TURKISH STATE RAILWAYS (TCDD)Infrastructure Development & Regulations in Railway Sector

1

Ministry of Transport, Maritime Affairs and Communications

Page 2: TURKISH STATE RAILWAYS (TCDD)

Historical Development

State of Play

Key Projects

CONTENTS

Vision 2023

The Law on Liberalization of Rail Transport in Turkey

Page 3: TURKISH STATE RAILWAYS (TCDD)

Historical Development

State of Play

Key Projects

CONTENTS

Vision 2023

The Law on Liberalization of Rail Transport in Turkey

Page 4: TURKISH STATE RAILWAYS (TCDD)

YEAR 1856

YEAR 1924

YEAR 1927

YEAR 1950

YEAR 1953

YEAR 1984

YEAR 2003

YEAR 2004

YEAR 2008

YEAR 2009

The first high speed line was completed.

Total length of railways increased to 10.991 km and 6 of our ports were included in the privatisation programme.

Rail transport operations were opened to private sector.

Became a Public Economic Institution.

Became a State Economic Enterprise.

Total length of railways reached to 9.204 km.

General Administration of State Railways and Ports. (5.500 km)

The first railway construction between İzmir-Aydin

4.000 km long railways were nationalised

Ports were attached tothe Railways

Total length of railways: 9.204 km

Became a State Economic Enterprise

Became a Public Economic Institutiıon

Rail transport operations were opened to private sector.

Total length of railways: 10.991 km

The first high speed line were completed.

10 million passengers were transported. «The Law on Liberalization of Rail Transport in Turkey»entered into force on 1st May 2013YEAR 2013

Nationalization of the Railways

HISTORICAL DEVELOPMENT OF RAILWAYS

Page 5: TURKISH STATE RAILWAYS (TCDD)

Rail Network before the REPUBLIC 4,136 km Mainline

The First Years of the REPUBLIC (1923-1950) 3,764 km Mainline (avg. 134 km per annum)

From 1951 to 2002 945 km Mainline (avg. 18 km per annum)

From 2005 to end of 2012 1,094 km Mainline (avg. 137km per annum)

Lines under construction 3,400 km Mainline

İSTANBUL

EDİRNE

ESKİŞEHİR

POLATLI

ANKARA

KONYA

İZMİR

SİVAS

AFYON

KAYSERİ

BURSA ERZİNCAN

ERZURUM

KARS

MERSİN

ADANA GAZİANTEP

DİYARBAKIR

ELAZIĞ

MALATYA

ZONGULDAK

SAMSUN

BANDIRMA

VANTATVAN

2012 : 12,008 km ( Conventional+ High Speed)   

HISTORICAL DEVELOPMENT OF RAILWAYS

Page 6: TURKISH STATE RAILWAYS (TCDD)

Historical Development

State of Play

Key Projects

CONTENTS

Vision 2023

The Law on Liberalization of Rail Transport in Turkey

Page 7: TURKISH STATE RAILWAYS (TCDD)

Conventional Lines

High Speed Lines 

8 REGIONAL DIRECTORATES

7 PORTS

3 AFFILIATED COMPANIES

5 FACTORIES

İSTANBUL, ANKARA (2 Directorates), İZMİR, SİVAS, MALATYA, ADANA, AFYON

H.PAŞA, DERİNCE, İZMİR,(MERSİN, İSKENDERUN, SAMSUN and BANDIRMA  privatized.)

TÜLOMSAŞ, TÜVASAŞ, TÜDEMSAŞ

ADF and RAIL WELDING, AFYON and  SİVAS CONCRETE SLEEPER, ÇAMAF

4  PARTICIPATIONS EUROTEM, İZBAN, VADEMSAŞ, SİTAŞ

MALATYA

MERSİN

ÇAMAF

İSTANBUL

İSKENDERUN

SİVAS

ADANA

ANKARA

AFYON

İZMİR

SAMSUN

İZMİR

H.PAŞA

EUROTEM

ADF

TÜVASAŞ

TÜLOMSAŞTÜDEMSAŞ

SİVAS BT TRV

AFYON BT TRV

ESKİŞEHİR

IZBAN

BANDIRMA

DERİNCEVADEMSAŞ

ÇANKIRI

KONYA

ADAPAZARI

SİTAŞ

4 Participations have been established since 2003. 

ORGANIZATION

Page 8: TURKISH STATE RAILWAYS (TCDD)

Historical Development

State of Play

Key Projects

CONTENTS

Vision 2023

The Law on Liberalization of Rail Transport in Turkey

Page 9: TURKISH STATE RAILWAYS (TCDD)

RAIL INVESTMENTS

While the appropriation allocated for railways were 488 million TL in 2003, it reached

7 billion 929 million TL in 2013 increasing by 16 times.

0

1.000

2.000

3.000

4.000

5.000

6.000

7.000

8.000

2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

488964 1.060

1.460

2.184 2.350 2.281

4.5584.843

6.854

7.929

Million TL 

Page 10: TURKISH STATE RAILWAYS (TCDD)

TRANSPORTATION CORRIDORS (PROJECTED)

Istanbul‐Basra, Istanbul‐Kars‐Tbilisi‐Baku, Kavqaz‐Samsun‐Basra, Istanbul‐Aleppo‐Makkah, Istanbul‐Aleppo‐the North Africa/the South East Asia transportation corridors will be developed.

Istanbul‐Basra, Istanbul‐Kars‐Tbilisi‐Baku, Kavqaz‐Samsun‐Basra, Istanbul‐Aleppo‐Makkah, Istanbul‐Aleppo‐the North Africa/the South East Asia transportation corridors will be developed.

Samsun‐Kavqaz

Kars‐Tbilisi‐Baku

Kars‐Nahcevan‐Iran

Marmaray

Lake Van Crossing

North AfricaSouth East Asia

Tekirdağ‐Muratlı

The Middle East

Far East Asia

Kurtalan‐ Nusaybin‐ Iraq

The Central and North Asia

Page 11: TURKISH STATE RAILWAYS (TCDD)

MARMARAY PROJECT

Kazlıçeşme

Yenikapı

Sirkeci

Üsküdar

Ayrılıkçeşme

3. Procurement of new Rolling Stocks (CR2)

– 440 new train sets.

1. The Bosphorus Crossing (BC1)–Immersed tube tunnel (1,4 km),–Immersed tube depth is 60 m,–12 km bored tunnels & cut-cover tunnels, –4 new stations.

2. The Upgrading of the Commuter Rail (CR1/CR3)– New high standard triple track line (~ 65 km),– 37 new stations.

Total length : Approx. 77 km– At grade, European side 19.6 km 

– At grade, Asian side 43.4 km– Bored tunnels 12.2 km– Immersed tube tunnel 1.4 km

Marmaray (Ayrılıkçeşme-Kazlıçeşme) was commissioned on 29th October 2013. The line and

station renewal works are ongoing on Pendik-Söğütlüçeşme and Kazlıçeşme–Halkalı sections.

Page 12: TURKISH STATE RAILWAYS (TCDD)

Inauguration: October 29, 2013MARMARAY PROJECT

Page 13: TURKISH STATE RAILWAYS (TCDD)

İSTANBUL

EDİRNE

ESKİŞEHİR

Polatlı

ANKARA

KONYA

İZMİR

SİVAS

AFYONKARHİSAR

KAYSERİ

BURSA

ERZİNCAN

ERZURUM

KARS

MERSİN ADANA

GAZİANTEP

DİYARBAKIR

ELAZIĞ

MALATYA

ZONGULDAK SAMSUN

Bandırma

VAN

MUŞ

BİLECİK

ÇANKIRI

KIRIKKALE

TEKİRDAĞ

İZMİT

BALIKESİR

AYDINDENİZLİ

BURDUR

ISPARTA

UŞAKMANİSA

KARAMAN

NİĞDE

OSMANİYE

K.MARAŞ

AMASYA

BATMAN

MARDİN

Yerköy

KARABÜK

Yenişehir

Current YHT lines (888 km)

YHT lines under constructionYHT lines with final drawing completedYHT lines with final drawing under development

405 km

212 km

533 km

105 km

624 km

High Speed Trains (YHTs) are in operation between Ankara-Eskişehir since 13th March 2009.High Speed Trains (YHTs) are in operation between Ankara-Konya since 24th August 2011.High Speed Trains (YHTs) are in operation between Eskişehir-Konya since 23th March 2013.High Speed Trains (YHTs) will be put into operation between Ankara-Istanbul in 2014.High Speed Trains will be put into operation in Bursa-Bilecik, Ankara-İzmir and Ankara-Sivas by 2016.

HIGH SPEED RAILWAY NETWORK IS EXPANDING

Page 14: TURKISH STATE RAILWAYS (TCDD)

KONVANSİYONEL DEMİRYOLU PROJELERİ 2023 HEDEFİ

İSTANBUL

EDİRNE

ESKİŞEHİR

Polatlı

ANKARA

KONYA

İZMİR

SİVAS

AFYONKARHİSAR

KAYSERİ

ERZİNCAN

ERZURUM

KARS

MERSİN

ADANA

DİYARBAKIR

ELAZIĞ

MALATYA

ZONGULDAK

SAMSUN

Bandırma

VAN

MUŞ

BİLECİK

ÇANKIRI

KIRIKKALE

TEKİRDAĞ

İZMİT

BALIKESİR

AYDIN

DENİZLİBURDUR

ISPARTA

UŞAK

MANİSA

KARAMAN

NİĞDE

OSMANİYE

K.MARAŞ

AMASYA

BATMAN

MARDİN

KARABÜK

Palu

NusaybinHabur

Ş.URFA

Muratlı

Cumaovası

Tepeköy

Ödemiş

Kiraz

TavşanlıEnveriye

Aliağa

Bergama

Ispartakule

Halkalı

Arifiye

Pamukova

Ulukışla

Topr

akka

le

Bahç

e

Nur

dağ

B.pı

nar

A.göze

Nar

M.y

avuz

Bartın

Ereğli

Karasu A.pazarı

Turgutlu

K.paşa

Gemlik

BURSA

Tire

Güllük

Dilucu

8

Constructed lines (153 km)Lines under construction (978km)Lines at the phase of construction tender (298 km)Lines with final drawings produced (202km)Lines with final drawings in progress (4.038 km)

CONVENTIONAL RAILWAY PROJECTS

Page 15: TURKISH STATE RAILWAYS (TCDD)

KARS KARS

Nusaybin Nusaybin

G.ANTEP G.ANTEP KarkamışKarkamışT.kale T.kale

Yenice Yenice

MERSİN MERSİN

MenemenMenemen MANİSAMANİSA

AdapazarıAdapazarı

ArifiyeArifiye

P.ovaP.ova

TEKİRDAĞTEKİRDAĞ

MuratlıMuratlı

ZONGULDAKZONGULDAK

IrmakIrmak

ÇarşambaÇarşamba

PolatlıPolatlı

BoğazköprüBoğazköprü

SAMSUNSAMSUN

ANKARAANKARA

YenifakılıYenifakılı

KONYAKONYA

SİVASSİVAS

GelemenGelemen

KAYSERİKAYSERİ

UlukışlaUlukışla

DoğukapıDoğukapı

ERZURUM ERZURUM

ERZİNCAN ERZİNCAN

Kapıköy Kapıköy VAN VAN Tatvan Tatvan

MUŞMUŞ

BATMANBATMAN

Kurtalan Kurtalan DİYARBAKIR DİYARBAKIR

MALATYA MALATYA

ELAZIĞELAZIĞ

Çetinkaya Çetinkaya

KARAMANKARAMAN

K.MARAŞK.MARAŞ

ADANA ADANA

AFYONAFYON

KarakuyuKarakuyuİZMİRİZMİR

ÖdemişÖdemiş

SökeSökeDENİZLİDENİZLİ

ÇivrilÇivril

BURDURBURDURISPARTAISPARTA

EreğliEreğli

TorbalıTorbalı

AliağaAliağa

BALIKESİRBALIKESİRNusratNusrat

GökçedağGökçedağ

BandırmaBandırma

SeyitömerSeyitömerESKİŞEHİRESKİŞEHİR

KIRKLARELİKIRKLARELİ

HaydarpaşaHaydarpaşa

HalkalıHalkalı

UzunköprüUzunköprü

HudutHudut

Renewed tracksTracks to be renewed

7.261 km tracks were renewed during the last decade.

The total length of tracks to be renewed in 2013 is 1.098 km.

TRACKS UNDER RENEWAL 

15

Page 16: TURKISH STATE RAILWAYS (TCDD)

İSTANBUL

EDİRNE

ESKİŞEHİRANKARA

KONYA

İZMİR

SİVAS

AFYONKARHİSAR

KAYSERİ

BURSA ERZİNCAN

ERZURUM

KARS

MERSİN ADANA

GAZİANTEP

DİYARBAKIR

ELAZIĞ

MALATYA

ZONGULDAK SAMSUN

Bandırma

VAN

MUŞ

BİLECİK

ÇANKIRI

KIRIKKALE

TEKİRDAĞ

İZMİT

BALIKESİR

AYDINDENİZLİ

BURDUR

ISPARTA

UŞAKMANİSA

KARAMAN

NİĞDE

OSMANİYE

K.MARAŞ

AMASYA

BATMAN

MARDİN

KARABÜK

Divriği

T.kale

İskenderun

C.ovası

Aliağa

495 km

374 km

KÜTAHYA356 km

68 km

581 km

Tepeköy

67 km

Ulukışla

214 km

376 km

134 km

Selçuk52 km

Ortaklar

176 km

183 km

BAŞKENTRAY

393 km

136 km

410 km467 km

697 km

415 km

410 km

70 km

67 km

Operational signalled lines  ( 3.128 km)Lines under construction (2.493 km) Lines at the phase of construction tender(583 km) Lines with final drawings produced (67 km) Lines with final drawings in progress (2.998 km)

SIGNALLED RAILWAY NETWORK IS BECOMING WIDESPREAD

Page 17: TURKISH STATE RAILWAYS (TCDD)

Özel Sektör

Kamu

Özel Sektör

KamuKamu SektörüKamu SektörüHALEP

Güllük

Sincan Yerköy

KarasuEreğli

KartalSapancaHalkalı

Turgutlu

Torbalı

Manavgat

Alanya

Aliağa

Karkamış

HaburUlukışla

Yenice

Boğazköprü

Polatlı

Gemlik

Nusaybin

Cizre

Narlı

Hanlı

Mürşitpınar

ANKARAESKİŞEHİR

KAYSERİ

KONYA

ERZİNCAN

İSTANBUL

İZMİR

BALIKESİR BURSA

UŞAKMANİSA

KARAMANANTALYA

BARTIN

TRABZONKARS

MALATYA

ELAZIĞ

DİYARBAKIR

MARDİN

GAZİANTEP

AYDIN

ADANA

MERSİN

ADAPAZARI

EDİRNE

ŞANLIURFA

SAMSUN

ERZURUM

BİLECİK

DENİZLİ

EĞİRDİREĞİRDİR

ISPARTA

ISPARTA

GONCALIGONCALI

BURDUR

BURDUR

AFYONAFYON

National Railway Signaling System is developed by the cooperation of ;TCDDTÜBİTAK (The Scientific and Technological research Council of Turkey )İTÜ (Istanbul Technical University)

National Railway Signaling System is developed by the cooperation of ;TCDDTÜBİTAK (The Scientific and Technological research Council of Turkey )İTÜ (Istanbul Technical University)

The signaling project of Afyon-Denizli-Isparta line section (21 stations and 338 km length) will be achieved by TCDD, TÜBİTAK and İTÜ. This signaling system is aimed to become widespread in the country.

NEW SIGNALLING SYSTEM IS DEVELOPED

Page 18: TURKISH STATE RAILWAYS (TCDD)

İSTANBUL

EDİRNE

ESKİŞEHİRANKARA

KONYA

İZMİR

SİVAS

AFYONKARHİSAR

KAYSERİ

BURSA ERZİNCAN

ERZURUM

KARS

MERSİN ADANA

GAZİANTEP

DİYARBAKIR

ELAZIĞ

MALATYA

ZONGULDAK SAMSUN

Bandırma

VAN

MUŞ

BİLECİK

ÇANKIRI

KIRIKKALE

TEKİRDAĞ

İZMİT

BALIKESİR

AYDINDENİZLİ

BURDUR

ISPARTA

UŞAKMANİSA

KARAMAN

NİĞDE

OSMANİYE

K.MARAŞ

AMASYA

BATMAN

MARDİN

KARABÜK

Divriği

T.kale

İskenderun

C.ovası

Aliağa

495 km

374 km

KÜTAHYA356 km

68 km

581 km

Tepeköy67 km

Ulukışla

920 km

Selçuk52 km

MERSİN ADANAKARAMAN T.kale

İskenderun

134 km

183 km

BAŞKENTRAY

507 km

410 km

136 km

410 km

70 km415 km

67 km

552 km

Operational electrified lines (Current2.328 km) Lines under construction(1.446 km) Lines at the phase of construction tender(1.289 km)Lines with final drawings produced( 562 km) Lines with final drawings in progress (2.486 km) 

ELECTRIFIED RAILWAY NETWORK IS BECOMING WIDESPREAD

Page 19: TURKISH STATE RAILWAYS (TCDD)

Halkalı/İstanbulKöseköy/İzmit

Gökköy/Balıkesir

Uşak

Kaklık/Denizli

Kayacık/Konya

Yenice/Mersin

Türkoğlu/K.maraş

Boğazköprü/Kayseri

MardinHabur

Palandöken/Erzurum

Kars

Sivas

Gelemen/SamsunYeşilbayır/İstanbul

Bozüyük/Bilecik

Hasanbey/Eskişehir

It is planned to construct 18 Logistics Centers. 5 logistics centers in Samsun, Uşak, Denizli (Kaklık), Köseköy and Halkalı were put into operation. The construction works are going on in 6 logistics centers in Eskişehir, Balıkesir, Bozüyük, Mardin, Erzurum, Mersin (Yenice). The final drawings and expropriation studies are going on for 7 logistics centers.

LOGISTIC CENTERS ARE BEING ESTABLISHED

Page 20: TURKISH STATE RAILWAYS (TCDD)

VarnaPoti

Mersin

KavkazSamsun

Samsun(Turkey)-Kavkaz ( Russia) train ferry line through Black Sea, was officially put into service on 19th February 2013.

CONNECTIONS ARE BEING IMPROVED WITH TRAIN‐FERRY TRAFFIC

Page 21: TURKISH STATE RAILWAYS (TCDD)

21

Total Length  : 101 kmKars ‐ Georgia  : 73 kmTurkey ‐ Ahilkelek : 28 kmConstruction in Georgia started on21.11.2007Construction in Turkey started on24.7.2008 and will be completed in 2013. 

Existing Line in Georgia

Existing Line in Turkey

TURKEY

GEORGIA

Construction in Turkey: 76 km

Construction in Georgia: 29 km

KARS – TBILISI – BAKU PROJECT

Page 22: TURKISH STATE RAILWAYS (TCDD)

İSTANBUL

EDİRNE

ESKİŞEHİR

Polatlı

ANKARA

KONYA

İZMİR

SİVAS

AFYONKARHİSAR

KAYSERİ

BURSA

ERZİNCAN

ERZURUM

KARS

MERSİN ADANA

GAZİANTEP

DİYARBAKIR

ELAZIĞ

MALATYA

ZONGULDAK SAMSUN

Bandırma

VAN

MUŞ

BİLECİK

ÇANKIRI

KIRIKKALE

TEKİRDAĞ

İZMİT

BALIKESİR

AYDINDENİZLİ

BURDUR

ISPARTA

UŞAKMANİSA

KARAMAN

NİĞDE

OSMANİYE

K.MARAŞ

AMASYA

BATMAN

MARDİN

Yerköy

KARABÜK

To be operated between Tatvan – Van; 2 Ferries with a capacity of 50 wagons along with repairing of landing piers and construction of warehouse for ferriesThe ferries is being manufactured. Planned to be ready for operation at the end of 2014.

PROCUREMENT of NEW FERRIES

22

TATVAN

Page 23: TURKISH STATE RAILWAYS (TCDD)

RAILWAY CORRIDORS IN OUR REGION

Samsun‐Kavkaz

Kars‐Tbilisi‐Baku

Kars‐Nakhchivan‐Iran

Marmaray

Lake Van Crossing

North Africa

South East Asia

Tekirdağ‐Muratlı

The Middle East

Far East Asia

Nusaybin‐ Iraq

The Central & 

North AsiaEurope

There is a 75‐billion USD transport potential between Europe and Asia.

After the completion of the railway projects in Turkey, the Silk Road will gain more importance andEurope, Asia, esp. the Middle East, and the Central and Far East Asia will be interconnected by rail.

Istanbul‐Kars‐Tbilisi‐Baku, Nusaybin‐Iraq, Kars‐Nakhchivan‐Iran, Kavkaz‐Samsun‐Basra, 

Istanbul‐Aleppo‐Makkah & Istanbul‐Aleppo‐North Africa  transport corridors are being developed.

Page 24: TURKISH STATE RAILWAYS (TCDD)

R&D

Corporation

INDUSTRY

State

Training

UNIVERSITY

Manufacture

Railway Research and Technology Center, which aims to become bridge between local industry and universities and implement new technologies is established within TCDD.

THE IMPORTANCE OF R&D IS INCREASING

Page 25: TURKISH STATE RAILWAYS (TCDD)

The Law on Liberalization of Rail Transport in Turkey

Historical Development

State of Play

Key Projects

CONTENTS

Vision 2023

Page 26: TURKISH STATE RAILWAYS (TCDD)

İSTANBUL

EDİRNE

ESKİŞEHİR

Polatlı

ANKARA

KONYA

İZMİR

SİVAS

AFYONKARHİSAR

KAYSERİ

BURSA

ERZİNCAN

ERZURUM

KARS

MERSİN ADANA

GAZİANTEP

DİYARBAKIR

ELAZIĞ

MALATYA

ZONGULDAK SAMSUN

Bandırma

VAN

MUŞ

BİLECİK

ÇANKIRI

KIRIKKALE

TEKİRDAĞ

İZMİT

BALIKESİR

AYDINDENİZLİ

BURDUR

ISPARTA

UŞAKMANİSA

KARAMAN

NİĞDE

OSMANİYE

K.MARAŞ

AMASYA

BATMAN

MARDİN

Yerköy

KARABÜK

Yenişehir

405 km

212 km

533 km

624 km

Çobanbey

VISION 2023 HIGH SPEED LINES

TRABZON

Constructed HSLs (Ankara‐Eskişehir, Ankara‐Konya ‐ 888 km)HSLs under construction ( 1.748 km) HSLs at the stage of construction tender(454 km) HSLs with final drawings produced (4.728 km) HSLs with final drawings in progress ( 2.212 km)

Page 27: TURKISH STATE RAILWAYS (TCDD)

VISION 2023 CONVENTIONAL LINES

KONVANSİYONEL DEMİRYOLU PROJELERİ 2023 HEDEFİ

İSTANBUL

EDİRNE

ESKİŞEHİR

Polatlı

ANKARA

KONYA

İZMİR

SİVAS

AFYONKARHİSAR

KAYSERİ

ERZİNCAN

ERZURUM

KARS

MERSİN

ADANA

DİYARBAKIR

ELAZIĞ

MALATYA

ZONGULDAK

SAMSUN

Bandırma

VAN

MUŞ

BİLECİK

ÇANKIRI

KIRIKKALE

TEKİRDAĞ

İZMİT

BALIKESİR

AYDIN

DENİZLİBURDUR

ISPARTA

UŞAK

MANİSA

KARAMAN

NİĞDE

OSMANİYE

K.MARAŞ

AMASYA

BATMAN

MARDİN

KARABÜK

Palu

NusaybinHabur

Ş.URFA

Muratlı

Cumaovası

Tepeköy

Ödemiş

Kiraz

TavşanlıEnveriye

Aliağa

Bergama

Ispartakule

Halkalı

Arifiye

Pamukova

Ulukışla

Topr

akka

le

Bahç

e

Nur

dağ

B.pı

nar

A.göze

Nar

M.y

avuz

Bartın

Ereğli

Karasu A.pazarı

Turgutlu

K.paşa

Gemlik

BURSA

Tire

Güllük

Dilucu

8

Constructed conventional lines (153 km) 

Conventional lines under construction (978km) 

Conventional Lines at the stage of construction tender(298 km)

Conventional Lines with final drawings produced (202km) Conventional Lines with final drawings in progress (4.038 )

Page 28: TURKISH STATE RAILWAYS (TCDD)

Historical Development

State of Play

Key Projects

CONTENTS

Vision 2023

The Law on Liberalization of Rail Transport in Turkey

Page 29: TURKISH STATE RAILWAYS (TCDD)

RE‐ORGANISATION OF RAILWAY SECTOR IN TURKEY

29

Directorate General for Regulation of Railways

Regulatory Body

Safety Authority

Contract Manager for PSO

Accident Search & Investigation Board

DG for Infrastructure Investments

DG for Regulation of Dangerous Goods and Combined Transport

DECREE LAW No:655 (in 2011)

For All Transport Modes

Page 30: TURKISH STATE RAILWAYS (TCDD)

NEW LAW on SECTOR LIBERALIZATION

The Law No: 6461 on Liberalization of Rail Transport in Turkey was 

entered into force on 1 May 2013.

Main Objectives:

Restructuring of TCDD as Infrastructure Manager

Establishment of New Railway Undertaking (TCDD Transport JSC)

Opening up of the railway sector for competition

Arrangement of Public Service Obligations

Enabling the private sector to invest in rail infrastructure

Further Needs:Capacity Improvement for Regulatory Bodies

Elaboration of necessary secondary legislation by Regulatory Bodies

Page 31: TURKISH STATE RAILWAYS (TCDD)

FUTURE RAILWAY SECTOR IN TURKEY

31

Page 32: TURKISH STATE RAILWAYS (TCDD)

Thank You For Your Kind Attention

Tevfik Muhammed YEŞİLÇAM