dpt1 - 01 - rig sizing and selection

Upload: brahim-letaief

Post on 03-Jun-2018

262 views

Category:

Documents


5 download

TRANSCRIPT

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    1/65

    Rig Sizing and SelectionRig Sizing and SelectionRig Sizing and SelectionRig Sizing and Selection

    DPT1

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    2/65

    At the end of this lecture YOU will be able to:

    Select a rig for a given well

    Rig Sizing & Selection - Objectives

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    3/65

    1. Types of rigs

    2. Hoisting system

    Loads: hook, fastline and deadline Drawworks sizing

    Drilling line Sizing, Ton-Miles, Slip & Cut

    Derrick, Rig Floor & Substructure

    3. Rotating System

    4. Circulating System

    5. BOP System

    6. Power System7. Group exercise: Select a Rig for a 30000ft well

    Rig Sizing & Selection - Agenda

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    4/65

    There are a number of considerations that are fundamental to the design of the wellprogram and selection of the drilling equipment that will be used.

    Territory in which to operate

    Ranges of well depths and hole sizes to be drilled

    Casing loads expected, Drill string components weights and sizes

    Range of rotary speeds and torque required

    Mud system, tanks and manifolding, solids control equipment

    Auxiliary services and power required

    Substructure height - clearances

    Blowout prevention equipment

    Rig Sizing - Introduction

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    5/65

    Rig Sizing - Introduction

    A drilling rig is made of many individual pieces of equipment which togetherform a unit to construct wells. Without this unit wells could not be drilled andcased.

    The correct procedure for selecting and sizing a drilling rig is as follows:

    1) Design the well.

    2) Establish the various maximum loads to be expected during drillingand all other operations to be done with the rig (Testing, Completions)

    3) Find rigs available in the area that match the requirements

    4) Discuss availability with Rig Contractors.

    5) Issue tenders and select rig based on cost, capability and availability

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    6/65

    Rig Types:

    Land rig

    Offshore rigs:

    Floating rigs:

    Semisubmersible

    Drillships

    Bottom-supported rigs:

    Jack-up

    Platform

    Barge

    Rig Sizing

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    7/65

    Land Rig

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    8/65

    Mobile Land rigs

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    9/65

    Jack-up Rigs

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    10/65

    Rig Move - Rowan Gorilla

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    11/65

    Submersible Rigs/Barges

    Submersibles can be anchored when used in water depths

    of up to 175ft, or can rest on the seabed when working inwater depths from 5 to 20 ft. Swamp barges are typically

    used to drill wells in shallow water depths of up to 20ft ininland waterways and swamps.

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    12/65

    Semi-submersible Rigs

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    13/65

    Semi-submersible Rigs

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    14/65

    Drillship

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    15/65

    Drillship

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    16/65

    Rig Types - Summary

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    17/65

    Rig Components

    The major rig components that need to be reviewed for

    capability are:

    Hoisting system

    Derrick capacity and substructure

    Rotating equipment

    Circulating system

    Pressure control

    Power requirements

    Tubular goods

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    18/65

    Hoisting System

    The hoisting system consists of:

    1. The Supporting Structure:

    Derrick

    Rig Floor

    Substructure

    2. The Hoisting Equipment

    Drawworks

    Crown block

    Traveling block

    Hook

    Drilling line

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    19/65

    Hoisting System - Drawworks

    This is an assembly of a rotating drum, a series of shafts, clutches,chains and gears for changing speed and for reversing. It alsocontains the main brake stopping the drilling line.

    The drilling line is wound a number of times around the drum andpasses to the crown and traveling blocks

    The Drum

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    20/65

    Hoisting System - Drawworks

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    21/65

    A block located at the top of derrick

    It contains a number of sheaves onwhich the drilling line is wound.

    The crown block provides a meansof taking the drilling line fromthe hoisting drum to thetraveling block

    The crown block is stationary and isfirmly fastened to the top of thederrick

    Each sheave inside the crownblock acts as an individualpulley

    Hoisting System Crown Block

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    22/65

    Hoisting System - Sheaves

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    23/65

    A diamond-shapedblock containing anumber of sheaveswhich is always lessthan those in the crownblock.

    The hook and bailshang below the TB tofacilitate drilling with

    the swivel andrunning pipe.

    Hoisting System Travelling Block

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    24/65

    Connects the Kellyor Top Drive with

    the travelling Block.

    The hook carriesthe entire drillingload

    Hoisting System - Hook

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    25/65

    Hoisting System - Swivel

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    26/65

    The Dead Line Anchor anchors the last line coming from thecrown block and allows new line to be fed from the reel inwhich it is stored. New lengths of line can be fed into thesystem. The used line is cut off at the drum side.

    Hoisting System - Deadline Anchor

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    27/65

    The drilling line is wound continuously on the Crown and TravelingBlocks, with two outside ends being wound on the hoisting drum andattached to the deadline anchor respectively.

    The block and tackle is a term used to refer to the arrangement of crownblock, drilling line and traveling block.

    Hoisting System - Block & Tackle

    Fastline

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    28/65

    Hoisting System Wire Rope

    Wire rope differs in the number of strands and pattern of wiresin the strand. Most wire rope constructions are grouped intofour standard classifications, based on the number of strandsand wires per strand as shown in the following table taken fromthe IADC Drilling Manual:

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    29/65

    The strands can be placed in a right or left direction and the wires in thestrand can be placed such that they appear to be parallel to the rope axis(Regular) or to the axis of the strands (Lang).

    Lay used for Drilling Lines:Right Regular Lay (RRL)

    Strands are preformed to give them the helical shape they will take when

    they are placed on the wire: preformed strands (PRF)

    Patterns used in drilling line: Filler Wire, Seale, Combined patterns

    Hoisting System Wire Rope Strands

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    30/65

    The primary purpose of the core in wire rope is to provide foundation or supportfor the strands. There are 3 types of core:

    Fiber Core (FC), Strand Core, Independent Wire Rope Core (IWRC)

    The strands provide the whole of the tensile strength of a FC rope but with aIWRC rope, the core contributes to the nominal strength. For example in a 6strand rope with IWRC, 7.5% of the nominal strength is attributed to the core.

    Wire rope used for Drilling Lines has IWRC

    Hoisting System Wire Rope Core & Grade

    All rotary drilling lines are of 2 grades: Improved Plow Steel (IPS) or Extra

    Improved Plow Steel (EIPS)

    A standard 6 strand EIPS rope within the same classification have a nominalstrength 15 % higher than IPS ropes.

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    31/65

    The correct diameter of a wire rope is the diameter of a circumscribed circle

    that will enclose all the strands. It is the largest cross-sectional measurement.

    Measurements should be carefully made with calipers.

    Hoisting System Wire Rope Size

    The size of most Drilling Lines varies from 1/2 to 2

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    32/65

    The table below taken from the SPE ADE textbookshows the nominal breaking strength for 6X19 wire rope.

    Hoisting System Wire Rope Strength

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    33/65

    1 = Diameter of line5000 = Length of line

    6 = Number of Strands per Line19 = Number of Wires per Strand

    S = Seale PatternPRF = Preformed StrandsRRL = Right Regular Lay

    IPS = Improved Plow SteelIWRC = Independent Wire Rope Core

    Strength = 89800 lbs

    Hoisting System - Wire Rope

    What does the following description of a rotary drilling line mean?What is its nominal strength?

    1 X 5000 6 X 19 S PRF RRL IPS IWRC

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    34/65

    Design Considerations

    1. Determine the deepest hole to be drilled

    2. Determine the maximum drilling loads or casing loads

    3. Use these values and compare to the derrick capacities on

    available rigs

    Elements for Calculation

    1. Static Derrick Loading

    2. Efficiency Factor3. Dynamic Crown Load

    Hoisting System Design

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    35/65

    Exercise RIG 00 - Hoisting System

    Line Tension and Derrick Load Under Static Conditions:

    Crown Block

    Fixedsheaves

    Deadline

    Hook

    W

    Drawworks

    Fastline

    WWWW4444 WWWW

    4444

    WWWW4444

    WWWW4444 WWWW

    4444

    WWWW4444

    n

    WF

    L =

    n

    )n(*WF

    D

    2+=Derrick Load =Line Tension =

    Where: W = hookload and n = number of lines

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    36/65

    For dynamic conditions friction between the line and sheaves has to beaccounted for:

    For roller bearings which are the normal type of bearings in a block & tackle

    system, the Friction Factor is K=1.04.

    Hoisting System Dynamic Loading

    Efficiency Factor of the Hoisting System: (API RP9B)

    )K(N*K

    KEF

    S

    N

    1

    1

    =

    Where: N = the number of lines and S = the number of sheavesNote: For the general configuration of a block and tackle system of a rotary drilling rig S = N.

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    37/65

    Exercise RIG 01: Efficiency Factor

    Calculate the efficiency factor for a hoisting systememploying 8 string lines.

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    38/65

    Dynamic Fast-Line Load:

    Dynamic Deadline -Load is given by:

    n*EF

    WFFL =

    n*EF

    )K/(*WF

    n

    DL

    1=

    Hoisting System Dynamic Loads

    What is the total derrick load under dynamic conditions ?

    DLFLDT FFWF ++=

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    39/65

    1. The Total Derrick Load should not exceed 80% of the minimum

    hoisting system rating

    2. If the breaking strength of the drilling line is known, then a designfactor, DF, may be calculated as follows:

    DF = Nominal strength of wire rope (lb) / Fast-line Load (lb)

    Min Design Factors;

    Drilling / Tripping : 3

    Casing Running : 2

    Hoisting System - Design

    H i i S D k P

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    40/65

    Hoisting System Drawworks Power

    Power developed at hook: P = W x Vhk

    Power consumed at the drum: P = FFL x Vf

    P = W x Vhk/ EF

    Drum output (horsepower) = W x Vhk / (EFx33,000)

    Vf = Velocity of fast-line load (Vf)

    Vhk= Velocity of traveling block

    Vf = N x Vhk

    As a rule of thumb, the drawworks should have 1 HP for every 10 ft to be

    drilled. Hence for 20,000 ft well, the drawworks should have 2000 HP.

    E i RIG 02 D k P

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    41/65

    Exercise RIG 02 Drawworks Power

    The following data refer to an Oilwell block-and-tackle system:

    Number of lines = 10 with EF = 0.81,

    Maximum expected hook load = 500,000 lbf,

    Hook load speed = 120 ft/min,Hoisting drum diameter = 32,

    Mechanical efficiency of drawworks = 0.88

    Calculate:

    1) The power at the drawworks

    2) The motor power required

    3) The fast line speed.4) The RPM of the drawworks drum.

    E i RIG 03 D illi Li L d

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    42/65

    Exercise RIG 03 Drilling Line Loads

    Consider a travelling block with 10 lines of 1.5 EIPS wire rope of strength 228klbs

    Hole depth(MD) = 10,500 ftDP = 4000 ft 5 - 19.5 lb/ft (S-135-NC 50) 22.61 approx #

    = 5700 ft 5 19.5 lb/ft (E-75-NC 50) 20.85 approx #

    Drill collars = 800 ft, 8 x 2.825, 150 lb/ftMud weight = 10 ppgSheave bearing type = Roller Bearing (K=1.04)Travelling Block Weight = 23,500 lbs

    Calculate:

    1) Weight of drill string in air and in mud

    2) Hook load.

    3) Dynamic deadline and fast-line loads.

    4) Dynamic crown load5) Wirerope Design Factor during drilling

    6) Design Factor when running 7 in casing of 29 lb/ft

    D illi Li Sli & C t

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    43/65

    Fig. M4-1 of the IADC Drilling Manual Illustrates thecritical wear points of drilling line.

    Drilling Line Slip & Cut

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    44/65

    Sli & C t T Mil g l

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    45/65

    Drum

    Diameter 1" 1 1/8" 1 1/4" 1 3/8" 1 1/2" 1 5/8"

    18" 6.0 9.0

    19" 6.0 9.020" 7.0 9.0

    21" 7.0 10.0

    22" 7.0 10.0

    23" 8.0 10.0 13.0

    24" 8.0 11.0 13.0 17.0

    25" 8.0 11.0 14.0 17.0

    26" 9.0 11.0 14.0 17.0

    27" 9.0 12.0 15.0 18.0

    28" 12.0 15.0 18.0

    29" 12.0 15.0 18.0

    30" 13.0 16.0 19.0

    31" 16.0 19.0

    32" 17.0 20.0

    33" 17.0 20.0

    34" 18.0 21.0 24.0

    35" 21.0 25.0

    36" 22.0 25.0 26.0

    TON MILE PER FOOT CUT GOAL FOR RIGS HAVING NO PAST

    PERFORMANCE RECORDS

    The table below from the IADC manual shows the starting goal of ton miles per ft.

    for a rig without previous records. Depending on results the goal can be increasedor decreased.It should be noticed that the goal changes with rope diameter and drum diameter

    of the drawworks.

    Slip & Cut Ton-Mile goal

    Slip & Cut Cutting Length

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    46/65

    The idea is to prevent the rope to be passed from one critical point to another

    one. The following table prevents this from occurring; however, other lengthscan be used.

    Slip & Cut Cutting Length

    Slip & Cut Practice Ton Miles

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    47/65

    Grand total of work done by the drilling line is the sum ofton-Miles done during:

    1. Drilling

    2. Coring

    3. Tripping

    4. Setting casing

    Slip & Cut Practice Ton Miles

    Slip & Cut Round Trips Work

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    48/65

    Work done in round trip operations (TR) ton-miles

    M = mass of traveling block assembly (lb),Ls = length of each stand (ft),D = hole depth (ft),We = effective weight per foot of DP in mud,C = (L x Wdc- L x Wdp) x BF,

    Wdc = weight of DC in airWdp = weight of DP in air,L = length of DCs.

    00064022

    00056010 ,,

    )C

    M(D

    ,,W)DL(*DT esR

    +

    ++

    =

    Slip & Cut Round Trips Work

    Slip & Cut Drilling Coring Casing

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    49/65

    Slip & Cut Drilling, Coring, Casing

    When drilling from depth D1 to depth D2, the work done is:

    When coring from D1 to D2, the work done is:

    T1= Round trip at depth D1 where drilling/coring startedT2 = Round trip at depth D2 where drilling/coring stopped before POOH

    When setting Casing at depth D, the work done is:

    Wcs = effective weight per unit length of casing in mudLs = length of 1 Casing joint

    +

    +=

    000640200056010

    21

    ,,

    DM

    ,,

    W)DL(D/T

    csss

    [ ]123 TTxTd =

    [ ]122 TTxTc =

    Exercise RIG 04 Ton Miles Evaluation

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    50/65

    Exercise RIG 04 Ton Miles Evaluation

    Using the data given in Exercise RIG 03, determine;

    1) Round trip ton-miles at 10,000 ft;

    2) Casing ton-miles if one joint of casing = 40 ft ;

    3) Design Factor of the drilling line when the 7 inch casing is

    run to 10,000 ft;

    4) Ton-Miles when coring from 10,000 ft to 10.180 ft and5) Ton-Miles when drilling from 10,000 to 10,180 ft.

    Derrick Capacity and Substructure

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    51/65

    The derrick sits on a substructure on which the drillingequipment is mounted.

    The substructure must be rated to hold pipe setback plus the

    load of the heaviest casing run.The height of the substructure above the ground varies

    according to the size of the rig. It varies from 10 to 35

    Derrick Capacity and Substructure

    The derrick must support hookloads, deadline load, fastlineload, pipe setback and wind loads.

    The derrick provides the necessary height and support to lift

    loads in and out of the well

    Derricks

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    52/65

    Standard Derrick:

    Bolted structure that must be assembled part by part, usually used on offshoreplatforms.

    Derrick installed on floating rigs are designed to withstand extra dynamic stressesdue to rolling, heaving and stresses from the wind

    The space available between the rig floor and the crown block must be higher to

    handle the wave-induced vertical movement of the floating support.

    Derricks

    Mast or Portable Derrick:

    This type is pivoted at its base and is lowered to the horizontal by the use of

    drawworks after completing the well and the rig is ready to move to anotherlocation

    The mast is dismantled into a number of pin-jointed sections, each of which isusually a truck load.

    Mast or Portable Derrick

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    53/65

    Mast or Portable Derrick

    Rig Sizing & Selection - Agenda

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    54/65

    1. Types of rigs

    2. Hoisting system

    Loads: hook, fastline and deadline

    Drawworks sizing

    Drilling line Sizing, Ton-Miles, Slip & Cut

    Derrick, Rig Floor & Substructure

    3. Rotating System4. Circulating System

    5. BOP System

    6. Power System

    7. Group exercise: Select a Rig for a 30000ft well

    Rig Sizing & Selection - Agenda

    Rotating System

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    55/65

    Rotating System

    Rotary HorsePower

    The Rotary Horsepower requirement is usually

    between 1.5 to 2 times the rotary speed, depending onthe hole depth.

    Hence for rotary speed of 200 RPM, the powerrequirement is about 400 HP.

    Circulating System

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    56/65

    Circulating System

    Hydraulic Horsepower:The horsepower requirements of the

    pumps depends on the flow-rateand the pressure.

    1714

    )psi(essurePrx)gpm(FlowRateHP =

    The heart of the circulating system is

    the mud pumps

    Circulating System Mud Pumps

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    57/65

    A basic pump consists of a piston reciprocating inside a cylinder.

    A pump is described as single acting if it pumps fluid on the forward strokes

    (triplex pumps) and double-acting if it pumps fluid on both the forwardand backward strokes (duplex)

    Pump Liners fit inside the pump cavity, these affect the pressure rating and

    flowrate from the pump.

    Circulating System Mud Pumps

    For a given pump, different size liners have the same OD but different ID.

    The smaller liner (small ID) is used in the deeper part of the well where lowflow-rate is required but much higher operating pressure

    Circulating System Triplex Pumps

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    58/65

    Circulating System Triplex Pumps

    Mud Pumps Stroke & Efficiency

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    59/65

    A full hydraulic program needs to be calculated to determine the

    pressure requirement of the pump.

    The size of the pump is determined by the length of its stroke and thesize of the liner.

    Mud Pumps Stroke & Efficiency

    Volumetric Efficiency:

    Drilling mud usually contain little air and is slightly compressible. Hence thepiston moves through a shorter stroke than theoretically possible before

    reaching discharge pressure,

    As a result, the volumetric efficiency is always less than one; typically 95% fortriplex and 90% for duplex.

    In addition, due to power losses in drives, the mechanical efficiency of mostpumps is about 85%.

    Exercise RIG 05 Mud Pump Power

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    60/65

    Calculate the power requirement for the following pump:

    Flowrate = 1200 gpm,

    Pressure = 2000 psi,

    Mechanical Efficiency = 0.85

    p

    Circulating System -Auxiliaries

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    61/65

    Centrifugal Pumps:

    This type of pump uses an impeller for the movement of fluid, rather apiston reciprocating inside a cylinder. Centrifugal pumps are used

    to surcharge mud pumps and to provide fluid to solids controlequipment and mud mixing equipment.

    Mud Handling Equipment:

    Shale Shakers: size, type.

    Mud Pits: Number and size is determined by the size and the depth ofhole. Also by the size of the rig and space available, especially on

    offshore rigs. Size of a pit usually 8-12 ft wide, 20-40 ft long and 6-12 ft high

    Desanders, Desilters.

    Centrifuges and mud cleaners

    Degasser

    g y

    Pressure Control Equipment

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    62/65

    q p

    Required as per IPM Standards HSE 001, WCI 003, WCI 005 :

    Gas Detection Equipment

    BOP Stack and Diverter Kick Detection Equipment (Trip Tank, Flowshow)

    Required as per Good Oilfield Practice :

    Choke manifold, Choke and Kill lines

    Accumulator and BOP Control System

    Rotating heads if air drilling or UBD

    A fluids system with enough storage for all hole sections +100%

    Power System

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    63/65

    The power on modern rigs is most commonly generatedby diesel-electric power units,

    The power produced is AC current which is then isconverted to DC current by the use of SCR (SiliconControlled Rectifier),

    The current is delivered by cables to electric motors

    attached directly to the equipment involved such as mudpumps, rotary table, drawworks etc.

    y

    Power Requirements

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    64/65

    q

    The total power requirements of a rig is the sum of the power requirement of:

    Drawworks

    Rotary table or top drive

    Mud pumps Mud handling system.

    Auxiliary power requirements for lighting etc,

    Life support system.

    The actual power required will depend on the operation being carried out:

    - The maximum power used is during hoisting and circulation.

    - The least power used is during wireline operations

    Rig Sizing & Selection - Agenda

  • 8/11/2019 DPT1 - 01 - Rig Sizing and Selection

    65/65

    1. Types of rigs

    2. Hoisting system

    Loads: hook, fastline and deadline

    Drawworks sizing

    Drilling line Sizing, Ton-Miles, Slip & Cut

    Derrick, Rig Floor & Substructure

    3. Rotating System4. Circulating System

    5. BOP System

    6. Power System

    7. Group exercise: Select a Rig for a 30000ft well

    g g g