COUNCIL REPORT
M&C No. 2017-103
Report Date April 11, 2017
Meeting Date April 18, 2017
Service Area Saint John Water
His Worship Mayor Don Darling and Members of Common Council SUBJECT: “Project Performance Update – Safe, Clean Drinking Water Project” OPEN OR CLOSED SESSION This matter is to be discussed in open session of Common Council. AUTHORIZATION
Primary Author Commissioner/Dept. Head City Manager
Dean Price Brent McGovern Jeff Trail
RECOMMENDATION It is recommended that this report be received for information and filed. EXECUTIVE SUMMARY The project team requests 15 minutes to present the attached presentation in open session of Common Council. The purpose of this presentation is to provide Council with a current project performance update on the Safe, Clean Drinking Water Project. PREVIOUS RESOLUTION At its meeting of January 23, 2017 M&C Report No. 2017-004 titled “Project Performance Update – Safe, Clean Drinking Water Project” recommended and Council RESOLVED that: The report be received for information and filed. STRATEGIC ALIGNMENT The Safe Clean Drinking Water Project remains a high priority and focus as it will bring safe, clean drinking water to the citizens of Saint John and reduce the occurrence of boil water orders and service interruptions through the construction of sustainable infrastructure.
163
- 2 -
SERVICE AND FINANCIAL OUTCOMES Not applicable INPUT FROM OTHER SERVICE AREAS AND STAKEHOLDERS Input was provided by Port City Water Partners. ATTACHMENTS
Power Point Presentation – “Project Performance Update – Safe, Clean Drinking Water Project”- Reporting Period – January – March 2017
PDF – “SCDWP Statistics” – Reporting Period – January – March 2017
164
Project Performance Update
“Safe, Clean Drinking Water Project”
April 18th, 2017
Reporting Period – January to March 2017
165
Executive Summary
Project Map
Project Status Dashboard
By the Numbers
Mini Milestones
Performance Measurement
Construction photos
Open Data Statistics – Appendix “A”
2
Table of Contents
166
3
Executive Summary
Results this Period (January to March 2017)
PCWP’s substantial completion date is on track as planned
(November 30th, 2018)
PCWP’s West works are currently scheduled for commissioning
in Summer of 2017
City Project team is auditing the designs, quality management
and the construction
Concrete foundations and first floor process for the WTP have
advanced significantly
167
Results this Period (January to March 2017) (Con’t)
Construction continues on 5 of the 13 components
Grouting between the new HDPE pipe and the old Cast Iron
pipe completed on Ocean Westway
Well house building now has walls and a roof
4
Executive Summary
168
5
Executive Summary
What’s Working PCWP have made significant progress in the last few months on the WTP
and the other components
Winter construction methods have allowed continued progress
Notices regarding construction have been delivered to all the homes and facilities in the work zone
PCWP have had face to face discussions with the business owners and facility managers in the area.
PCWP have met with Saint John Transit
PCWP have met with the Loch Lomond Villa
PCWP have met with Woodlawn School
PCWP have met with the business owners on Loch Lomond Road between Bon Accord and Hickey on April 7th to discuss traffic flow during the work Reminder - Two live webcams on WTP site for the public
169
6
Executive Summary
Next Steps (work between now & early summer ) Complete the manufacture of the precast insulated concrete
wall panels here in Saint John for the WTP Complete the pipework on the WTP site
Seek Council permission for temporary McLean Street
barricade removal and hold open house for residents in the area
Continue to pour concrete at the WTP site
Adjusting plans to assist local businesses
Erect precast walls at the WTP in June
Mechanical / Electrical at the new Wellfield Building
Work to modify the Spruce Lake Pump house 170
7
Executive Summary
Next Steps (work between now & early summer ) Remind residents that all businesses will be open and
accessible during construction work
Communicate construction impacts to residents (ongoing) Notices delivered to homes Discussion with each business in the impacted zones Meeting with some Loch Lomond Road Businesses on April 7th Other face to face meetings with schools and facilities Orange signs giving advanced warning have been put up along
impacted corridors Encourage residents to sign up for email notices Radio notifications to advise motorist Open House held on March 30th (Well attended) City-wide Traffic Advisories at www.saintjohn.ca
Access will be maintained for emergency vehicles such as fire
Residents can call the City’s Customer Service Line 658-4455
for questions or concerns 171
Project Map
| 8
2017 / 2018
172
9
Project Status Dashboard
Metric Status Trend Comment Return to Green Plan
Scope Steady No change in scope ----
Schedule Steady Project is currently on schedule.
West Milestone - PCWP is planning to complete the work in late summer instead of early summer as originally planned. They are attempting to fast track the completion.
Budget Steady Project is on budget ----
Risks Steady No major risks to date. ----
Overall Health Steady Good ----
G Y R Steady Progress YELLOW – Some concerns, actions being taken RED – Critical, major Issues
G
G
G
G
Y
173
By the Numbers January – March 2017
10
162 Concrete
Trucks
Pipe Installed
1 Kilometre
166 Tons of Rebar
0 Truckloads
of Asphalt
174
Mini-Milestones January – March 2017
11
Date Mini-Milestone Project Components
February 7th Start of fabrication of pre-cast panels
1-1 Water Treatment Plant
February 10th Finished Masonry of well field Control building
4-5 Well Site Development
February 23rd Started concrete for foundation of Tank #2
2-1 Storage at WTP
March 30th Started installation of Tank Floor for Tank #2
2-1 Storage at WTP
March 24th Started installation of roof of well field control building
4-5 Well Site Development
175
Performance Measurement January – March 2017
12
Construction Complete
% Percentage for all 13 components
Design Complete
% Percentage for all 13 components
97%
3%
SCDWP Design Completion
SCDWP Design Remaining
30%
70%
SCDWP Construction Completion
SCDWP Construction Remaining176
Performance Measurement
13
Length of Watermain Installed / Rehabilitated to date
13.6 km
12.4 km
Pipe installed Pipe Remaining
177
14
Number of Issued For Construction (IFC) drawings
received from PCWP
1921 IFC Drawings received
Performance Measurement
0
50
100
150
200
250
300
350
400
450
500
178
15
SCDW Project WTP Rendering
179
16
SCDW Project Water Treatment Plant Site
180
17
SCDW Project Insulated Precast Panels
181
18
SCDW Project Insulated Precast Panels
182
19
Construction Photos January – March 2017
February 28th, 2017
January 17th, 2017
1-1 Water Treatment Plant (WTP)
183
20
March 17th, 2017
March 14th, 2017
1-1 Water Treatment Plant (WTP)
Construction Photos January – March 2017
184
21
February 9th, 2017
Janaury 17th, 2017
2-1 Storage at WTP
Construction Photos January – March 2017
185
22
March 30th, 2017
March 2, 2017
2-1 Storage at WTP
Construction Photos January – March 2017
186
23
3-2 Latimer Lake Intakes and Dam Upgrades
Construction Photos January – March 2017
March 23rd, 2017
187
24
4-1 Lakewood Heights Pump Station to WTP
Construction Photos January – March 2017
March 21st, 2017
188
25
January 11th, 2017 January 10th, 2017
4-5 Well Site Development
Construction Photos January – March 2017
189
26
February 22nd, 2017 February 10th, 2017
4-5 Well Site Development
Construction Photos January – March 2017
190
27
March 14th, 2017 March 1st, 2017
4-5 Well Site Development
Construction Photos January – March 2017
191
28
February 1st, 2017
Butterfly valve installation
5-3 - Ocean Westway
Construction Photos January – March 2017
192
29
Appendix “A”
Note: See the attached Excel Spreadsheet with raw
data and graphs
Open Data Statistics January – March 2017
193
30
Questions?
194
SCDWP Statistics 11/04/2017
Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17
0 1 3 1 2 3 1 2 2 2 0 0 1
0 2 2 3 4 1 8 3 4 1 3 0 3
0 0 15 14 17 27 19 19 29 32 15 14 29
0 3 20 18 23 31 28 24 35 35 18 14 33
City Staff Audits
Monthly Total
Management System Audit
Design audits
Site Audits (Scheduled)
1195
SCDWP Statistics 11/04/2017
Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18
0
2
49
51
City Staff Audits
0
10
20
30
40
50
60
Feb
-16
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Feb
-17
Mar
-17
To
tal
Au
dit
s d
uri
ng
pe
rio
d
Period
City Staff Audits
Management System Audit
Design audits
Site Audits (Scheduled)
2196
SCDWP Statistics 11/04/2017
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17
0% 0% 0% 0% 38% 44% 48% 60% 75% 91% 94% 96% 97% 98% 99%
0% 0% 0% 0% 38% 42% 50% 60% 75% 95% 99% 99.5% 100% 100% 100%
0% 0% 0% 0% 45% 70% 80% 85% 90% 90% 95% 95% 95% 95% 95%
0% 0% 0% 0% 30% 50% 60% 65% 70% 75% 80% 80% 82% 84% 86%
0% 0% 0% 0% 60% 90% 95% 95% 100% 100% 100% 100% 100% 100% 100%
0% 0% 0% 0% 60% 90% 100% 100% 95% 100% 100% 100% 100% 100% 100%
0% 0% 0% 0% 30% 60% 70% 75% 50% 85% 90% 93% 95% 96% 98%
0% 0% 0% 0% 30% 60% 70% 75% 50% 85% 90% 92% 94% 95% 96%
0% 0% 0% 0% 70% 90% 100% 100% 100% 100% 100% 100% 100% 100% 100%
0% 0% 0% 0% 60% 70% 80% 80% 80% 85% 100% 100% 100% 100% 100%
0% 0% 0% 0% 40% 50% 60% 62% 85% 90% 95% 96% 96% 96% 97%
0% 0% 0% 0% 30% 40% 60% 62% 75% 75% 75% 76% 78% 80% 80%
0% 0% 0% 0% 55% 90% 100% 100% 95% 100% 100% 100% 100% 100% 100%
Design Completion Progress (total)
5-1 LHPS to Westmorland
Road (Structural Lining)
5-2 Rothesay Avenue
(Structural Lining)
5-3 Ocean Westway
(Structural Lining)
4-1 LHPS to WTP
4-2 WTP to Commerce
Drive
4-3 Loch Lomond Road
and Westmorland Road
4-4 East Pressure
Modifications
4-5 Well Site Development
4-6 Sruce Lake Pump
Station Upgrades
1-1 Water Treatment Plant
2-1 Storage at WTP
3-1 Robertson Lake Dam
3-2 Latimer Lake Intakes
and Dam Upgrades
2197
SCDWP Statistics 11/04/2017
99%
1% Primary Infrastructure Design Progress
Primary Infrastructure DesignCompleted
Primary Infrastructure DesignRemaining
96%
4%
Additional Infrastructure Design Progress
Additional Infrastructure DesignCompleted
Additional Infrastructure DesignRemaining
97%
3%
SCDWP Design Progress
SCDWP Design Completion
SCDWP Design Remaining
3198
SCDWP Statistics 11/04/2017
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17
0% 0% 0% 0% 1% 3% 3% 4% 4% 11% 16% 19% 21% 23% 25%
0% 0% 0% 0% 0% 0% 8% 12% 12% 16% 20% 22% 24% 26% 29%
0% 0% 0% 0% 0% 0% 0% 0% 6% 7% 7% 7% 7% 7% 7%
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
0% 0% 0% 0% 1% 2% 3% 17% 44% 45% 46% 46% 46% 46% 46%
0% 0% 0% 0% 1% 14% 38% 50% 42% 52% 58% 61% 67% 68% 68%
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
0% 0% 0% 0% 1% 14% 22% 22% 26% 35% 39% 44% 52% 52% 60%
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 2% 6%
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
0% 0% 0% 0% 1% 2% 9% 24% 28% 51% 55% 58% 58% 60% 85%
5-1 LHPS to Westmorland
Road (Structural Lining)
5-2 Rothesay Avenue
(Structural Lining)
5-3 Ocean Westway
(Structural Lining)
4-6 Sruce Lake Pump
Station Upgrades
Construction Completion Percentage (total)
1-1 water Treatment Plant
2-1 Storage at WTP
3-1 Robertson Lake Dam
3-2 Latimer Lake Intakes
and Dam Upgrades
4-1 LHPS to WTP
4-2 WTP to Commerce
Drive
4-3 Loch Lomond Road
and Westmorland Road
4-4 East Pressure
Modifications
4-5 Well Site Development
4199
SCDWP Statistics 11/04/2017
25%
75%
Primary Infrastructure Construction Progress
Primary Infrastructure ConstructionCompleted
Primary Infrastructure ConstructionRemaining
33%
67%
Additional Infrastructure Construction Progress
Additional InfrastructureConstruction Completed
Additional InfrastructureConstruction Remaining
30%
70%
SCDWP Construction Progress
SCDWP ConstructionCompletion
SCDWP ConstructionRemaining
5200
SCDWP Statistics 11/04/2017
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17
0 0 7 0 11 110 3 195 148 135 374 130 94 34 37
0 0 0 0 0 0 0 22 2 1 42 6 0 0 14
0 0 0 0 0 0 0 0 4 16 0 0 0 0 1
0 0 0 0 0 0 0 0 0 0 0 0 4 0 0
0 0 0 0 0 17 10 0 3 13 18 0 0 1 1
0 0 0 0 0 50 14 41 23 17 19 6 0 1 1
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 13 65 0 8 0 8 1 15 15 8
0 0 0 0 0 0 0 0 0 0 0 0 16 0 0
0 0 0 0 0 0 0 0 0 0 14 2 13 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 45 32 8 14 5 10 1 2 0 1
0 0 7 0 11 235 124 266 202 187 485 146 144 51 63 0 0
3-2 Latimer Lake Intakes and
Dam Upgrades
1921
Total
Issued for Construction Drawings Received
5-1 LHPS to Westmorland Road
(Structural Lining)
5-2 Rothesay Avenue (Structural
Lining)
5-3 Ocean Westway (Structural
Lining)
4-1 LHPS to WTP
4-2 WTP to Commerce Drive
4-3 Loch Lomond Road and
Westmorland Road
4-4 East Pressure Modifications
4-5 Well Site Development
4-6 Sruce Lake Pump Station
Upgrades
1-1 water Treatment Plant
2-1 Storage at WTP
3-1 Robertson Lake Dam
6201
SCDWP Statistics 11/04/2017
0
100
200
300
400
500
Mar
-16
Ap
r-1
6
May
-16
Jun
-16
Jul-
16
Au
g-1
6
Sep
-16
Oct
-16
No
v-1
6
De
c-1
6
Jan
-17
Feb
-17
Mar
-17
IFC Drawings Received
7202
SCDWP Statistics 11/04/2017
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16
1-1 water Treatment Plant N N N Y Y Y Y Y Y Y Y Y
2-1 Storage at WTP N N N Y Y Y Y Y Y Y Y Y
3-1 Robertson Lake Dam N N N N N N N N Y Y N N
3-2 Latimer Lake Intakes and Dam Upgrades N N N N N N N N N N N N
4-1 LHPS to WTP N N N Y N N Y Y Y Y Y Y
4-2 WTP to Commerce Drive N N N N Y Y Y Y Y Y Y Y
4-3 Loch Lomond Road and Westmorland Road N N N N N N N N N N N N
4-4 East Pressure Modifications N N N N N N N N N N N N
4-5 Well Site Development N N N Y Y Y Y Y Y Y Y Y
4-6 Sruce Lake Pump Station Upgrades N N N N N N N N N N N N
5-1 LHPS to Westmorland Road (Structural Lining) N N N N N N N N N N N N
5-2 Rothesay Avenue (Structural Lining) N N N N N N N N N N N N
5-3 Ocean Westway (Structural Lining) N N N N N N Y Y Y Y Y Y
Activity On site
8203
SCDWP Statistics 11/04/2017
Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18
Y Y Y
Y Y Y
N N N
N N N
N N N
Y Y N
N N N
N N N
Y N Y
N Y Y
N N N
N N N
Y Y Y
Activity On site
9204
SCDWP Statistics 11/04/2017
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16
Water Main ≥ 400mm (m) 0 0 0 0 0 1781 862 2048 112 2291 907 597
Water Main < 400mm (m) 0 0 0 0 0 0 0 271 514 100 15 0
Structural Lining (m) 0 0 0 0 0 0 0 0 767 273 2100 0
Monthly Total 0 0 0 0 0 1781 862 2319 1393 2664 3022 597
Remaing Pipe to install (m) 26000 26000 26000 26000 26000 24219 23357 21038 19645 16981 13959 13362
Total Installed (km) 13.625
Total Remaining (km) 12.375
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16
Concrete Poured (m3) 0 0 0 0 0 0 15 395 938 798 722 675
Concrete Poured (Truckload*) 0 0 0 0 0 0 2 52 123 104 94 88
Rebar Installed (kg) 0 0 0 0 0 4987 49000 126000 150000 35000 210000 106000
Total Rebar (t) 0 0 0 0 0 4.99 49.00 126.00 150.00 35.00 210.00 106
Asphalt (t) 0 0 0 0 0 0 600 600 1200 671 970 0
Asphalt (truckload**) 0 0 0 0 0 0 38 38 75 42 61 0
*Truckload of Concrete = 10 Cubic Yards per load = 7.65 Cubic Metres (approx)
** Truckload of Asphalt = 16 tonnes/truckload
Total Rebar (t) 847.99
Total Concrete (m3) 4783 Verified
Total Asphalt (t) 4041
Miscellaneous
Water Main Layed and Lined
13.6 km
12.4km
Kilometres of pipe installed
Pipe installed Pipe Remaining
9205
SCDWP Statistics 11/04/2017
Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18
623 32 165
36 36 95
0 0 0
659 68 260 0 0 0 0 0 0 0 0 0 0 0 0 0 0
12703 12635 12375 12375 12375 12375 12375 12375 12375 12375 12375 12375 12375 12375 12375 12375 12375
Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18
601 139 500
79 18 65 0 0 0 0 0 0 0 0 0 0 0 0 0 0
72225 65520 28575
72.00 66 29
0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Miscellaneous
Water Main Layed and Lined
10206
SCDWP Statistics 11/04/2017
Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17
0 0 0 1 5 6 27 26 9 13 7 1 3
0 0 0 0 1 1 2 2 1 0 0 0 0
0 0 0 0 0 0 3 0 0 0 0 0 0
Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18
1 8
0 0
0 0
Customer Disruption
Customer Phone Calls
Traffic Detours
Service Disruptions
Customer Phone Calls
Traffic Detours
Service Disruptions
10207