environmental management...

36
ENVIRONMENTAL MANAGEMENT PLAN FOR THE PROPOSED RESIDENTIAL APARTMENT BALAJI DEVELOPERSBy M/s. BALAJI DEVELOPERS BBMP Khatha New No. 1375/113, Old No. 219/2, Pattanduru Agrahara Village, K R Puram Hobli, Bangalore East Taluk BY Mahesh & Dev 17/1, VSN Road Tasker Town, Bangalore 560 052 Tel: No: 22868425

Upload: truongthien

Post on 01-Apr-2018

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

ENVIRONMENTAL MANAGEMENT PLAN FOR THE PROPOSED RESIDENTIAL APARTMENT

“BALAJI DEVELOPERS”

By

M/s. BALAJI DEVELOPERS

BBMP Khatha New No. 1375/113, Old No. 219/2,

Pattanduru Agrahara Village, K R Puram Hobli,

Bangalore East Taluk

BY

Mahesh & Dev

17/1, VSN Road

Tasker Town, Bangalore 560 052

Tel: No: 22868425

Page 2: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

PROJECT AT GLANCE

1 Name & Designation

Correspondence Address

Mr. ARAVINDER REDDY MANAGING PARTNER M/s BALAJI DEVELOPERS No. 272/1 In front of Mytri layout E3 Lakshminarayapura Opharm Circle Whitefield Post Bangalore - 560066

2 Project Description Residential Apartment

3 Location BBMP Khatha New No. 1375/113, Old No. 219/2, Pattanduru Agrahara Village, K R Puram Hobli, Bangalore East Taluk,

4 Number of Sites/Flats 125

5 Total Plot Area 4922.76 Sq.M

6 Total Built up Area

F A R

Coverage

21620.78 Sq.M

3

37.86%

7 Total Plinth Area 1642.30Sq.M

8 Open space/green area 1431.51 Sq.M works out to 33%

9 Height of the Building 2B+ GF + 8 floors, 26.8mts

10.

10.A

10.B

Proposed Water Supply

Number of People

Water Consumption in KLD

BWSSB

625

84

11.

11.A

11.B

Proposed Sanitation

Sewage Quantity in KLD

S T P CAPACITY

Fully fledged treatment plant

67

70

12

12.A

12.B

Solid waste generated

Organic waste

In organic waste

281. 25 Kgs

168.45 Kg/day proposed to Compost and

use as Manure

112.5 Kg/day proposed to hand over to

municipal authorities

13 Configuration 2B+ GF + 8 floors

14 Car Parking Provided 141

15 Status of the Project Yet to start

16 Cost of the project 487 lakhs

Page 3: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

AREA STATEMENT

AREA OF PLOT : 4922.76 Sq.M

ALLOWABLE F A R : 3

COVERAGE : 37.86 %

TOTAL BUILTUP AREA : 21620.68Sq.M

CAR PARKING PROVIDED : 141 car parks provided

LAND : 250 LAKHS

BUILDING 21620.68 Sq.M

@ 11000/- per Sq.M : 237.27 LAKHS

TOTAL COST : 487 LAKHS

Page 4: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

ENVIRONMENTAL MANAGEMENT PLAN

1 Introduction

The Environmental management plan (EMP) is necessary to ensure sustainable development

in the area of the proposed project. Hence it needs to be an all encompassing plan for which the

Industry, Government, Regulating agencies likes pollution control board working in the region

and more importantly the population of the area need to extend their co-operation and

contribution.

It has been evaluated that the project area will not be affected significantly with the proposed

project. Mitigation measures at the source level and an overall management plan at the site level

are elicited so as to improve the surrounding environment.

The following mitigation measures are recommended in order to synchronize the economic

development of the project area with the environmental protection of the region. The

construction phase impacts are mostly short term, restricted to the plot area and not envisaged on

the larger scale. In the operational phase the environmental impacts are due to continuous

operation of the project, hence, the emphasis in the environment management plan (EMP) is to

minimize such impacts. The emphasis on the EMP development is on the following:

Mitigation measures for each of the activities causing the environmental impact

Monitoring plans for checking activities and environmental parameters and

monitoring responsibilities.

Role responsibilities and resources allocation for monitoring.

Following sections describes the environment management plan proposed for construction and

operation phases.

1.1 Management during Construction Phase

In the impact assessments following four activities have been identified as causing impact of

different degrees on the environment during construction phase:

1. Site clearance

2. Transportation of construction materials

3. Construction activity

4. Labour camps of construction workers

1.2 Mitigation measures

Page 5: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

Each of the above activities during construction phase is critically reviewed for suggestion of

mitigation measures. Based on this, the Table 1.1 to 1.4 gives the mitigation measures for the

activities considered to be causing significant environmental impacts during construction phase.

In general the best housekeeping practices are incorporated in the design as well as construction

phase to reduce the short terms impacts due to construction activities.

TABLE: 1.1

EMP FOR CONSTRUTION PHASE IMPACTS “SITE CLEARING”

Environmental

Impacts

Mitigation

Remarks

Soil erosion Extent of vegetation removal shall be

minimized to prevent extent of soil

erosion.

Vegetative cover shall be reprojected

/rehabilitated at the earliest practicable

time to minimize duration & extent of

soil erosion.

Implementation

Responsibility:

Contractor

Project consultants

Balaji Developers.

Noise generation Selection of equipment with less noise

generation to be used.

The earth moving equipment shall be

periodically checked and maintained

for noise levels. Since the site is more

or less even use of these earth moving

equipments may not be necessary.

The workers shall be provided with

adequate PPE such as earplugs to

reduce impact of high noise levels.

Implementation

Responsibility:

Contractor

Project consultants

Balaji Developers.

Dust generation The site cleared shall be periodically

watered to reduce emission of dust

particles.

The workers shall be provided with

PPE such as nose marks and goggles

to reduce impact on health.

Implementation

Responsibility:

Contractor

Project Consultants

Balaji Developers.

Page 6: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

TABLE: 1.2

EMP FOR CONSTRUCTION PHASE IMPACTS “TRANSPORTATION OF

CONSTRUCTION MATERIALS “

Environmental

Impacts

Mitigation

Remarks

Noise generation

A periodic maintenance vehicle is

required.

Implementation

Responsibility:

Contractor

Project consultants

Balaji Developers.

Dust generation Construction materials shall be

covered with tarpaulin sheets to

prevent the material from being air

borne.

The vehicle speed shall be regulated

The workers transporting materials

shall be provided with PPE such as

nose asks to reduce impact of air

borne dust on their health

Implementation

Responsibility:

Contractor

Project consultants

Balaji Developers.

Vehicular

Emission Periodic emission check for vehicles is

required.

Clean fuel shall be used for vehicles

Implementation

Responsibility:

Contractor

Project consultants

Balaji Developers.

Page 7: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

TABLE: 1.3

EMP FOR CONSTRUCTION PHASE IMPACTS “CONSTRUCTION ACTIVITIES”

Environmental

Impacts

Mitigation

Remarks

Noise generation Personnel protective Equipment (PPE)

such as ear plugs and helmets shall be

provided for construction workers.

The working hours shall be imposed

on construction workers.

Implementation

Responsibility:

Contractor

Project consultants

Balaji Developers.

Dust generation PPE in the form of nose masks shall

be provided for construction workers.

Use of water sprays to prevent the dust

contractor from being air borne.

Implementation

Responsibility:

Contractor

Project consultants

Balaji Developers.

Air Emissions

From

construction

machinery

Periodic check and regular maintenance of

construction machinery for emissions clean

fuel shall be used in equipments

Implementation

Responsibility:

Contractor

Project consultants

Balaji Developers.

Page 8: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

TABLE: 1.4

EMP FOR CONSTRUCTION PHASE IMPACTS “LABOUR CAMPS”

Environmental

Impacts

Mitigation

Remarks

Domestic

Wastewater

generation

Provision of adequate sanitary

facilities.

2 No.s 5kl septic tanks shall receive

wastewater. And cleaned periodically

Implementation

Responsibility:

Contractor

Project consultants

Balaji Developers.

Usage of water

Water for Labour camps shall be

supplied in required quantities and

from panchayat supply.

Implementation

Responsibility:

Contractor

Project consultants

Balaji Developers.

Solid waste

generation

Adequate facilities to handle solid-

wastes shall be provided and it will be

regularly disposed to panchayat.

Implementation

Responsibility:

Contractor

Project consultants

Balaji Developers.

1.3 Management during Operation Phase

Following are the identified operational phase activities which may have impact on the

environment.

Air Quality

Water Quality

Noise Quality

Solid waste disposal

Green belt development

Page 9: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

1.3.1 Air Quality Management

The Pollutants envisaged from the proposed project are SPM SO2, NOx, HC and CO mainly due

to burning of liquid fuel (HSD) in DG. Exhaust from DG set will be emitted from stack of

adequate height for dispersion of gaseous pollutants. The green belt development is also

proposed on the plot area. Following Table 1.5 presents the EMP for air quality management

during operation phase.

TABLE: 1.5

MANAGEMNT OF AIR QUALITY DURING OPERATION PHASE

Environmental

Impacts

Mitigation

DG Set Equipment selected will ensure the exhaust emission

standards as prescribed as per the latest amendments from

the ministry of environment & forest, Government of India.

DG will be used as stand – by unit.

Periodic check and maintenance

Ambient air

Quality Ambient air quality monitoring as per the prescribed norms

at regular interval.

1.3.2 Water Quality Management

TOTAL NO OF PERSONS

Number of abodes planned 125 Apartments

Total No of Persons = 625

Water requirement per capita per day = 125 x 135 = 84100 Liters= 84 KLD

Total Water requirement = 84 KLD

Total quantity of domestic sewage generated = 67 KLD

Sewage Treatment plant designed for the proposed Site - = 70 KLD

Page 10: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

1.3.3 SEWAGE TREATMENT PLANT

The design is made keeping in mind the total quantity of generation of 67000 lts per

day. The modular technology is adopted in the design, i.e. when the flow increases drastically,

the present units itself can be used with additional units attaching to it in modules, which would

be economical and saves on the area required too.

Characterization:

The general characteristic of untreated and treated sewage is considered as shown in the

table below.

Parameters Before Treatment After Treatment

pH 6.0 to 8.0 7.0 to 7.5

Suspended Solids 250 to 400 < 20

BOD 200 to 300 < 10

COD 400 to 600 250

Residual Chlorine > 1

Mode of Treatment:

It is proposed to set up a treatment plant for treating the domestic waste using the tested

and trusted activated sludge process with extended aeration through diffused aeration. The other

modes of treatment considered before arriving at activated sludge process are SAFE (Submerged

aerated fixed film reactor), SBR (Sequential Batch Reactor), RBC (Rotary Biological

Contractor). The advantages and disadvantages of the each scheme, initial investment and

maintenance cost etc were compared and finally arrived at the activated sludge process.

Page 11: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

The units proposed for the proposed STP with activated sludge process are:

SL.

NO.

Name of the Unit

Purpose

1. Bar Screen Chamber

For removing unwanted floating materials

2.

Equalization Tank To even out the flow variations, and continuous

uniform mixing operations with course bubble.

3. Aeration Tank Activated Sludge process for developing the bacterial

culture, which stabilizes the waste aerators.

4. Secondary Clarifier To separate out the solids from the treated sewage, And

to separate clear supernatant water

5. Pre-Filtration Tank To collect the supernatant clear water from the

secondary clarifier for further treatment.

6. Mechanical Filter Press To de-water the sludge taken out of settling tank and to

convert the same into manure.

7. Pressure Sand Filter To filter out minute suspended solids if any in the

treated water.

8. Activated carbon Filter To remove color and odor if any in the filtered water.

9. U V RADIATION FLOW

THROUGH SYSTEM

To disinfect the treated water to make it safe to come in

contact with humans so that the treated water can be

used for gardening.

Page 12: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

TREATMENT FLOW CHART:

Fig. 7.2 Treatment Flow Chart

Pumps

140 KLD RAW SEWAGE

SludgeExcess

Disposal as Manure

Sludge To

PressMechanical Filter

Sludge

Recycle

FlushingTo Resuse for Gardenings/

Final Holding Sump

DisinfectionU.V Radiation for

Activated Carbon Filter

FilterPressure Sand

Pre Filteration Sump

Clarifier Tank

Aeration Tank

Equalization Tank

Bar Screen Chamber

Page 13: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

Design of the individual units:

Bar Screen Chamber: Provide a chamber of size 1.5 m x 1.0 m to suit sewer gradient to accommodate an

inclined bar screen with opening less than 10 mm. Provide a bar screen of 20 x 6 mm flats with

10mm spacing in between.

Design Criteria:

Velocity through screen : 0.8 m/Sec.

Discharge : Discharge / day x 8 / 24

: = 67000 x 8/24

: = 0.34 Cum. /Sec

Peak Load : 0.34 x 3.0 = 1.02 cum /Sec

Adopting screens with bars of 6mm width and 10 mm clear opening considering 1.2 times the net

area of opening,

Net area = 1.02 x 10 /0.80

= 12.75 m

Gross area = 1.2 times of the net area of opening

= 1.2 x 12.75

= 15.3

= 3.91sqmts

Gross area of screen needed would be 2.8 x 1.4 Mt. for ease of maintenance.

Page 14: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

Equalization tank:

The flow from the bar screen chamber is let into the equalization tank of minimum 8 hours

capacity. This tank is provided to even out the flow variation, and to provide a continuous feed

into the secondary biological treatment units.

Design Flow = 67000/day

Provide min 8 hours holding capacity.

Hence required volume of the tank = 22.33 m3

Provide a tank of 25 m3. Capacity.

The tank size would be 6.0 x 2.5 x 2.0 m (effective volume)

Aeration tank with extended aeration (Activated Sludge Process )

Flow Rate : 67 m3/Day ~ 6.08 m3/Hr

Inlet BOD 5 @ 20 C : 250 mg/Ltr.

Organic Load : 67 x 250/1000 = 16.75Kgs / Day

Total oxygen required Assuming

that 2.2 kgs of O2/kg of BOD

Removal : 36.85 Kgs/day.

F/M : 0.15

MLSS : 4000mg/litre

Volume of the Tank required : 250 x 67/ 0.15 x 4000

27.9 m3

Total Volume Including 30 % Extra

Volume for Sludge Recirculation : 36.27 m3

Size of Aeration Tank Required : 8 m x 2.25 x 2.0 m SWD

Air required for aeration : 700 m 3/Hr

Type of aeration : Membrane Fine pore diffused

Aeration system.

Page 15: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

No. of membrane required : 24 Nos. of 1.0 m long.

Function : To aerate the contents of the

Aeration tank and to sustain the

Biological activity so as reduces

The organic load.

% of Oxygen in air = 0.21 Density of air = 1.2

Therefore air requirement in Cum. / Hr

= 67 x 100 = 279.16 cum / Hr.

24

Consider 40% excess considering the air required in the equalization tank.

Total air required = 390.83 cum / Hr.

Hence provide2 blowers each of 200 cum / Hr.

One as standby with an operating pressure of 0.5 KSC.

Transfer rate of oxygen in 1 mt. Long membrane diffusers = 10 cum / hr.

Therefore total no. Of membranes required =390.83 / 10

= 40 Nos.

Secondary Clarifier with sludge scraping mechanism:

The over flow from the aeration tank will be taken into the secondary clarifier separation

of biological floc.

Design quantity 67 KLD considering

Design Surface loading rate = 20 cum / m / day

Area of the tank required = 73 m3

The tank size shall be of 6.5 m x 4.5 m with 2.5 m depth for easy sludge settling allowance.

Page 16: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

Clarified Water/ Final Treated water Sump:

The flow from the settling tank i.e., the supernatant liquid is let into the clarified Tank, which has

a minimum 16 hours holding capacity. This tank is provided to hold the treated effluent and give

an even flow to the pressure sand filter.

Design flow = 67 KL/day

Provide min 8 hours holding capacity.

Hence required volume of the tank = 22.33 m3

Provide a tank of 25 KL. Capacity.

The above tank is divided into 2 compartments each of 15 and 10 for final effluent and clarified

water respectively.

The dimension of each tank will be 4 x 2.5 x 1.5 m and each. 4x1.5x2.0 m

Pressure sand Filter :

Flow = 67KL/day

Loading rate = 3.33 cum/ Sq.M. / Hr

Considering the operation of 20 hours of filter

Provide a pressure sand filter of 650 mm dia with sand as media over layer, under drainpipe,

Laterals face piping etc.

Activated Carbon Filter :

Flow = 67 KL/day

Loading rate = 3.33Cumec/Sq.M/hr.

Considering the operation of 20 hours of filter

Provide an activated carbon filter of 650-mm diameter with activated carbon filter media with

under drainpipe, lateral face piping.

Page 17: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

ULTRA VIOLET RADIATION

The filtered water is further passed through an online automatic U V radiation flow through

system for disinfection. Provide one no. 20000 Lts capacity U V flow through system

Pumps: a. Provide 2 Nos. Sewage transfer pumps (One working and one standby)

Capacity : 15 KLH @ 12.0 m head

Type : Open impeller non-clog centrifugal pumps

Make : Kirloskar

Solid handling size : Up to 10 mm

Duty: To pump the sewage from the Equalization tank to the Aeration Tank.

b. Provide 2 Nos. Sludge transfer pumps (one working and one standby)

Capacity : 7.5 KLS/hr @ 15.0 m head

Type : Open impeller non-clog centrifugal pumps

Make : Kirloskar

Solid handling size : Up to 10 mm

Duty : To Pump the sludge from the settling tank

To the sludge drying beds.

c. Provide 2 Nos Filter feed pumps (One working and one standby)

Capacity : 20 KLH @ 30.0m head

Type : Open impeller non-clog centrifugal pumps

Make : Kirloskar

Solid handling size : Up to 10 mm

Duty: To pump the treated effluent from the pre- filtration tank through the pressure sand filters

and activated carbon Filter.

Page 18: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

Filter Press:

Filter press mechanically operated plate type with collection trays etc., is provided for sludge

disposal.

Type : Rail slider

Plate Size : 18”x 18”

No. of Plates : 38 Nos

No. of chambers : 37 Nos

Area of Filtration : 4.5 M²

Cake holding capacity : 45 Litres

Operating pressure : 7 kg/cm2

1.3.4 SOLID WASTE MANAGEMENT

A. Solid waste consist of

1. Garbage

2. Ashes

3. Rubbish

4. Dust Etc.

Solid waste is broadly divided into

1) Organic or combustible matter.

2) Inorganic or mineral or non- combustible matter.

The solid waste generated during operation phase can be categorized under three types:

Domestic/Residential waste

Wet Garbage: Food waste, Lawn mowing wastes etc.

Dry Garbage: Paper, plastic, Bottles, etc.

Sludge from sewage Treatment Plant (STP)

The solid waste generated in the premises is estimated to be about 281.25 Kg/d, which will be

sent to proposed composting unit for further processing, Reusable items such as plastic bottles,

cold drinks, Meta/Glass containers, etc are sold to Recyclers.

Page 19: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

The various mitigation measures to be adopted during collection and disposal of wastes are as

follows:

It is preferable that the container and bins used for collection of waste should be of closed

type of that the waste is not expected and thus the possibility of spreading of disease

through flies and mosquitoes is minimized.

Collection system should be properly supervised so that quick and regular removal of

waste from the dustbin is practiced.

Door to door collection will be arranged in each commercial unit to collect the solid

wastes. The biodegradable wastes will be segregated and sent to the proposed composting

unit. Non-biodegradable wastes such as plastic materials, glass & metal wastes will be

handed over to the waste recyclers.

Quantity of Domestic Solid Waste

Quantity of domestic solid waste

Generated per day from the proposed Project

Total No of Persons = 625

= 625 X 0.45 = 281.25 Kgs Day

Total quantity from the establishment = 281.25Kg/day

Page 20: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

Disposal of solid waste generated

Solid waste generated in the premises to the following agencies for safe disposal.

Table 1.7: Solid waste Generation

Sl.

No.

Waste Quantity Treatment & Disposal

1. Total solid waste

Organic

Inorganic

281.25 Kgs/Day

168.75 Kgs/Day

112.5 Kgs/Day

Organic waste will be

composted at the project site

and inorganic waste will be

handed over to the BBMP door

to door collection facility.

2. STP Sludge 11.25 Kgs/Day STP Sludge will be used for

green belt development in the

project site.

B. Hazardous Waste Management

Waste oil from D.G’ Sets.

About 750 Liters of waste oil per year will be generated from standby DG sets. This will be

stored in leak-proof sealed barrels and will be given to KSPCB authorized waste oil re-

processors.

1.3.4 Noise Level Management

High noise generated units such as DG set will be provided with acoustic enclosures. Green belt

on the project boundary will further act as noise barrier and helps in attention of noise.

Following Table – 1.8 presents the EMP for noise levels.

Page 21: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

Table: 1.8

MANAGEMENT OF NOISE LEVELS DURING OPERATIONAL PHASE

Environmental

Impacts

Mitigation

Noise from DG

set area

DG set will be installed in an area (Utility section ) where the access

will be restricted

The use of PPD ( ear plugs) will be mandatory is this area selection

of equipment to ensure that the residual noise level of 75 dB ( A )

Noise levels will be checked periodically using a noise pressure

level meter

1.4 Green Belt Development

Green belt development (1431.55 Sq m) within the premises will reduce noise levels and dust

levels. To make the green belt effective for this purpose, it is essential to select proper plant

species and design the plant and row spacing that result in lowering the sheltering effect. In the

development of green belts multipurpose plant species should be selected. This will satisfy the

ecological requirement for species diversity.

1.5 Storm Water Disposal through Rain Water Harvesting

Rain water from roof tops, balconies etc. is allowed to flow through down take pipes that are

sloped to the concealed storm water collection tanks. This water can be used for house gardening

and for other domestic purpose for washing vehicles, etc.

Rain water from other sections of the site is led to catchments pit at each change in flow

direction and at each change in pipe diameter with horizontal & vertical grating depending upon

the road section.

Design of piping network is done on the basis of:

Site Topography & Effective Area

Sizing by Rationale’s Formula with full running pipe

Run-off Coefficient

Page 22: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

Rain water from all the roads is routed to the side drains on either side of the road which is

designed as per the Metrological report; intensity of rainfall is taken as 75mm – 100mm per hour.

Percolation pits can be provided below the tank bed of the collection tanks, thereby recharging

the ground water table as well.

Rain water harvesting will be done by both collection for reuse and ground water recharge.

For assessing the available quantum of water it is assumed that incidental rain fall less than 10

mm will not yield any collectable yield and such rain fall account for 50% of the total rainfall.

The runoff coefficient 0.9 for impervious surface, 0.7 for roads and driveways 0.55 for pervious

surfaces like gardens and soil surfaces is considered, duly accounting for evaporation, seepage

etc.

Rain Water Harvesting:

Rain fall & Yield from terrace

Annual average rain fall = 975 mm

Hence co-efficient of run off will be 0.9

Yield Available = 0.975 x 0.9 x 1645

= 1405 cum

Rain fall & Yield from driveways

Annual average rain fall = 975 mm

Hence co-efficient of run off will be 0.7

Yield Available = Area x 0.975 x 0.7

=1301 x 0.975 x 0.7

= 865 cum

Page 23: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

Rain fall & Yield from green way runoff

Annual average rain fall = 975 mm

Hence co-efficient of run off will be 0.55

Yield Available = Area x 0.975 x 0.55

=1431 x 0.975x 0.55

= 680cum

The Rainfall harvesting potential for the project is collectively 2950 cum annually. Which can

cater the needs for about 53days.

Rain water harvesting is proposed by means of

1. Collection tank of 100cum x 1no.s

2. Infiltration galleries of 0.45m x 0.45 m in the bed of storm water drain.

3. Recharge pits of 2M X 2M in open spaces. 21in No.

Mode of Usage of rain water:

The Ground water will be recharged through 21 No. of percolation pits. Each pit has a

capacity to absorb in excess of water. The balance water will be collected in two tanks of 1.0 ML

capacity each. The water collected in rainwater collection sump will be used for car washing

purposes after passing through the pressure sand and the activated carbon filter of diameter 650-

mm each.

Mode of usage of water incase of sudden flash floods / continuous rains: though the rainy

days are considered as 120 days in Bangalore and the total rain is divided by the no. of rainy

days, practically the intensity of rain is not the same every day. It varies from day to day. Incase

when there is a heavy and flash rain, the excessive rainwater is led into the existing municipal

storm water drain.

Page 24: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

1.6 Monitoring Strategy

The monitoring of various environmental parameters is necessary which is a part

And parcel of the environmental protection measures. A comprehensive monitoring

Programme is suggested below:

TABLE – 1.9

MONITORING SCHEDULE FOR ENVIRONMENTAL PARAMETERS

Sr.

No.

Particulars

Monitoring

Frequency

Duration of

monitoring

Important

Parameters for

Monitoring

I Air Quality

1 Ambient Air monitoring

project premises

Once in a month 24 hrly sample TSPM, RPM,

SO2, Nox.

2 Stack Monitoring Once in a month Grab SO2, SPM, Nox

HC, CO

II Water and wastewater Quality

1 Water Quality

i Ground water at two

locations ( up-gradient &

down-gradient) of treated

effluent discharge area/ land

Once in a month Grab As per KSPCB

requirements

2 Waste Water Quality

i Inlet to STP Daily Composite -

ii Treated effluent prior to

discharge

Daily Composite -

III Soil Quality

1 Within project premises at 1

location on effluent

discharging area land

Once in a month Composite

sample

As per KSPCB

requirements

2 Ecological preservation and

Up gradation

Seasonal Visual

Observations

Survival rate

IV Noise Quality Once in a month 24 Hrs

Monitoring

Noise levels in

Db(A)

Page 25: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

FINANCIAL ALLOCATION/ BUDGETORY PROVISIONS FOR

ENVIRONMENTAL MANAGEMENT ASPECTS DURING OPERATION

PHASE (per annum)

Sl. No

Description

Financial provisions (Rs In Lakhs)

Capital Cost Recurring cost

01 Construction of Sewage Treatment Plant 48.0 --

02 Operation of Sewage Treatment Plant per annum -- 6.5

03 Rain Water Harvesting Tanks and its facilities 8.0 1.0

04 Rain Water Recharging pits and its management 2.5 0.5

05 DG Maintenance -- 1.0

06 Landscaping, Top soil conservation 4.0 2.0

07 Solid Waste Management 4.0 1.0

08 Environment Monitoring Plan (Air, Noise, Water

and Solid Waste)

-- 2.0

TOTAL 66.5 13

Page 26: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

RISK ASSEMENT AND DISASTER MANAGEMENT PLAN

8.1 Introduction

Rapid development of the city has posed wide-ranging hazards threatening safety and

health of people. Accidents may adversely affect the environment and the people living in the

vicinity. These accidents can be minimized to a great extent by proper procedures, handling and

training. But it may be difficult to reach zero risk or absolute safety level. Whenever such

incidents do occur in order to prevent loss of lives and damage to property, it becomes necessary

to take immediate steps to control the situation. This can be achieved through a planned advance

preparation to face such a situation with respect to both on site and off site emergencies.

8.2 On – Site Management Plan

The On-site plan will be circulated to all concerned members of emergency teams. It is

essential that all concerned familiarize themselves with the overall on-site emergency plan and

their respective roles and responsibilities during and emergency. They should also participate

regularly in the mock drills that will be conducted so as to keep themselves and the emergency

organization in a state of perpetual preparedness at all times at all times to meet any emergency.

8.2.1 Objectives, Scope and contents of On-site Emergency Plan

Objective of Emergency planning are to maximize the resource utilization and combined

efforts towards emergency operations and would broadly cover the following.

1. To localize the emergency and if possible eliminate it.

2. To minimize the effects of accidents on people and property.

3. To take remedial measures in the quickest possible time to contain the incident and

control it with minimum damage.

4. To mobilize the internal resources and utilize them in the most effective way.

5. To get help from the local community and government officials to supplement internal

manpower and resources.

6. To minimize the damage in other sections.

7. To keep the required emergency equipment in stock at right places and ensure that they

are in working condition.

8. To keep the concerned personnel fully trained in the use of emergency equipment.

9. To give immediate warning to the surrounding localities in case of an emergency

situation arising.

10. To mobilize transport and medical treatment of the injured.

11. To educate the public in the surrounding villages regarding hazards.

12. To arrange for rescue and treatment of casualties.

13. To safe guard the people.

14. To identify the causalities and communicate to relatives.

Page 27: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

15. To render necessary help to concerned.

16. To rehabilitate area affected.

17. To provide information to media & government agencies.

8.2.2. Scope of Onsite Emergency Plan

The plan covers information regarding the properties of the commercial complex and

Multiplex, type of disasters and disaster/accident – prone zones, the actual disaster control plans

with authority delegation, controlling and other details. General details like locations, project

layout, neighboring entities and the assistance they can render etc., are also provided.

The important elements considered in this plan are

Statutory requirements

Emergency organization

Roles and responsibilities

Communications during emergency

Emergency shutdown & control of situation

Rescue & Rehabilitation

Emergency facilities

Important Information

The primary purpose of the on-site emergency plan of DMP is to control and contain the incident

and so to prevent if from spreading. It is not possible to cover every eventuality in the plan and

the successful handling of the emergency will depend on appropriate action and decisions being

taken on the spot. Other important aspects needing to be considered include the following:

8.3 Emergency

A major emergency in any situation is one, which has the potential to cause serious injury

or loss of life, which may cause extensive damage to the structures in the vicinity and

environment and could result in serious disruption to normal operation both inside and outside

the layout premises. Depending on the magnitude of the emergency, services of the outside

agencies may also be required for supplementing the internal effort to effectively handle the

emergency and to contain the damage.

The Management has to take effective steps to assess, minimize and wherever feasible

eliminate the risks to a large extent. Accidents may still occur and it is necessary to be fully

prepared to tackle all such emergencies if and when they occur.

It is likely that the consequences of such emergencies will be confined to the units

concerned or may affect outside. If the consequences are confined within the plant boundary, it is

then termed as on site Emergency and will be controlled by chief emergency controller.

Page 28: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

In order to generate the plans it is necessary to first determine the kinds of accidents

leading to an emergency that can occur in the layout. The most widely used technique in practice

is based on experience accumulated over many years and safety audits.

A. Methodology

The considerations in an emergency planning include the following:-

Identification and assessment of hazards and risks.

Hazard, consequence analysis

Alarm and communication procedures

Identifying, appointment of personnel & assignment of responsibilities

Identification and equipping emergency control center, identifying Assembly, Rescue

points, Medical facilities.

Emergency preparedness plan, procedures, steps to be taken before, during and after

emergency.

Formulation of plan and emergency sources.

Training rehearsal, evaluation and updating the plan

B Structure of Emergency Management

a) Nothing the accidents

b) Informing declarer of emergency

c) Declaration of emergency

d) Functions of declaration

e) Interaction with outside agencies

C Identification and Assessment of Hazards

This stage is crucial to both on-site and off-site emergency planning and requires

systematic identification of all possible emergencies that could arise in the plants. These should

range from small events, which can be dealt by plant personnel without any help from external

agencies to the largest event that would require outside help. The tackle such emergencies

effectively, it is essential to have clear-cut action plan. Experience has shown that for every

occasion that the full potential of an accident is realized, there are many occasions when some

lesser event occurs or when developing incident is made safe before reaching full potential.

D Infrastructure at Emergency Control Center

Emergency control centers should therefore contain the following

An adequate number of external telephones; if possible, one should accept

Page 29: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

Only outgoing calls, in order to bypass jammed switchboards during an

Emergency.

A adequate number of internal telephones

Radio equipment

A plan of the works, to show:

Areas where there are large inventories of hazardous materials.

Sources of safety and first aid equipment.

The fire-fighting system and additional sources of water.

Site entrance and roadways, including up-to-date information on road

Traffic.

Assembly points.

Vehicle parking and rail sidings.

Additional work and layout plans detailing alternate routes and affected area,

during an emergency.

Note pads, pens and pencils.

A nominal role of employee.

A list of key personnel, with addresses, telephone numbers, etc.

The emergency control center should be sited in an area minimum risk. Suitable location from

where clear view of the plant is possible or the control room can be designated as emergency

control center. All the site controller/ Incident controller officers, senior personnel would be

located here or have access to the ECC.

E. Emergency Medical Facilities

Stretchers, gas masks and general first aid materials for dealing with chemical burns, fire

burns, etc., would be maintained in the medical center as well as in his emergency control room.

A range of medicines should be maintained in the ECC/ medical center. Breathing apparatus and

other emergency medical equipment should be provided and maintained.

The medical center should display poster for treating burns and first aid. Some medicines

and facilities to be kept in the medical center are suggested. The list is indicative and the

qualified doctors of the medical center should use their professional judgment for medical

treatment.

Page 30: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

F Health and Safety Measures for the Workers

a. Buildings and Structures: No walls, Chimneys, Galleries, Stairways, floor,

platform, staging or structure whether of a permanent or temporary character shall

be constructed in such manner as to cause risk or bodily injury.

b. Provision of crawling boards etc: No person shall be required to stand to pass

over on or near by any roof of ceiling cover with fragile material through which he

is liable to fall, in case it breaks or gives away the distance for more than 3 meters

without use of sufficient number of suitable ladders, duck ladders or crawling

boards which are securely supports.

c. Service Platforms: Whenever practicable and demanded service platforms

and gangways will be provided for overhead shafting, and where required by him

these will be securely fence with guard rails and toe boards.

d. Belts, etc: All belts will be regularly examined to injure that the joints are safe

And the belts are proper tension.

e. Helmets: Helmets will be provided to the workers for safe guarding themselves

Against any head injuries.

f. Machinery: No machineries are equipments will be situated, operated or

Maintained in such a manner as to cause risk of bodily injury.

g. Methods of work: No process of work will be carried out in such a manner as

To cause risk of bodily injury.

h. Electricity: No electricity installation shall be provided during construction so

As to be dangers to human life or safety.

i. Medical Check-up: Medical examination every worker shall be examined by

Certified surgeon at least once in 3 months of a calendar.

G. Emergency action plans

a. Emergency Action Plan for Cylinder Fire:

1. When filled container containing LPG is involved in fire, internal pressure if not relieved,

shall build up above 70KG/SQCM and ultimately rupture the container. Rupture weak by

direct flame impingement. Ruptured containers can be propelled at distance by jet action.

2. If container’s pressure is not raised upto 70KG/SQCM leakage from screwed valve joint

can occur due to different expansion of steel and brass.

Page 31: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

3. Ignition of the escaping gas would aggravate the fire but release of fire reduces the

possibility of rupture.

4. No attempt should be made to extinguish the burning gas but the container under fire and

other containers in vicinity should be kept cool by water spray.

5. If the gas leakage does note ignite, the container should be approached from up and

removed to the place of safety away fro, the source of ignition.

b. Emergency Action Plan for Electric Fire:

1. Disconnect the affected areas electric supply.

2. Attempt to extinguish fire with the help of Co2, DCP.

3. If fire is not extinguished, extinguish by spraying water with fog nozzle after ensuring

complete isolation of electric circuit.

c. Emergency Action Plan for Office Fire:

1. Disconnected electric supply of the affected area.

2. Attempt to extinguish the fire with the help of Co2, DCP and sand.

3. If large fire, use hydrant system.

4. Attempt to save the record.

5. Attempt fire extinguisher.

d. Emergency Action Plan for Oil Fire:

1. Attempt to extinguish small fire with the help of DCP

2. If the fire is not controlled, use water foam to blanket the fire and further action is to be

taken.

e. Emergency Action Plan for Medical Aid:

f. Emergency Action Plan for Electric Shock Casualties:

Electric Shock results in:

Irreversible damage to brain cell begins followed by deterioration of the organs.

Rescue and first aid:

Do first aid quickly and without fuss and panic.

Switch off the supply if this can be done at once.

If not possible use a dry stick, dry cloth or other non-conductor to separate the victim

from electrical contact.

Page 32: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

The reducer must avoid receiving shock himself by wearing gloves or using a jacket to

pull the victim.

Always keep in mind that delay in rescue and resuscitation may be fatal. Every sound

counts.

ii. Artificial Respiration: Give artificial respiration if breathing has stopped. There are several methods of artificial

respiration, if the victim is nit injured over the face, try mouth to mouth.

a) Mouth to Mouth Method:

If there is obstruction to breathing, remove it with your fingers if it in mouth. Several

sharp blows between shoulder blade may help to is lodge an obstruction.

Lie casually on his back, put something under his shoulder to raise them & allow his

head to fall backwards. The head should be, if possible be a little lower than the trunk.

Remember that speed is essential.

Kneel at the causalities head and grasp his arms at the wrists then cross them firmly

over the lower chest. This movement should force air out of his lungs. Press with the

hands crossed on the lower part of the chest and maintain pressure for two seconds.

Release this pressure and pull out his arms with a sweeping movement upwards and

outwards above his head and backwards as far as possible.

This movement should cause air to be drawn in to his lungs. Retain the arms in this

position for three seconds.

Repeat these movements rhythmically about twelve times a minute checking the mouth

frequently for obstructions. Each cycle will thus take give seconds- two seconds for

hest pressure and three seconds for arm lift.

With the causality on his back there is danger of aspiration of vomit, mucus or blood

reentering the system. Keeping his head extended and a little lower than the trunk can

reduce this risk.

If an assistant is available, he can press the causality lower jaws so that the chin is

jutting out.

The assistant should also ensure that the mouth is kept open as far as possible and head

is tilted to one side.

When natural breathing begins, your movement should be adapted to correspond to it.

If burns are present, cover them with a dry sterile dressing

Handle the causality gentle

Do not allow people to crowd around and block fresh airflow

Arrange to remove the injured to the care of a doctor ad early as possible.

Page 33: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

f. Natural Hazards

i. Emergency Action Plan for Tornado/High Winds:

a. Weather reports shall be monitored from broadcast warnings threatening conditions.

b. If the tornado has been sighted or effect is felt, following steps should be taken by plant

personnel.

Persons shall be notified over public address system or through siren.

Emergency services shall be alerted for assistance.

Plant personnel should be advised to assemble in the administration building

basement, staff room, recreation room and rest rooms.

All safety systems should be kept on alert and all nonessential utilities should be

put off.

After the status is restored, personnel should inspect all the facilities for resource,

first aid and damage control activities, damage assessment, and clean up,

restoration and recovery.

ii. Emergency Action Plan for earthquakes

a. When first tremors are sensed during an earthquake, all personnel should evacuate

Buildings and assemble at safe place away from structures, walls and falling objects.

Emergency shut down should be declared.

b. Emergency services should be contacted for assistance.

c. After the status is restored, personnel should inspect all the facilities for rescue,

First aid and damage control activities, damage assessment, cleanup, restoration and

Recovery.

Page 34: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

g. Emergency Action Plan for Bomb Threat

When bomb threat cell is received the following measures are to be taken.

Inform the message to the highest local police authority and seek their assistance for

patrolling and security need.

Inform controller of Explosives the details and nature of the anonymous message and

read operations.

Request the local fore Brigade to position at least on fire tender at the location

immediately.

Keep the concerned Dept. at the Regional level informed with the developments at

regular intervals.

Alert the local Govt/Pvt. Hospitals and seek their help for providing Ambulances if

necessary

In The Location Premises:

Keep the fire Hydrant system/all fire Fighting and personnel protective equipment in

readiness

Every one entering the Location must be frisked at the Gate/Check all hand bags, Parcels

etc., for suspected explosive/ dangerous objects.

Have through inspection of the Location for any suspected dangerous object.

Materials and other boxes to be brought in to the Location must be deposited at gate for

minimum curing period of 48 Hrs.

Organization Employees Vigilance cell for round the clock observation for our premises.

Objects of suspicion In case of finding of suspected Articles, do not disturb its position, but the area around it

should be cordoned off to a distance of 100 meters and more depending upon the gravity

of situation.

Adequate staff or police Squad posted to prevent any unauthorized entry into the enforced

cordon.

Contact Controller of Explosives immediately, who on reaching the site will decide

suitable action for defusing and disposal of the suspected object.

Evolution of thick billowing smoke is an indication of impending explosion and in such a

case, with draw or evacuates all personnel from the spot, which has been identified.

As a general measure regulate the movement of the outsiders inside our premises and restrict

their entry with permits.

Page 35: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

9.1 Construction Phase

The number of concrete mixers, cranes, transport vehicles, etc. should be kept to an

optimum level to minimize risks of accidents.

Temporary colonies of the work force etc should have proper sanitation including toilets

and bathrooms. Sewage and other wastes generated in these settlements should be

collected and disposed of in an environmental friendly manner.

The construction noise level should be kept to a minimum particularly during the

excavation and slab construction.

The dust generation should be controlled by water sprinkling at regular interval at the site

and nearby roads.

Dedicated driveways should be marked for movement of construction equipments and

vehicles.

All personnel working at the site should be properly trained in safety procedures needs to

follow.

The personnel should also be trained in the operation of fire fighting machineries.

The personnel should also be made aware of the importance of wearing personal

protective equipments at all times as directed by their supervisor.

9.2 Operational Phase

Utilizing the experiences gained by the local environment during the construction period should

assemble a plan of action for mitigating the predicted adverse effects.

a. Traffic Control

Speed limit of 20 Km/h should be specified for roads within the premises

The separation of pedestrian movement and vehicular traffic should be strictly enforced.

b. Solid Waste

All House keeping persons working in the BALAJI DEVELOPERS must be trained to

segregate the bio-

Degradable waste from the non-bio-degradable waste, so that the quantity which requires

To be disposed off through vermin composting or any other safe method of disposal,

Thereby reducing the load on environment.

Good housekeeping practices should be maintained which helps in prevention of

contamination of soil through improper spillage of solids wastes and other materials.

Page 36: ENVIRONMENTAL MANAGEMENT PLANenvironmentclearance.nic.in/writereaddata/FormB/TOR/PFR/...Environmental Management Plan Balaji developers PROJECT AT GLANCE 1 Name & Designation Correspondence

Environmental Management Plan

Balaji developers

c. Full pledged Environmental Management cell exclusively for the proposed should be

constituted with qualified Engineers.

CONCLUSION

Any type of development activity has both beneficial and adverse impacts on the environment in

which it operates. The impacts are identified and evaluated by the project proponents to reduce

their negative effects and maximize the positive effects. The proposed Residential apartment

project is being developed to meet the city’s ever growing appetite for housing with good

ambience facilities. It is being ideally located in the midst of the city; the location of the project

also offers many distinct advantages.

The proposed project will have no Negative impact on the environment if the recommended

environmental management aspects were fully implemented.