Transcript
Page 1: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

THE OLD AND THE NEW

The Story of an Integrated Chilled Water PlantKelley Cramm, P.E.Kelley Cramm, P.E.

[email protected]

Page 2: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

The IRS Processing Facility

• Old Post Office – Offices – 500,000 sq. ft.• New 70,000 sq. ft. warehouse• New processing facility – 600,000 sq. ft.• Approximately 1.2 million total square feet of space

Page 3: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 4: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 5: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 6: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

The TeamA Cast of Thousands

•General Services Administration

•The Developer (under contract with GSA)

•The Architect (a joint venture between 2 firms) – under contract with the developer

•The Construction Manager•The Construction Manager

•The Commissioning Agent

•The Test and Balance Contractor

•The Mechanical Design/Build Contractor –4 MEP consulting firms

•The Electrical Design/Build Contractor –Another MEP consulting firm

•Lots of additional consultants

Page 7: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

DP

VSCHILLER

CHILLERCOOLING COIL

DP

PRIMARY SECONDARY SYSTEM

DECOUPLER

Size decouple pipe for very low pressure drop(It does not need a check valve)

Page 8: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Controls for Primary/Secondary

• Primary pumps are constant speed – matched to chillers• Secondary pump speed controlled to maintain remote

delta P• Chillers controlled to maintain leaving water temperature• Chillers staged on/off to maintain LWT• Chillers staged on/off to maintain LWT• Excess chilled water will bypass using the decouple pipe• Low delta T can be a problem, resulting in more water

required than what the operating chillers can flow• Consider resetting remote delta P based on coil valve

position

Page 9: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

100%LOAD

100 FT.

75%LOAD67 FT.

50%LOAD42 FT.

25%LOAD26 FT.

SUPPLYRETURN

P: 20 FT.

DIFFERENTIAL PRESSURE TRANSMITTER MUST BE LOCATED AT FAR END OF SYSTEM

PRESSURE GRADIENTS

PRESSURE VARIATIONS IN A CHILLED OR HOT WATER SYSTEM

(COILS AND CONTROL VALVES NOT SHOWN)

Page 10: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

CHILLER

DP

VS

VS

DP

DP

COOLING COIL

CHILLER

DP

VARIABLE PRIMARY SYSTEM

BYPASS VALVE

Page 11: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Controls for Variable Primary

• Pump speed controlled to maintain remote delta P• Bypass valve controlled to insure minimum chiller

evaporator flow• Use evaporator delta T to determine chiller flow – works

better than a flow meterbetter than a flow meter• Chillers controlled to maintain leaving water temperature• Chillers staged on/off on load (flow + delta T)• Consider resetting remote delta P based on coil valve

position

Page 12: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Important Design Points

• Size of bypass line and valve– Must flow difference between min. load and min. chiller flow

• Valves– slow chiller isolation valves don’t cause upset– Bypass valve must be actuated open and closed– Bypass valve must be actuated open and closed

• Chiller selection – Select evaporator near peak flow and list the minimum in the equipment

schedule

• Hard wire remote delta P to same controller as pump VFD

• Need tight controls specification

Page 13: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Advantages/Disadvantages

• Lower first cost• Fewer pumps• Smaller footprint• Lower energy cost• Helps combat low Delta T syndrome

• Operator unfamiliarity

• Helps combat low Delta T syndrome

MUST HAVE GOOD CONTROLS AND SAVVY OPERATORS

Page 14: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Existing Plant in Old Post Office

• 2 water cooled centrifugal chillers – 500 tons each – converted to R134A• 17 years old when design started (2003)• Constant flow system with 3-way valves at air handlers

Page 15: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 16: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

• Needed a total of 2500 tons• Originally planned to replace old chillers• 3 new chillers – variable primary flow• Why replace machines with life remaining?• Can we vary the flow through the old chillers?

Page 17: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

• Flow on old chillers could be reduced to 30% of • Flow on old chillers could be reduced to 30% of original design flow

• Obtained evaporator pressure drop curves• Settled on a minimum of 40% of design flow• Limited rate of change of flow when an old

chiller was running

Page 18: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

• Installed 2 new 850 ton machines• Variable frequency drive on one of the new chillers• Flow could drop as low as 25% of max evaporator flow• Made selections near peak of evaporator flow capability

Page 19: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 20: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 21: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 22: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Lessons Learned

• Communicate Communicate Communicate

• Just because someone says they did it doesn’t mean it’s done. Double Check

Page 23: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Communication is a two way streetCommunication is a two way street

Page 24: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Communication

• A Woman: without her, man is nothing.

Page 25: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

Communication Take 2

• A woman, without her man, is nothing.

Page 26: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office
Page 27: THE OLD AND THE NEW...THE OLD AND THE NEW The Story of an Integrated Chilled Water Plant Kelley Cramm, P.E. Kelley.cramm@hei-eng.com The IRS Processing Facility • Old Post Office

"I know that you believe you understand what you think I said, but I'm not sure you realize that what you heard is not what I meant."

Robert McCloskeyRobert McCloskey


Top Related