Essentials of Slide-in Bridge Construction: A Guide for Bridge Designers
Bala Sivakumar
HNTB Corp.
Agenda
Introduction to ABC
Introduction to Slide-In Bridge Construction (SIBC)
Slide shoes
Movement systems
Components of SIBC design
Permanent Bridge Design
Temporary Support System
Push / Pull System
Sliding Bearings
Sliding Forces SIBC Case Study
Accelerated Bridge Construction (ABC)
ABC is bridge construction that uses innovative planning, design and construction methods to
reduce when replacing / rehabilitating existing bridges.
What is ABC ?
ABC Elements and Methods
ACCELERATED BRIDGE CONSTRUCTION
Prefabricated Elements &
Systems (PBES)
Accelerated Geo-tech Work
Rapid Demolition
Structure Placement Methods
Innovative Contracting
Benefits of ABC
Reduces disruption to operations/
service
Safer; reduces exposure of workers
and public to construction activities
Better quality control due to prefabricated
elements
Reduced environmental
impacts
Time Metrics for ABC – Mobility Impact Time
Mobility Impacts Within:
Tier 1: Overnight or < 24 hours
Tier 2: Weekend or < 3 days
Tier 3: Up to 2 weeks
ABC Time
1. On-site construction time
2. Mobility impact time (ABC closure period)
ABC can minimize both
Project R04
Innovative Bridge Designs for Rapid Renewal2007 – 2013
HNTB – Prime
SHRP 2 ABC Toolkit
• SHRP 2 ABC Toolkit
• Published 2012
– Prefabricated elements
– Slide-In Bridge Construction (SIBC)
www.trb.org
Prefabricated Elements & Systems (PBES)
• Multi-axle platform
• Each axle moves independently
• Moves on uneven terrain
Self-Propelled Modular Transporter (SPMT)
Lake Champlain Bridge, NY – Float-In
Slide in Replacement
What is Slide In Bridge Construction (SIBC)
• A method of accelerated bridge construction also known as horizontal or lateral sliding.
• New superstructure is built parallel to existing bridge on temporary supports.
• Old bridge is then demolished, new substructure constructed, and then new bridge is slid into place.
• In some instances the new substructure is constructed below the existing structure, this reduces the overall traffic disruption time.
Slide-In Bridge Construction (SIBC)
• Sliding technique allows the new superstructure to be built alongside the exiting reducing traffic impacts.
• Requires availability of ROW / space.
Alternate Approach to SIBC
• In other instances, the existing bridge is first slid off of the existing alignment and then used as a temporary bypass bridge while the new bridge is constructed on the old (existing) alignment.
• In this case, the temporary substructure system must not only provide support for the bridge, but also live load and other transient loads.
Impediments to Using SIBC
• Impediments to SIBC
– Limited ROW
– Terrain around existing bridge is rugged
– Geotechnical conditions cannot adequately support temporary works
– Alignment restrictions
When to Use SIBC
• Bridges on high ADT routes over low ADT routes
• Bridges over waterways
• Railroad bridges
• Ideal conditions for SIBC
– Wide, flat area(s) adjacent to original structure
NJ Transit Hogback Bridge – Gladstone LineWeekend Slide in Replacement 2004
3 June 2008 20
Roll-Out Roll-In Hood Canal Bridge WSDOT
Before During After
Roll-Out Roll-In New York City 2005
• Bridge over I-678 – Van Wyck Expressway
• NYSDOT
Slide Bearings
• Rollers• Teflon Pads
Skid Shoes
Skidding System
Sliding System Main Components: skid shoes, push-pull units, skid tracks, hydraulic pumps and a monitoring and control system.
VSL Skidding System
Series of Teflon pads are mounted on the skid track
Skidding System
• Special skid tracks are available for use when moving loads along curves.
• A simplified version called a skid beam can be used if the load does not need to be raised in the vertical direction
• Capacity up to 250 tons per shoe
Synchronous Jacking and Skidding Systems
Hydraulic Power Pack
Control System
Load, stroke in the skidding jacks is monitored on the control computer
Movement Systems
Push/Pull hydraulic jacks
Movement Systems
Push/Pull hydraulic jacks
Pulling with
strand jacks / Power winch
NJ TRANSIT,Hogback BridgeCome-Along cable puller
Movement Systems
Components of Slide-In Construction Design
1. Permanent Bridge Design
2. Temporary Support System
3. Push / Pull System
4. Sliding Bearings
5. Sliding Forces
1. Permanent Bridge Design
• The design of the permanent bridge must consider anticipated construction activities.
• Consideration of the how the new bridge will be slid into place.
• Strengthening or modifying components of the superstructure and the substructure
– Local areas where the push/pull system will be attached,
– Where the sliding plates and/or rollers will support the structure, and
– Where the sliding track will be installed.
• End diaphragms and end diaphragm connections which support the bridge during the lateral slide
• Flexural, shear effects on capbeam from moving vertical load
Slide Support at AbutmentI-84 NY Bridge Slide
Diaphragm Slide Shoe
End Diaphragm & Slide Shoes
2. Temp Support System (falsework)
• Design must consider all applicable load effects including environmental loads as well as the anticipated load effects applied by the sliding system. (Contractor designed)
• Relative stiffness of permanent support structures (likely relatively stiff) versus stiffness of temporary support structures (likely relatively flexible).
• Anticipated deflection / settlement of the temporary system.
• Provisions for vertical adjustment of track girder
• Attach the temp support to the permanent structure for lateral restraint
2. Temp Support System (falsework)
• Temporary works usually lies within the contractor’s responsibilities.
• Must be conducted by a competent, registered professional engineer.
• Geotechnical work must be the responsibility of the engineer of record.
• Additionally geotechnical borings and report may be required to ensure that the temporary foundation system operates as desired/needed.
Design of Temp Support System (falsework)
3. Push / Pull System
• Adequate force application to overcome frictional forces
• Hydraulic jacks offer the opportunity to either push or pull the system. Strand jacks and winches are used for “pull only”
• Pairs of opposing strand jacks and winches can be used to develop a push/pull system
• System controls to ensure all components of the push/pull system work together
• Displacement control during the slide to ensure that the ends of the superstructure move at the same rate and thus avoid any racking or binding.
• Contingency planning in the event of equipment failure
4. Sliding Bearings
• Steel rollers, slide plates or PTFE sliding bearings can be used as sliding elements.
• Rollers have higher load capacity
• Rollers and slide plates require removal whereas a slide bearings could be designed to remain as part of the permanent structure.
• Eliminates vertical jacking requirements at the conclusion of the slide, saving money and time
• Rollers are more costly than pads and are often used on bridge projects with larger load requirements.
4. Sliding Bearings
• Pads also allow the use of an unguided system that will not bind if ends of the bridge move at different rates.
• Continuous lubrication of the pads is critical during the slide. • Normally, the sliding surface of the shoe consists of polished
stainless steel. • Often, slide pads are reused in a slide as the bridge slides over
them. For the final move into the bridge’s permanent position, new pads are placed and left in place.
• Monitoring is especially important on bridges moved without guides.
Slide Shoes & Slide BearingsPTFE Bonded to Elastomeric Pad
5. Sliding Forces
• Coefficients of friction for PTFE (Teflon) bearings are given in the AASHTO LRFD Specifications.
• Static coefficients in the range of 0.09 to 0.12 and dynamic coefficients in the range of 0.05 to 0.06 . Rollers have lower friction values
• Use a trial slide to verify friction values
• Pushing or pulling mechanisms should have a capacity in excess of the calculated pushing or pulling force in anticipation of higher frictional effects.
FHWA SIBC Implementation Guides
Slide In Bridge Construction:
Case Study
SHRP2 Demonstration Project
Slide-In Bridge Construction Weekend Replacement of NY I-84 Twin Bridges
• 20 Hr closure• Two weekend nights• Sept 21, 2013• Oct 19, 2013
Weekend Replacement of NY I-84 Twin Bridges
• Over 75,000 ADT
• 16% trucks
• Existing bridges are too narrow for cross-overs
• Elevation differences between EB & WB roadways
• Underpassing road at 16% grade
Original Plan
• Build new temporary bridge in the median to maintain traffic
• Additional cost of approximately $2.0 M
• One construction season for each bridge
• Significant traffic impact
ABC Design: Slide-In Replacement
• Slide-In replacement over two weekend nights
• Traffic disruption on I-84 reduced from two years to two Saturday nights (20 hr closures).
• Incentive/disincentive clause: $10,000 per hour for early or late completion ($50 K max incentive)
• Eliminates need for a temporary bridge & cross-overs –over; $2 M savings.
• Both slides completed within 10 months after NTP
• Traffic detoured onto state Route 6 for 20 hrs.
ABC Approach
• Weekend Replacement
• 20 Hr Closure
Rapid Demolition – 4 Hrs
• Chop and Drop• Local road below closed
Superstructure Sections
• Double T beams (NEXT)
• Precast approach slabs
• UHPC closure pour
ABC Design - New Bridges
• Single span 80’; three lanes at 12’
• Left shoulder 6’, right shoulder 12’
• Bridge width 33’-4” 57’-0”
• Use of asphalt wearing surface eliminates grinding
• Under passing Dingle Ridge Road on 16% grade
• New bridges are two feet higher than the existing to provide 14’-6” under-clearance.
• Minimize structure depth using double Tee sections
Abutment Design
Drilled shafts supporting cap beam
T-Wall
Cap Beam
T-Wall Wingwalls
Drilled Shafts Outside Existing Footprint
New Abutment
Straddle Bent Abutment
Diaphragm
Cap Beam
Slide Shoe
Falsework
Temporary Bents on H piles
Contractor designed
Slide BearingsStainless Steel on Elastomeric Bearings w/PTFE
PTFE bonded to Elastomeric Bearing
Slide-In Replacement Concept
Slide Surface
Temporary end span
Modular walls
During Slide
Precast Approach Slabs Temporary End Spans Carrying Traffic
Inverted T Sleeper Slabs
Lateral Slide -- Oct 21 2013
7 hours to demolish bridge and slide-in new bridge
Raising The Approaches
• Takes time: Critical path for closure period
Bridge Slides Completed 10 Months After NTP
ABC Benefits
• Road Closure will be significantly reduced from two construction seasons to two weekends.
• Safety within the work zone will be improved.
• Reduced Costs primarily by not building the crossovers and temporary bridge in the median
($2.0 M savings)
• Impacts to the New York City watershed will be substantially reduced; at least 5 acres of land will not have to be disturbed using ABC.
ABC is the clear choice