Building Design and Construction
Options
And Their Effect on the ITS Infrastructure Lifecycle
![Page 2: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/2.jpg)
BackgroundLarge Construction Projects Are Complex Working Environments With Many Moving Pieces.ITS and Its Supporting Infrastructure Have Become a Critical Building System Supporting Many Systems.It Takes a Proactive Project Team to Ensure Technology Infrastructure Is Not Overlooked and User’s Expectations Are Met.
![Page 3: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/3.jpg)
Background
Things To AvoidITS Stakeholders Brought Into Large Complex Projects:• Later Than Most Others• Without Clear Project Goals• Once Schedules and Budgets Are Defined
![Page 4: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/4.jpg)
Objectives
![Page 5: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/5.jpg)
OBJECTIVES
• Gain better insight into the design and construction project delivery mechanics which affect most aspects of technology procurement from preliminary planning and budgeting to commissioning and turn‐over.
• Join any technology or construction project at any stage and know where the contractual challenges and opportunities are, regardless of your individual role.
![Page 6: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/6.jpg)
Building Design And Construction
![Page 7: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/7.jpg)
Building Design and Construction• Why Build?
– Driven By Growth or Expansion• New services or business Units• Additional Staff or Equipment• Downsizing or Consolidation of Services
– Redevelopment or Re‐Zoning Plans– Compliance (i.e. Seismic Retrofit)– Replacement Facility
• Changes in business model (Hospital vs. MOB)
![Page 8: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/8.jpg)
Building Design and Construction• Why Build? The Cons
– Costly undertaking• Ever Increasing Materials and Labor Costs• Projecting Total Project Costs is a Science
– Lengthy process• Needs Assessment• Team Selection• Site Selection• Design and Approvals• Construction (sometimes phased)• Transition Planning
![Page 9: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/9.jpg)
Building Design and Construction• Why Build? ‐ The Cons
– Complicated project • Will require additional resources from internal staff
– “C‐Level” – Facilities – Accounting/Purchasing– IT
• May require external resources and experts– AEC– Specialty Consultants
» Cost consultant» Transition Planners» Commissioning Agents
![Page 10: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/10.jpg)
Building Design and Construction• Who Are The Players?
– Owner, Developer and Operator– Owner’s Representative, CM or Program Manager– A/E Team
• Architect• Engineer• Consultants
– Contractor• Subcontractors
– Vendors and Service Providers
![Page 11: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/11.jpg)
Building Design and Construction• Owner, Developer and Operator
• Sometimes these are separate entities• Each with their own interests and agenda
• Owner’s Representative, CM or Program Manager
• Control Schedule and Budget• Manage design and construction team• Interface with owner’s stakeholders• Interface with Vendors or Service Providers
![Page 12: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/12.jpg)
Building Design and Construction• A/E Team
– Architect(s)• Executive Architect – Stamps drawings • Design Architect – Aesthetics of building• Specialty Architect – Designs specialty areas
– Engineers• Civil• S‐MEP• ITS Consultant(s)• Specialty Consultants
![Page 13: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/13.jpg)
Building Design and Construction• Contractor
– GC• Prime• Joint Venture• CM at Risk
– Sub‐Contractors
• Specialty Vendors and Service Providers– FF&E– Telecom Services
![Page 14: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/14.jpg)
Building Design and Construction• What About the Technology Team?
– Owner’s IT and Telecom Group• May be separate entities • May have separate budgets • May have separate pathways and spaces
– IT Consultants• ITS Infrastructure• Networking and active electronics• Software
![Page 15: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/15.jpg)
Project Types
![Page 16: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/16.jpg)
Project Types• Project Types vs. Contract Types
– Delivery methods do not exclude contract type– Owner’s experience may influence project type– Budgets and Schedule may actually dictate project type and team make‐up
![Page 17: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/17.jpg)
Project Types• Design‐Bid‐Build
– Most traditional method for private contracts– Full design documents (contractual drawings)
• Not shown = Not built
– Requires more time – Greater checks and balances for design and construction processes
![Page 18: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/18.jpg)
Project Types• Design‐Assist
– Partial Complete design– Contractor completes design and details work– Shared design responsibility
• Planning and Schematic by A/E• Construction Documents by Contractor
– Perfect application of BIM coordination– Pre‐Fabrication head start– Perfect during lengthy review processes (OSHPD)
![Page 19: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/19.jpg)
Project Types• Design‐Build
– GC is the Prime Contract holder for all design and construction
– Speedier project possible due to compressed design and coordination
– Construction can begin while design is completed– Tighter coordination of design and construction – FF&E is sometimes contracted to GC
![Page 20: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/20.jpg)
Newer Delivery Methods
![Page 21: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/21.jpg)
Newer Delivery Methods• IPD – Integrated Project Delivery
– One “Big Happy Family”– A/E, GC and subcontractors Share:
• Design Responsibility• Construction Risks and Rewards• Single Construction Trailer • Faster, More Effective Coordination of Field Issues
– IPD is a re‐tooling of the construction process
![Page 22: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/22.jpg)
Newer Delivery Methods• Lean Construction
– Implements the spirit of Lean Manufacturing into the building design and construction process.
– It is not solely a construction methodology. – It is an end‐to‐end, holistic approach to design, construction, activation, maintenance, salvaging and recycling of buildings
– Lean Construction involves owners, architects, designers, engineers, constructors and suppliers.
![Page 23: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/23.jpg)
Newer Delivery Methods• Lean Construction
– The project method which can affect and address ITS infrastructure lifecycles the most
– Project Planning and Design• Will ITS be part of the plan?
– Integrates Construction Trades as a Matter of Course, not Chance
• ITS is most always left out of major construction discussions
![Page 24: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/24.jpg)
Newer Delivery Methods• Lean Construction
– The project method which can affect and address ITS infrastructure lifecycle the most
– Operation and Maintenance:• ITS : No longer just a tab in the O&M Manual• Can you say Intelligent Patching Systems?
– Deactivation and Recycling• Hugh?
![Page 25: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/25.jpg)
Contract Types
![Page 26: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/26.jpg)
Contract Types• Regardless of Delivery Method, there are also contractual differences which affect how ITS is procured on a project:– Low Bid– Negotiated Bid– Lump Sum– Cost Plus
![Page 27: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/27.jpg)
Contract Types• Low Bid
– Least forgiving method for both owners and contractors, as cost drives most selections
– Greatest potential for change order and scope creep if design documents are not in line with scope
– Low bid doesn’t always translate to lowest project cost
![Page 28: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/28.jpg)
Contract Types• Negotiated Bid
– “Best Value”– Scoring System
• Experience• Ability to perform work• Familiarity with facility or project type
– Eliminates large bidder pool• Short List selection• By Invitation Only
![Page 29: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/29.jpg)
Contract Types• Lump Sum
– Fixed Dollar Value– Not Necessarily Lowest Cost– Typically Scope Changes are Treated Outside of Lump Sum
• GMP– Not To Exceed Amount – May also be Open Book
![Page 30: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/30.jpg)
Contract Types• Cost Plus
– Open Book is Likely– Agreed upon fixed costs:
• Labor rates• Material Mark‐Up• OH and Profit
– Most Forgiving for Projects With Expected Changes
![Page 31: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/31.jpg)
How Does This Affect ITSInfrastructure and Systems?
![Page 32: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/32.jpg)
How Does This Affect ITS ?• ITS components affected by previous factors:
– Budgeting– Schedule– Design Requirements– Procurement Method– Installer(s) selected– QA/QC– O&M– Removal, Replacement and Recycling
![Page 33: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/33.jpg)
How Does This Affect ITS ?• ITS components affected by previous factors:
– Budgeting– Schedule– Design Requirements– Procurement Method– Installer(s) selected– QA/QC– O&M– Removal, Replacement and Recycling
![Page 34: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/34.jpg)
How Does This Affect ITS ?• Budget
– Proper planning can assure ITS requirements are incorporated into project budget
• Pathways and Spaces– J‐Hooks or Tray?
• Preferred Manufacturers• Firestopping Methods• Administration requirements• Record Documentation• Ongoing Maintenance and Support
![Page 35: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/35.jpg)
How Does This Affect ITS• Schedule
– Project Delivery Method Will Dictate the ITS Infrastructure Schedule from A‐Z
– Knowing How Project Schedule is Loaded Helps Allocate Resources To Best Meet Your Needs/Abilities
– ITS Participation at “Full Wall Schedule” Meetings
![Page 36: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/36.jpg)
How Does This Affect ITS• Design Requirements
– Have a Design Standards Document – Current – Addresses the Needs of Specific Project at Hand
• Basis of Design for a Housing Project May Not Be Applicable on a Lab Building Project
– Bake in Some Flexibility– Expect It To Be Challenged
![Page 37: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/37.jpg)
How Does This Affect ITS• Procurement Method
– ITS Procurement Plan in Large Projects Should Anticipate:
• Phased Installation of ITS Components• Division of Work by Trades or Vendors
– Pathways and Spaces– Cabling – Active Equipment– Commissioning and Activation
![Page 38: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/38.jpg)
How Does This Affect ITS ?• Installer(s) selected
– How Important Is This?– Some Project Types Don’t Allow for Preferred Installers
• Consider selection outside of GC• Added Risk• Requires More Involvement
– Will Installer Be Maintaining The System?
![Page 39: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/39.jpg)
How Does This Affect ITS ?• QA/QC
– Incorporate Into Contract Documents– Integrated into All ITS Components and Phases– Assign a QA/QC Champion– Perform QA/QC Audits Which Address ITS Concerns
• Not Always Addressed by Architect or GC
– Reduces Punch List Items at End of Project
![Page 40: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/40.jpg)
How Does This Affect ITS ?• O&M
– Large Installations Will Require Extended Training– Ensure O&M Manuals Include ALL Warranty Info
• Extended Warranty Certificates• Contact Information• Contractor’s Warranty vs. Manufacturer
– Consider Maintenance Plan for Special Systems• DAS• A/V• Security
![Page 41: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/41.jpg)
How Does This Affect ITS ?• Removal, Replacement and Recycling
– Is This Part of the New Construction Project?– Define Who is Responsible for Removal of Materials
– Are LEED Credits Pursued – Who Gets Scrap Material $ ?
![Page 42: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/42.jpg)
How Does This Affect ITS ?• Other Components Affecting ITS:
– Owner Furnished Equipment and Systems– Vendor Furnished Equipment and Systems– What About?:
• Interfaces• Integration• Middleware
![Page 43: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/43.jpg)
How Does This Affect ITS ?• Owner Furnished Equipment and Systems
– End User Devices– Networking Equipment– Servers– Software
![Page 44: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/44.jpg)
How Does This Affect ITS ?• Vendor Furnished Equipment and Systems
– Systems Furniture– Specialty Equipment – Hardware Interfaces– Middleware
![Page 45: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/45.jpg)
How Does This Affect ITS ?• Interfaces
– Create an Interface Plan to Address:
• Are Interface Expectations Achievable?• Where Are The Lines of Scope Delineation?• Who is Responsible If There Are Issues?• Is There a Contingency Plan?
![Page 46: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/46.jpg)
How Does This Affect ITS ?• Integration
– Define Integration– Assign a Stakeholder– Clearly Define Roles and Responsibilities– Avoid Finger‐Pointing – Assure Integration Doesn’t Void Warranties
![Page 47: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/47.jpg)
KEY TAKE‐AWAYS
![Page 48: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/48.jpg)
Key Take‐Aways
Project Design and Construction Options Have a Major Impact On ITS
Infrastructure:From Inception to Demolition
![Page 49: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/49.jpg)
Key Take‐Aways
Project Delivery MethodsAre Not The Same AsContract Vehicles
![Page 50: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/50.jpg)
Key Take‐Aways
Understanding the Project HierarchyWill Help You Reach Your Desired
Outcome
![Page 51: Building Design and Construction Options - BICSI Design and...Building Design and Construction Options And Their Effect on the ITS Infrastructure Lifecycle](https://reader034.vdocuments.mx/reader034/viewer/2022051722/5aa4af237f8b9a2f048c748f/html5/thumbnails/51.jpg)
Conclusion
Navigating Contractual Waters Is All About Knowing How To Read the
Compass.
• Budget and Scope• Schedule and Hazards• Desired Products, or Installers A• All Of The Above