![Page 1: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/1.jpg)
Financial and investment Financial and investment mathematicsmathematics
RNDr. Petr Budinský, CSc.RNDr. Petr Budinský, CSc.
![Page 2: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/2.jpg)
VŠFSVŠFS 22
FINANCIAL MATHEMATICSFINANCIAL MATHEMATICSFuture value – different types of compoundingFuture value – different types of compounding
![Page 3: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/3.jpg)
VŠFSVŠFS 33
ExampleExample::Assume FV = 100.000 CZK and interest rate = 12 %. Assume FV = 100.000 CZK and interest rate = 12 %. Calculate future value in 3 years time. Calculate future value in 3 years time.
… …
… …
![Page 4: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/4.jpg)
VŠFSVŠFS 44
Present value calculated from future valuePresent value calculated from future value
![Page 5: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/5.jpg)
VŠFSVŠFS 55
ExampleExample::Assume cash flows given by following table and interest rateAssume cash flows given by following table and interest rate
r = 6 %, compoundedr = 6 %, compounded
a) a) Once yearlyOnce yearly
year 1 2 3 4
cash flows 0 100 200 300
![Page 6: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/6.jpg)
VŠFSVŠFS 66
ExampleExample::Assume cash flows given by following table and interest rateAssume cash flows given by following table and interest rate
r = 6 %, compoundedr = 6 %, compounded
b) b) ContinouslyContinously
![Page 7: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/7.jpg)
VŠFSVŠFS 77
Yield calculated in case of fixed cash flowsYield calculated in case of fixed cash flows
![Page 8: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/8.jpg)
VŠFSVŠFS 88
Equalities and inequalities among yieldsEqualities and inequalities among yields
![Page 9: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/9.jpg)
VŠFSVŠFS 99
ExampleExample::Assume an investment P = 10.000 Kč for 5 years, after 5 Assume an investment P = 10.000 Kč for 5 years, after 5 years you earn an amount FV = 21.000 CZK. Calculate the years you earn an amount FV = 21.000 CZK. Calculate the yield.yield.
![Page 10: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/10.jpg)
VŠFSVŠFS 1010
ExampleExample::Assume a loan 1.000.000 CZK for 10 years. This loan is paid Assume a loan 1.000.000 CZK for 10 years. This loan is paid by same installments C at the end of each year with the by same installments C at the end of each year with the yield yyield y(1)(1) = 8 % p.a. Calculate the installment = 8 % p.a. Calculate the installment C.C.
C C can be splitted to the interest rate payment - 80.000 can be splitted to the interest rate payment - 80.000 CZK and to the amount 69.029,49 CZK by which the CZK and to the amount 69.029,49 CZK by which the loan will be decreased to 930.970,51 CZKloan will be decreased to 930.970,51 CZK..
1.000.000 = C (1/(1+ y) + 1/(1+ y)1.000.000 = C (1/(1+ y) + 1/(1+ y)22 + ... +1/(1+ y)+ ... +1/(1+ y)1010))
1.000.000 = C[1-1/(1 + y)1.000.000 = C[1-1/(1 + y)1010]/y]/y
C = 1.000.000 ⋅ 0,08/[1 −1/1,08C = 1.000.000 ⋅ 0,08/[1 −1/1,0810 10 ] = 149.029,49 Kč] = 149.029,49 Kč
![Page 11: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/11.jpg)
VŠFSVŠFS 1111
Table of paymentsTable of payments
Installment Interest rate part Principal payment Remaining part
![Page 12: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/12.jpg)
VŠFSVŠFS 1212
BondsBonds
zero-coupon bond: annuity:
perpetuity:
![Page 13: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/13.jpg)
VŠFSVŠFS 1313
Closed formula for bond priceClosed formula for bond price
![Page 14: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/14.jpg)
VŠFSVŠFS 1414
Rules for bondsRules for bonds Rule 1Rule 1::
If the yield y is equal to the coupon rate c, then the bond price P is equal to face value FV, if yield y is higher, resp. less than the coupon rate c, then the bond price P is smaller, resp. greater than the face value FV.
Rule 2Rule 2::If the price of the bond increases, resp. decreases, this results in a decrease, resp. increase of the yield of the bond. Reverse: decrease, resp. rise in interest rates (yields) results in an increase, resp. decrease in bond prices.
![Page 15: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/15.jpg)
VŠFSVŠFS 1515
Rule 3Rule 3::If the bond comes closer to its maturity, then the bond price If the bond comes closer to its maturity, then the bond price comes closer to the face value of bond.comes closer to the face value of bond.
Rule 4Rule 4::
The closer is the bond to its maturity the higher is the The closer is the bond to its maturity the higher is the
velocity of approaching the face value by the price of thevelocity of approaching the face value by the price of the
bond.bond.
Rules for bondsRules for bonds
![Page 16: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/16.jpg)
VŠFSVŠFS 1616
Rule for bondsRule for bonds Rule 5Rule 5::
The decrease in a bond yield leads to an increase in bond price by an amount higher than is the amount corresponding to the decrease (in absolute value) in the price of the bond if the yield increases by same percentage as previously decreased.
ExampleExample::Assume Assume a 5-year bond with a face value FV = 1.000 CZK, FV = 1.000 CZK, coupon rate c = 10 % coupon rate c = 10 % and yield y = 14 %.= 14 %.
Yield 12 % 13 % 14 % 15 % 16 %
Price 927,90 894,48 862,68 832,39 803,54
Price change 65,22 31,80 0 -30,29 -59,14
![Page 17: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/17.jpg)
VŠFSVŠFS 1717
Example::
Rule for bondsRule for bonds
CZK
CZK
CZK
CZK
CZK
CZK
![Page 18: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/18.jpg)
VŠFSVŠFS 1818
Relationship Relationship of the bondof the bond price and time to price and time to maturity of the bondmaturity of the bond
![Page 19: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/19.jpg)
VŠFSVŠFS 1919
Bond pricing – general approachBond pricing – general approach
![Page 20: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/20.jpg)
VŠFSVŠFS 2020
A + B = 360A + B = 360
![Page 21: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/21.jpg)
VŠFSVŠFS 2121
ExampleExample::Assume a 5-year bond with a face value FV = 10.000 CZK issued at 6. 2. 1998 with maturity 6. 2. 2003 and with coupon rate c = 14.85%. The yield of this bond was y = 7% on 9. 11. 1999. Calculate the clean price PCL of the bond.
CZK
CZK
CZK
CZK
CZK
![Page 22: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/22.jpg)
VŠFSVŠFS 2222
The sensitivity of bond prices to changes inThe sensitivity of bond prices to changes in interest ratesinterest rates (yields)(yields)
Modified duration DModified duration Dmodmod is a positive number expressing the is a positive number expressing the increase (in %), resp. decrease (in %) of the bond price if the increase (in %), resp. decrease (in %) of the bond price if the yield decreases, resp. increases by 1%. yield decreases, resp. increases by 1%.
![Page 23: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/23.jpg)
VŠFSVŠFS 2323
Macaulay durationMacaulay duration
![Page 24: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/24.jpg)
VŠFSVŠFS 2424
Macaulay durationMacaulay duration
zero-coupon bond:
annuity:
perpetuity:
![Page 25: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/25.jpg)
VŠFSVŠFS 2525
ExampleExample::Bond parameters are as follows : FV = 1.000 CZK,: FV = 1.000 CZK,n = 5, c = 10 %, y = 14 %.n = 5, c = 10 %, y = 14 %.
CZKCZK
CZK CZK
CZK
CZK
![Page 26: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/26.jpg)
VŠFSVŠFS 2626
The dependence of duration on c and y and y
1.1.
2. 2.
![Page 27: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/27.jpg)
VŠFSVŠFS 2727
Dependence Dependence of duration D of duration D on time to maturityon time to maturity n n
nn
![Page 28: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/28.jpg)
VŠFSVŠFS 2828
EstimateEstimate of changes in bond prices of changes in bond prices
ExampleExample::
a)a)
b)b)
CZK
CZK
CZK
CZK
![Page 29: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/29.jpg)
VŠFSVŠFS 2929
Bond convexityBond convexity
Convexity is sometimes called the "curvature" of the bond.
![Page 30: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/30.jpg)
VŠFSVŠFS 3030
Calculation of convexity
CX = 2/yCX = 2/y22
Zero-coupon bond:
Perpetuity:
![Page 31: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/31.jpg)
VŠFSVŠFS 3131
INVESTMENT MATHEMATICSINVESTMENT MATHEMATICSRisks associated with the bond portfolios
When investing in bonds investor must take into account the two risks:
1. risk of capital loss (if yields increase )2. risk of loss from reinvestment (if yields decrease )
![Page 32: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/32.jpg)
VŠFSVŠFS 3232
ExampleExample::Assume 5 year zero-coupon bond with face value
FV = 1.000 CZK and yield y = 4%. This bond is an investmenta) a) for 3 yearsfor 3 years
CZK
CZK
CZK
![Page 33: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/33.jpg)
VŠFSVŠFS 3333
ExampleExampleb) b) for 7 yearsfor 7 years
Investment horizon
CZK
![Page 34: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/34.jpg)
VŠFSVŠFS 3434
Investment horizon X DurationInvestment horizon X Duration
When you invest in a particular bond and if our investment horizon is: Short - you suffer a loss in case yields increase(„capital loss"> „input of reinvestment“)
Long - you suffer a loss in case yields decrease(„loss of reinvestment "> „capital gain")
If the investment horizon is equal to (Macaulay) duration of the bond, then the "capital loss", resp. „loss of reinvestment" is fully covered by "reinvestment income" , resp. by „return on capital" , in case of both increase and decrease of yields.
![Page 35: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/35.jpg)
VŠFSVŠFS 3535
Example:Example:Assume 8-year bond, which has a face value Assume 8-year bond, which has a face value FV = 1.000 CZK with coupon rate c = 9,2 % and the yieldFV = 1.000 CZK with coupon rate c = 9,2 % and the yieldy = 9,2 %. Ty = 9,2 %. This bond is an investment for 1 year, 2 years, 1 year, 2 years, 3 years, …, 8 years - we assume 8 investment strategies. 3 years, …, 8 years - we assume 8 investment strategies.
Further assume 5 Further assume 5 scenarios of development of the yields:8,4 %, 8,8 %, 9,2 % (8,4 %, 8,8 %, 9,2 % (unchanged yield ), 9,6 % and 10 %. ), 9,6 % and 10 %.
Combination of the chosen investment strategy with a particular yield scenario will provide 40 different options. For each of these options is calculated the realized yield. . All results are summarized in the table. The price of a bond
P = 1.000 CZK.P = 1.000 CZK.
![Page 36: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/36.jpg)
VŠFSVŠFS 3636
Investment strategies
![Page 37: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/37.jpg)
„„1. line“ – 1. line“ – income from coupons
nC;nC; „„2. line“ – 2. line“ – income from reinvestment of coupons after deduction of
the coupons
„„3. line“ – 3. line“ – capital gain (the difference between the sale and repurchase price of the bond)
„„4. line“- the total return (in CZK) the sum of 1., 2. and 3. line4. line“- the total return (in CZK) the sum of 1., 2. and 3. line „„5. line“ –the total return y5. line“ –the total return ynn in % (p.a.): in % (p.a.):
soso
VŠFSVŠFS 3737
![Page 38: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/38.jpg)
Bond portfolio durationBond portfolio duration
The duration of a coupon bond is a weighted average of durations (time to maturities) of the individual cash flows represented by coupons and face value, the weights correspond to the share of individual discounted cash flow as a proportion of the total price of the bond.
The duration of a coupon bond is mean lifetime of the bond.
The duration of a portfolio consisting of bonds is the weighted average of durations of individual bonds, where the weights correspond to investments in individual bonds as proportions of the total investment in the bond portfolio.
VŠFSVŠFS 3838
![Page 39: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/39.jpg)
VŠFSVŠFS 3939
Example:Example:
Assume an investment 1.000.000 CZK for 4 years, we have zero-coupon bonds with maturities of 1 year, 2 years, ..., 7 years with uniform yields y = 8% (assuming a flat yield curve). Create portfolios A, B, C, D as follows (n is the time to maturity of each bond)
CZK
CZK
CZK
CZK
CZK
CZK
CZK
![Page 40: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/40.jpg)
VŠFSVŠFS 4040
Change Change in in the value Vthe value V00 in case of in case of
changchange of the yielde of the yield
Realized amounts V0 (CZK)
![Page 41: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/41.jpg)
VŠFSVŠFS 4141
Bond portfolio convexityBond portfolio convexity
Bond portfolio convexity is the weighted average of convexities of individual bonds, where the weights correspond to investments in individual bonds as proportions of the total investment in the bond portfolio..
![Page 42: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/42.jpg)
VŠFSVŠFS 4242
The effect of convexity on the behavior of The effect of convexity on the behavior of bond portfoliosbond portfolios
![Page 43: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/43.jpg)
VŠFSVŠFS 4343
V4+ (D) > V4
+ (C) > V4+ (B) > V4 (A)
V4- (D) > V4
- (C) > V4- (B) > V4 (A)
A … FVA = 1 000 000 x 1,084 = 1 360 489 Benchmark V4(A) = 1 000 000 x 1,084 = 1 360 489 B … V4(B) = 500 000 x 1,083 x 1,081 + 500 000 x 1, 085 / 1,08 = 1 360 489 V4
+(B) = 500 000 x 1,083 x 1,091 + 500 000 x 1, 085 / 1,09 = 1 360 547 V4
-(B) = 500 000 x 1,083 x 1,071 + 500 000 x 1, 085 / 1,07 = 1 360 548 C … V4(C) = 500 000 x 1,082 x 1,082 + 500 000 x 1, 086 / 1,08 2 = 1 360 489 V4
+(C) = 500 000 x 1,082 x 1,092 + 500 000 x 1, 086 / 1,09 2 = 1 360 720 V4
-(C) = 500 000 x 1,082 x 1,072 + 500 000 x 1, 086 / 1,07 2 = 1 360 724 D … V4(D) = 500 000 x 1,081 x 1,083 + 500 000 x 1, 087 / 1,08 3 = 1 360 489 V4
+(D)= 500 000 x 1,081 x 1,093 + 500 000 x 1, 087 / 1,09 3 = 1 361 009 V4
-(D) = 500 000 x 1,081 x 1,073 + 500 000 x 1, 087 / 1,07 3 = 1 361 019
![Page 44: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/44.jpg)
VŠFSVŠFS 4444
REALIZOVANÉ VÝNOSY SC
ÉNÁŘ
E
A B C D 5% 1 360 489 1 361 029 1 362 649 1 365 350 6% 1 360 489 1 360 727 1 361 440 1 362 629 7% 1 360 489 1 360 548 1 360 724 1 361 019 8% 1 360 489 1 360 489 1 360 489 1 360 489 9% 1 360 489 1 360 547 1 360 720 1 361 009 10% 1 360 489 1 360 718 1 361 405 1 362 532 11% 1 360 489 1 361 000 1 362 532 1 365 088
ChangeChange in in the value V the value V44 in case of in case of changchange in e in
the yieldthe yield
Realized income
![Page 45: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/45.jpg)
VŠFSVŠFS 4545
DE = 0,7 x 1 + 0,3 x 11 = 4
CXE (1,082) = 0,7 x 1 x 2 + 0,3 x 11 x 12 = 41
IH = 4
•
1 11
3 7
7/10 3/10
w1 D1 + w2 D2 = DP = IH w1 + w2 = 1 w1 + 11 w2 = 4 w1 + w2 = 1 w1 = 0,7 ; w2 = 0,3
Portfolio E: 700 000 Kč (n=1) a 300 000 Kč (n=11)
n = 1 … FV = 756 000 Kč … D1 = 1 n = 11 … FV = 699 000 Kč … D2 = 11
CZK CZK
![Page 46: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/46.jpg)
VŠFSVŠFS 4646
BENCHMARK … V4 (A) = 1 360 489
V4 (E) = 700 000 x 1,081 x 1,083 + 300 000 x 1,0811 / 1,087 = 1 360 489
V4+
(E) = 700 000 x 1,081 x 1,093 + 300 000 x 1,0811 / 1,097 = 1 361 688
V4- (E) = 700 000 x 1,081 x 1,073 + 300 000 x 1,0811 / 1,077 = 1 361 741
DA = DB = Dc = DD = DE = 4
CXA < CXB < CXc < CXD < CXE
V4+ (E) > V4
+ (D) > V4+ (C) > V4
+ (B) > V4+ (A)
V4- (E) > V4
- (D) > V4- (C) > V4
- (B) > V4- (A)
![Page 47: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/47.jpg)
VŠFSVŠFS4747
Example:Example:
Assume an investment of 2.800.000 CZK for 5 years, and we have available two zero-coupon bonds A, B:
Create a portfolio hedged against interest rate risk and calculate yield to the investment horizon, provided that day after the purchased of the portfolio yield increased, resp. decreased by 1%.
A … n = 3, y = 4% B … n = 10, y = 4%
3wA + 10 wB = 5 wA + wB = 1 7wB = 2 wA = 5/7, wB =
2/7
A … 2 000 000 Kč B … 800 000 Kč V5 = 2 000 000 x 1,043 x 1,042 + 800 000 x 1,0410 / 1,045 = 3 406 628 Kč V5
+=2 000 000 x 1,043 x 1,052+ 800 000 x 1,0410/ 1,055 = 3 408 173 Kč V5
-= 2 000 000 x 1,043 x 1,032 + 800 000 x 1,0410/ 1,035 = 3 408 234 Kč
CZK
CZK
CZK
CZK
CZK
![Page 48: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/48.jpg)
VŠFSVŠFS 4848
Derivative contractsDerivative contracts
1. forward contracts2. option contracts (options)
Forward contract is an obligation, option contract is the right, to buy or sell-agreed number of shares-at agreed price-on the agreed date
Call option is right to buy.Put option is right to sell.
![Page 49: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/49.jpg)
VŠFSVŠFS 4949
Forward contractForward contract
profitShort position
Long position
![Page 50: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/50.jpg)
VŠFSVŠFS 5050
Option contractOption contract
profit
Call option Put option
Call option will be exercised only if ST ˃ X and profit of this option is equal to max {ST – X, 0}.
Put option will be exercised only if X ˃ ST and profit of this option is equal to max {X - ST, 0}.
![Page 51: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/51.jpg)
VŠFSVŠFS 5151
Graphs Graphs of profits of profits and losses and losses when usingwhen using optionsoptions
Call option, long position Call option, short position
Put option, long position Put option, short position
![Page 52: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/52.jpg)
VŠFSVŠFS 5252
Portfolio consisting of optionsPortfolio consisting of options
A. Combination of only one option type, eg. call options - portfolio is called "spread". All call options included in the portfolio have the same underlying stock and the same time to expiration, they differ in an exercise price – it is called "vertical spread". „Horizontal spread“ arises if, on the contrary same exercise price at different time expirations.
B. Combination of both types of options - portfolio is made up of call options and put options. Portfolio is called "combination".
C. Combination of call options or put options with underlying stocks. We speak about "hedging„.
![Page 53: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/53.jpg)
VŠFSVŠFS 5353
Bullish SpreadBullish Spread
![Page 54: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/54.jpg)
VŠFSVŠFS 5454
Bearish SpreadBearish Spread
![Page 55: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/55.jpg)
VŠFSVŠFS 5555
Butterfly SpreadButterfly Spread
![Page 56: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/56.jpg)
VŠFSVŠFS 5656
Condor SpreadCondor Spread
![Page 57: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/57.jpg)
VŠFSVŠFS 5757
Bottom StraddleBottom Straddle
![Page 58: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/58.jpg)
VŠFSVŠFS 5858
Bottom StrangleBottom Strangle
![Page 59: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/59.jpg)
VŠFSVŠFS 5959
HedgingHedging
![Page 60: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/60.jpg)
VŠFSVŠFS 6060
Example:Example:
Number PriceExcercise
pricePosition
Share
Call option
Put option
![Page 61: Financial and investment mathematics RNDr. Petr Budinský, CSc](https://reader036.vdocuments.mx/reader036/viewer/2022081504/56649f175503460f94c2db60/html5/thumbnails/61.jpg)
VŠFSVŠFS 6161