Cumulative Effects of RegulationApril 11, 2018
DyLanne Duvigneaud
1
Introduction• CATEGORY 2 MEETING
− The primary discussions are expected to be between the NRC and representatives of licensed fuel cycle facilities. Members of the public will be invited to participate in this meeting at designated points during the meeting.
• REMINDER− The information contained herein is for discussion
purposes only and does not represent the final NRC position.
− We will not be discussing the merits of the regulatory activities during this meeting.
2
Updated Integrated Schedule
Regulatory Activity Revised
JanFebrM
arcAprilM
ayJuneJulyAugSeptO
ctNovDecJanFebrM
arcAprilM
ayJuneJulyAugSeptO
ctNovDecJanFebrM
arcAprilM
ayJuneJulyAugSeptO
ctNovDecJanFebrM
arcAprilM
ayJuneJulyAugSeptO
ctNovDec
90-day comment
l l
To Commission Issue final rule
Part 73-Cyber Security Rulemaking
POC: Gary Comfort/James Downs l l l
Driver: SRM-SECY-14-0147 90-day comment To Commission Issue final rule
l l
To Commission Issue final rule
l
l l
Issue ISG
l
Issue IN
l
l
l
FCIX Meeting
= Reg. Basis/Draft Guidance = Proposed Rule/Draft Guidance = Final Rule/Final Guidance = Public Interaction
= Implementation = Non-rulemaking/NRC Activities
= Meeting occurrence l = Marks a milestone with text = Change occurred below arrow http://www.nrc.gov/materials/fuel-cycle-fac/regs-guides-comm.html#cumeffects
V = Site Visit A = ACRS Meeting
2021
03/29/2018 The FCIX will be held biennially.
03/29/2018
03/29/2018
03/29/2018
03/29/2018
03/29/2018
03/29/2018
Commission directed staff to issue a supplemental rule for comment.
Awaiting Commission direction regarding issuance of proposed and final rule
03/29/2018Part 61 - LLW Disposal
POC: Gary ComfortDriver: SRM
IN - Unplanned Contamination Events POC: Alayna Pearson
Driver: Staff
RG 3.71, Revision 3POC: Christopher Tripp
Driver: Staff
2020
Docket ID – NRC-2009-0096 and Docket ID NRC–2013–0195
03/29/2018
Docket ID – NRC-2015-0179
Awaiting Commission direction regarding issuance of ISG
Comments2018
03/29/2018 * Part 21 rulemaking is terminated.
2019
ANS 57.11 (ISA)POC: April Smith
Driver: SRM
Part 73-Enhanced Security for SNMPOC: Ed Lohr/Nick Baker
Driver: SRM
IN - Unanalyzed Conditions Involving Long-Term Fissile Accumulation
POC: Jeremy MunsonDriver: Staff
03/29/2018
FCIXPOC: DyLanne Duvigneaud/Mollie Semmes
Driver: Staff
03/29/2018
03/29/2018
IN - Adequate Management Measures POC: April Smith
Driver: Staff03/29/2018
Acute Chem. Exposures (ISG)POC: Marilyn DiazDriver: Staff/SRM
Part 21 - Draft Guidance POC: Richard Jervey
Driver: Staff
Enhanced Weapons Rulemaking POC: Robert Beall/Nick Baker
Driver: SRM
Financial Assurance for Material Licensees (ISG)
POC: Kenneth KlineDriver: Staff
Part 74-MC&APOC: Thomas Young/Tom Pham
Driver: SRM
Part 61 “Proposed Rule: Low-Level Radioactive Waste Disposal”
4
Contact:Gary ComfortNMSS/MSTR/RPMB301-415-8106
Key Information
• The final rule package was submitted to the Commission on September 15, 2016.
• The Commission issued an SRM on September 8, 2017, directing the staff to issue a supplemental rule for comment.
Meeting Information • August 2018 – 90-day comment period on supplemental propsed rule.
Regulatory Activity Revised
JanFebrM
arcAprilM
ayJuneJulyAugSeptO
ctN
ovD
ecJanFebrM
arcAprilM
ayJuneJulyAugSeptO
ctN
ovD
ecJanFebrM
arcAprilM
ayJuneJulyAugSeptO
ctN
ovD
ecJanFebrM
arcAprilM
ayJuneJulyAugSeptO
ctN
ovD
ec
202120202018 2019
90-day comment
03/29/2018Part 61 - LLW Disposal
POC: Gary ComfortDriver: SRM
90-day comment
Part 61 - LLW DisposalPOC: Gary Comfort
Driver: SRM12/19/2017
Part 73 “Part 73-Enhanced Security for SNM”
5
Key Information
• In April 2016, the Commission directed the NRC staff to suspend efforts on the Enhanced Security of SNM rulemaking. Later, the Commission directed staff to interact with DOE in order to share and discuss perspectives and ideas on the material attractiveness approach in the Enhanced Security of SNM Rulemaking. This work is on-going. As such, the staff does not anticipate that the rulemaking will resume in FY2018, but could resume in early FY2019.
Meeting Information • None Scheduled.
Contact: Edward LohrNMSS/DRM/MRPB 301-415-0253
Contact: Nick Baker NMSS/FCSE/FMB301-415-7119
Part 73-Enhanced Security for SNMPOC: Ed Lohr/Nick Baker
Driver: SRM03/29/2018
12/19/2017Part 73-Enhanced Security for SNM
POC: Ed Lohr/Nick Baker Driver: SRM
Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Rulemaking
6
Key Information • The draft final rule is due to the Commission in May 2018.
Meeting Information • None Scheduled.
Contact: Robert BeallNMSS/DRM/RRPB301-415-3874
Contact: Nick Baker NMSS/FCSE/FMB301-415-7119
l l
To Commission Issue final rule
03/29/2018Enhanced Weapons Rulemaking
POC: Robert Beall/Nick Baker Driver: SRM
12/19/2017Enhanced Weapons Rulemaking
POC: Robert Beall/Nick Baker Driver: SRM
Part 73 “Cyber Security”
7
Key Information
• The proposed rule package was submitted to the Commission on October 4, 2017, as SECY-17-0099 ML17018A218. The proposed rule package consists of the Commission paper, Federal Register notice (FRN), Draft Regulatory Analysis, Draft Backfit Analysis, and Draft Environmental Assessment.
Meeting Information
• Summer 2018 – 90-day comment period on proposed rulemaking.• Fall 2018 – Public meetings to support comment period on the proposed
rulemaking. (Note: These dates are tentative. Additional public meetings will be conducted, as needed).
Contact:James DownsNMSS/FCSE/ECB301-415-7744
Part 73-Cyber Security Rulemaking
POC: Gary Comfort/Matthew Bartlett l l l
Driver: SRM-SECY-14-0147 90-day comment To Commission Issue final rule
12/19/2017
Part 73-Cyber Security Rulemaking
POC: Gary Comfort/James Downs l l l
Driver: SRM-SECY-14-0147 90-day comment To Commission Issue final rule
03/29/2018
Part 74 “Material Control & Accounting of Special Nuclear Material”
8
Contact:Thomas YoungNMSS/MSTR/RPMB301-415-5795
Key Information • The staff anticipates submitting the draft final rule to the Commission in early 2019.
Meeting Information • TBD - Public meeting with Industry to discuss implementation.
Contact:Tom PhamNMSS/FCSE/MCAB301-415-7254
l l
To Commission Issue final rule
03/29/2018Part 74-MC&A
POC: Thomas Young/Tom PhamDriver: SRM
l12/19/2017Part 74-MC&A
POC: Thomas Young/Tom PhamDriver: SRM
Part 21 Draft Guidance
9
Contact:Rick Jervey NMSS/FCSE/PORSB301-415-6201
Key Information
• The Part 21 rulemaking effort was discontinued. As directed in SRM SECY-16-0009, the Commission approved the staff’s recommendation to continue with guidance development using the existing regulatory requirements.
• The staff has decided to discontinue development of draft regulatory guidance to non-reactor and non-power reactor licensees on the implementation of Part 21.
• The staff will determine at a later date, an appropriate vehicle to document Part 21 guidance for fuel cycle facilities (i.e., NUREG-1520, Interim Staff Guidance).
Meeting Information • None Scheduled.
Part 21 - Draft Guidance - 3049POC: Jennifer Fisher
Driver: Staff 12/19/2017
03/29/2018Part 21 - Draft Guidance
POC: Richard JerveyDriver: Staff
ANS 57.11 “ISA Standard”
10
Contact:April SmithNMSS/FCSE/PORSB301-415-6547
Key Information
• On April 3, 2018, the working group chair hosted a conference call to discuss gaining consensus on purpose and eventual approach to completing the standard.
• Based on the discussion, the working group chair committed to developing action items to re-align the working group and consider success paths.
Meeting Information • None scheduled.
03/29/2018ANS 57.11 (ISA)POC: April Smith
Driver: SRM
lANS 57.11 (ISA)POC: April Smith
Driver: SRM12/19/2017
Acute Chemical Exposures (Dermal and Ocular)
11
Contact:Marilyn DiazNMSS/FCSE/FMB301-415-7110
Key Information
• The Commission converted the information paper into a vote paper. • The staff is awaiting Commission direction regarding issuance of ISG.
Meeting Information • None scheduled
03/29/2018Acute Chem. Exposures (ISG)
POC: Marilyn DiazDriver: Staff/SRM
Acute Chem. Exposures (ISG)POC: Marilyn DiazDriver: Staff/SRM
12/19/2017
Financial Assurance for Material Licensees (ISG)
12
Contact:Christopher McKenneyNMSS/DUWP/PAB301-415-6663
Key Information
• The draft ISG is scheduled to be completed in June 2018.• The final ISG is scheduled to be completed in October 2018.
Meeting Information • June 2018 – 45-day comment period on draft ISG.
l l
Issue ISG
Financial Assurance for Material Licensees (ISG)
POC: Christepher McKenneyDriver: Staff
12/19/2017
l l
Issue ISG
03/29/2018
Financial Assurance for Material Licensees (ISG)
POC: Kenneth KlineDriver: Staff
IN - Reporting of Unplanned Contamination Events
13
Key Information
• An IN is being developed to highlight the staff position on reporting unplanned contamination events.
• The final IN is scheduled to be issued in June 2018.
Public Interaction • None scheduled
Contact:Alayna PearsonNMSS/FCSE/PORSB301-415-1096
l
Issue IN
03/29/2018IN - Unplanned Contamination Events
POC: Alayna PearsonDriver: Staff
Issue RIS
l l
Comment period for draft
RIS - Unplanned Contamination Events POC: Alayna Pearson
Driver: Staff12/19/2017
RG 3.71, “Nuclear Criticality Safety Standards for Nuclear Materials Outside Reactor Cores,” Revision 3
14
Key Information
• Draft RG 3.71, Revision 3 (82 FR 40173) was published in the Federal Register for public comment on August 24. 2017, and the comment period closed on October 23, 2017.
• RG 3.71, Revision 3 is scheduled to be completed in May 2018.
Public Interaction • August 24, 2017 - October 23, 2017 – 60-day comment period
Contact:Christopher TrippNMSS/FCSE/PORSB301-415-8741
l03/29/2018RG 3.71, Revision 3
POC: Christopher TrippDriver: Staff
lRG 3.71, Revision 3
POC: Christopher TrippDriver: Staff
12/19/2017
IN 2018-06, Adequate Measurement Measures
15
Key Information • IN 2018-06 was issued April 10, 2018 (ML18029A105)
Public Interaction • August 24, 2017 - October 23, 2017 – 60-day comment period
Contact:April SmithNMSS/FCSE/PORSB301-415-6547
lIN - Adequate Management Measures
POC: April SmithDriver: Staff
03/29/2018
lIN - Adequate Management Measures
POC: April SmithDriver: Staff
12/19/2017
IN 2018-06, Unanalyzed Conditions Involving Long-Term Fissile Accumulation
16
Key Information • IN 2018-05 was issued March 26, 2018 (ML18022A211).
Public Interaction • August 24, 2017 - October 23, 2017 – 60-day comment period
Contact:Jeremy MunsonNMSS/FCSE/PORSB404-997-4732
l
IN - Unanalyzed Conditions Involving Long-Term Fissile Accumulation
POC: Jeremy MunsonDriver: Staff
03/29/2018
l
IN - Unanalyzed Conditions Involving Long-Term Fissile Accumulation
POC: Jeremy MunsonDriver: Staff
12/19/2017
FCIX
17
Contact:DyLanne DuvigneaudNMSS/FCSE/PORSB301-415-4010
Contact:Mollie SemmesNMSS/FCSE/ECB301-415-7486
Key Information • The FCIX is held biennially.
Related Documents
• Link to the NRC public website on the 2017 FCIX http://www.nrc.gov/public-involve/conference-symposia/fcix.html.
Meeting Information • The next FCIX will be held in June 2019.
FCIX Meeting
03/29/2018FCIX
POC: DyLanne Duvigneaud/Mollie SemmesDriver: Staff
FCIX Meeting
FCIXPOC: DyLanne Duvigneaud/Mollie Semmes
Driver: Staff12/19/2017
Summary
• Main Integrated Schedule and Supplement
• CER public website:
http://www.nrc.gov/materials/fuel-cycle-fac/regs-guides-comm.html#cumeffects
• Next meeting – September 2018
18