rs. 300.00

    Rs. 9496.40

    Rs. 7695.00

    Rs. 300.00

    Rs.17491.00

  • 7/23/2019 Estimating & Costing

    63/83

    213Paper - II Estimating and Costing

    Materials :Teakwood of cross section 8 cmx12 cm.

    Length of the frame = 2x( 2.14+1.2)=6.68 m. Quantity of

    timber=6.68x0.08x0.12=0.064 m3.

    Add 5% for wastage = 0.0032 m3. Total quantity of timber

    =0.064+0.0032=0.0672 m3.

    Rate of sal wood = Rs. 40012.00/m3.

    Cost of timber = 0.0672x40012.00= Rs. 2688.80

    Labour : Head carpenter =1/16 No. Cost =350x1/16= Rs.21.90

    Carpenter =1/4 No. Cost =315x1/4= Rs.78.75

    Men mazdoor = No. Cost =250x1/2= Rs.125.00Cost of labour Rs.225.65

    Add 20% allowance Rs.45.20

    Total cost of labour Rs.270.85

    Total cost of materials and labour = Rs. 2688.80+Rs.

    270.85=Rs.2959.65 say Rs. 2960.00

    Width of the plank=1.0-0.10-0.10-0.10=0.6 m. (Width of the stiles)

    Length of the plank = 2.0-0.10-0.10-0.10-0.15-0.10=1.55 m. (width

    of top, frieze, lock and bottom rails

    Unit rate of 40 mm. thick paneled door shutter of size 1.0x2.0 sq m.

    double door in teak wood.

    AmountParticulars

    Materials:-

    timber

    Stiles

    Top railFrieze rail

    Lock rail

    Bottom

    rail

    No.

    4

    1

    1

    1

    1

    L

    2.00

    1.00

    1.00

    1.00

    1.00

    B

    0.10

    0.10

    0.10

    0.15

    0.10

    Thick

    ness

    0.04

    0.04

    0.04

    0.04

    0.04

    Quantity/

    Nos.

    0.032

    0.004

    0.004

    0.006

    0.004

    Rate

  • 7/23/2019 Estimating & Costing

    64/83

    Construction Technology214

    Planks for

    panels

    Brass

    accessories

    Tower bolt

    30 cm.

    Tower bolt

    15 cm.

    Handle 10

    cm.

    Hinges

    Aldrop 30

    cm.

    Door

    stopper

    Labour

    Head

    carpenter

    Carpenter

    Helpers

    1

    1No.

    1No.

    2.no

    6.no

    1 No.

    1 No.

    1/15

    No.

    4 Nos.

    1.55

    Add

    5%

    0.6

    for

    Cost

    0.025

    wastage

    Of

    0.023

    0.073

    0.00365

    0.0767 m3

    1 No.

    1 No.

    2 Nos.

    6 Nos.

    1 No.

    1 No.

    accessories

    1/15 No.

    4 Nos.

    2 Nos.

    Rs.1054

    86.00/m3

    Rs.248

    .00/No.

    Rs.121.00/

    No.

    Rs.337.00/

    No..

    Rs.112.00/

    No.

    Rs.

    729.00/No.

    Rs.

    146.00/

    No.

    Rs. 350/

    day

    Rs. 315/day

    Rs. 250/

    day

    Rs.8090.80

    Rs. 248.00

    Rs.121.00

    Rs.674.00

    Rs. 672.00

    Rs. 729.00

    Rs.146.00

    Rs.2590.00

    Rs. 23.35

    Rs.1260.00

    Rs.500.00

    Rs.

    1783.35

  • 7/23/2019 Estimating & Costing

    65/83

    215Paper - II Estimating and Costing

    Cost of materials = Rs. 8090.80

    Cost of brass accessories=Rs.2590.00

    Cost of labour = Rs. 2140.00

    Total cost = Rs.12820.80

    Summary

    Specification defines the nature and class of work, materials to be used

    in the work, workmanship etc.

    Cost of materials at the source : The amount required to purchase

    the materials at the source of its production is the cost of materials at the source.

    Cost of materials at the site = Cost of materials at the source + Seignories

    + Taxes + Royalties + Transport + Loading + unloading etc.

    Cost of transport on metal led road is given in the S.S.R.

    Distance on cart track = 1.1 x Distance on metal led road

    Distance on sand track = 1.4 x Distance on metal led road

    Standard Schedule of Rates (S.S.R.) :Standard schedule of rates

    consists of the rates of materials, machinery, hiring charges and wages of labour.

    It is prepared by the board of chief engineers and approved for that year.

    Lead and Lift : The horizontal distance between the source of the

    material to the work site is known as the lead. The vertical height through which

    the material is lifted is known as the lift.

    Lead Statement :The statement in detail of the cost of materials at the

    site is known as the lead statement.

    Quantity of materials in Plain cement concrete (1:5:10) :

    Quantity of cement = 1.52 x 1/16 = 0.095 cu m. = 0.095 x 1440/50 =

    2.74 bags

    Quantity of sand = 1.52 x 5/16 = 0.475 cu m.

    Add 20%

    extraTotal

    Rs. 356.65

    Rs. 2140.00

  • 7/23/2019 Estimating & Costing

    66/83

    Construction Technology216

    Quantity of coarse aggregate = 1.52 x 10/16 = 0.95 cu m.

    Brick masonry in cement mortar for 1.0 cu m.

    Number of bricks of size 19 cm. x 9 cm. x 9 cm. = 500

    Volume of mortar = 0.32 cu m.

    Course rubble masonry :

    Quantity of stone = 1.25 cu m.

    Volume of mortar = 0.40 cu m.

    Plastering 20 mm. thick : The volume of cement sand mortar required

    for an area of 100 sq m. and a thickness of 20 mm. is 3.0 cu m.

    Plastering 12 mm. thick :The volume of cement sand mortar requiredfor an area of 100 sq m. and a thickness of 12 mm. is 2.0 cu m.

    Pointing : The volume of cement sand mortar required for pointing of

    an area of 100 sq m. with a mix proportion 1:2 is 0.60 cu m.

    Short Answer Type Questions

    1. Define specification.

    2. What is cost of materials at the source.?

    3. What is the cost of materials at the site?

    4. Write a tabular form for an abstract estimate.

    5. List out the various types of labour.

    6. Define standard schedule of rates.

    7. What is lead and lift?

    8. What is a lead statement.

    Long Answer Type Questions

    1. Prepare specifications for the following

    (a) Earthwork in excavation, (b) Cement concrete in foundation, (c) R.R. masonry, (d) Brick work in cement mortar.

    2. Find the unit rate for Plain cement concrete (1:6:12)

    3. Find the unit rate for course rubble masonry of cement mortar (1:6).

  • 7/23/2019 Estimating & Costing

    67/83

    217Paper - II Estimating and Costing

    4. Find the unit rate for brick work in cement mortar (1:6) using standard

    size of bricks.

    5. Find the unit rate of plastering 12 mm. and 20 mm. thick with a

    proportion of (1:5) cement mortar.

    O.J.T. Questions

    1. Prepare a unit rate of brickwork in cement mortar for 1.0 cu m.

    using modular bricks.

    2. Prepare a unit rate of R.C.C. (1:2:4) for 1.0 cu m. in slabs, beams

    and columns.

    3. Find the cost of a door (1.00m. x 2.00 m.) in country wood

    4. Find the cost of a window (1.2 m x 1.2 m) in Sal wood.

  • 7/23/2019 Estimating & Costing

    68/83

    Construction Technology218

    Structure

    6.0 Introduction

    6.1 Trapezoidal, Prismoidal, Mid ordinate

    6.2 Taking out quantities from L.S. and C.S. in cutting and embankment

    Learning Objectives

    After studying this unit student will be able to

    Calcualate the quantities of earth work in banking and cutting by

    Trapezoidal and Prismoidal Rule

    6.0 Introduction

    All types of roads, railways and irrigation works are constructed over

    earthwork. To understand the calculation of earthwork involved in these structures,

    these methods of calculation have to be studied in detail.

    Cross section of earthwork is in the form of a trapezium. The quantity of

    earthwork may be calculated by the following methods.

    6UNIT

    Earthwork Calculations

  • 7/23/2019 Estimating & Costing

    69/83

    219Paper - II Estimating and Costing

    6.1. Trapezoidal, Prismoidal, Mid ordinate

    Sectional and mean sectional area methods for calculating earthwork.

    Mid sectional area method : In the mid sectional area method, the

    average height of the two ends is taken as the mean depth. L is the length of the

    section. B is the formation width, and S:1 is the side slope and d1 and d2 are the

    height of the embankment at the two ends

    Mean height dm = (d1+d2)/2

    Area of midsection = Area of rectangular portion+ area of two triangular

    portions=Bdm+1/2sdm2+1/2sdm2=Bdm+2dm2.

    Quantity of earthwork = (Bdm+sdm2)xL

    The quantities of earthwork may be calculated in a tabular form as below

    Mean Sectional Area Method : In this method, the area at the ends

    of depth d1 and d2 are calculated and the mean area of the section is found.

    Sectional are at one end A1 = Bd1+S(d1)2

    Sectional area at the other end = Bd2+S(d2)2=A2

    The mean sectional area A=(A1+A2)/2

    Quantity Q=((A1+A2)/2)xL

    The quantities of earthwork may be calculated in a tabular form as follows

    Stations Depth

    or

    Height

    Mean

    depth or

    Height

    Central

    area Bd

    Area of

    sides Sd2

    Total

    sec

    tional

    area

    Bd+Sd2

    Length

    between

    stations L

    Quantity

    (Bd+Sd2)xL

    Embank

    ment cutt

    ing

    Station Height

    or depth

    Area of

    central

    port ion

    Bd

    Area of

    s i d e s

    Sd2

    T o t a l

    sectional

    a r e a

    Bd+Sd2

    M e a n

    sectional

    area

    Length

    between

    stations

    L

    Quantity

    =(Bd+Sd2)

    x LBankingCutting

  • 7/23/2019 Estimating & Costing

    70/83

    Construction Technology220

    Fig 6.1

    Trapezoidal-Prismoidal Formula : In the prismoidal formula the areas

    at the ends and the mid sectional area are als