electrical safety inspection report

14
ELECTRICAL SAFETY INSPECTION REPORT HI-TECH APPARELS LTD Purinda Bazar, Shatgram, Arhajar, Narayangon GPS Coordinates:23.85100, 90.63320 Factory List: Author(s) : Md Nurul Islam Reviewed by : Md Nurul Islam Approved by : Banna Kasemi Inspected on: May 25, 2021

Upload: others

Post on 18-Dec-2021

39 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: ELECTRICAL SAFETY INSPECTION REPORT

u

b

D

e

m

o

(

)

S

e

l

e

c

t

i

o

n

.

P

a

s

t

e

A

p

p

l

i

c

a

t

i

o

n

.

S

c

r

e

e

n

U

p

d

a

t

i

n

ELECTRICAL SAFETY INSPECTION REPORT

HI-TECH APPARELS LTD

Purinda Bazar, Shatgram, Arhajar, Narayangon

GPS Coordinates:23.85100, 90.63320

Factory List:

Author(s) : Md Nurul Islam Reviewed by : Md Nurul Islam Approved by : Banna Kasemi

Inspected on: May 25, 2021

Page 2: ELECTRICAL SAFETY INSPECTION REPORT

Page 2 of 14 HI-Tech Apparels Ltd, ID 24160

ELECTRICAL SAFETY INSPECTION REPORT HI-TECH APPARELS LTD

Purinda Bazar, Shatgram, Arhajar, Narayangon

1. INTRODUCTION

The Factory was surveyed for electrical safety by RMG Sustainability Council. The

purpose of the survey was to identify significant electrical safety issues and to provide

recommendations for remediation based on applicable standards specified by the RSC.

Electrical Safety Audit is a methodical approach to evaluate potential electrical hazards

and to recommend suggestions for improvement. The scope of this initial electrical

safety inspection was limited to the review and identification of major electrical safety

issues. The inspection did not include identification of minor deficiencies, which would

be further dealt with as part of follow-up inspections.

2. LIMITATIONS

The information in this electrical safety inspection report was obtained during a visit to

the facility and during discussion with local factory management. Services performed

by the auditors are conducted in a manner consistent with that level of care and skill

generally exercised by members of the engineering and auditing profession. However,

an effort has made to discover all meaningful areas under the stipulated time available.

In evaluating subject site, Inspector relies in good faith on information provided by

factory management or employees. The Inspector assumes that the information

provided is factual, accurate and accepts no responsibility for any deficiency,

misstatement or inaccuracies contained in this report as a result of omission or

misrepresentation of any person interviewed or contacted.

The findings and recommendations in this report are not intended to imply, guarantee,

ensure or warrant compliance with any government regulations. Additionally, the

results do not imply in any way that compliance with the findings or recommendations

as stated in this report will eliminate all risks or exposures not referred to in this report

do not exist. Compliance with the findings and recommendations stated in this report

does not relieve the factory owner from obligation to comply with specific project

requirements, industry standards, or the provisions of any local government regulations.

3. DEFINITION

3.1. TIME FRAME

The amount of time being allocated based on the remediation work volume of the

electrical issues considering the feasibility and ideal status of materials, capital and

working condition. Criticality and priority level of the issue is not taken into

consideration. It is bound only for the particular finding unless mentioned ‘typical’, shall

include the whole typical findings.

Page 3: ELECTRICAL SAFETY INSPECTION REPORT

Page 3 of 14 HI-Tech Apparels Ltd, ID 24160

3.2. PRIORITY LEVEL

3.2.1. Electrical issues related to code violation and/or non-conformity with codes possessing immediate fire hazard, direct threat to human safety, shall be considered as P1 Level of priority. The execution of remediation works shall commence immediately without compromising with any other issues and must strictly complete within the allocated remediation time frame. It shall include only the critical issues

3.2.2. Electrical issues related to code violation and/or non-conformity with codes, protection of electrical switchgears and equipment, spatial arrangement and location of switchgears and equipment, design and drawings, shall be considered as P2 Level of priority. The execution of remediation work of P2 shall commence along with or soon after the P1 level remediation work has commenced. It shall include only the moderately-critical issues.

3.2.3. Electrical issues related to violation of code and/or non-conformity with codes, workmanship of operation and maintenance and obsolete technology of electrical system, shall be considered as P3 Level of priority. The execution of remediation work of P3 shall commence along with or soon after the P2 level remediation work has commenced. It shall include only the non-critical issues.

3.2.4. It doesn’t take into consideration the remediation time frame and feasibility of remediation. It doesn’t take into consideration the capital, materials and working environment.

4. GENERAL BUILDING INFORMATION

1. Factory Name : HI-Tech Apparels Ltd

2. Factory Address : Purinda Bazar, Shatgram, Arhajar, Narayangon

3. ID : 24160

4. Inspection participates : 1. MAHABUBUR RAHMAN BHUYAN

Executive Director

Mob: 01619008688

Email: [email protected]

2. Md Azahar Ali Ashik

Maintenance Engr,

Mob: 01844453997

Email: [email protected]

Page 4: ELECTRICAL SAFETY INSPECTION REPORT

Page 4 of 14 HI-Tech Apparels Ltd, ID 24160

5. BUILDING DATA

A. General

HI-Tech Apparels Ltd. is established in its 4 storied (G+3) RCC production building. As

reported by the Factory Management, building was constructed in around December,

2016 and the production began in around March, 2019. The production building

construction was completed in March, 2019. During the time of the Inspection, the

factory accommodated a total of 290.

The floor wise utilization of the buildings are as detailed below:

Produstion Building (17000 sft):

Ground Floor : Jaquard Machine, Prayer room

First Floor : Finishing, Washing, linking, Inspection Office

Second Floor : General store, winding, bonded ware house

Third Floor : Chiller Unit

Utility Building RCC:

Ground Floor : Substation Room, Generator Room, boiler Room

Security Post (Shed):

Ground Floor : Security room, Child care, Doctor Room.

FLOOR LAYOUT INFORMATION

The four storied (G+3) i.e. factory building is 45 feet tall and has a total floor area of

approx. 70,500 sqft. Figure 1 shows the second floor layout plan of the factory:

Figure 1: Floor layout plan

Page 5: ELECTRICAL SAFETY INSPECTION REPORT

Page 5 of 14 HI-Tech Apparels Ltd, ID 24160

ELECTRICAL SYSTEM & UTILITY INSTALLATION INFORMATION

Hi-Tech Apparels Ltd premise is connected to grid (REB) supply, which is the main

source of power supply tapped from 11kV Over Head line and delivered through High

Tension cable. The 11kV supply is stepped down by 1250 kVA x 1 nos, 11/0.415kV, 3

phase power transformer installed in substation room. Electrical system and Utility

installation information at a glance:

Query Information Remarks

Grid Electricity Supplier REB

Sanctioned Load 570 kW

Number of Transformer 01

Type of Transformer Outdoor type oil cooled

Capacity of each transformer 1250kVA

Transformer location in the factory Far apart from main production building

Transformer owned by factory Yes, and maintained by factory

HT switch gear HT switchgear is located near the

transformer

Number of Generator 1

Capacity of each Generator 300 kVA (MTU)

Generator location in the factory Far apart from main production building

Number of Compressor 1

Capacity of each Compressor 15 kW

Number of Boiler 1

Capacity of each Boiler 1000kg/hour (1.00ton)

Total no. of LT panel 1

Total no. of Distribution boards 18

Power distribution system All through BBT trunking with few cabling

Number of manual changeovers 1

Number of synchronizer No

Number of Automatic transfer switch No

Substation room location Far apart from main production building

Page 6: ELECTRICAL SAFETY INSPECTION REPORT

Page 6 of 14 HI-Tech Apparels Ltd, ID 24160

B. ELECTRICAL PRACTICES IN OPERATION AND MAINTENANCE

Maintenance and Operations is done by in-house electrical and maintenance team

of the factory. However, the maintenance of major equipment like transformer,

generator and boilers are sometimes outsourced to the service centers.

Inspecting teams were presented with the maintenance programs, logs and

maintenance schedule of the factory’s electrical facilities; Some typical practices

are shown below.

HT Panel

LT and PFI Panel

Transformer

Generator

Typical electrical distribution panel.

Boiler

Page 7: ELECTRICAL SAFETY INSPECTION REPORT

Page 7 of 14 HI-Tech Apparels Ltd, ID 24160

6. LIGHTNING PROTECTION RISK ASSESSMENT

Calculation of Risk Index Factor (BNBC 2006) for Main Building Index A Use of Structure

Small and medium size factories, workshops and laboratories

6

Index B Type of Construction Reinforced concrete with nonmetal roof 2

Index C Contents or Consequential Effects

Industrial and agricultural buildings with specially susceptible contents

5

Index D Degree of Isolation Structure located in a large area having structures or trees of similar or greater height, e.g. a large town or forest

5

Index E Type of Terrain Flat terrain at any level 2

Index F Height of Structure 9 – 15 m 4

Index G Lightning Prevalence Over 21 21

Total Risk Index of the building 45

Requirement of installing LPS Yes

It is required to calculate risk index for all structures, design LPS as per standard and

install it properly.

Page 8: ELECTRICAL SAFETY INSPECTION REPORT

Page 8 of 14 HI-Tech Apparels Ltd, ID 24160

7. FINDINGS AND RECOMMENDATIONS

The table below summarizes the major electrical hazards identified during the walk

through inspection. Recommendations have been provided to each finding.

The implementation schedule shall be developed by the factory to remediate each

of the findings. The specific timing of improvements, including any requested

extensions due to design / installation constraints, shall be submitted to the RSC

for an approval.

FINDING NO: E - 1

CATEGORY: DOCUMENTATION

FINDING:

Electrical Single Line Diagram (SLD) is unavailable in the factory.

RECOMMENDATION:

As built Electrical SLD must be prepared; it must have factory's whole electrical installation information.

PRIORITY: P2

REMEDIATION TIME FRAME: 2 MONTHS

FINDING NO: E - 2

CATEGORY: LIGHTNING PROTECTION SYSTEM

FINDING:

Lightning Protection System (LPS) and drawing is unavailable in the factory.

RECOMMENDATION:

Factory has to design Lightning Protection System (LPS) for the whole factory (where the Risk index is more than 40). Once a LPS is designed properly, installation must be done accordingly asap.

PRIORITY: P1

REMEDIATION TIME FRAME: 3 MONTHS

Page 9: ELECTRICAL SAFETY INSPECTION REPORT

Page 9 of 14 HI-Tech Apparels Ltd, ID 24160

FINDING NO: E - 3

CATEGORY: DOCUMENTATION

FINDING:

Earth Pit resistance record is unavailable.

RECOMMENDATION:

All earthing systems shall be tested for resistance on any dry day not less than once in every two years. A record of every earth test made and the result shall be kept for not less than two years and shall be available to the Inspector when required.

PRIORITY: P2

REMEDIATION TIME FRAME: 1 MONTH

FINDING NO: E - 4

CATEGORY: DOCUMENTATION

FINDING:

Electric safety training program has not initiated/conducted.

RECOMMENDATION:

Electrical safety training and awareness program for the electrical personnel must be initiated. It is a periodic task which factory has to continue to improve the overall electrical safety situation for the staffs.

PRIORITY: P2

REMEDIATION TIME FRAME: 1 MONTH

FINDING NO: E - 5

CATEGORY: TESTING & PERIODIC MAINTENANCE

FINDING:

There is no programmed schedule for periodical inspection & testing of electrical equipment.

RECOMMENDATION:

An electrical maintenance program shall be prepared which will include inspections and testing of the electrical systems (preventive and proactive).

PRIORITY: P2

REMEDIATION TIME FRAME: 1 MONTH

Page 10: ELECTRICAL SAFETY INSPECTION REPORT

Page 10 of 14 HI-Tech Apparels Ltd, ID 24160

FINDING NO: E - 6

CATEGORY: TESTING & PERIODIC MAINTENANCE

FINDING:

Personal Protective Equipment (PPE) for Electrical Work is not available.

RECOMMENDATION:

Personal Protective Equipment (PPE) must be arranged by the factory management team for the safety of their employee and worker.

PRIORITY: P2

REMEDIATION TIME FRAME: 1 MONTH

FINDING NO: E - 7

CATEGORY: DOCUMENTATION

FINDING:

Transformer Oil Test (dielectric strength test) report is unavailable.

RECOMMENDATION:

Transformer oil test (dielectric strength test for oil) shall be done once in a year.

PRIORITY: P2

REMEDIATION TIME FRAME: 1 MONTH

FINDING NO: E - 8

CATEGORY: DOCUMENTATION

FINDING:

Insulation resistance test of electrical power cables is not performed.

RECOMMENDATION:

Insulation resistance test of all the cables (you can avoid less than 25 sq.mm) must be performed once in every 2 years’ cycle and recorded (this must require a complete power shut off).

PRIORITY: P2

REMEDIATION TIME FRAME: 1 MONTH

Page 11: ELECTRICAL SAFETY INSPECTION REPORT

Page 11 of 14 HI-Tech Apparels Ltd, ID 24160

FINDING NO: E - 9

CATEGORY: DISTRIBUTION BOARD/PANEL

FINDING:

Distribution Board's bottom is left open (typical issue).

RECOMMENDATION:

Each electrical distribution board/panel must be properly sealed to avoid ingression of fluffs; but an adequate ventilation system must also be ensured. Gland shall be used, where required.

PRIORITY: P2

REMEDIATION TIME FRAME: 1 MONTH

FINDING NO: E - 10

CATEGORY: EARTHING SYSTEM

FINDING:

Earth pits are not identifiable.

RECOMMENDATION:

Each earth pit shall be properly identifiable and marked for periodic maintenance.

PRIORITY: P2

REMEDIATION TIME FRAME: 1 MONTH

FINDING NO: E - 11

CATEGORY: DISTRIBUTION BOARD/PANEL

FINDING:

Unterminated live wire is kept inside the electrical distribution panel.

RECOMMENDATION:

All the unterminated live power cables must be removed as soon as possible.

PRIORITY: P2

REMEDIATION TIME FRAME: 1 MONTH

Page 12: ELECTRICAL SAFETY INSPECTION REPORT

Page 12 of 14 HI-Tech Apparels Ltd, ID 24160

FINDING NO: E - 12

CATEGORY: DISTRIBUTION BOARD/PANEL

FINDING:

Distribution boards have no clear identification markings.

RECOMMENDATION:

All distribution boards, switchboards, sub main boards and switches shall be marked clearly for proper identification.

PRIORITY: P3

REMEDIATION TIME FRAME: 1 MONTH

FINDING NO: E - 13

CATEGORY: DISTRIBUTION BOARD/PANEL

FINDING:

Multiple cables (came from different electrical consumers) terminated at MCCB terminals/ Busbar. RECOMMENDATION:

Each electrical circuit must be terminated at single MCB/MCCB/Busbar terminals.

PRIORITY: P2

REMEDIATION TIME FRAME: 2 MONTHS

FINDING NO: E - 14

CATEGORY: DISTRIBUTION BOARD/PANEL

FINDING:

List of circuit or SLD of existing circuits are not available on each electrical panel/board.

RECOMMENDATION:

List of circuit or SLD of respective circuits shall be available for each electrical panel/board. PRIORITY: P2

REMEDIATION TIME FRAME: 1 MONTH

Page 13: ELECTRICAL SAFETY INSPECTION REPORT

Page 13 of 14 HI-Tech Apparels Ltd, ID 24160

FINDING NO: E - 15

CATEGORY: DISTRIBUTION BOARD/PANEL

FINDING:

Panel doors are not connected with earth.

RECOMMENDATION:

All metal installation which are part of electrical system must be connected to earth to avoid electrical shock or electrocution.

PRIORITY: P1

REMEDIATION TIME FRAME: 1 MONTH

FINDING NO: E - 16

CATEGORY: DISTRIBUTION BOARD/PANEL

FINDING:

No/Inadequate rubber (insulation) mat at the working area of distribution board/panel.

RECOMMENDATION:

Electrical insulation (not less than 3 mm thick in case of rubber mat) at the working area of each electrical installation (Transformer/LT panel/MDB/DB/SDB/ other manual operated machineries) must be ensured.

PRIORITY: P3

REMEDIATION TIME FRAME: 1 MONTH

FINDING NO: E - 17

CATEGORY: DISTRIBUTION BOARD/PANEL

FINDING:

No LOTO (Lock-Out-Tag-Out) policy is introduced for safety of the personnel during any kind of maintenance work.

RECOMMENDATION:

Need to introduce and implement LOTO policy with LOTO (Lock-Out-Tag-Out) device instead of any other means to ensure safety of the personnel during any maintenance.

PRIORITY: P2

REMEDIATION TIME FRAME: 1 MONTH

Page 14: ELECTRICAL SAFETY INSPECTION REPORT

Page 14 of 14 HI-Tech Apparels Ltd, ID 24160

FINDING NO: E - 18

CATEGORY: DISTRIBUTION BOARD/PANEL

FINDING:

Phase barrier/separators are missing in MCCBs.

RECOMMENDATION:

Phases must be separated by insulator (a rubber type no-flammable materials shall be used for it).

PRIORITY: P3

REMEDIATION TIME FRAME: 1 MONTH

FINDING NO: E - 19

CATEGORY: DISTRIBUTION BOARD/PANEL

FINDING:

BBT tap-off box side is left open (typical issue)

RECOMMENDATION:

Seal each TOB side wall cable entry and use cable glands holding/supporting cables.

PRIORITY: P3

REMEDIATION TIME FRAME: 1 MONTH