"enhancing service delivery through the consolidation of data
TRANSCRIPT
1
SEMINAR PERSONEL ICT SEKTOR AWAMBIL 1 TAHUN 2010
(19 APRIL 2010)
Salmah KhairuddinMAMPU, PM‟s Department
By
“ENHANCING SERVICE DELIVERY THROUGH THE CONSOLIDATION OF DATA CENTRES
AND DISASTER RECOVERY SERVICES IN THE PUBLIC SECTOR”
2
Agenda
Click to add Title1
Click to add Title2
Click to add Title3
Background
Major Data Centre Issues and Challenges Faced by Public Sector Agencies
The Malaysian Public Sector Consolidated
Data Centre and DRC Programme
From Disaster Recovery to Business
Resilience
Click to add Title5 Consolidated DC/DRC Value Proposition
4
Conclusion6
4
Background
A data centre houses among the most important assets of an agency
namely its ICT equipment and applications
Equally as important is having a disaster recovery facility which ensures
the continuity of the agency‟s key services when its primary data centre
is struck with a disaster
Thus, having high performance data centres is critical to the efficiency
of service delivery as it:
Ensures high availability
Provides greater security, resiliency
and business continuity
Helps garner public
confidence when transacting online
with Government agencies
6
1. Low specs, small sized and low density
2. Insufficient cooling
3. Electrical power trips and power instability
4 . Water leaks, fires
5. Insufficient security
6. Inadequate personnel
7. Absence of/inadequate standard operating procedures (SOP)
8. Absence of disaster recovery plans (DRP)
Major Data Centre Issues and Challenges Faced by Public Sector Agencies
8| 8
Business requirements have evolved from “recovery” following a disruption to providing
uninterrupted business process capability
Regulatory Pressures Online Computing Availability Requirements
The Changing Dynamics
Recovery Times Risk Profiles Approach to Planning Technology Capability
Business Recovery
Recovering business operations following an interruption
Business ResilienceMaintaining business operations/viability through all kinds
of stresses and strains … and opportunities
Business Continuity Maintaining business capabilities through disruptive events
Disaster Recovery IT Recovery following some sort of “catastrophic” failure
9
Causes of Disruptions
Frequency ofoccurrences
per year
1,000
100
10
1
1/10
1/100
1/1,000
1/10,000
1/100,000US$1 US$10 US$100 US$1,000 US$10,000 US$100,000 US$1,000,000 US$10,000,000 US$100,000,000
Fre
qu
en
tIn
frequ
ent
Consequences (single occurrence loss) in dollars per occurrenceLow High
Virus
WormsDisk failure
System availability failures
Pandemic
Natural disaster
Application outage
Data corruption
Network problem
Building fire
Terrorism/civil unrest
Data driven
Event driven
Business driven
Regulatory Compliance
Workplace inaccessibility
Failure to meet
industry standards
Regional power failures
Governance
Source: IBM
Data GrowthLong Term Preservation
M&A
New Products
Marketing Campaigns
Audits
10
Enterprise-Wide Approach to Resilience Management
• A holistic approach to evaluate all aspects of business resilience
• The layers are broken down into IT and business objects
13
Pusat Data
Sektor Awam 2
(PDSA 1)
(Putrajaya)
Pusat Data
Sektor Awam 1
(PDSA 1)
(Cyberjaya)
DATA CENTRE CLOUD
Agency 1
Agency 2
• Database Hosting
• Web, email, and video
conferencing hosting
• Application hosting
• Disaster Recovery
Services
o Hot site
o Warm site
o Cold site
The Public Sector Data Centre (DC) andDisaster Recovery Centre (DRC) Concept
Agency 3
Agency 4
Agency…n
14
SCENE
The Public Sector Data Centre (DC) andDisaster Recovery Centre (DRC) Concept...contd.
Intranet
Internet
Agency 1 Agency 2 Agency…n...........
Public Sector DC and DRC
Physical Infrastructure
Users
MAMPU
SLAs
15
• 98% have own data centres
• 4% hosting at other agencies‟ data centres
• 10% renting private sector DC facilities
• 10% have DRC services
Until 2009PHASE I
2011 – 2012(Pilot)
PHASE II2013 – 2015
(Rolling Plan)
• PDSA 1
• PDSA 2
• Data Centre Rolling Plan (PDSA 1 and PDSA 2)
• Possible nation-wide establishment of data centres by region
RMKe-10
CONSOLIDATION
Data Centre Transformation
16
Data Centre Study 2009 (113 data centres)
• 75 data centres (64%) built with under-spec raised flooring (<18 inches)
• 30% data centres don‟t have precision airconditioning
• 50 data centres (43%) have no CCTVs
• 69% data centres don‟t have environment monitoring system
• 22% data centres don‟t have fire detection and suppression system.
• 67% data centres don‟t have water detection system.
• 81 (69%) data centres don‟t have standard operating procedures (SOP)
• 76% data centres don‟t have disaster recovery plan (DRP)
Until 2009PHASE I
2011 – 2012(Pilot)
PHASE II2013 – 2015
(Rolling Plan)
• ITIL/ISO 20000
• ISO IEC 27001
Information
Security
Management
System
• Green Data Centre
• Trusted Data Centre
• Standard Operating
Procedures
• ITIL/ISO 20000
• ISO IEC 27001
Information
Security
Management
System
• Green Data Centre
• Trusted Data Centre
• Standard Operating
Procedures
RMKe10
CO
NS
OL
IDA
TIO
N
Data Centre Best Practices
18
Consolidated DC/DRC Value Proposition
18
• Speedier deployment
• Greater scalability
• Better resource allocation and utilisation
• Bigger capacity
• Higher availability
• Improved business continuity and resilience
• Improved security
Availability Agility
Costs and Energy
Efficiency
Service Delivery
• Greater opportunities for „green„ initiatives and „cloud‟ computing
• Reduced carbon emission
• Reduced costs
• Trust and
confidence when
transacting
online with the
Government
Standardization& Modularity
19
Requirements
Budget
Implementation Requirements
ManpowerLocation
• Utilise existing MAMPU
data centres
• Rolling Plan – Establish
more PDSAs nation-wide
20
MAMPUClient
• Conducts user requirement study
• Conducts technical assessment and requirement study
• Ensures readiness of facilities
• Provides and maintains DC and DRC services
• Implements continuous improvement
• Identifies critical applications
• Conducts risk analysis
• Carries out business impact analysis
• Prepares Disaster Recovery Pan (DRP)
Roles and Responsibilities
21
Activities
Year
2010 2011 2012 2013 2014 2015
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
PDSA 1 and PDSA 2
• User Requirements and Service Portfolio
• JTICT Approval
• Procurement Process
• Upgrading Data Center PDSA1 and PDSA 2
• Rollout and Engagement with 5 agencies
• Impact Analysis
Disaster Recovery Centre (DRC)
• Preparation of Disaster Recovery Plan (DRP)
• Technical Accessment
• Procurement Process
• Rollout and Engagement with 10 agencies
• Impact Analysis
Rolling Plan
• Rolling Plan for Public Sector Data Centre
• Rolling Plan for Public Sector Disaster
Recovery Centre
Implementation Plan
22
Perlis
Kedah
P.Pinang
PerakKelantan Terengganu
Selangor
N. Sembilan
MelakaJohor
Pahang
Sabah
Sarawak
Cyberjaya /Putrajaya
DRC (Central Zone)
DRC (Southern
Zone)
DRC (Eastern
Zone)
DRC (Northern
Zone) DRC (Sarawak)
DRC (Sabah)
The nation-wide expansion of Public Sector DCs and DRCs
Rolling Plan 2013 - 2015
Johor
24
1
4
Conclusion
35
Global trends point to the increasing use of „green‟ initiatives and consolidation of government data centres and DRCs
2
33
Many data centres in the Public Sector have been facing a host of issues and challenges
Most agencies do not have a disaster recovery plan nor suscribe to disaster recovery services
The Malaysian Public Sector is planning to embark on a similar strategy to reap the benefits of shared ICT infrastructure and services and enhancing service delivery
Strong support and commitment required from all user agencies
26
Key Findings
26
Key findings from the Public Sector Data Centre/DRC
Study in 2009 (from a total of 113 respondents):
105 agencies have own data centres (117 in total)
5 agencies using data centre services of other agencies
11 agencies using private sector data centres
11 agencies have disaster recovery services
27
Study Findings…Contd.
Size
79 data centres (68%) are small in size (<1000 sq. ft)
Raised Flooring
• 7 data centres do not have raised flooring
• 75 data centres (64%) built with raised flooring that is too low (<18 inches)
Precision Air Conditioning
35 data centres (30%) are using comfort airconditioninginstead of precision air conditioning
Generator Sets
50 data centres (43%) are not getting back-up power from generator sets
CCTV
50 data centres (43%) have no CCTVs
28
Study Findings….Contd.
Personnel
29 (25%) data centres have less than 3 personnel dedicated to the data centre
Standard Operating Procedures
81 (69%) data centres do not have standard operating procedures (SOP)
Disaster Recovery Plan
87 (74%) data centres do not have disaster recovery plans (DRP).
Disaster Recovery Services
Only 11 agencies have disaster recovery services
31
Korea
Korea has set up 2
consolidated data
centres for the
Public Sector
located at Daejeon
and Gwangju
32
Whole-of-Government Consolidated Data Centre Strategy (2007 – 2017).
Implementation involves the consolidation of many discrete agency data centres into several large, shared facilities each offering high levels of availability, security, scalability and disaster recovery capability.
State of Queensland, Australia
33
Since 2004, Michigan has shut down 35 of its 38 data centres and repurposed nearly half of its existing IT equipment
Saved more than US$19 million and reclaimed 30,000 square feet of office space
Planning to build a massive data centre between 80,000 to 100,000 sq. ft. dubbed the Great Lakes Information and Technology Centre
State of Michigan, USA
34
In February 2010, the Governor issued an executive order for a major overhaul of
the state government‟s entire IT infrastructure including aggressive targets for IT
energy use and data centre floor space
Each state agency to reduce energy consumption of its ICT infrastructure by
10% by July this year, 20% by July 2011 and 30% by July 2012.
Size of data centre floors to be reduced by 25% by July 2010 and 50% by July
2011
The entire state government to use a common technology platform and
shared services
State CIO given authority over all ICT infrastructure used by state agencies
including:
Data centres and data centre services
Hosting of all internal and public-facing applications
Shared services such as email and directory.
California State Government
35
Through efficient placement of racks in hot aisle/cold aisle environment
„Green‟ Technology
Through proper design and implementation of data and electrical cabling
..................................... .................................
.....................................................................
The development and application of products, equipment and systems used to conserve the natural environment and resources, which minimizes and reduces the negative impact of human activities.
Through the use of:
Energy-efficient servers
Server and storage consolidation
Objectives:
To reduce the cost of electricity
To reduce carbon emission
36
Cloud Computing
• “I only care about result, not how IT capabilities are implemented”
Acquisition Model Service-based
• “I want to pay what I use, like a utility”
Business ModelUsage-based
• “I can access services from anywhere, from any device”
Access ModelInternet, Intranet
• “I can scale up or down the capacity, as needed”
Technical ModelDynamic, flexible
A style of computing where massively scalable IT-enabled capabilities are provided “as a service” over the network