edcm development workshop welcome 1 | energy networks association 13 january 2011

107
EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Upload: reginald-mccoy

Post on 29-Dec-2015

249 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

EDCM Development Workshop

Welcome

1 | Energy Networks Association 13 January 2011

Page 2: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Introduction

Andrew NevesCentral Networks

CMG Chair

2 | Energy Networks Association 13 January 2011

Page 3: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Agenda morning

3 | Energy Networks Association

START 10am

• Ofgem• Background and recent developments • Overview of EDCM Charging Model• Main charging proposal

– LRIC/FCP charges and network use factors– Transmission exit and reactive power charges– Demand Scaling – Sole use assets– Generation charges and scaling– Application of charges and tariff structures– Justification of charges and addressing outliers– Interconnected network and IDNO charging

LUNCH 1pm

13 January 2011

Page 4: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Agenda afternoon

4 | Energy Networks Association

LUNCH 1pm – 1.30pm

• Break Out Sessions

• Output from Breakout Sessions

• Next steps

• Ofgem – Forthcoming process

• Questions

CLOSE 3pm

13 January 2011

Page 5: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

EDCM workshop

Objectives and key issues for the EDCM

Geoffrey Randall13 January 2011

5 | Energy Networks Association 13 January 2011

Page 6: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Ofgem’s objectives for the EDCMWhat we have now

What we want

Why is this important?

Efficiency Sustainable development

Competition

Methodologies largely untouched for decades

Revised cost reflective charging model

- Efficient investment and use of existing assets will contribute to lower system charges and help fuel poverty

- Facilitate the development of DG- Compliment smart metering roll out- Incentivise Demand Side Management

- Facilitate IDNO competition by creating consistent IDNO charging framework

Variety of methodologies across 14 DNOs

Common charging methodology

- Reduced administrative costs and charging risk premium

- Lower barriers to new generation entrants

- Lower barriers for new supply market entrants

Pace of change dictated by DNOs

Deadline (Submit April 2011, implement April 2012)

- Cost reflective charges could reduce capex requirements

- Measures to tackle climate change required as a matter of urgency

- Development of IDNO market has been slow relative to IGT market

Change depends on DNO modification proposals

Common governance & non-DNO access

- Consumers and suppliers will be able to propose efficient changes to DNO methodologies

- Necessary to ensure methods are responsive to major changes anticipated on distribution networks

- Ensures DNOs are accountable to needs of generation and supply markets

6 | Energy Networks Association 13 January 2011

Page 7: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Key issues – demand and generation charging

Determination of the revenue targets• Are the proposed methods appropriate?

Method used for scaling residual revenue• Demand: 2 approaches are presented – site specific assets approach and

voltage level average assets approach– Any new arguments in favour of one option would be particularly helpful

• Generation: fixed adder approach– Is the proposed approach appropriate?

7 | Energy Networks Association 13 January 2011

Page 8: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

8 | Energy Networks Association 13 January 2011

Page 9: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Background and developments

Harvey Jones

CE Electric

DCMF Chair

9 | Energy Networks Association 13 January 2011

Page 10: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Background

Date Action1 October 2008 • Ofgem publishes proposals for Common EHV Charging Methodology

based on LRIC.

• SPEN and SSEPD raised statutory objections to the licence conditions mandating the LRIC method in these proposals.

20 March 2009 • Ofgem decided not to refer to the Competition Commission, and came back with proposals for a choice between LRIC and FCP methods

1 July 2009 • Licence conditions creating obligations on DNOs to develop and implement the common distribution charging methodology (CDCM), based on the HV/LV part of the October 2008 proposals, came into force.

31 July 2009 • Ofgem proposed principles for the FCP/LRIC approaches and a set of licence conditions to mandate their development and implementation. There was no objection from DNOs to these proposals.

28 August 2009 • DNOs published proposals for the CDCM. Ofgem accepted these proposals after relevant conditions had been met by DNOs in December 2009. The CDCM came into force on 1 April 2010.

1 October 2009 • Licence conditions creating obligations on DNOs to develop and implement the EHV distribution charging methodologies (EDCM), based on FCP or LRIC as specified in the 31 July 2009 document, came into force. These conditions required DNOs to come forward with proposals for the EDCM by 1 September 2010 for implementation by 1 April 2011.

10 | Energy Networks Association 13 January 2011

Page 11: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Background

Date Action23 April 2010 • DNOs published a consultation on options for the allocation of

customers between the EDCM and CDCM methodologies (the EDCM/CDCM boundary). Responses were received from all DNOs and from three other stakeholders.

• Also published a summary of responses on 26 May 2010, available from http://2010.energynetworks.org/structure-of-charges-edcm/

15 June 2010 • Ofgem issued a consultation document on the boundary between the EDCM/CDCM which seeks industry views on the options for defining the boundary to be used to determine whether customers should be subject to the EDCM or the CDCM.

25 August 2010 • Ofgem modified the distribution licence to change the EDCM/CDCM boundary.

27 August 2010 • Ofgem published a letter to the DNOs derogating the DNOs from the requirement to submit the EDCM methodology and illustrative tariffs on 1 September 2010.

1 September 2010 • Publication of information about developments to the proposals since June 2010.

11 | Energy Networks Association 13 January 2011

Page 12: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Background

At the last workshop we told you about:•EHV boundary change

•Pre-2005 DG

•Governance processes

•The decision to delay

Since then we have been working on:•Deciding the most appropriate scaling options for EDCM

•Publishing the consultation (21/12/10)

•The transfer into the licence of the EDCM amendments

12 | Energy Networks Association 13 January 2011

Page 13: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Decision to delay – a reminder

13 January 201113 | Energy Networks Association

Ofgem concerned over customer impacts, the need to consult on new scaling options and changes to generation charges:•DNOs asked to “justify” charges•Ofgem consulted stakeholders•Published decision to extend deadline on 27 August

Ofgem made specific requests of DNOs:•Further stakeholder consultation•Amend the methodology to address comments•Amend the methodology following sense checks•Work closely with customers

Page 14: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

The consultation

We welcome responses to this consultation, including contributions and ideas on the proposals, in particular on:•Whether the proposed methodology meets the objectives of the EDCM;•The proposed approaches to demand and generation scaling;•The proposed approaches for sense checking final charges and addressing outliers;•Application of charges to in-year consumption; and•Our approach to justifying charges under the EDCM.

The deadline for responses to the consultation is Tuesday 1 February 2011.

14 | Energy Networks Association

Page 15: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Overview of the model

Shankar Rajagopalan Reckon LLP

(ENA/CMG consultant)

15 | Energy Networks Association 13 January 2011

Page 16: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Overview of the EDCM model

• The model calculates charges for demand and generation tariffs according to the methodology set out in the December consultation

• EDCM charges apply to sites covered by Ofgem’s definition of an EHV designated property

• Separate import and export tariffs will apply in the case of mixed generation and demand sites

• Final charges include elements derived from LRIC or FCP methodologies

13 January 201116 | Energy Networks Association

Page 17: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Overview of the EDCM model

EDCM charges include the following components:

•A fixed charge (both demand and generation)

•A capacity charge (both demand and generation)

•Unit rate charges for consumption during the super red time band (demand only)

•Excess reactive power unit rate charge (for demand and generation with some exceptions)

•A unit rate credit for export by non-intermittent generation

13 January 201117 | Energy Networks Association

Page 18: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Overview of the EDCM model

Demand tariff components are made up of the following:

•Marginal charges calculated using FCP or LRIC methodologies

•Transmission exit charges

•Excess reactive power charges

•An allocation of DNO direct operating costs

•An allocation of DNO indirect costs

•An allocation of DNO business rates (network rates)

•An allocation of the part of the DNO’s allowed revenue which has not been allocated as above (residual revenue)

13 January 201118 | Energy Networks Association

Page 19: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Overview of the EDCM model

Generation tariff components are made up of the following:

•Marginal charges (or credits) calculated using FCP or LRIC methodologies

•Excess reactive power charges

•Transmission exit credits for qualifying generators

•An allocation of DNO direct operating costs to sole use assets

•An allocation of DNO business rates (network rates) to sole use assets

•A generation scaling charge (may be positive or negative)

13 January 201119 | Energy Networks Association

Page 20: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Summary of EDCM demand tariffs

13 January 201120 | Energy Networks Association

Tariff component Unit Correspondence to tariff elements

Fixed charge p/day Sole use asset charges for direct operating costs and network rates

Import capacity charge

p/kVA/day Local element of FCP/LRIC charge 1, direct operating costs, indirect costs, network rates, demand scaling charge and possibly the transmission exit charge (Consultation Q4)

Super-red unit rate p/kWh Remote element of FCP/LRIC charge and possibly the transmission exit charge (See Q4)

Excess reactive power charge

p/kVArh Average charge based on DNO revenue per unit distributed.

Page 21: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Summary of generation tariffs

13 January 201121 | Energy Networks Association

Tariff component Unit Correspondence to tariff elements

Fixed charge p/day Sole use asset charges for direct operating costs and network rates

Export capacity charge

p/kVA/day Both elements of FCP/LRIC charge 2 and the generation scaling fixed adder

Generation credit p/kWh Both elements of FCP/LRIC charge 1 for non-intermittent generation only

Excess reactive power charge

p/kVArh Average charge based on DNO revenue per unit distributed. This would not apply to generation subject to grid code requirements (on the corresponding import tariff as well)

Page 22: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

FCP/LRIC charges and Network Use Factors

Mo Sukumaran

SSE Power Networks

22 | Energy Networks Association 13 January 2011

Page 23: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Introduction

13 January 201123 | Energy Networks Association

Ofgem allowed DNOs to choose, develop and implement the EDCM methodology for EHV pricing based either on the:

•FCP - Forward Cost Pricing model

or•LRIC - Long Run Incremental Cost model

Page 24: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Introduction

13 January 201124 | Energy Networks Association

Network studies produce £/kVA/annum cost that is reflective of the cost of future reinforcement of the network on a locational basis:

• on a ‘Network Group’ (i.e. zonal) basis under FCP• on a ‘Nodal’ basis under LRIC

Charges are part of EDCM Demand and Generation tariffs

Page 25: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Overview of Methodologies

Long Run Incremental Cost Pricing (LRIC)

Forward Cost Pricing(FCP)

Price granularity Node Network group

Analysis period Infinite 10 years

Network security standards

Load: N-1Generation: N-1

Load: N-1, limited N-2 scenariosGeneration: N-1

Reinforcement requirements

Change in NPV of reinforcements due to 0.1MW increment

Cost of reinforcements in 10-yr period

Network load growth Fixed at 1% across entire network Calculated for each substation from

LTDS data

Load analysis Assessment of impact of a 0.1MW increase in load at each node

Sequential year-on-year modelling using expected substation loads

Generation analysis Assessment of impact of a 0.1MW increase in generation at each node

Probabilistic approach based on expected generation connections

13 January 201125 | Energy Networks Association

Page 26: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

FCP Network group Analysis

13 January 201126 | Energy Networks Association

GSP 1

Level 3Primary Group 1

400/132kV

Level 1GSP Group 1

GSP 2

BSP 1 BSP 2Level 2

BSP Group 1

Level 3Primary Group 2

Level 3Primary Group 3

Level 3Primary Group 4

275/132kV

132/33kV 132/33kV

132/11kV

Pry 1 Pry 2 Pry 3 Pry 4

Pry 5

33/11kV 33/11kV 33/11kV 33/11kV

(B) 33kV

Level 2BSP Group 2

(1) STSG33

(2) CTSG33

(3) CTSG33

Existing

Existing

Existing Existing

(1) STSG33

(2) CTSG33

(3) CTSG33

GSP Network Group

BSP Network Group

Primary Network Group

Substation TSG

Existing Generation

CircuitTSG

Group under consideration

Page 27: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

LRIC Nodal Analysis

13 January 201127 | Energy Networks Association

0 5 10 15 20 25

Years

MV

A

Rating

Base Case Flow (from pow erflow analysis)

Base power flow

Page 28: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

LRIC Nodal Analysis

13 January 201128 | Energy Networks Association

Base power flow

0 5 10 15 20 25

Years

MV

A

Rating

Base Case Flow (from pow erflow analysis)

Years to reinforcement(from base case)

Page 29: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

LRIC Nodal Analysis

13 January 201129 | Energy Networks Association

Base power flow

0 5 10 15 20 25

Years

MV

A

Rating

Incremented Flow (from pow erflow analysis)

base

incremented

Years to reinforcement (base)

Years to reinforcement (inc)

Page 30: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Improvements - LRIC

13 January 201130 | Energy Networks Association

• Revision of generation modelling in the ‘Minimum Demand’ scenario– generation coincidence within GSPs introduced

• ‘Sense-checking’ of power flows derived from the application of security factors– power flows approximated for branches with ‘security

factors’ greater than 6

• ‘Sense-checking’ of recovery of branch reinforcement costs– ‘recovery factors’ introduced for branches for which

total cost recovery is greater than the annuitised reinforcement cost

Page 31: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Improvements - FCP

13 January 201131 | Energy Networks Association

• Increased testing of impact of generation across network– increased testing around perimeter of network group

– tests conducted at the ‘source(s)’ and all exit points within each network group

• ‘Sense-checking’ of ‘test size’ generators (TSGs)– ‘circuit’ and ‘substation’ TSGs introduced

– thresholds introduced – 100MW at the 132kV voltage level and equivalents for other voltage levels

Page 32: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Application of Network Use Factors (NUFs)

32 | Energy Networks Association

• NUF shows the network usage by an EDCM customer in comparison to the notional average usage from CDCM’s 500MW Model

• NUF = 1 indicates that the value of assets used by the customer at that network level is equal to the average value of assets used at that level by all customers (EDCM and CDCM)

• NUF = 2 indicates that the value of assets used by the customer at that network level is equal to twice the average value of assets used at that level by all customers

• All else being equal, a customer with a NUF = 2 will have a shared asset-based cost allocation which is twice that of a customer with a NUF of 1

13 January 2011

Page 33: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Application of Network Use Factors (NUFs)

33 | Energy Networks Association

• Through power flow analysis, for each customer, we:– Identify notional assets ‘deemed’ to be used by the customer– Calculate the sum of annuitised notional asset MEAV (£) at each

voltage level.– Identify the customer usage in kW at the exit point, and hence the

£/kW/annum value at each voltage level.

• Some NUFs can be significantly greater than 2

• Calculation of NUFs from the power flow model analysis

13 January 2011

Voltage EDCM User site specific cost

CDCM User average cost

NUFs

132kV £5/kW £10/kW 0.5

132/33kV £40/kW £20/kW 2

Page 34: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Transmission exit chargesExcess reactive power charges

Simon Yeo

Western Power Distribution

34 | Energy Networks Association 13 January 2011

Page 35: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Transmission Exit Charges

Demand Tariffs will have a charge• Two options under consideration

– Option 1: Uniform p/kW/day converted to p/kVA/day using site specific kW/kVA relationship and applied as part of capacity charge

– Option 2: Uniform p/kWh applied to consumption during super red time band (see appendix 4 of consultation for DNO time bands)

• Consultation Q4 seeks views

13 January 201135 | Energy Networks Association

Page 36: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Transmission Exit Charges

Generation Tariffs may have a credit•To receive a credit

– Generator must have agreement with DNO to provide P2/6 support during supergrid transformer (SGT) outage conditions

•Credit calculated using a uniform £/kVA/yr (forecast expenditure ÷ system max demand)•Applied on same basis as Charge 1 credits

– converted to p/kWh and applied to units exported– only applies to non-intermittent generation

13 January 201136 | Energy Networks Association

Page 37: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Reactive Power Charges

Demand and Generation Tariffs include a charge for excess reactive power• Sites subject to Grid Code requirements exempt

– ‘Large’ generators as defined (100MW E&W, 30MW SPT, 10MW SHETL and 10MW for all offshore

– These sites are required to operate continuous voltage control which can lead to reactive power flows

• For all other tariffs– Single non-locational charge proposed

– p/kVArh = 0.889 x EDCM demand revenue / EDCM kWh

– 0.889 set on the basis of a single reactive power factor band

– Charge applied to reactive power units that take customers power factor below 0.95

13 January 201137 | Energy Networks Association

Page 38: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Demand scaling

Shankar Rajagopalan Reckon LLP

(ENA/CMG consultant)

38 | Energy Networks Association 13 January 2011

Page 39: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

What is demand scaling?

• Each DNO has an allowed revenue that is set as part of Ofgem price controls

• DNOs recover their allowed revenue from EDCM and CDCM customers through use of system charges

• An EDCM demand revenue target is the result of a fair split of the allowed revenue.

• Recovery from marginal charges and allocated costs from EDCM demand customers may not match the revenue target

• Scaling charges make up the difference

13 January 201139 | Energy Networks Association

Page 40: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Two alternative scaling methods

• We are considering two alternative approaches to demand scaling:

– The “site specific” assets approach

– The “voltage level” average assets approach

• Both approaches raise the same amount of revenue from the EDCM demand customer group

13 January 201140 | Energy Networks Association

Page 41: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Two alternative scaling methods

The approaches differ in the way some DNO costs and scaling charges are allocated to customers

• The site specific approach uses customer-specific notional asset values derived using power flow analysis

• The voltage level average approach uses average asset values at each network level derived from the 500 MW model

13 January 201141 | Energy Networks Association

Page 42: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Methodology overview

13 January 201142 | Energy Networks Association

Page 43: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Steps in demand scaling

Both approaches to scaling share the following steps:

Step 1: Calculate the contributions from each EDCM demand customer towards the EDCM demand revenue target.

Step 2: Allocate cost-based elements of the target to individual customers

Step 3: Calculate the scaling charge to individual customers.

13 January 201143 | Energy Networks Association

Page 44: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Step 1: Customer contributions

• The EDCM demand revenue target is the sum of the EDCM share of:

– DNO direct operating costs, indirect costs and network rates

– DNO allowed revenue minus the above

• The EDCM shares above are calculated as the aggregates of each customer’s contributions.

• Contributions from customers are driven by notional asset values (including sole use assets for direct costs and network rates). Notional assets are network assets that are deemed to be used by the customer

– Notional asset values are determined using the CDCM 500 MW model and network use factors from power flow analysis

13 January 201144 | Energy Networks Association

Page 45: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Step 2: Customer allocations (1)

• Each EDCM demand customer is assigned an allocation of individual cost-based target elements:

– Direct operating costs

– Indirect costs

– Network rates

• The indirect cost target is allocated on the basis of a measure of customer capacity and peak-time demand

– Calculated as the sum of 50 per cent of import capacity and 100 per cent of demand during the DNO super-red time band

13 January 201145 | Energy Networks Association

Page 46: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Step 2: Customer allocations (2)

• The direct operating cost and network rates targets are allocated to individual customers on the basis of network assets used

– The site specific approach uses site specific notional asset values to allocate these elements

– The voltage level approach uses voltage level average asset values to allocate these elements

– Sole use asset values are added to shared network asset values in both approaches

13 January 201146 | Energy Networks Association

Page 47: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Step 3: Calculating the scaling charge (1)

• A residual scaling target is calculated as the EDCM demand revenue target:

– Minus the cost-based target elements relating to direct costs, indirect costs and network rates

– Minus the forecast recovery from the application of FCP/LRIC charges to EDCM demand

– Plus the cost of EDCM generation credits based on FCP/LRIC

• In other words, the residual scaling target is set so that the total recovery from different charge elements is equal to the EDCM revenue target

• The residual scaling target could be positive or negative

13 January 201147 | Energy Networks Association

Page 48: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Step 3: Calculating the scaling charge

• The residual scaling target is split into two

• 80 per cent of the scaling target is allocated to individual customers on the basis of network assets used

– The site specific approach uses site specific notional asset values to allocate the residual scaling target

– The voltage level approach uses voltage level average asset values to allocate the residual scaling target

– Sole use assets are not taken into account in either approach

• 20 per cent of the scaling target is allocated to individual customers on the basis of their import capacity and peak-time demand (like the indirect cost target element)

13 January 201148 | Energy Networks Association

Page 49: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Stylised example of demand scaling

• Simplified example to illustrate the scaling approaches

– Ignore sole use assets, generation charges or credits

• DNO allowed revenue - £20 million

– Direct operating costs - £3 million

– Indirect costs - £4 million

– Network rates - £3 million

– Residual revenue - £10 million (Allowed revenue – costs)

• Total network assets based on the CDCM 500 MW model - £200 million

– £180 million assets used by CDCM customers

13 January 201149 | Energy Networks Association

Page 50: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Customer information

13 January 201150 | Energy Networks Association

Customer 132 kV customer 33 kV customer 1 33 kV customer 2

Capacity 50,000 kVA 10,000 kVA 40,000 kVA

LRIC/FCP charge £2/kVA/year £10/kVA/year £5/kVA/year

Avg 500MW assets at 132 kV

£5 million £1 million £4 million

Avg 500MW assets at 33 kV

Not used £2 million £8 million

Network use factors at 132 kV

0.4 1 1

Network use factors at 33 kV

- 0.5 2

Notional assets at 132 kV

£2 million £1 million £4 million

Notional assets at 33 kV

Not used £1 million £16 million

Page 51: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Demand revenue target

• The EDCM demand revenue target is built up on the basis of notional assets

• EDCM notional assets are £24 million out of a DNO total of £200 million (12 per cent)

• EDCM demand revenue target is £2.4 million (12 per cent of allowed revenue), of which

– Direct operating cost element is £360,000

– Indirect cost element is £480,000

– Network rates element is £360,000

– Residual revenue element is £1.2 million

13 January 201151 | Energy Networks Association

Page 52: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

The scaling target

• The scaling target is the difference between the EDCM demand revenue target and the forecast recovery from other charges

– The forecast recovery from the LRIC/FCP charge is £400,000

– The forecast recovery from direct operating costs, indirect costs and network rate allocations £1.2 million

– The scaling target is therefore £800,000 (£2.4 million – £1.2 million - £400k)

13 January 201152 | Energy Networks Association

Page 53: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Allocation to customers

• The elements to be allocated to customers:

– Direct operating cost element is £360,000

– Indirect cost element is £480,000

– Network rates element is £360,000

– Scaling element is £800,000

• Indirect cost element and 20 per cent of the scaling element are allocated on the basis of capacity and demand during super-red time bands

• The other elements are allocated on the basis of assets

– Voltage level average assets or site specific assets

13 January 201153 | Energy Networks Association

Page 54: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Voltage level assets approach

13 January 201154 | Energy Networks Association

Customer 132 kV customer 33 kV customer 1 33 kV customer 2

Capacity 50,000 kVA 10,000 kVA 40,000 kVA

LRIC/FCP charge £100,000 £100,000 £200,000

Avg 500MW assets at 132 kV

£5 million £1 million £4 million

Avg 500MW assets at 33 kV

Not used £2 million £8 million

Direct cost and network rates alloc

£180,000 £108,000 £432,000

Indirect cost alloc £240,000 £48,000 £192,000

80 per cent residual £160,000 £96,000 £384,000

20 per cent residual £80,000 £16,000 £64,000

Total charges £760,000 £368,000 £1,272,000

Page 55: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Site specific assets approach

13 January 201155 | Energy Networks Association

Customer 132 kV customer 33 kV customer 1 33 kV customer 2

Capacity 50,000 kVA 10,000 kVA 40,000 kVA

LRIC/FCP charge £100,000 £100,000 £200,000

Notional assets at 132 kV

£2 million £1 million £4 million

Notional assets at 33 kV

Not used £1 million £16 million

Direct cost and network rates alloc

£60,000 £60,000 £600,000

Indirect cost alloc £240,000 £48,000 £192,000

80 per cent residual £53,333 £53,333 £533,333

20 per cent residual £80,000 £16,000 £64,000

Total £533,333 £277,333 £1,589,333

Page 56: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Summary

13 January 201156 | Energy Networks Association

Customer 132 kV customer 33 kV customer 1 33 kV customer 2

Capacity 50,000 kVA 10,000 kVA 40,000 kVA

LRIC/FCP charge £100,000 £100,000 £200,000

Avg DRM assets at 132 kV

£5 million £1 million £4 million

Avg DRM assets at 33 kV

Not used £2 million £8 million

NUF at 132 kV 0.4 1 1

NUF at 33 kV - 0.5 2

Final charge under the voltage level approach

£760,000 £368,000 £1,272,000

Final charge under the site specific approach

£533,333 £277,333 £1,589,333

Page 57: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Comparison of scaling approaches

• Demand scaling should achieve two objectives

– It should preserve the forward-looking signals from the FCP and LRIC charges

– It must not lead to final charges that are materially different from a fair allocation of their forward looking business costs

• Both approaches would recover the same total amount of revenue from EDCM demand customers as a whole

• Charges for individual customers would be different

– Differences are driven by the choice of asset values – site specific or voltage level averages

13 January 201157 | Energy Networks Association

Page 58: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Comparison of scaling approaches

• The voltage level average approach is better at preserving signals from FCP or LRIC

– Under the voltage level approach, final charges to customers with the same capacity, demand patterns, sole use assets and uses the same network levels would differ only by their FCP or LRIC charges

– The site specific approach additionally require the customers to use the same value of shared network assets

• The site specific approach produces final charges that represent a fairer allocation of DNO costs

– NUFs allow a finer differentiation in the value of assets used by customers

– Only if asset value is a fair allocation driver for DNO costs

13 January 201158 | Energy Networks Association

Page 59: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

EDCM demand revenue

13 January 201159 | Energy Networks Association

Breakdown of EDCM demand revenue

-2 0 2 4 6 8 10 12 14 16 18 20 22

WPD West

WPD Wales

UKPN SPN

UKPN LPN

UKPN EPN

SSEPD SHEPD

SSEPD SEPD

SPEN SPM

SPEN SPD

ENW

CN West

CN East

CE YEDL

CE NEDL

£ millions

Sole use asset charges Transmission exit Direct costs Indirect costs

Network rates LRIC/FCP charges Demand scaling

Page 60: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

EDCM demand revenue

13 January 201160 | Energy Networks Association

Breakdown of EDCM demand revenue (percentages)

-10% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

WPD West

WPD Wales

UKPN SPN

UKPN LPN

UKPN EPN

SSEPD SHEPD

SSEPD SEPD

SPEN SPM

SPEN SPD

ENW

CN West

CN East

CE YEDL

CE NEDL

Percentages

Sole use asset charges Transmission exit Direct costs Indirect costs

Network rates LRIC/FCP charges Demand scaling

Page 61: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

EDCM demand revenue

13 January 201161 | Energy Networks Association

EDCM demand revenue vs Current demand revenue

0

5

10

15

20

25

WPDWest

WPDWales

UKPNSPN

UKPNLPN

UKPNEPN

SSEPDSHEPD

SSEPDSEPD

SPENSPM

SPENSPD

ENW CNWest

CN East CEYEDL

CENEDL

£ m

illio

ns

Total EDCM demand revenue Current demand revenue

Page 62: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Sole Use Assets

Andy Pace

Electricity North West

13 January 201162 | Energy Networks Association

Page 63: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Sole Use Assets – Definition (1)

Sole Use Assets (SUA):

Sole Use Assets are assets in which only the consumption or output associated with a single customer can directly alter the power flow in the asset, taking into consideration all possible credible running arrangements

i.e. all assets between the customer's Entry/ Exit Point(s) and the Point(s) of Common Coupling with the general network are considered as sole use assets.

13 January 201163 | Energy Networks Association

Page 64: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Sole Use Assets – Definition (2)

Point of Common Coupling:

The Point of Common Coupling for a particular single customer is the point on the network where the power flow associated with the single customer under consideration, may under some (or all) possible arrangements interact with the power flows associated with other customers, taking into account all possible credible running arrangements.

13 January 201164 | Energy Networks Association

Page 65: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Sole Use Assets – Example (1)

13 January 201165 | Energy Networks Association

Page 66: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Sole Use Assets – Example (2)

13 January 201166 | Energy Networks Association

Page 67: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Sole Use Assets – Charges (1)

• SUA Charges applied are:– SUA MEAV (£) * Direct Operating Costs charging rate (%)

– SUA MEAV (£) * Network Rates charging rate (%)

• Direct Operating Cost charging rate is calculated as total direct costs divided by total assets, and applying EHV operating expenditure intensity factor (68%)

• Network Rates charging rate is calculated as total Network Rates divided by total assets

13 January 201167 | Energy Networks Association

Page 68: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Sole Use Assets – Charges (2)

13 January 201168 | Energy Networks Association

• Previous Consultation – SUA charge was allocated to the import tariff

• Current Consultation – SUA allocated between the import and export tariffs proportionally to import and export capacity

• EDCM charges relating to sole use assets will be charged as a fixed p/day charge to both import and export tariffs.

• The charging rates are applied equally to sole use assets attributed to demand and generation tariffs.

Page 69: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Sole Use Assets – Charges (3)

Application of demand scaling to SUA Charge:

• Demand scaling is not applied to the sole use asset charge in the consultation.

• DNOs considered applying a proportion of demand scaling to take account of replacement.

• Applying demand scaling means SUA would attract an allocation of residual revenue to the total EDCM revenue target

• Demand scaling is not applied as sole use assets tend to be fully contributed and are not always replaced.

• This position may change depending on consultation responses.

13 January 201169 | Energy Networks Association

Page 70: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Generation charges and scaling

Oliver Day

UK Power Networks

70 | Energy Networks Association 13 January 2011

Page 71: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Generation Charges

71 | Energy Networks Association

• Generation charges reflect both the costs and benefits provided by users exporting energy onto the network

• Costs are based on

– Marginal charges from LRIC/FCP

– Element relating to direct operating costs (sole use assets only)

– Element relating to business rates (sole use assets only)

– Scaling – maybe positive or negative

• Benefits are based on

– Marginal charges from LRIC/FCP

– Transmission exit

13 January 2011

Page 72: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Generation Tariffs

72 | Energy Networks Association

Generation tariffs comprise the following elements:

• Fixed Charge– Reflects a proportion of sole use asset charge for direct operating

costs and business rates

– Proportion based on split of import agreed capacity and export agreed capacity

• Export Capacity Charge– Reflects both the local and remote LRIC/FCP charge 2 and the

generation fixed adder

• Generation Credit– Reflects both the local and remote LRIC/FCP charge 1

• Excess reactive charge– Reflects the average revenue per unit in the EDCM

13 January 2011

Page 73: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Generation Charge Rationale

73 | Energy Networks Association

• Generation users could trigger generation caused reinforcement during minimum demand conditions

• Some generation users could offset need for demand caused reinforcement during maximum demand conditions

• Generators do not meet other network costs – reflecting the view that the prime driver for the network is demand users

• Generation charges are scaled to meet a generation target revenue

• Generation credits are not scaled

13 January 2011

Page 74: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Generation Scaling

74 | Energy Networks Association

• Generation scaling is the process of matching generation charges to a generation target revenue

• Generation scaling is entirely separate from demand scaling

• Any shortfall or excess in meeting the revenue target will be adjusted using a single fixed adder to export capacity charges

13 January 2011

Page 75: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Generation Target Revenue

75 | Energy Networks Association

• The generation target revenue for the EDCM represents an estimate of the DNO expenditure caused by EDCM generation users

• The target revenue is based on the actual distributed incentive revenue for post 2005 generators and a notional distributed generation revenue for pre 2005 generators

• This target revenue excludes the revenue that would be attributed to CDCM generation

13 January 2011

Page 76: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Tariff Structures

Pat Wormald

CE Electric

76 | Energy Networks Association 13 January 2011

Page 77: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Tariff Structures

77 | Energy Networks Association 13 January 2011

The following tariff components are calculated within the EDCM:

Tariff Component Demand Generation

Fixed charge Yes Yes

Capacity charge Yes Yes

Unit rate charge Yes – at the time of DNOs peak (super-red time period only)

Yes for credits – all year round

Excess reactive power charge

Yes (with the exception of sites subject to grid code requirements)

Yes (with the exception of sites subject to grid code requirements)

Under the EDCM, separate import (demand) and export (generation) tariffs will apply whenever metering allows for data about power flows in both directions to be recorded in settlements.

Page 78: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Demand Tariffs

78 | Energy Networks Association

• Marginal charges calculated using the FCP or LRIC methodologies;

• Transmission connection (exit) charges;• An element relating to the direct operating costs of the DNO;• An element relating to the indirect operating costs of the DNO;• An element relating to the business rates (network rates) payable

by the DNO; and• An element relating to the part of the DNO’s allowed revenue that

has not been charged using the cost-based charges above.

13 January 2011

Demand tariffs include the following elements which are calculated within the EDCM:

Page 79: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Tariff Components - Demand

79 | Energy Networks Association 13 January 2011

Tariff Component

Unit Correspondence to tariff elements

Fixed charge p/day Sole use asset charges for direct operating costs and network rates.

Import capacity charge*

p/kVA/day Reflects the local element of the FCP/LRIC charge 1, pre-allocation of direct operating costs, indirect costs, network rates and the demand scaling charge.

Super-red unit rate*

p/kWh Reflects the remote element of the FCP/LRIC charge 1.

Excess reactive power charge

p/kVArh Reflects average revenue per unit in the EDCM. Would not apply to sites subject to grid code requirements for generation.

Application of tariff components for demand tariffs

* May also include the transmission exit charge – (Consultation Q4)

Page 80: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Export Tariffs

80 | Energy Networks Association

• Marginal charges calculated using the FCP or LRIC methodologies;

• Credits based on FCP or LRIC methodologies;• Transmission connection (exit) credits;• An element relating to the direct operating costs of the DNO (for

sole use assets only);• An element relating to the business rates (network rates)

payable by the DNO (for sole use assets only); and• An element relating to generation scaling (this may be positive

or negative).

13 January 2011

Export tariffs include the following elements which are calculated within the EDCM:

Page 81: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Tariff Components - Export

81 | Energy Networks Association 13 January 2011

Tariff Component

Unit Correspondence to tariff elements

Fixed charge p/day Reflects sole use asset charges for direct operating costs and network rates.

Export capacity charge

p/kVA/day Reflects both local and remote element of the FCP/LRIC charge 2 and the generation scaling fixed adder.

Generation credit

p/kWh (negative)

Reflects both the local and remote element of the FCP/LRIC charge 1 (and any transmission exit credit).

Excess reactive power charge

p/kVArh Reflects average revenue per unit in the EDCM. Would not apply to sites subject to grid code requirements for generation.

Application of tariff components for export tariffs

Page 82: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Tariff Structures

82 | Energy Networks Association 13 January 2011

Following feedback from the workshops and earlier consultations we have taken on board the need for customers to influence the level of their charges within the charging year.

We therefore propose to implement unit charges and reactive power charges for demand, which will reflect the remote element of the FCP/LRIC charge 1. This was previously included as part of the capacity charge.

One of the questions we are asking in the consultation is whether or not we should also include transmission exit charges as a unit charge rather than as currently proposed as a capacity charge. Most DNOs support the capacity charge option as this is a fixed cost to DNOs – however we welcome your views.

Page 83: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Justification of charges and addressing outliers

Nigel Turvey

Western Power Distribution

83 | Energy Networks Association 13 January 2011

Page 84: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Justification of charges (1)

84 | Energy Networks Association 13 January 2011

Derogation to delay the submission deadline included the following requirement on each DNO*:

•“To make changes to the methodology as required following sense checks, to ensure they are able to justify the level of charges – particularly where charges are moving significantly (either up or down) from current levels”

* In a letter to DNOs on 27 Aug 2010

Page 85: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Justification of charges (2)

85 | Energy Networks Association 13 January 2011

Several licence conditions are of relevance to justifying charges:• SLC 19.1 - The licensee must not discriminate between any person or

class or classes of persons:– (a) in providing Use of System; ….

• 13B.8 - The second Relevant Objective is that compliance with the EDCM facilitates competition in the generation and supply of electricity and will not restrict, distort, or prevent competition in the transmission or distribution of electricity or in participation in the operation of an Interconnector.

• 13B.9 - The third Relevant Objective is that compliance with the EDCM results in charges which, so far as is reasonably practicable after taking account of implementation costs, reflect the costs incurred, or reasonably expected to be incurred, by the licensee in its Distribution Business.

• In addition, 50A.12 by referring to the original Ofgem specification requires a fixed adder to be used

Page 86: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Justification of charges (3)

86 | Energy Networks Association 13 January 2011

• We believe that: calculating the amount of total required revenue that should be allocated to EDCM demand customers by assessing their usage of assets at the time of system peak, is a fair way to allocate required revenue

• Both proposed methods of scaling residual revenue after allocating marginal costs, operating cost etc, have some risk of producing non-cost reflective charges

Page 87: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Outliers

87 | Energy Networks Association 13 January 2011

• Outliers with potentially non cost reflective charges can occur for several reasons including:

– The customer’s characteristics are significantly different from the ‘average’ on the network. e.g. a customer with a large capacity who only uses a short part of the network may face large and potentially unjustifiable charges under the voltage level scaling approach

– The power flow analysis could indicate usage of network assets that may not be strictly necessary to supply that customer if the network were designed from scratch. In such cases the site specific approach may result in charges that cannot be justified

• Consideration is being given to whether these issues can be addressed by ‘capping’ parts of the charges.

Page 88: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Outliers – Potential Solutions

88 | Energy Networks Association 13 January 2011

Potential solutions are:• For the voltage level scaling approach

– the ’80% of residual’ scaling element could be capped to an annuity on the value of site specific network assets used by the customer – this would improve the situation for customers using significantly less network than the average

– As the site specific network assets are calculated at the time of peak demand, it may be appropriate to scale these site specific network assets to the agreed capacity of the customer to account for those with low demands at the time of system peak

• For the site specific scaling approach– the network use factors could be capped to a specific value e.g. set

at 85th percentile – this would improve the situation for customers that would use significantly less network if it were being designed from scratch

Page 89: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Justification of charges summary

89 | Energy Networks Association 13 January 2011

• Resulting charges need to be justified

• After many options of scaling have been assessed it appears unlikely that there is one that produces justifiable charges in all circumstances

• Some form of capping to part of the charges may be necessary to address these outliers

• Ultimately, each DNO will have to satisfy itself that it is complying with the Licence

Page 90: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Interconnected Network Charging

Alan Stewart

SP Energy Networks

90 | Energy Networks Association 13 January 2011

Page 91: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Interconnected Network Charging (1)

91 | Energy Networks Association

• DNO to DNO interconnections

– Normally Closed (Active), benefitting one DNO only, will be treated as EDCM user.

– Closed, identifiable benefit to both DNOs, each DNO treats other as EDCM user.

– Open (To provide backup), Special arrangements agreed, UOS charges agreed outwith EDCM

– All Other, DNO charges other DNO as EDCM user

13 January 2011

Page 92: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Interconnected Network Charging (2)

92 | Energy Networks Association

• Offshore Network Charging

– EDCM

• DNO to Unlicensed Networks, either

– Part of Total System under BSC, can be treated as LDNOs

– Or, EDCM to calculate import & export at boundary

• DNO to nested Networks

– Dependant upon DCUSA modifications

– Development by IDNO/DNO Enduring Billing Group

13 January 2011

Page 93: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

IDNO Charging (1)

93 | Energy Networks Association

• LDNO Charging - CDCM– Portfolio tariffs for end users within CDCM

• Method M used to calculate discount percentages for LV, LVS & HV end users

• 33kV Boundary, 33kV s/stn Boundary & 132kV Boundary (E&W only)

• 2 Part charging process

– Separate percentages for Operating Costs, Dep’n & RAV elements (Excl Transmission exit charges)

– Split percentages for EHV network for EDCM asset levels

• Discount Calculated as ratio of network level provided by LDNO to sum of percentages for all network that would be provided by DNO

– Generation End Users• Treated similar to Demand Users

13 January 2011

Page 94: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

IDNO Charging (2)

94 | Energy Networks Association

• LDNO Charging – EDCM

– Portfolio tariffs for end users within EDCM

• Apply FCP/LRIC to calculate portfolio EDCM charge / credit

• Calculated as if EDCM end user notionally connected at boundary between DNO & LDNO

• Attract charges (credits) for reinforcement Caused (avoided)

• No charge for Sole use assets on LDNO network

• Charges for Sole use assets of an embedded DNO will be charged proportionally

• Demand Scaling to be applied as normal to EDCM user

– Generation scaling applied as normal to generators connected to LDNO’s network

13 January 2011

Page 95: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

IDNO Charging (3)

95 | Energy Networks Association

• LDNO Charging (Cont’d)

– Future Developments

• Write a Current User manual for Model M

• Update Model M to create fully integrated model to incorporate CDCM and latest EDCM proposals

• Provide new CDCM User Manual following consultation responses

• Submit to DCUSA / in line with Open Governance

13 January 2011

Page 96: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Any Questions?

96 | Energy Networks Association 13 January 2011

Page 97: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Lunch

Restart at 1.30pm

97 | Energy Networks Association 13 January 2011

Page 98: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Breakout sessions

Breakout sessions:

Pink, Green or Ice blue rooms

1:30 – 2:15

98 | Energy Networks Association 13 January 2011

Page 99: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Breakout groups

99 | Energy Networks Association 13 January 2011

Group A Mo Group B Andrew Group C Harvey

ICE BLUE ROOM GREEN ROOM PINK ROOM

Andrew Pace Andrew Neves Alan Stewart

Andy Manning Ben Nicaudie Christopher Granby

Christine Pearson Brian Harris-Ross Claire Campbell

Colin Prestwich Chris Goodwin Conor Martin

David Speake Dominique Tilquin Craig Handford

Franck Latremoliere Geoffrey Randall Diana Kennedy

Gary Holmes Glenn Sheern Garth Graham

Glyn Lenton Graham Ross Graeme Cooper

Guy Donald Jamie Paul Grant Elder

Julia Haughey John Cole Jane Griffiths

Karl Maryon Mark Hedges Harvey Jones

Michael Dodd Pat Wormald Hui Yi Heng

Mo Sukumaran Pippa Stirling Ian Walker

Peter Barry Shankar Rajagopalan Matt McDermot

Scott Francis Simon Russell Mike Harding

Stephen Booth Simon Vicary Nigel Turvey

Steve Matthews Simon Yeo Oliver Day

Stephen Andrews Rekha Theaker

Wasif Anwar Ynon Gablinger

Chenghong Gu

Page 100: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Breakout sessions feedback

Feedback from breakout sessions:

•Group A•Group B •Group C

100 | Energy Networks Association 13 January 2011

Page 101: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

EDCM workshop

Stakeholder involvement and next steps

Geoffrey Randall13 January 2011

101 | Energy Networks Association 13 January 2011

Page 102: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

How you can get involved

It is important to engage with industry now and not wait until Ofgem consults on the submission. There are a number of ways to do this:

•Respond to the DNOs’ consultation

•Individual DNO workshops / talk to relevant DNO(s)

•Work streams B (EDCM model) and C (volatility/transparency)

•DCMF – discussion forum every 2 months, next meeting 15 February

•ENA site http://energynetworks.squarespace.com/structure-of-charges-edcm/

If you have any further queries over the methodology please contact your DNO. If you require further assistance you can contact Ofgem at [email protected]

102 | Energy Networks Association 13 January 2011

Page 103: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Next steps

The key dates are:

•Consultation responses by 1 February 2011

•DNOs’ EDCM submission to Ofgem 1 April 2011

•Ofgem’s consultation ~ May 2011

•Ofgem’s decision by end August 2011

•EDCM implementation 1 April 2012

103 | Energy Networks Association 13 January 2011

Page 104: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

104 | Energy Networks Association 13 January 2011

Page 105: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Next steps

105 | Energy Networks Association

Andrew Neves

Central Networks

13 January 2011

Page 106: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

Next steps

Any Questions?

106 | Energy Networks Association 13 January 2011

Page 107: EDCM Development Workshop Welcome 1 | Energy Networks Association 13 January 2011

EDCM Development Workshop

Thank you!

107 | Energy Networks Association 13 January 2011