engineers india limited - eiltenders.eil.co.in/newtenders/images/single part bidding.pdfjuly 2013 2...
TRANSCRIPT
July 2013 2
INTRODUCTION
Engineers India Ltd (EIL) as a part of execution of various projects for its clients is
involved in procurement of variety of materials and equipments. Under the current
system of limited enquiries for items, where neither technical vendor data is required
nor any technical deviations / stipulations are permitted, the bids are invited under
one of the following options:-
I) Composite bids: comprising of technical and commercial information including
prices in a single bid/envelope.
II) Two part bids: technical / un-priced bid and priced bid are invited in separate
envelopes. Price bids are opened after determining techno-commercial
acceptability of bids.
In continuation of our endeavor to achieve fast and efficient procurement, EIL
intends to implement a fast track bidding process for selected items in which only
price bids shall be invited from bidders.
July 2013 3
IDENTIFIED ITEMS
SINGLE (PRICED) PART BIDDING METHODOLOGY shall be initially adopted for Indigenous
enquiries issued for following items under which only price bid shall be obtained from the
bidders:-
PIPING PIPELINES ELECTRICAL STATIC
EQUIPMENTS
INSTRUMENTATION
PIPIES FLANGES HV CABLES VESSELS PRESSURE GAUGES
FLANGES FITTINGS MV CABLES COLUMNS DRAFT GAUGES
FITTINGS COMMUNICATION
CABLES & FA CABLE
TEMPERATURE GAUGES
GASKETS SIGNAL CABLES
BOLTS & NUTS THERMOCOUPLE EXTN
CABLE
STANDARD
VALVES
GAUGE GLASS & COCKS
July 2013 4
SALIENT ASPECTS
SINGLE (PRICED) PART BIDDING shall be initially done only for Indigenous
enquiries.
If a Bidder submits the price bid, it shall be construed that the Bidder has
accepted all Technical requirements and Commercial Terms & Conditions as per
Bidding Document in totality.
Following documents shall only be furnished by the Bidder :-
Priced Bid strictly in the Price Schedule format issued with the RFQ.
Latest Annual Financial Report including Profit & Loss Statement and
Balance Sheet.
Duly filled up Form-I indicating applicable Freight, Taxes & Duties and other
information as per the Format.
Any other document like Integrity Pact, Power of Attorney etc if required.
Any enclosure other than those mentioned above or any deviation on Technical /
Commercial conditions of RFQ shall lead to rejection of the bid.
July 2013 5
SALIENT ASPECTS
Original Integrity Pact (IP) shall be submitted at EIL within the bid due date.
If applicable, authenticated MSE certificate shall be submitted at EIL within
the bid due date & time in physical form failing which applicable advantage
shall not be extended to the bidder.
Bidders shall furnish firm Freight charges in price schedule /FORM-I. In
case freight is not indicated it shall be deemed that freight charges are
included and accordingly evaluation / ordering shall be done.
If Bidder indicates Freight “extra at actuals” / “to pay basis”, offer shall be
rejected.
Taxes & Duties as quoted by the Bidder in Form-I shall be considered for
evaluation / ordering. In case the same is not quoted, prevailing rates shall
be considered for evaluation / ordering. However, in case Service Tax / ED/
Sales Tax /VAT on Freight is not specified, the same shall be considered as
Not Applicable.
July 2013 6
SALIENT ASPECTS
EIL does not intend to issue any commercial or technical queries and therefore
any conditional statements in the offer which render the evaluation inconclusive
shall result in rejection of the bid. An example of such a statement is that “part
order is acceptable subject to mutual discussion”.
Bid validity shall be 30 – 45 days from the final bid due date.
Bidder to quote only for items in line with their enlisted capability with EIL.
Time for submission of bids shall be 1-2 weeks.
The bidding methodology above is tentative and is being discussed in order to
keep bidders apprised and to obtain their feedback. Actual terms & conditions
may vary and shall be detailed in the enquiry document.
July 2013 7
IMPLEMENTATION IN E-PROCUREMENT
EIL is resorting to e-procurement in a major way, and implementation of Single
(price) Part Bidding in e-procurement cases shall be our priority.
In order to achieve the same a macro enabled MS-Excel workbook shall be issued
along with enquiry containing 2 works sheets as under :
A) Form-I : Bidders shall select suitable drop down options and enter requisite
information, taxes & duties, freight charges etc.
B) Form-II : Once bidder enters all details as required in Form-I and accepts all
terms & conditions by marking tick in the specified check boxes, then only he
shall be allowed to fill the Form-II (price schedule work sheet).
Prior to editing Form-I Bidders shall enable macros in “Excel Options”
Bidder shall select suitable drop down option against each rows. For example
against Excise Duty including Edu. Cess, bidder shall first select its applicability i.e.
“YES” / “NO” under drop down menu. If “YES” is selected then only he shall be able
to fill applicable rate in the adjacent cell. If “NO” is selected, the adjacent cell shall
remain locked.
July 2013 8
IMPLEMENTATION IN E-PROCUREMENT
Similarly, for freight charges drop down options would be “NIL” / “Quoted in Price
Schedule” / “Quoted in percent”. If bidder selects “Quoted in Price Schedule” , he
shall fill freight charges in the Price Schedule format (i.e. FORM-II). In case “Quoted
in percent” is selected, the adjacent cell shall become editable, wherein bidder shall
enter freight percent.
For Part Order Acceptance: Bidder can select “Accepted”/”Not Accepted”/ “Accepted
subject minimum Order Value”/ “Accepted subject Minimum Freight”. Bidder can
select suitable option and indicate Minimum Order Value acceptable or Minimum
Freight Acceptable as applicable.
Illustrative screen shots are enclosed in following slides.
July 2013 11
IMPLEMENTATION IN E-PROCUREMENT
Provisions for those deviations which are loadable as per RFQ document, shall
be there in the FORM-I itself. Bidder may select option acceptable to him.
Example: For acceptance to Price Reduction Schedule (PRS), the drop down
option shall be there listing possible deviation which Bidder may take.
SAMPLE SCREEN SHOT 3 OF FORM-I
July 2013 12
IMPLEMENTATION IN E-PROCUREMENT
The applicable rate of loading shall be in line with the provisions of the RFQ document.
SAMPLE SCREEN SHOT 4 OF FORM-I
July 2013 15
FEED BACK
Our target is to implement the proposed Single (priced) Part Bidding Methodology by 16-Aug-
2013.
Dear Suppliers, with your support we look forward to upgrade to a faster and more efficient
procurement system.
Kindly send your feedback / queries / suggestions to below mentioned email ids by 26-July-
2013 so that due consideration and redressal of your concerns can be taken up before
implementation.
Ms. Sunita Mitra
AGM (C&P)
Mr. Shashank Tinku
Sr. Engineer (C&P)