environmental management...
TRANSCRIPT
ENVIRONMENTAL MANAGEMENT PLAN FOR THE PROPOSED RESIDENTIAL APARTMENT
“BALAJI DEVELOPERS”
By
M/s. BALAJI DEVELOPERS
BBMP Khatha New No. 1375/113, Old No. 219/2,
Pattanduru Agrahara Village, K R Puram Hobli,
Bangalore East Taluk
BY
Mahesh & Dev
17/1, VSN Road
Tasker Town, Bangalore 560 052
Tel: No: 22868425
Environmental Management Plan
Balaji developers
PROJECT AT GLANCE
1 Name & Designation
Correspondence Address
Mr. ARAVINDER REDDY MANAGING PARTNER M/s BALAJI DEVELOPERS No. 272/1 In front of Mytri layout E3 Lakshminarayapura Opharm Circle Whitefield Post Bangalore - 560066
2 Project Description Residential Apartment
3 Location BBMP Khatha New No. 1375/113, Old No. 219/2, Pattanduru Agrahara Village, K R Puram Hobli, Bangalore East Taluk,
4 Number of Sites/Flats 125
5 Total Plot Area 4922.76 Sq.M
6 Total Built up Area
F A R
Coverage
21620.78 Sq.M
3
37.86%
7 Total Plinth Area 1642.30Sq.M
8 Open space/green area 1431.51 Sq.M works out to 33%
9 Height of the Building 2B+ GF + 8 floors, 26.8mts
10.
10.A
10.B
Proposed Water Supply
Number of People
Water Consumption in KLD
BWSSB
625
84
11.
11.A
11.B
Proposed Sanitation
Sewage Quantity in KLD
S T P CAPACITY
Fully fledged treatment plant
67
70
12
12.A
12.B
Solid waste generated
Organic waste
In organic waste
281. 25 Kgs
168.45 Kg/day proposed to Compost and
use as Manure
112.5 Kg/day proposed to hand over to
municipal authorities
13 Configuration 2B+ GF + 8 floors
14 Car Parking Provided 141
15 Status of the Project Yet to start
16 Cost of the project 487 lakhs
Environmental Management Plan
Balaji developers
AREA STATEMENT
AREA OF PLOT : 4922.76 Sq.M
ALLOWABLE F A R : 3
COVERAGE : 37.86 %
TOTAL BUILTUP AREA : 21620.68Sq.M
CAR PARKING PROVIDED : 141 car parks provided
LAND : 250 LAKHS
BUILDING 21620.68 Sq.M
@ 11000/- per Sq.M : 237.27 LAKHS
TOTAL COST : 487 LAKHS
Environmental Management Plan
Balaji developers
ENVIRONMENTAL MANAGEMENT PLAN
1 Introduction
The Environmental management plan (EMP) is necessary to ensure sustainable development
in the area of the proposed project. Hence it needs to be an all encompassing plan for which the
Industry, Government, Regulating agencies likes pollution control board working in the region
and more importantly the population of the area need to extend their co-operation and
contribution.
It has been evaluated that the project area will not be affected significantly with the proposed
project. Mitigation measures at the source level and an overall management plan at the site level
are elicited so as to improve the surrounding environment.
The following mitigation measures are recommended in order to synchronize the economic
development of the project area with the environmental protection of the region. The
construction phase impacts are mostly short term, restricted to the plot area and not envisaged on
the larger scale. In the operational phase the environmental impacts are due to continuous
operation of the project, hence, the emphasis in the environment management plan (EMP) is to
minimize such impacts. The emphasis on the EMP development is on the following:
Mitigation measures for each of the activities causing the environmental impact
Monitoring plans for checking activities and environmental parameters and
monitoring responsibilities.
Role responsibilities and resources allocation for monitoring.
Following sections describes the environment management plan proposed for construction and
operation phases.
1.1 Management during Construction Phase
In the impact assessments following four activities have been identified as causing impact of
different degrees on the environment during construction phase:
1. Site clearance
2. Transportation of construction materials
3. Construction activity
4. Labour camps of construction workers
1.2 Mitigation measures
Environmental Management Plan
Balaji developers
Each of the above activities during construction phase is critically reviewed for suggestion of
mitigation measures. Based on this, the Table 1.1 to 1.4 gives the mitigation measures for the
activities considered to be causing significant environmental impacts during construction phase.
In general the best housekeeping practices are incorporated in the design as well as construction
phase to reduce the short terms impacts due to construction activities.
TABLE: 1.1
EMP FOR CONSTRUTION PHASE IMPACTS “SITE CLEARING”
Environmental
Impacts
Mitigation
Remarks
Soil erosion Extent of vegetation removal shall be
minimized to prevent extent of soil
erosion.
Vegetative cover shall be reprojected
/rehabilitated at the earliest practicable
time to minimize duration & extent of
soil erosion.
Implementation
Responsibility:
Contractor
Project consultants
Balaji Developers.
Noise generation Selection of equipment with less noise
generation to be used.
The earth moving equipment shall be
periodically checked and maintained
for noise levels. Since the site is more
or less even use of these earth moving
equipments may not be necessary.
The workers shall be provided with
adequate PPE such as earplugs to
reduce impact of high noise levels.
Implementation
Responsibility:
Contractor
Project consultants
Balaji Developers.
Dust generation The site cleared shall be periodically
watered to reduce emission of dust
particles.
The workers shall be provided with
PPE such as nose marks and goggles
to reduce impact on health.
Implementation
Responsibility:
Contractor
Project Consultants
Balaji Developers.
Environmental Management Plan
Balaji developers
TABLE: 1.2
EMP FOR CONSTRUCTION PHASE IMPACTS “TRANSPORTATION OF
CONSTRUCTION MATERIALS “
Environmental
Impacts
Mitigation
Remarks
Noise generation
A periodic maintenance vehicle is
required.
Implementation
Responsibility:
Contractor
Project consultants
Balaji Developers.
Dust generation Construction materials shall be
covered with tarpaulin sheets to
prevent the material from being air
borne.
The vehicle speed shall be regulated
The workers transporting materials
shall be provided with PPE such as
nose asks to reduce impact of air
borne dust on their health
Implementation
Responsibility:
Contractor
Project consultants
Balaji Developers.
Vehicular
Emission Periodic emission check for vehicles is
required.
Clean fuel shall be used for vehicles
Implementation
Responsibility:
Contractor
Project consultants
Balaji Developers.
Environmental Management Plan
Balaji developers
TABLE: 1.3
EMP FOR CONSTRUCTION PHASE IMPACTS “CONSTRUCTION ACTIVITIES”
Environmental
Impacts
Mitigation
Remarks
Noise generation Personnel protective Equipment (PPE)
such as ear plugs and helmets shall be
provided for construction workers.
The working hours shall be imposed
on construction workers.
Implementation
Responsibility:
Contractor
Project consultants
Balaji Developers.
Dust generation PPE in the form of nose masks shall
be provided for construction workers.
Use of water sprays to prevent the dust
contractor from being air borne.
Implementation
Responsibility:
Contractor
Project consultants
Balaji Developers.
Air Emissions
From
construction
machinery
Periodic check and regular maintenance of
construction machinery for emissions clean
fuel shall be used in equipments
Implementation
Responsibility:
Contractor
Project consultants
Balaji Developers.
Environmental Management Plan
Balaji developers
TABLE: 1.4
EMP FOR CONSTRUCTION PHASE IMPACTS “LABOUR CAMPS”
Environmental
Impacts
Mitigation
Remarks
Domestic
Wastewater
generation
Provision of adequate sanitary
facilities.
2 No.s 5kl septic tanks shall receive
wastewater. And cleaned periodically
Implementation
Responsibility:
Contractor
Project consultants
Balaji Developers.
Usage of water
Water for Labour camps shall be
supplied in required quantities and
from panchayat supply.
Implementation
Responsibility:
Contractor
Project consultants
Balaji Developers.
Solid waste
generation
Adequate facilities to handle solid-
wastes shall be provided and it will be
regularly disposed to panchayat.
Implementation
Responsibility:
Contractor
Project consultants
Balaji Developers.
1.3 Management during Operation Phase
Following are the identified operational phase activities which may have impact on the
environment.
Air Quality
Water Quality
Noise Quality
Solid waste disposal
Green belt development
Environmental Management Plan
Balaji developers
1.3.1 Air Quality Management
The Pollutants envisaged from the proposed project are SPM SO2, NOx, HC and CO mainly due
to burning of liquid fuel (HSD) in DG. Exhaust from DG set will be emitted from stack of
adequate height for dispersion of gaseous pollutants. The green belt development is also
proposed on the plot area. Following Table 1.5 presents the EMP for air quality management
during operation phase.
TABLE: 1.5
MANAGEMNT OF AIR QUALITY DURING OPERATION PHASE
Environmental
Impacts
Mitigation
DG Set Equipment selected will ensure the exhaust emission
standards as prescribed as per the latest amendments from
the ministry of environment & forest, Government of India.
DG will be used as stand – by unit.
Periodic check and maintenance
Ambient air
Quality Ambient air quality monitoring as per the prescribed norms
at regular interval.
1.3.2 Water Quality Management
TOTAL NO OF PERSONS
Number of abodes planned 125 Apartments
Total No of Persons = 625
Water requirement per capita per day = 125 x 135 = 84100 Liters= 84 KLD
Total Water requirement = 84 KLD
Total quantity of domestic sewage generated = 67 KLD
Sewage Treatment plant designed for the proposed Site - = 70 KLD
Environmental Management Plan
Balaji developers
1.3.3 SEWAGE TREATMENT PLANT
The design is made keeping in mind the total quantity of generation of 67000 lts per
day. The modular technology is adopted in the design, i.e. when the flow increases drastically,
the present units itself can be used with additional units attaching to it in modules, which would
be economical and saves on the area required too.
Characterization:
The general characteristic of untreated and treated sewage is considered as shown in the
table below.
Parameters Before Treatment After Treatment
pH 6.0 to 8.0 7.0 to 7.5
Suspended Solids 250 to 400 < 20
BOD 200 to 300 < 10
COD 400 to 600 250
Residual Chlorine > 1
Mode of Treatment:
It is proposed to set up a treatment plant for treating the domestic waste using the tested
and trusted activated sludge process with extended aeration through diffused aeration. The other
modes of treatment considered before arriving at activated sludge process are SAFE (Submerged
aerated fixed film reactor), SBR (Sequential Batch Reactor), RBC (Rotary Biological
Contractor). The advantages and disadvantages of the each scheme, initial investment and
maintenance cost etc were compared and finally arrived at the activated sludge process.
Environmental Management Plan
Balaji developers
The units proposed for the proposed STP with activated sludge process are:
SL.
NO.
Name of the Unit
Purpose
1. Bar Screen Chamber
For removing unwanted floating materials
2.
Equalization Tank To even out the flow variations, and continuous
uniform mixing operations with course bubble.
3. Aeration Tank Activated Sludge process for developing the bacterial
culture, which stabilizes the waste aerators.
4. Secondary Clarifier To separate out the solids from the treated sewage, And
to separate clear supernatant water
5. Pre-Filtration Tank To collect the supernatant clear water from the
secondary clarifier for further treatment.
6. Mechanical Filter Press To de-water the sludge taken out of settling tank and to
convert the same into manure.
7. Pressure Sand Filter To filter out minute suspended solids if any in the
treated water.
8. Activated carbon Filter To remove color and odor if any in the filtered water.
9. U V RADIATION FLOW
THROUGH SYSTEM
To disinfect the treated water to make it safe to come in
contact with humans so that the treated water can be
used for gardening.
Environmental Management Plan
Balaji developers
TREATMENT FLOW CHART:
Fig. 7.2 Treatment Flow Chart
Pumps
140 KLD RAW SEWAGE
SludgeExcess
Disposal as Manure
Sludge To
PressMechanical Filter
Sludge
Recycle
FlushingTo Resuse for Gardenings/
Final Holding Sump
DisinfectionU.V Radiation for
Activated Carbon Filter
FilterPressure Sand
Pre Filteration Sump
Clarifier Tank
Aeration Tank
Equalization Tank
Bar Screen Chamber
Environmental Management Plan
Balaji developers
Design of the individual units:
Bar Screen Chamber: Provide a chamber of size 1.5 m x 1.0 m to suit sewer gradient to accommodate an
inclined bar screen with opening less than 10 mm. Provide a bar screen of 20 x 6 mm flats with
10mm spacing in between.
Design Criteria:
Velocity through screen : 0.8 m/Sec.
Discharge : Discharge / day x 8 / 24
: = 67000 x 8/24
: = 0.34 Cum. /Sec
Peak Load : 0.34 x 3.0 = 1.02 cum /Sec
Adopting screens with bars of 6mm width and 10 mm clear opening considering 1.2 times the net
area of opening,
Net area = 1.02 x 10 /0.80
= 12.75 m
Gross area = 1.2 times of the net area of opening
= 1.2 x 12.75
= 15.3
= 3.91sqmts
Gross area of screen needed would be 2.8 x 1.4 Mt. for ease of maintenance.
Environmental Management Plan
Balaji developers
Equalization tank:
The flow from the bar screen chamber is let into the equalization tank of minimum 8 hours
capacity. This tank is provided to even out the flow variation, and to provide a continuous feed
into the secondary biological treatment units.
Design Flow = 67000/day
Provide min 8 hours holding capacity.
Hence required volume of the tank = 22.33 m3
Provide a tank of 25 m3. Capacity.
The tank size would be 6.0 x 2.5 x 2.0 m (effective volume)
Aeration tank with extended aeration (Activated Sludge Process )
Flow Rate : 67 m3/Day ~ 6.08 m3/Hr
Inlet BOD 5 @ 20 C : 250 mg/Ltr.
Organic Load : 67 x 250/1000 = 16.75Kgs / Day
Total oxygen required Assuming
that 2.2 kgs of O2/kg of BOD
Removal : 36.85 Kgs/day.
F/M : 0.15
MLSS : 4000mg/litre
Volume of the Tank required : 250 x 67/ 0.15 x 4000
27.9 m3
Total Volume Including 30 % Extra
Volume for Sludge Recirculation : 36.27 m3
Size of Aeration Tank Required : 8 m x 2.25 x 2.0 m SWD
Air required for aeration : 700 m 3/Hr
Type of aeration : Membrane Fine pore diffused
Aeration system.
Environmental Management Plan
Balaji developers
No. of membrane required : 24 Nos. of 1.0 m long.
Function : To aerate the contents of the
Aeration tank and to sustain the
Biological activity so as reduces
The organic load.
% of Oxygen in air = 0.21 Density of air = 1.2
Therefore air requirement in Cum. / Hr
= 67 x 100 = 279.16 cum / Hr.
24
Consider 40% excess considering the air required in the equalization tank.
Total air required = 390.83 cum / Hr.
Hence provide2 blowers each of 200 cum / Hr.
One as standby with an operating pressure of 0.5 KSC.
Transfer rate of oxygen in 1 mt. Long membrane diffusers = 10 cum / hr.
Therefore total no. Of membranes required =390.83 / 10
= 40 Nos.
Secondary Clarifier with sludge scraping mechanism:
The over flow from the aeration tank will be taken into the secondary clarifier separation
of biological floc.
Design quantity 67 KLD considering
Design Surface loading rate = 20 cum / m / day
Area of the tank required = 73 m3
The tank size shall be of 6.5 m x 4.5 m with 2.5 m depth for easy sludge settling allowance.
Environmental Management Plan
Balaji developers
Clarified Water/ Final Treated water Sump:
The flow from the settling tank i.e., the supernatant liquid is let into the clarified Tank, which has
a minimum 16 hours holding capacity. This tank is provided to hold the treated effluent and give
an even flow to the pressure sand filter.
Design flow = 67 KL/day
Provide min 8 hours holding capacity.
Hence required volume of the tank = 22.33 m3
Provide a tank of 25 KL. Capacity.
The above tank is divided into 2 compartments each of 15 and 10 for final effluent and clarified
water respectively.
The dimension of each tank will be 4 x 2.5 x 1.5 m and each. 4x1.5x2.0 m
Pressure sand Filter :
Flow = 67KL/day
Loading rate = 3.33 cum/ Sq.M. / Hr
Considering the operation of 20 hours of filter
Provide a pressure sand filter of 650 mm dia with sand as media over layer, under drainpipe,
Laterals face piping etc.
Activated Carbon Filter :
Flow = 67 KL/day
Loading rate = 3.33Cumec/Sq.M/hr.
Considering the operation of 20 hours of filter
Provide an activated carbon filter of 650-mm diameter with activated carbon filter media with
under drainpipe, lateral face piping.
Environmental Management Plan
Balaji developers
ULTRA VIOLET RADIATION
The filtered water is further passed through an online automatic U V radiation flow through
system for disinfection. Provide one no. 20000 Lts capacity U V flow through system
Pumps: a. Provide 2 Nos. Sewage transfer pumps (One working and one standby)
Capacity : 15 KLH @ 12.0 m head
Type : Open impeller non-clog centrifugal pumps
Make : Kirloskar
Solid handling size : Up to 10 mm
Duty: To pump the sewage from the Equalization tank to the Aeration Tank.
b. Provide 2 Nos. Sludge transfer pumps (one working and one standby)
Capacity : 7.5 KLS/hr @ 15.0 m head
Type : Open impeller non-clog centrifugal pumps
Make : Kirloskar
Solid handling size : Up to 10 mm
Duty : To Pump the sludge from the settling tank
To the sludge drying beds.
c. Provide 2 Nos Filter feed pumps (One working and one standby)
Capacity : 20 KLH @ 30.0m head
Type : Open impeller non-clog centrifugal pumps
Make : Kirloskar
Solid handling size : Up to 10 mm
Duty: To pump the treated effluent from the pre- filtration tank through the pressure sand filters
and activated carbon Filter.
Environmental Management Plan
Balaji developers
Filter Press:
Filter press mechanically operated plate type with collection trays etc., is provided for sludge
disposal.
Type : Rail slider
Plate Size : 18”x 18”
No. of Plates : 38 Nos
No. of chambers : 37 Nos
Area of Filtration : 4.5 M²
Cake holding capacity : 45 Litres
Operating pressure : 7 kg/cm2
1.3.4 SOLID WASTE MANAGEMENT
A. Solid waste consist of
1. Garbage
2. Ashes
3. Rubbish
4. Dust Etc.
Solid waste is broadly divided into
1) Organic or combustible matter.
2) Inorganic or mineral or non- combustible matter.
The solid waste generated during operation phase can be categorized under three types:
Domestic/Residential waste
Wet Garbage: Food waste, Lawn mowing wastes etc.
Dry Garbage: Paper, plastic, Bottles, etc.
Sludge from sewage Treatment Plant (STP)
The solid waste generated in the premises is estimated to be about 281.25 Kg/d, which will be
sent to proposed composting unit for further processing, Reusable items such as plastic bottles,
cold drinks, Meta/Glass containers, etc are sold to Recyclers.
Environmental Management Plan
Balaji developers
The various mitigation measures to be adopted during collection and disposal of wastes are as
follows:
It is preferable that the container and bins used for collection of waste should be of closed
type of that the waste is not expected and thus the possibility of spreading of disease
through flies and mosquitoes is minimized.
Collection system should be properly supervised so that quick and regular removal of
waste from the dustbin is practiced.
Door to door collection will be arranged in each commercial unit to collect the solid
wastes. The biodegradable wastes will be segregated and sent to the proposed composting
unit. Non-biodegradable wastes such as plastic materials, glass & metal wastes will be
handed over to the waste recyclers.
Quantity of Domestic Solid Waste
Quantity of domestic solid waste
Generated per day from the proposed Project
Total No of Persons = 625
= 625 X 0.45 = 281.25 Kgs Day
Total quantity from the establishment = 281.25Kg/day
Environmental Management Plan
Balaji developers
Disposal of solid waste generated
Solid waste generated in the premises to the following agencies for safe disposal.
Table 1.7: Solid waste Generation
Sl.
No.
Waste Quantity Treatment & Disposal
1. Total solid waste
Organic
Inorganic
281.25 Kgs/Day
168.75 Kgs/Day
112.5 Kgs/Day
Organic waste will be
composted at the project site
and inorganic waste will be
handed over to the BBMP door
to door collection facility.
2. STP Sludge 11.25 Kgs/Day STP Sludge will be used for
green belt development in the
project site.
B. Hazardous Waste Management
Waste oil from D.G’ Sets.
About 750 Liters of waste oil per year will be generated from standby DG sets. This will be
stored in leak-proof sealed barrels and will be given to KSPCB authorized waste oil re-
processors.
1.3.4 Noise Level Management
High noise generated units such as DG set will be provided with acoustic enclosures. Green belt
on the project boundary will further act as noise barrier and helps in attention of noise.
Following Table – 1.8 presents the EMP for noise levels.
Environmental Management Plan
Balaji developers
Table: 1.8
MANAGEMENT OF NOISE LEVELS DURING OPERATIONAL PHASE
Environmental
Impacts
Mitigation
Noise from DG
set area
DG set will be installed in an area (Utility section ) where the access
will be restricted
The use of PPD ( ear plugs) will be mandatory is this area selection
of equipment to ensure that the residual noise level of 75 dB ( A )
Noise levels will be checked periodically using a noise pressure
level meter
1.4 Green Belt Development
Green belt development (1431.55 Sq m) within the premises will reduce noise levels and dust
levels. To make the green belt effective for this purpose, it is essential to select proper plant
species and design the plant and row spacing that result in lowering the sheltering effect. In the
development of green belts multipurpose plant species should be selected. This will satisfy the
ecological requirement for species diversity.
1.5 Storm Water Disposal through Rain Water Harvesting
Rain water from roof tops, balconies etc. is allowed to flow through down take pipes that are
sloped to the concealed storm water collection tanks. This water can be used for house gardening
and for other domestic purpose for washing vehicles, etc.
Rain water from other sections of the site is led to catchments pit at each change in flow
direction and at each change in pipe diameter with horizontal & vertical grating depending upon
the road section.
Design of piping network is done on the basis of:
Site Topography & Effective Area
Sizing by Rationale’s Formula with full running pipe
Run-off Coefficient
Environmental Management Plan
Balaji developers
Rain water from all the roads is routed to the side drains on either side of the road which is
designed as per the Metrological report; intensity of rainfall is taken as 75mm – 100mm per hour.
Percolation pits can be provided below the tank bed of the collection tanks, thereby recharging
the ground water table as well.
Rain water harvesting will be done by both collection for reuse and ground water recharge.
For assessing the available quantum of water it is assumed that incidental rain fall less than 10
mm will not yield any collectable yield and such rain fall account for 50% of the total rainfall.
The runoff coefficient 0.9 for impervious surface, 0.7 for roads and driveways 0.55 for pervious
surfaces like gardens and soil surfaces is considered, duly accounting for evaporation, seepage
etc.
Rain Water Harvesting:
Rain fall & Yield from terrace
Annual average rain fall = 975 mm
Hence co-efficient of run off will be 0.9
Yield Available = 0.975 x 0.9 x 1645
= 1405 cum
Rain fall & Yield from driveways
Annual average rain fall = 975 mm
Hence co-efficient of run off will be 0.7
Yield Available = Area x 0.975 x 0.7
=1301 x 0.975 x 0.7
= 865 cum
Environmental Management Plan
Balaji developers
Rain fall & Yield from green way runoff
Annual average rain fall = 975 mm
Hence co-efficient of run off will be 0.55
Yield Available = Area x 0.975 x 0.55
=1431 x 0.975x 0.55
= 680cum
The Rainfall harvesting potential for the project is collectively 2950 cum annually. Which can
cater the needs for about 53days.
Rain water harvesting is proposed by means of
1. Collection tank of 100cum x 1no.s
2. Infiltration galleries of 0.45m x 0.45 m in the bed of storm water drain.
3. Recharge pits of 2M X 2M in open spaces. 21in No.
Mode of Usage of rain water:
The Ground water will be recharged through 21 No. of percolation pits. Each pit has a
capacity to absorb in excess of water. The balance water will be collected in two tanks of 1.0 ML
capacity each. The water collected in rainwater collection sump will be used for car washing
purposes after passing through the pressure sand and the activated carbon filter of diameter 650-
mm each.
Mode of usage of water incase of sudden flash floods / continuous rains: though the rainy
days are considered as 120 days in Bangalore and the total rain is divided by the no. of rainy
days, practically the intensity of rain is not the same every day. It varies from day to day. Incase
when there is a heavy and flash rain, the excessive rainwater is led into the existing municipal
storm water drain.
Environmental Management Plan
Balaji developers
1.6 Monitoring Strategy
The monitoring of various environmental parameters is necessary which is a part
And parcel of the environmental protection measures. A comprehensive monitoring
Programme is suggested below:
TABLE – 1.9
MONITORING SCHEDULE FOR ENVIRONMENTAL PARAMETERS
Sr.
No.
Particulars
Monitoring
Frequency
Duration of
monitoring
Important
Parameters for
Monitoring
I Air Quality
1 Ambient Air monitoring
project premises
Once in a month 24 hrly sample TSPM, RPM,
SO2, Nox.
2 Stack Monitoring Once in a month Grab SO2, SPM, Nox
HC, CO
II Water and wastewater Quality
1 Water Quality
i Ground water at two
locations ( up-gradient &
down-gradient) of treated
effluent discharge area/ land
Once in a month Grab As per KSPCB
requirements
2 Waste Water Quality
i Inlet to STP Daily Composite -
ii Treated effluent prior to
discharge
Daily Composite -
III Soil Quality
1 Within project premises at 1
location on effluent
discharging area land
Once in a month Composite
sample
As per KSPCB
requirements
2 Ecological preservation and
Up gradation
Seasonal Visual
Observations
Survival rate
IV Noise Quality Once in a month 24 Hrs
Monitoring
Noise levels in
Db(A)
Environmental Management Plan
Balaji developers
FINANCIAL ALLOCATION/ BUDGETORY PROVISIONS FOR
ENVIRONMENTAL MANAGEMENT ASPECTS DURING OPERATION
PHASE (per annum)
Sl. No
Description
Financial provisions (Rs In Lakhs)
Capital Cost Recurring cost
01 Construction of Sewage Treatment Plant 48.0 --
02 Operation of Sewage Treatment Plant per annum -- 6.5
03 Rain Water Harvesting Tanks and its facilities 8.0 1.0
04 Rain Water Recharging pits and its management 2.5 0.5
05 DG Maintenance -- 1.0
06 Landscaping, Top soil conservation 4.0 2.0
07 Solid Waste Management 4.0 1.0
08 Environment Monitoring Plan (Air, Noise, Water
and Solid Waste)
-- 2.0
TOTAL 66.5 13
Environmental Management Plan
Balaji developers
RISK ASSEMENT AND DISASTER MANAGEMENT PLAN
8.1 Introduction
Rapid development of the city has posed wide-ranging hazards threatening safety and
health of people. Accidents may adversely affect the environment and the people living in the
vicinity. These accidents can be minimized to a great extent by proper procedures, handling and
training. But it may be difficult to reach zero risk or absolute safety level. Whenever such
incidents do occur in order to prevent loss of lives and damage to property, it becomes necessary
to take immediate steps to control the situation. This can be achieved through a planned advance
preparation to face such a situation with respect to both on site and off site emergencies.
8.2 On – Site Management Plan
The On-site plan will be circulated to all concerned members of emergency teams. It is
essential that all concerned familiarize themselves with the overall on-site emergency plan and
their respective roles and responsibilities during and emergency. They should also participate
regularly in the mock drills that will be conducted so as to keep themselves and the emergency
organization in a state of perpetual preparedness at all times at all times to meet any emergency.
8.2.1 Objectives, Scope and contents of On-site Emergency Plan
Objective of Emergency planning are to maximize the resource utilization and combined
efforts towards emergency operations and would broadly cover the following.
1. To localize the emergency and if possible eliminate it.
2. To minimize the effects of accidents on people and property.
3. To take remedial measures in the quickest possible time to contain the incident and
control it with minimum damage.
4. To mobilize the internal resources and utilize them in the most effective way.
5. To get help from the local community and government officials to supplement internal
manpower and resources.
6. To minimize the damage in other sections.
7. To keep the required emergency equipment in stock at right places and ensure that they
are in working condition.
8. To keep the concerned personnel fully trained in the use of emergency equipment.
9. To give immediate warning to the surrounding localities in case of an emergency
situation arising.
10. To mobilize transport and medical treatment of the injured.
11. To educate the public in the surrounding villages regarding hazards.
12. To arrange for rescue and treatment of casualties.
13. To safe guard the people.
14. To identify the causalities and communicate to relatives.
Environmental Management Plan
Balaji developers
15. To render necessary help to concerned.
16. To rehabilitate area affected.
17. To provide information to media & government agencies.
8.2.2. Scope of Onsite Emergency Plan
The plan covers information regarding the properties of the commercial complex and
Multiplex, type of disasters and disaster/accident – prone zones, the actual disaster control plans
with authority delegation, controlling and other details. General details like locations, project
layout, neighboring entities and the assistance they can render etc., are also provided.
The important elements considered in this plan are
Statutory requirements
Emergency organization
Roles and responsibilities
Communications during emergency
Emergency shutdown & control of situation
Rescue & Rehabilitation
Emergency facilities
Important Information
The primary purpose of the on-site emergency plan of DMP is to control and contain the incident
and so to prevent if from spreading. It is not possible to cover every eventuality in the plan and
the successful handling of the emergency will depend on appropriate action and decisions being
taken on the spot. Other important aspects needing to be considered include the following:
8.3 Emergency
A major emergency in any situation is one, which has the potential to cause serious injury
or loss of life, which may cause extensive damage to the structures in the vicinity and
environment and could result in serious disruption to normal operation both inside and outside
the layout premises. Depending on the magnitude of the emergency, services of the outside
agencies may also be required for supplementing the internal effort to effectively handle the
emergency and to contain the damage.
The Management has to take effective steps to assess, minimize and wherever feasible
eliminate the risks to a large extent. Accidents may still occur and it is necessary to be fully
prepared to tackle all such emergencies if and when they occur.
It is likely that the consequences of such emergencies will be confined to the units
concerned or may affect outside. If the consequences are confined within the plant boundary, it is
then termed as on site Emergency and will be controlled by chief emergency controller.
Environmental Management Plan
Balaji developers
In order to generate the plans it is necessary to first determine the kinds of accidents
leading to an emergency that can occur in the layout. The most widely used technique in practice
is based on experience accumulated over many years and safety audits.
A. Methodology
The considerations in an emergency planning include the following:-
Identification and assessment of hazards and risks.
Hazard, consequence analysis
Alarm and communication procedures
Identifying, appointment of personnel & assignment of responsibilities
Identification and equipping emergency control center, identifying Assembly, Rescue
points, Medical facilities.
Emergency preparedness plan, procedures, steps to be taken before, during and after
emergency.
Formulation of plan and emergency sources.
Training rehearsal, evaluation and updating the plan
B Structure of Emergency Management
a) Nothing the accidents
b) Informing declarer of emergency
c) Declaration of emergency
d) Functions of declaration
e) Interaction with outside agencies
C Identification and Assessment of Hazards
This stage is crucial to both on-site and off-site emergency planning and requires
systematic identification of all possible emergencies that could arise in the plants. These should
range from small events, which can be dealt by plant personnel without any help from external
agencies to the largest event that would require outside help. The tackle such emergencies
effectively, it is essential to have clear-cut action plan. Experience has shown that for every
occasion that the full potential of an accident is realized, there are many occasions when some
lesser event occurs or when developing incident is made safe before reaching full potential.
D Infrastructure at Emergency Control Center
Emergency control centers should therefore contain the following
An adequate number of external telephones; if possible, one should accept
Environmental Management Plan
Balaji developers
Only outgoing calls, in order to bypass jammed switchboards during an
Emergency.
A adequate number of internal telephones
Radio equipment
A plan of the works, to show:
Areas where there are large inventories of hazardous materials.
Sources of safety and first aid equipment.
The fire-fighting system and additional sources of water.
Site entrance and roadways, including up-to-date information on road
Traffic.
Assembly points.
Vehicle parking and rail sidings.
Additional work and layout plans detailing alternate routes and affected area,
during an emergency.
Note pads, pens and pencils.
A nominal role of employee.
A list of key personnel, with addresses, telephone numbers, etc.
The emergency control center should be sited in an area minimum risk. Suitable location from
where clear view of the plant is possible or the control room can be designated as emergency
control center. All the site controller/ Incident controller officers, senior personnel would be
located here or have access to the ECC.
E. Emergency Medical Facilities
Stretchers, gas masks and general first aid materials for dealing with chemical burns, fire
burns, etc., would be maintained in the medical center as well as in his emergency control room.
A range of medicines should be maintained in the ECC/ medical center. Breathing apparatus and
other emergency medical equipment should be provided and maintained.
The medical center should display poster for treating burns and first aid. Some medicines
and facilities to be kept in the medical center are suggested. The list is indicative and the
qualified doctors of the medical center should use their professional judgment for medical
treatment.
Environmental Management Plan
Balaji developers
F Health and Safety Measures for the Workers
a. Buildings and Structures: No walls, Chimneys, Galleries, Stairways, floor,
platform, staging or structure whether of a permanent or temporary character shall
be constructed in such manner as to cause risk or bodily injury.
b. Provision of crawling boards etc: No person shall be required to stand to pass
over on or near by any roof of ceiling cover with fragile material through which he
is liable to fall, in case it breaks or gives away the distance for more than 3 meters
without use of sufficient number of suitable ladders, duck ladders or crawling
boards which are securely supports.
c. Service Platforms: Whenever practicable and demanded service platforms
and gangways will be provided for overhead shafting, and where required by him
these will be securely fence with guard rails and toe boards.
d. Belts, etc: All belts will be regularly examined to injure that the joints are safe
And the belts are proper tension.
e. Helmets: Helmets will be provided to the workers for safe guarding themselves
Against any head injuries.
f. Machinery: No machineries are equipments will be situated, operated or
Maintained in such a manner as to cause risk of bodily injury.
g. Methods of work: No process of work will be carried out in such a manner as
To cause risk of bodily injury.
h. Electricity: No electricity installation shall be provided during construction so
As to be dangers to human life or safety.
i. Medical Check-up: Medical examination every worker shall be examined by
Certified surgeon at least once in 3 months of a calendar.
G. Emergency action plans
a. Emergency Action Plan for Cylinder Fire:
1. When filled container containing LPG is involved in fire, internal pressure if not relieved,
shall build up above 70KG/SQCM and ultimately rupture the container. Rupture weak by
direct flame impingement. Ruptured containers can be propelled at distance by jet action.
2. If container’s pressure is not raised upto 70KG/SQCM leakage from screwed valve joint
can occur due to different expansion of steel and brass.
Environmental Management Plan
Balaji developers
3. Ignition of the escaping gas would aggravate the fire but release of fire reduces the
possibility of rupture.
4. No attempt should be made to extinguish the burning gas but the container under fire and
other containers in vicinity should be kept cool by water spray.
5. If the gas leakage does note ignite, the container should be approached from up and
removed to the place of safety away fro, the source of ignition.
b. Emergency Action Plan for Electric Fire:
1. Disconnect the affected areas electric supply.
2. Attempt to extinguish fire with the help of Co2, DCP.
3. If fire is not extinguished, extinguish by spraying water with fog nozzle after ensuring
complete isolation of electric circuit.
c. Emergency Action Plan for Office Fire:
1. Disconnected electric supply of the affected area.
2. Attempt to extinguish the fire with the help of Co2, DCP and sand.
3. If large fire, use hydrant system.
4. Attempt to save the record.
5. Attempt fire extinguisher.
d. Emergency Action Plan for Oil Fire:
1. Attempt to extinguish small fire with the help of DCP
2. If the fire is not controlled, use water foam to blanket the fire and further action is to be
taken.
e. Emergency Action Plan for Medical Aid:
f. Emergency Action Plan for Electric Shock Casualties:
Electric Shock results in:
Irreversible damage to brain cell begins followed by deterioration of the organs.
Rescue and first aid:
Do first aid quickly and without fuss and panic.
Switch off the supply if this can be done at once.
If not possible use a dry stick, dry cloth or other non-conductor to separate the victim
from electrical contact.
Environmental Management Plan
Balaji developers
The reducer must avoid receiving shock himself by wearing gloves or using a jacket to
pull the victim.
Always keep in mind that delay in rescue and resuscitation may be fatal. Every sound
counts.
ii. Artificial Respiration: Give artificial respiration if breathing has stopped. There are several methods of artificial
respiration, if the victim is nit injured over the face, try mouth to mouth.
a) Mouth to Mouth Method:
If there is obstruction to breathing, remove it with your fingers if it in mouth. Several
sharp blows between shoulder blade may help to is lodge an obstruction.
Lie casually on his back, put something under his shoulder to raise them & allow his
head to fall backwards. The head should be, if possible be a little lower than the trunk.
Remember that speed is essential.
Kneel at the causalities head and grasp his arms at the wrists then cross them firmly
over the lower chest. This movement should force air out of his lungs. Press with the
hands crossed on the lower part of the chest and maintain pressure for two seconds.
Release this pressure and pull out his arms with a sweeping movement upwards and
outwards above his head and backwards as far as possible.
This movement should cause air to be drawn in to his lungs. Retain the arms in this
position for three seconds.
Repeat these movements rhythmically about twelve times a minute checking the mouth
frequently for obstructions. Each cycle will thus take give seconds- two seconds for
hest pressure and three seconds for arm lift.
With the causality on his back there is danger of aspiration of vomit, mucus or blood
reentering the system. Keeping his head extended and a little lower than the trunk can
reduce this risk.
If an assistant is available, he can press the causality lower jaws so that the chin is
jutting out.
The assistant should also ensure that the mouth is kept open as far as possible and head
is tilted to one side.
When natural breathing begins, your movement should be adapted to correspond to it.
If burns are present, cover them with a dry sterile dressing
Handle the causality gentle
Do not allow people to crowd around and block fresh airflow
Arrange to remove the injured to the care of a doctor ad early as possible.
Environmental Management Plan
Balaji developers
f. Natural Hazards
i. Emergency Action Plan for Tornado/High Winds:
a. Weather reports shall be monitored from broadcast warnings threatening conditions.
b. If the tornado has been sighted or effect is felt, following steps should be taken by plant
personnel.
Persons shall be notified over public address system or through siren.
Emergency services shall be alerted for assistance.
Plant personnel should be advised to assemble in the administration building
basement, staff room, recreation room and rest rooms.
All safety systems should be kept on alert and all nonessential utilities should be
put off.
After the status is restored, personnel should inspect all the facilities for resource,
first aid and damage control activities, damage assessment, and clean up,
restoration and recovery.
ii. Emergency Action Plan for earthquakes
a. When first tremors are sensed during an earthquake, all personnel should evacuate
Buildings and assemble at safe place away from structures, walls and falling objects.
Emergency shut down should be declared.
b. Emergency services should be contacted for assistance.
c. After the status is restored, personnel should inspect all the facilities for rescue,
First aid and damage control activities, damage assessment, cleanup, restoration and
Recovery.
Environmental Management Plan
Balaji developers
g. Emergency Action Plan for Bomb Threat
When bomb threat cell is received the following measures are to be taken.
Inform the message to the highest local police authority and seek their assistance for
patrolling and security need.
Inform controller of Explosives the details and nature of the anonymous message and
read operations.
Request the local fore Brigade to position at least on fire tender at the location
immediately.
Keep the concerned Dept. at the Regional level informed with the developments at
regular intervals.
Alert the local Govt/Pvt. Hospitals and seek their help for providing Ambulances if
necessary
In The Location Premises:
Keep the fire Hydrant system/all fire Fighting and personnel protective equipment in
readiness
Every one entering the Location must be frisked at the Gate/Check all hand bags, Parcels
etc., for suspected explosive/ dangerous objects.
Have through inspection of the Location for any suspected dangerous object.
Materials and other boxes to be brought in to the Location must be deposited at gate for
minimum curing period of 48 Hrs.
Organization Employees Vigilance cell for round the clock observation for our premises.
Objects of suspicion In case of finding of suspected Articles, do not disturb its position, but the area around it
should be cordoned off to a distance of 100 meters and more depending upon the gravity
of situation.
Adequate staff or police Squad posted to prevent any unauthorized entry into the enforced
cordon.
Contact Controller of Explosives immediately, who on reaching the site will decide
suitable action for defusing and disposal of the suspected object.
Evolution of thick billowing smoke is an indication of impending explosion and in such a
case, with draw or evacuates all personnel from the spot, which has been identified.
As a general measure regulate the movement of the outsiders inside our premises and restrict
their entry with permits.
Environmental Management Plan
Balaji developers
9.1 Construction Phase
The number of concrete mixers, cranes, transport vehicles, etc. should be kept to an
optimum level to minimize risks of accidents.
Temporary colonies of the work force etc should have proper sanitation including toilets
and bathrooms. Sewage and other wastes generated in these settlements should be
collected and disposed of in an environmental friendly manner.
The construction noise level should be kept to a minimum particularly during the
excavation and slab construction.
The dust generation should be controlled by water sprinkling at regular interval at the site
and nearby roads.
Dedicated driveways should be marked for movement of construction equipments and
vehicles.
All personnel working at the site should be properly trained in safety procedures needs to
follow.
The personnel should also be trained in the operation of fire fighting machineries.
The personnel should also be made aware of the importance of wearing personal
protective equipments at all times as directed by their supervisor.
9.2 Operational Phase
Utilizing the experiences gained by the local environment during the construction period should
assemble a plan of action for mitigating the predicted adverse effects.
a. Traffic Control
Speed limit of 20 Km/h should be specified for roads within the premises
The separation of pedestrian movement and vehicular traffic should be strictly enforced.
b. Solid Waste
All House keeping persons working in the BALAJI DEVELOPERS must be trained to
segregate the bio-
Degradable waste from the non-bio-degradable waste, so that the quantity which requires
To be disposed off through vermin composting or any other safe method of disposal,
Thereby reducing the load on environment.
Good housekeeping practices should be maintained which helps in prevention of
contamination of soil through improper spillage of solids wastes and other materials.
Environmental Management Plan
Balaji developers
c. Full pledged Environmental Management cell exclusively for the proposed should be
constituted with qualified Engineers.
CONCLUSION
Any type of development activity has both beneficial and adverse impacts on the environment in
which it operates. The impacts are identified and evaluated by the project proponents to reduce
their negative effects and maximize the positive effects. The proposed Residential apartment
project is being developed to meet the city’s ever growing appetite for housing with good
ambience facilities. It is being ideally located in the midst of the city; the location of the project
also offers many distinct advantages.
The proposed project will have no Negative impact on the environment if the recommended
environmental management aspects were fully implemented.