![Page 1: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/1.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
An Experiment in Takt Time
![Page 2: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/2.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Introduction to Project • 7,500 SF Gut and Remodel• Downtown San Mateo, CA• OSHPD Project• Occupied Building/ Operational Hospital • IFOA-IPD Contract with Trade Partners• Last Planner• Pull Scheduling • BIM Modeling
![Page 3: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/3.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Why Takt Time?
• P2SL looking for small project• James Pease of Sutter Health
recommended P2SL for Pankow
![Page 4: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/4.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
What is Takt time?
• German word for beat• Match production rate to
demand rate
Operation 1 Operation 2 Operation 3 Operation 4
Cycle timeTakt time
Dura
tion
![Page 5: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/5.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Takt Time
![Page 6: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/6.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Takt-time planning process
• Adapted from Ballard and Tommelein (1998) white paper on continuous flow
Data Collection
Zone / Work definition
Rough balancing
Team agreements
Fine balancing
![Page 7: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/7.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Flow Summary
1
3
2
4
Fire sprinkler Duct Piping
DrywallElectrical
Are these work flows compatible?
![Page 8: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/8.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
0123456789
10
Operation1
Operation2
Operation3
Operation4
Average Activity Durations
0123456789
10
Operation1
Operation2
Operation3
Operation4
Updated Durations
Takt-time planning process
• Adapted from Ballard and Tommelein (1998) white paper on continuous flow
Data Collection
Zone / Work definition
Rough balancing
Team agreements
Fine balancing
Sequence Details:- Rough in electrical before top of wall drywall
- “I can install prefab walls in 4 days, but only if entire space is clear.”
![Page 9: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/9.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Line of Balance Scheduling• What is Line of Balance?• What does it have to do with Takt Time?
![Page 10: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/10.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Line of balance scheduling
• Optimize the schedule• Used it for pull planning• Did not use the full BIM, still improved
the schedule significantly• Line of balance scheduling IS NOT
takt-time planning Zone 1
Zone 2
Zone 3
Zone 4
Time
![Page 11: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/11.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Dreams to Field• How did we implement Takt Time and Line of Balance in the field?
![Page 12: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/12.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Overhead Phase LOB
• Begins with Layout on the floor, ends with duct insulation, plumbing chlorinated and all overhead conduit installed.
• 44 days total
![Page 13: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/13.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
![Page 14: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/14.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Individual Trade Workflows
Duct Sequence: 2,1,3,6,5,4
Piping Sequence: 2,1,3,6,5,4
Electrical Sequence: 5,4,1,2,3,6
![Page 15: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/15.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Overhead LOB
![Page 16: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/16.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Controlling the schedule
• Last Planner system• Visual plan system in the field• Goal: Communicate where
people are actually working, how fast they are, and if they need to speed up or slow down
![Page 17: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/17.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Communicating and controlling the space schedule
10/4/2014 17
Daily progress reports and space schedule displayed via whiteboard
![Page 18: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/18.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Interactive Daily Reports and Color Up
![Page 19: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/19.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Continuous Improvement of the Plan
• Initially structured with 4-day takt time, but this needed to be adapted.
![Page 20: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/20.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Continuous Improvement of the Plan
• Printed out 11x17 of the LOB schedule and worked with the trades to reschedule w/ a pencil and ruler
• Took out 8 days in the schedule due to changing the sequence and crews
![Page 21: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/21.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Current Inwall Phase LOB
•Now: 29 day sequence. (initially 37 with 4-day takt).
![Page 22: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/22.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Overhead Phase SummaryTakt Time Planning Results
• 44 to 32 days • Slowed down some trades,
redirected some trades, sped up others, identified Last Responsible moment to speed up or slow down
• “9/10 when we accelerate, this costs us money. We’ve gone so much faster on this job and it hasn’t cost us a dime”- PM Jeff Stewart of Southland
![Page 23: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/23.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Trade Partners Panel• Thoughts when first introduced to Takt Time and Line of Balance• Benefits and Draw Backs?• Opinion of Daily Color Ups and Reports• Effect on working conditions • Ownership of space/ cooperation • Crew Sizes/ Hours Spent compared to original estimate• Material Management
![Page 24: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/24.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
![Page 25: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/25.jpg)
16th LCI Congress | San Francisco, CA | October 7-10, 2014
Final Thoughts and Lessons Learned• Data of Findings (PPC)• Success of Project• Calculated Risk• Final Perspective of Takt Time• Incorporating Owner Change Order and saving time
![Page 26: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible](https://reader034.vdocuments.mx/reader034/viewer/2022042103/5e806346f4b67157b42966e8/html5/thumbnails/26.jpg)