BC Lottery Corporation (BCLC) Chances Energy Audit
Energy Audit Case Study
Innes Hood, P.Eng, CEM
![Page 3: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/3.jpg)
Agenda
1 Rationale for conducting energy audits
2 Procedure for conducting energy audits
3 Case study of Chances facility
4 Lessons learned
![Page 4: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/4.jpg)
Energy Management Rationale1. Save money
2. Maintain reliability and aesthetics of facilities
3. Achieve tangible environmental benefits
• Corporate sustainability strategy
• Corporate social responsibility reporting
• Energy
• Water
• Greenhouse gas emissions
• Ozone depleting substances
![Page 5: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/5.jpg)
Corporate Energy Management
The ISO 50001 Approach
1. Management responsibility
2. Define policy
3. Energy planning
4. Implementation and operation
5. Checking
6. Management review
![Page 6: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/6.jpg)
The Audit Process
1. Billing analysis
2. Onsite review of energy using systems
3. Develop energy balance
4. Identify & analyse potential energy conservation measures (ECMs)
5. Develop business case for ECMs
6. Implement upgrades
7. Measurement and verification
![Page 7: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/7.jpg)
Chances Facility
![Page 8: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/8.jpg)
Billing Analysis
Electricity $94,000, 70%
Natural Gas $40,100, 30%
Cost
![Page 9: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/9.jpg)
Onsite Audit
![Page 10: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/10.jpg)
Develop Energy BalanceLighting
9%
Other Electrical (Slots, Ventila-
tion)54%
Heating26%
Kitchen7%
Domestic Hot Water 4%
![Page 11: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/11.jpg)
Energy Conservation MeasuresSystem
Lights Lighting relamp and fixture replacement Exterior lighting upgradeLighting controls upgrade
Mechanical VFD on Kitchen ExhaustBathroom Exhaust Occupancy Sensor
Plug Loads
Electrical Power Factor Correction
Envelope
![Page 12: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/12.jpg)
Develop Business Case
• Capital cost of upgrade
• Energy savings
• Maintenance impacts
• Life of upgrade
![Page 13: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/13.jpg)
Summary of Audit Results
• Payback of ECMs range from 2 years to 13 years• Aggregate 11 year payback• GHG and energy expenditures reduced by 7%• Annual savings of $9,300/year
![Page 14: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/14.jpg)
Lessons Learned
• Critical success factors
• Ensuring management support
• Delineation of responsibility
• Provision of budget
• Continuous improvement
![Page 16: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/16.jpg)
Implementing Energy Audit Recommendations
Michael UrbasGreat Canadian Gaming Corporation
![Page 17: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/17.jpg)
Agenda
• What to do with the energy audit
• Key finding of the audit
• Choosing projects from the audit
• Benefits vs risks
• How to sell the project
• Managing the project
• Building operations and sustainability
![Page 18: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/18.jpg)
Energy Audit – Uses
• The importance of reading the audit
• Not only for Energy Managers
![Page 19: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/19.jpg)
Energy Audit – Key Findings
• Building and system description
• Energy performance
• Recommended energy conservation measures
![Page 20: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/20.jpg)
Energy Audit – Choosing a Project
• Savings
• Cost
• Finance
![Page 21: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/21.jpg)
• Electrical
• Fuel
• Water
• Steam
• Etc……
Energy Audit – Savings
![Page 22: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/22.jpg)
Energy Audit – Cost
• Retrofit cost
• Incentives
![Page 23: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/23.jpg)
Energy Audit – Finance
• Simple pay back
• Net present value
• Internal rate of return
![Page 24: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/24.jpg)
Energy Audit – Benefits vs Risks
• Investigating
• Prioritizing
• Holding back from implementing
• The human factor
![Page 25: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/25.jpg)
Energy Audit – Selling the Project
• Understanding business priorities
• Context
• Making the connections
• Gain top management support
![Page 26: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/26.jpg)
Energy Audit – Managing the Project
• Complexity
• Resources
• Lead
• Support
![Page 27: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/27.jpg)
Building Operations and Sustainability
![Page 28: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/28.jpg)
Questions?
![Page 29: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/29.jpg)
Energy Specialist Panel
• Mr Innes Hood, Stantec.
• Mr Jeff Lee, Gateway Casinos & Entertainment.
• Dr Cristian Suvagau, BC Hydro PowerSmart.
• Mr Michael Urbas, Great Canadian Gaming Corporation.
![Page 30: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/30.jpg)
Energy Manager Challenge
Imagine you are the energy manager at a 20 year old gaming facility in BC. Your GM has challenged you to develop a strategy for reducing operating costs by 30% by 2019 through energy upgrades. Q1: What would be your top five priorities in year one?
![Page 31: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/31.jpg)
Energy Manager Challenge
Imagine you are the energy manager at a 20-year-old gaming facility in BC. Your GM has challenged you to develop a strategy for reducing operating costs by 30% by 2019 through energy upgrades. Q1: What would be your top five priorities in year one?
Q2: In year two, your GM tells you that the last RG audit recommended an increase in natural light, to give players a better sense of time. He wants you to prioritize this as part of your energy strategy. What changes would you make to your original plan?
![Page 32: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/32.jpg)
Panel Feedback and Questions
Imagine you are the energy manager at a 20-year-old gaming facility in BC. Your GM has challenged you to develop a strategy for reducing operating costs by 30% by 2019 through energy upgrades. Q1: What would be your top five priorities in year one?
Q2: In year two, your GM tells you that the last RG audit recommended an increase in natural light, to give players a better sense of time. He wants you to prioritize this as part of your energy strategy. What changes would you make to your original plan?
![Page 33: Pre-Conference Workshop: Energy Conservation in Gambling Facilities](https://reader033.vdocuments.mx/reader033/viewer/2022061119/54638d9ab1af9fbf588b4584/html5/thumbnails/33.jpg)