System Process DocumentAssociating Overheads with Resources
Department
Responsibility/Role
File Name 27759806.docRevision
Document Generation Date 18/01/2010 09:35:00
Date Modified 1/18/2010 09:35:00 AM
Last Changed by
Status
Associating Overheads with Resources
Trigger:
Concept
The Resource Overhead Associations page enables you to associate overheads with resources.
You can assign resource cost as dollars per hour. If you enter a new resource, you can directly
enter a frozen unit cost. However, you cannot directly update the frozen unit cost for a previously
entered resource.
In this topic, you will associate overheads with resources.
Required Field(s) Comments
Output - Result(s) Comments
Additional Information
Last changed on: 1/18/2010 09:35:00 AM Page 1
-
8/14/2019 Associating Overheads With Resources_SPD
2/17
System Process DocumentAssociating Overheads with Resources
Procedure
Step Action
1. Begin by navigating to the Resources page.
Click the vertical scrollbar.
Page 2 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Associating Overheads With Resources_SPD
3/17
System Process DocumentAssociating Overheads with Resources
Step Action
2. Click the Manufacturing and Distribution Manager link.
Last changed on: 1/18/2010 09:35:00 AM Page 3
-
8/14/2019 Associating Overheads With Resources_SPD
4/17
System Process DocumentAssociating Overheads with Resources
Step Action
3. Click the vertical scrollbar.
Step Action
4. Click the Resources link.
Page 4 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Associating Overheads With Resources_SPD
5/17
System Process DocumentAssociating Overheads with Resources
Step Action
5. Use the Organizations page to select your organization.
Last changed on: 1/18/2010 09:35:00 AM Page 5
-
8/14/2019 Associating Overheads With Resources_SPD
6/17
System Process DocumentAssociating Overheads with Resources
Step Action
6. Click the M1 Seattle Manufacturing list item.
Step Action
7. Click the OKbutton.
orPress [Alt+O].
Page 6 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Associating Overheads With Resources_SPD
7/17
System Process DocumentAssociating Overheads with Resources
Step Action
8. Use the Resources page to enter a resource name unique to the organization to
describe the resource.
Last changed on: 1/18/2010 09:35:00 AM Page 7
-
8/14/2019 Associating Overheads With Resources_SPD
8/17
System Process DocumentAssociating Overheads with Resources
Step Action
9. Click in the Resource field.
Step Action
10. Press [F11].
Page 8 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Associating Overheads With Resources_SPD
9/17
System Process DocumentAssociating Overheads with Resources
Step Action
11. Enter the desired information into the Resource field. Enter "HG_TST_MCH".
Last changed on: 1/18/2010 09:35:00 AM Page 9
-
8/14/2019 Associating Overheads With Resources_SPD
10/17
System Process DocumentAssociating Overheads with Resources
Step Action
12. Press [Ctrl+F11].
Step Action
13. Click the Overheads button.
orPress [Alt+a].
Page 10 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Associating Overheads With Resources_SPD
11/17
System Process DocumentAssociating Overheads with Resources
Step Action
14. Use the Resources Cost page to associate overheads with resources.
Last changed on: 1/18/2010 09:35:00 AM Page 11
-
8/14/2019 Associating Overheads With Resources_SPD
12/17
System Process DocumentAssociating Overheads with Resources
Step Action
15. Click in the Cost Type field.
Step Action
16. Enter the desired information into the Cost Type field. Enter "Engineer".
Page 12 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Associating Overheads With Resources_SPD
13/17
System Process DocumentAssociating Overheads with Resources
Step Action
17. Click in the Description field.
Last changed on: 1/18/2010 09:35:00 AM Page 13
-
8/14/2019 Associating Overheads With Resources_SPD
14/17
System Process DocumentAssociating Overheads with Resources
Step Action
18. The Allow Updates check box indicates whether the cost type is defined as
updatable.
Step Action
19. Click in the Overhead field.
Page 14 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Associating Overheads With Resources_SPD
15/17
System Process DocumentAssociating Overheads with Resources
Step Action
20. Enter the desired information into the Overhead field. Enter "MfgEng".
Last changed on: 1/18/2010 09:35:00 AM Page 15
-
8/14/2019 Associating Overheads With Resources_SPD
16/17
System Process DocumentAssociating Overheads with Resources
Step Action
21. Click in the Description field.
Step Action
22. Click the Save button.
Page 16 Last changed on: 1/18/2010 09:35:00 AM
-
8/14/2019 Associating Overheads With Resources_SPD
17/17
System Process DocumentAssociating Overheads with Resources
Step Action
23. You have completed the Associating Overheads with Resources procedure.
End of Procedure.