16 th LCI Congress | San Francisco, CA | October 7-10, 2014 An Experiment in Takt Time

Upload: others

Post on 22-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

An Experiment in Takt Time

Page 2: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Introduction to Project • 7,500 SF Gut and Remodel• Downtown San Mateo, CA• OSHPD Project• Occupied Building/ Operational Hospital • IFOA-IPD Contract with Trade Partners• Last Planner• Pull Scheduling • BIM Modeling

Page 3: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Why Takt Time?

• P2SL looking for small project• James Pease of Sutter Health

recommended P2SL for Pankow

Page 4: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

What is Takt time?

• German word for beat• Match production rate to

demand rate

Operation 1 Operation 2 Operation 3 Operation 4

Cycle timeTakt time

Dura

tion

Page 5: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Takt Time

Page 6: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Takt-time planning process

• Adapted from Ballard and Tommelein (1998) white paper on continuous flow

Data Collection

Zone / Work definition

Rough balancing

Team agreements

Fine balancing

Page 7: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Flow Summary

1

3

2

4

Fire sprinkler Duct Piping

DrywallElectrical

Are these work flows compatible?

Page 8: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

0123456789

10

Operation1

Operation2

Operation3

Operation4

Average Activity Durations

0123456789

10

Operation1

Operation2

Operation3

Operation4

Updated Durations

Takt-time planning process

• Adapted from Ballard and Tommelein (1998) white paper on continuous flow

Data Collection

Zone / Work definition

Rough balancing

Team agreements

Fine balancing

Sequence Details:- Rough in electrical before top of wall drywall

- “I can install prefab walls in 4 days, but only if entire space is clear.”

Page 9: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Line of Balance Scheduling• What is Line of Balance?• What does it have to do with Takt Time?

Page 10: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Line of balance scheduling

• Optimize the schedule• Used it for pull planning• Did not use the full BIM, still improved

the schedule significantly• Line of balance scheduling IS NOT

takt-time planning Zone 1

Zone 2

Zone 3

Zone 4

Time

Page 12: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Overhead Phase LOB

• Begins with Layout on the floor, ends with duct insulation, plumbing chlorinated and all overhead conduit installed.

• 44 days total

Page 13: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Page 14: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Individual Trade Workflows

Duct Sequence: 2,1,3,6,5,4

Piping Sequence: 2,1,3,6,5,4

Electrical Sequence: 5,4,1,2,3,6

Page 15: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Overhead LOB

Page 16: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Controlling the schedule

• Last Planner system• Visual plan system in the field• Goal: Communicate where

people are actually working, how fast they are, and if they need to speed up or slow down

Page 17: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Communicating and controlling the space schedule

10/4/2014 17

Daily progress reports and space schedule displayed via whiteboard

Page 18: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Interactive Daily Reports and Color Up

Page 19: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Continuous Improvement of the Plan

• Initially structured with 4-day takt time, but this needed to be adapted.

Page 20: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Continuous Improvement of the Plan

• Printed out 11x17 of the LOB schedule and worked with the trades to reschedule w/ a pencil and ruler

• Took out 8 days in the schedule due to changing the sequence and crews

Page 21: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Current Inwall Phase LOB

•Now: 29 day sequence. (initially 37 with 4-day takt).

Page 22: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Overhead Phase SummaryTakt Time Planning Results

• 44 to 32 days • Slowed down some trades,

redirected some trades, sped up others, identified Last Responsible moment to speed up or slow down

• “9/10 when we accelerate, this costs us money. We’ve gone so much faster on this job and it hasn’t cost us a dime”- PM Jeff Stewart of Southland

Page 23: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Trade Partners Panel• Thoughts when first introduced to Takt Time and Line of Balance• Benefits and Draw Backs?• Opinion of Daily Color Ups and Reports• Effect on working conditions • Ownership of space/ cooperation • Crew Sizes/ Hours Spent compared to original estimate• Material Management

Page 24: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Page 25: An Experiment in Takt Time - Lean Construction Institute Presentation...• 44 to 32 days • Slowed down some trades, redirected some trades, sped up others, identified Last Responsible

16th LCI Congress | San Francisco, CA | October 7-10, 2014

Final Thoughts and Lessons Learned• Data of Findings (PPC)• Success of Project• Calculated Risk• Final Perspective of Takt Time• Incorporating Owner Change Order and saving time