FAIR – Status Report
Walter F. Henning
UNILACSIS
FRS
ESR
SIS 100/300
HESRSuperFRS
NESR
CR
RESR
The Future International Facility at GSI: FAIR - Facility for Antiproton and Ion
Research
100 m
ExistingExisting
Future ProjectFuture Project
Beams now:Z = 1 – 92(protons to uranium)up to 2 GeV/nucleonSome beam cooling
Beams now:Z = 1 – 92(protons to uranium)up to 2 GeV/nucleonSome beam cooling
Beams in the future:Intensities: 100 – 1000 fold Species: Z = -1 – 92(anti-protons to uranium; pol. p) Energies: up to 35 - 45 GeV/uPrecision: full beam cooling
Beams in the future:Intensities: 100 – 1000 fold Species: Z = -1 – 92(anti-protons to uranium; pol. p) Energies: up to 35 - 45 GeV/uPrecision: full beam cooling
_
UNILACSIS
FRS
ESR
SIS 100/300
HESRSuperFRS
NESR
CR
RESR
The Future International Facility at GSI: FAIR - Facility for Antiproton and Ion
Research
100 m
ExistingExisting
Future ProjectFuture Project
_
• Nuclear Structure Physics and Nuclear Astrophysics with Radioactive Ion-Beams
• Hadron Physics with Antiprotons
• Physics of Nuclear Matter in Relativistic Nuclear Collisions
• Plasma Physics with Highly Bunched Laser- and Ion-Beams
• Atomic Physics, Fundamental Symmetries (Antimattersystem) and Applied Sciences
• Accelerator Physics
• Nuclear Structure Physics and Nuclear Astrophysics with Radioactive Ion-Beams
• Hadron Physics with Antiprotons
• Physics of Nuclear Matter in Relativistic Nuclear Collisions
• Plasma Physics with Highly Bunched Laser- and Ion-Beams
• Atomic Physics, Fundamental Symmetries (Antimattersystem) and Applied Sciences
• Accelerator Physics
The International Steering Committee for FAIR
PAC QCD E.Chiavassa
PAC NUSTAR R.Casten
PAC APPA D.Schwalm
TAC Yanglai Cho
Observers:
FAIR Project
Cost Review Group(CORE)
Full Cost Structure Group
AFI Working GroupAdministrative and Funding
IssuesH.F.Wagner
Legal Working GroupU.B. Jahn
STI Working GroupScientific + Technical Issues
S. Gales
ISCInternat. Steering Committee
H.Schunck
The International Steering Committee for FAIR
PAC QCD E.Chiavassa
PAC NUSTAR R.Casten
PAC APPA D.Schwalm
TAC Yanglai Cho
Observers:
FAIR Project
Cost Review Group(CORE)
Full Cost Structure Group
AFI Working GroupAdministrative and Funding
IssuesH.F.Wagner
Legal Working GroupU.B. Jahn
STI Working GroupScientific + Technical Issues
S. Gales
ISCInternat. Steering Committee
H.Schunck
J. Eschke
I. Augustin T. Beier
H. Gutbrod
2004 2005 2006
PAC's Technical Committee
Signing of MoU
Phase I – Governed by MoUPhase II
Governedby
Contracts
The ISC-FAIR International Working Groups
MoU
Proposals / TR's
LoI's
2004 2005 2006
Contract(s) Development
Contract(s) Negotiations
Closing
PAC's Technical Committee
Signing of MoU
Phase I – Governed by MoUPhase II
Governedby
Contracts
The ISC-FAIR International Working Groups
MoU
Proposals / TR's
LoI's
2004 2005 2006
Contract(s) Development
Contract(s) Negotiations
Closing
PAC's Technical Committee
Signing of MoU
Phase I – Governed by MoUPhase II
Governedby
Contracts
The ISC-FAIR International Working Groups
MoU
Proposals / TR's
LoI's
(2200 authors)
2004 2005 2006
Contract(s) Development
Contract(s) Negotiations
Closing
PAC's Technical Committee
Signing of MoU
Phase I – Governed by MoUPhase II
Governedby
Contracts
The ISC-FAIR International Working Groups
Evaluation by Advisory CommitteesMid March 05
Cost Review by CORE groupby June 05
Draft Project Definition by July 05
MoU
Proposals / TR's
LoI's
TDR's
SIS100/300 Underground Tunnel
5 m
-24 m
Tunnel in Open-Pit Construction
Tunnel Drilling Machine
Legal and Regulatory Procedures for Construction Planning of FAIR (1)
Procedure / Decision Agency Start Complete
0. Base Decision German Ministry (BMBF)
Febr. 03
I. Construction Planning Process and Environmental Impact Screening
I.1 Initiation Decision City of Darmstadt I.2 Scoping I 16 agencies from
city, county and publ. associations
March 03
I.3 Scoping II dto. May 04 I.4 Pre-Process / Preparation Disclosure
(§§ 3 (1)/4(1) BauGB) City of Darmstadt agencies
Dec. 04 Jan. 05
I.5 Pre-Process Evaluation dto. Feb. 05 June 05 I.6 Disclosure Decision,
1. Discl., TÖB §§ 3 (2)/4(1) BauGB) dto.
July 05
Aug. 05
I.7 Disclosure Assessment / Preparation of Statutory Decision
dto.
Sep 05 Dec. 05
I.8 Statutory Decision dto. Feb. 06
Legal and Regulatory Procedures for
Construction Planning of FAIR
√
√√
Legal and Regulatory Procedures for Construction Planning of FAIR (2)
Procedure / Decision Agency Start Complete
II.1 Civil Construction Plan (B-Plan) II.1.1 Conceptual Construction Plan Develop.
Layout/Dimensions Site exploration Geotechnical. Consulting Feasibility Study
GSI / Companies Inst. f. Geotechn. TU Darmstadt BUNG AG
Jan. 04
June 04
II.1.2 City-Planning and Zoning REGIOPLAN May 04 June 04 II.1.3 Construction Plan Draft /Justification REGIOPLAN June 04 Nov. 04 II.1.4 B-Plan Draft & Justification REGIOPLAN
City of Darmstadt Feb. 05 June 05
II.1.5 Final B-Plan Presentation / Justification REGIOPLAN City of Darmstadt
Jan. 06 Feb. 06
II.2 Landscaping Concept and Compensation to B-Plan
II.2.1 Status Assessment and Rating March 03 July 04 II.2.2 Compensation Concept
Greenlands and Reforestation March 04 Sept. 04
II.2.3 Pre-Draft of Landscape and Compensation Plan
June 04 Oct. 04
II.2.4 Draft of Landscape and Compensation Plan
Feb. 05 June 05
II.2.5 Final Landscape and Compensation Plan Document
Jan 06 Feb. 06
√
√
√
√
√
√
Legal and Regulatory Procedures for Construction Planning of FAIR (3)
Procedure / Decision Agency Start Complete
II.3 Environmental Impact Study (UVS) and Report
REGIOPLAN March 03 Nov. 04
II.3.1 Assessment and Coordination (Scoping I / Scoping II)
REGIOPLAN & City of Darmstadt
March 03 March 04
II.3.2 Related Expert Studies II.3.2.1 Groundwater / Water Budget
- hydrogeological assessment - deep well drilling
TU Darmstadt & Commercial companies
Sept. 03
Oct. 04
II.3.2.2 Exploration Fauna bioplan Sept. 03 Aug. 04 II.3.2.3 Exploration Flora REGIOPLAN
City of Darmstadt Sept.03 Sept. 04
II.3.2.4 Accoustic Emission Study Eng. Office Fritz Sept. 03 July 04 II.3.2.5 Forest Ecological System ECOPLAN Jan. 04 Sep. 04 II.3.3 Pre-Draft UVS and Report REGIOPLAN July 04 II.3.4 Draft UVS and Report Disclosure REGIOPLAN Nov. 04
√
√
√
√
√√
√
√
√
Radiation Safety Approval
In February 2002, one year before the “green light” was obtained from the German government, GSI applied for the Construction of an
International Facility for the Research with Ion and Proton Beams at the Hessian Ministry for Environment
In December 2003, GSI received official letter with the first approval:
....the planned facility will fulfill the requirements in accordance withthe German radiation protection laws for the construction
of the whole installation and the operation as outlinedin the Conceptual Design Report.
This permit was confirmed in Fall 2004 also for open pit construction
3-Phase Project Staging
Stage 1
Stage 2
Stage 3
General Strategy:General Strategy:
• Groundwork, supply systems and major buildings as early as financially possible
(potential for smoothing of financial profile?)• Scientific facilities staged according to three
science programmes• Contributions from outside mainly in-kind for
scientific facilities (?)
Three stages Three stages according to fields of science:according to fields of science:
– Radioactive beam physics• Nuclear structure and nuclear astrophysics• Atomic physics studies with highly charged/radioactive ions
– Proton-antiproton physics• QCD studies with protons and antiprotons• Precision studies with antiproton beams addressing fundamental
symmetries and interactions
– Full facility research• Full parallel operation of up to four experiments • Full energy and luminosity for nuclear collisions program at CBM• Precision QCD Studies at PANDA up to 15 GeV/c • Plasma research (full gain factor in power density: ~400)• Atomic reaction studies with fast beams
Accumulated Costs for FAIR
0,0
20,0
40,0
60,0
80,0
100,0
120,0
140,0
160,0
180,0
200,0
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
Year
Mio
. EU
RO
Preparation and Planning Phase Construction Phase Personnel Sum Total incl. escalation
FAIR construction cost
total cost: 989 Mio€
Organisational & Management Structure
Research Division
HADES
FAIR GmbH with international shareholders
Accelerator Operation Infrastructure Division
BuildingsFacility Maintenance
Central Services
ALICE
FOPI
PHELIX+PP
Spectroscopy
SHE / Chemistry
Material Research
Atomic Physics
Bio Physics
Injectors
Rings
Beam Diagnostics
Vacuum
HF
Operating
HD-Therapy
IT
Technical Services
Detector-Lab.
Target-Lab.
Documentation / Library
Human Resources
Administration
Finance
Purchasing
FAIR Division(FAIR Technical Director)
Civil Construction
CBM -TIPANDA-TI
Integration
Theory
FRS/ESR
HE Reactions
International Steering Commitee
Administration andFinancial Issues WG
Scientific and TechnicalIssues WG
Company General Assembly
Supervisory Board
Directorate DG
Sci. Tech. Admin. FAIR
International FAIR Project Management Board
Administrative Council
Scientific Council
Scietific / Technical Advisory Committees
Controlling,Legal IssuesSafety
EU Contracts,3rd Party Funding
Users, Public Relations
Experiment Electronics Electrical Engineering
Super-FRS-TIRIB Low Energy Branch TI
RIB High Energy Cave TIRIB Ring Branch TI
FLAIR & SPARC &Applications Facilities TI
Plasma Physics TI
Theory /systems
ControlsSC MagnetsCryosystems
TI= Technical Infrastructure
CBM
PANDA
NUSTAR Exp. groups
FLAIR & SPARC
Accelerator
FAIR Experiments -TI
FAIR Project Management Team
SIS100
3.
SIS2006T4.
CR System
6.
HESR
7.
PANDA
9.
NESR
8.
SIS18Upgrade
1.
Super-FRS
11.
CBM
10.
Plasma Phys. Exp.
12.
AtomicPhys. Exp.
13.
Buildings +Infrastructure
14.
Acc. SystemPhysics
5.
Integration
15.
P-Linac
2.
Advisory Committees PACs, TAC, EMAC,...
Accelerator Technical Board
Research Technical Board Civil ConstructionIntegration
Board
International FAIR Project Management Board
Project Director, Deputy Director Research Coordinator, Accelerator
Coordinator,Civil Construction Coordinator,
Technical Integration Coordinator, Administrative Coordinator
Organizational Structure of the FAIR Project
FAIR ProjectManagement Team
Contracts & Legal, Budget & Finances, Scientific Coordination, Accelerator Technical Coordination, Civil Construction & Regulatory Procedures, International Project Integration
Convention(Governmental Contract –
provisions for general framework, procedures, arrangements; annexes?)
Articles of Association(based on rules of German limited liability company (GmbH) law;
recorded and registered with notary public;
any changes require full notary public process)
By-Laws(contract(s) on specific rules and regulations between shareholders;
does not require notary public involvement)
plus additional bi-lateral, multi-lateral contracts, MoU's etc betweenshareholders and other parties
R & D
Accelerator Physics and Technology for FAIR
Main R&D challengesSuperconducting, fast ramping synchrotron magnets
High gradient, low frequency RF cavities
Fast stochastic and electron cooling
Novel lattice/collimation design: Beam optics studies
Control of collective effects:Large scale simulation studies
Ultra high vacuumfor intense beams
HESR e-cooler
SIS 100 dipole magnet
CR compressor cavity
control of stripping losses
Desorption test-stand Working pointdiagram:Stabilityof intensebeams
Thank you for your attention!!