eia efficacy hearing portfolio committee for water and environmental affairs, parliament, cape town...

9
EIA Efficacy Hearing Portfolio Committee for Water and Environmental Affairs, Parliament, Cape Town Mike Mangnall 31 July 2013

Upload: georgina-horn

Post on 11-Jan-2016

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: EIA Efficacy Hearing Portfolio Committee for Water and Environmental Affairs, Parliament, Cape Town Mike Mangnall 31 July 2013

EIA Efficacy HearingPortfolio Committee for Water and Environmental Affairs, Parliament, Cape Town

Mike Mangnall31 July 2013

Page 2: EIA Efficacy Hearing Portfolio Committee for Water and Environmental Affairs, Parliament, Cape Town Mike Mangnall 31 July 2013

Strengths

EIA process is clear, structured and robust Involves a thorough, inclusive and transparent process•Ensures I&APs are informed of potential projects and have adequate opportunity to voice concerns or support•Allows for information to be shared at understandable levelClearly regulated timeframes allow for proper planning process • Not always adhered to by DEA (see

below)Dynamic nature of EMP development allows for new information to be incorporated• Does not constrain project to

unrealistic expectationsWind farm in Europe

Page 3: EIA Efficacy Hearing Portfolio Committee for Water and Environmental Affairs, Parliament, Cape Town Mike Mangnall 31 July 2013

Weaknesses

DEA has enormous EIA workload•>600 wind and solar applications = approx. 30 000MWs•Approx. 20% might reach construction•Number are speculative but long lead EIA timeframes force early application•Numerous other consents to be Bid compliantProcess too prescriptive and, in many cases, too onerous•Unnecessary delays and frustrationsReviews inconsistent and often exceed stipulated timeframesEase with which stakeholders can lodge appeals is concerning • No costs involved; could be done to extract compensation/ delay process• No participation in EIA required; interested but not affectedAppeal timelines are regulated but in practice are completely open-ended • 90-day resolution timeframe can be reset by requesting further

information/ clarification

Page 4: EIA Efficacy Hearing Portfolio Committee for Water and Environmental Affairs, Parliament, Cape Town Mike Mangnall 31 July 2013

Weaknesses cont.

Environmental Authorisations (EAs) are inter alia conditional on further compliance with other legislation, e.g. NWA and SALA• Other departments (e.g. DWA and DAFF) often impose restrictions

that conflict with EA, resulting in Amendments which further stretch DEA

Quality of reporting by EAPs and specialists varies dramatically • In particular, mitigation measures for birds and bats are often based

on misunderstanding of wind farms and related technology

Current process and EAs allow for little flexibility in development design• Not practical to specify every detail during EIA, hence >projects have

to apply for Amendments for minor changes, e.g. altering turbine hub height or micro-siting turbine positions

• EA should approve specific on-site “areas for development” versus “co-ordinates” to allow for flexibility when turbines are only selected a few months prior to bidding

• Continue to approve range of, or maximum, turbine heights

Page 5: EIA Efficacy Hearing Portfolio Committee for Water and Environmental Affairs, Parliament, Cape Town Mike Mangnall 31 July 2013

Recommendations

Additional resources should be employed within DEA to deal specifically with wind (and solar) farm applicationsA body of suitably-qualified expertise, or advisory capacity, should be created within DEA that is capable of scrutinising technical content of EIAs, in particular specialists’ impact mitigation recommendations• Should limit unworkable recommendations and EA conditions, and

reduce need for subsequent clarification and amendmentsGreater effort should be made to integrate various permitting processes and other government departments should be involved at an early stage by DEA in terms of providing inputs into EIA process• More streamlined process• Avoid unnecessary or conflicting comments between various

departments• Reduce amendment applications post-authorization

Page 6: EIA Efficacy Hearing Portfolio Committee for Water and Environmental Affairs, Parliament, Cape Town Mike Mangnall 31 July 2013

Recommendations cont.

More emphasis should be placed on Scoping Phase• Scoping responses are very standardized, despite differences in

receiving environment and projectsScope/ screen out areas of high impact earlier• Should result in improved and more streamlined EIA• EAP reporting and DEA reviews should be more consistent and of

better quality• Efforts could be focused on more-sensitive sites/ projects• Would save significant resources and time for all partiesWhere project impacts are likely to be low, instead of requiring full EIA or Basic Assessment process, implementation of EMP and appointment of ECO should only be requestedWhere a non-substantive amendment is required, direct application by developer should be allowed

Page 7: EIA Efficacy Hearing Portfolio Committee for Water and Environmental Affairs, Parliament, Cape Town Mike Mangnall 31 July 2013

Recommendations cont.

Extreme caution should be taken if Strategic Environmental Assessment (SEA) to select Renewable Energy Development Zones (REDZ) continues• Industry well-advanced (detailed studies since 2008); do not need

maps to guide (N.Cape not included)• Validity of assumptions used, accuracy of data, appropriateness of

major exclusion criteria• Runs risk of impeding consenting process for applicants outside

Preferred Zones and penalising them unduly• Wind farm site selection is complicated process which requires

appropriate expertise and assessment, and it will not be straightforward to delist activities in zones, which is likely to increase workload of DEA rather than reduce it

Page 8: EIA Efficacy Hearing Portfolio Committee for Water and Environmental Affairs, Parliament, Cape Town Mike Mangnall 31 July 2013

Way forward

Increased collaboration should be facilitated between SAWEA, DEA, environmental specialists and EAPs with regards to understanding and promoting environmentally responsible and sustainable wind energy development in South AfricaImproved integration of permitting should be facilitated by DEA with other departments to ensure more efficient, consistent and effective decision-making• Agreement on “rules of engagement”Clear platform allowing for follow-up on progress of EIAs and appeals within DEA should be established• Could be run online, include official access rights, waiting lists,

list of missing documents, automatic progress updates, standard checklists for both applicant and case officer, for example

Will ultimately lead to a more efficient, interactive and clearly-scheduled process

Page 9: EIA Efficacy Hearing Portfolio Committee for Water and Environmental Affairs, Parliament, Cape Town Mike Mangnall 31 July 2013

Thank you