THE SPOTIA PROJECT (CEG-Univ. Lisboa; CES-Coimbra; IST-CESUR)
Sustainable Spatial Policy Orientations and Territorial Impact Assessment - Contribution to
Portuguese context
Project purposes:
• studying the Portuguese plans and programmes;
• assessing how they intervene in territorial development;
• analyzing them within the mainland regions.
Case studies:
- the New Lisbon Airport (NLA);
- the Portuguese high-speed rail (HSR);
- the Multiple-Purpose Undertaking of Alqueva (EFMA), a project linked to the Alqueva Dam.
SUSANA MARREIROS | JORGE GONÇALVESWHERE WILL THE AIRPORT LAND? A NARRATIVE ABOUT THE LOCATIVE UNCERTAINTY OF THE NEW LISBON AIRPORT
PURPOSE
Overview of the New Lisbon Airport’s (NLA) recent history (2007 – 2012) as it was
portrayed in the media and intersect that information with the airport legislation
released during the same time slot.
SUSANA MARREIROS | JORGE GONÇALVESWHERE WILL THE AIRPORT LAND? A NARRATIVE ABOUT THE LOCATIVE UNCERTAINTY OF THE NEW LISBON AIRPORT
RESEARCH/ANALYSIS STEPS PLAN
News2007-2012
Categorisation of all the news
Yearly progress graph
Selection of the most relevant news
Quarterly calendar
Timeline
Decision-making documents /
legislation
SUSANA MARREIROS | JORGE GONÇALVESWHERE WILL THE AIRPORT LAND? A NARRATIVE ABOUT THE LOCATIVE UNCERTAINTY OF THE NEW LISBON AIRPORT
THE AIRPORT AS A CATALYST FOR...
• the economy
– potential for being a hub
– potential for air cargo
– “peak hour” surcharge
• employment
– 10% more passengers → 1% increase more employment in service-related businesses (Brueckner,
2003)
– direct and derived effects
• regional development
SUSANA MARREIROS | JORGE GONÇALVESWHERE WILL THE AIRPORT LAND? A NARRATIVE ABOUT THE LOCATIVE UNCERTAINTY OF THE NEW LISBON AIRPORT
THE LISBON METROPOLITAN AREA: AIRPORT/AIRFIELD INFRASTRUCTURES
SUSANA MARREIROS | JORGE GONÇALVESWHERE WILL THE AIRPORT LAND? A NARRATIVE ABOUT THE LOCATIVE UNCERTAINTY OF THE NEW LISBON AIRPORT
News2007-2012
Categorisation of all the news
Yearly progress graph
Selection of the most relevant news
Quarterly calendar
Timeline
Decision-making documents /
legislation
SUSANA MARREIROS | JORGE GONÇALVESWHERE WILL THE AIRPORT LAND? A NARRATIVE ABOUT THE LOCATIVE UNCERTAINTY OF THE NEW LISBON AIRPORT
2007 2008 2009 2010 2011 20120%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Delays
Locative uncertainty
Portela+1
Alcochete
Ota
SUSANA MARREIROS | JORGE GONÇALVESWHERE WILL THE AIRPORT LAND? A NARRATIVE ABOUT THE LOCATIVE UNCERTAINTY OF THE NEW LISBON AIRPORT
YEARLY PROGRESS
News2007-2012
Categorisation of all the news
Yearly progress graph
Selection of the most relevant
news
Quarterly calendar
Timeline
Decision-making documents /
legislation
SUSANA MARREIROS | JORGE GONÇALVESWHERE WILL THE AIRPORT LAND? A NARRATIVE ABOUT THE LOCATIVE UNCERTAINTY OF THE NEW LISBON AIRPORT
Confirmation and re-confirmation of the
Ota airport
Ota questioned. Southern side: desert
or opportunity?
Studies frozen for the Ota airport, and
developed for the Southern side
Ota and Alcochete in collision. The studies
continue. Guaranteed funding
Airport in Alcochete announced
Ota option set aside “permanently"
Compensations to the West and work begins
in Alcochete
"Guarantee" of constructions for 2009
Contest about E.I. announced by the
NAERConvictions and delays
NLA stays in the plans and expenses, with a
reticent public opinion
Insistence for the public works
Conditions to go forward but
uncertainty regarding the 2017 goal
More delays, postponements and
contradictions
Even though the TGV is cancelled, the NLA
stays
NLA under pressure despite the
Government’s guarantees
Results of the crisis in the NLA NLA reevaluated End of the NAER
announcedNLA will not go
forward. Portela+1 option weighted
Portela+1 is the most debated option
Passos doesn’t want the NLA. Portela+1
idea remains
Decision about the NLA delayed for another 15 years
1st trimester 2nd trimester 4th trimester3rd trimester
2007
2008
2010
2011
2012
2009
SUSANA MARREIROS | JORGE GONÇALVESWHERE WILL THE AIRPORT LAND? A NARRATIVE ABOUT THE LOCATIVE UNCERTAINTY OF THE NEW LISBON AIRPORT
Type of document Date Description
Decree-Law September 2007
Creates a system of services acquisition in order to conduct a compared technical analysis of the different locative alternatives for the NLA.
Resolution of the Council of Ministers January 2008 Ratifies the LNEC report that compares the alternatives for the NLA and defines actions that have to be
developed for the implementation of the project.
Resolution of the Council of Ministers May 2008 Adopts the conclusions and recommendations of the LNEC report, and confirms the approval of the NLA
location in Alcochete.
Decree July 2008 Creates preventive measures for the Alcochete area where the NLA is planned to be built and its surrounding areas.
Law August 2008 Revokes the law that extended the term of preventive measures of soil occupation in the Ota area.
Resolution of the Council of Ministers March 2010 Creates preventive measures for two years (extendable for one more year), for areas needed to build the
train connection to the NLA.
Resolution of the Council of Ministers July 2010 Extends, for one year, the preventive measures in the area planned for the construction of the NLA and its
surrounding areas.
Resolution of the Council of Ministers November 2011
Approves the Strategic Transport Plan which supports the idea of rethinking and reflecting about the NLA with an approach towards keeping the Portela airport and the possibility of converting an airfield infrastructure into a small airport for low-cost companies.
SUSANA MARREIROS | JORGE GONÇALVESWHERE WILL THE AIRPORT LAND? A NARRATIVE ABOUT THE LOCATIVE UNCERTAINTY OF THE NEW LISBON AIRPORT
2007 2008 2009 2010 2011 20120%
10%20%30%40%50%60%70%80%90%
100%
Delays
Locative uncertainty
Portela+1
Alcochete
Ota
CONCLUSIONS
The mutations that occurred throughout this 6-year period generate multiple consequences, which can be
caused by legal documents that impose preventive measures or by rules from land management instruments.
The consequences are:
• when the location, the characteristics or the temporal materialisation of this kind of infrastructure change,
the whole economic, social and territorial framework is strongly affected;
• even if nothing changes formally – as it is happening now – the indefinition still results in costs, since
contradictory expectations continue to be fueled, making it impossible to set a consistent and articulated
path towards the development of the territory.
SUSANA MARREIROS | JORGE GONÇALVESWHERE WILL THE AIRPORT LAND? A NARRATIVE ABOUT THE LOCATIVE UNCERTAINTY OF THE NEW LISBON AIRPORT
WHERE WILL THE AIRPORT LAND?A NARRATIVE ABOUT THE LOCATIVE UNCERTAINTY OF THE NEW LISBON AIRPORT
Projecto SPOTIA: Orientações de Política Territorial Sustentável e Avaliação de Impactes Contributos para o caso português (PTDC/CS-GEO/105452/2008).Coordinated by CEG-Univ. Lisboa; with the participation of CES-Coimbra and IST-CESUR.
SUSANA MARREIROS | JORGE GONÇALVES