Page Clause Item Description Category Comment / Clarification / Deviation
No. No. I / II / III I II III
Documents No. RFQ
3 OF 5,
4 of 10
26/1.2.1 of
doc no. 6-43-
0340
Governance of Precedance III SCC & Data sheet should preside over every other documents. Please correct it. please refer clause no. 26 of RFQ.
ITB
3 OF 58 5 Site Visit II
Please get us details of Stores & site distance, terrain details of site,
accessibility detaills, site layout,
DG sets will be in open to sky installation or in Closed Room.
If it is in closed room, all ventillation, lighting provision & supply is in
purchaser's scope.
Approx. distance between Stores & DG location at site is 100 m.
DG set will be in Closed Room
Noted.
OISD 192
Only clause 5.8.5 is to comply. All rest of the clauses are Not applicable in
our case. Please delete. Purchaser's should provide : Secndary fuel
reservoir, no confined spaces i.e. suitable site, care should be taken to
avoid spilling fuel ,no person should smoke or have an naked light in the
vicinity ,a fire extinguisher should be kept
readily available.
Follow the Provisions of RFQ
3 OF 3 7 Miscellaneous II Following will be in purchasr's scope :
All Civil work Noted.
Unloading, storage, security of the equipment at site.Noted.
Refer sl. No. 02.00 of Price Schedule Format
Power cables between DG set & DG Breaker panel and outgoing
Control cables
cable trays
In line with S.No. 10 of DG Set Data sheet (A415-000-16-50-DS-5161
Rev.A) Fabricated steel cable trays and racks as required for cabling in the
battery limits is covered in the scope of MR.
Earthing pits & earthing connection
In line with S.No. 10 of DG Set Data sheet (A415-000-16-50-DS-5161
Rev.A) Earthing within the battery limits and connection to main earthing
grid is covered in the scope of MR.
Ventillations, lighting Noted.
consumables at site like construction power, water, diesel, load etc. Diesel and load shall be in puchaser's scope. Rest all by vendor
Statutory approvals & permissions This shall be in vendor's scope
3 of 3 Note 2 Spares replenishment II Please clarify replenishment is for which spares ???Replenishment of commissioning spares/any spare which is to be used
during erection/commissioning
DOC NO. A415-000-16-45-SU-5160 SITE DATA
1.2 FGL II please clarify FGL elevation & accessibility. Refer site and utility data of MR
ENGINE DADA SHEET DOC NO. A415-000-16-45-DS-5160
2 OF 4 98 12 hours tank capacity III Tank supplied will be subbase suitable for 4 hours back up. Follow MR requiremetns
99 Fuel Float Tank III Regret , no such tank is provided. Noted.
108 Inlet Silencer III No such silencer is provided/required by the engine design standard. Noted.
VENDOR DATA REQUIREMENT IIAll documents submitted must be approved with Cat 1 approval for
manufacturing clearance.
For mfg clearnance, documents shall be at-least approved with Code-2
(with comments) or Code-R (record)
35 of 113Key SLD Doc no. A415-
000-16-50-DS-5162II
NGR will not be provided, intead solid earthing will be done. AVR is part of
Engine panel, not separately mounted elsewhere. MCCB will be 4 Pole
fixed type 35KA rating with electromech release.
a) Not acceptable. NGR along with NGR monitoring relay is to be provided
in line with MR.
b) AVR location is noted.
c) In line with MR, MCCB with O/L, S/C and E/F release (Microprocessor
based) is to be provided.
TECHNICAL SECTION dated. 13.05.14
DOC NO. A415-000-16-45-CL-5160 CHECK LIST
In line with S.No. 7 of DG Set Data sheet (A415-000-16-50-DS-5161 Rev.A)
Power and Control cabling in between the package equipment is covered in
the scope of MR.
RFQ No.: RJ/A415-000-MD-MR-5160/1030
Item : DIESEL GENERATOR SET
REPLY TO PRE-BID QUERIES-TECHNICAL
EIL Reply
Page Clause Item Description Category Comment / Clarification / Deviation
No. No. I / II / III I II III
TECHNICAL SECTION dated. 13.05.14
RFQ No.: RJ/A415-000-MD-MR-5160/1030
Item : DIESEL GENERATOR SET
REPLY TO PRE-BID QUERIES-TECHNICAL
EIL Reply
Make of Electrical Items IIAll Control Panels will be our make only, but make of breakers, relays etc. as
per EIL standard.
Make of control panel is not mentioned in the vendor list attached with PR.
In line with S.No. 7 a) of Data sheet Part-2 of DG Set Data sheet (A415-000-
16-50-DS-5161 Rev.A), Make of other equipment/components not
mentioned above shall be subject to prior approval of EIL/Owner. The same
shall be verified based on proven track record of the item.
ITP FOR EMERGENCY DG SET DOC NO. 6-81-1040
Noise & Vibration Test will not be offered at Alternator factory, but Type Test
Certificate will be submitted.
Noise & vibration test are part of Acceptance test. Supplier to demonstrate
the same at works.
Transient Response Analysis will be performed at 0.8 pf as per manufacturer's
test procedure.OK
Alternator Type Test IIIShort Ckt withstand & measurement of reactances, time constances & pottier
reactances will not be applicable.To be demonstrated in one machine as Type test.
SPECIFICATION FOR EMERGENCY GENERATOR DOC NO. 6-51-0040 R6
5 OF 12 5.1 Name plate rating & Duty III
Please note, DG set quoted is not designed for rated capacity power output for
unlimited number of hours operating continuously per year. It is designed as per ISO
8528 for prime duty application at variable load condition and to be run to 85% of its
rated prime capacity & yealy operation of 1500 hours.
Noted. For finalization of PRP rating, refer MR.
8 of 12 7.6 AVR IIIAVR is located in Engine control panel. which is mounted near DG set inside
acousticNoted.
NGR will be made in 2mm MS enclsoure Noted.
MAKE OF CONTROL PANELS will be our make only.
Make of control panel is not mentioned in the vendor list attached with PR.
In line with S.No. 7 a) of Data sheet Part-2 of DG Set Data sheet (A415-000-
16-50-DS-5161 Rev.A), Make of other equipment/components not
mentioned above shall be subject to prior approval of EIL/Owner. The same
shall be verified based on proven track record of the item.
Alternator Routine Test4.1 III
Sr.No. Page No Clause No Description Deviation EIL reply
1 02 of 08Sr.No. 5 of PRICE SCHEDULE FORMAT-
A
Price Shedule for 2 years Operation & Maintenance
SparesPlease clarify running hours Diesel Generator Set.
Vendor to provide quotation of their standard special
tools and tackles.
2 18 of 113Data Sheet
Sr. No. 69Class of Accuracy
We will provide Governor class EMS 2.2 which is better than class A
1.Kindly confirm.Follow MR requirements.
3 18 of 113Data Sheet
Sr.No. 97Capacity of daily service tank.
In built daily service tank of 750 liters will be provided along with
the DG set in lieu of separate 990 liters day tank. Please clarify the
same.
Follow MR requirements.
4 18 of 113Data Sheet
Sr.No. 119
Fuel consumption & Governing Test at Engine
Manufacturer's Shop
Please note we will submit engine & alternator test certificate for
review & acceptance before dispatch of the equipment to the site.Follow MR requirements.
5 42 of 113Approved Makes
7Make of Electrical Equipment
We will provide Leroy Somer Make Generator.Kindly clarify the
same.
Not acceptable. Make of alternator shall be in line with
MR.
6 29 of 113 1.4.2 EQC for DG set
1. We are OEM of xxxxxxxxxx Engine since 2006 range from 250
KVA to 625 KVA. We have supplied approx 200 Machine.
2.We are offering 320 KVA rating for both 300 KVA & 325 KVA DG
sets. Kindly approve & accept the same.
3.Regarding the performance certificate of DG Set in compliance
with CPCB-I norms , we are having rating of 380 KVA DG Set. Due
to CBCB - II Norms applicable wef. 1st july 2014 same
engine(380KVA CPCB-1 complied) rating has been changed to
400KVA.
We are having 400 KVA DG set in comliance with CPCB 2 norms
instead of 380KVA wef. from 1 july 2014. So, we will provide
performance certificate of 380 KVA or higher rating. Kindly accept
the same.
1. Noted. OEM shall meet the MR requirements.
2. Not acceptable for 325 kVA.
3. Not acceptable. Follow MR requirements.
7 60 of 113 Inspection & Testing of NGR Panel We are not offering Inspection & Testing of NGR panelSupplier’s proposal is not acceptable. Inspection to be
carried out at panel manufacturer’s works
1 DG layout drawing We request to provide site lay-out drawing Layouts attached
2 Quantity for low side work We request to provide us detail BOQ to quote. Follow MR requirements
3 Site TestingSite testing whether load and consumables will be provided by
customer or is it in our scope.Please Confirm
Load and diesel are in purchaser's scope. Rest by
vendor.
4 List of attachment Kindly provide us list of documents to be submitted along with bid. Follow MR requirements
General Points
RFQ No.: RJ/A415-000-MD-MR-5160/1030
Item : DIESEL GENERATOR SET
REPLY TO PRE-BID QUERIES-TECHNICAL